    A is for Agile, not Anarchy

    Sunday, February 24, 2013

    Scaled Agile Framework 3/5 - Program level pipelinemanagement and the program kanban

    Part 2 of the seriesconcluded with the final stage of the demand management process

    1 or more Epics generated from the COE level initiative and handed off to the relevant

    delivery groups. In this post we will explore the lifecycle of an Epic as it travels through

    the delivery group functioning as an Agile Release Train Strategic Delivery.

    As described in Part 1, the adoption of the Agile Release Train in Strategic Delivery

    commenced in early 2012 (April). Whilst it is being continually refined, the implementationhas gone through a number of step changes in approach.

    After describing the initial adoption context and approach and covering some of the early

    experiences, the post will conclude by illustrating the current operating model.

    At the time of adoption, the group was modelled roughly as follows:

    5 project-based Scrum teams all with the same team-shape, following a

    reasonably similar model and in the final stages of delivery for their projects

    1 project-based pseudo-Kanban team with 3-4 months remaining on delivery

    of their project

    2 stakeholder-aligned pseudo-Kanban teams with very different team shapes

    and 4-5 months of work remaining in their pipelineA newly formed System Team working on implementing a continuous

    integration capability

    10-15 projects running under an outsourced/offshored waterfall model

    A group of system analysts fulfilling requirements and design elaboration for

    the waterfall projects

    18 project managers

    The initial approach was defined in a series of workshops between the general manager

    of the delivery group and her extended leadership team. The objectives of the workshops

    were:

    Establish a shared understanding of SAFe fundamentals

    Determine the initial implementation model and approach to

    transitioning/maturing beyond initial implementation

    Determine the most effective organisational structure for the group

    Upon conclusion, the group had reached agreement on the following plan:

    Immediately establish an Agile Release Train involving the 5 Scrum teams,

    converting them from project based to stable feature teams. All new work

    entering the group would be fed to the train.

    Manage the outsourced waterfall projects through to conclusion.

    Allow the pseudo-Kanban teams to conclude their current commitments,

    whilst gradually reshaping them to be ready to join the train upon completion.

    The organisation to support this had the following structure:

    Agile Pipeline Management Services (APMS) composed of the group of

    project managers from the Scrum teams and the system analysts. Primary

    responsibility: Manage preparation of the pipeline of work for PSIs and make

    sure the teams had the support they needed in delivery.

    Development Services run by the equivalent of the Release Train Engineer

    and composed of the feature teams. Primary responsibility: Deliver PSI

    outcomes

    Deployment Services run by the deployment manager and incorporating the

    Introduction

    Initial adoption context

    Scaled AgileFrameworkApplied 2/5 -DemandManagement andthe Portfolio

    Kanban

    Introduction Asdescribed in theintroductory post , theimplementationbeing described isnot managing an enterprise levelp...

    Scaled AgileFramework 3/5 -

    Program levelpipelinemanagement andthe program

    kanban

    Introduction Part 2 of the seriesconcluded with the final stage ofthe demand management process 1 or more Epics generated...

    Scaled Agile Framework Applied -Part 1/5: Introduction and Context

    Since encountering DeanLeffingwells Scaled AgileFramework(SAFe) , I havepresented the model to dozens of

    senior executives a...

    When is a SAFePSI not a PSI?

    Over the lastcouple of months,Ihave delivered theLeading SAFe

    course half a dozen times to adiverse set of companies andaudiences. Wh...

    Scaled AgileFrameworkApplied 4/5 - In-play work and the

    program levelFeature wall

    In Part 3 , we covered the programbacklog lifecycle. This post willfocus on implementation life andfeature level visualisation. Wehave...

    Launching yourAgile ReleaseTrain - Preparingfor the firstRelease PlanningEvent

    You've decided to adopt SAFe,found your first Agile Release

    Train and are embarking on thelaunch journey. You have a bunchof Safe Ag...

    Scaled Agile Framework Applied5/5 - Conclusion

    What you see is all there is I'vejust finished reading a book called"Thinking Fast and Slow" byDaniel Kahneman. Set in t...

