333Acceler8 UpdateKenneth G. Ammon, P.E.
Deputy Executive Director, CERP
Task Force MeetingWest Palm Beach, Florida
February 22-23, 2006
Acceler8 UpdateKenneth G. Ammon, P.E.
Deputy Executive Director, CERP
Task Force MeetingWest Palm Beach, Florida
February 22-23, 2006
Everglades Restoration Accelerated Projects
Everglades Restoration Accelerated Projects•• CC--43 (Caloosahatchee River) West 43 (Caloosahatchee River) West
ReservoirReservoir
• EAA Reservoir Phase I/Boles & Cross Canals
• EAA Stormwater Treatment Area Expansion
• Picayune Strand (Southern Golden Gate Estates) Restoration
• C-44 (St. Lucie Canal) Reservoir / STA
• Water Preserve Areas
• Biscayne Bay Coastal Wetlands Phase I
• C-111 Spreader Canal
Active Construction ProjectsActive Construction Projects
STA 2, Cell 4 Site Preparation ISTA 2, Cell 4 Site Preparation IISTA 2, Cell 4 Expansion ProjectC-43 West Storage Reservoir Test Cell Pilot ProjectSTA 5, Flow-way 3 ProjectSTA 6, Section 2 Construction and Section 1 Modification
STA 2 Cell 4 Expansion ProjectSTA 2 Cell 4 Expansion Project
North Build-out
South Build-out
Cell 4
STA - 2
CONTRACT INFORMATIONCONTRACT INFORMATIONA8 Project Manager: Maria Clemente, P.E.A8 Construction Manager: Rich Hall, P.E.Design Consultant: Brown and CaldwellConstruction Contractor: Gulf CorporationContract Amount: $18,688,458Notice to Proceed: January 10, 2006
Substantial Completion #1: November 6, 2006Substantial Completion #2: June 8, 2007Final Completion: July 18, 2007
CONSTRUCTION PHOTOSCONSTRUCTION PHOTOS
EAA STA 6 Section 2EAA STA 6 Section 2
CONTRACT INFORMATIONCONTRACT INFORMATION
A8 Project Manager: Maria Clemente, P.E.A8 Construction Manager: Rich BartlettDesign Consultant: URS CorporationConstruction Contractor: Harry Pepper and Assoc.Contract Amount: $23,460,167.Pre-Construction Meeting: February 6, 2006Notice to Proceed: February 7, 2006
Substantial Completion #1: December 11, 2006Substantial Completion #2: June 8, 2007Final Completion: July 18, 2007
CONSTRUCTION PHOTOCONSTRUCTION PHOTO
C-43 Test Cell ProjectC-43 Test Cell Project
CONTRACT INFORMATIONCONTRACT INFORMATION
A8 Project Manager: LuAnn McVicker, P.E.A8 Construction Manager: Bruce Phillips, P.E.Design Consultant: Stanley ConsultantsConstruction Contractor: Barnard Construction Co.Contract Amount: $10,245,000Notice to Proceed: January 16, 2006
Substantial Completion: June 6, 2006Notice to Proceed: April 15, 2007
CONSTRUCTION PHOTOSCONSTRUCTION PHOTOS
EAA STA 5 Flow-way 3EAA STA 5 Flow-way 3
CONTRACT INFORMATIONCONTRACT INFORMATIONA8 Project Manager: Maria Clemente, P.E.A8 Construction Manager: Miguel Cruz, P.E.Design Consultant: URS CorporationConstruction Contractor: Interlaken, Inc.Contract Amount: $12,903,000.Notice to Proceed: January 18, 2006
Substantial Completion #1: November 19, 2006Substantial Completion #2: March 21, 2007Final Completion: April 22, 2007
CONSTRUCTION PHOTOSCONSTRUCTION PHOTOS
Acceler8 Accomplishments Since December 2005
Acceler8 Accomplishments Since December 2005
EAA Seepage Canal & Embankment Preliminary DesignEAA STA 2 Cell 4 Construction Started 1/11/06EAA STA 5 Flow-way 3 Construction Started 1/18/06EAA STA 6 Section 2 Construction Started 2/7/06Biscayne Bay Draft BODR SubmittedBiscayne Bay Coastal Wetlands start Preliminary DesignC44 Reservoir Draft BODR SubmittedEAA Reservoir CM @ Risk Team Ranking Identified
Acceler8 Milestones Prior to Next Task Force Meeting
Acceler8 Milestones Prior to Next Task Force Meeting
C43 Reservoir Test Cell Celebration 2/24/06Site 1 BODR 3/17/06C111 BODR 3/20/06C44 Reservoir Test Cell Celebration 3/24/06Acme Basin B Ground Breaking 3/21/06C43 Reservoir CCM 3/27/06Construction Symposium Martin/St. LucieOkeechobee 4 & 5/06