A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

Embed Size (px)

Citation preview

  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    1/7

    A nancial feasibility evaluation of using evaporative cooling with air-conditioning

    (in hybrid mode) in commercial buildings in India

    Varun Jain, S.C. Mullick, Tara C. Kandpal

    Centre for Energy Studies, Indian Institute of Technology Delhi, Hauz Khas, New Delhi 110016, India

    a b s t r a c ta r t i c l e i n f o

    Article history:

    Received 22 March 2012

    Revised 2 November 2012Accepted 4 November 2012

    Available online 19 December 2012

    Keywords:

    Hybrid system

    Direct evaporative cooling

    Payback period

    Life cycle cost

    Net present value

    Results of a preliminaryanalysisto study thenancial feasibility of a hybrid mode operation of a direct evaporative

    cooler(DEC) with an airconditioning (AC) unit to reduce theannual expenditureon electricityusage(as against a

    standalone AC unit to provide almost similar level of comfort) are presented. Four different building applications

    located in four different cities of India have been considered in the study. The hybrid mode operation is found

    nancially attractive for movie theater and waiting hall building applications for all the climatic conditions consid-

    ered in the present study.

    2012 International Energy Initiative. Published by Elsevier Inc. All rights reserved.

    Introduction

    The need and use of air-conditioning are rapidly increasing in

    urban India and normally vapor compression systems are beingused for this purpose. As a consequence the electrical consumption

    for air-conditioning is also increasing at a rapid rate. It is therefore

    imperative to develop and implement practically feasible alternative

    options that can provide acceptable levels of comfort with relatively

    lower electricity consumption. For commercial buildings, use of direct

    evaporative cooling based systems in a hybrid mode with conven-

    tional vapor compression based air-conditioning systems during hot

    and dry months of the year is one such possibility. Besides the opera-

    tional issues of a hybrid system, the primary consideration in making

    a choice for the hybrid system as against a standard vapor compres-

    sion based air-conditioning system would concern the nancial

    viability of increased capital investment (higher cost of a hybrid sys-

    tem consisting of both the vapor compression air-conditioning (AC)

    system as well the direct evaporative cooler (DEC) as against its

    lower overall cost of operation due to lower electricity consumption

    of the hybrid system as against that of a standalone AC unit for

    satisfaction of the same demand). The approach and the results of

    an attempt to study the nancial feasibility of an investment in a

    hybrid (AC+DEC) system as compared to a standalone AC system

    are presented in this paper for four Indian cities.

    Four cities in India namely Akola (hot and dry climate), Bangalore 1

    (temperate climate), Delhi (composite climate) and Indore (composite

    climate) were considered for the study. Though the sites of Delhi and

    Indore are in the same climatic zone, but being in different regions

    their ambient conditions differ considerably and hence also the room

    conditions (Hindoliya, 2005). Building application congurations con-sidered include (i) high density ofce (with high internal loads due to

    occupancy, lights, computers etc.), (ii) low density ofce, (iii) movie

    theater and (iv) waiting hall. The external and internal input parame-

    ters toTRNSYS (2005)for these buildings are presented inTable A1of

    the Appendix (Jain, 2010). In the case of the standalone AC unit the

    room temperature is set at 26 C and RH70%. Since with the use of a

    direct evaporative cooler (DEC) the attained room conditions change

    with ambient conditions, a range of room temperatures and relative

    humidity values are considered as set points (27.1 C, 70%; 27.6 C,

    60%; and 28.1 C, 50%) (Jain, 2010). A systematic procedure (Fig. 1)

    was followed for estimating the electricity requirement for maintaining

    the desired comfort level in the chosen building congurations at the

    four selected locations. TRNSYS (2005) was used to simulate the

    rooms/buildings. The fractions of time during the year when cooling is

    needed and a DEC can provide the acceptable comfort were estimated.

    The results obtained are summarized inTable 1.

