19
Welcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated Bridge Construction University Transportation Center (ABC-UTC) at Florida International University Website: abc-utc.fiu.edu Email: [email protected] October 16, 2014 – 1:00 p.m. to 2:00 p.m. Eastern

Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Embed Size (px)

Citation preview

Page 1: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Welcome to Webinar onAccelerated Bridge Construction

Accelerated Bridge Construction in Pennsylvania

Sponsored byAccelerated Bridge Construction University Transportation Center

(ABC-UTC) at Florida International University

Website: abc-utc.fiu.eduEmail: [email protected]

October 16, 2014 – 1:00 p.m. to 2:00 p.m. Eastern

Page 2: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Webinar AgendaABC Announcements (10 minutes)Featured Presentation (35 minutes)

Accelerated Bridge Construction in Pennsylvania

Lou Ruzzi, P.E., District Bridge Engineer, PennDOT (Pittsburgh area); &

Nikki Bedillion, P.E., Senior Associate, Johnson, Mirmiran & Thompson, Inc.

Question and Answer (15 minutes)

Please post your questions in the chat box

Page 3: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

2014 National Accelerated Bridge Construction Conference

December 4-5, 2014December 3 – Nine (9) workshops

Hyatt Regency, Miami, Florida

www.2014abc.fiu.edu

Page 4: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

2014 National Accelerated Bridge Construction Conference

Online Registration Deadline is Friday, November 21

www.2014abc.fiu.edu

Page 5: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Travel Scholarships

A few travel scholarships are still available

Send an email to [email protected]

Page 6: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Nine Workshops – Wed., Dec. 3, 2014

Four workshops from 8:00 am to Noon

W-01: Lightweight Concrete – A Tool for Accelerated Bridge Construction Part I

W-02: Today’s Precast, Prestressed Concrete Bridge Design

W-03: Rapid Replacement of Bridges Using the SHRP2 ABC Toolkit

W-04: GeoTechTools – Geotechnical Solutions for Accelerated Bridge Construction

Visit www.2014abc.fiu.edu for Details

Page 7: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Nine Workshops – Wed., Dec. 3, 2014

Five workshops from 1:00 pm to 5:00 pm

W-05: Lightweight Concrete – A Tool for Accelerated Bridge Construction Part II

W-06: Guidelines for Design of Efficient Steel Bridges using AASHTO LRFD Bridge Design Specifications

W-07: GRS-IBS – Geosynthetic Reinforced Soil Integrated Bridge System – for Accelerated Bridge Construction

W-08: Design Management (DM) Guide for Design-Build and Construction Manager / General Contractor Projects

W-09: Slide-in Bridges: Overview for Owners, Designers, and Contractors

Page 8: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Additional Information

Please visit www.2014abc.fiu.edu to:- Register online.

- For exhibiting and list of exhibitors to date, visit Exhibitor page of the Conference web site. Fifty (50) Companies to date have reserved their booths. Space is still available.

Page 9: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

In-Depth Webinar Series

MassDOT’s 93FAST14 Project

November 4, 201411:00 a.m. to 3:00 p.m. Eastern

Six 40-minute modulesVisit www.abc-utc.fiu.edu

Page 10: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

In-Depth Webinar SeriesNov 4, 11:00 a.m. to 3:00 p.m. Eastern

Module # Module Title Speaker

1 Introduction Tom Donald, P.E., Director of Bridge Project Management, Massachusetts DOT

2 Planning and Preliminary Design

Mike Culmo, P.E., Vice President, Transportation & Structures, CME Associates, Inc.

3 Design Details –Substructure Rehabilitation

Joe Gill, P.E., President, Gill Engineering

4 Design Details –Superstructure Replacement

Joe Gill, P.E., President, Gill Engineering

5 Preliminary Construction Planning

Kevin Lampron, Jr, P.E., Area Manager, J.F. White Contracting Company

6 Construction Kevin Lampron, Jr, P.E., Area Manager, J.F. White Contracting Company

Page 11: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

In-Depth Webinar SeriesNov 4, 11:00 a.m. to 3:00 p.m. Eastern

Registration Process

1- Visit www.abc-utc.fiu.edu2- Select In-Depth Webinar Option3- Walk through the steps4- Cost is $95 per site

for all six 40-minute modules

Page 12: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Automated ProcedureIssuing PDH Certificate

Procedure is automated!

Page 13: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

FHWA Every Day Counts‐3 Websitehttp://www.fhwa.dot.gov/everydaycounts/summits/edc‐3.cfm

Page 14: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

FHWA EDC‐3 Websitehttp://www.fhwa.dot.gov/everydaycounts/summits/edc‐3.cfm

Innovation Sessions at EDC‐3 Regional Summits– broadcast live –

Ultra‐High Performance Concrete Connectionsfor Prefabricated Bridge Elements:

• October 23, 2014: 3:15–5:00 pm CT• October 30, 2014: 8:00–9:45 am PT

Register online

Page 15: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

FHWA EDC‐3Websitehttp://www.fhwa.dot.gov/everydaycounts/summits/edc‐3.cfm

Innovation Sessions at EDC‐3 Regional Summits– broadcast live –

Geosynthetic Reinforced Soil– Integrated Bridge System (GRS‐IBS):

• October 23, 2014: 1:00–2:45 pm CT• October 29, 2014: 1:00–2:45 pm PT

Register online

Page 16: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

FHWA EDC‐3Websitehttp://www.fhwa.dot.gov/everydaycounts/summits/edc‐3.cfm

Innovation Sessions at EDC‐3 Regional Summits– broadcast live –

• 3D Engineered Models• Improving Collaboration & Quality

Environmental Documentation• Improving DOT & Railroad Coordination

Register online

Page 17: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Please visitabc-utc.fiu.edu

for other ABC-related news and events

Page 18: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Next WebinarMonday, November 10, 2014 (1:00 – 2:00 p.m. Eastern)

Featured Presentation

Milton-Madison Bridge Replacement: the Mega-Lateral Slide

byKevin Hetrick, P.E., Design Director, Office of

Innovative Project Delivery, Indiana DOT;Aaron Stover, P.E., Michael Baker Engineers; &

Charlie Gannon, P.E., Walsh ConstructionTo register, visit: www.abc-utc.fiu.edu

Page 19: Accelerated Bridge Construction in Pennsylvania · PDF fileWelcome to Webinar on Accelerated Bridge Construction Accelerated Bridge Construction in Pennsylvania Sponsored by Accelerated

Webinar AgendaABC Announcements (10 minutes)Featured Presentation (35 minutes)

Accelerated Bridge Construction in Pennsylvania

Lou Ruzzi, P.E., District Bridge Engineer, PennDOT (Pittsburgh area); &

Nikki Bedillion, P.E., Senior Associate, Johnson, Mirmiran & Thompson, Inc.

Question and Answer (15 minutes)

Please post your questions in the chat box