a9110-e Bts Commissioning Manual Ed04

Embed Size (px)

Citation preview

  • Alcatel BSS

    A9110E BTS CommissioningManual

    Commissioning Manual

    Release B6B7

    3BK 17416 3081 RJZZA Ed.04

  • Status RELEASED

    Short title COM

    All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel/Evolium.

    BLANK PAGE BREAK

    2 / 74 3BK 17416 3081 RJZZA Ed.04

  • Preface

    PrefacePurpose This document describes how to commission an Alcatel A9110E micro BTS.

    This document applies to operational BSS, release B6B7.

    Audience This document is intended for:

    Site administrators

    Supervisors

    Project managersField service technicians

    Occasional users.

    Assumed Knowledge The personnel involved must be familiar with:

    ALCATEL Operation & Maintenance (O&M) concepts for the Base StationSubsystem (BSS)Commissioning tools

    Personal Computers (PCs) using the Windows NT environment.

    3BK 17416 3081 RJZZA Ed.04 3 / 74

  • Preface

    HistoryDate Edition Comments

    030404 01 Creation

    031031 02 Download of operational software for connectinginto networks older than B7 MR6

    031211 03 Update for commissioning package BTSCAT02B

    040106 04 ITL Catalogue (3DF 00462 0004 AAAGA) and IOCatalogue (3DF 00462 0004 UAZZA) were updatedinto documentNew HAKI for mounting

    4 / 74 3BK 17416 3081 RJZZA Ed.04

  • 1 General Information

    1 General Information

    This chapter provides general information concerning the operating principleand requirements of the procedure:

    Hardware description

    Prerequisites

    Restrictions

    Initial state

    Final state

    Tasks sequences

    Time schedule

    Information required

    Conventions.

    3BK 17416 3081 RJZZA Ed.04 5 / 74

  • 1 General Information

    1.1 Hardware Description

    1.1.1 ConfigurationsWith this product, one BTS comprises up to six units of two TRX, in ahierarchical interconnection.

    Only one of these units handles the Abis lines; this unit called the master,the other units called slaves.

    A unit can have one antenna output (3.2 W/TRX max. power) or twoantenna outputs (7 W/TRX max. power).

    One lower slave cannot be equipped because of 12 TRX limitation!In the following exemples the Slave 22 is eliminated, but depending on siteconfiguration, you can have maximum 3 lower slave units on the 4 possiblepositions: Slave11, Slave12, Slave 21, Slave 22.

    Figure 1: Example of 6 modules with Single Antenna only starting with software version BSSSAT02G (B7MR6)

    6 / 74 3BK 17416 3081 RJZZA Ed.04

  • 1 General Information

    Figure 2: Example Low-Loss Configuration With Antenna Diversity (6 sectors) only starting with softwareversion BSSSAT02G (B7 MR6)

    The following rules are defined for pure M5M and M4M/M5M mixedconfigurations:

    Maximum 6 modules are allowed for B7 SW version BSSSAT02G (B7MR6) or higher.Only 3 modules for B7 SW version older than BSSSAT02G (B7 MR6).Maximum 3 hierarchy levels are allowed (Master, Upper Slave, Lower Slave)Lower slave allowed only for B7 SW version BSSSAT02G (B7 MR6) or higher

    M5MMaster

    M5MLower Slave 11

    M5MLower Slave 12

    M5MLower Slave 21

    M5MUpper Slave 1

    M5MUpper Slave 2

    Figure 3: M5M pure configuration (maximum 6 M5M modules, 12 TREs) onlystarting with software version BSSSAT02G (B7 MR6)

    3BK 17416 3081 RJZZA Ed.04 7 / 74

  • 1 General Information

    M4M module allowed only as upper slave, no lower slaves can connect to it.

    M5MMaster

    M5MLower Slave 11

    M5MLower Slave 12

    M5MUpper Slave 1

    M4MUpper Slave 2

    Figure 4: M5M / M4M mixed configuration (5 modules: 4 M5M +1 M4M, 10TREs in total ) only starting with software version BSSSAT02G (MR6)

    M5MMaster

    M4MUpper Slave 1

    M4MUpper Slave 2

    Figure 5: M5M / M4M mixed configuration (3 modules: 1 M5M + 2 M4M, 6TREs in total )

    8 / 74 3BK 17416 3081 RJZZA Ed.04

  • 1 General Information

    1.1.2 Weight and Dimensions

    Characteristics Each unit with cover(2TRX, 2 ANT)

    Each unit without cover(2TRX, 2 ANT)

    Width (mm) 450 385

    Height (mm) 815 (w/ o PG)915 with fan (w/ o PG)

    735 (w/ o PG)

    Depth (mm) 190 162

    Max. weight with 2 ant. (kg) 26 26

    Cover weight (kg) 7 - 9 0

    Support weight (kg) 5.6 5.6

    Maximum weight (kg) 38.6 - 40.6 31.6

    1.2 RestrictionsNone.

    1.3 PrerequisitesThe following prerequisites apply:

    The site must comply with the Safety rules ( See BSS Methods Handbook)The BSC must be operational and ready for BTS connection

    The following requirement is not mandatory: antenna connected.

    1.4 Initial StateThe MOCOs are installed and connected as described in the installationmanual: power supply, PCM (for master unit) even not connected to thenetwork, external alarms.

    The micro-BTS units are not plugged into their connection boxes.

    1.5 Final StateThe BTS is installed (master and slave units)The BTS is commissioned, powered up and connected to the BSC via aPCM interface ready for network integration

    Integrated antenna option: integrated antennas are installed on all units

    3BK 17416 3081 RJZZA Ed.04 9 / 74

  • 1 General Information

    Antennas present: the antennas have been connected

    Antennas absent: the tests have been carried out under load.

    Figure 6: Example of A9110E BTS ( Maximum 6 M5M Configuration With Cover )

    CustomerAlarmBox

    Alarm pointsfor Customer

    230 VAC

    1.5 m

    MASTERSLAVE 2 SLAVE 1

    GroundPlate

    Wire braid

    Figure 7: Example of A9110E BTS (3 modules with SSC Option)

    10 / 74 3BK 17416 3081 RJZZA Ed.04

  • 1 General Information

    1.6 Operating PrinciplePreparation before leaving for the site

    Preparation after arrival at the site

    Manual lift/ CraneInstallation with the crane

    Option: Install the integrated antenna

    Option: Install the VSWR detector

    Make the connections to BTS

    Check the power supply and power up the BTS

    Download the BTS software

    Set the antenna mapping

    BTS initialization

    Perform BTS inventory

    Set and check the external alarms

    Check the module status

    Case: Antenna present

    Check the VSWR under load

    Abis loop test

    End of commissioning test

    Set the transmission module paramenters

    Connect to the BSC

    Finish the commissioning

    Check the antenna VSWR

    YES NO

    Installation with the manual lift

    Download the operational software

    3BK 17416 3081 RJZZA Ed.04 11 / 74

  • 1 General Information

    1.7 Time Schedule

    Duration (min) 1st person 2nd personPreliminary checks 15 15

    Installing the micro-BTS units(1)

    Case A: Installation with the manual lift 10 / unit 10 / unit

    Case B: Installation with the crane 15 / unit 15 / unit

    Making the connections to the BTS

    Option: Installation of integrated antenna 5 / unit 5 / unit

    Option: Installation of the VSWR detector 10 / unit 10 / unit

    Making the connections to BTS units 5 / unit 5 / unit

    Checking power supply and powering up 10 10

    Commissioning tests

    BTS software downloading 5 -

    Setting antenna mapping 2 -

    BTS initialization 5 -

    Performing BTS inventory 5 -

    Setting and checking the external alarms 5 5

    Checking status of modules 2 -

    VSWR check 5 / unit 5 / unit

    Abis loop test(2) 3(2) 3(2)

    End of commissioning(3) 5-10(3) -

    Setting transmission module parameters 5 -

    Downloading the operational software(4) 10(4) -

    Connecting to the BSC 5 5

    Finishing commissioning 5 5

    1h 42 - 3h 00 1h 08 - 2h 15

    (1) : Tasks where two persons are mandatory(2) : Not performed if MW or TNL equipment installed in SSC(3) : 10 min only if the inventory has to be performed again

    12 / 74 3BK 17416 3081 RJZZA Ed.04

  • 1 General Information

    (4) : If the network runs into software version older than B7 MR6

    The times given are based on technical constraints, not taking into accountsafety considerations.