    Popular Posts

    ! More Next Blog Create Blog Sign In

    http://scaledagileframework.com/system-team/http://www.agilenotanarchy.com/2013/01/scaled-agile-framework-applied-part-15.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/http://www.agilenotanarchy.com/http://www.agilenotanarchy.com/http://www.agilenotanarchy.com/http://www.agilenotanarchy.com/https://www.blogger.com/next-blog?navBar=true&blogID=7030397814607511868http://www.agilenotanarchy.com/2014/01/launching-your-agile-release-train.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/01/scaled-agile-framework-applied-part-15.htmlhttp://www.agilenotanarchy.com/2013/01/scaled-agile-framework-applied-part-15.htmlhttp://www.agilenotanarchy.com/2013/01/scaled-agile-framework-applied-part-15.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/http://www.agilenotanarchy.com/http://www.agilenotanarchy.com/https://www.blogger.com/home#createhttp://www.agilenotanarchy.com/2014/01/launching-your-agile-release-train.htmlhttps://www.blogger.com/https://www.blogger.com/home#createhttps://www.blogger.com/next-blog?navBar=true&blogID=7030397814607511868http://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-55.htmlhttp://www.agilenotanarchy.com/2014/01/launching-your-agile-release-train.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/01/scaled-agile-framework-applied-part-15.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2014/01/launching-your-agile-release-train.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://www.agilenotanarchy.com/2013/09/when-is-safe-psi-not-psi.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://scaledagileframework.com/rte/http://scaledagileframework.com/system-team/http://www.agilenotanarchy.com/2013/01/scaled-agile-framework-applied-part-15.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    2/10

    System Team. Primary responsibility: Liaise with enterprise release

    management and operations and ensure smooth deployment and ongoing

    continuous integration capability uplift.

    Transition Services composed of the pseudo-Kanban teams and the

    outsourced waterfall projects/PMs. Primary responsibility: Ensure graceful

    conclusion of inflight work whilst preparing the teams for transition onto the

    train.

    Some insights into the early experiences of the leadership group in the implementation

    can be found in this earlier post, but Ill delve here into a number of key activities.

    For the first month or so, it was business as usual for the feature teams. They were

    already operating on the same iteration cadence, and all had a number of sprints

    committed in order to deliver on existing commitments. The primary focus area was the

    formation of the APMS group, but before delving into that Ill briefly cover the feature

    teams.

    The feature teams basically had two things to do:

    Become stable feature teams instead of project teams

    Normalise sizing.

    The first was great fun and fairly trivial. Formerly known by the reference number for the

    project they were working on (ie the 5531 team), they were asked to select a name for

    themselves. The name had to be train related and safe for work so we wound up with

    teams such as Maglev and Astrotrain. A simple change but immensely powerful when itcomes to sense of identity.

    The second was painful. The concept of story point normalisation is perhaps one of the

    most controversial in SAFe. Having been reluctantly convinced of the need by Dean, I still

    found that no matter how carefully you approach it you will still be impacted by most of the

    evils used to argue against the concept. We began by using the past 8 iterations metrics

    for every team to construct a normalisation formula. Simplistically, some teams

    downshifted their sizing one notch on the Fibonacci scale and other upshifted by one. It

    was deceptively simple, and one of the key lessons learnt in the time since is that we

    should have far more actively coached and retrospected on sizing practices.

    The APMS team had 4 initial objectives:

    Establish the Epic Kanban system reflecting both the active work in the feature

    teams and work in the pipeline

    Prepare the work in pipe and logistics for the first PSI

    Work with the rest of the COE (in particular the PMO) to agree governance,

    financial and other details of how the release train would mesh with the

    broader enterprise.

    Continue to provide project management support to the feature teams

    APMS Challenge 1 Team Formation

    Whilst APMS was composed of PMs, System Analysts and an architect, there was a no

    exception stance on the release train being Agile top to bottom. So, the team had a

    scrum-master and an aspiration to work as a cross-functional team with shared

    commitments, standups, retrospectives, transparency and accountability to the feature

    teams. Today, it is a high-performance team with an exceptional team ethic but the

    journey was more challenging than for any other agile team Ive ever worked with. In the

    end, it required a far larger change of mindset for the team members than for a typical dev

    team and involved significant tuning of team balance and membership.

