54
A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Embed Size (px)

Citation preview

Page 1: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

A Survival CourseOn the new

Building and Construction Industry Security of Payment Act 2009 (SA)

Robert Fenwick Elliott

Page 2: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Wake up Call

• Subcontractor – ignores an invoice from a subbie

• Head Contractor – Payment Schedule but no reasons

• Developer - certificate

Page 3: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott
Page 4: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

UK Construction taxed costs statistics by Professor Hazel Genn

Page 5: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott
Page 6: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott
Page 7: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott
Page 8: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Purpose of adjudication

Resolving disputes effectively

Or shifting a politico-commercial balance?

Page 9: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

UK v NSW

• All disputes• Adjudication to

ascertain facts• Free to agree on

adjudicator• Oral hearings OK• “Pay now argue later”

• Just payment claims• Adjudicator limited to

default material• Forbidden to agree

adjudicator• Very limited scope for

conferences• Loser could provide

security instead of paying

Page 10: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Cole Report - 2003

Page 11: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

WA + NT go with evaluative

Page 12: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

In

• Construction contracts• Subcontracts• Suppliers• Related services (architectural, QS etc)

Page 13: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Out

• Oil & Gas• Mining• Banks• Domestic• Interstate• Quantum meruit cases

Page 14: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

When?

• Commencement date – mid-2010?• Contracts entered into from then

Page 15: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott
Page 16: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Act creates a new statutory right

• Contractual right to payment• Price payable under Worker’s Liens Act 1893 –

triggered by WLA s10(2)(A) notice• Progress payment – new statutory right

created by this Act

Page 17: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

The new statutory right

• No contracting out, or restriction• Arises on each “reference date”• Overreaches any certification provisions• Carries interest at at least 10% p.a.• ? Limited rights of set-off• Sum claimed is effectively deemed due if no

payment schedule in 15 days: no other defences allowed

Page 18: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

The new statutory right

8—Rights to progress payments On and from each reference date under a

construction contract, a person— (a) who has undertaken to carry out

construction work under the contract; or (b) who has undertaken to supply

related goods and services under the contract,is entitled to a progress payment.

Page 19: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Reference date

reference date , in relation to a construction contract, means— (a) a date determined by or in accordance with the

terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract; or

(b) if the contract makes no express provision with respect to the matter—the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month;

Page 20: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Circular?

The reference to a progress payment here is not to a progress payment as defined in the Act, but to a progress payment provided for by the contract; Quasar Constructions NSW Pty Ltd v Demtech Pty Ltd [2004] NSWSC 116; (2004) 20 BCL 27 at [19]-[21]; Thiess Pty Ltd & Anor v Lane Cove Tunnel Nominee Company Pty Ltd & Anor [2009] NSWCA 53 at paragraph 44.

Page 21: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Set-off

• In law – a defence• Three main types

– Contractual– Common law (abatenment)– Equitable

• Also statutory (insolvency)

Page 22: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Perform (NSW) Pty Ltd v MEV-AUS Pty Ltd & Anor [2009] NSWCA 157

• 140 It is most doubtful whether adjudicators have the right to consider any equitable rights and titles. I adhere to what I said in Wooding v Estoe [2006] NSWSC 277 that adjudicators cannot recognize equitable assignments of contracts.

• 141 I do not wish to make any definite ruling as to whether adjudicators can take account of equitable set-off. I will content myself with saying: (1) it is doubtful whether they can do so; (2) if they can do so, it is doubtful whether the appellant’s claims in the instant case would qualify for equitable set-off.

Page 23: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Section 13(2) – Payment claim

(2) A payment claim— (a) must identify the construction work (or related goods and services) to which the progress payment relates; And (b) must indicate the amount of the progress payment that the claimant claims to be due (the "claimed amount"); and (c) must state that it is made under this Act.

Page 24: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Take note that if you fail to serve a payment schedule in the required form within 15 days, then you are going to have to pay up what we are claiming

regardless of whether the money is really due or not. This 15 day period cannot be

extended, even for good reason.

Page 25: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Protectavale Pty Ltd v K2K Pty Ltd [2008] FCA 1248

... a payment claim must be sufficiently detailed to enable the principal to understand the basis of the claim. If a reasonable principal is unable to ascertain with sufficient certainty the work to which the claim relates, he will not be able to provide a meaningful payment schedule. That is to say, a payment claim must put the principal in a position where he is able to decide whether to accept or reject the claim and, if the principal opts for the latter, to respond appropriately in a payment schedule. ... That is not an unreasonable price to pay to obtain the benefits of the statute.

