206
A-E DESIGN MANUAL Marine Air Ground Task Force Training Command Marine Corps Air Ground Combat Center Twentynine Palms, CA MARCH 31, 2013

A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 1

A-E DESIGN MANUAL

Marine Air Ground Task Force Training Command

Marine Corps Air Ground Combat Center

Twentynine Palms, CA

MARCH 31, 2013

Page 2: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 2

Table of Contents

1. INTRODUCTION ........................................................................................................................ 6

1.1. GENERAL ....................................................................................................................... 6

1.2. DESIGN CRITERIA ......................................................................................................... 6

1.3. PHYSICAL SECURITY AND ANTITERRORISM............................................................. 7

1.4. DRAWING FORMAT ....................................................................................................... 7

1.5. FIRE AND LIFE SAFETY DATA ...................................................................................... 7

1.6. AVAILABILITY OF EXISTING DATA ............................................................................... 7

1.7. FIELD INVESTIGATION AND REQUIREMENTS FOR DELIVERABLES ....................... 8

2. SUSTAINABLE DESIGN ........................................................................................................... 9

2.1. GENERAL ....................................................................................................................... 9

3. EXISTING CONDITIONS (DIVISION 2) ..................................................................................... 9

3.1. GENERAL ....................................................................................................................... 9

3.2. REMOVAL AND DISPOSAL OF UNDERGROUND STORAGE TANKS ....................... 10

3.3. ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS .................... 10

3.4. REMOVAL AND DISPOSAL OF LEAD CONTAINING PAINT ...................................... 10

3.5. DESERT TORTOISE PROTECTION REQUIREMENTS .............................................. 10

4. CONCRETE (DIVISION 3) ....................................................................................................... 11

4.1. CAST -IN-PLACE CONCRETE ..................................................................................... 11

5. MASONRY (DIVISION 4) ......................................................................................................... 11

5.1. REINFORCED MASONRY ............................................................................................ 11

6. METALS (DIVISION 5) ............................................................................................................. 11

6.1. COLD FORMED METAL FRAMING .............................................................................. 11

6.2. METAL FABRICATIONS ............................................................................................... 11

7. WOOD, PLASTICS AND COMPOSITES (DIVISION 6) ........................................................... 12

7.1. ROUGH CARPENTRY .................................................................................................. 12

7.2. FINISH CARPENTRY .................................................................................................... 12

7.3. SOLID POLYMER FABRICATIONS .............................................................................. 12

8. THERMAL AND MOISTURE PROTECTION (DIVISION 7) ..................................................... 12

8.1. GENERAL: .................................................................................................................... 12

8.2. MINERAL FIBER BLANKET INSULATION ................................................................... 13

8.3. STANDING-SEAM METAL ROOFING .......................................................................... 13

Page 3: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 3

8.4. BUILT-UP ASPHALT ROOFING (AGGREGATE SURFACED)..................................... 13

8.5. BUILT-UP ASPHALT ROOFING (MINERAL SURFACED) ........................................... 13

8.6. MODIFIED BITUMINOUS MEMBRANE ROOFING ...................................................... 13

8.7. FLASHING AND SHEET METAL .................................................................................. 13

8.8. ROOF ANCHOR POINTS ............................................................................................. 14

9. OPENINGS (DIVISION 8) ......................................................................................................... 14

9.1. GENERAL ..................................................................................................................... 14

9.2. STEEL DOORS AND FRAMES ..................................................................................... 14

9.3. WOOD DOORS ............................................................................................................. 14

9.4. ALUMINUM WINDOWS ................................................................................................ 15

9.5. PLASTIC WINDOWS .................................................................................................... 15

9.6. DOOR HARDWARE ...................................................................................................... 15

9.7. GLAZING ....................................................................................................................... 17

10. FINISHES (DIVISION 9) ......................................................................................................... 17

10.1. GENERAL ................................................................................................................... 17

10.2. METAL SUPPORT ASSEMBLIES ............................................................................... 18

10.3. PLASTER AND STUCCO ........................................................................................... 18

10.4. GYPSUM WALLBOARD ............................................................................................. 18

10.5. CERAMIC TILE, QUARRY TILE AND PAVER TILE ................................................... 18

10.6. PAINTING ................................................................................................................... 18

11. SPECIALTIES (DIVISION 10) ................................................................................................ 18

11.1. TOILET PARTITIONS ................................................................................................. 18

11.2. IDENTIFICATION DEVICES ....................................................................................... 18

11.3. FIRE PROTECTION SPECIALTIES ............................................................................ 19

11.4. TOILET AND BATH ACCESSORIES .......................................................................... 20

12. EQUIPMENT (DIVISION 11) .................................................................................................. 20

12.1. FOOD SERVICE EQUIPMENT ................................................................................... 20

12.2. OTHER EQUIPMENT .................................................................................................. 20

13. FURNISHINGS (DIVISION 12) ............................................................................................... 20

13.1. BLINDS, VENETIAN AND AUDIO VISUAL ................................................................. 20

14. SPECIAL CONSTRUCTION (DIVISION 13) .......................................................................... 20

14.1. PRE-ENGINEERED METAL BUILDINGS ................................................................... 20

Page 4: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 4

14.2. Energy management and control systems (EMS) ....................................................... 21

15. CONVEYING EQUIPMENT (DIVISION 14) ............................................................................ 21

15.1. ELEVATORS ............................................................................................................... 21

16. FIRE SUPPRESSION (DIVISION 21) ..................................................................................... 21

16.1. FIRE SUPPRESSION ................................................................................................. 21

16.2. WET PIPE FIRE SUPPRESSION SPRINKLERS ........................................................ 21

16.3. FIRE PROTECTION SPECIALTIES ............................................................................ 22

17. PLUMBING (DIVISION 22) .................................................................................................... 22

17.1. PLUMBING FIXTURES ............................................................................................... 22

18. HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) (DIVISION 23) .................... 22

18.1. BASIC MECHANICAL MATERIALS AND METHODS ................................................. 22

18.2. MECHANICAL INSULATION....................................................................................... 25

18.3. HIGH TEMPERATURE HOT WATER (HTHW) PIPING SYSTEMS ............................ 26

18.4. NATURAL GAS AND LIQUID PETROLEUM PIPING SYSTEMS ............................... 28

18.5. CENTRAL REFRIGERATION EQUIPMENT FOR AIR-CONDITIONING .................... 29

18.6. EVAPORATIVE COOLING SYSTEMS ........................................................................ 30

18.7. UNITARY AIR CONDITIONING EQUIPMENT ............................................................ 31

18.8. SPACE TEMPERATURE CONTROL SYSTEMS ........................................................ 31

19. INTEGRATED AUTOMATION (DIVISION 25) ....................................................................... 32

19.1. DIRECT DIGITAL CONTROL SYSTEMS .................................................................... 32

19.2. SMOKE DETECTORS ................................................................................................ 33

19.3. MISCELLANEOUS REQUIREMENTS ........................................................................ 33

20. ELECTRICAL (DIVISION 26) ................................................................................................. 33

20.1. BASIC ELECTRICAL MATERIALS AND METHODS .................................................. 33

20.2. THREE-PHASE PAD-MOUNTED TRANSFORMERS ................................................ 38

20.3. SINGLE-PHASE PAD-MOUNTED TRANSFORMERS ............................................... 39

20.4. OVERHEAD TRANSMISSION AND DISTRIBUTION ................................................. 39

20.5. UNDERGROUND TRANSMISSION AND DISTRIBUTION ......................................... 39

20.6. SECONDARY UNIT SUBSTATIONS .......................................................................... 39

20.7. LIGHTING ................................................................................................................... 40

20.8. SOLAR PHOTOVOLTAIC SYSTEMS ......................................................................... 40

20.9. CATHODIC PROTECTION SYSTEM .......................................................................... 40

Page 5: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 5

21. COMMUNICATIONS (DIVISION 27) ...................................................................................... 41

21.1. TELECOMMUNICATIONS STANDARDS ................................................................... 41

22. ELECTRONIC SAFETY AND SECURITY (DIVISION 28) ..................................................... 41

22.1. FIRE ALARM SYSTEM ............................................................................................... 41

22.2. MASS NOTIFICATION SYSTEM ................................................................................ 43

23. EARTHWORK (DIVISION 31) ................................................................................................ 43

23.1. EARTHWORK, EXCAVATION, BACKFILLING AND COMPACTING, EXCAVATION AND FILL .............................................................................................................................. 43

24. EXTERIOR IMPROVEMENTS (DIVISION 32) ....................................................................... 43

24.1. FIRE ACCESS AND FIRE LANES .............................................................................. 43

24.2. MARKERS FOR FIRE HYDRANTS ............................................................................ 44

24.3. ASPHALT PAVING ...................................................................................................... 44

