177
Summer Internship Program (SIP) Project Report On Financial Statement Analysis & Procurement Management At National Thermal Power Corporation By: Abhinay Seth Apeejay Institute of Technology School of Management Page 1

Abhinay Project Report

Embed Size (px)

Citation preview

Page 1: Abhinay Project Report

Summer Internship Program(SIP)

Project Report

On

Financial Statement Analysis&

Procurement ManagementAt

National Thermal Power Corporation

By:Abhinay Seth

Project Report

On Financial statement analysis

&

Apeejay Institute of Technology School of Management Page 1

Page 2: Abhinay Project Report

Procurement ManagementAt

National Thermal Power Corporation

A report submitted in partial fulfillment of the requirement of

PGDM program ofApeejay Institute Of Technology

Prepared under the Guidance of

FACULTY GUIDE: Prof. Amar k.Saxena

(Finance Faculty)

COMPANY GUIDE: Dinesh Bahuguna

(DGM Finance)

By:Abhinay Seth

TABLE OF CONTENTS

S r . N o . C O N T E N T P A G E N O .

1 A B S T R A C T 1

Apeejay Institute of Technology School of Management Page 2

Page 3: Abhinay Project Report

2 I N T R O D U C T I O N 3

3 S C E N A R I O O F P O W E R S E C T O R 5

4 B A C K G R O U N D O F N T P C 8

5 P R O C U R E M E N T M A N A G E M E N T 2 0

6 G E N E R A L C L A U S E S 4 2

7 I L L U S T R A T I N G O N T E N D E R I N G6 6

8 F I N A N C I A L S T A T E M E N T A N A L Y S I S

8 4

9 F I N A N C I A L P O S I T I O N 1 1 2

1 0 S W O T A N A L Y S I S 1 1 4

1 1 C O N C L U S I O N 1 1 7

1 2 R E C O M M E N D A T I O N 1 1 9

1 3 R E F E R E N C E 1 2 1

Abstract

The report entitled “Financial Statement Analysis & Procurement Management at

National Thermal Power Corporation” is about the purchase practices followed at

NTPC for every equipment and financial statement analysis will provide the

knowledge about current financial status of the company and its comparison with

Apeejay Institute of Technology School of Management Page 3

Page 4: Abhinay Project Report

the other player in the same sector will enable to know which one is performing

better. Procurement management activities are followed during all procurement

by NTPC.

Procurement Management at NTPC starts with Indenting by the department that

requires the material and goes to the cost department and finance department for

required approval. In between various activities like Liquidated Damages

calculation, Spare Parts procurement terms, Guarantee in Liability Defect period

etc are undertaken. Once all the terms and conditions are formulated and

approved, the tender document preparation starts. The tender documents are

issued to the prospective bidder for a cost that starts from Rs 200 to Rs 3000.

The content of the tender document is prepared in such a manner that the

prospective bidder comes to know about all the important details about the

contract. The issuance of tender document is followed by the receipt of Bids from

various vendors in the specified format. Once all the bids are received, they are

opened in presence of some nominated officials from Finance, Contracts and

Materials department. The representatives from the bidders may also be present.

Then a comparative statement of the quoted bids is prepared and the contract is

awarded to the lowest quoting bidder.

During the document preparation phase, payments terms are also decided and

documented in the General Condition of Contract, which is issued to the bidder

with the tender documents. Apart from payments, there are various other issues

like Arbitration, which are dealt in the tender documents. Liquidated Damages is

one of the very important clauses. Liquidated damage is a payment to be made

by the contractor in case he fails to complete the project in the stipulated time. In

case of equipment, it is related to the performance of the equipment. The

purchase is followed by the evaluation, which is done for two things, the vendor’s

performance and the purchase performance. The Vendor evaluation comes in

handy for placing future orders where as the Purchase Performance evaluation

provides detailed insight into the procedures being followed to procure the

required material.

Financial statement analysis is yet another one of the important part of the

project where in various crucial ratios which help to analyze the financial position

of the company are being calculated which provide inside into the growth

Apeejay Institute of Technology School of Management Page 4

Page 5: Abhinay Project Report

prospects of the company. The tool used for financial statement analysis is Ratio

Analysis and cash flow analysis. Ratio Analysis is the process of determining and

presenting the relationship of items or group of items in the financial statement. It

has emerged as a principle technique for the analysis of the financial statements

of the companies.

These ratios are being calculated with the help of the 2 most important financial

statements of the company i.e. profit and loss account and balance sheet. These

are important not only for the working of the company but they are even

important for the outsiders of the company like creditors, investors etc. and

further its comparison with other power sector players Reliance Energy and Tata

power will help to analyze the better position of the company in comparison to

others or in case of any loop holes the company can perform better in future.

Cash flow analysis is statement which shows the cash requirement of the

company or the way through which company can meet its day to day obligations.

It is one of the most important components as it shows day to day requirement of

the company.

The project also includes over all study of the power sector which will help in

knowing the company in much better sense and its position in power sector.

Introduction

The electricity services in India were generally provided by the State Electricity

Boards, as it was believed that being under the control of the State governments,

they could protect the consumer interests against exploitation. Over a period of

time, it however, came to be realized that because of their monolithic nature, the

Apeejay Institute of Technology School of Management Page 5

Page 6: Abhinay Project Report

State Electricity Boards suffered from operational inefficiencies on account of

which they had incurred heavy losses. The services rendered by them were also

of poor quality. These factors forced the governments to think in terms of

commercialization of the services so that the additional investments necessary

for infrastructure development become available through private sector

involvement and the services rendered become globally competitive.

Central Government issued a policy resolution dated 22-10-1991 on

private sector participation in power sector. It was followed by necessary

changes in the legal framework. Despite the policy of liberalization, the entry of

new players continued to be regulated by the government who remained the final

arbiter in all matters, including tariff fixation. It became necessary, therefore, to

provide a level playing field to new players and to provide for competition. It was

decided to encourage private sector participation in the generation, transmission

and distribution since future expansion could not be achieved through public

resources alone. Thus, the phenomenon of private sector involvement in power

sector is a relatively modern reaction to the revealed concerns and issues

associated with complete reliance on the public sector provision of infrastructure.

It should also be decided to set up independent Central and State Regulatory

Commissions.

Promotion of competition, efficiency and economy in electricity industry can be

conveniently achieved through the process of competitive bidding. The Central

Government issued detailed guidelines for competitive bidding of power projects

in January 1995 whereby the competitive procurement of power sector projects

was made mandatory. These guidelines laid emphasis on project identification,

justification and development before taking up competitive bidding.

National Thermal Power Corporation one of the major players of the power

sector and it has shown consistent results year after year NTPC has set new

benchmarks for the power industry both in the area of power plant construction

and operations. It is providing power at the cheapest average tariff in the country.

With its experience and expertise in the power sector, NTPC is extending

consultancy services to various organizations in the power business.

Apeejay Institute of Technology School of Management Page 6

Page 7: Abhinay Project Report

It follows all the bidding procedures as are being stated by the power ministry

and other authorities. Procurement Management is one of the major departments

at NTPC as for every purchase at the NTPC proper procurement management

procedures are being followed which help to analyze the working and even

results in efficient working of the process. Through this working the bidder who

quotes the best is being awarded with the work n through these working only

companies is efficiently able to cut down at its cost.

Financial statement analysis one the other hand helps to analyze the financial

position of the company. They act as the lens of the company’s performance

over the years.

Analysis of financial statements is the systematic numerical calculation of the

relationship between one fact with the other to measure the profitability,

operational efficiency and the growth potentials of the business. It includes three

major steps they are as follow:

(1) Selection of the information which is relevant to the decision under

consideration.

(2) Classification or grouping of the information in such a way that significant

relationship is established.

(3) Interpretation and drawing of inferences and conclusions by studying

these relationships.

Financial analysis can be used as the preliminary screening tool in selection of

stock in secondary market .It can be used as a forecasting tool of future financial

condition and results. It may be used as a process of evaluation and diagnosis of

managerial, operating, or other problem areas.

Apeejay Institute of Technology School of Management Page 7

Page 8: Abhinay Project Report

National Thermal Power Corporation

&

Scenario of Power Sector in India

Growth of Indian power sector

Power development is the key to the economic development. The power Sector

has been receiving adequate priority ever since the process of planned

development began in 1950. The Power Sector has been getting 18-20% of the

total Public Sector outlay in initial plan periods. Remarkable growth and progress

have led to extensive use of electricity in all the sectors of economy in the

Apeejay Institute of Technology School of Management Page 8

Page 9: Abhinay Project Report

successive five years plans. Over the years (since 1950) the installed capacity of

Power Plants (Utilities) has increased to 89090 MW (31.3.98) from meagre 1713

MW in 1950, registering a 52d fold increase in 48 years. Similarly, the electricity

generation increased from about 5.1 billion units to 420 Billion units – 82 fold

increase. The per capita consumption of electricity in the country also increased

from 15 kWh in 1950 to about 338 kWh in 1997-98, which is about 23 times. In

the field of Rural Electrification and pump set energisation, country has made a

tremendous progress. About 85% of the villages have been electrified except far-

flung areas in North Eastern states, where it is difficult to extend the grid supply.

Structure of power supply industry

In December 1950 about 63% of the installed capacity in the Utilities was in the

private sector and about 37% was in the public sector. The Industrial Policy

Resolution of 1956 envisaged the generation, transmission and distribution of

power almost exclusively in the public sector. As a result of this Resolution and

facilitated by the Electricity (Supply) Act, 1948, the electricity industry developed

rapidly in the State Sector.

The Electricity Laws (Amendment) Act, 1998 passed with a view to make

transmission as a separate activity for inviting greater participation in investment

from public and private sectors. The participation by private sector in the area of

transmission is proposed to be limited to construction and maintenance of

transmission lines for operation under the supervision and control of Central

Transmission Utility (CTU)/State Transmission Utility (STU). On selection of the

private company, the CTU/STU would recommend to the CERC/SERC for issue

of transmission licence to the private company.

Current problem of power sector

The most important cause of the problems being faced in the power sector is the

irrational and unremunerative tariff structure. Although the tariff is fixed and

realized by SEBs, the State Governments have constantly interfered in tariff

setting without subsidizing SEBs for the losses arising out of State Governments

desire to provide power at concessional rates to certain sectors, especially

Apeejay Institute of Technology School of Management Page 9

Page 10: Abhinay Project Report

agriculture. Power Supply to agriculture and domestic consumers is heavily

subsidized. Only a part of this subsidy is recovered by SEBs through cross

subsidization of tariff from commercial and industrial consumers. The SEBs, in

the process, have been incurring heavy losses. If the SEBs were to continue to

operate on the same lines, their internal resources generation during the next ten

years will be negative, being of the order of Rs.(-) 77,000 crore. This raises

serious doubts about the ability of the States to contribute their share to capacity

addition during the Ninth Plan and thereafter. This highlights the importance of

initiating power sector reforms at the earliest and the need for tariff

rationalization.

Power supply position at the beginning of 9th plan

The total installed capacity at the beginning of 9th Plan i.e. 1.4.97 was 85,795

MW comprising 21,658 MW Hydro, 61,012 MW Thermal including gas and

diesel, 2,225 MW Nuclear and 900 MW Wind based power plants.

The actual power supply position at the beginning of the 9th Plan indicates peak

shortage of 11,477 MW (18%) and energy shortage of 47,590 MU (11.5%) on All

India basis. To meet the growing demand and shortages encountered, sufficient

capacity would need to be added in subsequent plan periods.

Ninth plan capacity addition programme

The Working Group on Power, constituted by Planning Commission, in its report

of December 1996 had formulated, a need based capacity addition programme

of 57,735 MW for the Ninth Plan which would by and large meet the power

requirements projected in 15th Electric Power Survey Report. However, it was

felt that this capacity addition of 57,735 MW is not feasible and a target for

capacity addition of 40245 MW was fixed for Ninth Five-year plan. The above

target was finalised after considering the status of Sanctioned/ongoing schemes,

new projects in pipeline, likely gestation period for completion of the projects and

likely availability of funds. The Sector-wise/type-wise details are given below:

Sector-wise / type-wise capacity addition programme during ninth plan (Figures

in MW)

Apeejay Institute of Technology School of Management Page 10

Page 11: Abhinay Project Report

Background of National Thermal Power Corporation

Apeejay Institute of Technology School of Management Page 11

Page 12: Abhinay Project Report

NTPC Limited is the largest thermal power generating company of India. A public

sector company, it was incorporated in the year 1975 to accelerate power

development in the country as a wholly owned company of the Government of

India. At present, Government of India holds 89.5% of the total equity shares of

the company and the balance 10.5% is held by FIIs, Domestic Banks, Public and

others.

Within a span of 31 years, NTPC has emerged as a truly national power

company, with power generating facilities in all the major regions of the country.

Based on 1998 data, carried out by Data monitor UK, NTPC is the 6th largest in

terms of thermal power generation and the second most efficient in terms of

capacity utilization amongst the thermal utilities in the world.

NTPC’s core business is engineering, construction and operation of power

generating plants. It also provides consultancy in the area of power plant

constructions and power generation to companies in India and abroad.

Apeejay Institute of Technology School of Management Page 12

Page 13: Abhinay Project Report

As on date the installed capacity of NTPC is 26,404 MW through its 14 coal

based (21,395 MW), 7 gas based (3,955 MW) and 4 Joint Venture Projects

(1,054 MW).

NTPC acquired 50% equity of the SAIL Power Supply Corporation Ltd. (SPSCL).

This JV company operates the captive power plants of Durgapur (120 MW),

Rourkela (120 MW) and Bhilai (74 MW). NTPC also has 28.33% stake in

Ratnagiri Gas & Power Private Limited (RGPPL) a joint venture company

between NTPC, GAIL, Indian Financial Institutions and Maharashtra SEB

Holding Co. Ltd. The present capacity of RGPPL is 740 MW.

NTPC’s share on 31 Mar 2006 in the total installed capacity of the country was

19.51% and it contributed 27.68% of the total power generation of the country

during 2005-06.

NTPC has set new benchmarks for the power industry both in the area of power

plant construction and operations. It is providing power at the cheapest average

tariff in the country. With its experience and expertise in the power sector, NTPC

is extending consultancy services to various organizations in the power business.

NTPC is committed to the environment, generating power at minimal

environmental cost and preserving the ecology in the vicinity of the plants.

Apeejay Institute of Technology School of Management Page 13

Page 14: Abhinay Project Report

NTPC has undertaken massive afforestation in the vicinity of its plants.

Plantations have increased forest area and reduced barren land. The massive

afforestation by NTPC in and around its Ramagundam Power station (2600 MW)

have contributed reducing the temperature in the areas by about 3°c. NTPC has

also taken proactive steps for ash utilization. In 1991, it set up Ash Utilization

Division to manage efficient use of the ash produced at its coal stations.

This quality of ash produced is ideal for use in cement, concrete, cellular

concrete, building material.

A "Centre for Power Efficiency and Environment Protection (CENPEEP)" has

been established in NTPC with the assistance of United States Agency for

International Development. (USAID). Cenpeep is an efficiency oriented, eco-

friendly and eco-nurturing initiative - a symbol of NTPC's concern towards

environmental protection and continued commitment to sustainable power

development in India.

As a responsible corporate citizen, NTPC is making constant efforts to improve

the socio-economic status of the people affected by the its projects. Through it's

Rehabilitation and Resettlement programmes, the company endeavors to

improve the overall socio-economic status of Project Affected Persons.

NTPC was among the first Public Sector Enterprises to enter into a

Memorandum of Understanding (MOU) with the Government in 1987-88. NTPC

has been Placed under the 'Excellent category' (the best category) every year

since the MOU system became operative.

Recognizing its excellent performance and vast potential, Government of the

India has identified NTPC as one of the jewels of Public Sector ‘Navratnas’- a

potential global giant. Inspired by its glorious past and vibrant present, NTPC is

well on its way to realize its vision of being “A world class integrated power

major, powering India’s growth, with increasing global presence”.

Apeejay Institute of Technology School of Management Page 14

Page 15: Abhinay Project Report

Installed capacity of NTPC

AN OVERVIEW Projects No. of Projects Commissioned Capacity

(MW)

NTPC OWNED

COAL 14 21,395

GAS/LIQ. FUEL 07 3,955

TOTAL 21 25,350

OWNED BY JVCs

Coal 3 314*

Gas/LIQ. FUEL 1 740**

GRAND TOTAL 25 26, 404

* Captive Power Plant under JVs with SAIL

** Power Plant under JV with GAIL, FIs & MSEB

PROJECT PROFILE

Coal Based Power Stations Coal based State Commissioned

Capacity

(MW)

1. Singrauli Uttar Pradesh 2,000

2. Korba Chattisgarh 2,100@

3. Ramagundam Andhra Pradesh 2,600

4. Farakka West Bengal 1,600@

5. Vindhyachal Madhya Pradesh 2,760@

6. Rihand Uttar Pradesh 2,000

7. Kahalgaon Bihar 840@

8. NTCPP Uttar Pradesh 840@

9. Talcher Kaniha Orissa 3,000

10. Unchahar Uttar Pradesh 1,050

11. Talcher Thermal Orissa 460

12. Simhadri Andhra Pradesh 1,000

13. Tanda Uttar Pradesh 440

Apeejay Institute of Technology School of Management Page 15

Page 16: Abhinay Project Report

14. Badarpur Delhi 705

Total (Coal) 21, 395

Gas/Liq. Fuel Based Power Stations Gas based State Commissioned

Capacity

(MW)

15. Anta Rajasthan 413

16. Auraiya Uttar Pradesh 652

17. Kawas Gujarat 645

18. Dadri Uttar Pradesh 817

19. Jhanor-Gandhar Gujarat 648

20. Rajiv Gandhi at Kayamkulam Kerala 350

21. Faridabad Haryana 430

Total (Gas) 3,955

Power Plants with Joint Ventures

Coal Based State Fuel Commissioned Capacity

(MW)

22. Durgapur West Bengal Coal 120

23. Rourkela Orissa Coal 120

24. Bhilai Chhattisgarh Coal 74@

25. RGPPL Maharastra Naptha/LNG 740

Total(JV) 1054 Grand Total (Coal + Gas + JV) 26,404

@ Additional capacity under implementation • Bhilai 500 MW (2 x 250 MW)

Apeejay Institute of Technology School of Management Page 16

Page 17: Abhinay Project Report

Power plant operations

The operating performance of NTPC has been considerably above the national

average. The availability factor for coal stations has increased from 85.03 % in

1997-98 to 89.91 % in 2004-05, which compares favorably with international

standards. The PLF has increased from 75.2% in 1997-98 to 87.54% during the

year 2005-06 which is the highest since the inception of NTPC.

It may be seen from the table below that while the installed capacity has

increased by 43.93% in the last eight years, the employee strength went up by

only 1.95

Description Unit 1997-98 2005-06 % of increase

Apeejay Institute of Technology School of Management Page 17

Page 18: Abhinay Project Report

Installed Capacity MW 16,847 24,249 43.93

Generation MUs 97,609 1,70,880 75.07

No. of employees No. 23,585 24,044 1.95

Generation/employee MUs 4.14 7.81 88.65

The energy conservation parameters like specific oil consumption and auxiliary

power consumption have also shown considerable improvement over the years.

