16
a & w team • Mandate • Activities • Procedures • Tooling • Resources • Planning • Conclusions Andrea Musso TE-MSC-CMI

a & w team

  • Upload
    brigid

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

a & w team. Mandate Activities Procedures Tooling Resources Planning Conclusions. Mandate. To open all W bellows starting “The Train” To close all W bellows completing “The Train” To install all missing Pressure Relief Devices (DN200) To upgrade all thermal screens - PowerPoint PPT Presentation

Citation preview

Page 1: a & w  team

Andrea Musso TE-MSC-CMI

& a w team

• Mandate

• Activities

• Procedures

• Tooling

• Resources

• Planning

• Conclusions

Page 2: a & w  team

Andrea Musso TE-MSC-CMI

Mandate

• To open all W bellows starting “The Train”

• To close all W bellows completing “The Train”

• To install all missing Pressure Relief Devices (DN200)

• To upgrade all thermal screens

• To remove, repair and reinstall all M bellows’ protections

Page 3: a & w  team

Andrea Musso TE-MSC-CMI

How to… W bellows openingRemove screws

Open bellows Remove MLI blankets 1

Welds to cut

Remove thermal shields

Remove MLI blankets 2Remove shield (screwed)

Courtesy Thierry

Renaglia

Page 4: a & w  team

Andrea Musso TE-MSC-CMI

Thermal screens upgrade

All the removed thermal screens have to be modified

The main reasons for modification are:

– To avoid welding in the tunnel [risk of fire]

– To avoid welds to be removed during (next) openings [RP issue]

Page 5: a & w  team

Andrea Musso TE-MSC-CMI

The new design…

Cour

tesy

G. V

illig

erCo

urte

sy G

. Vill

iger

Hinge

Braids

Clamp with silver-plated screws

Snap fastener

Outer

Inner

Outer

Inner

Outer side view

Clamp

New design validated by analytical calculations and cold test at SM18

Approved by TE-TM – ECR fully approved

Page 6: a & w  team

Andrea Musso TE-MSC-CMI

How to… Thermal screens upgrade

The main tasks to perform:

– RP clearance for transport

– Transport to surface (Building 183, dedicated workshop)

– Welds removal and re-shaping

– Installation of clamp, hinge, latches, aluminum braids

– ….. back to the tunnel, ready for installation

Page 7: a & w  team

Andrea Musso TE-MSC-CMI

Installation of Safety Relief Devices (DN200) 1/2

This activity was partially performed during last shutdown (2008-2009)

There are 612 SRV left for installation in 4 sectors:

– Sector 2-3– Sector 4-5 (partially)– Sector 7-8– Sector 8-1

Nota: a partial opening of the interconnection (i.e. W opening and MLI removal) is requested to install the SRD’s

Page 8: a & w  team

Andrea Musso TE-MSC-CMI

Installation of Safety Relief Devices (DN200) 2/2

Page 9: a & w  team

Andrea Musso TE-MSC-CMI

How to… M Bellows protections

All M bellows protections need to be removedAfter removal, a threaded insert will be installed in order to avoid seizing[RP issue]

Screws to be removed

Insert to be installed

Page 10: a & w  team

Andrea Musso TE-MSC-CMI

Procedures and ECR’s

All procedures for these activities are written and were circulated for approvals

Title Type Number EDMS Approved Released

Safety Relief Devices ECR LHC-QJ-EC-0001 1155385 Yes Yes

Safety Relief Devices Procedure LHC-QBBI-IP-0016 1236232 Yes In progress

Thermal screen modification ECR LHC-QBBI-EC-0002 1236451 Yes Yes

Opening of W bellows Procedure LHC-QBBI-IP-0017 1236329 Yes Yes

Closing of W bellows Procedure LHC-QBBI-IP0018 1236362 Yes In progress

Page 11: a & w  team

Andrea Musso TE-MSC-CMI

(Special) ToolingSafety Relief Devices

• Cutting machine + saw blade => needed 125m, ordered• Electrical motor => needed 9x, OK• Gearbox => needed 6x, OK• Blade holder => needed 6x, in progress

• Swarf collector => needed 3x, OK

W Bellows (+ Thermal screens upgrade + M protections)

• Lifting rail => Needed 10x: 6x available, 4 in progress

• Swarf collector => prototype ready, 10x needed, order in progress

• Drilling template => prototype ready, 10x needed, order in progress

• All other tooling is standard from industry, being ordered

Page 12: a & w  team

Andrea Musso TE-MSC-CMI

Resources

Andr

ea M

usso

(A

nna

Chru

l)

Jose Manuel Gomes De Faria SRD

Activity Leader

DUBNA Team leaderFeb 1st 2013

(March 1st 2013)

Team 1 (2x)March 15th 2013

Team 2 (2x)March 15th 2013

Alain Bastard W Opening & Closure

Activity Leader

NTUA Dimitrios Damianoglou

(Kostantinos Razakias, Feb 1st)

Team 1 (3x)March 1st 2013

Team 2 (3x)March 1st 2013

Team 3 (3x)March 1st 2013

WUT InstituteNov 1st 2012

(Feb 1st 2013)

Team 1 (3x)March 15th 2013

Team 2 (3x)March 15th 2013

Team3 (3x)March 15th 2013

Graeme Barlow Thermal Shields Upgrade

Activity Leader

Team 1 (2x FSU)(Feb 2013)

Each team installs 3 SRD’s per day

(i.e. 30 per week total, 6 weeks / sector)

Each team opens or closes 3 or 4 interconnections per day(i.e. ~90 per week total, 3

weeks / sector)

Page 13: a & w  team

Andrea Musso TE-MSC-CMI

Resources

A video was realized in order to give information to personnel from Institutes before they arrive at CERN

Click here to access video

Summary:– 4 CERN staff– 11 People from collaboration with Greece (NTUA)– 11 + 1 People from collaboration with Poland (WUT)– 6 (7) people from collaboration with Russia (DUBNA)– 2 FSU

Total: 32 persons

Page 14: a & w  team

Andrea Musso TE-MSC-CMI

Planning

Safety Relief Devices Considering the previous experience and the available personnel, there are no show-stoppers identified.The planning can be followed and the teams shall end before “the train” arrives.

W Bellows (+ Thermal screens upgrade + M protections) If openings could strictly follow “the train”, there would be an appropriate contingency.Considering other openings to be performed in parallel in several sectors (magnets exchange, leak detection, ball test…) , two teams will need to be detached from “the train”. Still feasible but needs good coordination.

Page 15: a & w  team

Andrea Musso TE-MSC-CMI

Planning some numbers

During the Long Shutdown 1 our team will have to perform:

• 1695 Openings

• 1695 Closures

• Remove, transport twice, re-work and install 3400 shields (+1700 radiative

shields); this includes 1700 hinges, 3400 latchers, 3400 braids, 1700

clamps, 8500 holes to drill in-situ…

• Remove, repair and re-install 10200 M protections (~80.000 holes to drill)

• Install 612 SRD

• ………

+ needed due to NCR’s

Page 16: a & w  team

Andrea Musso TE-MSC-CMI

Conclusions

• All documentation is ready and available

• Resources are adequate, training is foreseen for all members

• Planning can be respected but good coordination with parallel

openings is required to avoid stopping “the train”

• Tooling is (almost) ready