Upload
dinhdang
View
221
Download
1
Embed Size (px)
Citation preview
16April 2013
RailwaysAbout
Contents
04
06
09
10
12
14
16
18
19
22
24
26
28
30
33
36
38
Perfectly in placeThere it is, high and dry above the 20-metre-deep North Sea:
the topside for the Riffgat wind park, designed and
constructed by the Strukton Hollandia JointVenture
Next stop Hästveda! About a drastic improvement of regional transport in the
south of Sweden
The missing link 270 km of a cherished dream are still missing:
a railway line along the Gulf of Bothnia that connects
Sweden and Finland. This Norrbotniabanan is expected
to materialise, although no one knows when
A great boostEurailscout renews long-term contracts in the Netherlands
and Denmark
“Let’s get going as quickly as possible!”Technical consultant Rob Redeker about the (mock)
commotion surrounding the launch of the ERTMS safety
system in the Netherlands
Beyond borders in three stepsStrukton Rail Equipment is gradually expanding into a single
European organisation and supervisor Silvio Gehde is
growing along
Packed up in the Netherlands, unpacked down underOne day, four ballast removal trains went on their way to
Australia. A blow-by-blow breakdown of the journey
The Hanze Line, the prologueAbout what had been going on before the new line was
included in the timetable. Testing, testing, testing and the
icing on the cake
Photo on cover:
Fridhemsplan Station, one of 105 stops that make up the Stockholm
metro. Strukton Rail has been awarded greater responsibility for
an even longer period. Read more about this on page 4, ‘Subway
contract in Stockholm’.
In a nutshellNewsflash
Europe 3.0: the worldStrukton Rail’s CEO Schoots about two decades of growth,
starting in the Netherlands, extended into Europe and now in
countries further away. “The real big growth will be beyond
Europe’s borders”
No waters too wide, no shore too farThe international orientation of Strukton’s Italian partner
Clf Group is bearing fruit. Projects are waiting in Algeria,
Montenegro and Venezuela
The history of a planThe Delft Railway Zone undergoes prestigious urban renewal.
Strukton Rail secured the contract for the superstructure
The brightest boys in the classA visit to one of Strukton’s ‘centres of excellence’, the
Belgian Survey Team. “The supporters of our approach are
getting the upper hand”
PaperworkBy 2020, the new CBTC safety system is to be operational
on the S-Bane in Copenhagen. Siemens is to supply the
system and Strukton/Aarsleff to install it. The year 2012 was
characterised by meticulous preparation
Notes on a bleak undertakingWhen does a job become hopeless? And then what? Icy
cold renewal in Stuttgart
Tracks through the Iron KingdomMidsummer and it’s the first day of work on a track renewal
project between Storvik and Morshyttan
Training for the topStrukton Rail in Sweden is making work of its future. Eleven
men and women entered a trainee programme in the autumn
of 2011 aimed at making them the managers of tomorrow
About Railways 16 I April 2013 54 About Railways 16 I April 2013
In a nutshellA fellowship in Italy – In honour of the
memory of Managing Director Giuseppe
Neri who passed away in 2010 at the age
of 63, CLF has created a Research
Fellowship at the University of Bologna.
Additionally, the railway construction com-
pany will be awarding an annual ‘Giuseppe
Neri scholarship’ to the best technical thesis
in the ‘field of rail infrastructures’. The first
Research Fellowship was awarded to
Stefano Angelini (24), who recently qualified
as an engineer at the University of Bologna.
He will be conducting further research into
‘optimising rail networks’.
Orders for Rolling Stock – Strukton
Rolling Stock succeeds in securing four
promising assignments within a relatively
short period of time. Malaysian monorail
producer Scomi orders 72 traction inverters
for 12 new monorail trains on the Kuala
Lumpur network. Further assignments for
Scomi in Brazil and other emerging markets
are expected. South African Transnet Rail
Engineering, good for the renovation of
more than 2,500 passenger trains and
freight locomotives, places an initial order
for electronic controls. Both parties see
potential gains in gradually expanding
cooperation. In Amsterdam and Toulouse,
Strukton Rolling Stock secures international
tenders. Strukton Rolling Stock will deliver
new auxiliary converters for the Amsterdam
metro S3M4 vehicles. The tender in
Toulouse concerns the order from Tisséo
for the delivery of battery chargers and
inverters for all 28 fully-automated VAL206
vehicles. Back in 2011, Strukton Rolling
Stock received an order from Tisséo for all
new IGBT chopper traction converters for
the metro vehicles in Toulouse.
POSS in Istanbul – Strukton Systems is
installing the POSS monitoring system at
two stations along the light rail connection
between Istanbul and Atatürk Airport. POSS
will be monitoring four points at each station
for the initial period of a year. POSS is the
preventive maintenance and fault diagnostics
system developed in-house by Strukton.
Operated remotely, it monitors the condition
of points and other rail equipment.
The system successfully prevents at least
35% of all potential cases of malfunction.
Tracks in Den Bosch – The tracks in
and around Den Bosch station are ready for
serious renewal; the location will be trans-
forming from a bottleneck to a major junction
offering capacity for increased train traffic.
Bridges and fly-overs will be constructed,
rails disentangled and platforms extended.
Strukton Rail secured the sizable super-
structure contract and will be responsible for
everything from engineering to implementation.
The project embraces all disciplines needed
for the railway system. Work got underway in
summer 2012, constructing an emergency
platform and renewing the tracks, points,
overhead line construction, safety systems,
sound system, platform and station roof.
The project will be completed in summer
2014.
Subway contract in Stockholm – Major
contracts, presented with pride: Strukton Rail
AB signed on the dotted line of the renewed
maintenance contracts for two rail networks
in Stockholm: the subway and Roslagbanan
railway systems. In both cases, the customer
is Storstockholms Lokaltafik (SL). More so
than under the previous contracts, Strukton
Rail will bear responsibility within the chain
for tasks ranging from inspection to imple-
mentation. Strukton Rail will therefore be
taking over some activities from SL. The term
of the contract has been extended from three
to nine years. The contracts are valued at a
sum of €340 million. Stockholm’s subway
network is more than 100 km long and
counts 105 stations. Roslagsbanan is a
65-km-long narrow-gauge urban railway
system in Stockholm with 39 stations. The
new contracts started on January 2013.
SNCF joins Eurailscout – A second
domestic market for Eurailscout; only far
bigger than that of the Netherlands. The UFM
160 track inspection and measurement train
will be relocating permanently to France. In
the not too distant future, Eurailscout France
will emerge focusing entirely on carrying out
measurements across the French railway
network, with the exception of its high-speed
lines. All in all, offering good prospects for a
new undertaking.
France’s national railway company SNCF
joined forces with Strukton Rail to lead
Eurailscout Inspection & Analysis. SNCF took
over the 50% stake from Strukton’s former
partner and co-founder of Eurailscout, the
German railway company GSG Knape. At the
presentation of SCNF’s entry in September
2012 Strukton Rail’s CEO Aike Schoots said:
“Cooperation between SNCF and Strukton
will provide a quantum leap ahead, to further
develop and operate measurement trains and
data management technologies. This will
enable us to improve the quality, safety, cost
effectiveness and transparency of the railway
network.” SNCF Infrastructure’s CEO Pierre
Izard also spoke only of benefits: “Using the
synergies between our own skills which
enabled us to design the Iris 320 inspection
train that measures the geometry of high
speed lines at 320 km/h, and those of
Eurailscout which are also founded on
innovation and efficiency at the service of
rail infrastructure maintenance, we will be
able to develop state-of-the-art solutions to
assist infrastructure managers and European
rail network maintainers.” Eurailscout already
has international operations in countries
including the Netherlands, Belgium, Denmark,
Switzerland and Italy.
Even more POSS for ProRail – Dutch
railway manager ProRail has given Strukton
Systems an order to connect 487 points to
the POSS monitoring system. They must be
connected and operational in 2013. A total of
more than 1,850 of the most significant and
crucial points in the Dutch rail network –
those at forks and station entrances – will
be equipped with POSS. POSS currently
monitors several thousand rail objects around
the globe. Within the space of a decade, it
has expanded to become Europe’s most
widely used points monitoring system.
A new workshop – Strukton Rail and Arriva
started using a new joint workshop in
Zutphen featuring five tracks, two of which
are used by Arriva for the maintenance of 38
regional passenger trains. Strukton Rail will
be using the train workshop not just for
standard activities such as maintaining its
own track-based machinery and locomotives
but also for installing train security systems
and overhauling third-party trains. Anne
Hettinga, Managing Director of Arriva in the
Nederlands refers to the cooperative venture
as unique and a very special milestone for
the organisation: “Because, for the first time
in the Netherlands, we will be responsible for
maintaining our own rolling stock. A good
outcome driven by market forces.”
A strategic takeover – Strukton Rail has
acquired a 50% stake in A1 Electronics
Netherlands. The healthy PCB producer is of
key importance to Strukton Rolling Stock and
Strukton Systems as a supplier. It narrowly
escaped being dragged into bankruptcy.
For many years, A1 Electronics has special-
ised in producing PCBs in limited and
medium-sized series. Opting not to go in
for mass production in 2001 appears to have
been the right strategic choice. In just over a
decade, A1 Electronics has expanded to
employ a 22-strong workforce, generating
increasing annual revenues.
Only 2010 showed a slight dip, which was
amply compensated by 35% growth the
following year. The company produces
electronic PCBs and end products for heavy
industry (automotive, aviation, paramedical,
infrastructure) and home automation or
domotics (interior automation in professional
market segments including care centres).
Strukton Rail uses PCBs in its train systems.
The partial takeover will safeguard
organisation-wide quality and continuity.
Joining forces in the high-tech market
– Seizing a stronger position in a broader
market through utilising greater expertise.
Harnessing synergies served as the driving
force behind Centric TSolve’s transition to
Strukton Rolling Stock effective January
2013. The former 25-strong division of
Centric ICT will be further expanding its
specialisation under the new name of
Strukton Embedded Solutions. Strukton
Rolling Stock occupies a unique position
worldwide when it comes to developing,
producing and supplying drive systems
(traction converters), on-board supply
converters (auxiliary converters) and train
control and management systems (TCMS).
Under its old name, Strukton Embedded
Solutions specialised in providing engineering
services in the fields of electronics, embedded
software and project management, focusing
on wireless communication, automotive
modules and pre-compliance testing.
The workforce will continue operating in the
Benelux region and Germany. The benefits
of joining forces will manifest in (power)
electronics, embedded software, mechanics,
PLC/ Scada technology, assembly and
production. Centric TSolve previously formed
part of the ICT organisation of Centric BV, a
broad-based supplier in the field of computer
services, financial services, and consultation
and engineering services, employing a work-
force of more than 15,000 employees at
home and abroad. In mid-2010, Centric took
over the Strukton Group from NS.
About Railways 16 I April 2013 76 About Railways 16 I April 2013
Europe 3.0: the worldA statement from Strukton Group’s 1992 Annual Report:
“Realisation of the European internal market immediately
raises the question of whether expansion will take place
across national borders. The answer is affirmative. Particularly
for the railway industry, which Strukton will use to expand into
neighbouring countries. In so doing, cooperative ventures will
be sought with suitable companies and potential takeovers
considered.”
Who or what came first?
“I think I joined the company just before the chapter opened.
But I was not alone. Frank van Rijssen, then Chairman of the
Board for the Strukton Group, and I shared this vision: we will
only achieve growth if we expand abroad as well. We anticipated
that achieving economies of scale would become the trend. It
was a choice of, well, ‘to be or not to be’ and we decided to
go for it.”
Twenty years ago, a small-scale
subcontractor entered the European arena,
filled with optimism about a single
European market. Today, Strukton Rail is
one of its biggest private players.
Chief executive Aike Schoots has shaped
its growth over these same two decades.
His vision of Europe’s railways, then and
now – and more far-flung markets,
tomorrow and thereafter.
From a very optimistic angle on European unification?
“Yes. And we’ve not lost that optimism either, having been reinforced
by years of experience now. The railways are inherently multinational,
with standardised tracks. That we’ve still got some way to go can be
seen from the introduction of the European signalling system ERTMS.
But you can also see that we’re persevering, however costly or bumpy
the road may be. The railways are becoming increasingly European.”
Reinforced by years of experience?
“You can see what Europe itself is struggling with: national interests
versus community interests. Everyone knows that open borders bring
loads of benefits, but there’s caution when it comes to creating real
economic and political unity. This reverberates across the world of rail,
an especially traditional industry. Each country continues to have its
own focus. We’ve always taken this into account. Although it is lifting,
step-by-step, it’s still very ingrained. Austria is perhaps most alone, but
it’s everywhere. You find it in legislation, allowing access to equipment
for example. The headlights have to be changed for each country, a
different board, a different axle gauge, a different braking system.