    1.8 Information RequiredSite Position of breakers on the customers power panel

    If DDF cabled: position of PCM cables (Abis1, Abis2) on the DDF side.Equipment configuration Configuration of the BTS (number of units, type: M4M/M5M)

    Configuration of sectors and number of MTREs per sector

    Mapping table correlating logical and physical BTS sectors

    If DDF installed: external alarm mapping and position of alarm wires onthe DDF side

    If SSC option: customer external alarm mapping (other than SSC externalalarms).

    Other Software version

    Test frequencies

    Transmission configurationQmux addressOML TS and signalling rate (optional).

    Antennas connected or not.

    1.9 ConventionsThe following list gives the conventions used in this document:

    Press [ Enter ] means press the Enter keyClick [ OK ] means click the button OK with the mouseOperator input is indicated after a double right-pointing arrow in Courier font

    Operator input

    To describe a menu path, the menu options are linked as follows:Tools Options Printer ...

    A message is indicated in Courier font:Message

    3BK 17416 3081 RJZZA Ed.04 13 / 74

  • 1 General Information

    14 / 74 3BK 17416 3081 RJZZA Ed.04

  • 2 Preliminary Checks

    2 Preliminary Checks

    This chapter describes the preparation of the operation in two steps:

    At base

    On arrival at the site.

    3BK 17416 3081 RJZZA Ed.04 15 / 74

  • 2 Preliminary Checks

    2.1 Before Going to the Site

    Check prerequisites fulfillment See Prerequisites (Section 1.3) .Check availability of informationrequired

    See Information Required (Section 1.8) .

    Check availability of documentation See List of Documents Required (in appendix B) .Check availability of tools See Tools Required (in appendix B) , refer to the Tools

    catalogue for content checking.Verify the calibration label when indicated in Tools Required(in appendix B) .

    Check availability and version ofsoftware

    See List of Software Required (in appendix B) ; refer to thecorresponding documents for checking the SW version.

    2.2 Before You Start (On Arrival at the Site)Check applicable notification list andOperation Instructions

    Refer to Catalogue of Technical and Logistic Information(ITL) to check whether notifications are to be applied duringthe operationRefer to Catalogue of Instruction Operation (IO) to checkwhether operation instructions are to be applied during theoperation

    Check that safety instructions areapplied

    Refer to BSS Methods Handbook for checking that safetyprecautions have been taken into accordance with safetyinstructions.

    Read instructions to be applied in caseof anomaly

    Refer to BSS Methods Handbook for instructions.

    Complete premises inspection form Refer to BSS site premises inspection, post handover andcomplete Premises inspection form (CEL).

    Fill in completion check list Complete the header field of the CCL (See CompletionCheck List)In particular, see tools catalogue and note downmeasurement accuracy when indicated in tool kit list(appendix)The CCL is completed as each installation instruction iscarried out.

    Check the antistatic wrist strap Check that the resistance of the antistatic wrist strap isgreater than 1M .Connect the antistatic wrist strap to rack earth.

    Check availability of Alcatel kits See List of Items Required (Appendix B) .

    16 / 74 3BK 17416 3081 RJZZA Ed.04

  • 3 Installing the Micro - BTS Units

    3 Installing the Micro - BTS Units

    This chapter describes the procedure for fixing the micro BTS on MOFRA.

    Before the installation of the BTS units, check the lead seal.If damaged, make a note in the CCL.

    The installation procedure is the same for master and slave units.

    Do not work under power.Open the circuit breakers to be sure that the power supply is disconnected.For an installation with SSC: Check that the " Battery back-up " is OFF (redLED is lit) !!! (in the case of battery back-up there is 288 V DC on the BTSconnector and the crane will be damaged!!!)

    3BK 17416 3081 RJZZA Ed.04 17 / 74

  • 3 Installing the Micro - BTS Units

    3.1 Case A: Installation With the Manual LiftPurpose To install the BTS on the MOCO.

    Preparation 1. Open the front cover to reveal the MOCO (with cover option)2. Remove the COBO protection cover (3BK 08586 AA).3. Remove the bottom protection cover of the micro-BTS unit (3BK 08555 AA).

    Install the Threaded Bolt 1. The threaded bolt must be screwed into the M8 thread on top of the A9110EBTS housing, down to the internal screw-thread stop (See Figure 8 )

    2. Do not tighten3. Arrange the bolt with the flattened sides to the left and right.

    Figure 8: Installation and Arrangement of the Threaded Bolt

    18 / 74 3BK 17416 3081 RJZZA Ed.04

  • 3 Installing the Micro - BTS Units

    Install the Handwheel 1. The handwheel must be screwed down to the threaded bolt stop (SeeFigure 9 )

    2. Make sure the handwheel and bolt are not damaged

    Figure 9: Installation of the Handwheel

    Install the Gallows 1. The gallows are plugged into the Mounting Frame (MOFRA) (See Figure 10 )2. The safety catch (1) keeps the gallows in place.

    Figure 10: Installing the Gallows

    3BK 17416 3081 RJZZA Ed.04 19 / 74

  • 3 Installing the Micro - BTS Units

    Install the BTS-Handle 1. Fix the metal pieces (3) with screws (4 two at each side) to each side ofthe BTS Handle (2), see figure 11

    2. Fix the assembly to the the hinge flanges, with one screw (4) at eachside (picture 12 )

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    123456789012345678

    12

    34 5Figure 11: Installing the BTS Handle

    3. Remove the A9110E BTS protective cap.

    Figure 12: BTS Handle fixed on the module

    20 / 74 3BK 17416 3081 RJZZA Ed.04

  • 3 Installing the Micro - BTS Units

    Install the A9110E BTSin Position

    1. Two people place the unit in the gallows (See Figure 13 )2. The A9110E BTS housing is let down by rotating the handwheel.3. Ensure that the housing descends into the right position.

    Figure 13: Putting the A9110E BTS in Position

    Fix the BTS in Position 1. Fix the housing on the mounting frame with the two screws on top ofhousing (See Figure 14 )

    2. Fix the housing on COBO with the two screws left and right of COBO.

    Figure 14: Fixing the Unit

    Remove the Manual Liftand the Handle

    1. Completely unscrew the handwheel, then remove it2. Remove the gallows from MOFRA, by lifting it (and pushing the safety catch)3. Unscrew the threaded bolt and remove it from the housing4. Detach the BTS-handle from the housing by releasing the screw (5) on

    figure 11.

    3BK 17416 3081 RJZZA Ed.04 21 / 74

  • 3 Installing the Micro - BTS Units

    3.2 Case B: Installation With the Crane

    3.2.1 Specific Safety Instructions for Craning

    You must carefully read the " A9110 Crane Instruction Manual " and theseinstructions before using the crane.

    It is strictly prohibited to stand under a floating crane load during theoperation

    Hot surface warning : Dont handle the crane by its motor after use, thetemperature can exceed 45 degrees Celsius (see left, " Hot Surface "label on the crane)

    Check availability of the completed " Security control - check list and report", enclosed with the crane (see " A9110 Crane Instruction Manual " ) the checkmust be carried out every six months, note the check date in the CCL.

    3.2.2 Installation of the Crane on MOFRAProcedure 1. Check that the lifting ring and the two screws for fixing to MOFRA are

    available2. Mount the lifting ring onto the top part of the micro-BTS unit. The ring must

    be screwed completely (See Figure 15 )3. Put the crane on top of MOFRA. The small safety blade keeps the crane

    in place (See Figure 16 )4. Open the COBO door5. Connect the crane power cable to the ACout BTS power connector (See

    Figure 17 )6. Hook the cables as shown in the drawings.