    Analysis

    The hybrid system considered in the system consists of a DEC unit

    along with the AC unit arranged in a manner that whenever the

    required comfort is not achieved with the DEC unit, the AC unit is

    switched on and DEC unit is switched off. The AC unit considered in

    the study is a split air cooled system with indoor and outdoor units

    interconnected with refrigerant piping and its cost includes the cost of

    refrigerant piping, cost of air distribution system and standard control

    Energy for Sustainable Development 17 (2013) 4753

    Corresponding author. Tel.: +91 11 26591262.

    E-mail address:[email protected](T.C. Kandpal).1 New name for city of Bangalore is Bengaluru.

    0973-0826/$ see front matter 2012 International Energy Initiative. Published by Elsevier Inc. All rights reserved.

    http://dx.doi.org/10.1016/j.esd.2012.11.002

    Contents lists available at SciVerse ScienceDirect

    Energy for Sustainable Development

    http://-/?-http://dx.doi.org/10.1016/j.esd.2012.11.002http://dx.doi.org/10.1016/j.esd.2012.11.002http://dx.doi.org/10.1016/j.esd.2012.11.002mailto:[email protected]://dx.doi.org/10.1016/j.esd.2012.11.002http://www.sciencedirect.com/science/journal/00000000http://www.sciencedirect.com/science/journal/00000000http://dx.doi.org/10.1016/j.esd.2012.11.002mailto:[email protected]://dx.doi.org/10.1016/j.esd.2012.11.002http://-/?-http://-/?-
  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    2/7

    components (suppliedwith the AC unit). The annual costof maintenance

    of the AC unit is essentially denedby thecost of its annual maintenance

    contract that includes all required spares, consumables, refrigerant gas

    and oil etc. as well as all scheduled and unscheduled maintenance visits.

    The cost of the hybrid system includes the cost of the DEC unit,

    variable frequency drive, and cost of air distribution system and control

    unit as well as the cost of the AC unit. Consequently, the annual cost of

    maintenance of hybrid system comprises the cost of annual mainte-

    nance contract for the AC unit, the DEC unit, variable frequency drive

    and the control unit.

    The annual cost of operation of an AC unit is essentially de ned by

    the cost of electricity consumed in its operation, while for the hybrid

    system it should include both the cost of electricity consumed as well

    that of water used in the DEC unit.The annual operating cost of a standalone AC unit during its rst

    year of operation can be estimated as the product of annual electricity

    consumption (in kWh) for standalone AC unit (AECac) and the unit

    price of electricity (Upe) for the user during the rst year. If the unit

    cost of electricity is expected to escalate at annual rate (in fraction)

    resc, the annual operating cost of the AC unit (AOC-ACj) in jth year

    of its useful life can be estimated as

    AOCACj AECac Upe

    1 resc

    j1: 1

    Cumulative present value of the life cycle operating cost of thestandalone AC unit (PVLCCac) with a useful life of n years can be

    estimated as

    PVLCCacAECac Upe

    dresc

    11 resc

    1 d

    n 2

    where d represents the discount rate.

    Similarly, the cumulative present value of the operating cost of the

    hybrid system (PVLCChybrid) can be expressed as

    PVLCChybrid AEChyb

    Upe

    dresc

    11 resc

    1 d

    n

    3

    where, AEChybrepresents the annual energy consumption (in kWh) of

    the hybrid system. As mentioned earlier, the annual maintenance cost

    of the hybrid (DEC+AC) system (AMChyb) essentially comprises of the

    annual maintenance costs of the vapor compression air-conditioning

    (AC) system (AMCac), of the direct evaporative cooler unit (AMCdec), of

    the VFD (AMCvfd) and that of the control (AMCcontrol). Thus

    AMChyb AMCac AMCdec AMCvfd AMCcontrol: 4

    If it is assumed that the overall annual cost of maintenance of

    the hybrid system escalates at an annual rate (in fraction) jesc, the

    cumulative present value of its annual costs of maintenance during

    its useful life (PVCOMhybrid) can be expressed as

    PVCOMhybrid AMChyb

    djesc 1 1 jesc

    1 d

    n

    : 5

    In order to facilitate a comparison of the nancial attractiveness

    of a hybrid system with a standalone vapor compression type AC

    system, the values of life cycle and levelized annual costs, as well as

    simplepayback period and net present value of incremental investment

    on the hybrid system have been calculated, for all the four building

    applications in the cities of Akola, Bangalore, Delhi and Indore.