Turnaround capability

NTPC has also demonstrated its ability in turning around sub-optimally

performing stations. The phenomenal improvement in the performance of

Badarpur, Unchahar and Talcher by NTPC stand testimony to this.

Badarpur (705 MW)

The expertise in R&M and performance turnaround was developed and built up

by NTPC with the operational turnaround of Badarpur TPS through scientifically

engineered R&M initiatives.

Unchahar (420 MW)

The Feroze Gandhi Unchahar Power Station was taken over by NTPC as part of

a win-win deal with the Uttar Pradesh Government whereby the dues of UPSEB

were adjusted was used to and the expertise of NTPC turnaround the

languishing station.

Talcher (460 MW)

An even more challenging turnaround story was being scripted at the OSEB's old

power plant at Talcher, taken over in June 1995. The table indicates the dramatic

gains in the performance of the power plant after take over.

While NTPC bettered the PPA commitments, from the viewpoint of capital

requirements, turning around such old units is a low cost, high and quick return

Apeejay Institute of Technology School of Management Page 18

Page 19: Abhinay Project Report

option. These successes helped NTPC, the concerned SEBs and the entire

nation in terms of economy and power availability.

Tanda

Tanda Thermal Power station was taken over by NTPC on the 15 Jan 2000.The

PLF of the power station improved from 14.9% at the time of the takeover to

86.39% for the year 2005-06.

Growth plans

Over the last three decades, NTPC has spearheaded development of thermal

power generation in the Indian power sector. In this process, it has built a strong

portfolio of coal and gas/liquid fuel based generation capacities. The company

has made initial forays in the area of hydropower development and plans to have

a significant share of hydro power in its future generation portfolio. Although

NTPC is also offering technical services, both in domestic and international

markets, through its Consultancy Wing, the generation business would continue

to be the single largest revenue generator for NTPC.

The Indian power sector is witnessing several changes in the business and

regulatory environment. The legal and policy framework has changed

substantially with the enactment of the Electricity Act 2003. In the foreseeable

future, India faces formidable challenges in meeting its energy needs. Recently,

a draft integrated energy policy has been issued, which addresses all aspects

including energy security, access, availability, affordability, pricing, efficiency and

environment. To meet the twin objectives of ensuring availability of electricity to

consumers at competitive rates, as well as attract large private investments in the

sector, a new Tariff policy has also been issued. The power sector thus offers a

mixed bag of challenges and opportunities to players and NTPC would continue

to review its business strategy and portfolio in light of these changes.

Growth of the Generation Business

Apeejay Institute of Technology School of Management Page 19

Page 20: Abhinay Project Report

Developing and operating world-class power stations is NTPC’s core

competence. Its scale of operation, financial strength and large experience serve

to provide an advantage over competitors. To meet the objective of making

available reliable and quality power at competitive prices, NTPC would continue

to speedily implement projects and introduce state-of-art technologies.

Total capacity portfolio

India’s generation capacity can be expected to grow from the current levels of

about 120 GW to about 225-250 GW by 2017. NTPC currently accounts for

about 20% of the country’s installed capacity and almost 60% of the total

installed capacity in the Central sector in the country. Going forward, in its target

to remain the largest generating utility of India, NTPC would endeavour to

maintain or improve its share of India’s generating capacity. Towards this end,

NTPC would target to build an overall capacity portfolio of over 66,000 MW by

2017.

Fuel / Energy mix for capacity addition

Currently, coal has a dominant share in the power generation capacities in India.

This is also reflected in the high share of coal-based capacities in NTPC’s current

portfolio. With high uncertainties involved in Domestic gas/ LNG, both in terms of

availability and prices, NTPC would continue to set up large pit-head coal based

projects, including few integrated coal cum power projects. To reduce the

dependence on fossil fuels, there is a need to push for renewable sources of

power in the sector. NTPC would avail of opportunities to add hydropower to its

portfolio subject to competitive tariffs. A first step in this direction has already

been taken with the investment in Koldam Hydro Power Project. NTPC would

continue to closely monitor developments on nuclear front also and be open to

setting up around 2000 MW of Nuclear power generation capacity, possibly

through a Joint Venture. As a leader in power generation, NTPC would also

consider other energy sources such as biomass, cogeneration, fuel cells, etc for

future development thereby reducing the dependence on thermal fuels.

While a decision on the fuel/energy mix for NTPC in the future would be largely

governed by their relative tariff-competitiveness, the fuel mix in 2017 may be

different from the existing portfolio, though not very significantly.

Apeejay Institute of Technology School of Management Page 20

Page 21: Abhinay Project Report

Diversification along the Value Chain

NTPC has achieved the distinction of being the largest thermal generating

company in India. In the past, this focus was adequate as the industry was highly

regulated with limited diversification opportunities. Over last few years, the

country has been facing acute shortages, both in coal and gas, severely affecting

optimum utilisation of its power stations and these shortages are likely to

continue in future as well. This is in spite of the fact that India is one of the largest

producers of coal in the World. To safeguard its competitive advantage in power

generation business, NTPC has moved ahead in diversifying its portfolio to

emerge as an integrated power major, with presence across entire energy value

chain. In fact, to symbolise this change, NTPC has taken on a new identity and a

new name “NTPC Limited”. NTPC has recently diversified into coal mining

business primarily to secure its fuel requirements and support its aggressive

capacity addition program. In addition, NTPC is also giving thrust on

diversification in the areas of power trading and distribution. Diversification would

also allow NTPC to offer new growth opportunities to its employees while

leveraging their skills to capitalise on new opportunities in the sector.

Establishing a Global Presence

To become a truly global company serving global markets, it is essential for

NTPC to establish its brand equity in overseas markets. NTPC would continue to

focus on offering Engineering & Project Management Services, Operations &

Maintenance services, and Renovation & Modernization services in the

international market.

Establishing a successful services brand would be a precursor to taking higher

investment decisions in different markets. Going forward, NTPC would continue

to evaluate various options for strengthening its presence in global markets

including setting up power generation capacity, acquisition of gas blocks etc.

Circa 2017: NTPC’s corporate profile

By the year 2017, NTPC would have successfully diversified its generation mix,

diversified across the power value chain and entered overseas markets. As a

Apeejay Institute of Technology School of Management Page 21

Page 22: Abhinay Project Report

result NTPC would have altered its profile significantly. Elements of the revised

profile that NTPC would seek to achieve are:

Apeejay Institute of Technology School of Management Page 22

Page 23: Abhinay Project Report

Apeejay Institute of Technology School of Management Page 23

Page 24: Abhinay Project Report

Procurement Management

At

National Thermal Power Corporation

Procurement Management at NTPC

Apeejay Institute of Technology School of Management Page 24

Page 25: Abhinay Project Report

Procurement is the acquisition of goods and services at the best possible total

cost of ownership, in the right quantity and quality, at the right time, in the right

place for the direct benefit or use of the governments, corporations or individuals

generally via but not limited to the contract.

Simple procurement may involve nothing more than repeat purchasing.

Complex procurement could involve finding long term partners or even co-destiny

suppliers that might fundamentally commit one organization to another.

A key question in procurement is what to buy, given a limited budget. If good

data is available it is good practice to make use of economic analysis methods

such as cost benefit analysis or cost utility analysis.

Procurement Process in General:

Procurement may also involve a bidding process. A company may want to

purchase a given product or service. It may call cost rates from various suppliers

and accept the one which cost it lowest.

Procurement steps:

Procurement life cycle in modern business usually consists of seven steps. They

are as follow:

1. Information gathering: if the potential customer does not already have

an established relationship with sales/marketing functions of the suppliers

of needed products and services then it is necessary for him to search for

the suppliers who can satisfy the requirement

2. Supplier contact: when one or more suitable suppliers have been

identified. Requests for the quotes, request for proposal, request for

information or requests for bids may be advertised or direct contact may

be established with suppliers for acquiring the required things.

3. Background Review: References for product or services quality are

consulted and any requirements for follow up services including

Apeejay Institute of Technology School of Management Page 25

Page 26: Abhinay Project Report

installation, maintenance and warranty are investigated. Samples of the

product and services being considered may be examined or trials

undertaken.

4. Negotiations: Negotiations are undertaken and price, availability and

customization possibilities are established. Delivery schedules are

negotiated and a contract to acquire the products and services is

completed.

5. Fulfillment: Suppliers preparations, shipment, delivery and payment for

the product and services are completed, based on contract terms.

Installation and training may also be included.

6. Consumption, Maintenance and Disposal: During this phase the

company evaluates the performance of the product & services and any

accompanying service support, as they are consumed.

7. Renewal: when the product and services has been consumed and/ or

disposed of the contract expires, or the product or services is to be re-

ordered, company experience with the product and services is reviewed. If

the product and services is to be re-ordered, the company determines

whether to consider other suppliers or to continue with the same suppliers.

INTRODUCTION TO PROCUREMENT

Apeejay Institute of Technology School of Management Page 26

Page 27: Abhinay Project Report

Procurement activities to be taken by NATIONAL THERMAL POWER

CORPORATION (NTPC) are to satisfy varying project requirement of equipment,

materials and services. Any procurement-requiring adherence to the IDA

procurement procedure, long equipment delivery periods, intense engineering

co-ordination or specialized engineering knowledge during procurement etc.

would be classified as category “A” contracts. All other procurement contracts

pertaining to a project will be classified as category “B” contracts.

Procurement at NTPC is initiated on the basis of approved indents/requisitions

and indicating budget and project estimate provisions. The contract

services/materials management services receive the requisition/indent for the

procurement of materials/equipment/services duly approved by the competent

authority and then plan and organize the procurement action.

Objective

The basic objective of procurement management at NTPC is to make available,

the needed equipment, material, works and services in the right quality and

quantity, at the right time and at the right price after giving fair and equal chance

to tenderers, so as to obtain the optimum value for each unit of expenditure

What is a contract?

Apeejay Institute of Technology School of Management Page 27

Page 28: Abhinay Project Report

A contract in its simplest form defined as a promise, or group of promises, that

the law will enforce. The promise is to do, or refrain from doing, a particular

activity.

But in commercial context, a contract is a document in which the terms of the

promise are recorded. It can also be explained, as “a contract is an agreement

enforceable at law between two or more parties to undertake or perform a

particular thing. In undertaking or performing that activity both the parties accept

certain responsibilities and in return receive certain benefit for performing the

same.

Procedure of procurement

Intent of the contracting parties :

An agreement between the two parties does not itself constitute a contract. There

must be a definite promisor, each of whom is legally capable of performing the

intended part of the agreement. It is necessary for the two parties to have their

agreement legally binding, that is, that the agreement be written and enforceable

by law.

At NTPC the department, which requires the materials is known as intending

department and the department that procures the material is known as the

material department. Hence intending department is the customer for material

department.

1. Intending for Procurement: Procedure for intending is as follow:

Apeejay Institute of Technology School of Management Page 28

Page 29: Abhinay Project Report

INDENT

COST ESTIMATION

FINANCE

CONTRACT MATERIAL HR

For the purpose of indenting, material planning is required. It is nothing but

classifying the materials into various categories to facilitate a speedy and efficient

procurement. In this process all the materials which may be required at any of

the NTPC projects or offices are classified in to five major categories and their

procurement is to be done on the basis predefined for them.

1. Stock item (Automatic Recoupement items/AR)

2. Insurance Items (I)

3. Unit Replacement item (UR)

4. Capital Item (P)

5. Other non-stock items (Not falling under any of the above category)

But since this classification is very vague and unspecific, a further classification

is done to exercise selective control over all Material Management activities. This

classification is known as the ABC analysis.

Identification of Responsibilities.

NTPC being a utility organization with projects located away from the corporate

office, has divided the responsibilities of contracts management, both pre award

and post award between the corporate office and project site. A contract

management functions as an independent specialized techno commercial

function unit to meet the overall corporate objective in the area of project

Apeejay Institute of Technology School of Management Page 29

Page 30: Abhinay Project Report

procurement. It has been in place since inception of NTPC as corporate contract

department or concurrence department.

The corporate contracts procures plants/ equipment and services for its projects,

which are characterized by the adherence to the procurement of external funding

agencies, factoring of the long process owner for award of all such contracts

including high value civil works, its monitoring and post award follow up till the

delivery of equipment from the suppliers works till the closure of the contracts.

The corporate contracts division/department is responsible for installation of the

plant & equipment and its execution is the responsibility of the project site.

There are number of the other small value contracts with lesser of engineering

coordination, whose pre award and post award contracts are handled by the

project sites. The principles and guidelines followed for these site contracts are

similar to those applicable to corporate contracts.

In view of the complexity involved in the construction of thermal generation

projects. The contracts management systems calls for the further sharing of

responsibilities for specialized functions such as engineering, finance, cost

engineering, quality assurance and inception at corporate center & erection, site

finance, field quality assurance etc. as the project site. The co-ordination and

division of responsibility between the departments at two responsibility centers

are also clearly defined.

Stages of international competitive bidding (ICB)

Step 1

(a) Contract packaging

Contract packaging is the first step of procurement for a project. The total

project work is broken into smaller well-defined packages. This is done with the

view to optimize the number of contracts to be handled for the better planning,

co-ordination and implementation of the whole project and at the same time to

execute the project at an optimum cost to the owner.

(b) Development of packages

Apeejay Institute of Technology School of Management Page 30

Page 31: Abhinay Project Report

First of all feasibility report for any project is prepared which contains the

details of the various equipment systems and services required for a

particular project.

Subsequently, as the conceptual design progresses, a detailed project

description emerges as design intent memorandum (DIM) incorporating

station schematics like thermal schematics, electrical signal line diagrams,

and station water flow systems, coal and ash handling systems etc. these

schematics provide the inter linkage between the various equipments and

services. The engineering function is responsible for development of such

schematics. Taking into consideration the requirement of the project master

network (PMNW) schedule, grouping of equipment and services is done to

arrive at contract packages. Each package as developed above normally

forms an independent contract.

The development of contract package list for a project is done jointly by

engineering, contracts, and corporate planning and finance functions. The

contract package being extremely vital to a successful project

implementation is approved for implementation by the highest corporate

level authority.

Step 2

Cost estimation.

(a) Cost estimation : cost estimation process is the most important financial

activity in the process of budgeting and procurement. Whenever NTPC

procures some material, it is either financed from the budget allocated to

the particular department requesting for the material or it will be financed

from the central fund. The procurement of the second kind requires

financial clearance from the finance concurrence department. For the

purpose, cost estimation is done before forwarding the indent document to

the finance department. There are various methods of cost estimation,

which are used at NTPC. Some of the methods use very technical details

and procedures whereas some are simple to implement and uses market

rate to prepare a cost estimate.

Apeejay Institute of Technology School of Management Page 31

Page 32: Abhinay Project Report

(b) Historical cost method: In this method of cost estimation. The cost

engineering department at NTPC uses the latest cost incurred for similar

kind of project. For example, if the cost estimate has to be prepared for a

new thermal power plant, the latest executed thermal power plant rates will

be used not any other. Hence the rates thus obtained are very near to the

actual rates that might be prevalent in the market at that point of time. But

to smoothen the effect of inflation and various other financial components in

the prices at the time of the execution of that project, an escalation factor is

used. All the prices of the previous projects are multiplied by this factor and

a very close estimation of market rare is thus obtained. This escalation

factor calculation is discussed separately in the report.

(c) Market rate method : market rate method is used for the procurement

that are not in very large numbers and value. In this method once an indent

is prepared, some of the vendors registered at NTPC or listed in trade

journals are sent a request for quoting the prices of a particular good. This

enquiry is not tender and the rates provided by the vendors are not part of

the bid. After the information is received, the rates quoted by various

vendors are compared and the lowest quoted price is taken as base rate for

calculations. However if the difference in the price quoted by two vendors

are reasonably high an average of the two may be taken as the base.

However for civil works component of the contract, the wages rates are

taken from the government gazettes and similarly for some homogenous

products like cement, steel etc. a standard market prevailing rate is used.

6. Tendering Procedure

Normally an open tendering system for procurement is adopted during

construction stage of a project. However depending on the circumstances and

the requirements, limited tendering or single tendering system is also adopted in

specific cases. Following are three types of tenders:

Types of tenders

Based on the materials classification and DOP, there are three types of tenders

Apeejay Institute of Technology School of Management Page 32

Page 33: Abhinay Project Report

(1) Open tender: procurements or value Rs 1 lakh and above must be

done through open tendering. All the plant packages are procured through

open tender. Open tender is accessible to all known reliable and proven

sources of particular equipment/ material. For the purpose, a notice

inviting tenders must appear in two or more newspapers of all India repute

in addition to one or more local newspaper where the materials/

equipment is to be delivered. However to avoid frivolous tenders, a pre

qualification procedure may be adopted. This process will take place once

in every three years by advertising in two or more newspapers of all India

repute in addition to one or more local newspapers where materials is to

be delivered. The criteria for pre qualification will inter-alia consist of past

performance, financial soundness, technical competence, organizational

capability etc. but for the items valued less than 1 lakh the pre qualification

can be done on the basis of data available in trade journals,

manufacturer’s directory or approved vendors list of state

government/central government/DGS & D vendors to whom enquiries

were floated in past.

(2) Limited tender: limited tender is a type of tender where instead of

sending bid enquiry to all the possible vendors through newspapers, a

limited number of vendors are intimated through post or fax. But a limited

tender may b invited only for the procurement worth less than Rs. 50000.

in limited tender, minimum of four bidders are invited to quote the prices

for the required equipment/materials/services and these four bidders must

be from the approved list of vendors mentioned in the open tender.

However a limited tender is a special case and cannot be issued without

proper explanation and requirement. In case of urgency, items worth more

than rs.50000 may also be procured with authorization of competent

authority and the reason must be recorded in the indent documents.

However the next higher authority of the procurement department will

decide the number and names of supplier.

(3) Single tender : this type of tendering is the easiest and fastest to

acquire goods but requires lot of paper work or documentation and

authorization before the acquisition can be initiated. These acquisitions

take place on the ground of standardization. To initiate a single tender, a

proprietary article certificate must be issued by a competent authority and

Apeejay Institute of Technology School of Management Page 33

Page 34: Abhinay Project Report

the purchase will not be made without authorization of a general manager

or to whom the power is delegated. This type of tendering is monopolistic

in nature and is avoided to the extent possible. However single tendering

is done in many other cases which are not mentioned anywhere in the

DOP.

Step 4

Qualifying requirements for bidders:

Normally the post qualification procedure is adopted for determining the capacity

and capability of the bidders as to know whether they would be able to

successfully execute the contract in case of award of contract to them. The

qualification requirements has two parts, the standard or general QR, which is

common for all contract packages and the specific QR as finalized for a particular

package.

In the notice for inviting tenders/ invitation for bids only the specific part of QR is

published. However the bidding documents stipulates the complete QR i.e. the

standard part of the qualification requirements as also the specific requirements

for a particular contract package. The QR’s for each of the contract package are

based on intensive and well researched interdisciplinary efforts and finalized by a

standing committee headed by the director (technical). Such qualification criteria

inter-aliia includes the status of a bidder i.e. manufacturer or project executing

agency, financial status, technical requirements to be fulfilled etc. in case of post

qualification procedure the analyses of bidder qualification data is carried out

during the bid evaluation process. Conformity by the lowest evaluated bidder to

be stipulated qualification requirements is a prerequisite for the award of the

contract. If required, a pre qualification procedure is adopted for obtaining offers

only from pre qualified bidders who meet the specified criteria.