    APMS Challenge 2 Feature Grooming: How much is enough?

    The second challenge lay in the approach to grooming features for the PSI. The reality of

    the funding model and the dependency complexity of the work required a fair amount of

    analysis and estimation work to create ready to play features. The best way to

    summarise this issue lies in the fundamental paradox of SAFe. Part of the reason the

    model is so powerful is because when you present it to program/project managers and

    architects they can readily map it to their existing mental models. On the other hand, the

    most common criticism I hear from agilists is that it looks too formal and RUP-like. What

    we experienced was that the intent of the model is too easily interpreted in practice into

    waterfall-like behaviours.

    The original feature grooming model involved the APMS group identifying the business

    intent and features for the Epic, resolving the high level architecture and feeding it through

    a feature team for enough discovery work to size it to +-30% confidence estimates. The

    Early Days

    Early days for the feature teams

    Early days for APMS

    Moving from beliefto action -implementingWSJF for valuebased prioritisationin SAFe (Part 2)

    In my last post , I described thesimulation I use to teach Cost ofDelay (CoD) and WeightedShortest Job First (WSJF). Thisoften provides...

    SAFe ReleasePlanning Tip 3 -Plan with Flow

    In Tip 2 , wecovered the firstmorning of the

    SAFe release planning event -establishing the vision for the PSIand starting the whole trai...

    Getting from theoryto practice withCost of Delay andWSJF in SAFe

    Recently, Ivenoticed a number

    of threads on the SAFe linked-ingroups indicating people arestruggling to get started with theSAFe Weigh...

    ! 2016 (1)

    ! 2015 (1)

    ! 2014 (10)

    " 2013 (9)

    ! November (1)

    ! October (1)

    ! September (2)

    ! March (2)

    " February (2)

    Scaled Agile Framework 3/5 -Program level pipelin...

    Scaled Agile FrameworkApplied 2/5 - DemandManage...

    ! January (1)

    ! 2012 (8)

    Blog Archive

    Mark Richards

    !"##"$ !"#

    View my complete profile

    About Me

    https://plus.google.com/105997851221079634629https://plus.google.com/105997851221079634629http://www.agilenotanarchy.com/search?updated-min=2012-01-01T00:00:00-08:00&updated-max=2013-01-01T00:00:00-08:00&max-results=8http://void%280%29/http://www.agilenotanarchy.com/2013_01_01_archive.htmlhttp://void%280%29/http://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttp://www.agilenotanarchy.com/2013_02_01_archive.htmlhttp://void%280%29/http://www.agilenotanarchy.com/2013_03_01_archive.htmlhttp://void%280%29/http://www.agilenotanarchy.com/2013_09_01_archive.htmlhttp://void%280%29/http://www.agilenotanarchy.com/2013_10_01_archive.htmlhttp://void%280%29/http://www.agilenotanarchy.com/2013_11_01_archive.htmlhttp://void%280%29/http://www.agilenotanarchy.com/search?updated-min=2013-01-01T00:00:00-08:00&updated-max=2014-01-01T00:00:00-08:00&max-results=9http://void%280%29/http://www.agilenotanarchy.com/search?updated-min=2014-01-01T00:00:00-08:00&updated-max=2015-01-01T00:00:00-08:00&max-results=10http://void%280%29/http://www.agilenotanarchy.com/search?updated-min=2015-01-01T00:00:00-08:00&updated-max=2016-01-01T00:00:00-08:00&max-results=1http://void%280%29/http://www.agilenotanarchy.com/search?updated-min=2016-01-01T00:00:00-08:00&updated-max=2017-01-01T00:00:00-08:00&max-results=1http://void%280%29/http://www.agilenotanarchy.com/2014/08/getting-from-theory-to-practice-with.htmlhttp://www.agilenotanarchy.com/2014/01/psi-planning-tip-3-plan-with-flow.htmlhttp://www.agilenotanarchy.com/2014/12/moving-from-belief-to-action.htmlhttp://www.agilenotanarchy.com/2014/08/getting-from-theory-to-practice-with.htmlhttp://www.agilenotanarchy.com/2014/01/psi-planning-tip-3-plan-with-flow.htmlhttp://www.agilenotanarchy.com/2014/12/moving-from-belief-to-action.htmlhttp://www.agilenotanarchy.com/2012/06/agile-leadership-and-learning-by-doing.html
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    3/10

