1
Amounderness Way Amounderness Way Norcross Ln. Fleetwood Rd. Sth. Fleetwood Rd. Sth. Preliminary work schedule Main work schedule Amounderness Way Amounderness Way Ashley Cl. Norcross Ln. Fleetwood Rd. Sth. Fleetwood Rd. Sth. Roundabout removal 22 July to 31 July 2019 (10 days) Amounderness Way island removal 1 August to 3 August 2019 (3 days) Norcross Lane island removal Road closure 5 August to 7 August (3 days) Fleetwood Road South (southern section) island removal Road closure 8 August to 10 August 2019 (3 days) Fleetwood Road South (northern section) island removal Road closure 12 August to 14 August 2019 (3 days) Amounderness Way verge work 19 August to 20 September (33 days) Phase 1 – Fleetwood Road South (southern section) Road closure - 1 September to 16 October 2019 (40 days) Road closure - 26 February to 4 March 2020 (6 days) Phase 2 – Fleetwood Road South (northern section) 16 September to 26 November 2019 (74 days) Road closure - 21 October to 26 November 2019 (37 days) Road closure - 20 February to 21 February 2020 (2 days) Phase 3 – Norcross Lane 14 October 2109 to 4 March 2020 (107 days) Road closure - 13 January to 19 February 2020 (38 days) Road closure - 24 February to 25 February 2020 (2 days) Phase 4 – Centre island 5 March to 31 March 2020 (39 days, no road closures) Phase 4 Phase 2 Phase 3 Phase 3 Phase 3 Phase 1 Phase 1 A585 Norcross roundabout improvement – Work Schedule Highways England creative MCR19_0122

A585 Norcross roundabout improvement – Work Scheduleassets.highwaysengland.co.uk/roads/road-projects/A... · Roundabout removal 22 July to 31 July 2019 (10 days) Amounderness Way

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A585 Norcross roundabout improvement – Work Scheduleassets.highwaysengland.co.uk/roads/road-projects/A... · Roundabout removal 22 July to 31 July 2019 (10 days) Amounderness Way

Amounderness Way

Amounderness Way

Norcross Ln.

Fleetwood Rd. Sth.

Fleetwood Rd. Sth.

Preliminary work schedule

Main workschedule

Amounderness Way

Amounderness Way

Ashley Cl.

Norcross Ln.

Fleetwood Rd. Sth.

Fleetwood Rd. Sth.

Roundabout removal22 July to 31 July 2019 (10 days)

Amounderness Way island removal1 August to 3 August 2019 (3 days)

Norcross Lane island removalRoad closure 5 August to 7 August (3 days)

Fleetwood Road South (southern section) island removalRoad closure 8 August to 10 August 2019 (3 days)

Fleetwood Road South (northern section) island removalRoad closure 12 August to 14 August 2019 (3 days)

Amounderness Way verge work19 August to 20 September (33 days)

Phase 1 – Fleetwood Road South (southern section)Road closure - 1 September to 16 October 2019 (40 days)Road closure - 26 February to 4 March 2020 (6 days)

Phase 2 – Fleetwood Road South (northern section)16 September to 26 November 2019 (74 days)Road closure - 21 October to 26 November 2019 (37 days)Road closure - 20 February to 21 February 2020 (2 days)

Phase 3 – Norcross Lane14 October 2109 to 4 March 2020 (107 days)Road closure - 13 January to 19 February 2020 (38 days)Road closure - 24 February to 25 February 2020 (2 days)

Phase 4 – Centre island5 March to 31 March 2020 (39 days, no road closures)

Phase 4

Phase 2

Phase 3Phase 3Phase 3Phase 1Phase 1

A585 Norcross roundaboutimprovement – Work Schedule

Highways England creative MCR19_0122