In case of pre qualification procedure, the bidders are required to furnish

documents/ data to validate past performance, financial status, technical

capability, organizational capacity for specific works through a pre qualification

notice published in leading newspapers.

Step 5

Apeejay Institute of Technology School of Management Page 34

Page 35: Abhinay Project Report

Issuance of invitation for bids

The invitation for bids (IFB) or notice inviting tender (NIT) are published in

leading national newspapers as per guidelines and procedures. Copies of IFB or

NIT are also sent to the bidders who have evinced interest in supplying similar

equipments or services in the past. In the case of procurements funded by

external funding agencies following international competitive bidding procedures,

the IFB are also published in the Indian trade journal and a copy of IFB sent to

each of the embassies/ high commissions of members countries of the funding

agency. In case of procurements under the World Bank funding the IFB is also

published in the “development business” of United Nations when required.

Contents of bidding documents:

Every time when a open tender is invited, the bidders are provided with a set of

documents, which provides various required information and terms and

conditions of the contract. The documents also contains the various contract

forms which the bidder is expected to sign and return to NTPC to acknowledge

the acceptance of the terms and conditions of the contract. The document also

contains the guidelines for bidders for bank guarantee to be submitted as bid

security i.e. 2% of total contract amount.

Earnest money and the like, this document is issued for a cost that is decided on the basis

of the total estimated value of the indent the costs of the documents are as follows:

s.no Estimated value of indent Cost of tender

documents

1 Up to Rs. 10 lakhs 200

2 Above Rs 10 lakhs and up to 25 lakhs 300

3 Above Rs 25 lakhs and up to 50 lakhs 500

4 Above Rs 50 lakhs and up to 100 lakhs 750

5 Above Rs 100 lakhs and up to 500 lakhs 1500

6 Above Rs 500 lakhs 3000

Every time a new tender is notified a set of tender documents are issued against

the payment of stipulated fee according to the price list given above. This set of

tender document consists of many different documents meant for different

Apeejay Institute of Technology School of Management Page 35

Page 36: Abhinay Project Report

purposes. The documents may vary from project to project. but there are certain

documents which are generally issued to bidders. They are as follow:

Instruction to Bidder (ITB): This document is meant to provide the

bidders the vital information required to understand and evaluate the tender offer.

The document contains the general instructions like the terms of payment, bid

security, contract performance security, liquidated damages, currencies

conversion, defects liability and work schedule. The document also specifies the

qualifying or eligibility requirements of the bidder and the goods and services

supplied. The ITB also contains information for the foreign bidders. Additionally

the ITB contains various references to clauses of GCC (General conditions of

contract) and SCC (special conditions to contract). Finally the document specify

about the language and interpretation and implied terms and conditions of all the

documents provided with the bid. ITB also contains information about how to

modify and withdraw the bids already submitted to NTPC. Hence in short we can

identify this document as the guidelines and information brochure to bidders

before they submit their quotations for the notified work.

(a) Bid proposal sheet or Bid data sheet: Bid proposal sheet is set

of documents which contains the formats for bidding, summary price

proposal, break up of bid price, equipment wise price break up, civil works

price break up, commercial deviation, technical deviations, guarantee

deceleration, price adjustments data, price break up of recommended

spares, construction equipments, special maintenance tools, QR data and

capacity data, work completion schedule, declaration of import content,

check list, information regarding value addition and type test charges. This

document is nothing but a standard format providing the bidder to furnish

the details required by the NTPC in a standard format used at NTPC.

(b) General condition of contract: The document titled general

condition of contract of GCC is document that takes care of the legal

aspect of the contract between bidder and NTPC. This document is also

an integral part of all bid documents with some minor changes or no

changed at all. The document starts with the definition for the terms used

in various tender documents. This is worth noting that all the terms used in

the bid document are predefined and have one and only meaning which is

Apeejay Institute of Technology School of Management Page 36

Page 37: Abhinay Project Report

defined in the GCC. The document also contains different formulas that

are to be used on some future dates to calculate the LD or the price

escalation. Finally the document also refers to the unforeseen events like

out break of war, bankruptcy of the contractor or any other force major.

The GCC also has a clause called RESOLUTION OF DISPUTES that

specifies the procedures to be followed if any dispute occurs, arising out of

or in connection with the contract.

(c) Special conditions of a contract: special conditions of contract or

SCC are not a standard document that is issued with all the tender

documents. The document takes care of the special issues that have

come up or may come up in the course of the execution of that particular

contract and has not been covered in the general condition of contract.

The very first clause of the document is TIME- THE ESSENCE OF

CONTRACT. The document also talks about the detailed manufacturing

plan and master schedule of the execution of the contract. It is the SCC

where we mention the issues related to liquidated damage clause. This is

mentioned in the document itself that “the following special condition (if

contract shall supplement the general conditions of contract). Whenever

there is a conflict. The provisions herein shall prevail over those in the

general conditions of contract”. Hence the document may also be

considered as the amendments to the GCC.

(d) Erection condition of contract : this document again is specific

document which may not be issued with all the tenders. As the name it

suggests. The document deals with the erection component of the

contract (if any).in the document some particular issues pertaining to the

erection component of the contract is dealt with. Typically, an Erection

Condition of Contract deals with the civil construction works undertaken at

the site where the equipment is to be installed and commissioned. This

also takes into consideration the statutory and local authority who may be

in charge of monitoring the work in progress and whose permission may

be required. Hence this document is a must for all the work where there is

an erection component.

Apeejay Institute of Technology School of Management Page 37

Page 38: Abhinay Project Report

(e) Technical specification : the document is the thickest document of

any bid document. This document contains all the specifications required

for that particular project. The document is prepared by the project

engineering department and contains the technical specifications of the

equipments and spares to be procured. It may also contain the drawings

of the equipments or layout of the project. Similarly the document will also

enlist all other possible alternatives to the already mentioned

specifications (if any). Since there is no financial aspect associated with

this document, a detailed study of this document is out of the scope of the

report.

Tender committee

Delegation of powers has very important role to play in purchasing power

process at NTPC. For every purchase value of exceeding Rs 200000.

The committee consists of three members, one representative each from the

indenting department, materials department and finance (concurrence). The

representatives are nominated by competent authority varying from senior

manager to DGM depending upon the value of the contract. This committee will

take into consideration every possible aspect of the terms and conditions, prices,

inspection procedures, phasing delivery if required etc. This committee also

formulates the QR (qualifying requirements) for the bidders of that particular

tender.

Tender opening:

Tender opening is the penultimate step in purchasing process. Tenders are

opened on the due date and time mentioned in the tender notification without fail.

If the date mentioned is declared holiday, the next working day will be considered

as the opening date but the time will remain the same. The sealed envelops

containing the bid will be opened by the purchase and finance executives

nominated by their head of the department. The representatives of the bidders

may also be present if they wish so however their absence will not hinder the

process. The name and rates quoted by all the present bidders will be read out

and any omission or irregularity will be pointed out on the spot.

Alterations will be initiated by the officers present at the time of the opening of the

tenders. All the quoted figures should also be encircled and will be written in

Apeejay Institute of Technology School of Management Page 38

Page 39: Abhinay Project Report

words if the bidder have not done so already and will be attested. Total number

of alterations and corrections will also be written and attested. These all activities

are done to ensure proper and transparent procurement process.

Security deposits:

A refundable security deposit may be asked at the time of submission of the bid.

This deposit is taken to ensure that the vendor who is awarded that contract will

not refuse to undertake the contract. If the bidder after successful bidet refuses to

undertake the contract, the earnest money deposited by him will be forfeited.

However there are various instances where this deposit may be waived off. For

example for all the purchases valued less than Rs. 50000 the EMD may be

waived off. Similarly for the PSUs, NSICs and SSI parties, the EMD can be

waived also. On successful completion of bidding the earnest money may either

be returned to the bidder or may be adjusted towards the security deposit to be

provided by the bidder. Another major deposit is in form of performance

guarantee of liquidated damage (LD) the equipments provided by the vendor fail

to perform as per the specification, the cost for this shortfall may be recovered

from the vendor. This guarantee is generally 10% of the awarded value and is in

form of bank guarantee. However in cases of procurement from proprietary

vendor the same may be waived depending upon the merit of case.

However in case of procurement of equipments or materials or services there is a

contract for providing spares for the next three years. In case the prices of these

spare parts goes up in the future and the vendor refuses to supply the spares at

the same rate than this guarantee deposit if forfeited. As a matter of fact, this

guarantee is taken just to make sure that the contractor does not refuse to honor

the contract in future after he realizes that the prices have gone up or for some

similar reasons.

Step 6

Submission, Receipt and Opening of bids

The time allowed for preparation and submission of bids by the bidders is

decided taking into consideration the particular circumstances and complexity of

work involved. Generally, a period of not less than 6 weeks from the date of

Apeejay Institute of Technology School of Management Page 39

Page 40: Abhinay Project Report

invitation of bids is considered for preparations and submission of bids. For large

and complex packages this period is extended to 10 to 12 weeks.

Bids are received in a sealed condition at the place, date and time identified in

the invitation for bids/bidding documents. A receipt is issued to the bidders for the

bids delivered by hand indicating the date and time of delivery.

The bids received are opened by a team comprising representatives from

engineering, contracts and finance departments in the presence of bidders

representative who chose to attend the bid opening. The details such as name

od bidder, bid price, availability of bid security, guaranteed parameter, discounts

if any, are read aloud during the opening of bid. All the participants in the bid

opening are required to sign a register as a proof of attendance maintained for

this purpose

.

Late and delayed tender

Though the last dates for receipt of tender and tender opening dates are

mentioned in the bid invitation notice and all the bidders are expected to adhere

to them, some time some tender documents posted by the bidders get delayed in

the post and reach the NTPC office later than the date specified in the tender

invitation notices. It can be caused by several reasons within bidder’s control or

out of one’s control. All such tenders are classified into two categories. Late

tenders and delayed tenders.

(1) Late tenders : the tender that have been posted on or after the due

date and received subsequently are considered to be late tender. Similarly

all the tenders posted through courier before the due date but received

after the due dare is also considered to be Late Tender. As a policy all the

late tenders are rejected out right.

(2) Delayed tender: when a tender documents is posted before the due

date but is received after the due date. For such tenders which are posted

through registered post or speed post before the due date and is received

within 6 working days of bids due date may be opened and considered

with the approval of competent authority. But this consideration has a

condition that the date of posting of the bids documents must be clearly

Apeejay Institute of Technology School of Management Page 40

Page 41: Abhinay Project Report

visible. on the postal stamp on the envelope containing the documents.

Tender those is posted by ordinary post and are received after the due

date and time will not be opened and will be returned to the party after

finalization of bid except in case where:

(a) The number of acceptance offer is less than three.

(b) Lowest and acceptable tender is unreasonably high when

compared with lowest purchase price.

(c) Artificial manipulation of rates by forming a ring is suspected.

(d) All the tenders are providing the make of only one manufacturer.

(e) If a substantial savings in foreign exchange is possible.

Step 7

Evaluation of Bids:

The bids are received, opened and evaluated by a duly constituted tender

committee comprising members from contracts, engineering and finance

functions in accordance with the ‘delegation of powers’. The committee

determines the lowest evaluated bid for award of contract in terms of criteria for

evaluation of bids stipulated in the bidding documents and puts up its

recommendation for approval of competent authority in accordance with the

‘delegation of powers’.

The process of evaluation of bids begins with an examination of the bids to

determine:

1. bid eligibility

2. Acceptability of bid security furnished by the bidder.

3. Completeness of bid and correctness of signature.

4. Acceptability of joint deed of undertakings

5. Computational errors in the bid price.

6. Stated deviations from the bidding conditions, which might reflect on the

substantial responsiveness of the bid and justify its rejection.

Though generally and to the extent possible avoided clarifications may be sought

from the bidders. If considered necessary by the tender committee, with the

approval of competent authority. Due care is taken of the fact that such

clarifications would not call for any material alterations on the bidder’s bid.

Apeejay Institute of Technology School of Management Page 41

Page 42: Abhinay Project Report

The detailed evaluation is carried out only for bids, which are substantially

responsive. Bid evaluation considers price and other factors in a transparent

manner and in accordance with the stipulated evaluation criteria stated in bidding

documents such as cost compensations for the deviations from the bidding

conditions taken by the bidders, differential price factors for guaranteed

parameters etc.

In case of procurement under international competitive bidding procedures, the

bid price are converted into a single currency i.e. in the Indian rupees based on

the exchange rate prevailing as on the date of bid and comparison of bids. Other

factors such as a domestic price preference and purchase preference to public

sector undertakings applicable as per the extant guidelines are also considered

for the purpose of evaluation of bids.

Once the lowest evaluated bidder is selected as above the next step is to

determine whether the qualification requirement as stipulated in bidding

documents are met and whether the bidder in question is capable to successfully

executing the contract. An affirmative determination of the above is prerequisite

for award of contract to the bidder. In case the lowest evaluated bidder does not

meet the above requirement, the similar determination is done for the next lowest

bidder. If the bidder also fails, the process is continued until the lowest evaluated

and qualified bidder is chosen.

Negotiation:

When adequate competition exists, the negotiation should and must be avoided.

This competition may be in from of many manufacturers making the same good

or a single manufacturer providing the goods through many retailers or suppliers

and all the retailers and suppliers are free to quote individually. However if it’s

found that the price quoted by all individual bidders are unreasonably high in

comparison to the last purchase price or estimate or in case of some ambiguous

technical or commercial terms and conditions, negotiations can be done with the

approval of competent authority as per DOP. In normal circumstances, the

negotiation should take place with the technically and commercially evaluated

lowest vendor only. However, depending upon the situation the negotiation may

be carried out with more than one party at a time. Normally the negotiation is

Apeejay Institute of Technology School of Management Page 42

Page 43: Abhinay Project Report

carried out by the tender committee. But in case a tender committee is absent i.e.

no committee was formed to monitor the procurement, representatives from

finance and purchase may complete the task of negotiation. However,

negotiation process is not always for negotiating the price of equipment or

material or services supplied but it may also involve terms and conditions of

supply. Future commitments for supply of spare parts and consumables and

many other aspect of the contract. For example a lowest price bidder may not get

the contract if it is found that another bidder who is quoting higher than him but is

offering lowest priced spares. Hence in this case a negotiation may be conducted

with the lowest to make him offer the spares at the same rate as being offered by

his competitor. Once the negotiation process is finished and the two parties

involved in the negotiation reach a consensus, the committee’s purchase

proposal or recommendation will be put up to the competent authority for

approval and subsequently the letter of indent may be faxed to the party.

Step 8

Contract Award

All the activities related to evaluation of bids and approval of evaluation report or

award recommendations by the competent authority, concurrence of the funding

agency (wherever applicable) and post bid discussions with the successful bidder

to resolve ambiguities or non conformity to the bidding provisions observed

during the bid evaluations are required within the bid validity period.

Post purchase activities

Vendor evaluations

Once a vendor has supplied some material to NTPC, the vendor is registered

with the NTPC and it is given a performance rating which may be used in future

to award of contract in case of limited tender and single tender. This rating

system is not very complex but some formulas are used.

Parameter Measure Weightag

e

A) Quality performance Rejection 4

B) Delivery Performance

Apeejay Institute of Technology School of Management Page 43

Page 44: Abhinay Project Report

(1) Time Schedule delivery Ratio of contractual delivery

to actual in a week 2

(2) Quantity Schedule delivery Deviation in Quantity 2

c) commercial & Contractual

Performance

Pre- post award performance 2

Calculations of vendor ratings will be done as follows:

(a)Quality performance = 1 – rejected quantity * weightage

Supplied quantity

(b) Time schedule = 1 – contract delivery in week * weightage

Actual delivery in week

© Quality schedule = quantity received * weightage

Quantity ordered

Parameter Minimum percentage score

Quality 70%

Delivery 50%

Commercial contractual Terms 50%

On the basis of points scored against each parameter categorization of vendor

shall be done as follows:

Vendor Rating Point Score

A) outstanding 8 and above

B) Very Good/Good 6-8

C) Unacceptable Less than 6

Indices of performance

Apeejay Institute of Technology School of Management Page 44

Page 45: Abhinay Project Report

1. Adherence to lead – time: Against each purchase order the

supplies are to be affected as per the declared lead time with a cushion

+10%. In case the actual lead time differs by more than +10% from the

declared lead time then the total lead time slippage shall be taken into

account for rating calculation.

2. Extent of Rejection : supplier as per specification and without

rejection should be the aim of all purchase executives. But at time the

rejections is possible due to non conformance of the specification or

performance slippage. Hence a rating system is developed to take care of

that

3. Budget compliance : The responsibility of each purchase personnel is

to keep the procurement within the allocated budget. The additional

responsibility is in form of maintaining the quality also at the same time.

The rating for budget compliance will be done as follows:

And over all rating is done on following basis:

Apeejay Institute of Technology School of Management Page 45

Rejected value of material supplied – value of materialRATING = value of material supplied

Budget allocated – Excess over budgetRATING = Budget allocation

Declared lead time slippage RATING = Declared Lead time

Page 46: Abhinay Project Report

Apeejay Institute of Technology School of Management Page 46

Sum of above rating * 100OVER ALL RATING = 3

Page 47: Abhinay Project Report

General clauses

A. INTRODUCTION

Source of Funds

National Thermal Power Corporation Ltd. (herein after called 'NTPC' or

'Employer) intends to finance the Package named in the Bid Data Sheet

(BDS), through external commercial borrowings, internal and other

sources.

NTPC intends to make financing arrangements for the subject package by

means of Buyers Credit from International Banks through the Export Credit

Agencies of the country concerned to the extent the goods and services

covered in the package are imported from OECO countries. For the above

purpose the Export Credit Agencies require certain. Procedure formalities to be

completed by the equipment supplier of their country. The bidder shall, in case of

award of contract, facilitate completion of such formalities as may be required by

the respective export credit agency to enable NTPC to avail Buyers Credit for

funding eligible goods and services covered in the package. The aforesaid option

of funding is also intended to be availed by NTPC for supply of goods and

services from OECD countries by the sub-vendors/sub-contractor of the bidder.

The bidder shall make similar compliance in respect of its sub-vendors/ sub-

contractors to the extent the goods are imported from concerned OECD country

ELIGIBLE PLANT, EQUIPMENT AND SERVICES

For the purposes of these bidding documents, the word "facilities" means the

plant and equipment to be supplied and installed, together with the services to be

carried out by the contractor under the contract. The words "plant and

equipment,” "installation services," etc., shall be construed in accordance with

the respective definitions given to them in the General Conditions of Contract.

Apeejay Institute of Technology School of Management Page 47

Page 48: Abhinay Project Report

All countries and areas are the eligible source countries for goods and services

to be supplied under this contract and accordingly goods and services to be

supplied under this contract may have their origin in any country and area

For purposes of this clause, "origin" means the place where the plant and

equipment or component parts thereof are mined, grown, or produced. Plant and

equipment are produced when, through manufacturing, processing or substantial

and major assembling of components, a commercially recognized product results

that is substantially different in basic characteristics or in purpose or utility from

its components.

The origin of the plant, equipment and services is distinct from the nationality of

the Bidder.

