14
Mike Strasik Flywheel Program Manager J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver 2010 Energy Storage Systems Program, November 2-4, 2010 Washington DC This work was supported by the U.S. Department of Energy/Sandia National Laboratories Energy Storage Program Contract #598172 and #1059559 . Design, Fabrication, and Test of a 5 kWh Flywheel Energy Storage System Utilizing a High Temperature Superconducting Magnetic Bearing

cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Mike StrasikFlywheel Program Manager

J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver2010 Energy Storage Systems Program, November 2-4, 2010 Washington DC

This work was supported by the U.S. Department of Energy/Sandia National Laboratories Energy Storage Program Contract #598172 and #1059559 .

Design, Fabrication, and Test of a 5 kWh Flywheel Energy Storage System Utilizing a High Temperature

Superconducting Magnetic Bearing

Presenter
Presentation Notes
1. Presenter may wish to say something about the University PI. Many are distinguished academics, nationally/internationally recognized. This can provide some instant credibility for the research you are about to describe.
Page 2: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

System Architecture for Deployment of a 3 kW / 5 kWh Flywheel Energy Storage System – DOE/Sandia Project

Benefits of Using FESS Instead of Idling 2nd Generator on Standby• Reduce Generator Maintenance by 50% (estimate)• Reduce Fuel Costs by $200k/yr (estimate)• Lower Pollution

Flywheel Energy Storage System would supply powerduring short peak demand periods

Objective: Design, build and deliver a flywheel energy storage system tailored for off-grid applications

One of three deployment options for the demo system, shown in relation to diesel genset and balance of system.

3 kW / 5 kWhFlywheel

Page 3: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

Energy Storage Program 5 kWh / 3 kW Flywheel Energy Storage System Project History and Roadmap

New Contract: System Integration Lab Test

• Rotor/bearing• Materials • Reliability

• Applications• Characteristics• Planning

• Site selection• Detail design• Build/buy

• System integration• Conduct lab spin testing• Post-test evaluation

6/99 – 9/99

10/10 – 9/11

11/01 – 03/07

5/00 – 3/01 3/01 – 11/-01 (funding interruption)

1/04 – 05/-04 (funding interruption)Phase I: Application ID and Initial System Specification

Phase II: Component Development and Testing

Phase III: System Integration and Component Testing

Phase I: Significant Outputs

• Unit characteristics

• System specification document

Phase II: Significant Outputs

• Prelim design complete

• HTS crystal array complete

• Material lifetime data

• Rotor upgrade complete

• Rotor qualification testing complete

Phase III: Significant Outputs

• Direct cooled HTS Bearing

• Most flywheel hardware built

04/07 – 03/101/09 – 8/09 (funding interruption)

3/10 – 10/10(funding interruption)

Page 4: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

Copyright © 2004 Boeing. All rights reserved.

Flywheel Energy Storage System

• Why Pursue Flywheel Energy Storage?• Environmentally clean (green)• Low maintenance• Potential for high power density (W/ kg) and high energy density (W-Hr/ kg)• Can handle rapid charge and discharge rates without degradation• Cycle life times of >25 years• Broad operating temperature range

• Why use high temperature superconducting bearings?

• Very low bearing losses to extend the idle mode

• Simple passive system• HTS bearings will support ultra

high-speed flywheels for high energy density

– (Energy = (1/2) (Moment of Inertia) (Spin Speed)2)

Page 5: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Boeing….Leading the industry by combining enabling technologies to create high energy dense electro-mechanical power systems for terrestrial and aerospace applications

Test Facility

Spin Tests

Cryogenics Safety Containment

Composite Rotors

Shaker TestsDynamics

Balancing

Flywheel Spin Test FacilityCutting Edge Technology for Energy Storage

Page 6: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

5 kWh / 3 kW Flywheel System Design

• Design Highlights• Non-Contact Hybrid Composite

Rotor with Aluminum Hub

• Direct Cooled HTS Bearing with Passive Damper

• Full Containment System

• Redesigned Touchdown (Backup) Bearings

• Custom Encoder for True Rotational Position

Page 7: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

5 kWh Boeing Modular Flywheel Design (DOE/Sandia)

