Accelerated Construction October 2014

ACCELERATED CONSTRUCTION El Paso District

Page 2: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Table of Contents

2

5-7

8-10

11-14

15-20

21

3-4 Overview

Lane Rental – IH 10/LP 375 Interchange

Milestones – Spur 1966

Milestones – IH 10 Downtown Bridges

A + B – IH 10 at Cotton Street

Summary

1

2

3

4

5

6

22-25 Takeaways 7

Page 3: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Overview

3

We do need to use accelerated construction techniques in El Paso -

– ADT’s on IH 10 vary from 100,000 to 236,000.

Page 4: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Overview

Nothing new. We’ve been doing this for a while.

Will cover some recent applications of the following in the El Paso metropolitan area –

– Lane Rental

– Milestones

– A + B Bidding

4

Page 5: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Lane Rental – America’s Interchange

IH 10 / LP 375 Interchange Construction – Series of projects to construct DC’s where none existed.

Phased Construction

– Phase I: Completed as design/build project $110M

– Phase II: On-going, $43M

– Phase III: To Begin 2015, $32M

5

Page 6: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Lane Rental – America’s Interchange

Project Goals for construction

Complete projects quickly and safely -

– Minimize traveler delay

– Maximize safety for the public and workers

– Minimize impact to rush hour

IH 10 ADT = 100,000

LP 375 ADT = 69,000

6

Page 7: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Lane Rental – America’s Interchange Method used to achieve

Project Goals - Lane Rental – Good fit

because the existing lanes are really only affected by some of the operations.

Contractor has options, but it is fairly clear what we don’t want them to do.

Lane Rental doesn’t necessarily mean that the overall project will be finished sooner.

It provides a method to minimize the impact to traffic.

Perception - we are still out there, but we’re not in the way.

7

Page 8: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Milestone – Spur 1966

Spur 1966 – New location Spur, $31M

Provides additional mobility around the University of Texas at El Paso

Construction consists of new structure over IH 10 mainlanes and railroads, connection to US 85, elevated roundabout at Schuster Ave., and grade separated pedestrian facilities at UTEP.

8

Note about Spur 1966 –

The 1965–66 Texas Western Miners basketball team, now known as the University of Texas at El Paso made history by winning the 1966 NCAA Men's Division I Basketball Tournament in 1966, becoming the first team with an all African American starting line-up to win an NCAA basketball national championship

Page 9: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Spur 1966 – Milestone

Project Goals for construction

Complete project quickly and safely

– Minimize disruption of classes at UTEP

– Maximize safety for the public, students, and workers*

– Minimize impact to IH 10 traffic

* - Attend Tim Twomey’s presentation in Construction II session for more about safety on this project.

9

Page 10: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Milestone – Spur 1966

Method used to achieve Project Goals -

Milestone – Good fit because it is difficult work in very constrained work area and no real way to avoid significant impacts to motorists and UTEP.

A milestone with a disincentive was established to complete the portion of the project most disruptive to UTEP during the summer break.

Schuster Ave. was closed. Work began on the $5M milestone at the end of May 2013 and was completed by end of August.

10

Page 11: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Milestone – Downtown Bridges

Downtown Bridges– $9M

Overall project provides for enhancements and improvements to IH 10 structures in downtown El Paso and the US 54/IH 10 interchange.

– Phase I - Structure repair, painting, and decorative pedestrian fencing on several bridges over IH 10

– Phase II – Other improvements within interchange

11

Page 12: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Milestone – Downtown Bridges

Project Goals for construction

Complete project quickly and safely

– Minimize traveler delay

– Maximize safety for the public and workers

– Complete work over IH 10 prior to special events in the area in October 2014

IH 10 ADT = 178,000

12

Page 13: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Milestone – Downtown Bridges

Methods used to achieve Project Goals - – Milestone with

different calendars – Good fit because only part of the work affected traffic and upcoming events:

– Phase I – Critical work over IH10. Work performed on a 7 day calendar with a milestone incentive and disincentive.

– Phase II – Other work not affecting interstate traffic performed on a standard workweek calendar.