But language too. In Sweden we register in Swedish; in France in
French. There isn’t a universal language in our world; the airline industry
is much closer on that front. But still, the fact that the French railway
company SNCF has now become our partner in Eurailscout provides
me with the best proof that the river is calmly flowing in the right
direction. Pressing on with the comparison, there has certainly been
turbulence, waterfalls, groynes reversing the flow, swamps, and more,
but the direction of movement is unswerving. France is opening up as a
huge potential domestic market for our specialised products in the field
of measurement, monitoring and maintenance management.
By the way, Europe was never a question for us: we had to make
tracks abroad. In the Netherlands, the scale is too limited and the
market too small to sufficiently develop all aspects of the railway
profession at the highest level, to conduct research and development
and to provide an adequate springboard for new products.
The market is just too small to earn back investments in the quality and
capacity of people and high output machines. We’ve developed into a
state-of-the-art rail service supplier; our machine park needs tens of
thousands of km of track to be sufficiently utilised.”
Venturing into Belgium, Italy, Sweden and, although more difficult,
Germany, proved successful, but Strukton Rail has had to suspend
activities in Norway and Denmark because structural progress was poor
at first.
“Actually, it’s not that bad. That we’ve not succeeded in Norway is
disappointing for several reasons. There’s a great deal of overdue
maintenance in Norway and the demand for good service is high.
Still, we’ve not succeeded in getting the organisation on track; we’ve
not been able to attract a sufficient number of good – but especially
loyal – professional people. But we’re persevering in Denmark. We
entered the fray too soon there; the political intention to deregulate the
maintenance market recoiled. And we were insufficiently prepared at
that point. Our staff then were more strategically and politically oriented
and less able to provide operational direction. We didn’t manage to
shape that sufficiently at the time from the Netherlands.
Now, almost five years down the line, Strukton Rail still has a foothold
in Denmark, with a small team of dedicated people, and highly
proficient, operationally oriented management. Prospects are good.
We carry out major projects with our partner Aarsleff. We’re cooperating
well, but will ultimately have to go for it alone. Given the language
aspect, we’re largely linked to Sweden, with support from Germany and
the Netherlands. We’re aiming for a stable annual turnover of some €20
to €30 million, generated mainly through specialisation: machine work,
measurement, monitoring, maintenance engineering, catenary systems,
traction systems – our top products that offer a high degree of added
value.”
What were the biggest adventures over these twenty years?
“There have been three. In 1996, the works carried out in Italy ultimately
led to us taking out a stake in Clf, the biggest rail construction company
there. The foundation of Eurailscout, the specialised rail track
inspection and measurement company followed in 2000. And in 2006,
Strukton Rolling Stock, through which we took the plunge into
developing and producing converters in the form of traction converters,
auxiliary converters and train control and management systems (TCMS)
for use in people movers, trains and locomotives. The demand for
these products is now worldwide. These three events were very
exciting, each of them ultimately delivering positive results.
About Railways 16 I April 2013 98 About Railways 16 I April 2013
Italy turned out to be a good move. We drew our high-output
technology from there, the first renewal train in our country; we’ve
generated enormous returns from it. The next step for us is to look
and learn from Clf to see how they succeeded in generating profits
in Algeria and Venezuela with major contracts. Venezuela ties in with
our ambitions in Colombia. We intend to shape these in cooperation
with the Geoingenieria engineering agency that has been active
there for more than 20 years. Geoingenieria forms part of the
Antea Group, with 100 offices in 15 countries in which the engineering
and consultancy activities conducted by our owner Oranjewoud are
established. A large-scale metro project and several heavy rail projects
are in the pipeline in Colombia. We’ll see what we can do there. And in
the same way our Italian company Clf leads the pack in Venezuela, so
too will we pull ahead in Colombia.”
To what extent did the crisis in Europe prompt you to venture abroad?
“We took the initiative at an earlier stage. I’m convinced we can
achieve growth in Europe’s niche markets; read Eurailscout in France.
Europe is certainly not a ‘dead end’. Like I said, things are still flowing
in the world of rail. Aside from the environmental aspect, a determining
factor in Europe will be whether travellers demand an excellent rail
product. But the real big growth will be beyond Europe’s borders.
We’re looking at Australia for example. There’s definitely a market
there for our expertise. While we have yet to define our strategy for
Australia in stone, we’ve got aspirations to get our feet on the ground
there. The question is whether we’ll be doing that in a partnership
or not. We’re working for BHP Billiton at the moment: heavy trains
carrying iron ore from the mines to the Port Hedland docks.
Operations there have to run like clockwork without disruption; the
economic interests involved are huge. Finally, we’re also working out
what we can do in the Middle East, more specifically in Saudi Arabia,
the Emirates and Qatar. The demand for logistics there is enormous.
We share our interest in these markets with Clf. We’re still getting our
bearings, but we plan to get going in at least one or possibly two of
these areas.”
How would things be if the choice for European expansion had never
been taken?
“As a subcontractor back then, we actually supplied strong men to
work on the railways. I think we’d certainly still be going. In any event,
we’d be a smaller player – more at the back of the pack than out in
the lead. Perhaps we’d have degenerated or downgraded to a tempo-
rary employment agency for rail layers. And maybe we’d have had to
close shop because we missed the boat with the trendsetters in our
industry. Now I can boldly say that we’re one of the top two players in
Europe. And that in our way, not only in terms of critical mass, but
certainly and especially because of the technology we offer, we’re
number one.”
No waters too wide no shore too far The international orientation of Strukton’s Italian partner Clf Group is bearing fruit.
With fruit falling far and wide in some cases.
Clf Group is shifting its focus to specifically
embrace foreign markets in addition to its
Italian home base. Within but a few years,
the organisation must be generating more
than 40% of its revenues abroad. Clf’s
commercial director Pier Paolo Bertozzi:
“Areas in which we intend to achieve further
development, where we are participating
in tenders and seizing new opportunities
include the Maghreb, the Balkans and
Central East Europe, the Arab States of
the Persian Gulf and South America.”
Clf is no stranger to the world beyond the
borders of Italy. It first built up experience
on foreign shores 20 years ago in Poland.
Since then, projects have been successfully
concluded in the countries of former
Yugoslavia and in Bulgaria. In recent years,
headed up by Bertozzi, Clf further shaped
its ‘foreign team’ and established permanent
representation in Croatia, Bulgaria, Serbia,
Montenegro, Algeria, Morocco and
Venezuela.
Clf’s unswerving foreign policy is still
delivering new foreign contracts in Algeria,
Montenegro and Venezuela. Although ‘Algeria’
had been in the pipeline for some time, last
year saw definitive preparations get under
way. Clf has built a portfolio of close to 600
km of track and is looking forward to kicking
off in 2013 with laying phase one – 132 km
of dual track for the high-speed line between
Oued Tlelat and Tlemcen. The customer is
Anesrif, acting on behalf of Algeria’s Ministry
of Transport, which is responsible for the
development of railway projects, from pre-
liminary studies to tendering.
In September 2012, Clf started work in
Montenegro implementing a contract to
renew and upgrade part of the country’s most
important line, the Bar-Vrbrnica, a stretch
between Mijatovo Kolo and Mojkovac. The
contract is valued at €10 million; the financing
comes partly from the European Commission
and more than half in the form of a loan from
the European Investment Bank. Clf is the
main contractor, carrying responsibility for the
superstructure, electrical systems, security
systems and civil engineering works, including
bridge and tunnel renewal. The work essentially
follows on from an assignment completed
earlier in January 2012, involving the renewal
of the Trebaljevo-Kolasin line.
In the wake of the Italian-Venezuelan
consortium Grupo Contuy, Clf has also been
successful in Venezuela. Since 2002, Grupo
Contuy has been working on large-scale civil
engineering assignments within the scope of
a mega rail works project intended to deliver
more than 13,000 new km of track in
Venezuela by 2030. Grupo Contuy carried out
tunnel works on the line between the Port of
Puerto Cabello and La Encrucijada and Clf
has now been awarded to lay the connection:
128 km of dual track. The line includes
15 tunnels adding up to a stretch of 27 km,
41 bridges and 13 overpasses.
Venezuela, a country that is certainly not
known for its railways, hopes to have linked
up all its major cities by the year 2030.
The overall ambition is one of being able to
comfortably accommodate 240 million train
travellers a year by that time.
Track renewal in Bulgaria, October 2011
About Railways 16 I April 2013 1110 About Railways 16 I April 2013
Once upon a time, let’s say in the late
Middle Ages, when Delft was already world-
famous, an earthen mound was raised here,
with a moat and a city wall to keep out
enemy factions. Centuries later, a railway
line was laid alongside and a station built.
They were situated on the periphery of the
ancient city centre at the time, a highly
practical arrangement. A century and a half
later on, despite not having moved an inch,
they literally bisected the city, which had
expanded to around ten times its size in the
meantime. Delft had a problem; it had been
cut in two, the incision was far from pretty
and had an alarming air of permanence.
They’d tried all sorts of solutions: turning
the canal into a tram line, running the trains
over a viaduct, traffic engineering solutions,
but the city remained split. Although getting
rid of the level crossings did benefit the
city’s rapidly expanding motor traffic levels,
the trains continued to squeal their way
around the bend of the viaduct – while the
constantly shaded strip of car park below it
was soon adopted as a dog-walking area
cum student urinal. The viaduct was tightly
restricted to dual track, which began to
cause increasing problems, as the remain-
der of the Randstad conurbation developed
a sorely needed four-line network. The city
became one big traffic jam, its railway con-
gested. Then Dutch Rail (NS) came up with
the idea of broadening this bottleneck on
stilts to twice the width, and the council
dug its heels in sharply, determined not to
allow another carbuncle to appear on its fair
city’s already wrinkled complexion.
The time was finally ripe for an ambitious
the history of a plan
One doesn’t encounter these very often: extensive, prestigious urban renewal
operations, in which the railway is the core of both the problem and the solution.
The Delft Railway Zone is just such a project. Strukton Rail secured the contract
for the superstructure. “The real work actually started in March
2012, close to the future entrance at the
northern end of the tunnel. We began
excavating at the former yard where raw
materials were previously loaded and
unloaded. New rails and points are to be
laid at almost this very spot in 2013, albeit
at a level 2.5 metres higher. At the southern
end, we began building a substation for the
power supply to the track in the tunnels. We
are also to lay a 10kV connection between
the main power station and this substation.
2013 will be primarily characterised by
preparations for the work to be carried out
in the tunnel. We will then have three
months’ time to build the track in the
tunnel: two separate tunnel tubes, each
of which can accommodate one track.
The cables come first, then the ballast mats
to absorb some of the noise and vibrations,
then the ballast and sleepers, rails and
overhead power lines. We will have to go
full tilt for three months, constantly on the
move, building everything up one layer after
the other. That’s a lot of work within a short
“You’ve got one entrance and one exit, and that’s it”
Joost Delwel spent six years cutting his teeth on contracts, project planning and
tender management, just waiting for that one opportunity. He wanted the chance to
operate in the field; to take charge of both a major and multidisciplinary project.
The Delft Railway Zone became the one.
space of time; there won’t be much time for
sleep. Six months of technical testing will
then follow, by which time the end of 2014
will be upon us.
The work in the tunnel is causing us some
logistical headaches. You’ve got one entrance
and one exit, and that’s it. You can’t just skip
from the one track to the other, and therefore
have to follow one another up the line.
The work has to be carried out in a city centre.
The idea is to start in the middle and build
outwards in opposite directions, but we may
ultimately opt to go in one direction.
Thankfully, we have sufficient time to consider
all the angles of this interesting problem.
All of this will keep us occupied until the end
of 2014, at which stage we will proceed to
work several long weekends. In the spring of
2015, we will divert the existing surface track
to link up to the new ones in the tunnels.
This process is to be completed in one go.
While people will therefore still be using the
aboveground platform on the Thursday, by
the next Monday morning they’ll be boarding
and disembarking down in the tunnel. It is
both highly exciting and spectacular, because
there will come a point of no return when
everything will have to work properly. By that
stage – in 2015 – the media are bound to have
sharply focused their attention on the project.
The current major challenge we face is that of
coordinating the various disciplines involved.