24.4. CONCRETE PAVING .................................................................................................. 44

24.5. PARKING STALL STRIPING....................................................................................... 44

24.6. PAVEMENT MARKING ............................................................................................... 45

24.7. CHAIN LINK FENCES AND GATES ........................................................................... 45

25. UTILITIES (DIVISION 33) ....................................................................................................... 45

25.1. WATER DISTRIBUTION ............................................................................................. 45

25.2. HYDRANTS ................................................................................................................. 47

25.3. NON-POTABLE WATER DISTRIBUTION ................................................................... 47

25.4. SANITARY SEWER SYSTEMS .................................................................................. 49

25.5. STORM DRAINAGE .................................................................................................... 50

26. APPENDIX A - DETAILS AND DIAGRAMS .......................................................................... 52

26.1. GENERAL ................................................................................................................... 52

26.2. CIVIL ........................................................................................................................... 52

26.3. ARCHITECTURAL ...................................................................................................... 53

26.4. MECHANICAL ............................................................................................................. 54

26.5. ELECTRICAL .............................................................................................................. 55

27. APPENDIX B - REFERENCES ............................................................................................ 204

Page 6: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 6

1. INTRODUCTION

1.1. GENERAL

1.1.1. This Manual provides policy and standards for the design, development, and revision of project documents such as plans, specifications, cost estimates, studies, and Requests for Proposals (RFP’s) for facilities at the Marine Air Ground Task Force Training Command—Marine Corps Air Ground Combat Center at Twentynine Palms, California (MAGTFTC-MCAGCC, hereafter shortened to MCAGCC, which designates the physical facility). This Manual supplements UFC 1-200-01 “General Building Requirements” and UFC 1-300-09N, “Design Procedures” by providing information, requirements and details that are site-specific to MCAGCC. UFC 1-300-09N, “Design Procedures” is modifies as follows:

1.1.1.1. PWD prefers the use of United States customary units in the design and preparation of construction documents. Do not use dual units on drawings This Manual applies to both Design-Bid-Build (DBB) and Design-Build (DB) projects.

1.1.1.2. For locally funded and HQMC funded projects, the Statement of Architectural Engineering Services (SOW) lists which deliverables and what quantities of deliverables the Government requires. This list will supersede the requirement for various deliverables described in Chapters 9 through 12 of UFC 1-300-09N.

1.1.2. Whenever a contract includes this Manual as an appendix or attachment, for example in a DB project where the Designer has a direct contractual relationship with the construction Contractor, replace every instance of the word should in this Manual, with the word shall.

1.1.3. Project documents shall conform to all applicable United Facilities Criteria (UFCs).

1.1.4. Refer to the MCAGCC Twentynine Palms Base Exterior Architecture Plan (BEAP). Bring any conflicts or deviations from the BEAP noted in this Manual to the attention of the Engineer in Charge (EIC).

1.1.5. Project documents shall conform to all conditions identified in the project’s National Environmental Policy Act (NEPA) Decision Memorandum. At project closeout the construction Contractor shall submit a certification to the Contracting Officer on company letterhead that the Contractor met the requirements of its Environmental Protection Plan (EPP) and the conditions of the Decision Memorandum during the construction period. An official of the Contractor’s company or a responsible employee who has personal knowledge of the Contractor’s compliance shall sign the letter.

1.1.6. The A-E accepts full responsibility for the technical accuracy of the project designs and professional quality of the products and services furnished. Before deviating from this Manual, confer with the EIC for approval.

1.2. DESIGN CRITERIA

1.2.1. Project designs shall conform to this A-E Design Manual, the project “Statement of Architectural-Engineering Services” or Scope of Work (SOW), and the latest edition of UFC 1-300-09N. Any deviations from these criteria require EIC approval.

1.2.2. Project designs shall conform to any federally mandated requirements in effect

Page 7: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 7

when the project is in design or construction.

1.2.3. Project designs shall conform to all federal, state and local codes, standards, regulations and ordinances, including but not limited to the latest revision or edition of any applicable codes listed in Appendix B - REFERENCES.

1.3. PHYSICAL SECURITY AND ANTITERRORISM

1.3.1. Consult with MCAGCC’s Physical Security Chief and comply with the requirements of UFC 4-010-01.

1.3.2. Provide some type of barrier to prevent vehicles from breaching the stand-off. The preferred method to maintain the stand-off is an ATFP wall around inhabited facilities. See detail SKC- 38 for the preferred method. Other methods may be used in lieu of the wall; but they shall make for an aesthetic appearance.

1.4. DRAWING FORMAT

1.4.1. A/E/C CAD Standard: Comply with the latest edition of the standard available on the whole building design guide website.

1.4.2. The project SOW will indicate the quantities of deliverables needed and other submittal requirements. Most often these will include the submittal of scalable hard-copy drawings on 11” x 17” bond paper (ANSI B-size).

1.4.3. Use font sizes that are at least 3/32” high after photo-reduction of drawing sheets to 11” x 17”.

1.4.4. Orient drawings so that north arrows always point either to the top or to the left margins. Customarily, project north orients to the left margin on drawings in the MCAGCC archive. Project north for Mainside is 38.8 degrees west of true north. Mainside is MCAGCC’s primary area of development at its southern border.

1.4.5. As a rule, the north arrow shall appear at the bottom right corner of the sheet or detail.

1.4.6. NAVFAC drawing numbers are not required for locally funded or HQMC funded projects.

1.5. FIRE AND LIFE SAFETY DATA

1.5.1. The life safety plan, fire alarm system, and fire suppression system plans (shop drawings) require the stamp of a licensed Fire Protection Engineer (FPE) and must be approved by the Fire Department prior to construction.

1.6. AVAILABILITY OF EXISTING DATA

1.6.1. Existing utility maps, record drawings and other information may be available in hard copy or in electronic format for review and reproduction. Contact the EIC to obtain as-built information.

1.6.1.1. The A-E may need to provide CD-ROM’s or other acceptable media for copying electronic drawing files. Flash drives may not be connected to DoD computers.

1.6.1.2. The A-E may need to sign a non-disclosure agreement to obtain data. Allow two weeks for acquiring data.

1.6.2. The EIC is MCAGCC’s point of contact for project information and for access to

Page 8: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 8

resources from Public Works Division (PWD) and other offices on the base.

1.7. FIELD INVESTIGATION AND REQUIREMENTS FOR DELIVERABLES

1.7.1. The SOW or RFP for each project addresses the types and quantities of deliverables required at each submittal.

1.7.2. The A-E shall make all requests for information, coordination meetings, field investigation and study through the project EIC. The EIC can provide points of contact as required.

1.7.3. The A-E shall coordinate with the EIC before entering, surveying, or photographing any facilities.

For security reasons, MCAGCC does not permit indiscriminate photography of base facilities. Coordinate in advance with the EIC so that the appropriate base personnel can be notified in a timely manner.

1.7.4. The A-E shall provide adequate notice and comply with the latest security requirements for access to MCAGCC.

1.7.5. The A-E shall complete field investigation prior to the 45% submittal.

1.7.6. Address design submittals, including those for Design-Build projects, to the EIC at PWD.

For additional guidance see UFC 1-300-09N.

UFC 1-300-09N uses the terms “Pre-Final” and “100% submittals” synonymously. These two terms generally refer to separate submittals at MCAGCC. At MCAGCC, the 100% submittal is as described in UFC 1-300-09N paragraph 10-4. The pre-final submittal consists of a stamped, wet-signed cover sheet and a few other items described in the SOW that the EIC may use to ensure that the final submittal will address previous review comments. This submittal is not for general review and the Government will not use it for construction or to advertise the project for construction. Instead, it satisfies an administrative requirement for PWD to deliver a fully signed drawing set in electronic format to the ROICC. The EIC and one or more accepting officials from MCAGCC will sign the title block. The EIC will then return this fully signed cover sheet to the design firm so the firm can proceed to the final submittal. Refer to the SOW for the pre-final deliverable requirements. These usually include:

1.7.6.1.a. Half-sized drawings (11” x 17”) marked Pre-Final Submittal and dated.

1.7.6.1.b. A half-sized (11” x 17”) print of the title sheet (G-1) with stamp and wet signatures. Note: mark this signed title sheet “Final Submittal,” not “Pre-Final Submittal.”

1.7.6.1.c. Annotated responses to 100% design submittal review comments.

1.7.7. Record Drawings: Prepare record drawings that reflect changes made during construction as well as existing conditions that differ from those known at the time the construction drawings were prepared. Revise the construction drawings to reflect as-built conditions at the completion of construction. The registered Architect or Engineer of Record in design-build contracts shall stamp and sign the record drawings. Incorporate the information gathered from the following sources:

1.7.7.1. Construction drawings annotated by the Contractor to indicate changes made

Page 9: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 9

during construction.