    Figure 15: Mounting the Lifting Ring

    22 / 74 3BK 17416 3081 RJZZA Ed.04

  • 3 Installing the Micro - BTS Units

    MOFRA

    Crane

    Power cable

    Figure 16: Installing the Crane

    Ac out BTS connector is used to power the crane

    3BK 17416 3081 RJZZA Ed.04 23 / 74

  • 3 Installing the Micro - BTS Units

    Figure 17: ACout BTS Power Connector of ACCO Board is Used to Power the Crane

    3.2.3 Preparation for Craning

    The following checks and precautions must be considered before craning!Depending of the country and customer regulations more tests foroverloading and usage time may be required.To be checked and applied!

    Purpose

    To check the fixing of the MOCO and crane.

    Procedure 1. Check the screws securing the MOCO on the wall2. Define a safety area 2 m around the MOFRA and make sure that nobody will

    enter the area during operations3. Move the unit under the crane on the floor4. Remove the COBO protection cover (3BK 08586 AA).5. Close the circuit breakers that power COBO6. Using the switching box on the crane power cable, let down the lifting

    band to the micro-BTS level7. Hang the unit on the crane (make sure the belt is not turned on itself)8. Lift the unit and suspend it 10 cm above the floor9. Execute a movement up and down with the micro-BTS

    10. Lay the micro-BTS an the floor11. Check the MOFRA - Crane assembly and fixings.

    24 / 74 3BK 17416 3081 RJZZA Ed.04

  • 3 Installing the Micro - BTS Units

    3.2.4 Installing the Micro-BTS on MOCO

    Figure 18: Lifting and Plugging in the Micro-BTS Unit

    3BK 17416 3081 RJZZA Ed.04 25 / 74

  • 3 Installing the Micro - BTS Units

    Take care not to damage the connectors during the operation.Do not lift the BTS by hand from the ground, use the crane!

    Do not work under powerOpen the circuit breakers to be sure that the power supply isdisconnected.For installation with SSC: Check that the Battery back-up is OFF(red LED is lit) !!!

    PurposeTo install the BTS on the MOCO.

    Procedure 1. Lift the micro-BTS unit to an appropriate level for mounting (See Figure 18 )2. Remove the bottom protection cover of the micro-BTS unit (3BK 08555 AA).3. Fit the handle on the reel of the crane, on the left side4. Move the micro-BTS nearer to the MOFRA (by pushing the handle) and fit it

    onto the guide bolts (there are two guide bolts on MOFRA that must fit intothe back part of the micro-BTS unit)

    5. Plug the micro-BTS unit into the COBO by slowly releasing the unit andfitting the two guide pins of the COBO into the corresponding holes in themicro-BTS housing

    6. Fix the micro-BTS onto the MOCO using the four screws provided (SeeFigure 19 )

    7. Unhook the micro-BTS8. Unplug the crane power cable9. Remove the crane from MOFRA

    10. Unscrew the lifting ring and put it with the crane to avoid losing it.

    26 / 74 3BK 17416 3081 RJZZA Ed.04

  • 3 Installing the Micro - BTS Units

    Figure 19: Fixing the Micro-BTS to MOCO

    3BK 17416 3081 RJZZA Ed.04 27 / 74

  • 3 Installing the Micro - BTS Units

    28 / 74 3BK 17416 3081 RJZZA Ed.04

  • 4 Making the Connections to the BTS

    4 Making the Connections to the BTS

    This chapter describes:

    How to install the integrated antenna, with the integrated antenna option

    How to instal the VSWR detector, with the VSWR option

    How to make the necessary connections to the BTS units

    3BK 17416 3081 RJZZA Ed.04 29 / 74

  • 4 Making the Connections to the BTS

    4.1 OPTION: Installing the Integrated AntennaPurposeTo install the integrated antenna on each micro-BTS unit (master and slaves).

    This procedure is the same for master and slave units.

    Figure 20: Installation of Integrated Antenna (GSM and DCS)Connect the integrated antenna to the upper housing side of the A9110EBTS using the four self tapping screws (M3 x 16) provided in the integratedantenna kit.

    The above figure also shows the special front cover and the final view of aBTS with integrated antenna.On fact, the front cover will not be mounted until the end of commissioning.

    30 / 74 3BK 17416 3081 RJZZA Ed.04

  • 4 Making the Connections to the BTS

    4.2 OPTION: Installing the VSWR DetectorPurpose To install the VSWR detector on each micro-BTS unit (master and slaves)

    This procedure is the same for master and slave units.

    4.2.1 Mechanics

    Figure 21: The VSWR Detector

    3BK 17416 3081 RJZZA Ed.04 31 / 74

  • 4 Making the Connections to the BTS

    4.2.2 Fixing the VSWR Detector

    The VSWR detector can not be used together with an integrated antenna, if theisolation between antennas on the same site is < 25 dB.

    Procedure 1. Unlock the bottom section of the front protective cover, open it upwards andfix it at the front cover by the installed magnetic snap-on fastening

    2. Connect the VSWR detector to the antenna output connector of theA9110E by screwing the N male connector (See Figure 22 )

    3. Connect the VSWR RF jumper cable to the RF output N-female connector ofthe VSWR detector

    4. Connect the standard antenna cable to the RF jumper cable.

    EVOLIUMBTS A9110E

    VSWRdetector

    RF Jumper Cable

    Antenna Jumper

    COBO

    F

    M : Nmale connector F : N female connector

    M F M

    Figure 22: VSWR Detector - RF Installation

    32 / 74 3BK 17416 3081 RJZZA Ed.04

  • 4 Making the Connections to the BTS

    4.2.3 Connecting the CablesProcedure 1. Open the COBO

    2. Unscrew the appropriate PG gland3. Run the ALARM / VCC cable through that PG gland into COBO4. Screw the PG gland with the ALARM/ VCC cable5. Connect the ALARM/ VCC wires inside the COBO to the clamp strips

    located on the ABISCO board as shown in Figure 23 .In a two antenna configuration the isolated wires for VCC-VSWR1 andVCC-VSWR2 and ground (GND) have to be fixed together with the enclosedcable and sleeves and inserted in the described terminals of the ABISCO(See Figure 23 ).

    Figure 23: Connecting the ALARM / VCC Cables

    3BK 17416 3081 RJZZA Ed.04 33 / 74

  • 4 Making the Connections to the BTS

    4.3 Making the Connections to the BTS

    One lower slave cannot be equipped because of 12 TRX limitation!Depending on site configuration, you can have maximum 3 lower slave unitson the 4 possible positions: Slave11, Slave12, Slave 21, Slave 22.When connecting a slave unit, the position where to plug the IEB cable intomaster unit (S1 or S2 connectors) will determine if it is Slave1 or Slave2.

    Purpose

    To connect the antenna

    To connect the IEB cables in a master-slave configuration.

    Procedure 1. With the integrated antenna option, connect the integrated antennas RFcables to the antenna connector(s) of the micro-BTS unit (master andslaves, as appropriate)

    2. With external antennas, connect the antenna jumper(s) to the antennaconnector(s) of the micro-BTS units (master and slaves) according to theirsector number (See Information Required (Section 1.8) )

    3. To install the slave units, connect the IEB cables between the master andslaves:

    At the Master unit plug the cable into the Conn. to Slave 1 or Conn. to Slave 2 connector, depending the slave (1 or 2) that isgoing to be connected

    At the Slave 1 unit plug the cable from master into the Conn. toMaster connector. Plug the cable to Slave 11 into Conn. to Slave 1 and / or the cable to Slave 12 into Conn. to Slave 2.

    At the Slave 2 unit plug the cable from master into the Conn. toMaster connector. Plug the cable to Slave 21 into Conn. to Slave 1 and / or the cable to Slave 22 into Conn. to Slave 2.

    At the Slave 11 unit and / or Slave 12 unit plug the cables from Slave1into the Conn. to Master connector.

    At the Slave 21 unit and / or Slave 22 unit plug the cable from Slave2into the Conn. to Master connector.