    teams would thus hold a portion of their velocity available to be dedicated to these

    activities, which would be done in parallel with fulfilling their delivery commitments. What

    eventuated was the analysts/architects in the APMS group identifying and specifying the

    features and handing fully articulated designs to the teams who then simply estimated the

    design theyd been handed and handed their estimates back to the PM. This caused no

    end of problems, and was eventually heavily course corrected as youll see once we reach

    the current-day model.

    APMS Challenge 3 The Product Owner construct

    Prior to the adoption of the release train, finding the right product owners for agile

    initiatives had been a serious challenge for the group. Given the nature of a data

    warehouse, there are extremely diverse groups of stakeholders for any given initiative and

    finding someone with sufficient diversity of domain knowledge, sufficient availability and

    sufficient empowerment had been entirely unsuccessful. Deans Product

    Manager/Product Ownerseparation was the key to unlocking the puzzle. Whilst we

    couldnt employ it exactly as specified in the framework, the underlying principal of

    separation of concerns was a huge enabler. In standard SAFe, the Product Manager is

    basically the overall decision maker on prioritisation and scope for the release train whilst

    the product owner travels with the team. In our context, there could be 15 different funding

    sources active at once and prioritisation and scope had to belong to the sponsors

    providing the money.

    The solution adopted was to employ Epic Owners and Feature Owners. The Epic

    Owner was the person providing the funding for an Epic, and was looked to for

    engagement at key points and strategic prioritisation and scope calls for their Epic. The

    Feature Owner, on the other hand, was to have deep domain expertise on a particular

    feature, have delegated authority within the scope of the feature and be far more actively

    engaged with the team whilst their feature was in play. The construct resolved a vast

    number of issues, particularly in addressing the contrast between availability and authority.

    APMS Challenge 4: Can we really do PSIs?

    Ive left the biggest challenge for last. SAFe deliberately separates the deployment cycle

    from the PSI cycle. Whilst the PSI produces a potentially shippable increment, the

    framework allows for either deployment on the PSI boundary, multiple PSIs before a

    deployment or multiple deployments within a PSI. Our intent at launch was to run 8-week

    PSIs and use the PSI as a planning boundary with multiple deployments happening in

    any given PSI.

    The first difficulty we encountered was feature shaping. Given that the standard guidance

    for a feature is small enough to be delivered in a single PSI but large enough to represent

    a significant outcome for the business, there was a clash between good feature shaping

    and deployment window requirements. Available deployment windows were specified by

    enterprise release management, with 1 per month for minor deployments without

    significant integration requirements and a varying cadence for enterprise deployments

    with major integration involved. Further, the deployment window for a feature was

    generally dictated by external dependencies. It was impossible to find a PSI cadence

    which aligned well with deployment boundaries, and shaping features to PSIs was also

    largely impossible as we would regularly encounter features which would need to be

    deployed 1 iteration into a PSI but needed 2-3 iterations to implement.

    Feature shaping was difficult but not insurmountable in the end, we could have resolved

    it by allowing cross-PSI features whilst still maintaining strong size limitations. However,

    the bridge-too-far lay in establishment of sufficient funded pipeline. Once again driven by

    enterprise level gating cycles and funding processes, an 8 week PSI that fully funded and

    committed the entire release train was just not emerging.

    By this point, however, we had established significant momentum with every aspect of the

    release train other than the PSI launch. The pipe was operating, the work was flowing into

    the teams, deployments were going out the door and momentum was tangible. One large

    leadership workshop later, we made the call: know that PSIs will start eventually, but in

    the meantime develop compensating mechanisms and keep maturing the release train.