1.7.7.2. Drawings and instructions issued during construction as responses to Requests for Information (RFIs).

1.7.7.3. Change Orders.

1.7.7.4. Substitutions.

1.7.8. Building designs at MCAGCC shall conform to the latest federal mandates and California Title 24 standards for energy consumption plus ten percent.

1.7.9. When projects require LEED certification, give priority to energy savings points.

2. SUSTAINABLE DESIGN

2.1. GENERAL

2.1.1. Project shall be designed in compliance with all applicable federal, state, county, and municipal environmental laws and regulations, as well as any applicable existing permits and administrative orders

2.1.2. Some buildings at MCAGCC contain hazardous materials such as asbestos, lead containing paints and mold. Some existing hazardous material surveys are available at PWD that may help designers review existing conditions and specify appropriate mitigation requirements. Additional surveys may be necessary in a project to avoid presuming the existence of hazardous materials and to ensure protection of human health and the environment. The SOW may require the A-E to perform such services. If such services are necessary and the SOW does not address them, then the A-E shall delegate them to the Contractor. Hazardous material surveys shall be completed prior to any renovation or demolition that affects hazardous materials. MCAGCC is located within the MDAQMD.

2.1.3. Natural Resources and Environmental Affairs (NREA) is the base authority on environmental compliance.

2.1.4. Provide LEED services as described in the RFP or SOW. The specifications shall clearly indicate that the contractor is responsible for LEED commissioning.

2.1.5. See Combat Center Fire Department Solar Photovoltaic Installation Guidelines and APPENDIX B – REFERENCES for additional information on photovoltaic panel installation.

3. EXISTING CONDITIONS (DIVISION 2)

3.1. GENERAL

3.1.1. Provide profiles of sanitary sewer and storm drain utilities. Show all obstructions the Contractor will encounter and identify them as to location, type and size. Conform to UFC 3-200-10N, "Civil Engineering" requirements.

3.1.2. Show all existing utility lines, both in plan and in profile, which may be in the vicinity of the proposed construction, including water, sewer, electrical, telephone, high temperature hot water (HTHW), compressed air, gas, storm drain, fire alarms, fuel oil, telecommunication, cable TV, and any others. Contractor shall obtain a “DIG PERMIT” prior to start of any site work.

Page 10: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 10

3.2. REMOVAL AND DISPOSAL OF UNDERGROUND STORAGE TANKS

Projects involving the removal or disposal of UST’s require coordination with the Government throughout design and construction to ensure regulatory compliance. Coordinate with the EIC and the ROICC for meetings with Natural Resources and Environmental Affairs (NREA) as required.

3.3. ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS

3.3.1. Some buildings at MCAGCC contain asbestos.

3.3.2. Verify with the EIC if asbestos surveys are available for a building, structure or facility.

If surveys are available, review them for conformance with current regulatory requirements. If no survey is found to be in conformance with these requirements, confer with the EIC about the need to perform a satisfactory survey.

3.4. REMOVAL AND DISPOSAL OF LEAD CONTAINING PAINT

3.4.1. Some buildings at the MCAGCC contain lead based or lead containing paints.

3.4.2. Confer with the EIC about the need to perform lead surveys to meet regulatory requirements.

3.5. DESERT TORTOISE PROTECTION REQUIREMENTS

3.5.1. The Endangered Species Act (ESA) protects the Desert Tortoise and lists it as a threatened species. Construction activities shall follow the conservation measures outlined in United States Fish & Wildlife Service's (USFWS) Biological Opinion and the MAGTFTC's Integrated Natural Resources Management Plan (INRMP). The following conservation measures are Desert Tortoise specific and Contractors shall comply with them while performing work at the MAGTFTC. The following conservation measures are location dependent and may not be applicable at all sites.

3.5.2. The project site(s) shall have a pre-construction and pre-clearance tortoise survey conducted by a biologist approved by the USFWS or a designated MAGTFTC Government employee of the Natural Resources and Environmental Affairs (NREA) Division no more than 48 hours in advance of construction activities. Contractors shall coordinate this action with NREA.

3.5.3. The Contractor shall provide an approved biological monitor during all or some phases of construction. The biological monitor shall have the authority to halt work if a tortoise is exposed to “take” or “harassment” as defined in the ESA.

3.5.4. All employees that will be working at or visiting the construction site shall receive a desert tortoise awareness briefing (approximately 1/2 hour) provided by the on-site monitor or Government personnel from NREA. NREA will need 48 hours advance notice in order to provide the briefing.

3.5.5. Cover or fence trenches and holes with approved tortoise exclusionary fencing (18” minimum height) if the trenches or holes are to be left exposed overnight. A monitor shall inspect them before they are filled.

3.5.6. All pipe 2 inches or greater in diameter stored on the ground surface shall have the ends capped until installed and covered.

Page 11: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 11

3.5.7. Park all vehicles within existing road limits or at a designated area approved by the Contracting Officer. All workers or visitors to the site shall inspect for tortoise under and around their vehicles and equipment prior to moving the vehicles or equipment. Cross-country use of vehicles shall not occur unless it is essential to project activities, and then only after NREA approves a route.

3.5.8. Promptly place all trash in covered containers and remove it from the work site on a regular basis.

3.5.9. No dogs or firearms are authorized on a project site.

4. CONCRETE (DIVISION 3)

4.1. CAST -IN-PLACE CONCRETE

4.1.1. Portland cement shall be Type I or Type II, conforming to ASTM C150.

4.1.2. Reinforcement shall conform to ASTM A615, Grade 60.

4.1.3. Welded wire fabric is not permitted except in storm channels.

4.1.4. Conform to UFC 3-250-01FA, "Pavement Design for Roads, Streets, Walks, and Open Storage Areas" for rigid pavement.

5. MASONRY (DIVISION 4)

5.1. REINFORCED MASONRY

5.1.1. Masonry used in alterations or repairs of existing facilities shall match existing adjacent surfaces.

5.1.2. Use integral color CMU with matching colored mortar unless existing adjacent CMU surfaces are unpainted or painted gray.

5.1.3. Include sketches of reinforcing details in preliminary design calculations.

5.1.4. Minimum grout strength shall be 2,000 pounds psi.

5.1.5. Provide dual cavity hollow load bearing masonry units (i.e., CMU with inner cell for grout and other cell for insulation).

6. METALS (DIVISION 5)

6.1. COLD FORMED METAL FRAMING

6.1.1. Provide galvanized studs and joists only.

6.2. METAL FABRICATIONS

6.2.1. All steel fabrications shall be galvanized.

6.2.2. All exposed metal fabrications shall have a UV resistant finish such as polyvinylidene fluoride (Kynar), fluoropolymer, or silicone polyester. Epoxies shall have a UV resistant clear topcoat.

6.2.3. Metal Fabrication to screen mechanical equipment:

6.2.3.1. Screen on-grade mechanical equipment according to the BEAP.

6.2.3.2. Provide parapets or mechanical screens to conceal roof-mounted equipment.

Page 12: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 12

7. WOOD, PLASTICS AND COMPOSITES (DIVISION 6)

7.1. ROUGH CARPENTRY

7.1.1. Exposed wood may not be used as an exterior finish or trim material.

7.2. FINISH CARPENTRY

7.2.1. Provide solid surface material for work counters and countertops.

7.3. SOLID POLYMER FABRICATIONS

7.3.1. Provide molded solid polymer vanities in toilet rooms, bathrooms and shower rooms.

8. THERMAL AND MOISTURE PROTECTION (DIVISION 7)

8.1. GENERAL:

8.1.1. The A-E shall consult with the EIC on the type of roofing system desired. New roofs shall conform to the BEAP.

8.1.2. Standing-seam metal roofs are preferred. Other types of metal roofing are prohibited, with the exception of pre-engineered buildings, sheds and uninsulated structures such as outdoor sunshades and patio covers.

8.1.3. Where standing-seam metal roofing is not feasible or at “flat” roofs (slope < 2:12) traditional built up roofing (BUR) or modified bitumen roofing may be used over composite type combination perlite board and polyisocyanurate, polystyrene, or polyurethane insulation over the roof deck.

8.1.3.1. Traditional built up roofing is field fabricated with layers of bitumen, alternating with plies of reinforcing felts.

8.1.3.2. Two different polymers, styrene butadiene styrene (SBS), and atactic polypropylene (APP), are used to modify the membrane to impart greater elasticity and resistance to punctures, extreme temperatures, and wind uplift. SBS is typically installed with hot asphalt or cold adhesives; APP typically utilizes the torch method.

8.1.3.3. Fluid applied elastomeric roofing may be used on roofs having multiple penetrations or irregular shapes, or restricted use of hot asphalt or heat welding.