    The life cycle cost (LCC) is estimated as the total sum of the capital

    cost, and the cumulative present value costof operation andmaintenance

    during the life cycle of theproject. The levelized annual cost is the sum of

    theannualized capital cost andthe levelized annualcost of operation and

    maintenance. The levelized annual values of the cost of operation and

    maintenance have been estimated by rst calculating the equivalentpresent value life cycle costs and then redistributing the same over the

    useful life by using the capital recovery factor. Such a procedure allows

    Selection of building application

    Use of TRNSYS for calculation of cooling load for each

    building application, for the city considered

    Estimating the supply conditions and air change rate of

    DEC to achieve best possible room conditions,using a

    computer program developed for this purpose

    Supply conditions and airchange rate calculated in the

    previous step are used as inputs in TRNSYS for

    respective building applications to determinethe room

    conditions

    DEC can provide comfort, if the room conditions is

    acceptable for that particular hour, otherwise the AC is

    needed

    Total energy consumed in the hybrid mode operation (AC

    and DEC)is compared with the energy consumed if

    standalone AC is operating for all hours that require cooling

    during the year

    Fig. 1.Schematic diagram of the procedure for estimation of energy savings with the

    use of hybrid system.

    Table 1

    Potential of using direct evaporative cooler unit and corresponding annual electricity savings.

    Building Application Fraction of time DEC can be used for demand satisfaction Annualamount of electricity savedwith theuse ofhybrid system(kWh)

    Akola Bangalore Delhi Indore Akola Bangalore Delhi Indore

    High density ofce 0.56 0.88 0.37 0.65 5600 6100 1900 4500

    Low density ofce 0.57 0.83 0.37 0.65 3000 4000 1300 3100

    Movie theater 0.53 0.79 0.35 0.61 13,600 7100 3800 8800

    Waiting hall 0.43 0.55 0.31 0.55 11,700 6700 3700 8500

    Notes: (i) hours of operations of AC unit and DEC unit in a hybrid system are presented in Table A2of the Appendix.

    (ii) Capacities of AC unit and DEC unit are indicated inTable A3of the Appendix.

    48 V. Jain et al. / Energy for Sustainable Development 17 (2013) 4753

  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    3/7

    internalization of any annual escalation in the cost of operation and

    maintenance.

    The NPV of incremental investment required for the hybrid sys-

    tem essentially takes into account, the incremental costs of hybrid

    unit (both capital as well maintenance costs) as well as the monetary

    savings due to reduced electricity consumption. The simple payback

    period is determined as the length of time required to recover

    the incremental investment on DEC, VFD and controls through the

    net monetary savings due to reduced electricity consumption while

    using a hybrid system.

    Assumptions and input parameters

    Effective value of unit price of electricity to the user

    Since most of the commercial buildings use diesel generating

    (DG) set(s) to meet the electricity requirements during periods of

    unavailability of grid electricity, the weighted average of the cost of

    grid electricity and the cost of electricity from the DG set(s) has been

    used as the unit cost of electricity to the user. In this study, it assumed

    that, on an annual average basis, the grid electricity is available for

    60% time of the year at a price of Rs 6.00 per kWh 2 and the remaining

    40% of the time DG Set based electricity is used at an estimated price

    of Rs 11.00 per kWh. Thus a weighted average value of Rs 8.00 per

    kWh (=6(0.6)+11(0.4)) is obtained. An annual increase of 5% in the

    weighted average value of the unit price of electricity for the user is

    also internalized in the calculations.

