18
A Premier Australian Copper Producer March 2014 Quarterly Report Presentation Webcast – Karl Simich, Managing Director & CEO 17 April 2014 Access this presentation at: http://www.brrmedia.com/event/122782 / http://www.sandfire.com.au S a n d f I r e R e s o u r c e s - A P r e m I e r A u s t r a l I a n C o p p e r P r o d u c e r

A Premier Australian Copper Producer - … 2014/SFR_170414...A Premier Australian Copper Producer ... Underground diamond drilling continuing throughout 2014 targeting resource additions

Embed Size (px)

Citation preview

A Premier Australian

Copper Producer

March 2014 Quarterly Report Presentation

Webcast – Karl Simich, Managing Director & CEO 17 April 2014

Access this presentation at: http://www.brrmedia.com/event/122782 / http://www.sandfire.com.au

S a n d f I r e R e s o u r c e s - A P r e m I e r A u s t r a l I a n C o p p e r P r o d u c e r

Important Information and Disclaimer Forward-Looking Statements and Competent Person’s Statement

Forward-Looking Statements

• This presentation has been prepared by Sandfire Resources NL. This document contains background information about Sandfire Resources NL current at the date of this presentation. The presentation is in summary form and does not purport to be all inclusive or complete. Recipients should conduct their own investigations and perform their own analysis in order to satisfy themselves as to the accuracy and completeness of the information, statements and opinions contained in this presentation.

• This presentation is for information purposes only. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in any jurisdiction.

• This presentation may not be distributed in any jurisdiction except in accordance with the legal requirements applicable in such jurisdiction. Recipients should inform themselves of the restrictions that apply in their own jurisdiction. A failure to do so may result in a violation of securities laws in such jurisdiction.

• This presentation does not constitute investment advice and has been prepared without taking into account the recipient's investment objectives, financial circumstances or particular needs. The opinions and recommendations in this presentation are not intended to represent recommendations of particular investments to particular persons. Recipients should seek professional advice when deciding if an investment is appropriate. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments.

• To the fullest extent permitted by law, Sandfire Resources NL, its officers, employees, agents and advisers do not make any representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of any information, statements, opinions, estimates, forecasts or other representations contained in this presentation. No responsibility for any errors or omissions from this presentation arising out of negligence or otherwise is accepted.

• This presentation may include forward-looking statements. Forward-looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of Sandfire Resources NL. Actual values, results or events may be materially different to those expressed or implied in this presentation. Given these uncertainties, recipients are cautioned not to place reliance on forward looking statements. Any forward looking statements in this presentation speak only at the date of issue of this presentation. Subject to any continuing obligations under applicable law and the ASX Listing Rules, Sandfire Resources NL does not undertake any obligation to update or revise any information or any of the forward looking statements in this presentation or any changes in events, conditions or circumstances on which any such forward looking statement is based.

Competent Person’s Statement

• The information in this report that relates to exploration results is based on information compiled by Mr. Shannan Bamforth who is a Member of The Australasian Institute of Mining and Metallurgy. Mr. Bamforth is a permanent employee of Sandfire Resources NL and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Bamforth consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Exploration and Resource Targets

• Any discussion in relation to the potential quantity and grade of Exploration Targets is only conceptual in nature.

2

Agenda

• Highlights

• Safety

• Mining

• Processing

• Sales

• Operating Costs

• Exploration

• Summary

March 2014 Quarterly Report Presentation

3

March 2014 Quarterly Highlights Record production; increased Mineral Resource; financing completion test met

Production and Operations

• March Qtr: 18,098t copper and 10,035oz gold produced; C1 cash cost of US$1.08/lb

• 1.5Mtpa underground mining rate maintained; development of C1 and C4/5 declines on schedule

• Copper recoveries of 91%; further recovery optimisation initiatives underway

• 50,036t of copper and 24,605oz gold produced for FY2014 to date: June Qtr results expected to be in-

line with March Qtr

Exploration

• Increased high grade Mineral Resource: +29,000t Cu and 41,000oz Au (net of mining depletion)