    Our focus then turned to compensating mechanisms what were the key things we lost

    by not having the PSI, and how could we utilise our knowledge of the principals to achieve

    the purpose. To my mind, we identified the first 3 of the 5 key ingredients initially:

    The power of having the whole release train in a planning workshop together

    from the perspective of developing a sense of release train as one large team

    with shared outcomes as well as release train as team of teams

    Employing a deliberate set of disciplines to groom out 4 iterations worth of

    backlogs at the release train level and ensure that visibility, dependency, risks

    http://scaledagileframework.com/psi-release/http://scaledagileframework.com/product-management/
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    4/10

    and issues were fully articulated at the story level for all active features.

    Release train level Inspect and Adapt cycles

    Maintenance of a strategic view of capability buildout on the platform that

    effectively capitalises on synergies between features.

    Strategic showcasing and communication of PSI level outcomes to draw

    together the whole of product view of progress for broad stakeholder groups

    and avoid fragmented and isolated demonstration and communication feature

    by feature/epic by epic to narrow stakeholder groups.

    Id like to write that we rapidly implemented effective compensation strategies, but Id be

    lying. Being brutally honest, Id suggest that we initiated effective strategies for the first

    and third items immediately. Time and painful lessons triggered focus on the second and

    fourth, and the fifth is currently in the spotlight.

    The first strategy was the concept of PSI-lite, better known as Unity Day. A 1-hour

    whole of train session at the start of each sprint aimed at building a sense of train as

    team and ensuring everyone started the sprint on the same page. These have been

    incredibly powerful from a cultural transformation perspective. They are always attended

    by numerous visitors, and repeat attendees regularly comment on the tangible change in

    atmosphere over time. (for a deeper treatment, see this post)

    The second strategy involved the establishment of Team Loco 131, composed of the

    extended leadership group and functioning as a program level continuous improvement

    team. Their stories are generated through learning generated by various forms of

    retrospective, and the leaders are fully bought into the lean management model of taking

    responsibility for improving the system of work.

    Whilst the story of addressing backlog grooming challenges is too long and torturous to

    describe here, I will offer the following. Many organisations find the investment of putting a

    whole program and set of stakeholders in a room for 2 days planningevery 8-10 weeks

    unpalatable. For Strategic Delivery, this commitment was one of the major sticking points

    in management workshops although the general manager bought in and was willing to

    support it, most of her leadership group felt it was unjustifiable. Ive heard similar stories

    from many other SAFe Program Consultants. Our journey, painful lessons and ongoing

    investment required to compensate in the area of release train level backlog

    grooming/planning have utterly convinced me of the vital importance of this activity. To put

    my systems thinking hat on, failure to implement effective PSI planning creates an insane

    amount of failure demand across the entire release train. Weighing the cost of the failure

    demand against the investment required for the PSI planning days provides a scale very

    heavily tipped towards the investment.

    Before digging into the specifics of how the Program (or Epic) kanban operates today,

    The Program Kanban

    http://2.bp.blogspot.com/-T00Vy42QYlQ/USoMYI_LC-I/AAAAAAAAADA/ilu03kK-PAk/s1600/Epic+Kanban+Wall+-+Full+(Blog+Size).jpghttp://scaledagileframework.com/release-planning/http://www.agilenotanarchy.com/2012/08/scaled-agile-and-self-organising-program.html
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    5/10

    there are two final points to cover off. The first involves a holistic view across both the

    initiative level kanban system and the epic level. Astute readers will notice a number of

    glaring inefficiencies between the two. Whilst Ill cover this in a little more detail in the

    concluding post for the series, I will offer a reminder at this time that the purpose of explicit

    visualisation in a kanban is to bring to light waste and opportunity.

    The second point is that whilst this blog series focuses on wall visualisations, every wall

    depicted is replicated in Rally with far more underlying detail. The Rally Portfolio

    Management capability is a key enabler in effective management and measurement of the

    system, whilst the walls are vital for tactile insight and facilitation of communication.

    The Epic Kanban is, obviously, dedicated to the flow of an Epic through the release train

    value chain. Every card on the wall is an Epic. The value chain is divided into 5 phases,

    each with a number of states:

    Initiate Phase: Transition from demand management and connection with

    stakeholders.