8.1.3.4. Application of asphaltic or modified bitumen roofing is generally “hot” or “cold.” “Hot” application is most typical for new construction; “cold” application is used when a building is required to be occupied during reroofing so as to minimize exposure of occupants to noxious vapors or where the presence of heat or open frame is restricted. Fluid applied roofs are typically applied “cold.”

8.1.4. At least 75% of the roof surface shall provide a Solar Reflectance Index (SRI) of at least 78 at “flat” roofs (slope < 2:12) for a “cool roof,” per Cool Roof Rating Council (CRRC) guidelines.

8.1.4.1. White marble aggregate on built up asphaltic (BUR) roofing or a white mineral granule cap sheet on modified bitumen roofing reduce heat loads and extend the useful life of the roofing membrane. Provide 400 lb. per square white marble chips for aggregate surfaced built-up roofing, 72 lb. per square for standard mineral granule cap sheet, or 78 lb per square for mineral granule cap sheet that is specifically designated for “cool roof” use. Exact weights of stone aggregrate may

Page 13: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 13

vary by manufacturer.

8.1.4.2. Where aggregate or mineral cap sheets do not provide an SRI of at least 78 an elastomeric acrylic latex roof coating, compatible with bituminous roof surfaces, shall be applied. Coating to be white in color and CRRC listed.

8.1.5. Provide asphalt impregnated roof protection boards for walkways. Provide space (gap) between boards to maintain roof drainage.

8.1.6. Composite shingles shall be nailed and not stapled.

8.1.7. Roof Slope:

8.1.7.1. Provide a minimum 4-inches per foot roof slope for standing-seam metal roofs.

8.1.7.2. Provide a minimum 1/2–inch per foot roof slope, including along valleys, to the low point (the roof drain or scupper) for “flat” roofs.

8.1.8. MCAGCC is a high wind area. Design all roofing systems to withstand uplifts resulting from winds in excess of 90 mph.

8.1.9. The required minimum R-value for roofing assemblies is R-30.

8.1.10. The required minimum R-value for wall assemblies in permanent inhabited structures is R-19, and R-15 for exterior walls in temporary trailer facilities.

8.2. MINERAL FIBER BLANKET INSULATION

8.2.1. Provide foil or Kraft paper faced blanket insulation.

8.3. STANDING-SEAM METAL ROOFING

8.3.1. Metal roofs require proper attic ventilation and roof deck insulation due to high summer temperatures.

8.3.2. Metal roofing shall be 22-gauge minimum.

8.3.3. See 14.1 for additional metal roofing requirements for pre-engineered buildings.

8.4. BUILT-UP ASPHALT ROOFING (AGGREGATE SURFACED)

8.4.1. Provide 4-ply built-up roofing for repair and replacement of existing aggregate surfaced built-up roofs.

8.5. BUILT-UP ASPHALT ROOFING (MINERAL SURFACED)

8.5.1. Provide 4-ply built-up roofing for repair and replacement of existing mineral surfaced built-up roofs.

8.5.2. Provide reflective mineral granule capsheets with white granules.

8.6. MODIFIED BITUMINOUS MEMBRANE ROOFING

8.6.1. Provide 4-ply modified bituminous roofing for repair of existing modified bitumen roofs.

8.6.2. Provide reflective mineral granule capsheets with white granules.

8.6.3. Do not provide modified bituminous membrane roofing for new roofs.

8.7. FLASHING AND SHEET METAL

8.7.1. Provide pre-finished flashing. Finish shall be UV resistant. Polyvinylidene

Page 14: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 14

fluoride or fluoropolymer type finishes are preferred.

8.8. ROOF ANCHOR POINTS

8.8.1. Fall Prevention: Provide fall protection systems for any work on an elevated surface over 4 feet from the ground in accordance with EM-385-1-1, Safety and Health Requirements Manual published by the US Army Corp of Engineers and the following requirements:

8.8.1.1. Provide anchor points independent of the support structure for platforms or other elevated work areas. If a platform were to fail, the anchor point shall remain intact in order to protect workers on the platform. When construction is complete, leave anchor points in place.

8.8.1.2. Anchor points shall be capable of supporting a 5,000-pound load per employee attached with a fall restraint system. This rated load is sufficient to stop a falling person and absorb the energy of the fall.

8.8.1.3. Locate and rig anchor points so that a worker will fall no more than 6 feet and will not contact the floor, a lower level or any other obstruction.

9. OPENINGS (DIVISION 8)

9.1. GENERAL

9.1.1. Contact the MCAGCC lock shop early in the design to ensure that the doors and hardware specified are correct.

9.1.2. At exterior doors and windows provide shade with deep overhangs and recesses of at least 24 inches.

9.2. STEEL DOORS AND FRAMES

9.2.1. Provide insulated doors at building exteriors. Insulation shall have a minimum “U” value of 0.48.

9.2.2. All steel doors shall be of seamless construction with flush top and vertical stiffeners as specified in Steel Door Institute publication SDI-100, “Recommended Specifications for Standard Steel Doors and Frames” (a.k.a. ANSI/SDI A250.8-2003 (R2008). All doors and frames shall have reinforced backing for closers, strikes, hinges locks and latches.

9.2.3. Provide heavy duty, level 3, doors in offices and administrative spaces.

9.2.4. Provide maximum duty, level 4, doors in barracks, toilets, locker rooms and bathrooms.

9.2.5. Provide a complete door schedule. The schedule shall assign a separate number for each opening and shall indicate door type and style, material, design, size, thickness, glazed or unglazed, class fire rating for fire doors, hardware set number, threshold material, if any, and material for frames, mullions, and transom bars.

9.3. WOOD DOORS

9.3.1. Use wood doors at interior only; never at exterior.

9.3.2. Provide solid core wood doors.

9.3.3. Provide plastic laminate finish or match the existing interior finish of wood door

Page 15: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 15

veneer or paint.

9.4. ALUMINUM WINDOWS

9.4.1. Provide Grade HC-40 windows only.

9.4.2. Horizontal sliding thermal windows are preferred.

9.4.3. All operable exterior windows require insect screens.

9.4.4. Provide aluminum windows with UV resistant organic coating or Class I anodized finish.

9.4.5. Provide reflective glazing for east and west exposures with the exception of pedestrian walkways and entries.

9.4.6. Provide north-facing clerestories and skylights for illuminating interior spaces.

9.4.7. Replace existing steel windows with aluminum framed horizontal sliding thermal windows. Lower fixed panels shall be replaced with an insulated spandrel glazing with matching aluminum trim.

9.5. PLASTIC WINDOWS

9.5.1. Window sash and frame color shall be integral to the PVC extrusion.

9.5.2. Provide Grade HC-40 windows only.

9.5.3. Horizontal sliding windows are preferred.

9.5.4. All operable exterior windows require insect screens.

9.5.5. Corners of PVC frames and sashes shall be welded. Reinforce frames and sash as necessary to meet HC-40 Requirements.

9.6. DOOR HARDWARE

9.6.1. Conform to ANSI/BHMA A156 for all hardware items. Furnish all doors with hinges, locksets, wall or floor bumper guards, kick plates and closers with hold open capability.

9.6.1.1. Provide mop plates on the push side of doors to toilet rooms, janitorial closets and locker rooms.

9.6.2. All door hardware shall be Grade 1, heavy duty and conform to the following base standard unless approved otherwise by the base locksmith:

9.6.2.1. Key System: Schlage, provide Everest D restricted D124 keyway cylinders with T124 restricted key blanks for all new projects; existing projects may use Classic keyways. Contact the base locksmith for keying on all projects.

9.6.2.2. Locksets: Provide mortise locksets, Schlage L9000P series 17L 626, for exterior applications. Provide cylindrical locksets, Schlage ND series Sparta 626, for interior applications.

Cylinders for mortise and bored locksets shall be six-pin tumblers with full size interchangeable cores which are removable by special control keys. Key locksets to the existing MCGACC master key system.

Page 16: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 16

9.6.2.2.a. The specifications shall clearly describe the process MCAGCC uses to ensure that the contractor installs the correct cores in the correct door locks.

9.6.2.2.a.1. The contractor installs temporary construction cores and submits floor plans with the hardware schedule to the Government.

9.6.2.2.a.2. The locksmith will provide a bitting chart that indicates all the keys required, including those for mechanical rooms, and the Contractor bases the order of permanent cores and keys on this chart.

9.6.2.2.a.3. The Contractor installs the permanent cores in accordance with the bitting chart. The Contractor shall schedule this operation at the end of construction since it effectively surrenders access control back to the Government.

9.6.2.2.a.4. The Contractor tests locks to ensure functionality and the MCAGCC locksmith will verify that the Contractor has installed locks and supplied keys in accordance with the bitting chart.