Page 26: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

9 Lorne Bay served a revised invoice on 2 May 2008. In terms it purports to be a payment claim for the purposes of the Payment Act. The invoice identifies the construction contract between the parties and contains a revised claim of $635,448.06. The invoice states that the "construction work in respect of which this Payment Claim is made and the amount claimed ... is listed below in the table (and attached Schedule[s])". The table reads:

Page 27: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Contract Sum $6,295,000.00Variations (See the attached Schedule 1) $232,772.45Prolongation claim (See the attached Schedule 2) $129,058.00Adjusted Contract Sum $6,656,830.05LessRetentions (0.125% of the Contract Sum - $6,300,000 ...) $78,750.00Payments Received $6,000,400.00Subtotal $6,079,150.00Claimed amount ... (Adjusted Contract Sum – Subtotal) $577,680.05GST $57,768.01Claimed amount (incl GST) $635,448.06The two schedules give details of the variations and prolongation claims.

Page 28: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Neumann Contractors P/L v Peet Beachton Syndicate Limited [2009]

QSC 376.

• Same point• No sufficient identification of what was being

claimed, as a part of the total sum due

Page 29: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Contract SummaryAmountOriginal Contract Sum $ 4,250,601Add – VARIATIONS $ 715,660Adjusted Contract Sum (to date) (excluding GST) $ 4,966,261Plus 10% GST $ 496,626Adjusted Contract Sum (including GST) $ 5,462,887Payment Claim SummaryAmountValue of Work Completed to Date $5,320,019.94Less Retention Nil. Less Previous Claim (ex. GST) $5,239,710.58Payment Claim No. 12 Sub-Total $ 80,309.36Add previously claimed & unpaid $ 467,775.37AMOUNT NOW DUE (excluding GST) $ 548,084.73Plus 10% GST $ 54,808.47TOTAL AMOUNT THIS PAYMENT CLAIM (including GST) $ 602,893.20This is a payment claim made under the Building and Construction Industry

Payments Act 2004 (QLD) ”

Page 30: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

The invoice under consideration in that case indicated the amount claimed to be due by taking the contract sum and making a number of adjustments. Whilst certain items were set out in sufficient detail, his Honour concluded that what was noticeably absent was:

“... any identification of the work previously completely and paid for and the work (apart from the variations) to which the invoice relates. ... The only information provided is that the amount is referable to the “Contract Sum” and “Payments Received””.[26]

Page 31: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Mr Beacham argues, however, that the basis of the claim is evident on the face of the document, that is, it is a claim for all work for which Neumann has previously claimed save for the work for which it has been paid. In order for Peet to decide whether it should respond it would need to engage in a careful analysis of the schedules exhibited to the summary set out the work which was undertaken under the contract over some 25 pages and marry the work with the amounts paid on the progress certificates and arrive at the outstanding items. Requiring a respondent to a payment claim to undertake that kind of research which would be subject to error and within the time constraint of 10 days under the Payments Act[30] leads me to conclude that the payment claim does not identify the construction work to which that claim relates and does not fulfil the requirements of s 17(2) of the Payments Act.

Page 32: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

The Protectavale Issue

Jan Feb Mar April Work done in April?Breakdown of April claim

unpaid and claimed

Claimed:

Foundations 5 10 12 13 1 5

Frame 0 2 8 8 0 0

Walls 0 0 3 7 4 3

External 0 2 3 4 1 0

Roof 5 5 8 12 4 2

Painting 0 0 0 5 5 0

Electrics 0 0 1 6 5 0

Total 10 19 35 55 20 10

Less paid 0 7 14 24 21

Balance claimed 10 12 21 31 -1

Paid: Paid for re April

Foundations 4 7 8 8 0

Frame 0 2 3 8 5

Walls 0 0 3 4 1

External 0 2 3 4 1

Roof 3 3 6 10 4

Painting 0 0 0 5 5

Electrics 0 0 1 6 5

Total 7 14 24 45 21

Less previously paid 0 7 14 24

Balance paid 7 7 10 21

But consider alternative payment strategy: Paid for re April

Monthly payment (no breakdown) 6.5 7.7 9.6 20.9 ?

Total paid 6.5 14.2 23.8 44.7

Page 33: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Section 14 – Payment Schedules

(1) A person on whom a payment claim is served (the "respondent") may reply to the claim by providing a payment schedule to the claimant.

(2) A payment schedule— (a) must identify the payment claim to which it relates; and (b) must indicate the amount of the payment (if any) that the respondent proposes to make (the "scheduled amount").

(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent's reasons for withholding payment.

