Case study: Achieving Good Practice waste recovery
Kier Marriott and Wastecycle at
Bowbridge Primary School
The new education building for Bowbridge Primary School was created with the vision to be as near carbon neutral as possible in design, construction and use. To support this vision, the project construction contractor, Kier Marriott, worked with Wastecycle to divert mixed construction waste from landfill and supply supporting waste data.
Project code: WAS800-003 ISBN:
Research date: November 2008 to September 2009 Date: April 2010
WRAP’s vision is a world without waste,
where resources are used sustainably.
We work with businesses and individuals
to help them reap the benefits of reducing
waste, develop sustainable products and
use resources in an efficient way.
Find out more at www.wrap.org.uk
Document reference: WRAP, 2010, Case Study: Kier Marriott and Wastecycle at Bowbridge Primary School (WRAP Project
WAS800-003). Report prepared by Hill, A R; Pearson, G A, Scott Wilson Ltd
Written by: Dr Annette Hill and Gillian Pearson (Scott Wilson)
Front cover photography: Bowbridge Primary School new school building, courtesy of Kier Marriott
WRAP and Scott Wilson Ltd believe the content of this report to be correct as at the date of writing. However, factors such as prices, levels of recycled content and
regulatory requirements are subject to change and users of the report should check with their suppliers to confirm the current situation. In addition, care should be taken
in using any of the cost information provided as it is based upon numerous project-specific assumptions (such as scale, location, tender context, etc.).
The report does not claim to be exhaustive, nor does it claim to cover all relevant products and specifications available on the market. While steps have been taken to
ensure accuracy, WRAP cannot accept responsibility or be held liable to any person for any loss or damage arising out of or in connection with this information being
inaccurate, incomplete or misleading. It is the responsibility of the potential user of a material or product to consult with the supplier or manufacturer and ascertain
whether a particular product will satisfy their specific requirements. The listing or featuring of a particular product or company does not constitute an endorsement by
WRAP and WRAP cannot guarantee the performance of individual products or materials. This material is copyrighted. It may be reproduced free of charge subject to the
material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must
not be used to endorse or used to suggest WRAP’s endorsement of a commercial product or service. For more detail, please refer to WRAP’s Terms & Conditions on its
web site: www.wrap.org.uk
Kier Marriott and Wastecycle at Bowbridge Primary School 1
Executive summary
The new education building for Bowbridge Primary School was created with the vision to be as near carbon
neutral as possible in design, construction and use and to be delivered within a defined budget. The project was
completed in September 2008 at a cost of £3.2 million.
To support this vision, developed by Nottinghamshire County Council (the client and designer) and Bowbridge
Primary School (the end-user), the project construction contractor, Kier Marriott, worked with Wastecycle to
divert construction waste from landfill and report waste management data.
The design of the building incorporated many sustainable features including:
� the orientation and layout of the building;
� the use of recycled and renewable materials and pre-fabricated components in the construction; and
� the incorporation of wood fuelled heating, solar water heaters and rainwater harvesting in the building.
To embed the vision for the project through the construction phase, a ‘Building Charter’ was established
collaboratively between Nottinghamshire County Council, Bowbridge Primary School and Kier Marriot, that
included a requirement to reduce waste to landfill by reusing and recycling waste where possible.
Kier Marriott operates a regional and national supply chain for the procurement of all sub-contractors including
waste management contractors. The companies are required to meet certain standards in order to remain on the
supply chain and are subject to regular audits to review procedures and progress.
Kier Marriott identified that space constraints on the project site would only enable limited on site segregation of
wastes and therefore it was important to appoint a waste management contractor that could deliver high rates of
recycling of waste from mixed stream collections
Wastecycle was appointed to manage the skip waste from the project. The company offered segregated and
mixed waste collections as well as average recycling rates of around 86% for all materials managed at the
company’s materials recovery facility (MRF).
Wastecycle provided waste management data reports to Kier Marriott via its online customer area to enable Kier
Marriott to track progress and report against the project ‘Building Charter’ and corporate KPIs.
104.4 tonnes of mixed and segregated waste was handled by Wastecycle of which 88.9 tonnes was recycled or
recovered through the company’s MRF, achieving a recovery rate of 85.2%.