9.6.2.2.a.5. The Contractor turns keys over to the Government.

9.6.2.3. Padlocks: Provide Kryptonite by Schlage, KS43D2300 Series. Contact base locksmith for keying.

9.6.2.4. Exit Devices: Provide Von Duprin 99 (Medium or Wide Stiles Storefront) & 33 series (Narrow Stile Storefront). Use key-removable mullions and rim devices at pairs of doors. Use IC cylinders at panics. Use 626 finishes.

9.6.2.5. Mullions: Provide Von Duprin KR series based on the application.

9.6.2.6. Surface Closer: For exterior closers use LCN 4041 series x EDA arms everywhere. For interior closers, use LCN 1461 series.

9.6.2.7. Access Control: Provide Schlage AD 250 series and Schlage CO 200 series locks.

9.6.2.7.a. Provide main access doors to living units with electronic access control of mortise design. The electronic hardware shall be fully compatible with existing hardware. The existing electronic locking system is Ingersoll Rand Security Technology (Locknetics AD250).

9.6.2.7.b. Provide Schlage Management System, including computer and software, HHD and cables, blank cards and system training. Contact IR Integration for this requirement at 909-548-2634Note: the government will not use FSRM funds to purchase this equipment, but will likely use O & M funds.

9.6.2.8. Floor Closers: Do not use or specify floor closers. Remove existing floor closers and replace with continuous hinges.

9.6.2.9. Use auto-flush bolts.

9.6.2.10. Hinges: Use continuous hinges at exterior doors including storefronts. All interior door hinges shall be stainless steel, anti-friction bearing type.

9.6.2.11. Overhead Stops: Use only where floor or wall stops are inadvisable. When used, provide heavy weight hinges or continuous hinges.

9.6.2.12. Floor Stops: For interior applications use dome stops. For exterior applications use floor mounted bumpers.

Page 17: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 17

9.6.2.13. Door Plates: Provide kickplates, push and pull plates, and anti-vandal plates not only where customary, but also where the Government anticipates rough use.

9.6.2.14. Thresholds: Provide commercial grade mill aluminum saddle thresholds. Furnish disabled accessible ramp thresholds where required at existing conditions.

9.6.2.15. Weatherstripping: Provide all exterior doors with weatherstripping, and for doors exposed to weather provide head flashing and door sweeps or shoes.

9.6.2.16. Door Seals: Provide mill finish aluminum astragal/perimeter seals with silicone inserts. Avoid adhesive type seals.

9.6.2.17. Hollow Metal Doors and Frames:

9.6.2.17.a. Exterior: Provide 14 GA honeycomb core, galvanized, capped doors for full glass, “16 GA tubular, galvanized, capped on top. Provide fully welded galvanized 14 ga frames.

9.6.2.17.b. Interior: Provide 16 GA honeycomb core, with fully welded 16 GA frames. Use 16 GA honeycomb core. All doors and frames shall have closer reinforced with continues hinge (Roton) or high frequency hinge reinforcement.

9.6.3. MCAGCC uses IR Security & Safety Consultants for doors and door hardware. Contact MCAGCC’s security and safety consultant before completing the hardware specification (Section 08 71 00). They can review hardware designs and specifications, and write hardware specifications. There is no fee for their service. MCAGCC personnel are trained in the installation and maintenance of the above products and the maintenance department stocks materials for repair work. MCAGCC is not prepared to adopt additional standard materials as the hardware standard in place serves the campus well.

This requirement is in accordance with FAR 6.302-1, “Only one responsible source and no other supplies or services will satisfy agency requirements” as supplies may be deemed available only from the original source in the case of a follow-on contract for the continued development or production of a major system or highly specialized equipment, including major components thereof, when it is likely that award to any other source would result in substantial duplication of cost to the Government that is not expected to be recovered through competition.

9.7. GLAZING

9.7.1. Provide insulating, dual pane glazing on all exterior windows. Provide a maximum “U” value of 0.31 and a minimum shading coefficient of 0.56.

9.7.2. Glazing will be subject to extreme variations in temperature. Select tints, films and treatments accordingly. Use “low E” glazing.

9.7.3. Coordinate with the EIC on the use of safety glass, fragment retention films or plastic glazing on exterior windows to meet physical security or hardening requirements for facilities. MCAGCC only allows the use of fragment retention films on retrofitted windows.

10. FINISHES (DIVISION 9)

10.1. GENERAL

10.1.1. Coordinate with the EIC before selecting materials. Discuss the introduction of

Page 18: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 18

any new product or finish system thoroughly with the EIC.

10.1.2. All material and finishes in barracks shall be vandal-resistant.

10.2. METAL SUPPORT ASSEMBLIES

10.2.1. Provide galvanized studs only.

10.3. PLASTER AND STUCCO

10.3.1. Provide integral color stucco only.

10.3.2. Provide only galvanized expanded metal lath.

10.3.3. Provide a minimum stucco thickness of 3/4 inch.

10.4. GYPSUM WALLBOARD

10.4.1. Provide 5/8 inch gypsum wallboard throughout.

10.4.2. Provide impact resistant gypsum wallboard in barracks and corridors of administrative facilities.

10.4.3. Provide cementitious backer board for ceramic tile underlayment and exterior soffits.

10.5. CERAMIC TILE, QUARRY TILE AND PAVER TILE

10.5.1. Quarry tile and paver tile shall be “mud” set in new installations. Wall tile shall be “thin set” over cementitious backer board.

10.5.2. Use integral color grouts. Avoid white grouts in barracks and public areas.

10.6. PAINTING

10.6.1. Provide semi-gloss paint finishes in sleeping rooms, toilet rooms, locker rooms and showers.

10.6.2. Doors and doorframes shall be painted with acrylic enamel.

10.6.3. All paints and coatings shall be compliant with local VOC regulations and shall be water based.

10.6.4. Exterior paints will be subject to extreme variations in temperature and shall be UV resistant.

10.6.5. Do not paint over labels identifying fire rated doors and frames or builder plates on machinery, motors, etc.

11. SPECIALTIES (DIVISION 10)

11.1. TOILET PARTITIONS

11.1.1. Toilet partitions shall be either stainless steel or molded phenolic. Color shall be integral.

11.1.2. Toilet partition hardware shall be of stainless steel.

11.1.3. Toilet partitions shall be ceiling braced and urinal screens shall be wall hung.

11.2. IDENTIFICATION DEVICES

11.2.1. Facility number signs shall be 16 inches high by 36 inches wide with 12 inch

Page 19: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 19

block lettering, on sign blanks of white reflective metal. Refer to detail SKA-24.

11.2.2. Interior directional and room identification signage shall be plaques with a matte finish, fabricated of melamine plastic, 1/8 inch thick. Refer to detail SKA-26. Provide slots in base laminate for insertion of changeable message strips as shown in the detail. Provide ½ inch radius corners.

11.2.3. Provide separate signage in rooms containing fire alarm panels, fire sprinkler risers or fire inspectors system test controls that clearly indicate their location.

11.2.4. All doors leading to fire suppression equipment will be marked with permanent signage.

11.2.5. A permanent evacuation diagram is to be posted on each floor in accordance with NFPA 101 7.10.8.5 – show the location “you are here” with primary and alternate routes of escape.

11.2.6. Buildings that do not have civilian employees or visitors may not require Architectural Barriers Act Accessibility Standards (ABAAS) compliant signage. Verify the need for ABAAS compliant signage with the EIC

11.2.7. Hotels, motels, and barracks – provide durable manufactured evacuation signs on the back of each door in accordance with NFPA 101 chapter 28.7.4.1.

11.2.8. All assembly areas require permanent, mounted occupant load signs. The FPE’s code analysis and life safety plan will determine the occupant load.

11.2.9. Post room numbers at each entry doors and other doors at all buildings including barracks and public living quarters. Assign room numbering sequentially using a 100 series for the ground floor, 200 series for the 2nd floor and so on with a pattern of low to high beginning at the north and west ends of corridors, with odd numbers on the west and north and even numbers on the east and south.

11.2.10. For other guidelines on signs see the BEAP.

11.3. FIRE PROTECTION SPECIALTIES

11.3.1. Provide portable fire extinguishers in recessed or semi-recessed cabinets in new and existing facilities. Coordinate with the EIC if wall construction in existing facilities does not permit such installation.