    Useful life

    The expected useful life of the AC unit as well as that of the

    DEC unit is assumed to be 15 years with the provision of an annual

    maintenance contract.

    Cost of annual maintenance contract for AC and DEC units

    Based on detailed discussions with the manufacturers and suppliers

    of both the AC and DEC units inthe country,the cost of AMC isestimated

    at 10% of the total capital cost with an annual increase of 5% from the

    base year value.

    Cost of air distribution system

    Air distribution system includes sheet metal duct, exible connec-

    tion, volume control dampers, supply/return air diffusers, exhaust air

    grilles etc. Using the cost estimates received from the manufacturers

    and suppliers (Table 2) the following cost function is obtained for the

    cost of air distribution system (Cads) in Indian Rupees as a function of

    the air ow rate (AFR) in cubic meter per minute.

    Cads 2752:6 AFR 0:6861

    6

    Capital cost of AC unit

    The cost estimates as obtained from manufacturers for different

    capacity split air cooled type AC units are presented inTable 3.

    Capital cost of direct evaporative cooling unit

    An air washer type direct evaporative cooling (DEC) unit used in

    commercial buildingsis considered in the present study. It typically con-

    sists of a centrifugal fan and motor assembly, isolators, lters, humidi-

    cation media (cellulose pad), GI water tank, FRP header for the water

    distribution, and an appropriate sized pump to re-circulate the water.

    The cost estimates of DEC units as a function of airow rate as obtainedfrom the manufacturers and suppliers are presented in Table 4. The

    following cost function is obtained for the capital cost of the DEC (C dec)

    in Indian Rupees as a function of the air ow rate (AFR) using the data

    presented inTable 4.

    Cdec 466:1 x AFR 0:9792

    : 7

    Discount rate

    A discount rate of 12% is used in the study.

    Cost of variable frequency drive (VFD) and controls

    Based on the inputs received from the manufacturers the cost of

    VFD and cost of controls is assumed to be Rs. 25,000 each.

    Results and discussion

    Using the numerical values of input parameters presented in

    Assumptions and input parameters section, the values of life cycle

    cost (LCC), levelized annual cost, as well as the simple payback period

    (SPP) and NPV of incremental investment on a hybrid system have

    been calculated. The results are presented in Table 5 and a brief

    discussion on the results is presented in the following paragraphs.

    It is observed, that in Indore the hybrid system is nancially

    attractive for high density ofce, movie theater and waiting hall and

    not for the low density ofce. This may be attributed to a relativelylow value of LCC of a standalone AC unit in the low density ofce.

    2

    US $1=Indian Rupees (Rs) 45.50 in October, 2010.

    Table 2

    Dependence of cost of air distribution system on the ow rate.

    Air ow rate

    (in cubic feet per minute)

    Air ow rate

    (in cubic meter per minute)

    Costa of air distribution

    system (Rs)

    1000 28 27,050

    2000 57 44,400

    3000 85 58,550

    5000 142 81,450

    a Values of various costs quoted in the paper pertain to year 2010 (US $1=Rs 45.50

    in October, 2010).

    Table 3

    Costs of split air cooled AC units.

    Capacity of AC unit (TR) Cost of AC unit (Rs)

    3.0 48,000

    5.5 78,000

    8.5 110,000

    11.0 145,000

    17.0 210,000

    22.0 280,000

    Table 4

    Capital cost of direct evaporative cooler (DEC) units (air washer type).

    Capacity of DEC unit

    (cubic feet per minute)

    Capacity of DEC unit

    (cubic meter per minute)

    Cost of DEC unit

    (Rs)

    2500 71 30,000

    3000 85 36,000

    5000 142 60,000

    10,000 283 120,000

    15,000 425 172,500

    20,000 567 230,000

    25,000 708 287,500

    30,000 850 345,000

    49V. Jain et al. / Energy for Sustainable Development 17 (2013) 4753

    http://-/?-http://-/?-http://-/?-
  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    4/7

    Table 5

    Measures ofnancial attractiveness for all the four building applications in Akola, Bangalore, Delhi and Indore.