Kier Marriott and Wastecycle at Bowbridge Primary School 2
Contents
1.0 Introduction................................................................................................................................ 3 1.1 Key facts ............................................................................................................................3 1.2 The project.........................................................................................................................3 1.3 Client and designer: Nottinghamshire County Council .............................................................4 1.4 End-user: Bowbridge Primary School.....................................................................................5 1.5 Construction contractor: Kier Marriott....................................................................................5 1.6 Waste management contractor: Wastecycle...........................................................................6
2.0 Background................................................................................................................................. 7 2.1 The Design .........................................................................................................................8 2.2 Building Charter ..................................................................................................................8 2.3 Key drivers .........................................................................................................................9
3.0 Procurement process.................................................................................................................. 9 3.1 The Process........................................................................................................................9 3.2 Procurement process – Summary .......................................................................................10
4.0 Contract arrangements............................................................................................................. 10 4.1 Contract conditions and requirements .................................................................................10 4.2 Contract management .......................................................................................................11
5.0 Service delivery......................................................................................................................... 11 6.0 Data collection, collation and reporting................................................................................... 12
6.1 Other data reporting..........................................................................................................15 7.0 Use of the Site Waste Management Plan................................................................................. 15 8.0 Auditing..................................................................................................................................... 15
8.1 Auditing procedures ..........................................................................................................15 8.2 Waste data auditing ..........................................................................................................16
9.0 Outcomes .................................................................................................................................. 16 9.1 Key learning points............................................................................................................16
10.0 Next steps ................................................................................................................................. 17 11.0 Further information .................................................................................................................. 17
Acknowledgements
WRAP and Scott Wilson would like to thank Kier Marriott, Wastecycle, Nottinghamshire County Council and
Bowbridge Primary School.
Kier Marriott and Wastecycle at Bowbridge Primary School 3
1.0 Introduction
The new education building for Bowbridge Primary School was created with the vision to be as near carbon neutral as possible in design, construction and use. To support this vision, the project construction contractor, Kier Marriott, worked with Wastecycle to divert mixed construction waste from landfill and supply supporting waste data.
1.1 Key facts
� Client and designer: Nottinghamshire County Council
� End-user: Bowbridge Primary School
� Construction contractor: Kier Marriott
� Waste management contractor: Wastecycle
� Other key stakeholders: pupils and parents, staff, school governors, community services, divisions across the
education department, elected members of Nottinghamshire County Council
� Nottinghamshire County Council procured a framework of three construction contractors to deliver the
construction of the county’s schools over a period of three years. Kier Marriott was appointed to this
framework.
� The project involved the construction of a new school building for Bowbridge Primary School at a cost of £3.2
million.
� Nottinghamshire County Council and Bowbridge Primary School drove cost and sustainability issues through
all project phases, from design to construction and end use.
� A ‘Building Charter’ was established collaboratively between Nottinghamshire County Council, Bowbridge
Primary School and Kier Marriott that provided the vision for the construction phase of the project, including
waste management.
� Kier Marriott operates a regional and national supply chain for the procurement of all sub-contractors
including waste management contractors. The companies are required to meet certain standards in order to
remain on the supply chain and are subject to regular audits.
� Kier Marriott identified that space constraints on site would only enable limited on site segregation of wastes
and therefore it was important to identify a waste management contractor that could deliver high rates of
recycling of waste from mixed streams.
� Wastecycle was appointed to manage the skip waste from the project and offered segregated waste
collections as well as recycling rates of 86% on average for mixed waste collections, by sorting the materials
at the company’s materials recovery facility (MRF).
� Wastecycle provided waste management data reports to Kier Marriott via its online customer area to enable
Kier Marriott to track progress and report against the project Building Charter.
1.2 The project
The new education building for Bowbridge Primary School in Newark-on-Trent, Nottinghamshire was created with
a vision to:
� be as near carbon neutral as possible in design, construction and use;
� be of innovative design and construction;
� provide an exemplar for Nottinghamshire County Council in its programme of new school buildings; and
� be delivered within a strict budget.
Kier Marriott and Wastecycle at Bowbridge Primary School 4
The project involved the construction of a new school building to replace the existing converted 1940’s army
barracks. The new two storey building contains ten classrooms, five group study rooms, a meeting room and
large atrium, as well as an outdoor covered playground and other outdoor learning areas.
The project was undertaken as part of Nottinghamshire County Council’s schools construction framework. The
programme of stakeholder consultation began in 2005, the construction programme commenced in September
2007 and was completed in September 2008, at a cost of £3.2 million.
1.3 Client and designer: Nottinghamshire County Council
Nottinghamshire County Council played a dual role in the project:
� the Resource Department: provided the architect, landscape architect, quantity surveyor, and electrical and
mechanical engineers; and
� the Education Department: provided advisory services and information and communication technology (ICT)
systems support.
Nottinghamshire County Council established clear objectives for the project through broad consultation with the
end-user and the wider community.