During the course of 2013, we will have to
remain focused on 2014 and the construction
to be carried out in the tunnels. And through-
out the project, up to and including the
handover, we will have to clearly account for
our actions, given the nature of our contract
with ProRail. It is a design & build contract
with a supplementary clause. This implies
that it states in the finest detail exactly what
is to be done; we will have to remain
particularly alert to that supplementary
clause. The contract states that a great deal
remains unclear regarding the project at the
moment. We have already witnessed large
numbers of changes, additions and aspects
that are now entirely different to those on
which the tender was originally based.”
solution which would benefit the city and the
railway alike. The year was 1988.
The result is Delft Railway Zone, 30 hectares
of integrated redevelopment. Between 2025
and 2035, having borne the burdens of wind
and weather and investments to the tune of
some one billion euros, Delft emerges once
more as though reborn, in all its splendour.
The ugly incision has undergone some
cosmetic surgery, rendering it an elegant zip
fastener, swathed in a flowing green robe,
encrusted with the sparkling gems of water
features and a municipal park. And concealed
below is an underground car park.
Heading southwards, one encounters an
area peppered with housing and offices.
The municipal office building, a glass palace
dating from 2016, now graces the square
opposite the former railway station. This
palace also accommodates the station
concourse, however, with the station below.
It is located in the middle of two dual track
tunnel tubes, extending over a 2.5-km-long
stretch beneath the zip fastener. Two tracks
were already laid in the one tube in 2015,
while laying in the other remained shrouded
in the mists of the future. The tramline was
the only feature left in place.
After a preparatory phase spanning 20 years,
construction commenced in 2009. The work
had been split into four contracts: the tunnels,
the railway construction, the fitting-out of the
station and the municipal office building.
The one for the tunnel laying was awarded in
2008. The superstructure contract was
awarded to Strukton Rail in 2011, a five-year
project. And Strukton Bouw secured the
fitting-out contract in 2012. The core of the
superstructure contract acquired by Strukton
Rail, consists of laying dual track in one of
the tunnel tubes. This also includes the
connection to existing track, the overhead
power lines, the safety systems, the power
supply and the construction of a new railway
yard once the existing one occupying the
spot has been demolished.
The Delft Railway Zone:
About Railways 16 I April 2013 1312 About Railways 16 I April 2013
There are offices with their own version of
an attic room or garage storeroom. Take
Strukton Rail’s establishment in Merelbeke,
Belgium, for example. Don’t take the stairs
up in the main entrance, but take a sharp
right down and then follow the passage, left
through the workshop, past the storage
area, up a narrow flight of stairs at the end,
through a door, another right and then, at
the end of the passage where you can go
no further, it can’t be missed, a 4x4 room
with two windows looking out onto a blind
wall. It’s as cosy as any office could be. It
smells of coffee and confidence. The plants
look healthy. This is where the four-strong
Belgian Survey Team works, consisting of
Jo Derie, Bart Meeus, Peter de Reu and
Tom de Strooper – surveyors, the lot of
them.
The brightest boys in the classSnow and cold management in Sweden, machine work
in Germany, high-tech monitoring in the Netherlands:
in every country where Strukton Rail works, there’s
always something that’s faster, better or smarter than
elsewhere. Jargon puts it as ‘best practice’, ‘best of
class’ or ‘centre of excellence’. Bundle the centres and
you have the future in your hands. If it’s superior
surveying skills you’re after, you need the Belgian
Survey Team. Distance is not an issue.
As a team, they’ve elevated the art of track
positioning and alignment maintenance to
unprecedented heights. Even faster, more
precise and more efficient – and all this
demonstrable within a millimetre. When
there’s talk at Strukton Rail about centres of
excellence or best of class within the scope
of internationalising working methods, the
Belgian back room is never far away.
Jo Derie is the life and soul of the party.
After twelve years of measurement work for
specialised topographic maps, he was ready
for a change. He was used to working with
state-of-the-art equipment and had immersed
himself in the art of software development
purely out of curiosity. Armed with this
knowledge, he began focusing on railways
in 2004. What he encountered in terms of land
surveying at that point was minimal. “It was
as if the clock had stopped.” At work he
developed a new digital toolbox, a platform
where measuring equipment and track
machines speak the same language, operate
in the same world and can exchange data.
His work got noticed. Derie was rewarded
by the boss, won bronze at the national
Creativity Awards in 2009 and received the
Innovation Award at the Belgian Building
Awards in 2010. Derie and his team pressed
on to round off major projects in Belgium,
Denmark and the Netherlands.
Take the Hanze Line, which perhaps best
illustrates what they’re capable of achieving.
The construction team there ran into a brick
wall in terms of the deadline at the end of
2011 when the work had to be rounded off
and delivered. Track subsidence developed,
many more centimetres than expected in
places. Track geometrics needed definitive
refinement, high-speed quality. ProRail
squeezed in an extra session of measurement
and tamping work. Strukton Rail Equipment
wanted the best measurement quality and
recommended the Belgian team with a
glowing report about its hand in positioning
Diabolo, close to Zaventem. At such short
notice?
The men take over from one another, without
interruption, like cyclists in the lead group
chasing the finish. Jo Derie kicks off:
“Measuring and tamping in such a way as to
achieve the highest quality at the lowest level
of input from the tamping machines. You get
the design: this is what’s needed, a basic file
of less than a megabyte. The measurement
work begins, thirteen weeks of measurement,
surveying more than 200 km of track.
Data being fed back to Merelbeke every day.
Where requirements and reality were brought
in line and where a programme to manage
the tamping machines the next day was
devised. Tamping work rarely hits the spot
first time round: tamping machines do the job
in layers, at the lowest level of input. And
then the measurements are verified.”
A ‘just in time’ job
Bart Meeus takes over: “Yes, it was a ‘just in
time’ job. Measuring during the day, sending
the data through at night and recalibrating the
tamping machines for the next day. Stretches
of four to five km a day – a day’s measurement
yield matching the average capacity of the
tamping machine – a pace we could comfort-
ably maintain. Before, without the technology
developed in house, we’d have needed
sixteen hours of measurement for eight hours
of work with the tamping machine.”
Jo Derie adds: “Efficiency gains are largely
delivered by controlling the tamping machines.
We can get the machines to deliver the
best quality at the lowest level of tamping
runs. Some sections of the Hanze Line were
tamped four times, where five or six times
would have been necessary before.”
Tom de Strooper continues: “Yes, that was
before. Measuring small stretches, knocking in a
picket every 20 metres and then, tape measure
in hand, chalking in the measurements on the
track by hand. If we’d applied techniques like
that on the Hanze Line, measuring one km of
track a day would have been an achievement.
The capacity of the machines always out-
stripped the measurement output. Now we’re
in sync. And we simply plug a memory stick
into the tamping machine: direct transmission
of measurements to control. Work to the
millimetre and verification to the millimetre.
Even deviations can be precisely mapped.”
The benefits for customers are clear. Jo
Derie: “We made the deadline for ProRail
without having to push the machines too
hard. We succeeded in delivering a much
better product, more swiftly and efficiently.
Everyone speaks enthusiastically about it;
the men behind the machines are proud of
their work. The people are getting convinced,
those who support our approach are getting
the upper hand.”
“We quickly earn back what we cost...
and more”
But however much praise they receive,
scepticism remains. The mutterings of men
who swear by surveying pegs, tape measures
and chalk are visibly declining, flaring up
only on rare occasions to former heights;
commercial assertions that these methods
are too costly are holding ground for the time
being. “Quality costs money,” responds one
of the team. Another says: “It’s always the
‘last minute’ aspect though, if we could help
out after all because things aren’t going that
swimmingly.” Jo Derie continues: “We’re
probably a bit on the expensive side still.
But we do eliminate failure costs. If there
are no failure costs, they don’t come into
consideration. I’m convinced we quickly earn
back what we cost... and more. Could it be
done for less? Yes, but then you need to
place it in a broader context. We need to
establish a Europe-wide surveying team, with
people on site working towards the same
objective in the same way. With a centralised
processing unit. We’ve got to get away from
all the fragmentation.”
Whether they still use any of the good old
tools? Mirror callipers, circular slide rule, or
even more old fashioned. Peter de Reu looks
around on his desk: “Sometimes a pencil to
write down a fixed point.”
From left to right: Peter de Reu, Jo Derie, Tom de Strooper and Bart Meeus
About Railways 16 I April 2013 1514 About Railways 16 I April 2013
Only if the mass of paperwork has been approved down to the smallest
detail, will we get the green light to commence with the job of actually
installing the system in 2013. The first of the five phases has the status
of ‘early deployment’ and therefore offers scope for the resolution of
any teething trouble, while also offering drivers and traffic controllers
The CBTC – which stands for Communication Based Train Control –
safety system was to be installed on an autonomous metropolitan rail
network, consisting of four lines comprising a total of 170 km of dual
track and 84 stations. It is known as the S-Bane, and is situated in
Copenhagen.
The system supplier, Siemens, engaged the joint venture Strukton/
Aarsleff to perform the work. The work began by setting up a store-
room for a vast collection of documents: an installation schedule and
a test procedure. Every minute detail of how balises, axle counters,
cables, access to the radio system and the interlocking connection
were to be installed had to be accurately recorded. The customer,
Banedanmark, did not wish to run any risk whatsoever of receiving
claims, once the actual work had commenced.
PaperworkAnother seven years to go. By 2020, the new CBTC safety system is to be operational
on the S-Bane, the Greater Copenhagen suburban (metro) network. Siemens is to
supply the system and Strukton/Aarsleff to install it. The year 2012 was characterised
by meticulous preparation.
It took four months to get the schedule and procedure into order in
theory. Then another four months later, in August 2012, a test track
over a km long line had been set up. Several more months would be
needed to compare the theoretical and practical aspects, so that all
the paperwork might gradually begin to correspond with the actual
reality to be created during the next few years. The workforce of
Strukton/Aarsleff had until the end of 2012 to amend the installation
schedule on the basis of their newly acquired knowledge.
Jens Otto Daugaard is in charge of the venture. “A routine job?
No, anything but. You’re about to install a new system in a business
that is already operating. That’s hardly standard procedure, and
the method we are to employ is also new to us.” He laughs. “It will
become routine, I hope, as we begin to gain more experience.”
CBTC
CBTC and the European safety system ERTMS are like fraternal twins. Both are based on signalling comprising moving blocks.
They similarly facilitate higher train frequency, while offering improved safety and reduced maintenance costs in comparison with contemporary
‘fixed-block’ systems. The crucial difference is that CBTC uses radio signals for train-track communication, while ERTMS uses GSM-R.
This difference makes CBTC ideally suited for (partly) underground metro and light rail networks. ERTMS in turn enjoys preference on (inter)
national rail networks, because it complies with strict regulations pertaining to interoperability, which CBTC does not. CBTC does not require
this additional property, as metro systems are almost invariably insular operations, devoid of connections to external networks.
CBTC made its debut on San Francisco airport’s automatic people mover (APM) network in 2003, rapidly proceeding to prove its reliability
for use on more complex autonomous networks. There are currently six prominent system suppliers worldwide. The system delivered by
Siemens is known as Trainguard MT CBTC. Both the Barcelona metro and the Canarsie Line in the New York City subway were equipped
with Trainguard MT in 2009. And Siemens has since become the system of choice in cities as far flung as Paris, Helsinki, Beijing, Nanjing,
Rennes, Budapest, Guangzhou and Sao Paulo.
the initial opportunity to become closely acquainted with the new
system. This is to take place on the Hilleröd–Jägersborg route, one
of the less vulnerable peripheral lines. The final and most vital part, the
central line between Österport and Vesterport, is not to be tackled
until 2018. The system is to be rendered fully operational in 2020.
The line Hilleröd – Jägersberg, pase 1 in the installation of CBTC
About Railways 16 I April 2013 1716 About Railways 16 I April 2013
1. It’s 13 January 2012, Friday the 13th for the superstitious, when
Strukton Rail GmbH & Co KG first unleashes its high output equipment
on this major renewal project in Stuttgart-Untertürkheim. It’s a wintry
day, much like many others – dry, sunny and cold, with temperatures
around freezing. Good working weather. Regional weather statistics for
the past decade are relatively mild. The pros and cons have been
weighed up: the risks deemed acceptable. You can still weld up to a
few degrees below zero. The immediate prospects are good. At least
for now, it looks set to become warmer rather than colder.
2. Broadly speaking, the job involves mechanically renewing a
10-km stretch of track within a timeframe of six weeks during three
extended periods of line closure. The general plan, three 10-day
marathons from Untertürkheim to Zuffenhausen Station. But the
schedule was soon derailed. Although Deutsche Bahn (DB) only
awarded the contract relatively late, a concrete schedule was ready
at the start of November 2011 to commence operations pretty much
immediately after ringing in the New Year. In the run up to the work,
the men from Kassel put forward several proposals to DB for a more
sustainable approach to soil improvement. Good ideas, thought DB,
and adopted them.