Stability Direct-Cooled HTS Bearing

Composite Rotor

3 kW Motor/Generator

Lift Brackets

Flywheel Modular Frame

Bearing Rotor

Steel Vacuum Vessel

Energy-AbsorbingContainment Liner

Hex YBCO

Aluminum Hub

PM Lift Bearing

Mech Bearing

Mech Bearing

Cryocooler

Page 8: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

high-temperature superconductor

permanentmagnet

The permanent magnet levitates with passive stability, rotating freely while maintaining position

Relevant Properties of Superconductors:

1. Zero resistance to dc current flow

2. Strong diamagnetism, keeping applied magnetic flux from entering the superconductor

Bulk crystal form (not wire) is preferred for bearings

Basic Bearing Construction

Page 9: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

HTS Crystals

HTS Crystals

Stainless Steel Cryostat

HTS Bearing Rotor Structural Bearing Models

10”

Trapped Field Profile

Electromagnetic Models

Superconducting Bearing System

Page 10: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

Direct-Cooled HTS Bearing Design – Generation 3

Cold HeadBearing Rotor

Total Loss• 3.3 W at 2.1 mm gap• 1.6 W at 3.9 mm gap

Benefits:• ~60% fewer parts• Reduced power requirements• Eliminates the requirement for LN2• Reduces maintenance

G-10 Support

Bearing StatorYBCO

YBCO

Page 11: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

Quill Test Dynamic Model vs. Quill Test Data

Rotordynamic Response Plot

00.0010.0020.0030.0040.0050.0060.0070.0080.0090.01

0.0110.0120.0130.0140.0150.0160.0170.0180.0190.02

0 5000 10000 15000 20000 25000Rotor Speed, rpm

Res

po

nse

, In

ches

p-p

Major Amp

Boeing-5kWh - .008" P-P Damper MotionModel # 6100E (no orings behind upper ball bearing)

Sta. No. 118: Low er Rotor Response

xLrotor forced response plot showing the amplitude of unbalance vs rpm XLRotor Spreadsheet for Rotordynamic Analysis© Rotating Machinery Analysis, Inc.

Lower rim vibration vs speed 5kWh. 23,675 rpm (09/19/05)

0.0000.0010.0020.0030.0040.0050.0060.0070.0080.0090.0100.0110.0120.0130.0140.0150.0160.0170.0180.0190.020

0 5000 10000 15000 20000

Speed RPM

Vibr

atio

n, in

ches

p-p unbalance

Lower Rim data from high-speed quill testing showing the amplitude of unbalance vs rpm

Lower rim vibration vs speed 5 kWh, 23,675 rpm

• Normal max operational speed is 22,500 RPM• Quill tested at 105% or 23,675 RPM• Rotor Total Indicated Runout (TIR) held to 0.002” – didn’t need to balance

Page 12: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

5 kWh Flywheel Hardware Completed

Upper Touchdown Bearing Assembly

Composite Rotor with Hub

Lower Touchdown

Bearing Assembly

Lift Magnet Assembly

Stability Magnet Damper Assembly

Motor Stator Assembly

Safety Containment

Page 13: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

2010-2011 Future Tasks

Task 1: Complete fabrication of remaining components• Fabricate or modify mechanical components of the 5 kWh / 3 kW FESS system

Task 2: Continue Integration of 5 kWhr / 3 kW FESS• Continue integration of 5 kWh flywheel system to prepare for spin testing• Integrate and test new flywheel damper system• Perform motor encoder test and motor controller hardware integration test• Integrate flywheel rotor system into one vacuum / containment system which will be mounted into a single external support structure

Task 3: Low speed testing of 5 kWhr / 3kW FESS• Conduct and analyze low-speed testing of 5 kWh flywheel system

Task 4: Communicate program results and progress

Page 14: cognized. This can provide some instant credibility for the … 2010 Update... · 2012-03-26 · J R Hull, J A Mittleider, J F Gonder, P E Johnson, K E McCrary, and C R McIver. 2010

Engineering, Operations & Technology | Boeing Research & Technology Superconducting Flywheel System

Summary

• The 5 kWh rotor is complete and fully tested at 105% speed

• The direct cooled High Temperature Superconducting bearing was successfully tested

• Losses measured• Thermal models• Cryocooler performance measured and verified

• System design completed

• Majority of flywheel mechanical parts built and delivered

• Remaining parts on order

• Started system integration