“The new building will express the value of education in the community and it will give a welcoming and
positive image of the school. It will be an exemplar design from the architectural point of view as well as
per its energy efficiency, ecology and sustainability, which is in the school ethos’”
Nottinghamshire County Council 2006
Nottinghamshire County Council promotes the principles of sustainable development and construction across the
county through the ‘Sustainable Developer Guide for Nottinghamshire’1. The Guide sets out development
principles across a range of topics including:
� planning;
� land use, layout and landscape;
� travel and transport;
� building design and specification;
� energy use;
� renewable energy;
� health and pollution;
� waste reduction;
� water use and drainage;
� biodiversity;
� community;
� historic environment; and
� maintenance and management.
Areas of consideration under waste reduction include:
� applying the waste hierarchy principles (reduce, reuse, recycle, recover, dispose);
� reducing construction waste arising through efficient design and onsite reuse of materials;
� using construction materials with recycled content; and
� providing facilities for reusing, recycling and recovering waste generated during use.
The Guide also promotes the use of locally sourced materials and resources including staffing.
1 www.sdg-nottinghamshire.org.uk
Kier Marriott and Wastecycle at Bowbridge Primary School 5
1.4 End-user: Bowbridge Primary School
The building needed to provide a suitable learning environment for the school as well as a focal point for the
community. The building also supported the school’s ambition to achieve the Eco-Schools ‘Green Flag’ award (the
highest accreditation). Bowbridge Primary School expressed that the building should be a ‘learning building’ as
well as a ‘building of learning’, the intention being to utilise the way the building operates to assist the school in
teaching around a focus of education for sustainability.
The end-user played a lead role in driving the development of the project, through consultation with stakeholders
and driving the focus on sustainability.
1.5 Construction contractor: Kier Marriott
The Kier Marriott business specialises in public and private sector construction projects throughout the East
Midlands, East Anglia and the northern Home Counties and has a turnover in the order of £95 million.
Kier Marriott is a Regional Contracting Business within the Construction Division of the Kier Group. Kier Group is a
leading construction, development and service group specialising in building and civil engineering, support
services, private house building, property development and the Private Finance Initiative. The Group employs
over 11,000 people worldwide and has annual revenue in excess of £2.1 billion.
In 2007, Kier Group launched its Strategy for Sustainability that sets out the company’s policy and objectives
across environmental, social and economic issues. Kier Group operates under an environmental management
system certified to ISO 14001 standards, which is externally audited by an independent third party. The company
reports publicly on its Corporate Responsibility and in 2008 environmental key performance indicators included
‘cost of waste as a percentage of revenue’.
In 2009, the Kier Board signed up to WRAP’s Construction Commitments: Halving Waste to Landfill and
established targets for reducing waste to landfill. The Group is also a member of a number of schemes that
promote business sustainability including:
� Business in the Community (BITC); and
� Considerate Constructors Scheme (CCS).
Kier Group, ‘Environment Statement’ states:
“Kier Group is committed to conducting its business in a manner that is both professional and ethical
whilst paying particular attention to its environmental responsibilities. These responsibilities will be
discharged by implementing the following:
� The identification and then strict compliance with the letter and intent of all relevant legal and other
requirements;
� The provision of training to raise the awareness of those aspects of our business, which have an
impact on the environment;
� The effective communication of the responsibilities of the Group, our staff and those under our
control, to ensure that a high standard of environmental care is maintained at all times;
� The organisation of our operations in order to minimise pollution and disturbance to our neighbours
and the general public;
� Protection of flora & fauna and their habitats at our offices and depots and on sites where we hold
responsibility or can influence those that do;
� The efficient use of materials and resources with particular regard to the long-term sustainability of
consumable items;
� Minimising the need to travel but where travel is unavoidable, consider taking the least
environmentally damaging mode of transport;
� The establishment and maintenance of management structures within our operating companies and
divisions with specific responsibility for the implementation of environmental policy;
Kier Marriott and Wastecycle at Bowbridge Primary School 6
� The establishment of targets against which to measure the improvement in our environmental
performance in key areas, including energy use and waste;
� Regular management reviews of the content and implementation of the environmental policy, to
ensure improvement in performance through the adoption of best practice, provision of training and
raising awareness; and
� The introduction of environmental criteria to assess the commitment to sustainable procurement of
our supply chain.”
1.6 Waste management contractor: Wastecycle
Wastecycle Limited is a waste collection and recycling company based in the East Midlands. The company was
established in 1998 and now forms part of the Environmental branch of the DCC Group.
Wastecycle’s MRFs in Colwick, Nottingham currently recycle or recover an average of 86% of the waste received
each day. Recent improvements in the technologies at the MRF mean that recycling rates for construction waste
are now at over 92%, compared to around 82% in 2007-08 when the Bowbridge Primary School project was
carried out. The company is committed to ‘maximising the reuse of renewable and non-renewable resources
where economically and commercially viable’.
