Your Role: You are a manager for RiceUtility Production, and you missed themeeting with the consultants design team.Youve been given their PowerPoint file.
You have to let the other two managers onthe committee know what you think of theproposed design.
Sample Chemical Engineering
Student Team PowerPoint forAnalysis
7/28/2019 Aceton Plant
2/25
Note: Throughout, orange slides like thisone will ask you questions to help you pickout things you want to remember about
designing team PowerPoints.For more help or background information:Making Logical Technical
Arguments PPT; Team Presentations in Chemical and BiomolecularEngineering PPT
Sample Chemical Engineering
Student Team PowerPoint forAnalysis
7/28/2019 Aceton Plant
3/25
Acetone Production PlantDesign
December 2, 20__
Student Team AFrom Ace Consultants
7/28/2019 Aceton Plant
4/25
Project Motivation
Rice UP - acetone requirement for
increased Anphal production
Maintain ROI at higher production rate
7/28/2019 Aceton Plant
5/25
Project Goals
Increase Acetone Production by 30%
Minimize Plant Costs
Operating costs
Additional capital purchasing costs
7/28/2019 Aceton Plant
6/25
. eac or an r pp ng o umn1. Reactor and Stripping Column
1. Reactor and Stripping Column
7/28/2019 Aceton Plant
7/25
Sample Chemical EngineeringStudent Team PowerPoint for
Analysis
What was the point of the processflow diagram you just saw? Is thisthe teams recommendeddesign?
What is the team trying to tell youabout their work?
Are you impressed by their designso far? Why is it good?
Go back for a second look.
What should the heading be?
In regard to the previous slide:
7/28/2019 Aceton Plant
8/25
2. Acetone Purification
7/28/2019 Aceton Plant
9/25
3. Isopropyl Alcohol Recovery Column
7/28/2019 Aceton Plant
10/25
Process Specifications
99.9% Pure Acetone
90% Pure Hydrogen
TOC
7/28/2019 Aceton Plant
11/25
Cost Analysis
$243,000 /yr profit from given base case
~1 per pound of acetone product profitmargin
7/28/2019 Aceton Plant
12/25
If these are the specifications, what
criteria will you be looking for in the
teams design?
What does the team need to show you
to convince you the design will do
what is needed?
Did the team meet these requirements
in its design solution? How do you
know?
In regard to the previous slide:
7/28/2019 Aceton Plant
13/25
Modeling Issue
UNIFAC VLE Model does not accuratelypredict x-y diagram at high acetoneconcentrations
NRTL is best property package foracetone/water binary system
Based on DeChema VLE data
7/28/2019 Aceton Plant
14/25
Options
1) Use extractive distillation methods
2) Purchase 39MM lb acetone (openmarket)
3) Produce 97.6% acetone
7/28/2019 Aceton Plant
15/25
1) Extractive Distillation
3 Solvents 1,2 dimethoxyethane (Diglyme)
Acetonitrile
N-Methylpyrrolidone (NMP)
Case Study: Diglyme
Prohibitive Cost $6.765 MM /yr to purchase Diglyme
Additional Column
7/28/2019 Aceton Plant
16/25
How do you know the cost of extractivedistillation Is prohibitive?
Why is the Diglyme case of interest?
Is an additional column a solution orpart of the cost?
Is extractive distillation theh usualmethod of making acetone?
In regard to the previous slide:
7/28/2019 Aceton Plant
17/25
2) Purchase Acetone
Purchase 39 MM lb per year acetone for$10.92 MM
Shut down acetone production
Minimize investment losses
7/28/2019 Aceton Plant
18/25
How does the team know the cost willbe this much?
What has been the cost trend foracetone in the past?
How much of a loss will be avoided?
How do you know?
In regard to the previous slide:
7/28/2019 Aceton Plant
19/25
3) Produce 97.6% Acetone
Need to add 3 heat exchangers
Renegotiate deal?
Break-even point
7/28/2019 Aceton Plant
20/25
In regard to the previous slide:
What about the break-evenpoint?
What would it cost to produce
acetone at this purity?
Is that purity acceptable?
What is this slide telling us aboutthe option?
What do these three bulletpoints have in common?
7/28/2019 Aceton Plant
21/25
Recommendations
Buy acetone off open market
Dissolve acetone production facility
Recover maximum amount of lost $$
7/28/2019 Aceton Plant
22/25
Conclusions
Adjustment of property package identifiedseparation difficulty
Possible solutions Extractive distillation
Purchase acetone on the open market
Renegotiate contract for lower acetone purity
Purchase acetone on open market is best
7/28/2019 Aceton Plant
23/25
In regard to the previous slide:
Why put the conclusion after therecommendation?
7/28/2019 Aceton Plant
24/25
TAKE AWAY POINTS
After viewing this PowerPointWhat are yourtake-away lessons thatyou will apply to your own PowerPointnext time?
7/28/2019 Aceton Plant
25/25
This team puts its conclusions at the end and didnot use informative headings on its process flowdiagrams. The headings do not outline the
argument.
A pitch that presented the recommendation firstand gave evidence of calculations to support
claims would have been more persuasive.The PPT cant reinforce the oral message orpersuade readers on its own.
For more help:Making Logical Technical Arguments PPT; TeamPresentations in Chemical and Biomolecular Engineering PPT