BID PRICES

Unless otherwise specified in the Technical Specifications. Bidders shall quote

for the entire facilities on a "single responsibility" basis such that the total bid

price covers all the Contractor's obligations mentioned in or to be reasonably

inferred from the bidding documents in respect of the design, manufacture,

including procurement and subcontracting (if any), delivery, construction,

installation and Completion of the facilities including supply of mandatory spares

(if any). This includes all requirements under the Contractor's responsibilities for

testing, pre-commissioning and commissioning of the facilities and, where so

required by the bidding documents, the acquisition of all permits, approvals and

licenses, etc.; the operation, maintenance and training services and such other

items and services as may be specified in the bidding documents, all in

accordance with the requirements of the General Conditions of Contract and

Technical Specification.

Bidders are required to quote the price for the commercial, contractual and

technical obligations outlined in the bidding documents. If a Bidder wishes to

make a deviation to the provisions of the bidding documents save those listed,

such deviations shall be listed in Attachment 6 of its bid.

Apeejay Institute of Technology School of Management Page 48

Page 49: Abhinay Project Report

Bidders shall give a breakdown of the prices in the manner and detail called

for in the Price Schedules. The Bidders shall present their prices in the following

manner:

Separate numbered Schedules shall be used for each of the following

elements. The total amount from each Schedule (1 to 4) shall be summarized in

a Grand Summary (Schedule 5) giving the total bid price (s} to be entered in the

Bid Form.

Schedule No. 1

Plant· and Equipment including Type Tests charges and Mandatory Spare Parts

supplied from Abroad

Schedule No. 2

Plant and Equipment including Type Tests charges and Mandatory Spare Parts

to be manufactured within Employer's Country

Schedule No. 3

Local Transportation including port handling, port clearance, port charges, Inland

transit Insurance and other local cost incidental to delivery of Plant & Equipment

and Mandatory Spares

Schedule No. 4

Installation Services including Erection Works, insurance covers other than

inland transit insurance and other services as specified in the bidding document

Schedule No. 5 Grand Summary (Schedules Nos. 1 to 4)

Schedule No. 6 Recommended Spare Parts

Schedule No. 7 Taxes and Duties not included in Bid Price

Apeejay Institute of Technology School of Management Page 49

Page 50: Abhinay Project Report

Schedule No. 8A Break up of type test charges quoted in Schedule -1

Schedule No. 8B Break up of type test charges quoted in Schedule -2.

SCHEDULE OF UNIT RATES

The plant and equipment included in Schedule No. 1 and 2 above exclude all

materials used for civil, building and other construction works. All such materials

shall be included and priced under Schedule No. 4 (Installation Services).

In the Schedules. Bidders shall give the required details and a breakdown of their

prices as follows:

A) Plant and equipment- including Type Test charges and mandatory spares to

be supplied from abroad (Schedule No.1) shall be quoted on CIF Indian port-of-

entry. In addition, the FOB price shall also be indicated.

Further, Bidders seeking qualification on the basis at association / collaboration

with manufacturer(s) of particular equipment(s) are required to quote the price of

such equipment(s) including spares on CIF (Indian Port of Entry) basis, if the

items are to be imported by the manufacturer or the Bidder. In case, such

equipment and spares are not quoted by the bidder on CIF (Indian port-at-entry)

basis, then Employer shall assess the CIF (Indian port-of-entry) price of such

equipment and mandatory spares for the purpose of evaluation and accordance

of price preference

C) Plant and equipment including Type Test charges and mandatory spares

manufactured or fabricated within the Employer's country (Schedule No. 2) shall

be quoted on an EXW (ex factory, ex works, ex warehouse or off-the-shelf, as

applicable) basis, and shall be inclusive of all costs as well as duties and taxes

paid or payable on components and raw materials incorporated or to be

incorporated in the facilities. However, Sales Tax (not the surcharge in lieu of

Sales Tax), Local Tax including Entry Tax/Octroi (it applicable) and other levies;

n respect of direct transactions between the Employer and the Bidder shall not

be included in the Ex-works price but shall be quoted separately in Schedule

No.7. Further, taxes and other levies, if any, on type tests on equipment with

Apeejay Institute of Technology School of Management Page 50

Page 51: Abhinay Project Report

respect to direct transaction shall be quoted separately. The taxes, duties and

levies quoted by the bidder in Schedule-7 shall be as applicable in the

Employer's country as on seven (7) days prior to the last date for submission of

bids.

C) Local transportation, inland transit insurance, port clearance and port charges

and other local costs incidental to delivery of the Plant and Equipment including

mandatory spares shall be quoted in Schedule No. 3. The Employer shall be

responsible and be liable only for payment of custom duty and import duties, if

imposed in future, on CIF component of the plant and equipment including

mandatory spares to be supplied from abroad. However, the Employer, as a

consignee shall furnish promptly necessary clarifications and documents as may

be required to be furnished by the consignee for the purpose of customs

clearance

D) Installation services shall be quoted separately in sc no. 4 and shall include

rates or prices for all labors and contractor’s equipments, temporary works,

materials, consumables, and all matters and things of whatever nature, charges

for insurance cover other than inland transit insurance, operations, and

maintenance services, the provision of operations and maintenance manuals,

training, training of employer’s personnel etc. and other services are identified in

he bidding documents and necessary for proper execution of installation

services, including all taxes, duties, levies, and charges payable in employer’s as

of seven days prior to the deadline for submission of bids.

E) Recommended spare parts shall be quoted separately in Schedule-6 on

CIF/EXW basis in accordance, Local transportation charges including inland

transit insurance and port charges etc. for recommended spares shall also be

quoted in Sc.No.6.

Apeejay Institute of Technology School of Management Page 51

Page 52: Abhinay Project Report

BID SECURITY

The bidder shall furnish, as part of its bid, a bid security in a separate sea/ed

envelope in the amount and currency as stipulated in the Bid Data Sheet

The bid security shall, at the Bidder's option, be in the form of a Banker's cheque

irrevocable letter of credit or a bank guarantee. , In case of domestic bidders the

Bank Guarantee shall be from- a Bank as specified in the Bid Data Sheets. In

case of foreign bidders, the Bank Guarantee can be from any other bank also in

addition to the banks specified in Bid Data Sheet and if the Bank Guarantee is

from a Bank not specified in the Bid Data Sheet, then the Bank Guarantee shall

be confined by any such Bank as specified in the Bid Data Sheet. The format of

the bank guarantee or letter of credit shall be in accordance with the' form of bid

security included in the bidding documents. Bid security shall remain valid for a

period of forty five (45) days.

The bid security shall be furnished in a separate sealed envelope. Any bid not

accompanied by an acceptable bid security, in a separate sealed envelope, shall

be rejected by the Employer as being non-responsive and returned to the Bidder

without being opened. The bid security of a joint venture must be in the name of

all the partners in the joint venture submitting the bid.

The bid securities of unsuccessful bidders will be returned as promptly as

possible, but not later than twenty-eight (28) days after the expiration of the bid

Validity period.

THE BID SECURITY MAY BE FORFEITED

(a) If the Bidder withdraws its bid during the period of bid validity specified by the

Bidder in the Bid Form

Apeejay Institute of Technology School of Management Page 52

Page 53: Abhinay Project Report

(b) If the Bidder does not accept the correction of its Bid Price pursuant

(c) If the Bidder does not withdraw any deviations listed in Anachment-6 at the

cost of withdrawal indicated by him

(d) If the Bidder refuses to withdraw, without any cost to the Employer,

Any deviation not listed in Attachment 6 but found else...where in the bid.

In case of successful bidder, if the bidder fails within the specified time limit

To sign the contract agreement, in accordance with ITB.

To furnish the required performance security in accordance with ITB.

CONVERSION TO SINGLE CURRENCY

To facilitate evaluation and comparison, the Employer will convert all bid prices

expressed in the amounts in various currencies in which the bid price is payable

to a single currency. The currency selected for converting bid prices to a

common base for the purpose of evaluation, along with the source and date of

the exchange rate.

TECHNICAL EVALUATION

The Employer will carry out a detailed evaluation of the bids previously

determined to be substantially responsive in order to determine whether the

technical aspects are in accordance with the requirements set forth in the bidding

documents. In order to reach such a determination, the Employer will examine

and compare the technical aspects of the bids on the basis of the information

supplied by the bidders, taking into account the following factors:

a) Overall completeness and compliance with the Technical Specifications

And Drawings; deviations from the Technical Specifications as identified in

Attachment 6 to the bid; suitability of the facilities offered in relation to the

environmental and climatic conditions prevailing at the site; and quality, function

and operation of any process control concept included in the bid. The bid that

Apeejay Institute of Technology School of Management Page 53

Page 54: Abhinay Project Report

does not meet minimum acceptable standards of completeness, consistency and

detail will be rejected for non-responsiveness.

Achievement of specified performance criteria by the facilities

(b) Type, quantity and long-term availability of mandatory and recommended

Spare parts and maintenance services.

(c) Any other relevant factors, if any, listed in the Bid Data Sheet, or that

the Employer deems necessary or prudent to take into consideration.

COMMERCIAL EVALUATION

The comparison shall be of the EXW price of domestically manufactured plant

and equipment including Type Test charges and mandatory spares (within the

Employer's country), such price to include all costs as well as duties and taxes

paid or payable on components and raw materials incorporated or to be

incorporated in the plant and equipment including mandatory spares plus the CIF

(Indian port-of-entry) price of the plant and equipment including Type Test

charges and mandatory spares named port of destination offered from outside

the Employer's country, plus the cost of local transportation, insurance covers,

installation and other services required under the contract. The Employer's

comparison will also include the costs resulting from application of the evaluation

procedures .However, the Price of recommended spare parts quoted in Price

Schedule No. 6 shall not be considered for evaluation of Bids.

The Employer's evaluation of a bid will take into account, in addition to the bid

prices indicated in Price Schedules Nos.1 through 4 (with summary in Schedule

No.5) along with the corrections pursuant to ITB , the following costs and factors

that will be added to each Bidder's bid price in the evaluation using pricing

information available to the Employer

(a) The cost of all quantifiable deviations and omissions from contractual and

commercial conditions and the Technical Specifications as identified in

Attachment 6 to the Bid.

Apeejay Institute of Technology School of Management Page 54

Page 55: Abhinay Project Report

(b) Compliance with the time schedule to the Form of Contract Agreement

and evidenced as needed in a milestone schedule provided in the bid

(c) The functional guarantees of the facilities offered.

(d) The extra cost of work, services, facilities etc., required to be provided by

the Employer or third parties.

(e) Price Preference.

FUNCTIONAL GUARANTEES OF THE FACILITIES

(1) Bidders shall state the functional guarantees (e.g. performance,

Efficiency, consumption) of the proposed facilities in response to the Technical

Specifications. In case a minimum (or a maximum, as the case may be) level of

functional guarantees is specified in the Technical Specifications for the bids to

be considered responsive, bids offering plant and equipment with such functional

guarantees less (or more) than the minimum (or maximum) specified shall be

rejected.

2) For the purpose of evaluation, the adjustment specified in the Bid Data Sheet

will be added to the bid price for each drop (or excess) in the responsive

functional guarantees offered by the Bidder, below (or above) either a norm of

100 or the value committed in the responsive bid with the most performing

functional guarantees, as specified in the Bid Data Sheet. The Adjustment

Factors shall be converted to such currency as specified in Bid Data Sheet

WORK, SERVICES, FACILITIES ETC., TO BE PROVIDED BY THE EMPLOYER

Where bids include the undertaking of work or the provision of services or

facilities by the Employer in excess of the provisions allowed for in the bidding

documents, the Employer shall assess the costs of such additional work,

services and/or facilities during the duration of the contract. Such costs shall be

added to the bid price for evaluation

Apeejay Institute of Technology School of Management Page 55

Page 56: Abhinay Project Report

PRICE PREFERENCE

Any adjustments in price that result from the above procedures shall be

added, for purposes of comparative evaluation only, to arrive at an "Evaluated

Bid Price." Bid prices quoted by Bidders shall remain unaltered.

The method of evaluation is illustrated below

ILLUSTRATIVE METHOD OF EVALUATION

Quoted Bid Price without taxes

& Duties (after considering

Arithmetical errors)

ClF price including Type Test charges N1

+ Inland transportation including inland transit

Insurance for equipment and mandatory spares

(b) Ex-works price including

Type Test charges + in- N2

land transportation including

inland transit insurance for

equipment and mandatory spares

(c) Price for Installation Services N3

(d) Total price N=N1+N2+N3

Cost compensation

- Technical R

Apeejay Institute of Technology School of Management Page 56

Page 57: Abhinay Project Report

Cost compensation

- Commercial T

4 Deficiency in mandatory spares V

5 Adjustment works of Functional

Guarantee X

6 Additional work of employer Z1

7 Price preference PP= 0.15 x CIF

CIF value of import content of ex-work price quoted in schedule -2, shall be the

value of import content declared by Bidder in Attachment -9 to bid in respect of

plant and equipment including mandatory spares to be manufactured or

fabricated within the Employer’s country and quoted on Ex-works (India) basis.

8 Evaluated Bid Price EP1= (N+R+T+V+X+Z1+PP)

PRICE PREFERENCE

For granting price preference, the bid price of all bidders shall be increased by

fifteen percent (15%) of the CIF component contained in the bid.

Bidders seeking qualification on the basis of collaboration with manufacturer(s) of

particular equipment (s) are required to quote the price of such equipment(s)

including spares on CIF (Indian port-of-entry) basis, if the items are to be

imported by the manufacturer or the bidder. In case, such equipment and spares

are not quoted by the bidder on ClF basis, then Employer shall assess the CIF

(Indian port-of-entry) price of such equipment and mandatory spares for the

purpose of evaluation and the total bid price will be increased by 15% of such

assessed CIF price also for the purpose of granting price preference.

Apeejay Institute of Technology School of Management Page 57

Page 58: Abhinay Project Report

PERFORMANCE SECURITY

Within twenty-eight (28) days after receipt of the notification of award, the

successful Bidder shall furnish. The performance security for ten percent 10% of

the Contract Price and in the form provided in the section -Forms and

Procedures of the bidding documents or in another form acceptable to the

Employer.

In case Joint Deed(s) of Undertaking by the Contractor along with his

associate(s)/collaborator(s) form part of the Contract, then, unconditional Bank

Guarantee(s) from such associate(s)/collaborator(s) for amount(s) specified in

Sid Data Sheets shall be furnished within twenty eight (28) days after Notification

of Award. These Bank Guarantees shall be furnished in the form provided in the

section "Forms and Procedures· of the bidding documents and shall be valid till

such period as specified in the corresponding format for Deed of Joint

Undertaking.

In case of a successful foreign bidder, if the Employer accepts to enter

into the Second Contract and I or Third Contract with the Assignee, pursuant to

ITS Sub-Clause 28.4 above, then, within twenty eight (28) days after Notification

of Award, assignee shall furnish additional performance security for ten percent

(10%) of the value of the Contract entered into with assignee and the form

provided in the section "Forms and Procedures· of the bidding documents.

ADJUDICATOR

Adjudicator under the contract shall be appointed by the Appointing

Authority as mentioned in the Bid Data Sheets.

The adjudicator shall be paid fee plus reasonable expenditures incurred in

the execution of its duties as Adjudicator under the contract. These costs shall be

divided equally between the Employer and the Contractor

SPARE PARTS PROCUREMENT

Apeejay Institute of Technology School of Management Page 58

Page 59: Abhinay Project Report

Most or the NTPC procurements are related to equipment. On an average the

average economic life of a NTPC owned plant is considered to be 25 years and

depreciation is taken into account considering these 25 years. Hence during the

life lime of the equipment it will definitely require spares as well as some

consumables. Hence NTPC has incorporated a clause in the Bid Documents

issued to the bidders called SPARE PARTS. This clause has three sub clauses

that take care of different types of spare pans required during the lifetime of the

plant

If NTPC finds -that certain spare parts are mandatory for the plant operation, it

specifies so in the Technical specification. In such cases, the item wise price

breakdown of such spares on a ClF (India Port)/Ex Work's (India) basis is to be

included in the bid by the bidder. However these prices will be free form

escalation and should be indicated separately. The prices of spare parts shall

also come into picture while evaluating the bid. During the six months starting

from signing the contract, NTPC will have the right to increase or decrease the

number of spare parts to be procured. In addition, the bidder may by his own

experience provide a complete list of recommended spare parts for an

operational period of three (3) years for the equipment supplied. "The list should

be complete providing the details of how many of the suggested spare parts are

present in the equipment supplied as well as their expected operational life. The

bidder shall further indicate item wise price break-up on for site basis. The prices

quoted in the list shall be valid without any escalation for a period of not less than

six (6) months after the placement of order for Power Plant Turnkey Equipment

Basis. But this additional recommended spare parts list will not be taken into

consideration while evaluating the bid. However a specific clause in the General

Condition of Contract makes the supplier provide a list of addresses of all the

sub-supplier who provide the spare parts. The clause is "The Contractor will

provide the Owner with all the addresses and particulars of his sub-suppliers

while placing the order on vendors for items/components/equipment covered

under the Contract and will further ensure with his vendors that the owner, if so

desires, will have the right to place orders for spares directly on them on mutually

agreed terms based on offers of such vendors.

In addition, to cater to any exigency arising during the start-up and initial

Operation stages up to the satisfactory completion of Trial Operations due to

enfant mortality of items/components/consumable hardware, the bidder shall at

Apeejay Institute of Technology School of Management Page 59

Page 60: Abhinay Project Report

his own cost shall arrange and maintain an inventory of such items so as not to

have any major interruptions during the period from start up to Trial Operations.

PROCUREMENT OF FOREIGN SPARE PARTS

Many of the plants of NTPC are manufactured by foreign manufacturer. Hence

during the lifetime of the equipment, it may require many spares parts and

consumables. But to acquire these spare parts .there is no specific method

followed by NTPC. However in such a case the list of authorized agents of

manufacturer producing the parts is obtained from the manufacturer itself. If the

listed dealer is only supplier of manufacturer, the procurement is made through

single tender .Else a normal procurement procedure is followed.

For example a plant monitoring equipment was in need of batteries and a

connecting cable. Both the items were proprietary in nature and the firm had only

one authorized dealer providing the required material. Hence the dealer was

issued a single tender for supplying the required spares. Similarly in case of a

Diesel Generator Set which was manufactured by a US firm had only one

authorized service provider in the locality and hence a price list for the

components used in the DG Set was acquired from the manufacturer and the

contract was awarded to the sole service provider. In case of bigger value spare

parts a three year supply of the spare parts is guaranteed by the supplier at the

time of supplying the equipment and for further requirement of the spares the

vendor may be contacted or a global tender may be issued high value spares not

manufactured by any Indian firm or being imported by an Indian firm.

However the payments for both the types of spares will be made in following

manner,

Upon dispatch and against invoices and shipping documents :75%

On receipt and storage at Site on physical verification by the engineer: 25%

PAYMENTS:

Payment is the most important term for any contract. Hence the General

Condition of Contract deals the terms of payment. There arc various sub clauses

Apeejay Institute of Technology School of Management Page 60

Page 61: Abhinay Project Report

to this clause. The first clause deals with the currency of payment. The clause

specifically mentions that “the Contract Price shall be paid in the currency or

currencies in which the various price components have been stated and as

incorporated in the Contract”. Once the currency is settled and accepted by both

parties, the due date for the payment must be decided in advance. The payment

is generally made in parts. Once the contract is awarded, an Initial Advance

payment is made to the Contractor and afterwards payments against dispatch,

progressive completion of works and then a final payment is made to the

contractor. Whenever a payment has to be made it is divided into two parts (if

applicable), the Indian Rupee component and foreign currency component. The

due date for initial foreign currency component for the advance payment is 60

days from the award of the contract and 30 days for the Indian rupee component.