Notes on a bleak undertakingRailway tracks and weather conditions – a bumpy marriage. Ballast becomes icepack.
Diesel oil congeals. Gloves stick to the tracks, frozen solid. When does the job
become hopeless? And then what? Icy cold renewal in Stuttgart.
3. Renewing 10 km of track using heavy equipment.
It all sounds straight forward, with a few bends here and there.
Stuttgart-Untertürkheim is more complicated though.
A short to do list:
a depth of 35 cm
Neckar viaduct
year the exclusive domain of the customer; taken up here in the
specifications as the contractor’s responsibility
All aspects of the work must be carried out on a single track.
The adjacent track will remain operational. It’s busy around Stuttgart.
The sirens are bound to be going off every other minute: passing train
on the adjacent track. Quite a challenge, logistically.
4. At peak times, there will be around forty rail workers on the track.
Equipment needed for the job:
an hour
5. It all starts off well. Weather conditions for the time of year are
normal; in any event, they stay within statistical parameters. Part 1 of
the work is carried out and delivered without a hitch and according to
plan. But then things go wrong during the second line closure.
The temperature rises for a bit and the men have to contend with rain,
hail and snow. Then, from one moment to the next, a Siberian cold
front engulfs Western Europe, with temperatures plummeting to minus
15 degrees Celsius at night. The dirty ballast, saturated with water,
freezes into a solid icepack, rendering the ballast cleaner redundant.
The excavators can’t continue. Railway contractors are used to
challenges, but have never had to deal with anything quite like this
before. Unlike on civil engineering projects, the contractor can’t just
cover up the site. One can’t set up a tent over 3.5 km of track.
And laying down your tools from one day to the next and heading
indoors until the frost thaws is unheard of in the rail industry. Come
what may, the line must be taken back into operation; the schedule
around Stuttgart can’t carry diversions. In consultation with the
customer, a decision is reached to restrict the finishing to an absolute
minimum. Installing drainage would be impossible. People and
machines; pushing it to the limit. It’s no longer a question of wanting
to; it’s one of having to. It has to be done and, for this reason, the
track is delivered ready for use at the given time and handed back to
the traffic controllers.
They performed brilliantly, the men on the line, of that there is no
doubt. But this whole episode has certainly kept many a tongue
wagging.
6. When the line is closed for the third time, work grinds to a complete
standstill. The track bed has become so frozen that the ballast cleaner
jams. The parties involved at the time agree that all the available
technical options have been exhausted. It has become technically
impossible to work in accordance with the required quality standards.
In consultation, work is suspended before reaching a point of no return
and rescheduled for a new, as yet unspecified construction period.
7. Nine months later, in November 2012, the work is rounded off and
delivered without hitch and according to plan. The weather then stuck
nicely to the stats.
“A complex balancing act”
Paul de Haas, managing director of Strukton Rail GmbH & Co KG
in Kassel:
“The contract specifies that the contractor must take account of
weather-related risks. We assessed in advance whether the work
could in fact be carried out in January. The risks seemed acceptable
- at least until everything froze unexpectedly from one day to the
next. It’s a bit like doing the splits; you wish you could flip a switch;
come back once the weather’s better, but you know that’s not
even an option. It proved to be a complex balancing act to get
things done. The line needed to be taken back into service, give or
take a temporary compromise in implementation.
When the weather deteriorated so suddenly, we immediately spoke
to our customer to agree on appropriate measures so that the line
could be taken back into service on time. DB recognises and
acknowledges that under such extreme circumstances, the technical
limits under which work can and may be carried out were by far
exceeded. Technically, we found a way to carry out the work
properly in the end. A job like this teaches you the importance of
good communication with your customer. And that gauging risks
presented by the weather – despite having done so well – can pan
out quite differently in practice. And that in the end it’s always
people’s professionalism and ability to improvise that is decisive if
you want to complete such a project properly and on time, despite
all the setbacks. You get a glimpse of just how much people care
about the work they do. Once again, they managed to join hands
to deliver a useable product on time, despite extreme weather
conditions putting a spanner in the works.”
About Railways 16 I April 2013 1918 About Railways 16 I April 2013
All in all, about 100 people have gathered in
groups at Torsåker station. They are
working together on the project during the
summer weeks of 2012. Employees and
machinery from the Netherlands, project
managers from Sweden and a large number
of employees from various subcontractors.
The freight route extends from Storvik in
Gästrikland to Hallsberg. Strukton Rail
replaces sleepers and rails along the
38 km between Storvik and Morshyttan.
The job also includes renovating four
depots, laying cables along the whole
section and replacing seven sets of points
with accompanying signalling and electrical
works. Strukton Rail has committed several
of its high-output machines to this project:
the renewal train, the ballast cleaner and
MFS units. Naturally, the tamping machines,
ballast ploughs and a track
stabiliser are present as well. The total
contract sum is €30 million.
As soon as the Tåg i Bergslagen commuter
train heading for Gävle has passed, people
and machines start to move. The renewal
train is driven into position and starts work
on putting in the new rails and sleepers.
“The upgrading of this section of railway is
necessary,” says Strukton Rail’s Project
Manager Thomas Carlsson. “It carries a lot
of heavy goods traffic, which places a
heavy load on the tracks. This track has old
wooden sleepers that must be replaced,
and the heavily soiled ballast bed must be
cleaned and partly replaced.”
Old sins
The railway passes through the Iron
Kingdom, Bergslagen, a region that bears
traces of olden times. It was here where the
foundations of Swedish industry were laid,
thanks to the iron ore, the forests and
Tracks through the Iron KingdomMidsummer and it’s the first day of work on the track renewal project between Storvik
and Morshyttan.
hydropower. The oldest findings of processed
iron from this region date back to around
2000 years ago. It was the mining and iron-
processing activities that led to the need for a
railway, and in 1875 the freight track was laid
in its original form.
Traces of the past are uncovered. “The
ballast cleaner encounters large stones in
the ballast bed. We’ve also found really old
sleepers and remnants of steel and even
ancient platforms long hidden from view.
The track might well have been relaid a few
times, but it still covers a few old sins,”
explains Johnny Berg, who is responsible for
the project management in this project.
The track replacement train pulls out of
Torsåker station and makes its way through
the Kingdom of Iron. Torsåker was named
after Thor, the god of thunder, who swung his
hammer while driving his chariot across the
skies. Whether or not it’s Thor causing dark
clouds to gather over the valley, a thunder-
storm breaks out and work has to be stopped
for safety reasons.
The track is available for work for 7 hours a
day, between 09:30 and 16:50 hours. During
these hours, time also has to be set aside for
signalling and electrical engineers to restore
the track to a navigable state before trains
are allowed to use it once more. After all, the
track has to be fully operational again before
17:00 hours.
Languages and dialects
Day 2 starts off with a meeting. Project
management and supervisors gather to
assess yesterday’s work and review deviations
reported by staff. It’s one way of gathering
experiences and learning from situations that
arise during the project. The new day is
planned: what is to be done, in which
sequence and by whom? Discussions take
place mainly in English, occasionally inter-
spersed with Swedish and Dutch phrases
when explanations and terminology make it
necessary. Even among the Swedish rail
workers there are various accents, as they
migrate through the large country to wherever
there’s work to be done on the railways.
Strukton Rail completed the project
according to plan, renewing an average
of 1,000 metres of track each day.
Training for the topSweden is making work of its future. In the autumn of 2011, eleven men and women
entered a trainee programme aimed at making them the future site managers, project
managers and leaders of Strukton Rail.
“We’ve selected the people we want to see as our future executives
and leaders. We recognise their potential and have seized the
opportunity to foster them in our culture. I think this will have a major
impact on our future,” says Robert Röder, Director of Strukton Rail
in Sweden and the driving force behind the trainee programme.
The participants came from all over. Karin Persson, specialist HR
consultant at Strukton Rail explains: “We are looking for people with
strong leadership skills and the right values. They don’t necessarily
need to have experience of the industry – they will get that from us.”
All trainees get their own mentor and project tasks during the two-
year trainee programme. The trainees also take part in developing the
programme in preparation for the next intake in the autumn of 2014.
Both Karin Persson and Robert Röder take part in the joint trainee
sessions. Each trainee works alongside Robert Röder for a period,
accompanies him in his daily work and takes part in board meetings,
project meetings and meetings with government bodies.
“That was my idea,” admits Robert Röder. “I want to get to know
them, see what they’re made of. When they see my work up-close
they also acquire a broader knowledge about the company; they see
how decisions affect the whole organisation, they see things in
context and how we all work towards the same goals. I also get
feedback from the mentors about their everyday work. Personally
I never took part in any trainee programme, but I’ve had good bosses
who have coached me throughout my career. When I was appointed
CEO in 2000, I assigned two external mentors on the company’s
board of directors to monitor my work for eight years. It was the best
decision I ever made in my path towards becoming CEO.”
Many large companies in Sweden have trainee programmes, but
having the mentees accompany the Director through his working day
is – at least in the railway industry – unheard of. There may be an
opportunity for an exchange programme between countries in which
Strukton operates. Robert Röder: “I have spoken to some of my
Strukton colleagues elsewhere in Europe about this. They are
interested in our training programme and an international exchange
programme may be a possibility. I am happy to welcome trainees
from other countries; we need to find competent people in the whole
group, not just in Sweden.”
Fredrik Nilsson: “A personal journey”
Auto mechanic, railway worker, supervisor, since recently mentor of
two future supervisors and soon-to-be project manager. “The step
from blue-collar to white-collar employee is a big one. It’s a personal
journey that you really have to be prepared to take,” reflects Fredrik
Nilsson. “As a supervisor you can’t just walk away from the job at the
end of the day.”
About Railways 16 I April 2013 2120 About Railways 16 I April 2013
Fredrik had hands-on project management experience before joining
the trainee programme. When Robert Röder asked him what his
ambitions were, Fredrik felt that the next natural step would be to
make his project manager role official. “Provided that I would be
properly prepared,” was the condition that he set. “I knew there were
gaps in my knowledge; things I had to learn before I could take the
next step. While I was familiar with the company and the business,
I lacked certain key competences such as business administration
and construction law. And I needed a mentor.”
With the help of the trainee programme and the support of his mentor,
Fredrik has now filled some of his knowledge gaps and more courses
are planned. He’s not yet sure what the future holds in store.
“As Strukton’s first trainee group, we have a kind of ‘guinea pig’ role.
At evaluation sessions and meetings with the HR department we
discuss how the trainee programme can be developed and improved.
There are also plans to start up a training programme for mentors,”
he says. For Strukton, the trainee programme is an opportunity to find
tomorrow’s leaders. Every group includes a natural born leader who
can inspire others. But you need to identify which candidates can and
want to take the next step; those who can shoulder the responsibility
for planning and take the next step towards an executive role. It’s a big
step that has to be thought through carefully. A journey that takes
some people longer than others to make. I have come part of the way,
but I still need more knowledge and help.”
He keeps an open mind to the future. “Right now I enjoy what I’m
doing. I’ve just finished working on a large track renewal project at
Eastern Region, about 200 km north of Stockholm. I’m interested in
marshalling yard work and station rebuilding projects, but I am really
excited about the idea of new construction projects on virgin land
where we won’t disrupt other traffic.”
Victoria Björklund: “Gaining experience with various tasks”
Three steps in the life of Victoria Björklund: first a work placement
period, then a holiday job at Strukton Rail, followed, in 2011, by the
move to participate in the trainee programme. She thinks it’s a great
way to get to know the company and learn the business.
Victoria is a qualified project engineer with a specialty in railways.
Directly after completing her studies, she got a project engineering job
at Strukton in Norrköping, serving as the coordinating link between
supervisors and project managers. She ordered materials, coordinated
technical work and planned track maintenance times for different jobs.
“I was very well looked after,” she says. “My superiors suggested that I
take part in the training programme, as it would improve my opportuni-
ties within the company. And I get to try my hand at various tasks.”
After completing the foundation training, Victoria also took a number
of special training courses tailored to her personal wishes. “We can
influence our own professional development, what we want to
specialise in and which courses we need to take,” she explains.
“I, for instance, have completed a computer course so that I can work
with the Swedish Transport Administration’s system. I also took a
special course in accident site training. This means I am now accident
site manager and report for on-call duty once every five weeks.”