    Unit Akola Bangalore Delhi Indore

    AC system Hybrid system AC system Hybrid system AC system Hybrid system AC system Hybrid system

    (A) High density ofce

    Life cycle cost 1000 Rs 1165 1002 750 543 739 823 746 674

    Levelized annual cost 1000 Rs 171 147 110 80 108 121 110 99

    Simple payback period

    (of incremental investment)

    Years 3.6 3.3 42 6

    NPV (of incremental investment) 1000 Rs 163 207 84 73

    (B) Low density ofce

    Life cycle cost 1000 Rs 680 710 551 489 535 658 547 565

    Levelized annual cost 1000 Rs 100 104 81 72 79 97 80 83

    Simple payback period

    (of incremental investment)

    Years 14.5 6.1 Not feasible 12.2

    NPV (of incremental investment) 1000 Rs 30 62 123 18

    (C) Movie theater

    Life cycle cost 1000 Rs 3012 2329 1107 906 1979 1967 1625 1321

    Levelized annual cost 1000 Rs 442 342 162 133 291 289 239 194

    Simple payback period

    (of incremental investment)

    Years 1.1 4 8.7 2.9

    NPV (of incremental investment) 1000 Rs 684 201 12 304

    (D) Waiting hall

    Life cycle cost 1000 Rs 3180 2519 1384 1124 2011 1923 1752 1371Levelized annual cost 1000 Rs 467 370 203 165 295 282 257 201

    Simple payback period

    (of incremental investment)

    Years 0.6 2.5 4.1 1.7

    NPV (of incremental investment) 1000 Rs 661 260 89 354

    Fig. 2.Sensitivity of the net present value of hybrid system (DEC+AC) in high density

    ofce to the values of (a) discount rate, (b) useful life, and (c) unit price of electricity.

    Fig. 3. Sensitivity of net present value of hybrid system (DEC+AC) in low density

    ofce to the values of (a) discount rate, (b) useful life, and (c) unit price of electricity.

    50 V. Jain et al. / Energy for Sustainable Development 17 (2013) 4753

    http://localhost/var/www/apps/conversion/tmp/scratch_7/image%20of%20Fig.%E0%B3%80
  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    5/7

    It is noted the LCC for the standalone AC system is maximum for

    waiting hall building and minimum for low density ofce, for all the

    four cities considered in the present study. Also, as expected, the

    hybrid system becomes attractive when there is a large difference

    between LCC of standalone AC unit and that of a hybrid system.

    In Delhi, the hybrid system is not attractive in two out of four build-

    ing applications (i.e., hybrid system is attractive for movie theater and

    waiting hall building only). For city of Delhi, in the case of low density

    ofce theuse of a hybridsystem thoughreduces electricity consumption

    its operating cost (cost of AMC, electricity and water cost) is much more

    in than that for a standalone AC system. The attractiveness of the hybrid

    system at Akola is somewhat similar to that observed for the city of In-

    dore, i.e., the hybrid system is attractive for high density ofce, movie

    theater and waiting hall. However, the recovery of the capital cost isfaster as compared to Indore. For the case of high density ofce the sim-

    ple payback period (SPP) of incremental investment in a hybrid system

    is 6.0 years in Indorewhileit is 3.6 years forAkola. Similarly, while in In-

    dore the values of the SPP for movie theater and waiting hall buildings

    are 2.9 years and 1.7 years respectively the corresponding values for

    Akola are 1.1 year and 0.6 years respectively. In Bangalore, the hybrid

    system isnancially attractive for all the four building applications.