The Initial Advance payment is done automatically however the payments

against dispatch and payments against partial work completion are made after

the contractor applies for it. Once the contractor applies for payments, the validity

of the application is checked and the invoices or completion report by the

engineer is sought. This report is known as Interim Payment Certificate and it

certifies the value of the contract executed till the date of completion. However if

any part of the work completed docs not comply with the Contract or has been

done prematurely according to the master schedule provided at the time of the

contract, the NTPC shall not pay for that part of the work.

MODE OF PAYMENT: All the payment on the dispatch will be made in form of

Letter Of Credit (L/C) in favor of the contractor. The issue of Letter of Credit shall

be valid for a period of three months from the date of issue. The utilization of this

L/C however is sole responsibility of the contractor. Once the good is received at

the site and possession is taken by NTPC only then the payment will be made to

contractor’s Banker through Owner’s bank.

The payment for advance, Taxes and duties inland transportation, insurance and

erection portion of works and Type test charges (if any) will be directly made to

contractor.

PART PAYMENT: When NTPC agrees to pay the contractor in part with each

additional phase of plant completion, or each new lot of equipments/ material

received follows a payment schedule and regulation to make the payment. This

schedule is arrived at by analyzing the various component required in the

Apeejay Institute of Technology School of Management Page 61

Page 62: Abhinay Project Report

delivery of the equipment / material received or dispatched or it may issue at

advance made to contractors supplies for the procurement of the

equipment/material. For analysis purpose we have taken the schedule that has

been used for TANDA Thermal Power Station.

NATURE OF

PAYMENT

% OF TOTAL

EX-WORK

PRICE OF

EQUIPMENT

% OF EX-WORK

PRICE ON PRO-

RATA BASIS

CONDITION OF

PAYMENT

a) Initial Advance

b) Pro-rata

payment against

dispatches

c) Pro-rata

payment on item

received

d) On successful

completion of

performance and

guarantee test

10%

------------------

--------------------

10%

-------------------

60%

20%

-------------------

In ref. to GCC

On producing

invoice and

satisfactory

evidence.

Physical

variation &

certificate by

Engineer of test

results.

The owner will reimburse all the taxes and duties applicable to material

purchased by the NTPC in full once the dispatch of the equipment is proved with

enough documentary evidences. However the payments for the inland

transportation and insurance will be paid only after the material is received at the

site by owner. As far as the type-test charges are concerned, it will be paid in full

Apeejay Institute of Technology School of Management Page 62

Page 63: Abhinay Project Report

after successful completion of the test. However the owner reserve the right to

waive off any or all Type Test and all the cost of the test shall be deducted form

the total value of the contract as per rate mentioned in the Bid Proposal Sheet.

ESCALATION FACTORS:

Escalation factors or Contract Price Adjustment is an Endeavor to protect the

interest of the contractor as well as that of NTPC. The escalation factor is a

derived value by which the prices of materials vary or may vary on some date in

future. The clause is a very detailed. Clause and covers every aspect of the

price.

For the price adjustment purposes, only following components will be considered.

Ex-factory price for the equipment / material for the Indian origin and FOB price

component for the equipment / material of non-Indian origin (excluding spares)

subject to ceiling of 20%. In case of Indian contractor, for any equipment /

material etc. imported by him for the purpose of performance of the contract,

which is dispatched directly from the port of disembarkation to the site the words

“ ex-factory price” shall be deemed to mean the price of equipment / material as it

is dispatched from the port of disembarkation to the project site.

ERECTION COMPONENT

For the escalation of price in case of equipment / material, all the ex-factory

prices will be fragmented as Fixed Portion of price and the variable portion of the

price .The variable portion of price, assume to fluctuate with the changing labor

and material indices. The indices are obtained from the list of industrial Indices

published by the Ministry of Industries, Ministry of Labor and the Office of the

Economic Adviser, Govt. of India. Labour Bureau, Simla, publishes the labour

index or Consumer Price Index for Industrial Workers whereas the Economic

Apeejay Institute of Technology School of Management Page 63

Page 64: Abhinay Project Report

Adviser of the Govt. of India publishes the Material Index, or Index no of

wholesale price under group "All Commodities"

Hence based on the above-mentioned indices and price components, the

escalation will be calculated as illustrated below.

PRICE ADJUSTMENT FOR Ex-FACTORY /FOB PRICE OF EQUIPMENT

Let us assume that dEC is the escalated price component and ECo is the original

price. EC1 is the adjusted Ex factory price.

Hence

dEC= EC1 – EC0

a A1 x f1 b B1 x f2 cC1 x f 3 l L1 x f1

EC1= EC0 x {F + + + +---------------+ }

A B C L0

A, B, C etc. = Published price indices of corresponding Major material / items

such indices shall necessarily be in the country of origin of goods.

.

L = Labour index.

l

F = Fixed portion of Ex- factory Price / FOB price component of

equipments

a ,b, c, etc. = Coefficient of major materials involved in the ex-factory /FOB price

of the equipment / material expressed as component of contract price.

L = co-efficient of Labor component in Ex-factory / FOB price of the

equipment / Material

Apeejay Institute of Technology School of Management Page 64

Page 65: Abhinay Project Report

f1, f2, f3 etc = Exchange rate correction factor for respective material and f1 is

the ex-change correction factor for labor with reference to the currency of the

country of index and respective contract currency such that

Zo

f =

Z1

Where Z is the number of units of currency of the country of origin of the index,

which is equivalent to one unit of respective contract currency.

PRICE ADJUSTMENT FOR ERECTION COMPONENT:

For Indian rupees component of Erection Price.

dER =ER1-ER0

And ER1=ER0 * (0.15 +0.85 F1/F0)

b) For Foreign Currency portion of Erection Price.

dEE =EE1-EE0

And EE1=EE0 * (0.15 +0.85 EF1/EF0 x f)

Apeejay Institute of Technology School of Management Page 65

Page 66: Abhinay Project Report

F = Indian Field Labour Index- namely All India Consumer Price Index for

Industrial. Workers, as published by Labour Bureau, Simla of the Government of

India.

EF =Index for Expatriate Field Labour component of the erection work as

agreed in the Contract.

f = Exchange rate correction factors for respective materials and 11 is the

exchange rate correction factor for labour with reference to the currency of the

country of index and the respective contract currency such that ;

Zo

f =

Z1

Where Z is the number of units of currency of the country of origin of the index,

which is equivalent to one unit of respective contract currency

Note:

Subscript zero '0' will correspond to thirty days prior to the date of bid opening in

all cases and date of bid opening in case of ZO.

Subscript one' I' will correspond to the billing period.

iii) The price variation calculated by above formula will not be subject to any

ceiling unless specified in the Special Condition of Contract.

3. PRICE ADJUSTMENT FOR CIVIL WORK COMPONENTS

All the prices quoted by the bidder shall be the Base Prices which will· be

subjected to Price Adjustment. A fixed component of the civil work price will be

Apeejay Institute of Technology School of Management Page 66

Page 67: Abhinay Project Report

firms and sans any price adjustment. Balance portion will be subjected to price

adjustment. The' adjustment will be calculated as followed:

dCV = CV1-CV0

Lb L1f1 m M1 f2 d D1 f3

CV1= CV0 x (F + + +)

L0 M0 D0

F = Fixed Portion of the Ex factory Price/FOB component of the equipment.

(The value may change from project to project).

m = Material component of the contract price.

d = High Speed Diesel component of the contract price.

L = Labour Index which shall be index number of consumer price index for

industrial workers as published by Labour Bureau or India in their monthly

bulletin entitled INDIAN LABOUR JOURNAL.

Lb = Labour component of the contract priced

M = Material Index which will be Index number of wholesale price under group

all commodity as published by Ministry of Industry from the country of Origin.

D = High Speed Diesel price per litre, which will be price of high -speed diesel at

the Indian Oil Corporation retail outlet nearest to project.

f1, f2,f3 = exchange rate correction factor for labour with reference to the

currency of the country of index and the respective contract currency such that

Zo

f =

Z1

Apeejay Institute of Technology School of Management Page 67

Page 68: Abhinay Project Report

Where Z is the number of units of currency of the country of origin of the index,

which is equivalent to one unit of respective contract currency.

Notes:

Subscript '0' refers to the value of the above mentioned labour/material indices

for diesel price as on 7 days prior to the date of opening the bids.

Subscript 'I' refers to the values of corresponding labour/material indices or diesel

or diesel price as applicable for the month prior to the month in which the work is

executed.

ii) The total Price Adjustment amount shall not exceed 15% in any case.

TOTAL ADJUSTMENT TO CONTRACT PRICE:

To calculate the total adjustment required to be done in the contract –price,

we sum up all the item wise price adjustment and are applied to the total

contract price in order to get the exact value of the contract on the date of the

evaluation or for making the payments.

Total Price Adjustment = dEC+dER+dEE.

The price adjustment for various components of the contract is thus derived thus

derived is then applied to the contract price and a suitable and practical price is

obtained from the historical cost data available. This adjustment is highly project

specific because the percentage of the various components used in the project

changes. Hence every time a new project is executed, a new set of price

adjustment is arrived at by using the formulae discussed above and putting the

actual figure of the materials to be used by the project.

ARBITRATION

Apeejay Institute of Technology School of Management Page 68

Page 69: Abhinay Project Report

Despite all the care taken and all the irregularities avoided there are times when

the relationship between the supplier and purchaser becomes bitter. In that case

to avoid any legal complications a set of arbitration rules are laid down and

agreed upon in advance. These rules are indisputable and are accepted by both

the parties. Some of the important arbitration clauses are mentioned here.

1) In the event of any query, dispute or difference whatsoever arising under this

contract or in connection with any question relating to existence, meaning and

interpretation of [his contract or any alleged breach thereof, the same will be

referred to the sole arbitrator of the General Manager of the NTPC or to a person

appointed by him for the purpose. The arbitration shall be conducted in

accordance will the provisions of Indian Arbitration Reconciliation Act, 1996

2) It will be no objection that the Arbitrator is an interested person and/or that he

had to deal with the matters to which the contract relates and/or in the course of

his duties he expressed any view on any mutter in dispute. The award of

arbitrator shall be final and binding.

3) In the event of Arbitrator dying, neglecting, resigning or being unable to act for

any reason or his award being set aside by the court for any reason, it will lawful

for the General Manager of the NTPC to appoint another Arbitrator in place of the

outgoing Arbitrator.

4) It is further terms of this agreement that no person other than the person shall

act as an Arbitrator and that, if for any reason that is not possible, the matter

should not be referred to arbitration at all.

5) The Arbitrator may from time to time, with the consent of nil parties enlarge the

time ill making the award.

6) The cost incidental to the arbitration shall be at the discretion of the Arbitrator;

the arbitration shall be conducted in NEW DELHI or at such other places where

arbitrator may decide.

Apeejay Institute of Technology School of Management Page 69

Page 70: Abhinay Project Report

7) Not withstanding any dispute between the parties Supplier shall not be entitled

to withhold delay or defer his obligation under the contract and same shall be

carried out strictly in accordance with terms and condition of contract.

8) In the event of dispute or difference arising between parties the public sector

enterprise and Government, the provision of BPE office memorandum No

BPE/GL001/76/MAN/2110-75-BPE (GML-1) dated 1st January 1976 shall be

applicable.

ILLUSTRATING ON TENDERING

Apeejay Institute of Technology School of Management Page 70

Page 71: Abhinay Project Report

SUB: EVALUATION REPORT FOR FIRE PROTECTION SYSTEM PACKAGE

FOR STPP, STAGE II (2X500 MW)

1.0 BRIEF SCOPE OF THE WORK

The scope of work for the subject package includes design, engineering,

compliance with statutory requirements and obtaining clearances from

statutory authorities, wherever required, manufacture, inspection and

testing at manufacturer’s work or supplier’s work, packaging and

transportation from the manufacturers work to the site including customs

clearance and port clearance, port charges (if any), insurance, receipt,

unloading, handling, storage and in plant transportation at site, fabrication

at site, fabrication, pre assembly (if any) installation, testing and

commissioning including successful completion of trial operation and

performance and guarantee testing of fire protection system complete with

all associated civil works including furnishing of spare at site, reconciliation

with customs authorities (in case of foreign bidders) as per specifications

and scope defined in bidding documents.

2.0 FINANCING

The subject package is envisaged to be financed through external

borrowing, Internal and other sources.

Apeejay Institute of Technology School of Management Page 71

Page 72: Abhinay Project Report

3.0 COST ESTIMATE

The approved cost estimate for the subject package is rs.2363.74 lakhs

including CST and service tax

4.0 INVITATION FOR BID & BID RESPONSE

4.1 The bids for the subject package were invited under international

competitive bidding (ICB) procedures. The abridged Invitation for

Bid (IFB) was published in leading newspapers during third week of

May’2006 and Indian Trade journal on 9.6.2006. The detailed IFB

was displayed on internet.

4.2 As per the provisions of IFB, the bidding documents were on sale

from 18.05.2006 to 19.06.2006. in the response the following 9

parties had purchased the bidding documents:

M/S L6 New Delhi

M/S L5 New Delhi

M/S L4 New Delhi

M/S L3 New Delhi

M/S L2 Mumbai

M/S L7 Germany

M/S L8 Dubai

M/S L1 ltd. Japan

M/S L9 ltd.

As per the provisions of IFB, the bids were scheduled to be

opened on 14.7.2006. however, in view of requests received from

prospective bidders and issuance of various amendments or

clarifications to bidding documents, the bid opening date was

extended to 4.8.2006. The bids were finally opened on 11.8.2006 in

the presence of representative of the bidders who chose to attend.

Out of nine parties who had purchased the bidding documents, the

bid were received from following 5 parties:

I. M/s XYZ ltd., Japan (XYZ)

Apeejay Institute of Technology School of Management Page 72

Page 73: Abhinay Project Report

II. M/s ABC Ltd, Mumbai (ABC)

III. M/s PQR ltd, New Delhi (PQR)

IV. M/s UVW, New Delhi (UVW)

V. M/s LMN Ltd., Chennai (LMN)

5.0 Quoted Prices

5.1 the prices quoted (considering rebates/discounts, wherever applicable) by all

the participating bidders are bought out below:

S.NO Name Of the

Bidder

Total Quoted Price

without

discount/rebate

Discount Offered Net Quoted Price

after considering

the discount

1 L1 XYZ US $ 761592.57

+ Rs 262826314

9.2% on sch2

price of Rs

202117467

*269782648

2 L2 ABC Rs. 279016673 Nil 279016673

3 L3 PQR Rs. 352187305 19.5% on

Rs.343194705

285264337

4 L4 UVW Rs. 287895809 Nil 287895809

5 L5 LMN Rs. 297250000 Nil 297250000

Exchange rate of US $ = Rs 45.81 i.e. SBI BC selling rate as on 11.8.05 has

been considered.

5.2 The break up of prices as quoted by all participating bidders along with

details of discount is brought out in Annexure VI of every document

submitted.

6.0 Preliminary Evaluations of Bids

BID SECURITY

As per the provisions of ITB clause 12 & BDS Item no. 4 each bidder is

required to furnish a bid security for an amount equivalent to Rs.

47,28,000/- in currency of bid or in US dollars, which should be valid for

Apeejay Institute of Technology School of Management Page 73

Page 74: Abhinay Project Report

the period of 45 days beyond original bid validity period i.e. 225 days

from the date of bid opening (225 days from bid opening works out as

24.3.2007)

all the bidders who have participated in the bidding have furnished the bid

security, for the amount and in the form specified in the bidding documents.

However, the validity of bid security furnished by PQR and UVW are 6 days and

51 days short of the specified period to other bidders. The details of Bid security

submitted by all the 5 participating bidders are brought out at annexure V of the

bid submitted by bidders. As the shortfall in the validity of the bid security is

marginal, the bid security of PQR and UVW were accepted.

acceptance of important conditions

as per the clause ITB 21.5, no deviations whatsoever to the following provisions

of the bidding documents is permitted by the employer and the bidders are

required to give a certificate in the format as specified in bidding documents for

having taken no deviation to these conditions along with their bid. This clause

further stipulates that any bid not accompanied by such certificates shall be

rejected by the employer and returned to the bidder without being opened:

governing laws (clause 5 of GCC)

settlement of disputes (clause 6 of GCC)

terms of payments (clause 12 of GCC)

performance security (clause 13 of GCC)

performance security for deed of joint undertaking (clause

13.1 of GCC)

Taxes and duties (clause 14 of GCC)

Completion Time Guarantee (clause 26 of GCC)

Defect Liability (clause 27 of GCC)

Functional Guarantee (clause 28 of GCC)

Patents Indemnity (clause 29 of GCC)

Limitations of Liability (clause 30 of GCC)

All the five bidders have furnished the certificate confirming their acceptance to

the aforesaid important conditions.

Apeejay Institute of Technology School of Management Page 74

Page 75: Abhinay Project Report

BID VALIDITY

the bids submitted by all the bidders are valid for a period of 180 days from the

date of bid opening as called for in the bidding documents.

PRICE BASIS

as per clause 10.7 of ITB prices quoted by the bidder shall be subject to

adjustment during performance of the contract to reflect changes in the cost of

labor, material etc. in accordance with the procedures specified in appendix 2 to

the form of contract agreement.

Further as specified a bid submitted with a fixed price quotation will not

be rejected, but the price adjustment will be treated a zero. The price

adjustment provision will not be taken into consideration in bid

evaluation. Bidders are required to indicate details in bid submitted by

them in attachment 17 of the bid.

As may be seen from the para 6.2 above, all the bidders have confirmed their

acceptance to the specified provision on price adjustment while submitting the

required certificate.

POWER OF ATTORNEY

All the bidders are required to enclose power of attorney to sign the bid.

And same has been done by all the 5 bidders to the contract.

completeness of the bids

As per the clause mentioned in ITB bidders were required to complete the bid

form and the appropriate price schedules & attachments. All the bidders have

furnished the relevant schedules & attachments. However, in certain schedules &

attachments details or the required break up have not been furnished by the

bidders.

Bids of all the five bidders generally cover the complete scope of work except

certain deviations and other discrepancies.

ARITHEMATICAL ERRORS

As per the one of the clause in ITB of bidding documents, arithmetical

errors are rectified on the following basis.

Apeejay Institute of Technology School of Management Page 75

Page 76: Abhinay Project Report

Quote

If there is discrepancy between the unit price and the total price, which is

obtained by multiplying unit price and quantity or between subtotal and

the total price, the unit or sub total price shall prevail and the total price

shall be corrected. If there is a discrepancy between words and figures

the amount in words will prevail. If the bidder does not accept the

correction of errors, its bid is rejected and the bid security is being

forfeited in accordance with clause in ITB.