11.3.2. Fire extinguishers shall be of the size and rating appropriate to the hazard.

11.3.3. Protect mess halls and commercial cooking facilities with Class “K” wet chemical type fire extinguishers.

11.3.4. For repair and renovation projects, replace all fire extinguishers which are older than one year.

11.3.5. For Bachelor Enlisted Quarters (BEQ’s) provide fire extinguishers only at the duty desk and laundry room.

11.3.6. Extinguishers:

11.3.6.1. Portable Fire Extinguishers – to be located, sized and rated in accordance with NFPA 10, ABC “Ansul Sentry” (R-102 Wet Chemical Fire Suppression System) and mounted in cabinets or on hooks as dictated by the UFC 3-600-01. In barracks only provide extinguishers in supervised locations and high hazard areas (laundry rooms,

Page 20: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 20

duty rooms, etc.).

11.3.6.2. Fire extinguishers shall be tested and certified new within 12 months, serviced within 1 month of project final acceptance.

11.3.6.3. Install extinguishers in semi-recessed cabinets to be with no break glass and no locking components on the door, hydrostatically tested within 12 months and serviced within 1 month of project final acceptance.

11.4. TOILET AND BATH ACCESSORIES

11.4.1. Toilet accessories shall be stainless steel and recess mounted.

11.4.2. Buildings that do not have civilian employees or visitors may not require ABAAS compliance. Verify the need for ABAAS compliant toilet and bath accessories with the EIC.

12. EQUIPMENT (DIVISION 11)

12.1. FOOD SERVICE EQUIPMENT

12.1.1. Provide hood suppression systems for grease laden commercial cooking areas in accordance with applicable NFPA Standards. See Appendix B - References for additional information.

12.2. OTHER EQUIPMENT

12.2.1. Knox Box Key Vaults are required to be installed near main building entrance and/or approach. Install per manufactures recommendation. Authorization forms available through A/C Hull at Fire Administration. Contact (760) 830-5400.

13. FURNISHINGS (DIVISION 12)

13.1. BLINDS, VENETIAN AND AUDIO VISUAL

13.1.1. Provide passive solar devices such as Venetian blinds.

13.1.2. Cloth blinds are preferred. Use blinds with metal slats only after consulting with the EIC.

14. SPECIAL CONSTRUCTION (DIVISION 13)

14.1. PRE-ENGINEERED METAL BUILDINGS

14.1.1. Pre-engineered building manufacturer to provide all required engineering, components, details, shop drawings, etc. Coordinate with EIC

14.1.2. All exposed metal shall have a factory applied, UV resistant finish.

14.1.3. Coordinate insulation requirements with the EIC.

14.1.4. Include openings (exterior doors, overhead doors, windows, louvers, etc.) in the pre-engineered building package.

14.1.5. Lean-to additions to buildings with sloped roofs shall have the same roof pitch as the existing roof.

14.1.6. New buildings shall have a gable form with 4:12 roof pitch.

14.1.7. New buildings shall have a minimum 8” x 8” concrete curb at the exterior wall.

14.1.8. Orient buildings on site so that the primary doors face away from prevailing

Page 21: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 21

winds.

14.2. Energy management and control systems (EMS)

14.2.1. Coordinate with the EIC if proposed work will affect any existing EMS. Coordinate the removal or reconfiguration of existing EMS components with the EIC.

14.2.2. Use United Facilities Guide Specifications (UFGS) section 23 09 23.13 20 BACnet Direct Digital Control System for HVAC.

15. CONVEYING EQUIPMENT (DIVISION 14)

15.1. ELEVATORS

15.1.1. Elevators will be designed and constructed in accordance with the UFC 3-600-01 – 30.3 and Table 6.6.

15.1.2. Lock elevators (where installed) for use only by qualified personnel.

15.1.3. Firefighter operation will be by base standard barrel key HW 1002.

16. FIRE SUPPRESSION (DIVISION 21)

16.1. FIRE SUPPRESSION

16.1.1. Provide Knox locking fire department connection plugs.

16.1.2. Supervise indicating valve, control valves and backflow preventers with lock and chain in lieu of tamper switches. Provide commercial “Master Lock” model 8 81KA (keyed alike), keyed 50k33.

16.1.3. Shotgun risers shall be provided eliminating the alarm check valve and retard chamber style.

16.2. WET PIPE FIRE SUPPRESSION SPRINKLERS

16.2.1. The NAVFAC SW standard guide specification for wet pipe fire suppression sprinklers is a Design-Build type specification. See UFGS 21 13 00.00 40 Fire Suppression Sprinkler Systems.

Indicate the following information on the fire protection drawings:

16.2.1.1. Location and detail of each sprinkler system supply riser, fire department inlet connection, pressure or flow switch, fire suppression system inspector test valve, backflow preventer, fire alarm bell, fused disconnect switch and associated electrical connections.

16.2.1.2. Starting point of each sprinkler system including its connection to water distribution system piping.

16.2.1.3. Location of sprinkler system control valves, post indicator valves or wall indicator valves.

16.2.1.4. Floor area of new sprinkler system coverage when existing sprinkler system is protecting portion of existing floor area.

16.2.1.5. Anchoring of piping, including pipe clamps with tie rods or mechanical retainer glands; and details of seismic anchorage.

16.2.1.6. Indicate existing sprinkler piping layout and sprinkler heads on project drawings only if the existing sprinkler system will be modified and such layout

Page 22: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 22

improves clarity.

16.2.1.7. Industrial buildings supplied by a fire sprinkler system with a fire department connection shall have a double check valve type backflow preventer. Installation of backflow preventers shall be in accordance with California Code of Regulations (C.C.R.) Title 17.

16.2.1.8. The use of anti-freeze in sprinkler systems is prohibited

16.2.2. The A-E is responsible for conducting fire flow testing. Coordinate testing with the EIC.

16.2.3. The NAVFAC SW Fire Protection Engineer and the MCAGCC Fire Department review and approve fire suppression system drawings and specifications. Their approval is required prior to purchase of materials. Coordinate the review with the project EIC.

16.3. FIRE PROTECTION SPECIALTIES

16.3.1. For Fire Extinguishers and Fire Extinguisher cabinets see 11.3 – Specialties above.

17. PLUMBING (DIVISION 22)

17.1. PLUMBING FIXTURES

17.1.1. Specify commercial grade for all plumbing fixtures in order to reduce overall maintenance requirements.

18. HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) (DIVISION 23)

18.1. BASIC MECHANICAL MATERIALS AND METHODS

18.1.1. Desert climate considerations:

18.1.1.1. Outdoor summer dry bulb temperature can be as high as 124° F. For cooling design load calculations, use 115° F DB outdoor temperature.

18.1.1.2. Other outdoor design temperature data:

18.1.1.2.a. Latitude = 34°-14'.

18.1.1.2.b. Longitude = 116°-03'.

18.1.1.2.c. Elevation = 1781 feet.

18.1.1.2.d. Winter design data heating dry bulb = 29° F for 97.5 % range.

18.1.1.2.e. Summer design data cooling wet bulb = 73° F for 1 % range.

18.1.1.3. Indoor design conditions:

18.1.1.3.a. Summer:

18.1.1.3.a.1. Dry Bulb = 72° F (+/- 3° F).

18.1.1.3.a.2. Wet Bulb = 50% RH (+/-10%).

18.1.1.3.b. Winter:

18.1.1.3.b.1. Dry Bulb = 78° F (+/- 3° F).

18.1.1.3.c. Note: In order to reduce energy consumption, the Energy Management office

Page 23: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 23

uses a basewide EMS Control System that further limits some of the conditioned spaces during summer time to 75° F DB and during winter time to 72° F DB (Per UFC 3-410-01FA and local temperature data).

18.1.1.4. Temperatures below freezing dictate the following requirements for equipment and piping systems exposed to outdoor weather:

18.1.1.4.a. When cooling towers or evaporative cooling units will operate during the cold season, provide water pans with freeze protection features such as electric or hot water heating of water within water pans.

18.1.1.4.b. When cooling towers or evaporative cooling units will not operate during the cold season, then the water pans shall be drained. Provide manual draining valves for water pans.

18.1.1.4.c. For make-up water piping located outdoors, provide a drain valve at the lowest point to allow for manual draining; except for automatic dripping when utilized for freeze protection.

18.1.1.4.d. Due to freezing conditions, insulate all outdoor active piping systems, including small sized make-up water piping for HVAC systems.

18.1.1.4.e. Provide heat-tracing cables around various piping systems.

18.1.1.4.f. Use any other methods of freeze-protection common to standard practice that elements of the design dictate such as non-freeze hose bibbs (nitrogen filled heads).

18.1.1.5. Very high temperatures and dry outdoor conditions dictate that:

18.1.1.5.a. Evaporative cooling equipment such as cooling towers, industrial fluid coolers and rotary evaporative coolers are effective.

18.1.1.5.b. Air-cooled condenser units including packaged or split A/C units above five tons nominal capacity should not be used if chilled water distribution piping is available near a project site. When chilled water distribution piping is not available near a project site, then use a water cooled cooling tower system.