    Variation of the NPV of the incremental investment on a hybrid

    system, with discount rate, useful life and unit price of electricity,

    for high density ofce for all the four cities is presented in Fig. 2

    (a to c). It may be noted that the NPV of incremental investment

    in a hybrid system is quite sensitive to the values of these input

    parameters. Results of similar sensitivity analysis for the case of low

    density ofce for three locations (excluding Delhi) are presented in

    Fig. 3. Results for the cases of movie theater and waiting hall are

    presented inFigs. 4 and 5respectively for all the four locations consid-

    ered in the study. It may be noted that except the low density ofce, all

    the other three building applications in Indore and Akola can benet

    from the use of a hybrid system with monetary gains for the investor.

    In Delhi, only the movie theater and the waiting hall building can

    benet from the use of a hybrid system. This is different from the

    results obtained for Indore, although the city of Delhi is grouped in

    the same climatic zone i.e. composite zone as per the National Build-

    ing Code. In Bangalore, all the four building applications can benet

    from the hybrid system. A summary of the feasibility of using hybrid

    Fig. 4.Sensitivity of net present value of hybrid system (DEC+AC) in movie theater to

    the values of (a) discount rate, (b) useful life, and (c) unit price of electricity.

    Fig. 5.Sensitivity of net present value of hybrid system (DEC+AC) in waiting hall tothe values of (a) discount rate, (b) useful life, and (c) unit price of electricity.

    Table 6

    Feasibility of using hybrid system as against standalone vapor compression AC system

    {feasible: []; not feasible: [X]}.

    S. no. Cities (climatic zone

    as per NBC)

    High density

    ofce

    Low density

    ofce

    Movie

    theater

    Waiting

    hall

    1 Akola (ho t and dry

    climatic zone)

    X

    2 Bangalore (temperate

    climatic zone)

    3 Delhi ( composit e

    climatic zone)

    X X

    4 Indore (composite

    climatic zone)

    X

    51V. Jain et al. / Energy for Sustainable Development 17 (2013) 4753

    http://localhost/var/www/apps/conversion/tmp/scratch_7/image%20of%20Fig.%E0%B5%80http://localhost/var/www/apps/conversion/tmp/scratch_7/image%20of%20Fig.%E0%B4%80
  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    6/7

    Table A1

    External and internal input parameters for different building applications (Jain, 2010).

    Sl. no. Description High density of ce Low density ofce Mo vie the at er Waiting hall Remar ks

    1 Area (m2) Unit size of,

    10 m5 m

    Unit size of,

    10 m5 m

    Unit size of,

    10 m5 m

    Unit size of,

    10 m5 m

    Same area modular unita considered for

    purpose of comparison.

    2 Height (m) 3.50 m 3.50 m 6.00 m 3.50 m Same height considered for the purpose of

    comparison (except theater)

    3 Volume (m3) 175 m3 175 m3 300 m3 175 m3

    5 Occupancy (numbers) 8 4 75 50 As per National Building Code (NBC)6 Fresh air in cubic meter per minute

    (CMM)

    4.8 2.4 36 24 As per NBC

    7 Air changes per hour (ac/h) 1.65 0.82 7.2 8.23

    8 No rt h wall area (m2) 35 35 60 35

    9 South wall area (m2) 35 35 60 35

    10 Ceiling Internal partition Internal partition Internal partition Internal partition

    11 No rt h windo w (m2) 14 14 0 14 40% glass, as per Energy Conservation

    Building Code (ECBC)

    12 South windo w (m2) 14 14 0 14 40% glass, as per ECBC

    13 Equipment load

    (light/power density in W/m2)

    24 W/m2 11.8 W/m2 12.9 W/m2 10.8 W/m2 As per ECBC

    14 Wall U-factor (W/m2/K 0.39 0.39 0.39 0.39 Within the limit given in ECBC i.e., 0.4

    15 Solar heat gain coefcient (SHGC) 0.75 0.75 0.75 As per ECBC 0.25b

    16 Glass U-factor (W/m2/K) 2.83 2.83 0 2.83 Within the limit given in ECBC.

    Notes:

    All the other

    oors, walls are considered as internal partitions.