    34 / 74 3BK 17416 3081 RJZZA Ed.04

  • 4 Making the Connections to the BTS

    To SLAVE 2

    MASTER

    To SLAVE 1

    From MASTER

    SLAVE 1

    To SLAVE 11 To SLAVE 12 From MASTER

    SLAVE 2

    To SLAVE 21

    SLAVE 12

    From SLAVE 1From SLAVE 1

    SLAVE 11 SLAVE 21

    From SLAVE 2

    Figure 24: Connection of IEB PG 11 Glands to COBO for all modules

    3BK 17416 3081 RJZZA Ed.04 35 / 74

  • 4 Making the Connections to the BTS

    36 / 74 3BK 17416 3081 RJZZA Ed.04

  • 5 Checking Power Supply and Powering Up

    5 Checking Power Supply and Powering Up

    This chapter describes how to check the power supply voltage and power upthe micro-BTS units (master and slaves).

    Before checking the power supply and powering up the micro-BTS, ensurethat the safety instructions in the SAF procedure are followed ( See BSSMethods Handbook ). It is essential that:

    The protective earth is connected to the equipment earth terminal

    The ACout BTS connectors in the COBOs (Figure 25 ) that feed themicro-BTS units are disconnected.

    3BK 17416 3081 RJZZA Ed.04 37 / 74

  • 5 Checking Power Supply and Powering Up

    5.1 Case 1: A9110E BTS Without SSCProcedure 1. Check the power panel to make sure the breakers are OFF

    2. Using a multimeter, check at each COBO that there is no voltage between L(line) and N (neutral) , N and PE (protective earth), L and PE (See Figure 25 )

    3. Close the circuit breakers at the power panel4. Check the voltage (220 V AC) between line (L) and neutral (N) on the

    ACout BTS connector of each COBO5. Check that there is no voltage between N and PE6. Power up the unit by plugging in their ACout BTS connectors.

    FIRST power up the master unit, THEN power up the slave units!The slave units MUST be powered up within seconds after poweringup the master unit.

    5.2 Case 2: A9110E BTS With SSCProcedure 1. Check the power panel to make sure the SSC breakers are OFF

    2. Check the SSC to make sure main AC switch S1 is off and no green LEDsare lit (See Figure 26 )

    3. Close the circuit breakers at the site power panel4. Close main switch S1, the AC mains breaker then the BTS1, BTS2,

    BTS3 circuit breakers in the SSC5. Check the 220 V AC voltage between line (L) and neutral (N) on the ACout

    BTS connector (X401) of each COBO (See Figure 25 )6. Check that there is no voltage between N and PE7. Check that the Mains Power supply 1 and 2 and Charger LEDs are lit on

    the SSC front panel8. Push (if necessary) the Battery backup button to on (red LED is not lit)9. Power up the A9110E units by plugging in their ACout BTS connectors.

    FIRST power up the master unit, THEN power up the slave units!The slave units MUST be powered up within seconds after poweringup the master unit.

    10. Check that the BTS remains on battery supply if main switch S1 isdisconnected, then set the switch S1 to ON

    11. Push and hold down the Fan Test button and check that the SSC top fansare working.

    38 / 74 3BK 17416 3081 RJZZA Ed.04

  • 5 Checking Power Supply and Powering Up

    If the BTS must be powered down, disconnect the batteries first by pushingthe Back-up Off switch to ON (red LED is lit), then set the main powerswitch S1 to OFF.

    BTS fuses(T=2.5 A)

    FAN fuses(T=2.5 A)

    L

    N

    L

    N

    SLAVE 1SLAVE 2X403X404

    X401

    X402

    X400

    ACoutBTS

    IEC Conn.

    FAN

    ACin, Mains

    L

    L

    LL

    N

    NN

    NPE

    PE PE

    PE

    Figure 25: ACCO Board

    PS1 PS2 PS3

    Battery unit

    AC Connection Area

    S1

    BatterybackUpbutton

    BackUpOff

    Power 230V ACSocket AC 230V AC mains

    m

    BTS1m

    BTS2m

    BTS3

    Fan Test

    Power Supply 1Power Supply 2

    ChargerMains

    Figure 26: SSC Switch Configuration

    3BK 17416 3081 RJZZA Ed.04 39 / 74

  • 5 Checking Power Supply and Powering Up

    40 / 74 3BK 17416 3081 RJZZA Ed.04

  • 6 Commissioning Tests

    6 Commissioning Tests

    This chapter describes the following operations:

    BTS software downloading

    Setting antenna mapping

    BTS initialization

    Performing BTS inventory

    Setting and checking the external alarms

    Checking status of modules

    Checking the antenna VSWR

    Abis loop test

    End of commissioning.

    Use the antistatic wrist strap when working with the ABISCO board.Check that the BTS is isolated :At the DDF side by disconnecting terminals, from the PCM link comingfrom the network.For installation with SSC, by disconnecting connectors X2, X3 and X4on the connection area.

    One lower slave cannot be equipped because of 12 TRX limitation!Depending on site configuration, you can have maximum 3 lower slave unitson the 4 possible positions: Slave11, Slave12, Slave 21, Slave 22.Configuration is determined by IEB cable connections between units

    3BK 17416 3081 RJZZA Ed.04 41 / 74

  • 6 Commissioning Tests

    6.1 BTS Software DownloadingStart up BTS Terminal 1. Connect the BTS Terminal cable between the COM1 port of the PC and

    the MMI connector (X100) on the ABISCO board of the master unit (SeeFigure 28 )

    2. Launch the BTS Terminal according to the OS used (Windows NT)3. At the BTS Terminal:

    User / Group name:COMMTE

    Password:COMMTE

    Click [ Logon ].4. If the Setup Information window is displayed:

    Click [ Baudrate ] then select 115200 and the port for serial interface inthe BTS Terminal part of the window

    Select the Misc tab and if not already done, click [ Browse ] and selectthe path to INVENTAR (usually c:\WINVENT\Program\pwinvent.exe)Click [ Ok ].

    5. In the main menu select the terminal:Select BTS Terminal (Evolium BTS)

    6. Establish the connection:File Connect / DisconnectA message appears to confirm the connection.

    OPTION: Only if the Files are not Already on the PC1. Create the directory : c:\A9110_fls2. Copy all the BTS SW files into the above directory.

    Download the BTS Withthe BTS TE

    1. Commissioning Download BTS-SW...

    If a message asking you to check the Qmux address appears, set the correctQmux address and save it !

    Select at List files of type: on the left bottom corner: All files (*.*)Masterfile: bm*sat**.*** (1) (See InformationRequired (Section 1.8) )CPF File: 00o2at**.ddl (1)

    (1) Click [ Browse ] to give the path of each file: c:\A9110_fls2. Click [ Download ].

    Check the Downloadingof the BTS

    1. A disconnection occurs during the download, wait for the connection tobe re-established

    2. The message The connection to the OMU has been established !appears

    3. The following messages or windows appear during downloading:No operator action during next 80 seconds!!!

    42 / 74 3BK 17416 3081 RJZZA Ed.04

  • 6 Commissioning Tests

    BTS SW download in progress...Start operational software...No operator action during next 80 seconds!!!BTS SW download in progress...Initialization in progress...Receiving data...Reading all RIs .

    If the file downloading stops during several minutes and the BTS Terminalis showing no message or action, perform a second download of the BTS( See Download the BTS With the BTS TE (in section 6.1) .)

    BE PATIENT: WAIT for the Edit frequencies window, about 5 mn:1. Select the Frequency band (GSM 900/ DCS 1800/ DCS 1900/ EGSM)2. Select the test frequency by clicking [ Add ] or [ Remove ] in Available

    ARFNs list to obtain the correct frequencies in Select ARFNs list. Thetest frequencies are given by the customer (See Information Required(Section 1.8) ).

    3. Click [ Submit ].

    6.2 Setting Antenna MappingPurpose To set the antenna mapping table.

    ProcedureOpen the antenna mapping window:Commissioning Edit Sector mappingThe Sector mapping Micro BTS window appears (See Figure 27 )Set the mapping of BTS units ports to sectors, according to the requestedconfiguration and the mapping rules (See Information Required & AntennaPort and External Alarm Mapping Rules (Appendix D) )Click [ Save ]Wait for Updating flash... and Cabling detection in progress... messages to disappear.