Unquote

6.7.2 it may be noted that no arithmetical error was observed in the bid

XYZ, however certain arithmetical errors was observed in the bids of rest

of 4 bidders i.e. UVW,ABC,POR,LMN. The details of the arithmetical

corrections are as follow:

6.7.2.1 Arithmetical error in the bid ABC

There was no error in the schedule 1, schedule 2 and schedule 3.

however, schedule 4 when the installation price was calculated by

multiplying unit rate with specified quantity, there was an error of Rs.

+585/- , further there was totaling error of Rs. (-) 357/- in schedule 4 and

accordingly the total arithmetical error observed in ABC’s Bid workout to

be +228.

6.7.2.2 Arithmetical error in the bid PQR

Arithmetical errors was observed in bid PQR in respect of certain items,

which have been corrected by multiplying the unit rate with specified

quanity, to arrive at the corrected price. It was observed that the total of

schedule 2 price worked out to Rs 27,67,75,390/- instead of Rs

27,77,03,635 as indicated in PQR. Similarly the total price of schedule 4

worked out to Rs.7,56,42,359/- instead of Rs.6,54,91,070/- as indicated

by PQR. After considering the rebate of 19.5% the total arithmetical error

observed in PQR’s bid worked out to + Rs 74,24,551/-

6.7.2.3 Arithmetical error in the bid of UVW

It was observed that there was no error in quoted price in schedule 1,

schedule 2 and schedule 4 of the bid of UVW; however, there was

totaling errors in schedule 3. The total price for schedule 3 worked out to

Apeejay Institute of Technology School of Management Page 76

Page 77: Abhinay Project Report

be Rs 1,19,20,286/- instead of Rs 1,13,92,092/- thus the total arithmetical

error observed in UVW’s bid worked out to be + Rs 5,28.194/-

6.7.2.4 Arithmetical errors in the bid of LMN

Arithmetical errors was observed in bid of LMN in respect of certain

items, which was corrected by multiplying the unit price and specified

quantity, to arrive at the corrected price. In schedule 1, the total price for

main equipment and spares worked out to Rs 41755896 instead of

46120135 as stated by the bidder. In schedule 2 the total price of main

equipment and spares worked out to be Rs 225796948 and Rs 12266574

instead of Rs 225229631 and Rs 13595020 as indicated by the bidder.

Further the installation price indicated in schedule 4 worked out to be Rs

27949012/- instead of Rs 34084462/- as stated by bidder. Accordingly

total arithmetical error worked out to be (-) Rs 1,12,60,818/-

6.7.2.5 The computed price of all the bidders after considering the

arithmetical correction is given below:

s.no. Name of

the bidder

Total quoted price after

considering discount

Arithmetical

error

Total computed

price

1 L1 XYZ 26,97,82,648 NIL 26,97,82,648

2 L2 ABC 27,90,16,673 + 228 27,90,16,901

3 L3 PQR 28,52,64,337 +74,24,551 29,26,88,888

4 L4 UVW 29,72,50,000 -12,60,818 28,59,89,182

5 L5 LMN 28,78,95,809 +5,28,194 28,84,24,003

7.0 PRICE PREFRENCE

7.1 As per the clause mentioned in ITB for granting the price preference

the bid price of all the bidders was increased by 15% of the CIF

component contained in the bid.

Apeejay Institute of Technology School of Management Page 77

Page 78: Abhinay Project Report

7.2 The bidders are required to indicate the CIF value of import contents

of supply to be made by the bidders and its assignee (if applicable)

including its sub contractors or sub vendors. This is mentioned in the

attachment 9 of bid form.

7.3 The CIF content as indicated by the bidders in their bids is as follow:

S.No. Name of

the Bidders

CIF value of Import Content In

bid Currency

(In Sch I) In attch. 9

Total CIF value of

Import Content in

Equivalent Indian

Rupees. (Rs.)

1 XYZ US$761592 *US$761592 71102282

2 ABC Rs. 42502173 * 42502173 85004346

3 PQR - US$648280 30261710

4 UVW Rs. 55353736 - 55353736

5 LMN 46120135 NIL 46120135

It may be noted that amount indicated in schedule I was indicated in

attachment 9 also by both XYZ & ABC. Intentions of the bidder is not

clear ,however, for the purpose of evaluations import content indicated in

schedule I and attachment 9 was considered for the purpose of

evaluations. This aspect was discussed and ties up suitably with the

bidder in case of award.

Apeejay Institute of Technology School of Management Page 78

Exchange Rate Considered : 1 USD = Rs. 46.68 SBI BC selling rate as on OBD i.e. 11.8.2005

Page 79: Abhinay Project Report

7.4 Based on the above, price preference was worked out as 15% of the CIF

value of the import content and the same was considered for the evaluations as

under:

s.no. Name of the

bidder

Total CIF value of the import

content in Indian Rupees

Price Prefrence

1 XYZ 71102282 10665342

2 ABC 85004346 12750652

3 PQR 30261710 4539256

4 UVW 55353736 8303060

5 LMN 46120135 6918020

8.0 preliminary evaluated prices

8.1 considering the quoted prices, arithmetical corrections and the price

preference, the preliminary evaluated prices of the all bidders are as follows:

(All figures in Indian Rupees)

S.No. Name of

the bidder

Total quoted Price

(after arithmetical

corrections)

Price Preferences Preliminary

Evaluated price

1 XYZ 26,97,82,648 1,06,65,342 28,04,47,990

2 ABC 27,90,16,901 1,27,50,652 29,17,67,553

3 PQR 28,59,89,182 69,18,020 29,29,07,202

4 UVW 28,84,24,003 83,03,060 29,67,27,063

5 LMN 29,26,88,888 45,39,256 29,72,28,144

8.2 Short Listing

It is visible from para 8.1 above that the preliminary evaluated price of UVW,

PQR and LMN are substantially higher as compared to preliminary evaluated

price of other two bidders i.e. XYZ and ABC. As such the bids of the lowest two

bidders i.e. XYZ and ABC has been taken up for the detailed evaluations.

Apeejay Institute of Technology School of Management Page 79

Page 80: Abhinay Project Report

9.0 detailed evaluation

9.1 The detailed commercial and technical evaluation of the bids submitted by

XYZ and ABC was carried out in accordance with the stipulations of bidding

documents and was presented in section II & section III of this evaluation report

entitled commercial evaluation report and technical evaluation report

respectively.

9.1.1 as per clause 8.3 (f) of bidding documents, in case of any deviations to the

provisions of bidding documents, the bidders are required to list the deviations

only in attachment 6 to the bid form. The stipulation of the bidding documents in

this regard is quoted below:

Quote:

Deviations, if any, from the terms and conditions of the bidding documents or

technical specifications was listed only in attachment 6 to the bid. The bidder

shall also provide the additional price. If any, for withdrawal of the deviations.

However, the attention of the bidders is drawn to the provisions of ITB sub clause

21 regarding the rejection of bids that are not substantially responsive to the

requirements of the bidding documents.

Bidders may further note that expect for deviation listed in attachment 6, the bid

shall be deemed to comply with all the requirements in the bidding documents

and the bidders shall be required to comply with all such requirements of bidding

documents and technical specifications without any extra cost to the employer

irrespective of any mention to the contrary, any where else in the bid, failing

which the bid security of the bidders may be forfeited.

At the time of award of the contract, if so desired by the employer, the bidder

shall withdraw these deviations listed in attachment 6 at the cost of withdrawal

stated by him in his bid. In case the bidder does not withdraw the deviations

proposed by him , if any, at the cost of withdrawal stated in the bid, his bid will be

rejected and bid security forfeited.

Unquote

9.1.2 Accordingly, the deviation listed by bidder in attachment 6 has been

considered for evaluation and have been cost compensated, wherever required.

The other deviations or observations or variations though not listed in attachment

Apeejay Institute of Technology School of Management Page 80

Page 81: Abhinay Project Report

6 but elsewhere in the bid have been listed in relevant annexure of commercial

evaluation report i.e. section II and technical evaluation report (section III), for

recommended bidders only.

However, no cost compensation has been considered on account of the

deviations not stated in attachment 6 as these will be required to be withdrawn

by the bidders without cost implications in line with the bid conditions.

9.2. Detailed commercial evaluations

The detailed commercial evaluations of XYZ and ABC are presented in section II

entitled commercial evaluation report. Salient points of commercial evaluation in

respect of the deviations observed in the bids are presented here under:

9.2.1 XYZ

Bidder has not taken any commercial deviation in this attachment 6 and

accordingly as may be seen from the details enclosed in annexure IIA of section

II no cost compensation has been considered for the purpose of evaluation.

9.2.2 ABC

Bidder has not taken any commercial deviation in this attachment 6 and

accordingly as may be seen from the details enclosed in annexure IIA of section

II no cost compensation has been considered for the purpose of evaluation.

9.3 detailed technical evaluation

9.3.1 XYZ

The detailed technical evaluation of the bid of XYZ and ABC is presented in

section III of this evaluation report entitled “technical evaluation report”. Salient

points of technical evaluation in respect of the deviations observed in the bids are

presented hereunder been considered for the purpose of evaluation.

The mandatory spares and types tests offered by XYZ are generally in line with

the specification requirement.

9.3.2 ABC

The technical details of fire detection & protection system package offered by

XYZ are generally in line with specification requirements. Bidder has not taken

Apeejay Institute of Technology School of Management Page 81

Page 82: Abhinay Project Report

any technical deviation in this attachment 6 and accordingly no cost

compensation has been considered for the purpose of evaluation.

Certain deficiencies with respect to mandatory spares have been observed and

the same are also listed in annexure IID section III of this evaluation report. Price

implication due to scope of deficiency of mandatory spares work outs to be Rs.

9,76,165/-

9.4 quality assurance

It has been observed from the attachment 6 furnished by XYZ and ABC that they

have not taken any deviation on quality assurance issues. Further, evaluation of

the bid of afore mentioned two bidders have been carried out and is discussed in

Technical Evaluation Report, section III.

10.0 Work Schedule

10.1 as per the item number 9 of bid data sheets in bidding documents, the

completion of facilities (including trial operations) has been specified as 26

months from the date of notification of award for unit 4 and 31 months for unit 5

respectively.

10.2 The work schedule quoted by XYZ and ABC in attachment 16 is in line with

the schedule mentioned above. The detailed work schedule shall be discussed

and finalized with successful bidder.

11.0 FINAL EVALUATED PRICES

11.1 Based on the detailed evaluation of bids of XYZ and ABC, the final

evaluated prices of these bidders’ works out as under:

(All figures are in Rupees)

S.No. Description XYZ ABC

1 Preliminary Evaluated Price 28,04,47,990 29,17,67,553

2 Cost Compensations NIL NIL

3 Commercial NIL NIL

4 Technical NIL NIL

5 Deficiency in mandatory spares NIL NIL

6 Final Evaluated Price 28,04,47,990 29,27,43,718

Apeejay Institute of Technology School of Management Page 82

Page 83: Abhinay Project Report

11.2 As may be seen from the detailed evaluation at para 11.1 above, XYZ’s bid

has been found to be the lowest evaluated technically and commercially

responsive bid.

11.3 The taxes and duties as applicable for direct transaction between the

contractor and NTPC and as quoted by the bidder in schedule 7 though payable

by NTPC are not to be considered for evaluation as per the provisions of bidding

documents and accordingly, the same have not been considered in evaluation.

However, the taxes and duties quoted XYZ and ABC are as indicated below:

11.3.1 In schedule 7, XYZ have been indicated as “NONE” towards central sales

tax, local sales tax, entry tax/ octroi and any other tax or duties in their bid.

11.3.2 in schedule 7, ABC have indicated as “NIL” towards central sales tax,

local sales tax, entry tax/octroi and any other tax or duties in their bid.

12.0 Fulfillment of qualifying requirements

12.1 The following stipulations are indicated against ITB clause no. 8.3 (c) of

section II of bidding documents:

Quote:

In the absence of pre qualification, documentary evidence establishing that the

bidder is qualified to perform the contract, if its bid is accepted, shall be furnished

in attachment 3 to bid.

The documentary evidence of the bidder’s qualifications to perform the contract,

if its bid is accepted, shall establish to the employer’s satisfaction that the bidder

has the financial, technical, production, procurement, shipping, installation and

other capacities and capabilities necessary to perform the contract and meets the

experience and other criteria outlined below:

The bidder shall provide satisfactory evidence that he and/or, where applicable,

his collaborator or associate.

i) Is a supplier, from an eligible source country, who regularly

manufactures equipments of the type specified and/ or undertakes the

Apeejay Institute of Technology School of Management Page 83

Page 84: Abhinay Project Report

type of work specified and has adequate technical knowledge and

relevant experience for the works covered in the bidding documents.

ii) Does not anticipate a change in ownership during the proposed period

of execution of work (if such a change is anticipated, the scope and

effect thereof shall be defined).

iii) Has adequate financial stability and status to meet the financial

obligations pursuant to the works covered in the bidding documents.

iv) Has adequate capability and capacity to perform the work properly and

expeditiously within the time period specified. The evidence shall

specifically cover with written details the installed manufacturing and/or

fabrication capacities and present commitments (excluding those

anticipated under this specifications) of the bidder. If the present

commitments are such that the installed capacity results in an

inadequacy of manufacturing and/or fabrication capacities to meet the

requirements appropriate to the works cover in his bid, then the details

of alternative arrangement to be organized by the bidder for this

purpose and which shall meet the employer’s approval, shall also be

furnished.

v) Has an adequate field service organization to provide the necessary

field erection and management services required successfully erecting,

testing and commissioning the equipment/ systems are required by the

bidding documents.

vi) Has established quality assurance systems and organization designed

to achieve high level of equipment/ system reliability, both during

manufacturing and/ or fabrication and field installation activities.

In addition to the requirements stipulated above, the bidder should also meet

the qualifying requirements stipulated in item 3 of bid data sheets.

Unquote:

12.2 The following has been mentioned in item no.3 of bid data sheet:

In addition to qualifying requirements stipulated under section II,

instruction to bidder (ITB), the following shall also apply:

Quote:

Apeejay Institute of Technology School of Management Page 84

Page 85: Abhinay Project Report

12.2.1 The bidder should have designed, supplied, erected and

commissioned atleast 2 fire detection and protection systems

consisting of the systems described in (a), (b), (c), (d) below, in a

single contract of value not less than Rs.40 million or equivalent, in

industrial or commercial installations.

These systems must have been designed to the recommendations

of Tariff Advisory Committee of India or any other International

reputed authority and the systems should be in operating condition

for a period of not less than two years as on date of bid opening:

a. Fire hydrant system

b. Automatic high velocity water sprays or medium velocity water

spray or sprinkle system

c. Fire water pumping and pressurizing arrangement

d. Fire detection and alarm system comprising of smoke detectors

or heat detectors, interconnecting cable network and fire alarm

panels.

And

12.2.2 Bidder should have achieved an average annual turnover of Rs.

200 million or equivalent in the last three financial years.

Unquote:

12.3 As may be seen from the detailed evaluation at para 11.1 above, XYZ’s

bid has been found to be lowest evaluated bid. Accordingly, the

qualification data of XYZ has been analyzed and is presented as given

below:

12.4 Fulfillment of qualifying requirements by XYZ

The analysis of XYZ with respect to their meeting the general qualifying

requirements mentioned in clause 8.3 (c) of ITB, based on the data

furnished by them in their bid has been carried out and is presented

below:

(i) As per clause 2.2 of ITB all countries are eligible

source countries therefore XYZ is a supplier or

contractor from eligible source country. On perusal of

details furnished by XYZ in the bid and as discussed

at para 12.5.1 below, it is observed that XYZ have

executed ten fire protection packages for various

electric power companies, gas plants and other

Apeejay Institute of Technology School of Management Page 85

Page 86: Abhinay Project Report

clients and are executing fire works for fire protection.

From the above, it emerges that XYZ is a contractor

who regularly undertakes the type of work specified

and has adequate technical knowledge and relevant

experience for the work covered under the bidding

documents.

(ii) XYZ has confirmed that they do not anticipate any

change of ownership and scope during the proposed

period of execution of subject work.

(iii) It also evident from the analysis of financial data that

XYZ appeared to have adequate resources and

stability to execute the subject contract.

(iv) As per one of the clause of ITB it shows that capacity

and capabilities of XYZ has been analyzed from the

details enclosed by them in their bid. It emerged from

the analysis that XYZ has adequate capabilities to

execute the subject contract, if awarded.

12.4.2 In support of meeting the qualification requirements the bidder

in attachment 3A of their bid has declared the annual turnover

for the last three years that is as follow:

S.no. Financial Year In US $ In Indian rupees

1 2003-2004 562.17 27484.49

2 2004-2005 619.96 29541.09

3 2005-2006 682.60 33372.31

Average Annual Turnover 621.58 30132.63

From the above table the average turnover of the XYZ comes

outs to be 621.58 US$ equivalent to Rs 30132.63 million against

NTPC’s requirement of Rs.200 million as specified.

13. Comparison with Cost Estimate

13.1 The quoted price of XYZ in equivalent Indian rupees workouts

to be 26,97,82,648 and the same is higher by 14.3% as compared

to the approved cost estimate of Rs.2363.74 lakh.

Apeejay Institute of Technology School of Management Page 86

Page 87: Abhinay Project Report

Quote:

Review on basis of NIT cost estimate:

The bids for the subject package were opened on 11.8.2006 and the

quoted L1 price was 14.13% higher than approved NIT cost estimate

as communicated by contract service vide their IOM dated 13.8.2005.

The NIT estimate for the mechanical works was prepared on the basis

of L1 bid for kahalgaon II fire detection and protection package. Since

this bid was opened almost at the same time of the preparation of the

cost estimate, it reflected the latest market trend at the time of

preparation of cost estimate.

Updating the NIT cost estimate

Project Engineering (mechanical) water system vide their IOM has

informed that there are certain scope changes between BOQ which

was tendered and BOQ considered at the time of approval of NIT cost

estimate. Further, PE have informed that there is increase in scope of

work after initiation of the estimate and civil cost shall increase by 25%

due to increase in scope.

Unquote:

13.2 From the above It can be seen that quoted price of XYZ at US $

761592.57 + Rs. 234,231,507 (equivalent to Rs. 26,97,82,648) is

0.59% higher than the updated cost estimate.

14.0 AWARD RECOMMENDATION

In view of above, it is proposed to award the contract for fire

protection package for Sipat STPP stage II to M/s XYZ bosai ltd.,Japan

at a price of US $ 761,592.57 and Rs. 234,231,507/- (equivalent to

Rs. 26,97,82,648)

Apeejay Institute of Technology School of Management Page 87

Page 88: Abhinay Project Report

Apeejay Institute of Technology School of Management Page 88

Page 89: Abhinay Project Report

Financial statement analysis

At

National Thermal Power Corporation

Financial statements

Financial statements are the end products of the financial accounting process.

Financial statements are the tools of presenting financial information about the

company in concise and capsule form. Financial information is the information

which is related to the financial position at the moment in time and the results of

series of activities over a period of time

Financial statements include Balance Sheet and Profit & Loss or income

statement & cash flow statement of the company.

Apeejay Institute of Technology School of Management Page 89

Page 90: Abhinay Project Report

BALANCE SHEET: Balance Sheet is one of the most significant financial

statements of companies. The Balance Sheet is a statement which reports the

values of properties owned by the enterprise and the claims of the creditors and

owners against these properties. It is the screen picture of the financial position

of the company.