• Resource definition of eastern portion of Conductor 4 underway

• Drilling targeting Conductor 5 and Conductor 1 extensions planned for 2H CY2014

• Technical programs progressing as part of new regional farm-in joint ventures with Ventnor

Resources (Thaduna/Green Dragon) and Talisman Mining (Springfield)

Corporate and Financial

• Key financing completion test satisfied as part of original $380M facility

• Debt facility repayment: facility balance reduced to $190M following scheduled $40M repayment

• $90M cash and $16M receivables at 31 March 2014

• Acquisition of 37% interest in TSX-V listed WCB Resources: Tier-1 porphyry opportunity

4

Safety Continued sound safety performance

• Continued decline in Total Recordable Injury Frequency Rate

(TRIFR) to 13.0 at Quarter-end (vs. 13.5 at December Quarter-

end)

• Additional focus on prevention of lacerations, strain and sprain

injuries

5

TRIFR

0

2

4

6

8

10

12

14

16

18

20

Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '14 Mar '14

Mining Overview 1.5Mtpa underground mining rate maintained; mine development continuing on schedule

UNDERGROUND

• Four stopes on-line during the Quarter with four large

stopes commencing in March-April 2014

• Underground mining rate of 1.5Mtpa maintained with

381,439t of underground sulphide ore mined for the

Quarter

• Paste plant performance continues to improve

• C4/5 Decline development resumed following

successful realignment: no schedule or capital impacts

• Progressed development of C1 (369m) and C4/C5

(384m) declines from Evans Decline junction

• Total underground development progressed to +19km

6

Processing Copper recoveries increased and improving further; strong concentrate production

MILL THROUGHPUT

• 379,018t milled at average head feed grade of 5.3% Cu

• Nameplate 1.5Mtpa throughput maintained

RECOVERY

• Copper recovery of 91% achieved treating underground ore

• Gold recovery 53% on target

• Recovery increase due to improved operational stability with

advanced process control system

• Further recovery improvement initiatives underway targeting

~92% copper recovery

CONCENTRATE & METAL PRODUCTION

• 74,213t of concentrate produced

• 18,098t of contained copper produced: in line with guidance

7

Sales Copper and gold sales

• Quarterly sales of 20,867 tonnes

of copper and 10,842 ounces of

gold

• Nine shipments completed for

the Quarter including delayed

shipment from December 2013

• Port Hedland and Geraldton Ports

both operating well

• 5,000+ tonnes concentrate

holding at site and at port at

Quarter end

8

Quarterly Unit Operating Costs C1 and total production costs

Unit costs – DeGrussa Mine Q3 FY2014

(US$/lb) Commentary

Mining (net of development) 0.51

Unit costs reduced in line with record copper and

gold production

1H FY 2014 was impacted by restricted open pit

recovery and lower ore grades; C1 of US$1.30/lb

2H FY 2014 solely underground ore from

higher grade stopes and higher recovery;

driving production higher and costs lower

below the guided US$1.15/lb full year target level

Processing 0.33

Business services 0.13

Transport, treatment and refining 0.50

C1 cost (pre-by product credit) 1.47

By-product credit (gold) (0.39)

C1 cost 1.08

Royalties 0.19

Production cost 1.27

Depreciation and amortisation 0.62

Total production cost 1.89

9

Exploration Update Near-mine exploration delivering results; new regional exploration joint ventures

• Increased high grade Mineral Resource: +29,000t Cu

and 41,000oz Au (net of mining depletion)

• 35,935 m of RAB, RC and diamond drilling completed

• Underground drilling continuing:

• Resource delineation of eastern portion of Conductor 4

• Underground drilling planned in 2H 2014:

• Down-plunge extensions of Conductor 1

• Extensions of Conductor 5

• Co-funded deep diamond drilling confirms extensions of

prospective VMS horizon

• Technical work progressing as part of new regional

exploration joint ventures secured with Ventnor

Resources and Talisman Mining

10

Near-Mine Exploration: the Next Steps Underground diamond drilling continuing throughout 2014 targeting resource additions and repeats