    3BK 17416 3081 RJZZA Ed.04 43 / 74

  • 6 Commissioning Tests

    Figure 27: Sector Mapping Micro BTS Window

    6.3 BTS InitializationInitialize Commissioning 1. At BTS Terminal select:

    Commissioning Initialization All sectors...

    2. Wait for the Initialization for commissioning in progressmessage to disappear

    3. The HW check configuration window appears4. Check that the configuration shown in the HW check configuration

    window corresponds to the requested HW configuration (See InformationRequired (Section 1.8) )

    5. Wait for the MTRE and ANX module downloading to finish.

    Workaround: If the HW check configuration window information does not correspondto the antenna mapping information written in RI (this behaviour appearsusually when the final antenna mapping information is different from the initialinformation), repeat the initialization of all sectors (steps 1 and 2).

    44 / 74 3BK 17416 3081 RJZZA Ed.04

  • 6 Commissioning Tests

    Activation is finished when the options in the commissioning menu becomesactive.

    6.4 Performing BTS Inventory1. Use the tasks specified in CI 08 - Site Equipment Inventory for:

    Adding additional modules in RI

    Executing the Inventar program for the BTS

    2. For SSC installation, the SSC is considered as an additional module.

    Check that there are no alarms when running the Inventar for BTS. Thismeans that the modules inside the BTS meet the requirements for aspecific customer.

    6.5 Setting and Checking the External AlarmsPurpose

    To set the external alarm mapping in the RI according to requirements

    To check the reporting of external alarms to the BTS TE.

    6.5.1 Set and Check the Alarm MappingSet the logical numberof the external alarms

    1. AT BTS Terminal select:Commissioning Edit Remote Inventory (RI)...

    2. Module selection: UT_BTS_BCB 173. Click [ Upload ]4. Click [ Application part ]5. In the Application part window set the external alarm mapping according

    to the rules in the Appendix (See Information Required (Section 1.8) &Antenna Port and External Alarm Mapping Rules (Appendix D) )

    6. Click [ Manufacturing part ]7. Click [ Write back ] if modifications were made. Wait for Updating

    flash... message to disappear.8. Click [ Close ].

    Loop the External Alarm Loop the External Alarm Inputs that are not Connected to Their Sensors1. On the DDF loop the external alarms that are not connected to their sensors

    to avoid reporting of alarms to the OMC-R2. On the ABISCO board of each unit (master or slave) loop the declared alarm

    inputs that do not reach the DDF and are not yet connected to their sensors.

    3BK 17416 3081 RJZZA Ed.04 45 / 74

  • 6 Commissioning Tests

    6.5.2 Test the External Alarms

    Check the Alarms 1. On the BTS Terminal display the external alarms2. Monitor Active Alarms3. On the BTS Terminal check that there are no external alarms.

    Check the Alarms in DDF If the external alarms are transferred to a terminal block, generate analarm and check its appearance on BTS Terminal1. Open the circuits corresponding to the external alarms on the DDF side, by

    inserting a red disconnecting pin into the terminal block2. On the BTS Terminal, check that the appropriate alarm message is

    generated3. Close the circuit that has been opened at the terminal block by removing the

    disconnecting pin4. On the BTS Terminal, check that the external alarm message has

    disappeared.

    Check the Alarms ThatDo Not Reach the DDF

    In COBO (master and slaves)1. For the declared external alarms that do not reach the DDF, generate an

    alarm by opening and then closing a loop (See Connectors Description (inappendix C) in appendix for connectors description)

    2. Check alarm reporting on the BTS Terminal.

    Note: If the Fan option was included, check the fan alarm:1. Disconnect the fan power supply cable from ACCO board2. On the BTS Terminal , check that the alarm is present:

    BTS1, BTS EXTERN, Air condition (1)

    3. Plug in the fan power supply cable and check that the alarm is cleared.

    Note: If the SSC option was included, check the external alarms:1. Set the mains switch S1 to OFF to check mains power failure2. On the BTS Terminal, check that alarm 2 is present, then set switch S1

    to ON again3. On the BTS Terminal, check that alarm 3 is present (SSC door open) by

    completely closing (with the key) and opening the door.Note: If the VSWR option was included, check the external alarms:

    1. Make the connections as follows:

    For A9110E BTS units with one antenna output: use ANT A and the following MTREs for transmission:

    UT_TRE 18 or UT_TRE 19 for masterUT_TRE 38 or UT_TRE 39 for slave 1UT_TRE 54 or UT_TRE 55 for slave 2.UT_TRE 42 or UT_TRE 43 for slave 11.UT_TRE 46 or UT_TRE 47 for slave 12.UT_TRE 58 or UT_TRE 59 for slave 21.UT_TRE 62 or UT_TRE 63 for slave 22.

    46 / 74 3BK 17416 3081 RJZZA Ed.04

  • 6 Commissioning Tests

    For A9110E BTS units with two antenna outputs use ANT A and the following MTREs for transmission:

    UT_TRE 19 for masterUT_TRE 39 for slave 1UT_TRE 55 for slave 2.UT_TRE 43 for slave 11.UT_TRE 47 for slave 12.UT_TRE 59 for slave 21.UT_TRE 63 for slave 22.

    use ANT B and the following MTREs for transmission:UT_TRE 18 for masterUT_TRE 38 for slave 1UT_TRE 54 for slave 2.UT_TRE 42 for slave 11.UT_TRE 46 for slave 12.UT_TRE 58 for slave 21.UT_TRE 62 for slave 22.

    2. Check if an alarm is present at BTS Terminal:

    Commissioning Output Power Test

    In the Output Power Test window select the MTRE Number:UT_TRE** (See above)Select one timeslot and click [ On ] to enable the powerSelect an attenuation of -10dB on the used timeslot

    Click [ Start ]Wait for the BTS to start the emission

    Disconnect the antenna cable from the RF jumper cable.

    As the power level is lower than 50mW you are allowed to disconnect the cable..

    Wait 15 seconds to see if an alarm is sent to the BTS Terminal.

    At the BTS Terminal choose:Monitor Active alarms

    Check that an Alarm related to the tested TRE is present

    Connect the antenna cable to the RF jumper cableCheck at the BTS Terminal that no alarms are present

    3BK 17416 3081 RJZZA Ed.04 47 / 74

  • 6 Commissioning Tests

    Click [ Stop ]Wait for MTRE to stop transmission.

    After pressing the [ Stop ] button wait until MTRE stops transmission.Follow the messages that appear in the bottom part of the window,which indicates the state of MTRE.

    3. Repeat the actions from step 2 for all the antenna outputs of all BTSunits (master and slaves).

    6.6 Checking the Status of ModulesCheck the Status of

    the BTS1. At BTS Terminal choose:

    Monitor BTS Modules

    2. Check that BTS, CLLK, OMU and EACB are IT3. Check that the MTREs and TR_CLK are OP.

    Check the Active Alarms 1. At BTS Terminal choose:Monitor Active Alarms

    2. Check that there are no alarms present.

    6.7 VSWR CheckPurpose

    To connect the BTS to the antenna

    To check the Voltage Standing Wave Ration (VSWR) of the transmit antenna.

    Before transmitting on the antenna:

    Check that transmission is allowed at the nominal frequency

    If there are no antennas, measure the VSWR across the load.

    The VSWR measurement must be performed for each antenna output!

    Connect the PowerMeter/ Reflectometer

    Connect the power meter/ reflectometer between the BTS antenna jumperand antenna or load as appropiate1. For A9110E BTS units with one antenna output:

    connect the power meter/ reflectometer to the antenna jumper connectedto ANT A and use the following MTREs for transmission:

    UT_TRE 18 or UT_TRE 19 for master

    UT_TRE 38 or UT_TRE 39 for slave 1

    UT_TRE 54 or UT_TRE 55 for slave 2.

    UT_TRE 42 or UT_TRE 43 for slave 11.