Wastecycle offers a range of waste management services that include:
� a range of container types and sizes;
� waste collection services;
� licensed materials recovery facility and transfer station;
� recycling services;
� waste stream monitoring and assistance with segregation (including benchmarking and key performance
indicators (KPIs));
� waste collection and recycling reports;
� online dedicated customer area;
� reduced costs for segregated waste materials;
� advice on waste management; and
� established re-use markets for recycled materials.
The company operates under a management system that includes:
� a quality management system accredited to ISO 9001:2000; and
� an environmental management system accredited to BS EN ISO 14001:2004.
The management system accreditation requires the company to undertake regular internal audits as well as
regular auditing by an independent third party. The company is also required to demonstrate continual
improvement in its approaches to quality and environmental management.
Wastecycle is a member of the Recycling Registration Scheme and the Wood Recyclers Association and has been
awarded a Gold RoSPA for health and safety and an award from the Chartered Institute of Builders in the
‘Committed to the Environment’ category.
Wastecycle, ‘Environmental Policy Statement’ states:
“Wastecycle Ltd. shall ensure that our operations comply with and where possible exceed environmental
legislation, approved codes of practice and other requirements to which the organisation subscribes that
relate to our environmental aspects whilst co-operating fully and maintaining open relationships with all
regulatory authorities.
The company is committed to the process of enhancing its environmental performance and will continually
measure and monitor standards and implement improvements whilst ensuring that all personnel are
trained and aware of environmental issues and the environmental impact of their activities.
Kier Marriott and Wastecycle at Bowbridge Primary School 7
Wastecycle are committed to increasing the percentage of materials recovered and recycled from the
incoming waste stream and reducing the amount of waste being landfilled by the company in part by
raising awareness of the benefits of separation at source. We aim to maximise reuse and the amount of
energy recovered from waste by minimising the use of materials and non-renewable resources.
We are dedicated to assisting our customers in reducing their environmental impact by providing
reprocessing services and developing markets for secondary materials. Wastecycle will use contractors and
suppliers who hold environmental standards compatible with our own where practicable.
This policy will be communicated to all persons working for or on behalf of the organisation and made
available to interested parties and audited to ascertain that the information contained within it is
understood and accomplished. The policy will be reviewed periodically to ensure that it evolves with the
company’s activities and legislation as well as the needs and expectations of the community.
Adequate resources will be allocated for the development of the company environmental management
system and for the training of all employees.
The company will take all practical steps to prevent or diminish harmful impacts on the environment,
which may result from our activities.
The company will maintain an Environmental Management System throughout its operations subject to
recognised environmental programmes. The system will include the requirement for a comprehensive
report and audit programme which will be designed to progressively reduce the impact of the company’s
operations in key environmental areas.
An Environmental Review meeting, chaired by the Managing Director, will be the strategic body on
environmental matters and will commission and agree with the management team a programme of
objectives and targets consistent with this policy.”
2.0 Background
Nottinghamshire County Council procured a construction framework contract for the delivery of its schools
upgrade programme. The framework contract commenced in December 2006 and was for a period of three
years. The overall budget for projects to be delivered under the framework contract was approximate £170
million over the three year framework.
Nottinghamshire County Council procured and delivered the framework contract under the New Engineering
Contract (NEC). This form of contract is commonly used in publicly funded construction projects and includes
options for using key performance indicators and incentive schedules and has been designed to promote
partnership working and drive out inefficiency.
The framework procurement process included a number of stages involving:
� pre-qualification questionnaire;
� full proposal;
� site visit; and
� interview.
Nottinghamshire County Council appointed three construction contractors to the framework, including Kier
Marriott. The Council identified a range of KPIs and, as an incentive, each construction contractor’s performance
against the KPIs during the first year of the framework would influence their likely share of the work let under the
framework during years two and three.
The construction of the Bowbridge Primary School project was let to Kier Marriott through the County’s
framework contract. Under the framework, the construction contractor gets involved in the development of a
project at an early stage.
Kier Marriott and Wastecycle at Bowbridge Primary School 8
2.1 The Design
Nottinghamshire County Council and Bowbridge Primary School drove the integration of sustainability into the
design process for the project. A wide range of design objectives and features with sustainability and resource
and energy efficiency benefits were incorporated into the design that included:
� energy efficient features including a large south facing atrium to act as a passive collector in the winter and a
ventilation stack in the summer, building layout and orientation designed to promote light and solar gain in
appropriate parts of the building and passive ventilation design;
� flexible layout to accommodate a range of teaching and other activities;
� constructed mainly from renewable and / or recycled materials;
� locally sourced materials;
� high specification insulation;
� a wood burning boiler as the main source of heating;
� solar water heaters; and
� rainwater harvesting.