Page 34: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

•If the quantities claimed by the claimant is wrong, that needs to be set out•If the rates claimed by the claimant is wrong, that needs to be set out•If there are any defects in the claimant’s work, they need to be set out•If there are any other extents to which the claimant’s work is incomplete, they need to be set out

Page 35: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

•If the claimants claim is premature, that needs to be set out•If the claimant has failed to give proper credit for attention money, that needs to be set out•If the claimant has failed to give notice or follow any other contractual procedure, that needs to be set out•If the paying party has any sort of cross claim against the claimant, for example because the paying party has failed to complete his work in time, that needs to be set out.

Page 36: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

•There is no concluded contract between the parties•The claimant is not properly licensed as required by the Building Work Contractors Act•The claim is not for construction work or related goods and services as defined by the Act•One of the other exclusions applies•The payment claim was not properly served

Page 37: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Queensland ANAs

Adjudicate TodayPty Ltd (1057877)

IAMA (1057859)

LEADR (1058005)

Queensland LawSociety (1061878)

RICS AustralasiaPty Ltd (1064504)

Page 38: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

No fee for appointmentBut 40% of the adjudicator’s fee goes back to Adjudicate Today

Adjudicate Today – Bob Gaussen and Phillip Davenport

Page 39: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

$ Balance

012345678

0 50 100 150 200 250 300 350

Number of nominations

$ fo

r C

laim

ant

cf $

fo

r R

esp

on

den

t

Page 40: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

The Professional ANAs

Page 41: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Section 22 – the Decision

22—Adjudicator's determination(1) An adjudicator is to determine—(a) the amount of the progress payment (if any)

to be paid by the respondent to the claimant (the "adjudicated amount"); and

(b) the date on which any such amount became or becomes payable; and

(c) the rate of interest payable on any such amount.

Page 42: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Timing

Weeks

0 20 40 60 80 100 120

Litigation

West Coast

East Coast

Page 43: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Suspend work

• Where paying party does not pay schedule amount, or no payment schedule

• Claimant imunue from complaint• Right rarely exercised

Page 44: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Section 11(2) - Interest

• 10% (Supreme Court Act rate)• Or contract rate(whichever is the greater)

Page 45: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Section 12 - Pay when paid

• Pay when paid banned under section 12• Pay if paid banned under section 12• Pay when certified irrelevant to statutory

claims

Page 46: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Section 33 – No contracting out(1) The provisions of this Act have effect despite any provision to the

contrary in any contract.

(2) A provision of an agreement, whether in writing or not—

(a) under which the operation of this Act is, or is purported to be, excluded, modified or restricted, or that has the effect of excluding, modifying or restricting the operation of this Act; or

(b) that may reasonably be construed as an attempt to deter a person from taking action under this Act,

is void.

Page 47: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

UK Experience

Page 48: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Take up rates

Page 49: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Amounts awarded

NSW 1st Half 2006

0

50

100

150

200

250

0 - 19% 20 - 39% 40 - 59% 60 - 79% 80 - 100%

%age awarded

Nu

mb

ers

of c

as

es

Number s of cases

Page 50: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Queensland stats

Page 51: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Example 1 – Walter v CPL(Surry Hills)

• The parties entered into an AS4300 contract, with provision for certification of payments by the Superintendent (#2)

• The claimant put in a payment claim for $14.9 million (#4)

• The Superintendent certified $952k (#5), which was paid

• There was no payment schedule which complied with the Act (#8)

Page 52: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

• The claimant sued for the balance of his claim of $13.9m (#9)

• The defendant failed in 5 arguments why he should not have to pay:– That the claim was premature (#26 and 52)– That there was no certificate, not even due time for

certificate (#22 and 55)– That The claim included claims for delay and disruption

which were not construction work (#33 and 61)– That lump sum contracts are excluded (#42 and 70)– That the claimant conduct was deceptive and misleading

(#45 and 80)• The defendant was ordered to pay the $13.9 million,

plus interest

Page 53: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

Example 2 – Pullar v Harrop

• A payment schedule case• NB importance of detail in payment schedule• No deduction allowed for LADs

Page 54: A Survival Course On the new Building and Construction Industry Security of Payment Act 2009 (SA) Robert Fenwick Elliott

QuestionsUSB

Fenwick Elliot Grace adjudication toolkit on a 2GB USB Flash drive, containing an annotated copy of the Act, flowchart and list of drop dead dates, and all of the legal authorities. $25.00 plus GST each; email [email protected] to order.

Construction Law UpdateAbout once a month. No charge; email [email protected] to get aded to the list.