    Discovery Phase: Feature elaboration and estimation refinement

    Launch Phase: Approvals, funding and preparation to drop into teams for

    implementation

    Evolve Phase: Implementation

    Operate Phase: Deployment and follow-through to ensure happy users and

    successful transition to operations.

    One of the primary aspects of the phases is to indicate the f low of responsibility between

    APMS, Development Services and Deployment Services. For any given phase, one group

    will be moving the Epic and the others will be either supporting or being kept informed.You'll notice on the photo there are phases which have "rows" as well as "columns". The

    rows indicate teams, whilst the columns indicate states. Any state which has rows is one

    where a feature team has the ball - you'll notice photos in the start of each swimlane in the

    "Prepare Discover" state indicating which team is which.

    On the day PSIs become viable for this train, the phases and states will change very little.

    Initiate & Discover effectively involve the identification, sizing and prioritisation of features

    in preparation for PSI injection and maintenance of roadmap, Launch equates to locking in

    PSI content and executing PSI planning, and Evolve is delivery of the PSI.

    The Initiate Phase

    http://2.bp.blogspot.com/-J9soh8VwK7k/USoMZjjXeoI/AAAAAAAAADI/Eq2PAr75PKw/s1600/Initiate+Phase+%2528Blog%2529.jpg
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    6/10

    This phase is led by APMS and basically loads the Epic onto the train. The primary goals

    are as follows:

    Execute handover with the demand management group (PMO and Validate

    Entry states)

    Connect with the Epic Owner, ensure their value drivers for the epic are clearly

    articulated and introduce them to the operating model (Envision state)

    Identify candidate feature owners ( Envision state)

    Determine the feature team which will execute discovery, the sprint when it will

    occur, and ensure logistics are organised for discovery to proceed smoothly.

    (Prepare discovery state)

    This phase is the primary evidence of the response to APMS Challenge 2. It explicitly

    limits the amount and nature of the work done by APMS before connecting the Epic andFeature owners with the teams for further analysis. In effect, it eliminated roughly 70% of

    the preparation work that was initially being conducted.

    Looking at the wall, you'll see one epic that's just landed from demand management (with

    the smurf avatar on it indicating the project manager who's pulled the card). One is in the

    envisioning state, one has completed envisioning but is blocked from being pulled into

    discovery preparation (the big red "X" on it). Finally, there is one epic being prepared to

    drop into Discovery with the Astrotrain team.

    Discovery is led by the feature teams, and involves working with the Epic and Feature

    owners to discover the features and explore the feature level requirements sufficiently to

    articulate and size the outcomes. A feature team will typically have roughly 10% of their

    sprint capacity dedicated to discovery work, with discovery for most epics concluding

    within a single sprint. The flow of states is as follows:

    Kickoff Discovery: Workshop with Epic Owner and all Feature Owners to gain

    understanding of the vision for the epic, determine the exploration workshops

    required, identify key risks/issues and ensure the stakeholders understand the

    discovery process.

    Explore Features: Detailed workshops with feature owners to validate the

    feature composition, high level stories and feature level acceptance criteria.

    Consolidation: Consolidation of the outputs from feature exploration

    workshops, estimation and preparation of a high level release plan.

    Discovery Outcome: Presentation back to Epic and Feature Owners of

    consolidated discovery outputs for validation and agreement of outcomes

    The key outcome of Discovery is a set of prioritised, well-groomed features which have

    been estimated to a +- 30% level confidence and are ready to play for implementation.

    The other potential outcome is an Epic split. Once an Epic starts to look larger than half a

    million dollars, the preferred approach is to identify the highest priority features for initial

    implementation and carve off the remainder into a new Epic for a future release. In PSI

    parlance, its making sure no more than roughly a PSI worth of features are progressed at

    once on the Epic.