Victoria says the trainee programme is an excellent way to get an
overall picture of the company, both at a track and administrative
level. She has worked alongside supervisors, project managers and
site managers; she has supervised a number of her own projects and
is becoming ever more familiar with how the company works.
With her training period now entering its second year, she is looking to
deepen her expertise, take on more responsibility and work more
autonomously. “For Strukton, the trainee programme is a good way to
single out competent people internally and provide them with the tools
to grow. But it’s also an opportunity to attract people from outside.
People with different backgrounds, maybe from a completely different
industry, younger people who can contribute new ideas and perspec-
tives.”
Victoria Björklund’s ambitions are becoming ever more specific.
“I recently participated in a rail renewal project,” she says. “Managing
large railway projects, that has my special interest”.
Bart van Odijk: “A bridge between Sweden and the Netherlands”
Bart van Odijk and his wife, born and living in the Netherlands, dreamt
of working abroad. At Strukton Rail in Sweden, Bart is one of the more
cosmopolitan participants in the company’s trainee programme. “I am
delighted that Strukton has given me the opportunity and that it views
my background as an asset to the company. I hope to be a cultural
bridge for the company; a person who understands the mentality of
both countries,” he says in fluent Swedish.
When Bart’s previous employer, an engineering firm in the Netherlands,
hired him out to Strukton, he didn’t hesitate. He proudly accepted
Robert Röder’s offer of a place on Strukton’s trainee programme. This
decision was made easier by the fact that his wife, a qualified midwife,
had no problems finding work in Sweden.
Bart is a qualified engineer with eight years of professional experience
before coming to Sweden. He is knowledgeable about Dutch law,
contracts and client/contractor partnerships. As a trainee, in addition to
improving his fluency in Swedish, he also has to learn the Swedish
regulatory system and acquire in-depth knowledge of a number of
Strukton’s projects. “One of which is a project involving Tvärbanan,
one of Stockholm’s new light rail lines. We are building a side-track to
serve as parking space near the station,” he explains. “And I’m
involved in a number of track renewal projects.”
Bart has learned a lot during his two years in Sweden. He sees both
differences and similarities in the mentality of the Swedes and the
Dutch. “One difference is that there is more long-term micro-planning
in the Netherlands. Swedes tend to solve problems as they arise.”
In his second year as a trainee he hopes to gain experience of other
departments, take on more projects and maybe focus more on the
management side of things. During a two-week period, all mentees will
be working alongside Robert Röder in order to gain an insight into his
role. “His agenda then becomes my agenda. All I know right now is
that I’ll need my passport as there may be trips abroad on the hori-
zon,” he chuckles. “As trainees our task is to come up with proposals
that can help him develop his role – which is fairly uncommon in most
trainee programmes.”
Now that your dream of working abroad has been fulfilled, what’s next
on the horizon? Bart takes a moment to think about it, and then returns
to his bridge metaphor. “I would consider a job that involved helping
Strukton grow in Europe. Perhaps as management or maybe in a
partnership project between different countries. Preferably based in
Sweden, but working on assignments abroad.”
About Railways 16 I April 2013 2322 About Railways 16 I April 2013
There it is, high and dry above the 20-metre-
deep North Sea, a mere 30 km off the
German coastline: the topside for the Riffgat
wind farm, designed and constructed by the
Strukton Hollandia JointVenture.
In mid-February, the state-of-the-art Oleg
Perfectly in placeStrashnov crane vessel put the huge
38x34x16.5-metre structure in place on the
jacket foundation already delivered and
installed by the joint venture.
Once connected and operational, the switch-
ing station will transform eco-power from 30
wind turbines – from 3.6 megawatts each
to 155 kilovolts – enough to supply around
120,000 households with green electricity
from summer 2013.
The Strukton Hollandia JointVenture was
awarded the contract by wind farm owner
Riffgat GmbH & Co. KG, a joint venture of the
North German energy supply company EWE
and Enova, project developer and manager in
the field of wind and solar energy since 1989.
About Railways 16 I April 2013 2524 About Railways 16 I April 2013
Lorries are delivering concrete blocks for the platforms. Points and
tracks are being moved. A footbridge over the tracks is under con-
struction. Hästveda is just one of the locations in the region getting
new or refurbished stations – an investment designed to improve
public transport in northern Skåne and southern Småland. The
stations will be served by Pågatåg (Skåne) and Krösatåg (Småland).
Hästveda has been transformed into a busy work site, with new
platforms being built and tracks being rerouted. The whole project is
called Pågatåg North-East and Krösatåg and includes 16 stations
that previously had no passenger exchange, with work scheduled for
completion in 2014. The purpose is to improve regional traffic. Sveab
is the main contractor in charge of platforms and station buildings,
while Strukton is responsible for all track, electrical engineering,
signalling and telecom work. Project management is carried out
jointly by Sveab and Strukton.
On this particular Monday, everyone has gathered in Hästveda for
a work meeting attended by staff from the Swedish Transport
Administration, which is the principal, Sveab and Strukton. Project
work is being carried out according to a new model, known as
extended cooperation, where all parties are involved in the entire
Next stop Hästveda!Hästveda is a small, tranquil town in the south of Sweden. Its old station building has
remained intact and the name of the main street that passes the station is still Eastern
Railway Street. No trains have actually stopped here since 1975. But Hästveda is about
to wake up from its long sleep. Together with 15 other towns it will be opened up to a
larger labour market.
process from the planning phase to completion. “The main difference
between this and the usual performance contract is our involvement
in the planning process,” explains Strukton Project Manager Björn
Österberg. “We contractors attend the weekly planning meeting.
This results in much better forward planning, and we’re able to
influence how tracks are to be laid and suggest changes.”
Hästveda will be getting two new platforms, one at the old station
building and one between the two tracks. Large concrete elements
are being erected for the footbridge over the tracks. Curious local
residents are keeping an eye on construction work through the fence.
Björn Löfgren is one of the local inhabitants who welcomes the new
station: “More commuter services will make life much easier for people
who live here and work in Malmö or Älmhult. The jobs of the future will
all be around the big cities. Now people can stay here and watch their
children grow up in a safe environment,” he says.
Hästveda has a current population of 1,600 with only a limited number
of jobs available locally. There is no local industry whatsoever.
Businesses, local authorities, the Swedish Transport Administration,
and the Skåne and Småland Regional Councils have all lobbied to
enhance regional train services. This is based on the Swedish
Government’s 2010 decision that included
investments in regional train services in
this area in the national plan for the period
between 2010 and 2021. All the stakeholders
have co-financed the project, with local
authorities in northern Skåne and southern
Småland making the largest contributions.
The work is expected to cost €65 million in
total.
“The whole project gives more people access
to a larger job market,” explains Mats Persson,
Deputy Governor of the Regional Council and
Chairman of the Public Transport Committee
in Skåne. “People are often prepared to com-
mute for one hour each way. This expansion
means that people from places like Hästveda
will be able to reach Malmö/Lund and Växjö
in that time.”
150 years have gone by since the first grand
opening of Hästveda Station in 1862. History
is set to repeat itself very soon in Hästveda
after living with its back turned to the tracks
for almost forty years.
About Railways 16 I April 2013 2726 About Railways 16 I April 2013
When Norra Stambanan, the railway network in northern Sweden,
was built 100 years ago, it did not follow the coastline where the
communities, industries and population centres were. Russophobia,
which had been rampant in Swedish coastal areas during the
18th and 19th centuries, meant that it was built several cannon shots
away inland.
The missing linkA cherished dream, a railway along the Gulf of Bothnia that connects Sweden and
Finland, is creeping its way towards becoming a reality. It is, however, still missing
a 270-km stretch, the Norrbotniabanan or North Bothnia Line. The line is
expected to materialise, although no one knows when. It’s a question of money and
priorities.
The dream of a coastline railway unifying Sweden and Finland along
the Gulf of Bothnia has not faded. Slowly but surely this dream is
becoming a reality. The 190-km Botniabanan opened in 2010,
the Ådalsbanan (the Ådalen Line) was upgraded in 2011, and the
Haparandabanan (the Haparanda Line), which connects Sweden and
Finland, opened in December 2012. But there’s a 270-km stretch
missing between Haparandabanan and Botniabanan, linking the cities
of Umeå and Luleå.
A vital section of 270 km, not just for Sweden but also for the rest of
Europe. The EU considers the Norrbotniabanan strategically important
for linking the primary sections of line, the Northern axis and the Nordic
triangle. Stretches of track that form an indispensable part of the EU’s
Trans-European Transport Network (TEN-T) that must be completed by
2030.
Planning, designing and building a railway line like this will take years.
Today, the government committees on railways (there are six) for
Norrbotniabanan have completed their tasks. Municipalities and busi-
nesses along the line are awaiting the go-ahead to start construction
work as soon as all the environmental assessment work and micro
planning is ready.
Uncertainties surrounding financing
The price tag is expected to be around € 3 billion. EU and regional
funding is available and industries are responsible for building their own
railway sidings and carriages and are prepared to pay rail fees once the
track is completed. The situation regarding financing and scheduling
became uncertain after September 2012 when the Swedish govern-
ment announced ‘historic investments’ along with railways and roads,
earmarking a total investment of more than € 60 billion for the
forthcoming scheduling period. Two railway projects were mentioned in
particular: starting a new high-speed line at Stockholm-Linköping and
phase 1 of the Göteborg-Borås connection. But, again, nothing specific
about the Norrbotniabanan.
There is both professional optimism and frustration at
Norrbotniabanegruppen, the independent interest group made up of
representatives from the region’s municipalities and enterprise, district
councils and county administrative boards who want the line to be
completed. “The main problem for the Swedish government is that
Norrbotniabanan is again not included in the national transport plan,”
says Elisabeth Sinclair, Project Manager at Norrbotniabanegruppen.
The infrastructure budget shows that government is resolved to invest
heavily in the railways. Although this is good news, Elisabeth Sinclair is
disappointed that Norrbotniabanan was not mentioned again. She
hopes to get more news when the final budget is presented. “If the line
is included in the infrastructure bill and we get government’s go-ahead,
we can start work on the first stretch by the end of 2014. It’s not a
question of ‘if’ but ‘when’ the line will be built.”
Needed more than ever before
A large share of Sweden’s key industries – ore, steel and forestry – are
located in the north of the country. Around 90% of the EU’s iron ore
originates there along with a significant part of its copper, gold, silver
and lead stocks too. “Every day, Norrbotten supplies steel equivalent
to one Eiffel Tower going south,” says Elisabeth Sinclair. “Every year,
ore and metal to the tune of almost € 60 billion is processed in
Sweden.” The forestry, ore extraction and steel production industries
are competing for railway space. The slightest disruption to the winding
and hilly single-track Norra Stambanan (the Northern Main Line) has
major economic repercussions, and with new mines opening in
Norrbotten, the railways are needed more than ever before.
All calculations indicate that the railways are socially and economically
profitable. They provide more efficient and less disruption-sensitive
freight transports in the north-south direction. Estimations are that
capacity will increase by 30%, making further regional growth possible.
The 600,000 people who live in the Gulf of Bothnia region will benefit
directly. It is Sweden’s most densely populated region without daily
train connections. Travel times between coastal cities will be halved in
the future. Universities and businesses will find it easier to attract stu-
dents and employees. Tourism will be boosted and carbon emissions
will be cut by around 80,000 tonnes a year.
Elisabeth Sinclair sums it all up: “This is and promises to remain an
exciting journey for us. Norrbotniabanan is about Europe, about
competitive clout, competence management and the environment.
Once the Norrbotniabanan is operational, we’re going to see a real
Klondike type of situation unfolding here – a modern day gold rush.”
But when? “Sometime between 2025 and 2030; probably closer to
2030,” she says. “But that’s only if we can get started now.” And that’s
certainly not the case yet.
About Railways 16 I April 2013 2928 About Railways 16 I April 2013
“We first began working with ProRail when Eurailscout Inspection &
Analysis entered the market around 12 years ago. The old contracts
embraced our comprehensive measurement package: geometrics,
overhead lines, rail measurements (both ultrasonically and, later, using
eddy-current technology), ATB and ultrasonic manual measurements.
That’s what we’ve always done, the rails, two to six times a year;
ultrasonically up to four times a year, depending on the load. That’s
how it went from the start, we were always awarded a new contract.
The advantage being that each year anew, you know that your biggest
customer will still be your biggest customer. The disadvantage for
Eurailscout and customer alike is that with contract renewal being par
A great boostFor years, it was almost a matter of course for Eurailscout’s contract for railway
network measurements in the Netherlands to be renewed. Eurailscout Inspection &
Analysis and ProRail closed a new long-term agreement in the Summer of 2012.
