Method Statement for Testing
and Commissioning Of
Security Access Control
Testing.
Document: Method Statement Access Control Testing
Revision: 0
Commtech Asia (Singapore) Pte Ltd 138 Cecil Street #10-01 Cecil Court Singapore 069538 Tel: 65366372, Fax: 65366243, web: www.commtechasia.com
Access Control Testing 26 October 2015
Document Control
Contract No: SN15005 Contract Description:
Citibank - South Quarter Jakarta - Office Fit Out
Document Title: Method Statement for Security Access Control Testing Document No:
Rev. Date Comments:
0 23 October 2015
Prepared by: Checked by: Approved by:
Name
Initials VG
SDA
DFA
Prepared by: Checked by: Approved by:
Name
Initials
Access Control Testing 26 October 2015
Contents
1 Introduction………………………………….…… 4
2 Test Instruments/Tools Required…………….. 5
3 Reference Standards…………………………… 5
4 Test Procedures…………………………………. 6
5 Test Execution……..……………………………. 7
6 Test Record Sheets………………….………… 8
Access Control Testing 26 October 2015
1.0 Introduction.
1.1 The following test procedure has been prepared as a guideline for the Testing Of Access Control systems for this project.
1.2 This is to be enhanced and developed by the Contractor. Additional testing and
commissioning requirements may be proposed by the Contractor as appropriate and agreed with the Project M&E Engineer and Independent Testing and Commissioning Engineer.
1.3 This procedure will be adopted for all Access Control Equipment.
1.4 All Testing and Commissioning documentation must be presented for the
relevant Power Supplies to the Security equipment.
1.5 Schedule of equipment fitted and locations to be submitted prior to testing and to be attached to this report.
Access Control Testing 26 October 2015
2.0 Test Instrumentation / Tools Required.
2.1 All instrumentation used for the testing of Access Control Equipment, must have up to date (with at least 6 months validity) calibration certificates that is traceable to international standards
2.2 The following test instrumentation & tools will be required to undertake the tests
detailed within this procedure: Details to be recorded on equipment record sheets at annex A.
Loop Impedance tester.
Voltage Tester/ Multimeter
3.0 Reference Standards.
The Contractor is to confirm all Local and International codes relevant to this installation.
Access Control Testing 26 October 2015
4.0 Test Procedures.
Preparation.
Carry out the following prior to starting any testing. 4.1 Ensure all wiring is 100% complete, and that all ancillaries have been installed
correctly. 4.2 Confirm incoming cables have been tested in accordance with requirements.
4.3 The contractor shall carry out and submit test records on the testing equipment
record sheet included within the electrical test sheets. Tests to include
Insulation tests.
Loop Impedance Tests.
Cable Continuity Tests.
Electrical Resistance Tests
Visual Checks
Visual checks for physical installation against shop drawings and
‘Equipment Schedule’ spreadsheets.
Check general construction and standard of finishing are acceptable.
Check levelling and alignment are correct and acceptable
Check hinged panels with equipment mounted are properly grounded.
Check all fixings are of non-ferrous materials.
Visual Check - Incoming-outgoing Cables.
Check proper facilities have been provided for fixing of incoming/outgoing
cables.
Check adequate space has been allowed for fixing of incoming/outgoing
cables.
Check proper tightness of cable terminations has been checked.
Check proper identification has been provided for each cable.
Check unwanted openings have been sealed up.
Access Control Testing 26 October 2015
5. Test Execution.
The contractor shall carry out and submit all test records on the ‘Testing & Commissioning Report Forms’ for all applicable equipment. Test to be conducted will include the following:
Check operation of Entry Doors.
Check operation of Electric and manual locks.
Check operation of Exit Pushbuttons.
Check operation of ’thumb lock door opening devices (BGE).
Check operation of Break glass Units (BGU).
Check operation of Power Override Switches (POS).
Check operation of audible door alarms (sounders) and or strobe lights
(ADA/ST)
Check operation of any key-switches for ADA’s and or strobes.
Check operation of any emergency exit push bars.
Check operation of any other monitored doors.
Check operation of system on standby battery power.
Check operation of locks on standby battery power.
Access Control Testing 26 October 2015
ACCESS CONTROL TESTING EQUIPMENT RECORD SHEET Project: Citibank Jakarta Location: INDONESIA, JAKARTA Contractor:
Instrument List - Security
Type/Function Make Model Serial No. Date of
Calibration Certificate attached
Issued By:
Signature: Name: Date Contractor
Received By:
Signature Name: Date Commtech Asia
Access Control Testing 26 October 2015
Security System Test Sheet
Door Testing and Commissioning Report (On-site)
Office Location: Door Name:
Door Number in Layout: ( )
Door Type: Single Door Double Door Sliding Door
Wood Glass Steel Other:
DEVICE CONFIGURATION
Door Lock Electromagnetic Strike Drop-bolt Other:
Magnetic Contact Surface Mount Concealed
At Door Entry At Door Exit Other Location
Reader
Release Button
Exit Alarm
Break-glass
Key-switch
Yes / No
Device Layout is conformed to the requirement as set out in floor plans and door schedules
TESTS Yes / No
Door Lock Door is closed tight when door lock activated
Door Contact Alarm triggered when forced open
Card Readers (Touchpad) When correct card is swiped (PIN entered) LED turns green
When wrong card is swiped (wrong PIN) the LED stays red
When correct card is swiped door will open
When wrong card is swiped the door will remain locked
Touchpad is physically tested and functions normally
Release Button Door opens when release button is pressed
Audible Door Alarm/Strobe Sounder/Strobe activates when door is forced open/held open (60 Sec)
Sounder/Strobe can be turned off by key
Sounder/Strobe turns off when door closes
Emergency Break-glass When break-glass is triggered:
Power for door lock is cut off
Door can be opened
When door opened alarm is triggered
System Backup Power Test door readers function when mains power is off
Lock Backup Power Test doors remain secure when mains power is disconnected
Checks with Security Control Centre Yes / No
Correct card number received for entry
Wrong category card information received when tested
Door forced open report received
AKS activated/reset report received
Break-glass report received when tested
REMARKS:
Tested by: Name: Signature: Date:
Contractor
Witnessed By Name: Signature:
Date; Commtech Asia