    Room internal capacitance is considered as 2100 kJ/K for all the buildings excluding Movie theater where it is 3600 kJ/K.a Part unit size considered from a building oriented along eastwest (facing northsouth direction).b As per information received from the architects and HVAC designers, glass available with SHGC of 0.25 are very expensive, therefore, generally glass are provided with SHGC of

    0.7 to 0.75 with internal shadings (in buildings), to make up for the rest. In present study, SHGC of 0.75 with suitable internal shading accordingly is considered.

    system (as against the standalone vapor compression AC system) is

    presented inTable 6.

    Concluding remarks

    The results of the simple nancial analysis presented in the present

    study suggest that a hybrid system (comprising of an AC unit as well

    as a DEC unit) can be a nancially attractive option in certain cities/

    region of the country for high density ofce, movie theater and

    waiting hall applications as the hybrid system appears to be more

    attractive for building with higher cooling loads. Efforts should

    therefore be directed towards exploiting the potential of hybrid

    systems for meeting high cooling loads in suitable climatic

    conditions.

    Table A2

    Hours of operation of AC unit and DEC unit is a hybrid system for comfort conditions of 26 TSI (Jain, 2010).

    Building application Operating hours of AC and DEC in a hybrid system for comfort conditions of 26 TSI

    Akola Bangalore Delhi Indore

    AC DEC AC DEC AC DEC AC DEC

    High density ofce 3868 4887 1028 7732 3691 2187 2542 4727

    Low density ofce 3623 4881 1420 7090 3605 2146 2461 4510

    Movie theater 3956 4385 1774 6511 3711 1955 2643 4175Waiting hall 4854 3702 3842 4782 3998 1793 3141 3908

    Table A3

    Selected DEC unit capacity in m3/h for different building application and AC unit capacity for different building applications as well as for different cities (Jain, 2010).

    Building applications Capacity of selected DEC unit inow rate in m3/mina Capacity of selected AC unit (in tons of refrigeration (TR) and ow rate in m3/min).

    Akola Bangalore Delhi Indore

    TR m3/min TR m3/min TR m3/min TR m3/min

    High density ofce 87.5 5.5 62 3 34 3 34 3 34

    Low density ofce 87.5 3 34 3 34 3 34 3 34

    Movie theater 150 17 193 5.5 62 11 125 8.5 96

    Waiting hall 87.5 17 193 5.5 62 11 125 8.5 96

    a DEC unit capacity is calculated with volume of the room and air change rate. In our case, volume (10 m5 m3.5 m) and air change rate (30 ac/h) is same for all the type of

    buildings except in movie theater where volume is different as height is 6.0 m (air change rate is same as 30 ac/h).

    Appendix

    Thebuilding applications considered are of multi-storied and with multi-zone, however, for the purpose of study, part unit size of 10 m5 m

    is considered from a building oriented along east-west (facing northsouth direction). Same area modular unit* considered in all the building

    application for the purpose of comparison.

    52 V. Jain et al. / Energy for Sustainable Development 17 (2013) 4753

  • 8/10/2019 A financial feasibility evaluation of using evaporative cooling with air-conditioning.pdf

    7/7

    References

    Hindoliya DA. Evaporative Cooling for Thermal comfort in Buildings, Ph. D. Thesis.Delhi: Indian Institute of Technology Delhi, 2005.

    Jain Varun. Energy Conservation In Space Conditioning in India through Direct

    Evaporative Cooling, Ph. D. Thesis. Centre for Energy Studies, Indian Institute ofTechnology Delhi, 2010.

    TRNSYS, 16. A transient system simulation program. Solar Energy Laboratory, Universityof Wisconsin-Madison, 1500 Engineering Drive, 1303 Engineering Research Building,Madison, WI 53706 USA; 2005.

    53V. Jain et al. / Energy for Sustainable Development 17 (2013) 4753