11

Near-Mine Exploration: the Next Steps Underground diamond drilling continuing throughout 2014 targeting resource additions and repeats

2175 C4 DDD

2200 C4 DDD

• Down-plunge

extensions of

Conductor 4 drilled out

from 2200 C4 diamond

drill drive and being

incorporated in 2014

Mineral Resource

update

• Resource definition of

eastern portion of

Conductor 4

commencing from 2175

C4 diamond drill drive

12

CONDUCTOR 4

Near-Mine Exploration: the Next Steps Underground diamond drilling continuing throughout 2014 targeting resource additions and repeats

13

• Conductor 5 resource

definition drilling

program

• Conductor 5 exploration

drilling program

• Drilling to commence in

2H CY2014 when

Conductor 5 drill drive is

complete

CONDUCTOR 5

Sandfire – Dominant Position in an Emerging VMS Province Consolidating a strong position in Western Australia’s emerging Bryah Basin VMS copper-gold province

• Only operating base metals processing plant in the region (1.5Mtpa DeGrussa Concentrator)

• Outstanding organic growth potential – extensive 65km strike length of prospective VMS horizon

• Recently expanded strategic footprint via Talisman and Ventnor Joint Ventures

14 14

Investment in WCB Resources Opportunity to participate in a potential Tier-1 porphyry copper-gold discovery on Misima Island

• Low-cost, low-risk opportunity in a Tier-1 porphyry copper-gold play via $5.9M placement in WCB Resources (TSX-V:

WCB)

• Key asset: 70% interest in Misima Project alongside Pan Pacific Copper (PPC) – a joint venture between JX Nippon

15

Mining & Metals Corporation

and Mitsui Mining &

Smelting Company

• Project located on an

offshore island with strong

history of mining and

development (+4Moz

Misima mine previously

owned by Placer Dome)

within one of the richest,

high-grade copper-gold

porphyry belts in the world

Investment in WCB Resources Near-mine exploration delivering results; new regional exploration joint ventures concluded

• Principal target is the Misima Porphyry on Mt

Sisa, located on edge of historical gold deposit

• Major copper-in-soils anomaly extending over

1.1km by 0.9km

• Corresponds to strong magnetic anomaly with

skarn mineralisation

• Interpreted to be major porphyry intrusive centre

• No deeper drilling despite strong linkage between

large gold mines and underlying copper-gold

deposits in PNG, Indonesia and Philippines

• Additional exploration and development potential

at Misima gold mine (+1.6Moz remaining

resources)

16

ONE OF THE MOST ATTRACTIVE PROJECTS IN THE WORLD FOR A MAJOR COPPER DISCOVERY: DRILL-READY WITH DRILLING PLANNED IN

THE COMING MONTHS

Summary and Outlook

• Record quarterly production and cost performance:

• 18,098t copper, 10,035oz gold production at C1 cost of US$1.08/lb

• Financing completion test met

• Strong outlook for second half of FY 2014:

• FY2014 to date: 50,036t Cu, 24,605oz gold

• June Qtr results expected to be in line with March Qtr

• Strong operating cash flow:

• $40M repayment reduces finance facility to $190M

• Strong ongoing exploration commitment

• Technical programs progressing under new exploration JV’s: drilling

imminent

• New Tier-1 porphyry copper-gold opportunity secured

Record production quarter; strong outlook for 2H FY2014

A premier Australian copper producer

17

Contact Details:

Sandfire Resources NL Registered Office and Principal Place of Business

Level 1, 31 Ventnor AvenueWest Perth,

Western Australia 6005

T +61 8 6430 3800

F +61 8 6430 3849

www.sandfire.com.au

Access this presentation at: http://www.brrmedia.com/event/122782 / http://www.sandfire.com.au

S a n d f I r e R e s o u r c e s - A P r e m I e r A u s t r a l I a n C o p p e r P r o d u c e r