    48 / 74 3BK 17416 3081 RJZZA Ed.04

  • 6 Commissioning Tests

    UT_TRE 46 or UT_TRE 47 for slave 12.

    UT_TRE 58 or UT_TRE 59 for slave 21.

    UT_TRE 62 or UT_TRE 63 for slave 22.

    2. For A9110E BTS units with two antenna outputs connect the power meter/ reflectometer to the antenna jumper connectedto ANT A and use the following MTREs for transmission:

    UT_TRE 19 for master

    UT_TRE 39 for slave 1

    UT_TRE 55 for slave 2.

    UT_TRE 43 for slave 11.

    UT_TRE 47 for slave 12.

    UT_TRE 59 for slave 21.

    UT_TRE 63 for slave 22.

    connect the power meter/ reflectometer to the antenna jumper connectedto ANT B and use the following MTREs for transmission:

    UT_TRE 18 for master

    UT_TRE 38 for slave 1

    UT_TRE 54 for slave 2.

    UT_TRE 42 for slave 11.

    UT_TRE 46 for slave 12.

    UT_TRE 58 for slave 21.

    UT_TRE 62 for slave 22.

    Measure the VSWR Measure the VSWR of the antenna (VSWR1) or across the load (VSWR2) ifthere is no antenna

    Measure the VSWR ofthe antenna (VSWR1) 1. At BTS Termial choose:

    Commissioning Output Power Test

    2. In the Output Power Test window select the MTRE Number: UT_TRE**(See above)

    3. All Timeslots: click [ On ] to enable the power4. Select an attenuation of -4dB on each timeslot from TS0 to TS75. Click [ Start ]6. Record the VSWR value (VSWRx):

    VSWR 1 when measuring with antenna connected

    VSWR 2 when measuring across the load.

    7. Click [ Stop ]8. Wait for MTRE to stop transmission.

    3BK 17416 3081 RJZZA Ed.04 49 / 74

  • 6 Commissioning Tests

    Do not disconnect the power meter, the antenna or the load during MTREtransmission. After pressing the [ Stop ] button wait until MTRE stopstransmission.Follow the messages that appear in the bottom part of the window,which indicates the state of MTRE.

    Measure the VSWR(VSWR 2) Using a Load

    If antenna VSWR 1 > 1.3 measure the VSWR (VSWR 2) using a load1. Instead of antennas use 50 ohm loads2. Measure the VSWR 2 values with the BTS TE in the same way as in

    Measure the VSWR of the antenna (VSWR1)3. Analyze the results: (See Table 1 )

    VSWR 1 is the VSWR value measured in Measure the VSWR ofthe antenna (VSWR1)VSWR 2 is the VSWR value measured in Measure the VSWR (VSWR2) Using a Load.

    Value Sanction Action

    VSWR 2 >1.2 Fault in equipment supplied byAlcatel

    Check the tightness of theconnectors

    VSWR 2 1.2 andVSWR 1 1.5

    Fault on the feeder or antenna(when present)

    Inform the operator that theVSWR is within a critical range

    VSWR 2 1.2 andVSWR 1 >1.5

    Fault on the antenna or feeder(when present)

    Report the high reading to theSite Manager

    Table 1: Interpretation of VSWR Results

    Finish the Measurement 1. Disconnect the power meter and reconnect the antenna jumper tothe antenna or load as the case

    2. Repeat steps 1 to 4 for all the antenna outputs of all the BTS units(master and slaves)

    50 / 74 3BK 17416 3081 RJZZA Ed.04

  • 6 Commissioning Tests

    6.8 Abis Loop TestPurpose To test the PCM cabling between the master unit and DDF.

    For Microwave or TNL installation in SSC for PCM connection, do not performAbis loop test.

    Procedure 1. At BTS Terminal choose:

    Commissioning Station Unit Test...

    The Station Unit Test window appears.

    In the Station Unit Test window, select external loop

    Click [ Start ].

    A message appears prompting you to fit the shortcut connector.Do not use any shortcut connector, because you are testing the cabling tothe DDF, not the ABISCO board.

    2. At the DDF (not on ABISCO) set up loops between TX and RX for Abis1and Abis2, using wires.

    It is important for both Abis links to be looped!

    3. At BTS Terminal:

    Click [ Ok ]Remove the loops when the respective message window appears andthen click [ Ok ]Wait for the test to finish

    Check that the list of tests shown in the Station Unit Test window is Ok

    Click [ Cancel ].

    6.9 End of CommissioningPurpose

    To update the Remote Inventory of all the modules according to the site

    To perform an inventar in case any modules were changed duringcommissioning

    To end the commissioning phase

    To save the commissioning report.

    Procedure 1. At BTS Terminal :Commissioning Endcommissioning

    3BK 17416 3081 RJZZA Ed.04 51 / 74

  • 6 Commissioning Tests

    2. Check that the commissioning date is correct:

    If not, click [ Close ] and click [ Cancel ]Modify the internal date of the PC (in Control Panel)Go back to step 1.

    3. Give the name of the BTS site (< 10 characters) and the NetworkIdentity.

    4. Select all the modules from the list on the left (if any) to enter them inthe modules to be updated list

    Click [ Add ] for all the modules on the left (if any)Click [ Submit ].

    The following message appears: Do you want to execute INVENTARnow?

    5. Option: If any modules were added or changed during commissioning,run Inventar:

    Click [ Yes ]The Receiving Remote Inventory Data message appears, and theINVENTAR application is launched

    Use the tasks specified in CI 08 - Site Equipment Inventory for thefollowing actions:

    Adding additional modules in RI (if appropiate)Running Inventar for the BTS.

    6. Option: If no modules were added or changed during commissioningclick [ No ]

    When you end commissioning, the BTS is automatically reset after about 2minutes (the connection is lost for about 5s).Wait until the connection with the BTS is reestablished.The BTS is then ready for downloading from the BSC.

    7. Save the Commissioning Report window:

    Click [ Commissioning Report ] window to make it activeFile Save As...

    Give a name to the file (Site name and number of BTS - no more then 8characters) and save the file to a floppy disk.

    52 / 74 3BK 17416 3081 RJZZA Ed.04

  • 7 Setting Transmission Module Parameters

    7 Setting Transmission Module Parameters

    This chapter describes how to configure the transmission module of the SUMboard.

    3BK 17416 3081 RJZZA Ed.04 53 / 74

  • 7 Setting Transmission Module Parameters

    Purpose

    To set the Qmux address

    To set the OML TS and signalling rate, if this information is provided.

    Make sure the BTS is isolated at the DDF from the network beforeproceeding.

    Procedure 1. Set the Qmux address:

    At BTS Terminal choose:Settings Transmission Initial Settings...

    The Receiving current configuration data... window appears.

    Enter the parameter:Qmux address

    Click [ Transmit ]Click [ Close ].

    2. OPTION: Set the position and signalling rate for OML, if required:

    Settings Transmission Board Configuration...

    Click [ Get Config ]Set the signaling TS number and the signalling rate for OMU 1

    Click [ Transmit ]Click [ Close ].

    54 / 74 3BK 17416 3081 RJZZA Ed.04

  • 8 Download the Operational Software

    8 Download the Operational Software

    This download of the operational software must be done in B6 and in B7software versions older than BSSSAT02G (B7 MR6).Do not execute this section if the corresponding BSC in the network runssoftware version BSSSAT02G (B7 MR6) or higher.

    3BK 17416 3081 RJZZA Ed.04 55 / 74

  • 8 Download the Operational Software

    8.1 Download the Operational SoftwareConnect the Terminal 1. Connect the BTS Terminal (BTSWATU1 or higher) cable between the

    COM1 port of the PC and the MMI connector (X100) on the ABISCOboard of the master unit.

    2. Launch the BTS Terminal according to the OS used (Windows NT)3. At the BTS Terminal:

    User / Group name:COMMTE

    Password:COMMTE

    Click [ Logon ].4. In the main menu select the terminal:

    Select BTS Terminal (Evolium BTS)5. Establish the connection:

    File Connect / DisconnectA message appears to confirm the connection.