    The Discovery Phase

    http://1.bp.blogspot.com/-UARYcTVFu00/USoMaXw9tjI/AAAAAAAAADQ/64NQa_JTS3M/s1600/Discover+Phase+%2528Blog%2529.jpg
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    7/10

    Looking at the wall, you'll see Astrotrain f inalising Discovery for one Epic, Kaizen (3rd row)

    finalising one and kicking off another and Maglev consolidating one set of outputs whilst

    kicking off another. It's unusual for a team to have more than one Epic in Discovery at a

    time, in this case it's likely that they are small Epics which minimal feature elaboration

    required.

    This phase is reasonably self-explanatory. The focus returns to APMS, who look after

    gaining the appropriate approvals of the discovery outcomes and funding to proceed.

    Whilst in an ideal world this phase would be traversed rapidly to achieve a smooth flow

    from discovery to evolve, the reality is epics regularly sit here for significant periods whilst

    business cases gain approval and enterprise gating cycles complete. It has generated one

    simple and obvious insight the better the Initiate and Discovery phases are executed,

    the shorter and smoother the launch phase process.

    Launch concludes with evolve preparation. The feature team or teams to execute evolve

    are identified, logistics are organised for the release planning session at the start of

    evolve, the commencement sprint is locked in and the feature teams re-familiarise

    themselves with the discovery outcomes.

    The key aspect to evolve preparation is feature team selection. Obviously, the ideal

    scenario is for the entire epic to land with a single feature team and for the evolve feature

    team to be the same one which executed discovery. However, reality intervenes. Whilst

    evolve capacity availability is utilised in selecting the discovery team, when the launch

    phase is protracted that team is often not available for evolve. In these scenarios, some

    capacity is reserved in the backlog of the discovery team to ensure they are available to

    support the kickoff and rapid knowledge uptake of the evolve team(s). Likewise, where the

    Epic is too large to be executed by a single feature team, work will be spread acrossfeature teams on a feature by feature basis.

    Looking at the photo, you'll notice a few things. Firstly, queues are very visible :)

    Secondly, although the APMS team runs a kanban system for their work (as hinted at by

    the epic level cumulative flow diagram and control chart on the wall), they also track the

    sprint (or iteration) cadence. Their priorities on any given day are driven by where in the

    sprint cadence the feature teams are. Finally you'll see the cards with post-its on them

    Launch Phase

    http://1.bp.blogspot.com/-jUg7aLm-GSw/USoMdr7K3hI/AAAAAAAAADo/sFCwzQoXflo/s1600/Launch+Phase+%2528Blog%2529.jpg
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    8/10

    ('1', '2' and '4'). These would have been identified at the standup that day as needing

    urgent attention.

    Implementation and deployment of the epic will be covered in the next post, so I will keep

    this section intentionally light. The states are as follows:

    Plan Release: Execute the release planning which would normally occur in a

    PSI planning session. The stories identified in discovery are broken down into

    sprint-size and scheduled across sprints based on available capacity to

    create an initial release plan. One of the key outcomes of this workshop is

    establishment of working agreements with the feature owners. They know

    which sprints their feature will be active in, when acceptance testing for their

    feature will occur and can plan their availability accordingly.

    Implement: Build and acceptance testing of features.

    Integrate and Prep Deployment: This phase has a split personality depending

    on deployment type. For an independent deployment, it takes roughly a week

    and involves standard integration, deployment hardening and operational

    handover preparation activities. For deployments associated with an enterprise

    release (75-80%), it lasts 4-5 sprints. The work cannot be accelerated, as the

    timing and nature of involvement is dependent on enterprise level co-ordination. Teams thus wind up with a trickle-feed capacity reservation during

    this time.

    Looking at the wall, you'll see Astrotrain juggling 3 Epics in implementation, with a

    'stakeholder concern flag' on one probably giving hints as to why another Epic is being

    prepared to drop into the team. Moving down the board, Jacobite are implementing a

    single (large) Epic, Kaizen have one in implementation and are most likely getting close to

    done there based on the fact they're in release planning on a second. Maglev have a

    more even spread, with 5 epics at various stages of Evolve.