The building design and construction methods also significantly reduced waste generated on site. The building
comprised a timber frame and insulated timber panel walls and roof deck that were pre-fabricated off site and
simply assembled on site reducing surplus materials and waste. In addition, the temporary access road for the
site was constructed from recycled aggregates and incorporated a ground stabilising geogrid which maintained
the quality of the recycled aggregates and enabled its reuse in the construction of the new netball courts. Bricks
were also reclaimed from the site and reused in areas of the new build.
The design endorsed the principles defined in the ‘Sustainable Developer Guide for Nottinghamshire’1 and was
developed in consultation with school staff, pupils, parents and the local community from project inception
through to completion.
The project was also to serve as an exemplar design for Nottinghamshire County Council as it continues to roll
out new school buildings under the Private Finance Initiative (PFI) and Building Schools for the Future (BSF)
programme.
2.2 Building Charter
To ensure that the strong environmental and sustainability ethos that had been embedded throughout the design
phase of the project was positively embraced by the construction team, a ‘Building Charter’ was produced
collaboratively between Bowbridge Primary School, Nottinghamshire County Council and Kier Marriott.
The ‘Building Charter’ established that ‘the construction of the building should be consistent with the principles
already set in its design and in the Sustainable Developer Guide for Nottinghamshire………… the building should
be constructed in such a way as to minimise environmental damage’.
The Building Charter established guidance for:
� procurement of materials, including using sustainable or renewable sources of materials, that avoid excessive
packaging and have minimal impact during extraction / manufacture;
� travel and transport, including procuring local materials and using local contractors;
� energy use, including using bio-fuels and reducing the use of fuel;
� health and pollution, including using natural materials;
� waste reduction, including recycling / reusing as much waste as possible from site to avoid landfill or
incineration;
� water use and drainage, efficient use of water;
� maintenance and management, including ethical financing and carbon footprinting; and
� community, including regular consultation with pupils and the community and use of local workforce.
The Building Charter was to be adhered to wherever possible (within budget constraints) by Kier Marriott as well
as all sub-contactors.
Kier Marriott and Wastecycle at Bowbridge Primary School 9
The early involvement of the construction contractor in the project enabled a collaborative approach to the
development of the ‘Building Charter’.
2.3 Key drivers
The key drivers for the project include:
Client and designer – Nottinghamshire County Council
� Delivery of a new school building for Bowbridge Primary School, on time and to budget, that meets the needs
of pupils, staff and the community.
� Providing an exemplar in architectural design and sustainability for use in future projects.
� Delivering the project in line with the principles of the ‘Sustainable Developer Guide for Nottinghamshire’.
End-user - Bowbridge Primary School
� Providing a new school building that delivers a high quality learning environment for pupils and staff.
� Providing a flexible building that meets the needs of the school and local community.
� Supporting the school’s objective to achieve the Eco-Schools ‘Green Flag’ award.
Construction contractor – Kier Marriott
� Delivering client and end-user objectives.
� Delivering the framework KPIs to ensure the award of future projects.
� Delivering against corporate KPIs.
Waste management contractor – Wastecycle
� Achieving target recycling rates.
� Delivering company objectives and targets and achieving continuous improvement.
� Recycling as much waste as possible to reduce costs for the company and customers.
� Delivering customer requirements.
� Building long-term business relationships to secure future work.
3.0 Procurement process
Kier Marriott operates a regional and national supply chain that includes an approved suppliers list for all sub-contractors, including waste management contractors. Sub-contractors are expected to maintain defined standards to remain as an approved supplier and undertake work for the company.
Kier Marriott procures waste management services via its regional supply chain of approved suppliers. The Kier
Group also operates a national supply chain for specific products and services that are only available through a
limited number of suppliers across the country.
Kier Marriott introduced a programme of auditing of the waste management contractors that are on the regional
and national supply chain. The company applies a set of auditing criteria that define the minimum standards
expected from a waste management contractor on the supply chain (see Section 8.0 for details).
Kier Marriott uses this approach to ensure that the waste management contractors on the supply chain support
the company’s objective to reduce waste to landfill by operating under complementary policies that drive good
practice in their particular area of expertise.
3.1 The Process
For a particular project, Kier’s Buyers discuss the specific waste management requirements with the construction
site manager and local environment team. These requirements include:
Kier Marriott and Wastecycle at Bowbridge Primary School 10
� waste quantities;
� waste types;
� potential for on-site segregation;
� responsibilities of each party; and
� any site constraints.