Aad van der Zouwen on the runup to and consequences of the drive for quality
improvement.
for the course, both parties made promises each year and, despite
sharing the ambition to improve things, simply became flooded by
the hectic nature of the job and day-to-day pressures. The world was
changing as a whole, ProRail was changing, we were changing – and
this meant less time or attention for pushing through the intended
improvements. And if you hope to achieve improvements, establish
more efficient processes, then it’s imperative to do so together.
And that’s exactly what we’ve done. We’re planning to work even
more closely and professionally, which will benefit us both,” says
Aad van der Zouwen, Director of Eurailscout, summing up years of
cooperation in the afterglow of a new long-term contract.
ProRail entered into market consultations at the start of 2011 in the
runup to a public tender. Eurailscout had to pit its skills against the
competition in its own back yard. Men of measurements, what are your
views on such a contract? What opportunities and threats do you
perceive? And, one more question, what is it that you actually do? The
consultations led to discussions with three measurement companies.
The outcome showed that Eurailscout had so much more to offer than
the other parties that ProRail aborted the tender process to continue
working with Eurailscout alone.
Not simply a case of copy-paste
Aad van der Zouwen: “In preparation for the discussions, ProRail had
immersed themselves in the material and knew exactly what they
wanted. In the line of ‘I’m going to ask market parties to provide me
services in a commercial setting and I want to specify exactly what
services I require, of what quality and when they are needed, and –
aside from a great price – what I’d like to see in terms of added value.’
This produced a file that surprised us at first. We didn’t just continue
on autopilot, pressing copy-paste on last year’s activities, give or take
a few km of track and a change of frequency. We received a compre-
hensive, highly specific file detailing a strict set of crystal clear require-
ments. Some requirements had been tightened, especially in terms of
coverage ratios, delivery time and demonstrability. New requirements
were also set specifying the timeframe for data analysis and delivery.”
A new set of requirements resulting in new technological challenges?
“Not only technological, but economic too. A higher level of quality in
the form of greater measurement accuracy was requested for a
relatively small section of the package, often coupled with greater
availability and, more often, with the swifter delivery of measurement
results. That’s it for technology. And, purely in economic terms: ProRail
is a big customer, the Netherlands is our domestic market, you
wouldn’t want to lose a big customer, and your domestic market is
your calling card. That’s why it’s also important the contract includes
agreements on working together to enhance efficiency. That gives us a
great boost!”
Precision work at its best
Van der Zouwen refers to the new contract as a ‘boost for quality’ that
will extend beyond the domestic market. “The strength of this is that
we will now create files, shaping processes and procedures directed
at conducting measurements that are demonstrable, clear and
comprehensive. We have to prove that our customer’s requirements
are completely satisfied.
Of course, we can already do this in broad terms. Only now, driven in
part by this contract, the processes will be set up in such a way that
clear insight can be gained at any given moment into everything that is
weighed up, documented, compared and archived in relation to daily
operations. Post-processing will also be boosted because data
elaboration will need to be carried out more effectively and swiftly, with
demonstrable checks to verify measurement validity. We will be creating
a more accurate record of rail components than ever before. This will
be of great benefit to our customers – not to mention ourselves. What
we may previously have aspired to do, will now be integrated into our
business processes. What’s more, we will be able to include being
able to guarantee demonstrability in bidding for contracts in our other
markets. And that we can offer even greater transparency.”
The contract with ProRail started on 1 January 2013 and will run for
three years with an option to extend it twice for consecutive one-year
periods. In 2012, Eurailscout also renewed its contacts with the Danish
railway manager Banedanmark. After a short interlude, during which
Swedish competitor InfraNord got to wave its yardstick around in the
field of geometrics and overhead lines, Eurailscout is back in the
Danish equation with two contracts. Aside from existing ultrasonic and
eddy-current measurements, a further contract has been hammered
out for rail geometrics and overhead lines in the main network for a
term of two years with an option to extend it twice for consecutive
three-year periods. The contract models used by ProRail and
Banedanmark correspond in broad terms. And that’s no coincidence.
Years of careful deliberation in the sub-committees and sub-sub-work-
groups of the standardisation committee of the European Commission
– in this case subgroup 1, workgroup 28 – have borne fruit. Customers
in the various member states have adopted the guidelines on demon-
strability, along with the parameter definitions specifying the related
standard and limiting values. However slowly, and however much
plagued by compromise, the European member states are converging
when it comes to standardisation.
About Railways 16 I April 2013 3130 About Railways 16 I April 2013
And then two ERTMS islands emerged,
Amsterdam-Utrecht and the Hanze Line,
together stretching for around 100 km.
“The problem there being that double
systems had been installed. You can choose:
double systems in the train or double
systems along the tracks. If you install both
ATB train protection and ERTMS safety
control along the tracks, you can travel along
that stretch with conventional trains. But the
costs along the tracks with only ERTMS are
far lower – in my own calculations, more than
50% less – than if you combine a classical
safety system and an entire switching
system. What a pity, because you can’t make
optimal use of ERTMS. What’s more, the
islands are really small in relation to the scale
of our network.”
ProRail, the Dutch Railways (NS) and the
goods transporters first came up with an
integral approach in 2006. The preferred
scenario mapped building ERTMS in to the
trains first and then the tracks. In the process
of adhering to all the red tape, due diligence,
second opinions and sensitivity analyses, the
plan was downgraded to a draft and shelved.
“What a pity. A missed opportunity, I believe.”
What should have happened then?
“I don’t think it was necessary to convert all
the equipment at once. You could also have
started by creating a long corridor featuring
ERTMS between Amsterdam and Eindhoven,
for example, and deploying dedicated
equipment. How much equipment would be
needed? Just equip a limited number of
trains with ERTMS, possibly convertible.
One of the problems, even now, is that you
don’t want to dedicate equipment to a single
corridor; deployment across the Netherlands
is preferable. As a result, you need to convert
far more equipment than strictly necessary
for a long corridor alone. This choice was not
made.”
“Let’s get going as quickly as possible!”Rob Redeker’s business card says
Technical Consultant. He’s the man you
need for advice on anything to do with
signalling systems. He’s been up to his
elbows in it since 1975; first for the
Amsterdam Metro, then for Strukton
Rail. His vision of the (mock) commotion
surrounding the launch of the ERTMS
safety system in the Netherlands.
More than five years ago, the Netherlands was one of the first
countries in Europe to get acquainted with the envisaged European
ERTMS safety system when laying the high-speed line (HSL) to
Belgium and the Betuweroute.
“We weren’t the very first. Switzerland was ahead of us, they were
running a few tests in Germany and Italy was quick off the blocks.
Spain was not one of the first, but sped up with its rollout.”
In any event, the Netherlands was reasonably advanced at that time –
the consequences of which were apparently so shocking that we’re
now among the tail-end Chalies.
“That’s how it looks. Maybe the introduction came at a bad moment.
ERTMS wasn’t fully developed yet, at any rate not for the HSL.
And this had consequences. New versions had to be built in and no
agreements had been reached on the costs. So these got utterly out
of hand. Things went slightly better with the Betuweroute. But the
story with the HSL, well, it struck terror in the industry.”
Another factor compounding the extended
pause was that the Dutch Railways (NS) had
no intention of footing the bill for installing the
safety system in its trains. That’s all well and
good they said, government is asking us to
make commercial choices and we’re not
going down that road.
“NS certainly had a point. Government should
take the lead. I understand NS’ concerns,
being confronted with a mega investment in
equipment. At the very least, a solution
should have been sought.”
Another factor that contributed towards
grounding ERTMS was the idea that it was
ridiculously expensive and would therefore be
economically irresponsible. Amounts totalling
billions were brandished.
“ERTMS is a standard product supplied by
six big groups. In Denmark last year, we saw
that these six push the limits of competition.
Based on two tenders, Denmark will now be
getting ERTMS across its national network for
just over €700 million. As such, the notion
that ERTMS would cost billions in the
Netherlands has been slated, all the more
because the networks in Denmark and the
Netherlands are not dissimilar. Cost expecta-
tions in the Netherlands were extremely high.
Thanks to Denmark, we now understand that
implementing ERTMS in our country would
be possible for less than a billion euros,
which is financially feasible and economically
viable.
And don’t forget to consider the consequences
for maintenance! The maintenance costs
associated with ERTMS are proportionately
far lower because only a fraction of the
current equipment is on or around the tracks.
ERTMS implementation renders many cost
consuming items like ES welding, massive
copper stocks and track coils redundant.
ERTMS will also alleviate existing problems
with train detection systems, falling leaves,
gritting and extreme temperatures leading
to signal failure. We can’t resolve these
problems at the moment, because train
detection forms an integral part of the ATB
train protection system. If you speed up and
introduce ERTMS, it would be no trouble at
all to replace train detection with a new
system – take axle counters for example –
and put all the misery behind you.”
The last counter argument: ERTMS would still
be insufficiently developed.
“Version 2.3.0D is sufficiently stable. It’s
installed along the Betuweroute and is actually
used across Europe. There aren’t any
problems related to stability. So that argument
can’t be used any more. There’s a new
Baseline 3.0 version in the pipeline, but it’s
compatible with its predecessor. Version 3.0
offers a few extra features such as level-
crossing control, but that doesn’t play such
a big role in the Netherlands. A number of
extra brake curves would still be possible and
a cold start would then be easier, but the
benefits would be so small that a number of
companies have said they will already be
focusing on version 2.3.0D.”
In 2012, the cabinet already expressed its
support in principle for the implementation
of ERTMS. This came in response to a
parliamentary rail survey exposing a blend of
rudderlessness and gridlock. The freshly
instated new cabinet pinned a definitive date
to it in November 2012: installation starts in
2016. According to the minister, the solution
must come from within the industry itself.
“Yes, isn’t that brilliant? My proposal?
What I’ve said before: choose a corridor, an
important stretch where the benefits would
best come into their right, and where you can
introduce high speeds and train frequencies
too. Deploy as much dedicated equipment as
possible and get going in this way. Then
make plans to achieve countrywide rollout.
What Denmark’s doing would also be an
option: splitting the rail network into two sets
of specifications.”
About Railways 16 I April 2013 3332 About Railways 16 I April 2013
You have always advocated a quick introduc-
tion of ERTMS. Does this deliver extra work
for you as a contractor?
“Maybe just for the installation, but not for
the rest. On the contrary. The bizarre thing
is that as a contractor we propagate the intro-
duction of ERTMS, while in time we’re actually
shooting ourselves in the foot. Once ERTMS
has been installed, our maintenance volume
will fall considerably. But, there’s no stopping
ERTMS; Europe sensibly reached a decision
to build a uniform system to accommodate
international train traffic. It is safer, shortens
train frequencies, facilitates higher speeds, can
more flexibly combine passenger and goods
traffic flows and it’s far cheaper to maintain.
And to reiterate, it’s stable. It cannot be
sufficiently stressed: ERTMS provides better
quality at a lower cost. So, let’s get going with
that as quickly as possible instead of continuing
to mess around with an obsolete, outdated
system. Strangely, it’s those who stand to profit
least – the maintenance contractors – who are
its biggest proponents: we have to renew it all.
Why? Because, we simply want to deliver a
good train product. A goal, I would say, that
everyone should gladly share. But, as is often
the case, rail is a very conservative world.”
Will the Netherlands have ERTMS by 2030?
He laughs loudly: “I should hope so! If you
decide now to introduce ERTMS, the
throughput time for the Netherlands as a
whole could easily amount to 10 or 15 years,
and that’s pushing it to keep up a healthy
pace. We’re set to start building in 2016, so
you can work it out. If things go well, 2030
should just be possible. But that we now
know for sure that it’s coming – and when –
is fantastic news!”
Beyond borders in three stepsStrukton Rail Equipment is gradually expanding into a single European organisation.
Jacob Zeeman: “We’re well on our way.”
Whether broader politics wants it or not, a
single, indivisible European market is
emerging – slowly but surely. Heavyweight
national companies that do not move with
the times will come off worst sooner or
later. As a matter of principle, Strukton
Rail chose for Europe in 1992, even as a
relatively small player back then.
One of the business units that put a face
to these intentions then and still does
today is Strukton Rail Equipment, which
operates Strukton’s large-scale, state-of-
the-art equipment. Five years ago, one
percent of the turnover of our equipment
was generated abroad. That figure is now
almost 60%. Jacob Zeeman, Director of
Strukton Rail Equipment: “If Strukton had
not taken this step towards inter-
nationalisation, we’d be closing the main
part of our shop now. It’s been a tough
process for our employees, but the rewards
are clear. Internationalisation is seen as an
exciting challenge by many of our people.”