PROFIT & LOSS A/C: it is flow statement which reveals result of operations for a

period of time. It is condensed and classified record of the gains and losses

causing change in the owner’s interest for a period of time.

CASH FLOW STATEMENT: it is statement which shows the cash requirement of

the company or the way through which company can meet its day to day

obligations. It is one of the most important components as it shows day to day

requirement of the company.

Financial Statement Analysis

Analysis of financial statements is the systematic numerical calculation of the

relationship between one fact with the other to measure the profitability,

operational efficiency and the growth potentials of the business. It includes three

major steps they are as follow:

(4) Selection of the information which is relevant to the decision under

consideration.

(5) Classification or grouping of the information in such a way that significant

relationship is established.

Apeejay Institute of Technology School of Management Page 90

Page 91: Abhinay Project Report

(6) Interpretation and drawing of inferences and conclusions by studying

these relationships.

Financial analysis can be used as the preliminary screening tool in selection of

stock in secondary market .It can be used as a forecasting tool of future financial

condition and results. It may be used as a process of evaluation and diagnosis of

managerial, operating, or other problem areas.

Financial statements analysis major techniques which inform about the position

and profitability of the company are as follow:

(1) Ratio Analysis

(2) Cash flow Analysis

(3) Trend Analysis

Ratio Analysis

Ratio Analysis is the process of determining and presenting the relationship of

items or group of items in the financial statement. It has emerged as a principle

technique for the analysis of the financial statements of the companies.

Ratio analyses help to know the operational efficiency, profitability and liquidity of

the company which is important for the external users as well as insider users of

the company.

Apeejay Institute of Technology School of Management Page 91

Page 92: Abhinay Project Report

Financial tools that help in ratio analysis are as follow:

(1) Liquidity Ratio

(2) Activity or Efficiency Ratio

(3) Profitability Ratio

(4) Capital Structure of leverage ratio

(5) Investment Analysis ratio

NTPCYEAR 2006 2005 2004 2003 20021. Liquidity Ratio1.1 Current RatioCurrent Assets 126958 102113 108193 172657 153063Current liabilities 49102 52306 65244 34202 31881current ratio 2.59 1.95 1.66 5.05 4.801.2 Quick RatioQuick Assets 103553 84336 90813 154945 132887Current Liabilities 49102 52306 65244 34202 31881Quick Ratio 2.11 1.61 1.39 4.53 4.17

Apeejay Institute of Technology School of Management Page 92

Page 93: Abhinay Project Report

1.3 Cash RatioCash & Bank Balance 84714 60783 6091 5447 5511Current Liabilities 49102 52306 65244 34202 31881Cash Ratio 1.73 1.16 0.09 0.16 0.17

Liquidity Ratios

0

2

4

6

8

10

12

2006 2005 2004 2003 2002years

rati

os cash ratio

quick ratio

current ratio

(1) Liquidity Ratio :

Liquidity means the firms or company’s ability to meet its current financial

obligations as they arise. Short term liquidity involves current assets and

current liabilities of the company. if the company has sufficient working

capital that is current assets are more than current liabilities then company

is said to be liquid enough to meet is current or day to day obligations.

There are few ratios to measure the liquidity of the company they are as

follow:

(a) Current Ratio :

Current ratio is the relationship between current assets and current

liabilities.

Current Assets

Current Liabilities

Current assets of the company represent those assets which can be in

ordinary course of business converted into cash within a period of one

Apeejay Institute of Technology School of Management Page 93

Page 94: Abhinay Project Report

year. It includes cash, marketable securities, debtors, inventories, loan

and advances given and prepaid expenses.

Current liabilities of the company are the obligations of the company

which are to be paid within a period of one year. It includes loan and

advances taken, creditors, accrued expense and provisions.

Ideally a company should have 2:1 current ratio its shows that company

has enough funds to meet its short term obligations. Higher the current

ratio better it is for company as it enhances the liquidity position of the

company and builds creditors and investor’s trust.

FOR NTPC:

Current Ratio has been very good over the years. Though it has fallen from 4.80

times in the year 2002 to 2.59 times in the year 2006 but it is still a good one. It

shows that the Company’s current assets are 2.59 times more than current

liabilities.

The current ratio of company shows fluctuating trend but has always been good

as current assets have always been more than current liabilities which shows

that firm has always enough funds to meet its day to day obligations.

(b) Quick Ratio :

It measures the instant debt paying capability or company’s ability to pay

unexpected demand for working capital. This ratio establishes the

relationship between quick or liquid current assets and current liabilities

Current assets – (Inventories + prepaid expenses)

Current Liabilities

Apeejay Institute of Technology School of Management Page 94

Page 95: Abhinay Project Report

Ideally it should be 1:1 but if the liquid ratio or quick ratio is more

than 1:1 than company seems to be sound and good. On the other

hand if it is less than 1:1 the company is said to be unsound.

For NTPC

Quick Ratio was 4.17 in the year 2002 which came to 2.11 in the year 2006,

indicating that the company is having quick assets to pay its current liabilities.

It was best in year 2003 of 4.53 and average in rest of the years. This shows that

company keeps enough liquid funds to meet its unexpected cash requirements or

obligations. For NTPC it shows that it can meet unexpected need for funds

easily.

(c) Cash Ratio:

It measures the absolute liquidity of the company. it is a relationship

between absolute quick assets and quick liabilities.

Quick Assets includes cash, bank and marketable securities and

Quick Liabilities includes all current liabilities except bank over

draft.

Absolute Liquid Assets

Quick Liabilities

Ideally it should be 0.5:1

For NTPC

Cash Ratio has increased from 0.17 times in year 2002 to 1.73 times in year

2006 showing the firm’s ability to quickly pay its debt, and more cash in its

current assets. This means over the year’s company has increased its cash

balances with itself and made itself more liquid in terms of the liquidity

maintenance.

2. Activity or Efficiency Ratio2.1 Inventory Turnover RatioCost of Goods sold 224818 194734 160156 106156 147964inventory at the end 23405 17777 17380 17712 20176

Apeejay Institute of Technology School of Management Page 95

Page 96: Abhinay Project Report

inventory turnover ratio 9.61 10.95 9.21 5.99 7.33

2.2 Receivables Turnover RatioNet Sales 261153 225402 188519 190475 178153Receiveables at the end 8678 13747 4699 124349 115328Receiveables Turnover Ratio 30.09 16.40 40.12 1.53 1.54

2.3 Total Assets Turnover Rationet sales 261153 225402 188519 190475 178153Total assets 717371 659483 596346 493319 450411Total assets turnover ratio 0.36 0.34 0.32 0.39 0.40

2.4 Fixed Assets Turnover RatioNet Sales 261153 225402 188519 190475 178153Fixed Assets 460396 431062 400281 366106 328912Fixed Assets Turnover Ratio 0.57 0.52 0.47 0.52 0.54

2.5 C/ATurnover RatioNet Sales 261153 225402 188519 190475 178153Current Assets 126958 102113 108193 172657 153063Current Assets Turnover Ratio 2.06 2.21 1.74 1.10 1.16

2.6 Working Capital Turnover RatioNet Sales 261153 225402 188519 190475 178153Net Current Assets 95843 61606 54527 148282 119653W C Turnover Ratio 2.72 3.66 3.46 1.28 1.49

Apeejay Institute of Technology School of Management Page 96

Page 97: Abhinay Project Report

Activity Ratio

0

10

20

30

40

50

60

2006 2005 2004 2003 2002years

rati

os

W C Turnover Ratio

Current AssetsTurnover Ratio

Fixed AssetsTurnover Ratio

total assetsturnover ratio

ReceiveablesTurnover Ratio

inventory turnoverratio

(2)Activity or Efficiency Ratio: An activity ratio is the relationship between sales or cost of goods sold and

investment in various assets of the company. It is always expressed as

turnover. They are intended to describe how efficiently or intensively a firm

uses its assets to generate sales.

Some of the important activity or efficiency ratios are as follow:

a) Inventory or stock turnover Ratio:

It establishes the relationship between costs of goods sold and

average inventory. It is calculated to consider the adequacy of the

quantum of capital and justification for investing in an inventory.

The quantity of the stock should be sufficient to meet the demand

of the business and it should not be too large as it results in

unnecessary locking up of capital in stock.

Cost of Goods Sold

Average Inventory at cost

Here average stock is opening stock +closing stock

2

Cost of goods sold is computed as

(Opening stock + Purchase + direct expense) – closing stock

Apeejay Institute of Technology School of Management Page 97

Page 98: Abhinay Project Report

The ratio reveals the number of times finished stock is turned over

during a given accounting period in relation to sales. It also indicates

whether investment in inventory is within limit or not. The more high

the ratio the more profitable it is. Low ratio indicates dull business or

over investment in inventories.

FOR NTPC:

Inventory Turnover Ratio has increased from 7.33 times in the year 2002 to

9.61 times in the year 2006.indicating that NTPC maintained inventory 9.61 times

as compare to the year 2002 where it was 7.33 times. Since NTPC is into

business of power so it do not have its own inventory as such but for its business

it requires coal so here inventory is considered as coal which is not used for

selling purpose it can only show that how efficiently it is maintaining its current

inventory and inventory maintenance at NTPC is showing efficient results.

b) Receivable Turnover Ratio:

How far the company is efficient or successful enough in realizing

its credit debtor’s turnover ratio is being calculated. It establishes

relationship between net credit sales and average receivables of

the year.

Net Credit Sales

Average Receivables

Credit sales means all credit sales minus the sales returns. Or else

a total sale is considered as credit sales.

Average Receivables are computed as:

Opening Debtors and B/R + closing Debtors and B/R

2

For NTPC

Apeejay Institute of Technology School of Management Page 98

Page 99: Abhinay Project Report

Receivables Turnover has also rose from 1.54 times in the year 2002 to 30.09

times in the year 2006 indicating NTPC collected its outstanding credit account &

its collection of the fund has improved incredibly.

It was very poor in year 2002 where company had bad collections from debtors

as most of the funds of the company were blocked or had less recovery. But in

year 2004 it rose to 40.12 times which could have been possible due to large

fund collection at one time or major past collection must have been done in year

2004. But, in year 2005 it fell back to 16.40 times which was can be attributed as

average collection in the year because company can’t have huge collection every

year. And this ratio is good enough now in year 2006 which is 30.09 which shows

that company has good recollection system and its only small amount of fund is

blocked rest all is collected easily.

(C) Total Asset Turnover Ratio:

This ratio expresses relationship between costs of goods sold or net

sales and total assets or investments of a firm.

Net Sales or Cost of Goods Sold

Total Assets

Total Assets means all fixed and current assets but the provision for

depreciation is adjusted in it.

This ratio indicates the number of times the assets are turned over in a

year in relation to sales. A higher total assets turnover ratio is the

indicator of effective utilization of investment in assets where as lower

assets turnover ratio indicates that assets are not properly utilized in

comparison to sales. Thus, there is an over investment in assets.

Extremely high ratio means over trading in the business.

For NTPC

Apeejay Institute of Technology School of Management Page 99

Page 100: Abhinay Project Report

Total Assets Turnover Ratio indicates that NTPC in the year 2006, for

every 1 rupees in total assets generate 36 paisa in sales.

This shows that company still need to concentrate more on this ratio for its

effective utilization of the funds as it can even go much higher .

(d) Fixed Assets Turnover Ratio:

This ratio expresses the relationship between fixed assets (less

depreciation) and net sales or cost of goods sold. This ratio measures

the efficiency and profit earning capacity of the firm.

Sales or Cost of Goods sold

Fixed Assets less depreciation

The higher the ratio the greater is the intensive utilization of fixed assets.

Lower ratio means under utilization of fixed assets and excessive

investment in these assets.

For NTPC

Fixed Assets Turnover indicates that NTPC in the year 2006, for every 1

rupees in fixed assets generate 0.57 in sales. It shows intensive utilization of

fixed assets. Indicates the profit earning capacity of the company is high.

(e) Current Assets Turnover Ratio:

This ratio expresses the relationship between current assets and net

sales or cost of goods sold. This ratio reflects the efficiency and capacity

of working capital. On the basis of this ratio efficiency of current assets

and over and under investment in the company can be examined.

Sales or Cost of Goods Sold

Current Assets

For NTPC

Apeejay Institute of Technology School of Management Page 100

Page 101: Abhinay Project Report

Current Assets Turnover Ratio: indicates that NTPC in year 2006 for

every 1 rupees in current assets generate Rs.0.26 in sales. This shows that

company’s current assets are effectively utilized but more efforts should be

made to increase this ratio further.

(f) Working Capital Turnover Ratio:

This ratio establishes relationship between net working capital and net

sales or cost of good sold. This ratio is used to assess the efficiency with

which the working capital is being used in the business.

Sales or Cost of Goods Sold

Net Working Capital

A high working capital ratio indicates efficient management of working

capital or over trading i.e. low investment in working capital and more

profits. Low working capital turnover ratio implies under trading i.e. funds

are not being utilized efficiently.

For NTPC

Working Capital Turnover Ratio: indicates the proper management of the

working capital in the firm which is required for the day to day operations of the

firm. It shows that in year 2006 for every rupee in working capital generates

0.272 in sales. It has increased from 1.49 times in year 2002 to 2.72 times in

year 2006 which indicates that company is managing its working capital very

efficiently. And it is continuously improving which is good for the investors as well

as for the company.

3. Profitability Ratio (based on sales)

Apeejay Institute of Technology School of Management Page 101

Page 102: Abhinay Project Report

3.1 Gross Profit MarginGross Profit (PBIT) 77856 77737 92594 47456 46201Net Sales 261153 225402 188519 190475 178153Gross Profit Margin 29.81% 34.49% 49.12% 24.91% 25.93%

3.2 Operating profit RatioOperating Profit 72467 77180 61483 48950 58206Net sales 269581 234913 188519 190475 178153Operating Profit Ratio 26.88% 32.85% 32.61% 25.70% 32.67%

3.3 Net Profit RatioNet Profit 58202 58070 52608 36075 35396Net Sales 261153 225402 188519 190475 178153net profit Ratio 22.29% 25.76% 27.91% 18.94% 19.87%

Profitability Ratio

0.00%

20.00%

40.00%

60.00%

80.00%

100.00%

2006 2005 2004 2003 2002

years

rati

o net profit Ratio

Operating Profit Ratio

Gross Profit Margin

(3) Profitability Ratio :The main objective of the business firm is to earn profits. It is possible only

when resources of firm are efficiently utilized. Profitability depends on

quantum of sales, cost of production and use of financial resources etc.

The profitability of the firm can be easily measured by its profitability

ratios. These ratios indicate overall managerial efficiency. Profitability can

be measured based on sales or based on capital and assets.

(i) Profitability based on sales

Apeejay Institute of Technology School of Management Page 102

Page 103: Abhinay Project Report

(a) Gross profit Ratio:

This ratio expresses the relationship of gross profit on sales to net

sales in terms of percentage.

Gross Profit X 100

Net Sales

Gross profit can be computed as Net Sales – Cost of Goods Sold.

The ratio measures the trading effectiveness and basic profit

earning potentiality of a company. The higher the ratio the greater

will be the margin.

FOR NTPC:

Gross Profit Margin: has reduced from 49.12% in the year 2004 to 29.81% in

the year 2006. This tells that NTPC generate 30 paisa from every 1 rupee sales.

Although it was good in year 2004 which could due to the large sales in that

particular year or may be due to market favoring the environment of the sales.

Still it is good for year 2006 i.e. for every one rupee sale company can generate

30 paisa as profit after meetings it expenses of generation.

(b) Operating profit Ratio:

This ratio establishes the relationship between operating profit

and net sales. It is also defined as the ratio of profit before

depreciation, interest and tax to total turnover. Operating profit

means the net profit arising from the normal operations and

activities of the business without taking account of extraneous

transactions and expenses purely financial nature.

Operating Profit X100

Net Sales

This ratio indicates the net profitability of the main business i.e.

operating efficiency of a firm. The higher the operating ratio the

better would be the operational efficiency of the firm. A higher

operating profit ratio means that a firm has been able not only to

Apeejay Institute of Technology School of Management Page 103

Page 104: Abhinay Project Report

increase its sales but also been able to cut down its operating

expenses

(c) Net Profit Margin

This ratio measures the relationship between net profit and sales of

a firm. Net Profit is the excess of revenue over expenses during a

particular accounting period. The net profit ratio is determined by

dividing the net profit by sales and expressed as percentage.

Net Profit (after tax) X100

Net Sales

This ratio is the indication of over all profitability and efficiency of

the business. A high net profit ratio would only mean adequate

returns to the owners. It also enables a firm to withstand in cut

throat competition when the selling price is declining or cost of

production is rising. A low net profit ratio on the other hand, would

only indicate inadequate return to the owners.

For NTPC

Net Profit Margin: has increased from 19.87% in year 2002 to 22.29% in year

2006 but it has reduced in comparison to year 2004 as it was 27.91% in year

2004. This shows that company is running efficiently and it can pay more to its

investors as it generates 23 paisa in the profit for every single rupee of sale.

Though it is less than year 2004 but yet it is not bad it still displays the profit

earning efficiency of the company as good.

4. Profitability Ratio (based on capital)4.1 Return of Capital EmployedNet Profit (PBIT) 77856 77737 92594 47456 46201Capital Employed 523572 500540 458267 386343 356526Return of Capital Employed 14.87% 15.53% 20.21% 12.28% 12.96%

Apeejay Institute of Technology School of Management Page 104

Page 105: Abhinay Project Report

4.2 Return On Equity (ROE)Net Profit (PAIT) 58202 58070 52608 36075 35396Shareholder's Fund 449587 417763 355501 315040 286453return on equity 12.95% 13.90% 14.80% 11.45% 12.36%

4.3 return on total assetsnet profit after tax 58202 58070 52608 36075 35396total assets 717371 659483 596346 493319 450411return on total assets 8.11% 8.81% 8.82% 7.31% 7.86%

Profitability Ratio (based on capital)

0.00%

5.00%

10.00%

15.00%

20.00%

25.00%

2006 2005 2004 2003 2002

year

rati

os

Return of CapitalEmployed

return on equity

return on total assets

Profitability Ratio Based on Capital

(a)Return on Capital Employed:

Apeejay Institute of Technology School of Management Page 105

Page 106: Abhinay Project Report

This ratio expresses the relationship between profit and capital

employed and is calculated in percentage by dividing the net profit

by capital employed.

Net Profit (PBIT) X100

Capital Employed

The return on capital employed provides a test of profitability

related to long term funds. The higher the ratio, the more effective

and efficient would be utilization of capital or vice- versa.

For NTPC

Return on Capital employed: it has increased from 12.98% in year 2002 to

14.87% in year 2006 though it was maximum in year 2004 of 27.91%. all though

years it is showing the almost regular trend but it was higher in year 2004

because that was the year in which company got its maximum funds back.

This shows that company was making most effective utilization of its capital in

year 2004 but it is still operating efficiently.

(b)Return on proprietor’s funds or equity:

This ratio expresses the percentage relationship between the net

profit (after interest and tax) and proprietor’s funds or shareholder’s

investment.

Net Profit (after interest and tax) X100

Shareholder’s funds

Shareholder’s funds include preference share capital as well as

equity shareholders funds which in turn comprises of equity share

capital, share premium and reserves & surplus.