On the Bowbridge Primary School project, space for skips and waste collection containers on the site was
constrained and therefore Kier Marriott concluded that the opportunities for on site segregation were limited. In
order to meet the requirements of the ‘Building Charter’ and to deliver high rates of waste diversion from landfill,
Kier Marriott concluded that it was important to identify a waste management contractor that could achieve these
requirements through on site segregation of major waste streams together with off site segregation of mixed
waste collections. In addition, a local waste management contractor (located within 50 miles of the site) was
needed to meet the ‘Travel and Transport’ and ‘Community’ elements of the Building Charter.
For the Bowbridge Primary School project the waste management services were divided into three parts as
follows:
� Wastecycle was used for skip waste;
� specialist contractors were used for muck-away and asbestos; and
� the school’s existing waste collection service was used for collecting paper and card for recycling.
Wastecycle was awarded the skip waste collection because:
� the company was able to offer both segregated and mixed waste containers and collections;
� recycling rates at the company’s MRF are typically 86%;
� the company was located within 50 miles of the project site; and
� the company was able to supply waste management data to support Kier Marriott’s reporting requirements.
3.2 Procurement process – Summary
� Kier Marriott operates a regional and national supply chain which includes waste management service
provision.
� Kier Marriott sets minimum requirements for waste management contractors on the supply chain and
undertakes regular audits to confirm performance.
� Kier Marriott’s site manager and environment team work with Kier Buyers to identify waste management
requirements and constraints on a project and place an order with an appropriate waste management
contractor.
4.0 Contract arrangements
The contractual arrangements between Kier Marriott and Wastecycle are based around a supply chain agreement and project specific requirements. 4.1 Contract conditions and requirements
The contract between Kier Marriott and Wastecycle involves a supply chain agreement with project specific
service arrangements. The two companies worked together to identify the most significant potential waste
arisings and propose a suitable waste segregation strategy.
At the start of a project Wastecycle prepares a price proposal for waste management services based on:
� size of a waste container or skip;
� transport distance;
� expected waste composition;
� whether the waste streams will be source segregated or mixed; and
Kier Marriott and Wastecycle at Bowbridge Primary School 11
� recycling rates expected to be achieved for the particular waste streams.
Waste that is segregated by the customer is generally charged at a lower rate than mixed waste, which reflects
the lower operational cost to Wastecycle. The price per skip and waste type is usually fixed for the duration of a
project.
As part of the contract, Wastecycle also provides waste data reporting services via the company’s online customer
area.
4.2 Contract management
Kier Marriott and Wastecycle worked closely to understand the requirements of the project and to build an
effective working relationship.
To ensure that the expected standards are maintained, Kier Marriott undertakes regular auditing of the waste
management contractors that are on the regional and national supply chain. The company reviews a set of
auditing criteria that define the minimum standards expected from a waste management contractor on the supply
chain (see Section 8.0 for details). As part of the management of the contract on the project, Kier Marriott
audited Wastecycle.
5.0 Service delivery
Wastecycle provided a range of waste management services focussed on the recycling of waste through its materials recovery facility in Nottingham.
Wastecycle provided skips and containers for mixed and segregated waste collections from Bowbridge Primary
School. Due to space constraints on the site, only limited site segregation was feasible and was therefore
targeted at the most significant streams and those which had specific handling requirements, as follows:
� timber was source segregated and stored within an 8 cubic yard skip. This stream was expected to arise from
the construction of the timber frame and fit out phases;
� plasterboard was source segregated and stored within a separate container within the mixed waste skip so
that it could be easily lifted out at the MRF to ensure separation of the stream; and
� general / mixed waste was stored within an 8 cubic yard skip.
Figure 1 Mixed and segregated waste collection at Bowbridge Primary School
Kier Marriott and Wastecycle at Bowbridge Primary School 12
Wastecycle provided the skips and containers and collection of the wastes. All waste was taken to the company’s
materials recovery facility in Colwick, Nottingham where:
� timber is shredded and supplied to a range of specialist end users;
� plasterboard is collected and sent to a reprocessor; and
� mixed waste is fed through the MRF where it is sorted into a range of material streams and either baled or
bulked for supply to reprocessing plants (e.g. paper, plastics) or further processed for direct onward sale (e.g.
aggregates, soils).
Figure 2 Processing wood waste at Wastecycle’s MRF
6.0 Data collection, collation and reporting
Wastecycle prepared waste data reports for Kier Marriott that were accessed via an online customer area.
Wastecycle offers waste data reporting as part of its service to customers. Data reports are accessed via a
dedicated online customer area with a customer specific login.