13

Page 14: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Milestone – Downtown Bridges

Milestone in Phase I No Excuse Incentive was provided for by SP 008-163. The same amount applies as a disincentive after October 17, 2014. A. No Excuse Incentive for Early Substantial Completion of Work. The Department will pay the Contractor an incentive for early Substantial Completion of Work for Milestone 1, as defined above. The full incentive will be paid ONLY if the Contractor substantially completes the work on or before October 7, 2014 with the exceptions for the allowances of adjustments as provided herein. The full incentive for early Substantial Completion of Work is $250,000.00. For every day after October 7, 2014 the Contractor takes to meet Substantial Completion of Work, the incentive will decrease by $25,684.00 per day. NO incentive will be paid for Substantial Completion of Work after October 17, 2014. Time charges for computing incentive for early Substantial Completion of Work will not be adjusted for weather, weekends, holidays, suspension of contract time; unforeseen utility, right of way, railroad issues, or due to issues related to construction work; or any other unforeseeable event not under the control of the Department.

14

Page 15: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

A + B – IH 10 Bridge Hit

We had a bridge hit last year and A + B bidding was used to accelerate the repair.

Not this one. Hardly anybody noticed this bridge hit near downtown El Paso.

ADT = 236,000

15

Page 16: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

A + B – IH 10 Bridge Hit

Everybody noticed this one.

ADT = 178,000

16

Page 17: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

A + B – IH 10 Bridge Hit

IH 10 Bridge Hit – $1.5M

On October 18, 2013, a train derailed under IH 10 at Cotton Street.

The impact caused significant damage to the substructure.

Train cars can support bridges. Don’t try this at home.

All WB lanes were closed until shoring was installed. Two lanes of IH 10 WB were closed until repairs could be completed.

17

Page 18: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

A + B – IH 10 Bridge Hit

Project Goals

Re-open lanes on IH 10 as quickly as possible

– Complete repairs ASAP to relieve significant traffic congestion created by the loss of two lanes

– Maximize safety for the public and workers in close proximity to rail line.

Note: The rail line was re-opened shortly after clearing the debris and installing shore towers.

18

Page 19: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

A + B – IH 10 Bridge Hit

A + B was a good fit because traffic was already affected and opening the lanes was critical.

Using Road User Cost for the closed lanes, we established the “B” portion for bid –

Bidder Dollars Time Total

J. D. Abrams $1,389,160 15 $1,951,660

Jordan-Foster $1,084,600 30 $2,209,600

Haydon $1,170,458 30 $2,295,458

Sundt $863,300 40 $2,363,300

Contractors could earn $37,500/day, up to 3 days, as an early completion incentive.

19

Page 20: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

A + B – IH 10 Bridge Hit

Project Timeline

Bridge Hit – October 18th

Bid Opening – October 22nd

Work Begin – October 26th

Lanes Open – Nov. 2nd

Project Complete – Nov 6th

J. D. Abrams opened the lanes in 8 days and completed the project in 12 days. They received the full incentive.

Note: U.P.R.R. reimbursed 100% of costs including the incentive.

.

20

Page 21: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Summary

Lane Rental – Use this strategy to manage lane closures to minimize impact to traffic during construction.

Milestones – Use this strategy if there is a specific phase of the project with more impact to traffic, businesses, or other stakeholders.

A + B Bidding – Use this strategy for large or highly critical projects where early completion is so important that it should be a consideration for award of the contract.

21

Page 22: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Takeaways

Think through your goals. Don’t just tell the contractor to go fast.

Identify your objectives and use the right tool.

Assure that the contractor has the flexibility to implement new ideas.

It does rain in the “desert”.

22

Page 23: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Takeaways

Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season amount of 5.14 inches, making it the 30th wettest on record. Other totals include 14.32 inches in Orogrande, NM, 16.45 inches at an NWS employee’s home in northeast El Paso, and 19.10 inches in Cloudcroft.

Source: NWS El Paso

23

Page 24: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Takeaways

Assure that acceleration goals and priorities are clear and straight-forward.

It is a balancing act. Safety of the public and workers MUST be considered to establish reasonable goals for acceleration.

Striping materials make a mess in a collision, but more importantly -

24

Page 25: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

Takeaways

Attenuators save lives.

25

Page 26: AcceLERATED CONSTRUCTION · Sometimes it rains a lot - North American Monsoon 2014: The El Paso International Airport received 6.72 inches, which is 130% of the normal monsoon season

Accelerated Construction October 2014

QUESTIONS? [email protected] 915-790-4300