    Download theOperational Software

    1. Only if the files are not already on the PC:Copy all the A9110E operational software files (BMXSAT49F or higher)into c:\A9110_op_sw (create the directory if the case).

    2. Commissioning Download BTS-SW...Select at List files of type: on the left bottom corner: All files (*.*)

    Masterfile: bmxsat*9.49* (1)CPF File: 00o2atl*.ddl (1)

    (1) Click [ Browse ] to give the path of each file: c:\A9110_op_sw3. Click [ Download ].

    Follow the Downloadingof the BTS

    1. The following messages or windows appear during downloading:No operator action during next 80 seconds!!!BTS SW download in progress...Start operational software...No operator action during next 80 seconds!!!BTS SW download in progress...Initialization in progress...Receiving data...Reading all RIs .

    If the file downloading stops during several minutes and the BTS Terminalis showing no message or action, perform a second download of the BTS.

    BE PATIENT: 2. WAIT for the Edit frequencies window, about 5 mn.3. Select the Frequency band (GSM 900/ DCS 1800/ DCS 1900/ EGSM)4. Select the test frequency by clicking [ Add ] or [ Remove ] in Available

    ARFNs list to obtain the correct frequencies in Select ARFNs list. Thetest frequencies are given by the customer (See Information Required(Section 1.8) ).

    5. Click [ Submit ].The Sector mapping Micro BTS window appears.

    56 / 74 3BK 17416 3081 RJZZA Ed.04

  • 8 Download the Operational Software

    6. Close the sector mapping window without any modification.

    8.2 Initialize the Operational SoftwareInitialize the Operational

    Software1. At BTS Terminal select:

    Commissioning Initialization All sectors...

    2. Wait for the Initialization for commissioning in progressmessage to disappear

    3. The HW check configuration window appears4. Wait for the MTRE and ANX module downloading to finish.

    Activation is finished when the options in the commissioning menu becomesactive.

    8.3 Check the Module Status and Reset the BTSCheck the Status of

    the BTS1. At BTS Terminal choose:

    Monitor BTS Modules

    2. Check that BTS, CLLK and OMU and are IT.Ignore the error if present on EACB.

    3. Check that the MTREs and TR_CLK are OP.

    Reset the BTS 4. In the main menuCommissioning Reset BTS

    5. Disconnect the BTS Terminal after the reset have been executed.

    3BK 17416 3081 RJZZA Ed.04 57 / 74

  • 8 Download the Operational Software

    58 / 74 3BK 17416 3081 RJZZA Ed.04

  • 9 Connecting to the BSC

    9 Connecting to the BSC

    This chapter describes how to connect the BTS to the BSC and verify theOML status.

    3BK 17416 3081 RJZZA Ed.04 59 / 74

  • 9 Connecting to the BSC

    Purpose To connect the BTS to the BSC and check the OML status.

    Procedure 1. Connect the BTS to the BSC:

    Check that the BIE connectors are connected

    With BTS connected via the site distribution frame and an equipment distribution frame: disconnect the loop between the transmit andreceive terminal blocks on the site distribution frame

    With SSC option: connect the PCM cable to connectors X2, X3 andX4 in the SSC connection area.

    2. Check the state of the OML: on the SUM board check that the OML LEDis ON (indicating the OML is IT).

    For further information about downloading the BTS from the BSC andnetwork integration refer to Add BTS procedure.

    60 / 74 3BK 17416 3081 RJZZA Ed.04

  • 10 Finishing Commissioning

    10 Finishing Commissioning

    This chapter describes the final operations before leaving the site.

    3BK 17416 3081 RJZZA Ed.04 61 / 74

  • 10 Finishing Commissioning

    Purpose

    To leave the site

    To return the commissioning report and inventory files to base.

    Procedure 1. Leave the BTS powered up2. Leave the log book on site3. Close the COBO door4. Reposition the front cover and lock the bottom cover (if appropriate)5. Close the SSC door (if appropriate)6. Check the CCL and the appendices7. Remove all other packaging and surplus equipment.8. Clean the site9. Close the site and hand the keys to the key holder

    10. Return the completed forms and the inventory file related to the operationto base.

    62 / 74 3BK 17416 3081 RJZZA Ed.04

  • Appendix A : Abbreviations

    Appendix A: Abbreviations

    Abis Abis Interface: Interface between BSC and BTS

    ABISCO ABIS COnnection board

    AC Alternating Current

    ACCO Alternating Current Connection board

    AN Antenna Network

    BCB BTS Control Bus

    BCCH Broadcast Control Channel

    BSC Base Station Controller

    BSS Base Station Subsystem

    BTS Base Transceiver Station

    CLK Clock

    COBO COnnection BOx

    CPF Configuration Parameters File

    DC Direct Current

    DDF Digital Distribution Frame

    Dual Rate Full rate and Half rate

    E-GSM Extended band GSM

    ETS European Telecomunication Standard

    FIT Failure In Time

    GSM Global System for Mobiles (900 MHz)

    IEB Inter Entity Bus (between master and slave units)MD Multi Drop

    MDT Manufacturers Delegate Testing

    MMI Man Machine Interface

    MOCO MOFRA+COBO

    MOFRA MOunting FRAme

    MSC Mobile Switching Centre

    3BK 17416 3081 RJZZA Ed.04 63 / 74

  • Appendix A : Abbreviations

    MSUMA Micro-BTS Station Unit Module

    MTRE Micro-BTS Transceiver

    MUX Multiplexer

    O&M Operation and Maintenance

    OMC Operation and Maintenance Centre

    OMC-R Operation and Maintenance Centre - Radio (OMC of BSS)

    OML Operation and Maintenance Link

    OMU Operation and Maintenance Unit

    PCM Pulse Code Modulation (PCM link = 2.048 Mbit/s terrestrial link)

    RF Radio Frequency

    RI Remote Inventory

    RIT Replaceable ITem

    RSL Radio Signalling Link

    SDCCH Slow Dedicated Control Channel

    SBL Security BLock

    SSC Site Support Cabinet

    TCH Traffic Channel

    TRE TRansceiver Equipment

    TREA TRE - Analog part

    TRED TRE - Digital part

    VSWR Voltage Standing Wave Ratio

    XBCB External BTS Control Bus

    XIN External Input

    64 / 74 3BK 17416 3081 RJZZA Ed.04

  • Appendix B : List of Items Required

    Appendix B: List of Items RequiredInstallation Kits The following table is used to check, on site, the mandatory or optional delivery

    item kits.The used symbols are:

    mandatory kit

    technical choice kit

    customer option kit

    Optional kits for BTS configuration Mnemo Reference Qty

    Integrated antenna for GSM band PUIT - ANTG 3BK 08581 AAAA 1/ unit

    Integrated antenna for DCS band PUIT - ANTD 3BK 08582 AAAA 1/ unit

    VSWR detector for GSM band VSWG 3BK 25062 AAAA 1/ ant

    VSWR detector for DCS band VSWD 3BK 25063 AAAA 1/ ant

    .

    List of DocumentsRequired

    The following table is used to check, at base, the availability of the necessarydocuments.

    Catalogue of Technical and Logistic Information (ITL) 3DF 00462 0004 AAAGACatalogue of Instruction Operation (IO) 3DF 00300 0004 UAZZABSS Methods Handbook release B7 3BK 17416 0002 PCZZA

    CI 08 Site Equipment Inventory 3BK 17257 0001RJZZA

    Tools Catalogue for Field Activity 3BK 20458 0001 RJZZA

    Site premises inspection form (CEL) 8BL 00704 0015 DRBRA

    SPP 36 - Specification for site preparation A9110 BTS 8BL 00704 0052 DRAGA

    BSS site premises inspection, post handover 8BL 00704 0016 DRBRA

    A9110 Crane HW Instruction Manual 3BK 20489 AAAA PCZZA

    3BK 17416 3081 RJZZA Ed.04 65 / 74

  • Appendix B : List of Items Required

    List of SoftwareRequired

    The following table is used to check, at base, the availability and version ofthe necessary software;refer to corresponding document for checking theSW version.