    Fans of limiting WIP (presumably most readers of this blog) are probably looking at this

    picture and saying "why aren't they finishing one Epic before starting the next". My first,

    somewhat glib, response is "isn't it great that it's so obvious". On a more serious note, in

    a highly integrated world you often can't go at full pace on a single initiative. It has fast

    times and slow times as you synchronise with your interface partners and resolve other

    such dependencies. Having the flexibility to deal with this has been a very important

    aspect of the framework success.

    Evolve Phase

    Operate Phase

    http://4.bp.blogspot.com/-34PCSjJQ55c/USoMaj6_kLI/AAAAAAAAADY/aVR3RWPiVAQ/s1600/Evolve+Phase+%2528Blog%2529.jpg
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    9/10Posted by Mark Richards at 6:06 AM

    Under the leadership of deployment services, the epic is deployed and in operation.

    Whilst numerous tidy-up activities around production verification testing and governanceclosure occur here, the key component introduced has been the Epic retrospective. This

    closes a significant gap in the PSI Inspect and Adapt cycle. Whilst numerous release

    train feedback cycles existed, what was missing was the stakeholder learning. The

    feature team holds a retrospective with their epic and feature owners looking at the whole

    of lifecycle experience, and an invaluable source of strategic learnings is introduced.

    The second state is Spanked. It is the cause of much hilarity amongst visitors, but has

    become part of the cultural identity of the release train. Originally introduced for some

    personality on a team kanban wall by an English scrum-master, it stands for done done.

    The Epics in production, the customers are happy, and the team has spanked it.Looking

    at the wall, it's fairly easy to conclude that it's not long since a major deployment window.

    The daily rhythm of all the groups will be covered in the next post, but its worth making a

    few concluding comments here. The first is to play back to Deans concept of the release

    train as a self organising program. Effective visualisation of the epic lifecycle is a vital

    ingredient, as it generates so much knowledge at a glance of the state of play of the

    entire value chain. Within seconds, the group can identify what epics are where in the

    value chain, who has carriage, where the queues are and what needs focus. And of

    course, metric analysis through cumulative flow and cycle time charting at the Epic level.

    All of this across a system of work that at any given time generally has 30-40 epics

    somewhere in the value chain.

    I'll close with a hint of things to come when we talk about results in the final post for the

    series. You might remember a mention of 18 project managers in the initial context at the

    beginning of the post - there are now 3.

    PS Part 4 in the seriesis now posted and deals with the program level feature wall and in-

    play work.

    Conclusion

    http://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.htmlhttp://1.bp.blogspot.com/-T5_9tfBP_cI/USoMdETKc4I/AAAAAAAAADg/i5YXTtlpJg4/s1600/Operate+Phase+%2528Blog%2529.jpghttp://www.agilenotanarchy.com/2013/02/scaled-agile-framework-35-program-level.htmlhttps://plus.google.com/105997851221079634629
  • 7/24/2019 A is for Agile, Not Anarchy: Scaled Agile Framework 3:5 - Program Level Pipeline Management and the

    10/10

    Newer Post Older PostHome

    Subscribe to: Post Comments (Atom)

    $% '()*++(,- ./01 *, 2**34(

    Enter your comment...

    Comment as: Google Accoun

    Publish

    Preview

    No comments:

    Post a Comment

    Simple template. Powered by Blogger.

    https://www.blogger.com/https://www.blogger.com/share-post.g?blogID=7030397814607511868&postID=2092395649261347510&target=pinteresthttps://www.blogger.com/share-post.g?blogID=7030397814607511868&postID=2092395649261347510&target=facebookhttps://www.blogger.com/share-post.g?blogID=7030397814607511868&postID=2092395649261347510&target=twitterhttps://www.blogger.com/share-post.g?blogID=7030397814607511868&postID=2092395649261347510&target=bloghttps://www.blogger.com/share-post.g?blogID=7030397814607511868&postID=2092395649261347510&target=emailhttp://www.agilenotanarchy.com/feeds/2092395649261347510/comments/defaulthttp://www.agilenotanarchy.com/http://www.agilenotanarchy.com/2013/02/scaled-agile-framework-applied-25.htmlhttp://www.agilenotanarchy.com/2013/03/scaled-agile-framework-applied-45-in.html