We’ve reached the third step now, with our
field teams engaged on foreign projects
adopting more of an international character
too. This more or less completes the inter-
nationalisation of Strukton Rail Equipment.
Zeeman: “The more intensively our ballast
cleaner, renewal train and tamping machines
are in operation, the higher the yield.
The Dutch market is relatively small, espe-
cially since there’s less to do now and in the
near future. We had to look further afield to
guarantee continuity.”
Steps one and two are behind us. The big
machines involved in renewal projects are all
allowed in countries where Strukton Rail is
active: Sweden, Denmark, Germany, the
Netherlands and Belgium. According to
Zeeman, the last country in the list doesn’t
really count yet, “because Belgium
unfortunately does not see foreign renewal
machines as a real option yet, though the
door is left open a bit, also owing to efforts
made by our Belgian colleagues.”
“But, conversely,” he adds, “we hope to
benefit from the cooperation between
Eurailscout and SNCF. France is an attractive
country for rail companies, but still difficult
for them to get a foothold in.”
About Railways 16 I April 2013 3534 About Railways 16 I April 2013
During the second step, our European
production team focused on projects in
which High Output Equipment (HOE) could
perform optimally. In other words, high
levels of productivity within a short space
of time. And that’s been possible, but only
because Strukton Rail Equipment put feelers
out into the European market in time.
Zeeman: “In 2011, we had only a limited
number of HOE deployments. But we need
at least 100 for a satisfactory return on
investment. And that says it all.”
People and machines
Expectations are high within Strukton Rail
Equipment for a successful conclusion to
the third step – internationalisation of the
team involved within the scope of HOE
projects. Zeeman: “Buying the big machines
is the easy part. You just need a big
bag of money. And you can ship them
abroad, but still have a long way to go. It
all boils down to your employees and the
quality of their expertise. They make the
difference and they have to develop a feel
for the machines. This only happens if you
work with them a lot. And let’s not overlook
all the logistics involved. These projects are
complex and if you have a well-oiled team
with an established routine, you can act
decisively. You can’t just deploy anyone on
projects like these. More to the point, you
want your best people involved.”
By way of illustration, the renewal train
needs a team of twelve, the ballast cleaning
machines and material conveyors a team of
eight (depending on the amount of conveyors)
and the tamping machines require teams of
three or four. Then there’s the project
manager, supervisors, surveying technicians
and others. Zeeman: “You don’t get the
optimal effect if they’re only engaged once
a year to carry out such a complex project.
Where the supervisor may have only executed
one such project in any given year, we take
him on in the team where he is carrying out
mostly projects like this. Local supervisors
can therefore focus on other important parts
of the project. Ultimately, this will have a
favourable impact on quality, lowering failure
costs, reducing coordination hitches and there-
fore generating cost savings.”
But where’s the real need to implement
projects with a representative international
team? Surely, this only leads to confusion?
Zeeman’s not afraid of this in the least:
“They all speak ‘machine’. It’s a universal
language. And if required, the team mem-
bers get the opportunity to follow extra
training in English. No, the need arises from
being able to deploy the selfsame team in
multiple countries. Then it’s incredibly handy
if there’s always someone in the team who
speaks the local language. This simplifies
communication, also with Strukton Rail’s
local establishment. We want to be able to
take maximum advantage of the knowledge
available there, because each country, how-
ever European, does have its own technical
requirements and contracts. To this end, you
need to communicate in the local language,
even as a team.”
‘Best renewal project ever’
Last summer, it was the first time for Strukton
Rail Equipment to work with a multinational
team like this renewing an important stretch of
track in Sweden. Aside from a Swedish
contract manager and project manager, a
Dutch project manager was engaged on the
big machines with a German supervisor, while
a mix of staff from Sweden, Germany and the
Netherlands operated the machines. Zeeman:
“It went well. The customer said it was the
best renewal project ever. A genuine boost for
the entire team.”
Zeeman intends to push through further inter-
nationalisation with vigour. For example, part
of the German machine team with its
Bauleiters – generally brilliantly trained crafts-
men – will be added to the Dutch team.
He does not rule out that another team will
internationally specialise in points renewals.
“And we are making efforts to implement
standard working methods, aiming to make
unnecessary improvisation history”.
In summary, Zeeman concludes that taking
the initiative to change course five years ago
is developing in the right direction. A higher
utilisation rate, delivery of a better quality
product and fewer disruptions – and all this
at a lower cost. “Internationalisation has also
significantly strengthened ties between the
respective Strukton establishments. We are
now utilising our colleagues’ know-how and
knowledge far more, especially in Germany
and Sweden.”
Despite the positive developments, the market
has shown its dark side in recent years. The
biggest problem being overcapacity. Zeeman:
“Budgets are being slashed in many countries.
ProRail’s reserves are far smaller in 2013, so
that will be a difficult year in the Netherlands.
Germany also appears to be treading water for
the time being. I can only see lots of potential
for Sweden at the moment. This has all
brought loads of pressure to bear on prices.”
Jacob Zeeman has a clear vision of develop-
ments in the future. “The single European
market is evolving. It’s a good thing that within
Strukton Rail we’re growing towards becoming
a single European organisation. We’re well on
our way now.”
“Patience is very important”The horizons of Silvio Gehde, supervisor
Nobody has seen the horizon change quite
as dramatically as Silvio Gehde. Until the
age of 14, the 36-year-old Bauleiter was
still a citizen of East Germany. His line of
vision extended no further than the East
bloc – the world beyond appeared closed
off forever. The only foreign language he
spoke was Russian. Compulsory.
Nowadays, Gehde works throughout
Northwest Europe. And as a member
of the international team implementing
projects in a range of countries on
behalf of Strukton Rail Equipment using
high-output equipment, he’s following
supplementary classes in English.
He comments: “I think internationalisation
is enormously interesting on a personal and
professional level. It teaches you so much.”
Silvio was born and bred in Naumburg, in
the proximity of Leipzig. After secondary
school, he studied building engineering in
Erfurt. He did his traineeship at the depart-
ment of road and hydraulic engineering of
the former Reisse in Erfurt. The meeting
went so well for both parties that Silvio
was invited to stay and, even before he
qualified, he completed a project there.
“Actually,” he says, “I worked more than
I studied after my traineeship.”
Using the evenings, he still managed to
complete his studies within the allotted time-
frame. And, he’d moved from the department
of road and hydraulic engineering to the
rail-engineering department. He’s still with
the same department, as a Bauleiter – the
German word for site manager or supervisor.
Silvio: “In Germany, the contractor carries
final responsibility for a project’s
implementation. He prepares the project,
implements it and concludes it, also carrying
responsibility for its financial management.
An all-encompassing position, absolutely.”
His last project was the first one in which
Strukton Rail Equipment provided the blue-
print for the operational organisation of the
future. Three different nationalities were in
the team for the Swedish project, with Silvio
as captain of the big machines. Right up his
street, he says, “because I’m fascinated by
the big machines, and certainly in an
international perspective – I’m a willing
participant.” He learned a lot working in
Sweden. “The first thought you have to let
go of is ‘at home we do it differently.’ That
doesn’t work. Things are done differently in
every country. You must set aside enough
time to understand this, to be open to it.
Patience is very important then. And com-
munication. The need for communication is
far greater than usual.”
At the same time, he’s convinced that you
stand to learn a lot working in an international
context. “They do this better here and they
do that differently there. It’s a question of
picking out the best elements; learning
about the best practices as it were.”
Silvio Gehde is enthusiastic about the
internationalisation of Strukton. “More work,
new markets, and it makes you more
competitive. Your experiences abroad make
you stronger.” And his personal ambition
goes beyond reigning over the big machines.
Ultimately, Silvio Gehde hopes to carry final
responsibility for projects in their entirety.
Not that far-fetched for someone whose
horizons are always broadening.
About Railways 16 I April 2013 3938 About Railways 16 I April 2013
The faces had already been beaming with joy, long before the Hanze Line was actually handed
over. It had been a model project and one of considerable stature, too: design & construct,
multidisciplinary, integrated. And it had been executed in equally exemplary fashion: according
to schedule, within budget, in ample time and laid as sustainably as possible into the bargain.
“All the milestones were passed with flying colours,” Harold Verbruggen enthused. From start to
finish, he represented Strukton Rail as Operational Manager in HanzaRailTeam, the partnership
comprising Strukton Rail, VolkerRail, Arcadis and Alstom, which designed and built the new
railway line. In fact, even the customer saw the sunny side at quite an early stage of the
proceedings. ProRail’s Project Manager, Jaap Balkenende, blogged in March 2012 that
everything was going swimmingly. “Things are running so smoothly, in fact, that I was able to
take three months’ leave last summer to embark on a long-distance sailing trip.” And at the
time he wrote, there were still nine months to go before the official opening.
A new connection between the North and West of the Netherlands, unchallenged throughout
the nation, 50 km of dual track between Lelystad and Zwolle, featuring both the ATB and
ERTMS safety systems. The civil engineering part of the project commenced in 2006, and the
rail construction in 2010. And then, one day, the entire process was complete. On 30 June
2011, everything included in the drawings was in place: the railway bed, ballast, sleepers, rails,
points, portals, overhead power lines, substations, power, balises, cables and signals. Finished,
and everyone was satisfied.
What next? Well, that’s when the fun started: an apparently endless series of tests to establish
whether all of the systems were working properly, first independently, then jointly. These are
known as site integration tests, neatly numbered in packages from one to three. We’ll review
them one by one shortly. However, a problem had arisen that had to be resolved first.
The Hanze Line, the prologueThe Hanze Line was
commissioned in December
2012. The laying of this
connection between the
North and West of the
Netherlands had already
been completed 16 months
previously. What had been
going on in the meantime?
Testing, testing, testing and
the icing on the cake.
During the course of time, various parts of the
line had subsided. And while this was not
unexpected, the extent to which it occurred
certainly surprised some people; it had even
sunk up to eight centimetres on certain
stretches of peat bog. In fact, even the
stretches that had been excavated down to
the Pleistocene stratum still subsided by two
to three centimetres. Instructions were
therefore issued to tamp the entire route
once more. Strukton’s CSM tamping machine
effectively handled a total of some 230 km of
track again, layer upon layer, on a stretch of
dual track measuring 43 km. By the end of
December 2011, they had completed the job.
The initial tests
At the same time others were already
performing site integration test 1. Question:
do all the systems do what they are supposed
to on a stand-alone basis? Answer: yes, no
problem whatsoever, just a few minor adjust-
ments to be made. Conclusion according to
the protocol, September 2011: “Tested and
proven that the system and all subsystems
covered by the scope of the contract in
question operate properly and meet all the
requirements as stand-alone systems.”
Next stage: to connect the whole shebang to
the existing lines in the area of Amsterdam
and Zwolle and check whether the whipper-
snapper known as Hanze Line behaves as it
should, hand in hand with its more mature
companions. For instance, you need to know
that if someone at Rail Traffic Control in
Amsterdam throws a switch to move points,
then the appropriate set – say, in Lelystad –
is actually activated. Trains have to be able
to run along the line from A to B without
encountering any problems. The ERTMS
supplied by Alstom also needs to be fully
compatible with other contractors’ GSM-R
antennas. Eurailscout’s measurement trains
have to confirm that the overhead power lines
have been properly strung, while the track is
also suitably level after all the additional
tamping it has undergone. Brake tests.
Connecting the current to the overhead line,
and checking what happens if you simulate
a short circuit in a substation. How do the
switches respond in that case? Are they
tripped at the appropriate levels of under and
overvoltage? Yes, Harold Verbruggen
remembers well that there was one minor
point. “A switch had not been set quite
correctly.” And after six months’ work, site
integration test 2 was concluded on 31 March
2012, having proved that “the integrated
operation of the Hanze Line system and all
subsystems was suitable for all operational
scenarios, and had been issued a statement
by the certifying body, ISA-NOBO, devoid of
objections.” The next day, the line was
formally integrated in the national network:
the Hanze Line was now fully operational,
but had yet to be taken into service. From that
moment on, it would serve as a testing
ground for both the management authority
and carriers for several months to come.
Site integration test 3 was then to follow: the
opportunity to play with a life-sized train set,
the ultimate dream of every railway buff.