    Name Version checking

    Operating system See Tools Catalogue

    A9110E BTS commissioning

    BTS-Terminal

    A9110E BTS-SW

    Operational software for the BTS

    BTSCAT02B (B7 MR6 Commissioning package) / TEBTSCAT02B (B7 MR6 Commissioning package) / SWBMxSAT49F or higher

    .

    Tools Required The following table is used to check, at base, the availability of the necessarytools (See Tools Catalogue for content checking).

    Kit name Reference Calibration

    Utility PC DES 002 NO

    Power/ reflectometer DES 003 YES

    Basic toolkit OUT 001 NO

    Specific toolkit for A9110/A9110E BTS OUT 006 NO

    Test cables and plugs for A9110/A9110E BTS OUT 013 NO

    Radio connection kit OUT 014 NO

    66 / 74 3BK 17416 3081 RJZZA Ed.04

  • Appendix C : Description of ABISCO and ACCO Boards

    Appendix C: Description of ABISCO and ACCO Boards

    ABISCO Boards .

    Figure 28: ABISCO board for A9110E

    3BK 17416 3081 RJZZA Ed.04 67 / 74

  • Appendix C : Description of ABISCO and ACCO Boards

    X104,X115

    X105,X112

    X106,X110

    X107,X102

    X100: MMI

    X109CALCLK

    LED5: ABIS1LED6: ABIS2

    LED7*see table

    X200

    LED4BTS_LMT OK

    LED1: SLAVE1

    LED2: SLAVE2

    LED3: MASTER

    LED8 : MPSON

    X108FCLK

    X211 HDSLX210 ABISTRACE

    Figure 29: ABISCO board for A9110

    68 / 74 3BK 17416 3081 RJZZA Ed.04

  • Appendix C : Description of ABISCO and ACCO Boards

    Connectors Description .

    Figure 30: Connectors and LEDs on ABISCO

    3BK 17416 3081 RJZZA Ed.04 69 / 74

  • Appendix C : Description of ABISCO and ACCO Boards

    ACCO Board .

    BTS fuses(T=2.5 A)

    FAN fuses(T=2.5 A)

    L

    N

    L

    N

    SLAVE 1SLAVE 2X403X404

    X401

    X402

    X400

    ACoutBTS

    IEC Conn.

    FAN

    ACin, Mains

    L

    L

    LL

    N

    NN

    NPE

    PE PE

    PE

    Figure 31: Mechanical Drawing of ACCO

    AC in

    FFKDSA/V1 7.62

    (FFKDSA/V1 7.62)for 2.5 qmm

    FFKDSA/V1 7.62

    ACo2

    ACo1

    X404

    X403

    X400

    LP

    T=2 x 2.5 A

    T=2 x 1.25 A

    GICV 2.5/ 3GF7.62

    X402

    X401

    AC

    AC BTS

    IEC connector(cable lenght ~ 10 cm)

    Figure 32: Electrical Drawing of ACCO

    70 / 74 3BK 17416 3081 RJZZA Ed.04

  • Appendix D : Antenna Port and External Alarm Mapping Rules

    Appendix D: Antenna Port and External Alarm MappingRules

    Rules for antenna port mapping

    If there is an antenna port on a micro-BTS unit (master or slave), thecorresponding field will be completed with the sector number (1...6)If there is no antenna port (units with one antenna output or unconnectedslaves) the corresponding port will be completed with 0 (disabled)Example 1:Master unit with no slaves, two antenna outputs 1x2:

    Master port A: 1 Master port B: 1

    Example 2:Master-slave configuration 3x4, no diversity

    Master port A: 1 Master port B: 0

    Slave 1 port A: 1 Slave 1 port B: 0

    Slave 11 port A: 2 Slave 11 port B: 0

    Slave 12 port A: 2 Slave 12 port B: 0

    Slave 2 port A: 3 Slave 2 port B: 0

    Slave 21 port A: 3 Slave 21 port B: 0

    Example 3:Master-slave configuration 2x6, with diversity

    Master port A: 1 Master port B: 1

    Slave 1 port A: 2 Slave 1 port B: 2

    Slave 11 port A: 2 Slave 11 port B: 2

    Slave 12 port A: 2 Slave 12 port B: 2

    Slave 2 port A: 1 Slave 2 port B: 1

    Slave 21 port A: 1 Slave 21 port B: 1

    3BK 17416 3081 RJZZA Ed.04 71 / 74

  • Appendix D : Antenna Port and External Alarm Mapping Rules

    Rules for alarm mapping

    The mapping for alarms 9-56 are take into consideration only if the slave unitsare installed. Otherwise they are considered disabled and are not reported.

    All the alarms that are not used are set to 255 . This means that they aredisabled.

    Select each external alarm 1- 56 (See Figure 28 ) and modify the logicalnumber as required.

    If you select [ Default Setting ] in the Remote Inventory window ofUT_BCB_17, the good values will be directly mapped for the alarms, detailed inthe following tables.

    Note: If the Fan Option was chosen, typical mapping of the fan alarms is:

    Ext. alarm(physical)

    Number (logical) to bemapped for dedicatedexternal alarm reporting

    Refers to...

    08 234 Fan Alarm Master

    16 235 Fan Alarm Slave 1

    24 236 Fan Alarm Slave 2

    32 237 Fan Alarm Slave 11

    40 238 Fan Alarm Slave 12

    48 239 Fan Alarm Slave 21

    56 240 Fan Alarm Slave 22

    Note: If the SSC Option was chosen, typical mapping of the SSC alarms is:

    Ext. alarm(physical)

    Number (logical) to bemapped

    Refers to...

    01 11 SSC - Battery deep discharge

    02 02 SSC - Mains power failure

    03 03 SSC - Open door alarm

    72 / 74 3BK 17416 3081 RJZZA Ed.04

  • Appendix D : Antenna Port and External Alarm Mapping Rules

    Note: If the VSWR Option was chosen, typical mapping of the fan alarms is:

    Ext. alarm(physical)

    Number (logical) to bemapped

    Refers to...

    06 241 VSWR1 Alarm Master (ANT A)07 242 VSWR2 Alarm Master (ANT B)09 243 VSWR1 Alarm Slave 1 (ANT A)10 244 VSWR2 Alarm Slave 1 (ANT B)17 245 VSWR1 Alarm Slave 2 (ANT A)18 246 VSWR2 Alarm Slave 2 (ANT B)25 247 VSWR1 Alarm Slave 11 (ANT A)26 248 VSWR2 Alarm Slave 11 (ANT B)33 249 VSWR1 Alarm Slave 12 (ANT A)34 250 VSWR2 Alarm Slave 12 (ANT B)41 251 VSWR1 Alarm Slave 21 (ANT A)42 252 VSWR2 Alarm Slave 21 (ANT B)49 253 VSWR1 Alarm Slave 22 (ANT A)50 254 VSWR2 Alarm Slave 22 (ANT B)

    Note: Other alarms to be mapped:

    Ext. alarm (physical) Ext. alarm (logical) Refers to...04 04 Door Alarm Master

    05 05 PMS Alarm Master

    12 12 Door Alarm Slave 1

    13 13 PMS Alarm Slave 1

    20 20 Door Alarm Slave 2

    21 21 PMS Alarm Slave 2

    28 28 Door Alarm Slave 11

    29 29 PMS Alarm Slave 11

    36 36 Door Alarm Slave 12

    37 37 PMS Alarm Slave 12

    3BK 17416 3081 RJZZA Ed.04 73 / 74

  • Appendix D : Antenna Port and External Alarm Mapping Rules

    Ext. alarm (physical) Ext. alarm (logical) Refers to...44 44 Door Alarm Slave 21

    45 45 PMS Alarm Slave 21

    52 52 Door Alarm Slave 22

    53 53 PMS Alarm Slave 22

    11, 14, 15, 19, 22, 23, 27,30, 31, 35, 38, 39, 43, 46,47, 51, 52, 55

    255 Disabled

    Depending on the options installed, the alarm mapping can be changedaccording to the site situation.

    Figure 33: Application part Window

    74 / 74 3BK 17416 3081 RJZZA Ed.04