18.1.1.5.c. Cooling towers and industrial fluid coolers shall be oversized to compensate for very hot days in excess of 120° F DB with high humidity.

18.1.1.6. Wind direction: See Wind Rose; sheet SKC-28.

18.1.1.7. Sand storm conditions:

18.1.1.7.a. Sand storms are frequent at Twentynine Palms.

18.1.1.7.b. Consider providing:

18.1.1.7.b.1. Filter banks at outside air (OSA) intakes when conditioned spaces contain computer or electronic equipment. OSA intake openings shall face away from the most common wind direction.

18.1.1.7.b.2. Sediment drain sumps equipped with a manual drain valve and a shut-off valve at the bottoms of cooling towers and industrial fluid coolers in order to facilitate the washing of sand from the bottom of water pans.

18.1.1.7.b.3. Dirt legs (sediment traps) for suction lines before (i.e. it may be

Page 24: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 24

somewhere before, but not necessarily right “in-front of” the pump) condenser water pump inlets for cooling towers and industrial fluid coolers.

18.1.1.7.b.4. Other standard industry practices as applicable.

18.1.1.8. High indoor relative humidity damages electronic and computer training equipment, so limit the use of a 100% OSA economizer cycle to times when outdoor relative humidity is low. Use humidity control features, especially when conditioned spaces will house electronic or computer equipment.

18.1.2. Maintenance, service and down-time considerations:

18.1.2.1. MCAGCC is a remote site. This limits access to HVAC equipment manufacturer’s representatives and the provision of on-call emergency maintenance services. Shipment of spare parts is difficult, expensive and requires planning effort.

18.1.2.2. Limit downtime of existing HVAC systems during renovation or alteration of occupied buildings.

Deliver all new equipment and material to the job site prior to any demolition work.

18.1.2.3. Provide water filtration and chemical treatment for make-up water systems. In addition to a “strainer” with a full port ball valve at the end of the strainer’s filter section for flushing, provide the following filtration systems, specified in applicable UFGS sections as appropriate and as approved by the EIC for the intended application:

18.1.2.3.a. Forced flow sand filtration with backwash feature for water cooled cooling towers; or

18.1.2.3.b. Centrifugal type sand separator for water cooled cooling towers.

18.1.2.3.c. Chemical pot feeder for closed loop water systems.

18.1.2.3.d. Chemical treatment system for open loop systems.

18.1.2.3.e. Other filtration systems such as filter banks.

18.1.2.4. Consider the following:

18.1.2.4.a. Accessibility and ease of maintenance considerations by designers:

18.1.2.4.a.1. Critical HVAC equipment and piping systems shall not be exposed to view.

18.1.2.4.a.2. Locate HVAC equipment on grade.

18.1.2.4.a.3. Provide a steel platform around roof-mounted equipment for equipment maintenance. Many existing roofs have a rather high pitch.

18.1.2.4.a.4. To prevent foot traffic from damaging roofing material, provide walking pads, 3/4” thick and usually of the same material as the roofing material, around rooftop equipment and in a continuous path to the point of access to the roof.

18.1.2.4.a.5. Eliminate direct sun exposure to HVAC equipment if possible. Maintenance personnel prefer to work under shaded structures.

18.1.2.4.b. Other Considerations:

18.1.2.4.b.1. Phasing, sequencing, scheduling and planning of construction activities.

18.1.2.4.b.2. Provision of temporary HVAC systems and utilities to enable use of

Page 25: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 25

occupied buildings during construction.

18.1.2.4.b.3. Proper location of new HVAC equipment and proper routing of new piping systems, to keep existing HVAC equipment and existing piping systems operational during construction.

18.1.2.4.c. Other Requirements:

18.1.2.4.c.1. Provide a minimum five year full manufacturer’s warranty for material and labor coverage at site, in addition to the standard one year Contractor’s installation warranty.

18.1.2.4.c.2. Addition of new stand-by or back-up mechanical systems such as dual equipment chillers, cooling towers, pumps, boilers, utility loops, isolation valves, etc., in case “lead” equipment requires repairs, maintenance or replacement.

18.1.3. Other special requirements:

18.1.3.1. Select high efficiency HVAC equipment and motors in accordance with UFC’s.

18.1.3.2. Consult with the EIC and building user to select design features associated with:

18.1.3.2.a. Shielding of sensitive electronic equipment from HVAC noise.

18.1.3.2.b. Designing for electronic signal interference protection.

18.1.3.2.c. Grounding of exterior metal surfaces of HVAC equipment due to the build-up of any electrostatic charge associated with the operation of radar or communication equipment.

18.1.4. Other special considerations:

18.1.4.1. Noise reduction, vibration control and seismic restraint.

18.1.4.2. Enhanced requirements for HVAC systems supplying class rooms, computer rooms and electronic training laboratories.

18.1.4.3. At MCAGCC some equipment and systems, installed under Energy Savings Performance Contracts (ESPC’s), yields annual energy savings. Prior to the start of any design, coordinate with the EIC to find out if equipment or systems from any ESPC will be affected. No ESPC’s equipment or systems shall be removed without written consent from the EIC and the ESPC Contractor.

18.2. MECHANICAL INSULATION

18.2.1. Outdoor above grade piping insulation systems shall be of calcium silicate with a stainless steel jacket, especially on the supply and return for both high temperature hot water (HTHW) and chilled water.

18.2.2. Evaporative cooling duct work systems:

18.2.2.1. There shall be no duct insulation lining inside ductwork systems due to the risk of mold or bacteria growth inside wet or humid ducts.

18.2.2.2. Install insulation at the exterior surfaces of supply, return and relief ducts.

18.2.3. All duct insulation systems installed at the exterior surfaces of duct work, exposed to weather, shall have metal jackets in order to withstand wind, rain, and UV

Page 26: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 26

light.

18.3. HIGH TEMPERATURE HOT WATER (HTHW) PIPING SYSTEMS

18.3.1. Generation of HTHW is from two sources:

18.3.1.1. At Mainside from building 1577, the CHP and the adjacent and interconnected building 1579 co-generation (Co Gen) Plant.

18.3.1.2. At North Mainside, from a co-gen plant (Project P-126).

18.3.2. The Central Heating Plant (CHP), building 1577, generates and distributes high temperature hot water to Mainside zones I, II and III.

18.3.2.1. Contact the EIC for any work related to generation of HTHW within the CHP.

18.3.2.2. The CHP distributes HTHW to various buildings, as described below, at 350° F temperature and 300 psi pressure. Contact the EIC for verification of HTHW operating temperatures and pressures at specific locations.

18.3.2.3. Any new branch take-off requirement that will tie into the existing HTHW lines shall, if feasible, use a “hot tap” to lessen the non-availability of supply to affected systems.

18.3.3. In addition to the CHP and its three zones, co-generation plants supply HTHW to Mainside zones IV and V. Each zone has a main supply and return loop. Within each zone there are branch loops interconnected to the main loop. HTHW supply and return branch loop piping connects each building.

18.3.3.1. At Mainside, the entire main loop, branch loop, and building supply and return piping systems for all of the three zones flowing from Building 1577 act as a “PRIMARY LOOP” distribution system.

18.3.3.2. Zones IV and V will each has independent pumps and each acts as a “Primary Loop”.

18.3.4. Refer to the latest available utility map for a description of zones, routes and piping sizes located underground, above ground and within concrete tunnels.

18.3.5. For each building, the HTHW system may be the primary source for:

18.3.5.1. Space heating.

18.3.5.2. Domestic hot water heating.

18.3.5.3. Steam production for mess halls.

18.3.5.4. Chilled water production via HTHW absorption chillers. Note: the provision, installation or design of new absorption chillers shall be pre-approved by the EIC for coordination with other works under planning or construction.

18.3.6. Provide HTHW heating systems, whenever feasible since it is the most economical option for heating in new facilities.

18.3.7. These processes increase the demand for HTHW:

18.3.7.1. The generation of domestic hot water for BEQ’s where showers and lavatory usage by personnel occurs early in the morning (4:30 AM to 8:00 AM) and in the evening (5:30 PM to 10:00 PM).

Page 27: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 27

18.3.7.2. The cooling of buildings via absorption chillers for about eight months per year occurs during daytime.

18.3.7.3. The heating of buildings directly, using HTHW heating coils within air-handling units or HTHW space heating heat exchangers, for about four months per year occurs 24 hours per day.

18.3.8. HTHW absorption chillers are best for generating chilled water for the cooling of buildings. This provides “free” cooling for 8 months per year.

18.3.9. Tying into the HTHW system requires improvements to the existing HTHW piping distribution systems. Designers shall follow these past practices to improve the existing distribution system in order to optimize HTHW performance:

18.3.9.1. Provide balancing valves and metering stations in support of those throughout the existing HTHW distribution piping system.