Passenger trains had now become a standard
feature of day-to-day operations. However,
this was all part of a calculated approach to
some spine-chilling scenarios. The simulation
of nightmarish scenes. Sending trains head-on
towards one another just to see if they would
stop in time, only in a virtual setup. Simulating
a complex disaster. Train spotter Stefan Verkerk
was an eye-witness, and reported on the
scenes he saw towards the end of April 2012
on the Internet:(1)
A major disaster
“Last Saturday, the Drontermeer Tunnel
served as the backdrop for a major disaster
exercise. All of the emergency services in the
safety regions were deployed: dozens of fire
engines, ambulances and police cars
proceeded to both ends of the tunnel to
participate in the largest emergency services
exercise to be held for several years. At seven
thirty-seven in the morning, the communi-
cations centre received the first simulated fire
alarm. At the scene, it transpired that one
passenger train had been derailed, a goods
train carrying hazardous goods had sprung a
leak and another passenger train was involved
in the incident. A total of over 200 emergency
services personnel, 40 vehicles and 100
‘victims’ took part in the exercise. The special
deployment medical assistance group and
ambulance teams from the safety regions were
deployed. The teams had also set up tents in
which to treat victims.”
There was, however, no emergency whatso-
ever, as the incident had been pure fiction,
February 2012: first ERTMS test runs with Strukton loc Danique
April 2012: disaster exercise at the Drontermeer tunnel
About Railways 16 I April 2013 4140 About Railways 16 I April 2013
designed to serve as a highly essential dress
rehearsal for the type of disaster one never
wants to experience. Agreeing on who organ-
ises and who assumes responsibility for what.
How to arrive at the scene as soon as possi-
ble, how to access a tightly secured structure,
which fire-fighting equipment is needed where
and when, how to respond on encountering
victims. Procedures and processes. All these
and more factors had to be taken into consid-
eration and incorporated in the umpteenth
scenario to be compiled. And then all that
remains to do is hope the emergency services
never encounter them again in practice.
Each consecutive step nevertheless brought
things closer to the mundane. ‘Look,’ train
spotters urged one another in the spring,
proudly showing the first pictures they had
taken of passenger trains running on the
Hanze Line. Trial runs. Later, during the sum-
mer months of 2012, things would really start
moving. ‘Running according to the timetable,’
departing from Zwolle and proceeding to
check whether the pen-pushers had correctly
calculated the arrival time in Kampen included
in the new timetable. Then pausing for three
minutes to allow dozens of invisible passen-
gers to embark, before departing once more;
back and forth, time and time again. Here’s
another: train departs from a station, encoun-
ters a hold-up and is allocated an alternative
route. Will it work? By the close of June 2012,
site integration test 3 had been completed and
so had the work of the contractors’ consortium,
although they did remain on stand by at this
stage, for the sake of security. The protocol
conclusion proved remarkably brief in relation
to the previous two: “Operational procedures
and processes completed.”
A kind of school trip
From that moment onwards, the consortium
had the chance to take a breather, enjoying
the opportunity to view matters from a con-
venient branch line. However, the big day was
steadily approaching. No bears in the middle
of the road? Contractors know all about bears
on the road; they never actually look like
bears, but are nevertheless instantly recog-
nisable. Harold Verbruggen didn’t spot any,
thankfully. And although there was one
unexpected change, even he wouldn’t have
the gall to call it a teddy bear. “The customer
tightened its requirements, deciding that
over 400 ERTMS transponders needed to
be moved after all, some of them as far as
several metres. Once these had been moved,
specially adapted software also had to be
installed and tested once again, which took
another week and a half. It was a major
amendment, but nothing to get really anxious
about.” It was simply additional work, nothing
to do with bears at all. And by September
2012, this work had also been completed.
In the meantime a proper party had been held
in June. It was actually more a compulsory
component of the test schedule, but of the
kind which only needs the slightest dab of
make-up to turn it into an exclusive school
trip. Because she finally made an appearance:
a genuine high-speed train. It had taken quite
some time to find a suitable one, fast enough
and equipped with ERTMS level 2. Requests
had been issued far and near, but there simply
wasn’t one available in the Netherlands.
Finally, however, late in the afternoon of
Monday, 4 June, the ICE 70152 bearing the
nameplate ‘Frankfurt am Main’ tiptoed onto
the Hanze Line in her stocking feet. A real
looker, slim and white, and about as rare in
this neck of the woods as a pink pelican on
the island of Texel. The train spotters went
ballistic. They knew that they would only have
three days to snap pictures of the ICE maiden,
preferably in sharp focus with an equally
sharp contrasting background, so that you
would hardly notice she was doing two ton at
the time. After all, the chances of them ever
spotting an ICE here again were pretty slim to
say the least. Just three days’ time for eight
trial runs therefore. Would the new safety
system allow this slick lady to get up to 200
kph without any hiccups? Would the lay of
the track allow her to hug it tightly at such
high speed?
A poignant moment
The real party highlight was that three select
parties of just a few dozen people in total
were given the opportunity to experience first
hand the thrill of speed, on three of the eight
runs. The VIPs went first, followed by the
press, while the third trip was set aside for
staff, the men and women who had actually
built the line. This certainly had something of
the atmosphere of a school trip. Everybody
was enthusiastic, cheerful and contented, and
they emerged from the train just as happy as
they’d boarded. Calling it a school trip is a bit
below the belt, however, in Harold Verbruggen’s
opinion. “It was a highly significant milestone,
particularly for those who were involved in the
project. We all did our utmost to ensure that it
would prove successful. And if you are then
among the lucky few who are the first to do
200 on the stretch of line… well, it was a
poignant moment.”
The success story just seemed to go on and
on. ICE emerged from the Drontermeer
Tunnel, bound for Kampen. You could feel her
accelerate, but had little inkling of just how
fast you were going. She was as smooth as a
baby’s bottom, gliding like a snooker ball
across a match play cloth. You only realised
how fast she was actually travelling on look-
ing out of the window and noticing that she
easily outstripped the cars on the motorway
in the distance. What a terribly comfortable
means of transport this was. The Hanze Line
had passed with flying colours, flying even
more proudly than they had all those months
ago. ERTMS in perfect working order. The lay
of the track was validated. A top speed of
203 km per hour had been clocked. On the
radio,(2) ProRail’s Project Manager, Wim
Bakker, strung together one heartfelt superla-
tive after the other: excellent, wonderful, fan-
tastic, thrilling, and sensational. So smooth
and comfortable that you hardly notice the
speed. “The icing on the cake.”
During the intervening months, it was the turn
of the carriers. Back and forth, just playacting,
but learning at the same time. Clocking up
the hours, familiarising themselves.
This phase is known as ‘preparation for
commissioning’. And although no final date
had been set to commission the line, they
would actually be ready to do so as soon as
hundreds of train drivers were available to
run a service according to the formal timetable:
two intercities and two sprinters an hour.
And they were certainly prepared ahead of 6
December, as this was the day on which Her
Majesty, Queen Beatrix officially opened the
Hanze Line.
Nothing was allowed to queer the pitch.
ProRail and NS, railway manager and opera-
tor, always back in the row when it comes to
compliments, wanted to enjoy this moment of
carefree pride and joy. And they could. Her
Majesty brought her smile and pressed a red
button. The queen and dignitaries stopped at
all stations. Children read poems – train
rhymed with gain and sustain. Even the
weather, mostly the potential enemy, was
generous. The royal train passed through a
landscape that was powdered with fine snow
along the line. This time, snow was not a
byword for delay but for fairy tale. It could not
have been better, this one Thursday morning
in December.
(1) www.hanzelijn-hattem.nl, 24 April 2012
(2) BNR news radio, 7 June 2012
June 2012: test run with ICE 70152 ‘Frankfurt am Main’
About Railways 16 I April 2013 4342 About Railways 16 I April 2013
Strukton Rail bv
Westkanaaldijk 2, 3542 DA Utrecht, The Netherlands
telephone +31 (0)30 240 72 00
e-mail: [email protected]
internet: www.struktonrail.nl
Strukton Rail nv
Burg. Maenhautstraat 64, 9820 Merelbeke, Belgium
telephone +32 (0)9 210 79 10
Strukton Rail AB
Uddvägen 7, 131 34 Nacka, Sweden
telephone +46 (0)10 480 50 00
internet: www.strukton.se
Strukton Rail GmbH & Co KG
Forstfeldstrasse 5, 34123 Kassel, Germany
telephone +49 (0)561 57047-0
internet: www.struktonrail.de
Construzioni Linee Ferroviarie s.p.a. (Clf)
Via della Cooperazione 34, 40129 Bologna, Italy
telephone +39 051 32 34 24
internet: www.clfspa.com
Eurailscout Inspection & Analysis bv
Berkenweg 11, 3818 LA Amersfoort, The Netherlands
telephone +31 (0)33 469 70 00
Torellstrasse 1, 10243 Berlin, Germany
telephone +49 (0)30 293 808-50
internet: www.eurailscout.com
For further addresses and contact details please refer to Strukton Rail’s
website: www.struktonrail.com
Strukton Rail develops, builds, renews
and maintains rail and electric systems.
The organisation designs, builds and
installs custom-made technologies, which
have proven to contribute to the safety,
reliability and sustainability of railways,
rolling stock and electro-technical
infrastructures.
All efforts are aimed at making railway
transport more attractive and competitive.
Strukton Rail provides systematic
online insight into the status of system
components, both for management
organisations and for its own operational
disciplines. The principle is that up-to-
date knowledge enables preventive
action. The point is to keep one step
ahead of breakdowns to maximise rail
system availability.
Strukton Rail supplies all relevant
professional disciplines and is involved
in all stages of projects. Technical
specialists work permanently on
improving and refining inspection
systems, monitoring systems, data
capturing, maintenance concepts and
asset management.
The company has long-term operations
in Sweden, Denmark, Germany, the
Netherlands, Belgium, France and Italy
and works on projects and products far
beyond Europe. Its main assets are its
more than 3,000 employees and its
modern, full-service equipment.
Strukton Rail has been writing history
for over 90 years. The organisation is
part of Strukton Groep.
Gert Jansen (p. 28)
KieF photography (p. 22, 23)
Jeroen de Lange (p. 4)
Carry van der Maas (p. 6, 8, 30, 32, 36)
Foto Eppo Notenboom (p. 23)
Ryno Quantz (cover, p. 18)
Elisabeth Sinclair (p. 27)
Skeyes/Seaway Heavy Lifting (p. 23)
Aat Stout (p. 36)
Ronald Tilleman (p. 10)
Peter Thornvik (p. 14)
Martin Uitvlugt (p. 12)
Stefan Verkerk (p. 38, 39, 40)
Paul Vreuls (p. 35)
LAYOUT/POSTPRODUCTION
More than Live, Rotterdam
PRINTING
Quadraat, Oud-Beijerland
CONTRIBUTORS
Niklas Andersson, Bas Beltman (Eurailscout), Johnny Berg, Dominique Bex,
Victoria Björklund, Rudi Broekhuis, Caterina Cristallo (Clf), Jens Otto Daugaard,
Joost Delwel, Jo Derie, Ronny Fredriksson, Silvio Gehde, Paul de Haas, Géraud
Lausseur (Clf), Björn Löfgren, Jan van Losser, Bart Meeus, Jochen Meister,
Fredrik Nilsson, Bart van Odijk, Jan Oosterlaak, Björn Österberg, Rudy Oude
Vrielink (A1 Electronics), Karin Persson, Mats Persson (OV Skäne), Rob Redeker,
Tim Redelijkheid, Peter de Reu, Robert Röder, Elisabeth Sinclair
(Norrbotniabanegruppen), Tom de Strooper, Harold Verbruggen, Karel Vroom,
Roel Westenberg, Ed Wigman, Aad van der Zouwen (Eurailscout)
COLOPHON
About Railways is a Strukton Rail publication
which appears once a year
CONCEPT/EDITOR
Martin Uitvlugt, The Hague
PRODUCTION/COORDINATION
Irene van Dam-Aaldijk
PRODUCTION NORDIC
Lisa Hellkvist
EDITORIAL CONSULTANTS
Aike Schoots, Jacob Zeeman,
Diederik Schonebaum
EDITORIAL CONTRIBUTORS
Clf, Bologna (p. 9)
Cerca Media, Hölö (p. 18, 24)
Gunilla Schönning, Stockholm (p. 19, 26)
Paul Vreuls, Amsterdam (p. 33, 36)
TRANSLATIONS
Accuwrite English Language Services,
Kevin N. Martley, Middelie
PHOTOGRAPHY
Stig Almqvist (p. 21)
Cerca Media (p. 25, 33)
Clf (p. 9)
Melker Dahlstrand (p. 19, 20)
Taco Hoitsma (p. 16)