The online area provides customers with a range of reports and database search options to enable data to be
extracted in a form that is suitable for various needs. Kier Marriott’s project manager used the online area to
track waste generation, segregation, recycling and disposal for the project.
The data reports show information by:
� skip / container movement;
� construction project / site; or
� for all projects for a particular customer.
Database search options enable the data to be reviewed for a user-defined timescale or for the life of the project.
Kier Marriott and Wastecycle at Bowbridge Primary School 13
For each skip / container movement, the data report includes:
� the skip / container volume;
� description of the contents of the skip;
� weight of the waste; and
� recycling rate – reported as the waste management facility average for that day.
The waste within a skip is categorised into one of 12 different waste streams as follows:
� card;
� confidential waste;
� general mixed;
� glass;
� inert;
� metal;
� mixed recyclables;
� paper;
� plasterboard;
� plastic;
� secure burial; or
� wood.
For each waste stream the report shows the:
� total tonnage of waste collected;
� tonnage segregated by the producer and recycled by Wastecycle;
� tonnage segregated and recycled by Wastecycle;
� tonnage sent to landfill; and
� total recycled.
Wastecycle records data on all waste that it collects and manages. The data is collated from the Waste Transfer
Note and site weighbridge records. All waste collection vehicles entering and leaving Wastecycle’s MRF are
weighed on the calibrated weighbridge. The weight of the full and empty vehicle and waste container are
compared in order to determine the weight of the waste that has been deposited at or removed from the MRF.
The Waste Transfer Note and the weighbridge records are also used for invoicing and payment purposes and in
Wastecycle’s reporting to the Environment Agency.
The above data can be reported by month or year to date or cumulative for the project. The tonnage segregated
and recycled by Wastecycle is calculated from the MRF average recycling rate for that particular day. Wastecycle
also offers recycling rate data for individual skips / consignments, although a surcharge is usually charged for this
service.
The online customer area holds waste data for each site / project being undertaken by Kier Marriott where
Wastecycle are providing the waste management services. This function enables Kier Marriott to compare waste
management performance between projects and identify sites that are performing well or require improvements.
This enables Kier Marriott to target specific improvements that will impact on performance across the business.
Examples of waste data reports prepared by Wastecycle are shown in Figure 3.
Kier Marriott and Wastecycle at Bowbridge Primary School 14
Figure 3 Examples of Wastecycle data reports
Kier Marriott and Wastecycle at Bowbridge Primary School 15
6.1 Other data reporting
Kier Marriott uses the waste data to:
� report to Nottinghamshire County Council and Bowbridge Primary School on a monthly basis against the
requirements of the ‘Building Charter’;
� compare the recycling and waste management performance across Kier Marriott projects;
� identify examples of good practice and opportunities and actions required for future improvements; and
� report against business and Kier Group KPIs.
Wastecycle uses the waste data to:
� monitor recycling rates and operating efficiencies for the business;
� make decisions regarding future investment in new plant and equipment; and
� meet regulatory reporting requirements for completing Waste Returns as required by the Environment
Agency.
7.0 Use of the Site Waste Management Plan
Kier Marriott began using Site Waste Management Plans (SWMPs) for construction projects in 2007 before they
became a legal requirement in England under the SWMP Regulations 2008. The SWMP forms part of the Health
and Safety Plan on a project and is a live document that is continually updated throughout the project.
The SWMP for Bowbridge Primary School was prepared at the pre-contract stage and implemented and updated
as the project progressed.
8.0 Auditing
Kier Marriott undertakes regular audits of waste management contractors on its supply chain. Wastecycle’s management procedures are audited as part of the company’s accreditations.
8.1 Auditing procedures
Kier Marriott has introduced a regular programme of auditing of all waste management contractors on its regional
supply chain. The purpose of the audits is to ensure that standards and procedures are being maintained and
implemented, and to assist in ensuring the quality of waste management service provision. The audits are usually
undertaken by the local environment team and include a half-day site visit and an interview. Kier Marriott has
developed a general list of criteria against which the waste management contractor is audited, which includes
legal requirements as well as service options and good practice approaches across 14 areas of activity, as follows:
� appearance of facility;
� safety;
� people;
� service collection;
� locality to project;
� quality of product;
� documentation/systems;
� number of waste streams;
� recycling rates;
� capacity;
� local benefits;
� culture and landfill policy;
� vehicles and plant; and
� certification.
Kier Marriott and Wastecycle at Bowbridge Primary School 16
The audit regime also reviews the waste management contractor’s proposed future improvements and planned
investment in plant and equipment to ensure the company is committed to offering the highest quality of service.