For NTPC

Apeejay Institute of Technology School of Management Page 106

Page 107: Abhinay Project Report

Return on Equity (ROE): It is also consistent over the years reflecting not

much variation. It is 12.95% for the year 2005 indicating that NTPC generate 13

paisa in profit per 1Rs invested in Equity. Maximum was for year 2004.

(c) Return on Total Assets:

Profitability of the company can also be measured by establishing

relationship between net profit and total assets. Total assets mean

all net fixed assets, current assets and non trading investments.

Net Profit after Tax X 100

Total assets

This ratio measures the profitability of investments which reflects

managerial efficiency. The higher the ratio the better is the profit

earning capacity of the firm or vice versa.

For NTPC

Return on Assets (ROA): It has been consistent over the years; it is 8.11%

for the year 2006 indicating that NTPC generates 8 paisa of profit per one rupee

invested in assets.

5. Leverage or Capital Structure Ratio5.1 Debt - Equity RatioTotal Debt 201973 170878 154528 132157 115812Net Worth 449587 417763 355501 315040 286453Debt - Equity Ratio 0.45 0.41 0.43 0.42 0.40

Apeejay Institute of Technology School of Management Page 107

Page 108: Abhinay Project Report

5.2 Debt to Total Assets ratioTotal Liabilities 263375 238345 235469 178007 163958Total Assets 717371 659483 596346 493319 450411Debt to Total Assets Ratio 0.37 0.36 0.39 0.36 0.36

5.3 interest Coverage Rationet profit before interest and tax 77856 77737 92594 47456 46201fixed interest charges 17632 16955 33697 9916 8680Interest coverage ratio 4.42 4.58 2.75 4.79 5.32

5.4 Dividend Coverage Rationet profit after interest and tax 58202 58070 52608 36075 35396 dividend 23087 19790 10823 7080 7079Dividend Coverage Ratio 2.52 2.93 4.86 5.10 5.00

Leverage or Capital Structure Ratio

0

1

2

3

4

5

6

2006 2005 2004 2003 2002

years

rati

os

Debt - Equity Ratio

Debt to Total AssetsRatio

interest coverageratio

Dividend CoverageRatio

(4) Leverage or Capital structure Ratio: Leverage or capital structure ratios are calculated to judge the long term

solvency or financial position of the company.

Some of the important capital structure ratios are as follow:

Apeejay Institute of Technology School of Management Page 108

Page 109: Abhinay Project Report

(a) Debt – Equity Ratio :

This ratio indicates the relative proportion of debt and equity in

financing the assets of a firm. It reveals the relationship between

internal and external sources of funds of a company.

Total Debts

Net Worth

Total debts refer to the total outside liabilities i.e. short term and long

term loans. Net worth mean total paid up amount of equity and

preference share capital plus the total or accumulated amount of

reserves and surplus.

This ratio plays important role in analyzing the long term solvency of a

company. It indicates the firm’s capacity to pay long term debts and

procure additional loans and informs whether the firm is following the

policy of trading on equity.

For NTPC

Debt Equity Ratio: are also consistent and there has been not much

variation in this ratio over the years it was 0.40 in year 2002 and 0.45 times in

year2006. But, it is slowly and steadily rising each financial year. This ratio shows

that the long term solvency of the firm is sound enough it has good capacity to

pay its long term debts which make it easy for it to procure funds from the market

easily due to its long term solvency ratio.

(b)Debt to Total Assets Ratio:

This ratio measures the long term solvency of the business. It reveals

relationship between total assets and total external liabilities. External

liabilities mean all long term and short term liabilities.

Apeejay Institute of Technology School of Management Page 109

Page 110: Abhinay Project Report

Total Liabilities

Total Assets

This ratio measures the proportion of total assets provided by creditors

(long term as well as short term) of the company i.e. what part of

assets is being financed from loans. If total assets are more than

external liabilities the firm is treated as solvent. So, higher the ratio the

greater is the amount of creditors that is being used to generate profits

for the owners of the firm.

FOR NTPC:

Total debt ratio is consistent over the year; it was 0.36 times in 2002, 0.36 times

in 2003 and 0.39 times in 2004, 0.36 times in 2005 and 0.37 times in 2006

indicating that NTPC use 37% Debt and 63% Equity Capital structure in the year

2006. This shows that company is solvent enough as its total assets are more

than its total debt. It uses less funds from outside to finance its working or for

generating profits.

(c) Interest coverage Ratio:

This ratio measures the debt servicing capacity of the firm and

particularly where payment of fixed interest on long term loans is

concerned.

Net Profit (before interest and tax)

Fixed Interest Charges

The higher the ratio the more is the interest paying capacity of the firm

and safety margin available to long term creditors. The low ratio

indicates that the firm is using excessive debt. The investors can

forecast the financial risk by comparing interest coverage ratio with

standard ratio of the industry.

For NTPC

Apeejay Institute of Technology School of Management Page 110

Page 111: Abhinay Project Report

Interest coverage Ratio: has fallen from 5.32 times in the year 2002 to

4.42 times in the year 2006 but in year 2003 it started falling and then again

increased from 2.75 times in year 2004 to 4.42 times in year 2006 indicating how

well NTPC has its interest obligations covered. It was maximum in year 2002. As

compare to industry ratio of 6 times it is still good. This shows that firm can meet

its long term interest obligations on time as and when they arise. This is utmost

important for interest bearing securities. In case of NTPC it’s the loan that they

are carrying.

(d)Dividend Coverage Ratio:

This ratio measures the ability of a firm to pay dividend on preference

shares which carry a fixed rate of dividend. This ratio is expressed in

number of times of net profits after taxes.

Net profit after tax and interest

Dividend

This ratio indicates the safety margin available to preference

shareholders. The higher the dividend coverage ratio the better it is

from the preference shareholders’ point of view.

FOR NTPC:

Dividend Coverage Ratio: has fallen from 5 times in year 2002 to 2.52

times in year 2006. this is bad indicator has it shows that company is not able to

meet its dividend obligations of the shareholder as the investors who are

investing in firm requires more returns so this should be analyzed properly and

accordingly actions should be taken as it is hampering interest of shareholders.

Possible reason for it could be increase in the dividend rate which made the

dividend to fall and in case of NTPC there is no preference dividend its only

dividend paid to the equity shareholders is considered.

6.Investment Analysis Ratio6.1 earning per shareprofit after tax 58202 58070 52608 36075 35396

Apeejay Institute of Technology School of Management Page 111

Page 112: Abhinay Project Report

no of equity share 8245464400 8245464400 7812549400 7812549400 7812549400earning per share 7.05 7.06 7.06 7.06 7.06

dividend pay out ratiodividend per share dividend 23087 19790 10823 7080 7079outstanding shares 8245464400 8245464400 7812549400 7812549400 7812549400dividend per share 2.8 2.4 1.38 0.906 0.906earning per share 7.05 7.06 7.06 7.06 7.06dividend pay out ratio (DPS/EPS) 39.7 34.0 19.5 12.8 12.8

cost of capitaltotal debt (D) 201973 170878 154528 132157 115812total equity (E) 449587 417763 355501 315040 286453interest chareged (I) 17632 16955 33697 9916 8680cost of debt (I/D*100) (1-t) (kd) 5.79 6.59 14.5 4.98 4.98cost of equity capital (ROE) (ke) 12.94 13.9 14.8 11.45 12.36over all cost of capital (Ko)Kd*(D/D+E)+Ke*(E/D+E) 10.71 11.77 14.7 9.53 10.23

market value of firm (PBIT/Ko) 7269.467787 6604.6729 6298.91156 4979.643232 4516.226784

retained earning 31877 35600 40398 28600 28317net profit 58202 58070 52608 36075 35396retention ratio 0.548 0.613 0.768 0.793 0.800ROE (%) 12.95% 13.90% 14.80% 11.45% 12.36%growth (retention ratio * ROE) 0.071 0.085 0.114 0.091 0.099

Investment Analysis Ratio

0

10

20

30

40

50

2006 2005 2004 2003 2002

years

rati

os

growth (retention ratio* ROE)

dividend pay out ratio(DPS/EPS)

earning per share

Investment Analysis Ratios

Apeejay Institute of Technology School of Management Page 112

Page 113: Abhinay Project Report

1. Earning Per Share – EPS

The rate of dividend on shares depends upon the amount of profits

earned by the firm. Whatever profits remains, after meeting all

expenses and paying preference share dividend, belongs to equity

shareholders.

Profit after tax – Preference Dividend

No. of equity shares

This is a popular ratio as it measures the profitability of a firm from

owners’ standpoint. The higher the ratio the greater would be the

market price of a company’s shares or vice versa.

FOR NTPC:

EPS has been consistent over year it was 7.06 in year 2002 and is 7.05 in year

2006.

2. Dividend Yield Ratio:

It expresses relationship between the dividend per share and market

value per share.

Dividend per Share X100

Market Price per Share

This ratio shows the rate of return to shareholders in form of dividend

based on the market price of the share i.e. actual rate of dividend on

his investment.

FOR NTPC:

Dividend yield ratio increased from 12.8 in year 2002 to 39.7 in year 2006

which shows that the company will be paying higher dividend per share now its

retention ratio has fallen.

Apeejay Institute of Technology School of Management Page 113

Page 114: Abhinay Project Report

Apeejay Institute of Technology School of Management Page 114

Page 115: Abhinay Project Report

Apeejay Institute of Technology School of Management Page 115

Page 116: Abhinay Project Report

OVERVIEW

The financial statements have been prepared in compliance

with the requirement of the Companies Act, 1956 and

Generally Accepted Accounting Principals (GAAP) in India.

There is no material departure from the prescribed accounting

standards in preparation of the annual accounts. The

accounting polices adopted by the company and the estimates

and judgments relating to the financial statements have been

made on a prudent and reasonable basis in order that the

financial statements reflect the true and fair view of the

company’s state of affairs and profits for the year.

FINANCIAL POSITION:

Apeejay Institute of Technology School of Management Page 116

Page 117: Abhinay Project Report

1. Share Capital:

During the previous year the company made an Initial Public Offer (IPO) of

865.830 million equity shares. The IPO comprised fresh issue of 432.915 million

equity share and “Offer for Sale” by Government of India of 432.915 million

equity shares. As a result of fresh issue of Rs. 4330 million, the issued,

subscribed and paid-up equity share capital of the Company has increased from

Rs.78,125 million to Rs. 82,455 million comprising 8,245,464,400 equity shares

of Rs. 10 each fully paid up.

2. Reserves & Surplus:

The major items, which make up the Reserve and Surplus are detailed below:

2.1 Share Premium Account:

The fresh issue of equity shares made during the previous year at a price of Rs.

62 per share including a premium of Rs. 52 per share , which made additions of

22360 last year and this year with deduction of Rs. 53 in respect of share issue

expenses so it amounted to Rs 22307.

2.2 Bonds Redemption Reserve :

In line with the requirements of SEBI Guidelines for maintaining a Bond

Redemption Reserve a sum of Rs.2,926 million has been credited during the

year and Rs. 16 million has been written back towards redeemed Bonds.

2.3 General Reserve:

As per the requirements of the Indian Companies Act 1956 and taking into

consideration the dividend pay-outs made and proposed a sum of Rs.29032

million has been transferred from profit and loss account during the year. Also

adjustment towards dividend is done for Rs.10 million.

Apeejay Institute of Technology School of Management Page 117

Page 118: Abhinay Project Report

3.Ratings:

Borrowings and Fixed Deposits Scheme of the Company have been rated by

different rating agencies, the detailed are as under:

Instruments Rating Ratings

Rated Agency Assigned

Domestic Bonds CRISIL ‘AAA’

ICRA ‘LAAA’

Euro Bonds Standard & ‘BB outlook Positive’

Poor’s Fitch ‘BB + outlook Stable’

Fixed Deposits CRISIL ‘FAAA’

Apeejay Institute of Technology School of Management Page 118

Page 119: Abhinay Project Report

SWOT ANALYSIS

OF

NATIONAL POWER THERMAL CORPORATION

STRENGTHS OF NTPC

Apeejay Institute of Technology School of Management Page 119

Page 120: Abhinay Project Report

The company has kept itself sufficient liquid funds to meet any kind of

cash requirements.

Efficient working capacity of the plants

Efficient & timely completion of projects

A minimum risk factor

Best integrated project management system

Company with excellent records & high profits

An early starter more than 30 years experience in power sector

One among the 9 jewels of India called as NAVRATANS

Highly motivated & dedicated workers & officers.

Excellent growth prospects with significant additions, modifications &

replacements

Employee friendly personnel policies

Low project cost of NTPC’s plants.

one of the listed company on Bombay stock exchange

WEAKNESS OF NTPC

Depleting raw materials.

Some of the plants of NTPC have become old and need

investments for replacements or modifications.

OPPORTUNITIES FOR NTPC:

Demand & supply Gap.

Apeejay Institute of Technology School of Management Page 120

Page 121: Abhinay Project Report

Upcoming hydro & nuclear sector

Huge opportunity in the consultancy services both abroad as well as in

India.

Growth in power sector.

THREATS TO NTPC

Rising prices of raw materials makes working costly.

Huge competition from SEB’s, Reliance Energy, Tata Power & other

private players in power industry.

Coming up of other sources of power generation & consumption.

Huge capital requirement for expansion, diversification, horizontal &

vertical integration.

Conclusion

Apeejay Institute of Technology School of Management Page 121

Page 122: Abhinay Project Report

Purchase management activities at NTPC are one of the most vital activities

undertaken by the Rs.18000 Cr power giant of India. The process followed by

NTPC is very objective in nature and employs a very short term relationship with

its supplier. The system tries to take advantage of the competition in the field of

heavy engineering where foreign manufacturers like MHI, GE etc. are competing

with Indian manufacturers like BHEL and L&T. NTPC being a public sector

company, to be free from nepotism and favouritism has adopted a system where

transparency and automation is at its utmost level. Transparency was achieved

by a multi member team and sealed tenders where no one knows in advance the

quotation offered by a particular bidder. Automation here signifies that almost all

the contracts are awarded following the same procedures, by awarding the

contract to the lowest bidder that is L1 without much consideration.

Together they constitute a very reliable and corruption free system. At times it

seems that the system is capable of saving lots of money of NTPC but in most of

the cases the cost of maintaining the system itself combined with the poor

responsiveness amounts to a lower level of efficiency. In today’s world of

cutthroat competition only those firm are going to survive who are committed to

efficiency, as it were their core competency. Cost must be reduced by means of

optimum utilisation of resources and channelled into more profitable segments. It

is an established fact that on operational level NTPC is one of the world’s most

efficiently run organisations.

Benefits can not be evaluated in isolation as there are certain features very

unique to the kind of domain NTPC is into. As we have discussed earlier that

most of the item except coal and gas have a very infrequent and unpredictable

demand. This means that NTPC can not anticipate its demand in advance and

hence going into a long term supply contract is very difficult. For some

procurement which actually constitutes more than 70% of non fuel procurement,

the items are manufactured to order. In these cases even the manufacturer is not

sure of the future price and availability of the equipment and hence going into a

long-term contract based on current prices may do more harm than benefits.

Another factor which must be understood is that there are very few companies

which are into manufacturing of the kind of equipments or material required by

NTPC. And since the fixed capital employed by these firms are huge, many a

times they offer huge discounts just to acquire a particular order so that they can

Apeejay Institute of Technology School of Management Page 122

Page 123: Abhinay Project Report

fulfil some of their targets. NTPC has witnessed one such offer in past where a

substantial discount was offered by a vendor on the condition that the contract

should be awarded to him in a specific time period mentioned by the

manufacturer. These benefits could not have been availed by NTPC had it been

in a long-term relationship with a particular manufacturer.

Financial statement analysis of the national power thermal corporation shows

that firm is efficient enough to run its day to day business. The liquid ratios of the

company i.e. current ratio, quick ratio, and acid test ratio indicate that NTPC is

able to pay its short term bills without undue stress. This shows that company is

liquid enough to meet its day to day obligations.

The long term ratios i.e. debt equity ratio and interest coverage ratio indicates

that NTPC is easily able to meet its financial leverages. Turnover ratios i.e.

inventory turnover, receivables turnover, asset turnover indicates NTPC id

efficiently using its assets to generate sales. Also the profitability ratios i.e. profit

margin, return on equity etc. indicates there is slight fall in net income of the

company. But the earning per share has remained same all the year this shows

the investors side is safe enough.

Over all it can be summarised that NTPC is financially sound i.e. financial

position and profitability of the company is quite acceptable.

Apeejay Institute of Technology School of Management Page 123

Page 124: Abhinay Project Report

RECOMMMENDATIONS

The overlooked aspects of equity and transparency in processing of a tender

are also the important aspects and should not be overlooked at the sake of

technical suitability and commercial viability.

While preparing the estimates enough care should be taken to ensure that

quantities of items are neither on the higher side nor on the lower side. This

will help in checking the quantity deviation, erratic rates, legal disputes and

other difficulties.

Estimated rates should be worked out on the basis of market analysis. They

can also be prepared from standard schedules such as DSR, MES

schedules.

Enough care should be taken while preparing the bid documents. It must be

ensured that technical specifications do not contradict the items in the Bill Of

Quantity (BOQ) to avoid confusions, delays, favors etc during the execution

apart from the long drawn legal disputes, arbitrations. Etc

All payment terms, including advance payments should be mentioned in the

bid documents itself so as to obviate release of any payment out of the

purview of contract later on.

The QR should be clearly mentioned and should not be made unnecessarily

stringent suiting a particular agency. To avoid complications, the QR should

be prepared by a committee comprising a member each from the Indenting,

Finance and Contracts Department.

For facilitating the Limited Tender (LTE) inquiries, enlistment or the

registration of parties should be carried out on a project level periodically.

While issuing the Tender documents against the open tender advertisement

the credential of the bidders, in original, should be checked invariably in

respect to the QR. A photocopy of the credentials should be kept for record

purposes.

Apeejay Institute of Technology School of Management Page 124

Page 125: Abhinay Project Report

The tender committee officials should encircle and initial on each page of the

tender documents received form the parties on the tender opening date.

They should mention number of any corrections (if so made) on each page.

Otherwise they should mention ‘no cutting/no overwriting’. This will eliminate

scope for an tampering at the alter date.

The tender committee should ensure that all conditions having financial

implications are loaded properly in the tender evaluation and considered in

the comparative statement. They should study the reasonableness of the

rates offered by the bidders and while recommending the award, they should

ensure the reasonableness of the rates of the lowest bidder.

While recommending award of a contact to a particular bidder, a justification

analysis should also be prepared.

To avoid any chances of any selective relaxation of the stringent QR norms

the subsequent changes in the QR norms should be through the press

Corrigendum

Apeejay Institute of Technology School of Management Page 125

Page 126: Abhinay Project Report

References

List of Books Referred

Financial Management by Khan & Jain

Financial analysis techniques by Helfred

Annual Report of NTPC

Delegation of Powers Manual of NTPC

Purchase Management Manual of NTPC

Websites Referred

Official website of company www.ntpc.co.in

www.indiainfoline.com

www.moneycontrol.com

www.powermin.nic.in

www.ntpctender.com

www.pfc.com

www.teriin.org

www.worldenergy.com

www.ntpceoc.com

Apeejay Institute of Technology School of Management Page 126