The waste management contractors on the supply chain are generally audited once or twice a year, with further
audits undertaken for specific construction projects. Any waste management contractor that is new to the Kier
Marriott supply chain is required to meet the standards and be accommodating of the auditing process.
As part of the Bowbridge Primary School project Kier Marriott’s environment team audited Wastecycle to ensure
expected standards of service were being delivered.
Wastecycle operates under a quality management system accredited to ISO 9001:2000 and an environmental
management system accredited to ISO 14001:2004. As part of the accreditation, Wastecycle is required to
undertake regular audits both internally and by an approved independent third party, in order to confirm that
procedures set out by the company are being implemented effectively. The accreditation also requires Wastecycle
to demonstrate continuous improvements in its management systems and processes.
8.2 Waste data auditing
Wastecycle monitors the recycling rate achieved at its MRF by weighing incoming waste, outgoing recyclate and
outgoing waste to landfill. Wastecycle is required to report this data on a quarterly basis to the Environment
Agency on its Waste Returns form. This reporting is required as a condition of the site licence / permit but also
enables process efficiencies to be monitored. The weighbridge is used to weigh all waste entering and leaving the
site and is regularly calibrated in accordance with requirements.
9.0 Outcomes
Kier Marriott and Wastecycle worked together to divert waste from landfill, reduce costs and achieve client objectives.
� 104.4 tonnes of mixed and segregated waste was handled by Wastecycle of which 88.9 tonnes was recycled
or recovered, achieving a recovery rate of 85.2%.
� Kier Marriott worked with Wastecycle to effectively deliver outcomes that supported the objectives of the
project ‘Building Charter’, the construction framework KPIs and corporate KPIs.
� Nottinghamshire County Council and Bowbridge Primary School established a clear vision for the project that
was embedded throughout the design and construction phases and through the supply chain to Kier Marriott
and Wastecycle. The collaborative approach achieved waste reduction, the use of recycled content and the
reuse, recycling and recovery of waste.
9.1 Key learning points
Kier Marriott identified key learning points as:
� cost effective waste reduction and diversion of waste from landfill can be achieved by establishing a clear
vision and objectives early in a project and working collaboratively throughout the supply chain to embed and
deliver the objectives;
� the quality of waste management service provision can be enhanced by defining requirements expected from
waste management contractors, establishing a supply chain that meets the requirements, and auditing and
reviewing service provision on an ongoing basis;
� understanding the capabilities and range of services offered by waste management contractors and
developing a partnership approach to working can ensure expected service levels are delivered or exceeded
and continue to improve;
� waste management contractors can provide support in the planning, delivery and reporting of construction
waste management; and
� clients often consider sustainability issues to be of significant importance in projects and expect companies on
the supply chain to demonstrate how they will deliver measures that are both sustainable and cost effective.
Kier Marriott and Wastecycle at Bowbridge Primary School 17
Wastecycle identified key learning points as:
� by providing waste management services that support construction contractors objectives to provide cost
effective reductions in waste to landfill, effective long-term relationships can be developed; and
� good communications between the contract manager and site manager help to ensure the delivery of
expected standards of service in a timely and consistent manner.
10.0 Next steps
Kier Marriott and Wastecycle continue to identify and implement improvements in waste management performance and service provision.
� Kier Marriott is using the knowledge and experience gained at Bowbridge Primary School to demonstrate to
new clients the actions that can be taken to increase the sustainability of projects and reduce waste. This has
contributed to the company being appointed to additional framework and project contracts.
� Wastecycle is developing an improved data reporting tool on its online customer area to support
developments in SWMPs and requirements from customers.
� Kier Group is establishing waste management service contracts that include requirements for reporting waste
data in a way that supports the company’s approach to delivering SWMPs.
� Kier Marriott is undertaking a review of the waste management contractors on the regional supply chain to
ensure existing and new companies meet defined criteria.
� Kier Marriott has developed a Waster Transfer Note proforma that is used by site staff to record the
approximate composition of the waste within mixed waste skips. This process enables the capture of data on
mixed waste streams to inform decisions on waste segregation and management. Kier Marriott is also
requiring waste management contractors to undertake a similar exercise. This enables the data to be cross-
checked and gives greater confidence in the outcomes.
� the Bowbridge Primary School project has successfully achieved a number of awards including the RICS East
Midlands Award 2009 for Sustainability.
11.0 Further information
WRAP has prepared a range of resources to assist construction contractors and waste management contractors in
achieving Good Practice waste recovery in construction. They can be found at www.wrap.org.uk/construction and
include:
� action plans for construction contractors and waste management contractors;
� further case studies;
� guidance on services, reporting and auditing; and
� guidance on using model contract clauses.
www.wrap.org.uk/construction