18.3.9.2. Replace three-way modulating control valves with two-way modulating control valves. Installing two-way modulating control valves enables the following operational benefits:

18.3.9.2.a. A decrease of HTHW return temperature back to the CHP (Note: the original design temperature differential at building 1577 between HTHW supply and return was 150° F).

18.3.9.2.b. The availability of a higher differential temperature at air-handling units. HTHW heating coils, throughout the system.

18.3.9.2.c. Higher efficiency of central boilers at the CHP.

18.3.9.2.d. The capability of converting old constant volume type pumps inside building 1577 to variable volume type pumps.

18.3.10. Specifications for HTHW Equipment and Materials:

18.3.10.1. For HTHW heat exchangers:

18.3.10.1.a. Design for an operating pressure of 300 psi and a temperature of 350° F.

18.3.10.1.b. Factory test heat exchangers hydraulically to 600 psi.

18.3.10.1.c. Use welded steel support brackets or flanges; Class 300 steel primary water flanges.

18.3.10.1.d. Use stainless steel or seamless, stress relieved, cupro-nickel (90-10) U – tubes; steel head and flanged opening for easy tube bundle removal; and tube sheets and baffles of the same material as tubes or else steel.

18.3.10.1.e. For various components use 600 psi design pressure, including but not limited to: relief valve, thermal measuring element (sensor), pressure gage, vent, temperature gauge and drain valve.

18.3.10.1.f. Arrange heat exchanger piping so that the primary heating medium connects to the U – tube side with offset flanges and secondary water connects to the shell side.

18.3.10.1.g. Design of heat exchanger by manufacturer shall be in accordance with ASME BPVC Section VIII.

Page 28: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 28

18.3.10.2. For air-handling HTHW heating coils:

18.3.10.2.a. Construct factory fabricated heating coils for HTHW applications.

18.3.10.2.b. Design the coil units, including coil, casing and header, to have the following:

18.3.10.2.b.1. An operating pressure of 300 psi water pressure at 350° F operating temperature. Testing pressure shall be at minimum (not less than) 400 psi water pressure complying with ARI-401.

18.3.10.2.b.2. Tubes of seamless no. 20 BWG cupro-nickel (90-10).

18.3.10.2.b.3. Copper fins mechanically bounded to tubes.

18.3.10.2.b.4. Removable coils sealed to casing to prevent leakage of air around coils.

18.3.10.2.b.5. Return and supply headers constructed of welded steel.

18.3.10.2.b.6. Rolled tubes, bushed, brazed or welded into headers.

18.3.10.2.b.7. Multiple tube supports to prevent sagging.

18.3.10.3. The “CLASS” rating for various piping components and accessories shall withstand HTHW operating pressure and operating temperature.

18.3.11. Provide HTHW shut-off valves and balancing valves. Shut-off valves shall be steel body gate valves at HTHW supply and return lines. Flow balancing valves shall be steel body globe valves at the return line. Coordinate the exact locations at the main and branch to each building with the EIC.

18.3.12. For HTHW and steam piping gaskets:

18.3.12.1. Specify that the Contractor shall submit manufacturer’s published temperature and pressure ratings for approval by the Contracting Officer; that the gaskets shall be metallic winding materials, 304 stainless steel, Class 300, or approved equal; and that the dimensions of gaskets shall be per ASME 16.20 for ASME 16.5 flanges.

18.3.12.2. Provide semi-metallic spiral wound type gaskets for all steam, mid and high temperature flanged type valves, flanged connections, and at heat exchangers.

18.4. NATURAL GAS AND LIQUID PETROLEUM PIPING SYSTEMS

18.4.1. Propane usage:

18.4.1.1. Some sites use propane storage tanks when natural gas is not available, such as at Camp Wilson and the EAF. Contact the Engineering Branch to learn if natural gas is available at a specific site.

18.4.2. Natural Gas usage:

18.4.2.1. Refer to utility maps for existing natural gas distribution piping system information.

18.4.2.2. One primary gas reducing station reduces natural gas pressure from 400 psi to approximately 45 psi.

18.4.2.3. Several secondary gas reducing stations reduce natural gas pressure from 45 psi to 20 psi to feed various buildings.

Page 29: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 29

18.4.2.4. Individual gas regulators further reduce natural gas pressure from 20 psi in underground lines to feed buildings.

18.4.2.4.a. Each building shall have a natural gas meter.

18.4.3. Due to volatile utility rates, designs shall incorporate natural gas for cooling purposes whenever practical. Consider:

18.4.3.1. Natural gas engine driven chillers to generate chilled water, or

18.4.3.2. Direct-fired absorption chillers to generate chilled water.

18.4.3.3. When using natural gas to provide cooling, also practice waste heat recovery (co-generation) to increase the efficiency of the gas burning equipment.

18.5. CENTRAL REFRIGERATION EQUIPMENT FOR AIR-CONDITIONING

18.5.1. At Mainside:

18.5.1.1. There are several central chilled water plants and a number of underground chilled water loops interconnecting some buildings.

18.5.1.2. There is no additional capacity available on these existing chiller plant systems.

18.5.1.2.a. Any connection to existing chilled water distribution loops requires EIC approval.

18.5.1.3. Coordinate the construction of new chiller rooms with the Master Plan for the construction of additional chiller plants. Such construction requires EIC approval.

18.5.1.4. Given the above conditions, for new construction, designers must incorporate the following features:

18.5.1.4.a. Use a chilled water system design concept for cooling purposes, when combined cooling loads are above fifteen tons.

18.5.1.4.b. For combined cooling loads below fifteen tons and above five tons:

18.5.1.4.b.1. If chilled water is available at the project site, use air-handling units with chilled water coils. Avoid using self-contained compressor packaged units or split system air conditioning units.

18.5.1.4.b.2. The air-handling unit concept: When chilled water is not available at a site, then in addition to a DX cooling coil, equip the air-handling unit with additional inactive chilled water-cooling coils for future connection to the chilled water piping.

18.5.1.4.b.3. After chilled water becomes available, connect the inactive chilled water-cooling coils to the site chilled water distribution system and leave the DX coil as a stand-by cooling source.

18.5.2. Use water cooled (i.e., cooling tower type) chillers for hot desert weather conditions. Air-Cooled package chillers are not allowed.

18.5.3. A design shall construct the optimum chiller plant at sites where existing chilled water distribution is not available:

At a minimum, the optimum new chiller plant construction will account for the following criteria:

Page 30: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 30

18.5.3.1. Volatile utility rates of both electricity and natural gas.

18.5.3.2. Availability at a given site of sufficient HTHW flow between the hours of 9:00 AM and 5:00 PM.

18.5.3.3. Back-up and lead - lag equipment.

18.5.3.4. Reduction of peak cooling loads, and

18.5.3.5. The flexibility to generate chilled water at a single plant and use it to cool multiple buildings.

18.5.4. Chilled water expansion tanks:

18.5.4.1. Existing fan-coils and an air-handling unit’s chilled water cooling coils and chilled water piping systems may have the following types of air relief vent valves:

18.5.4.1.a. Manual, with or without isolation valves.

18.5.4.1.b. Automatic, with or without isolation valves.

18.5.4.1.c. No air relief vent valves.

18.5.4.1.d. Any combination of the above.

18.5.4.2. Select the appropriate type of chilled water expansion tanks and install them at the proper height to prevent damage to the chilled water piping systems.

18.5.5. Water treatment for cooling towers and industrial fluid coolers:

18.5.5.1. Provide one of the following treatment methods for open water loop systems:

18.5.5.1.a. A complete chemical treatment system.

18.5.5.1.b. Automatic flushing of the pan with a time clock or

18.5.5.1.c. A combination of treatment methods mentioned above.

18.6. EVAPORATIVE COOLING SYSTEMS

18.6.1. Rotary evaporative cooler units are preferred in warehouse areas. Use 4 to 5 CFM per square foot for evaporative cooling air circulation. For heating and ventilation modes the rotary evaporative cooler’s fan motor shall be two-speed. Refer to Detail SKM-01 for sample equipment schedules of rotary evaporative coolers. Note the following:

18.6.1.1. When providing evaporative cooling alone; do not use swamp cooler type units with pads at three sides, sump and re-circulating pump. Their fans have low static pressure and their pads require excessive maintenance. Use rotary evaporative coolers instead.

18.6.1.2. Use 2-stage coolers for air circulation volumes above 15,000 CFM. The 2-stage coolers shall consist of rotary cooler wheels for the evaporative cooling stage and a combination of a water-cooled cooling tower and copper tube or copper fin coil for the sensible cooling stage, a remote circulating pump, copper circulating piping, etc.

18.6.2. Rotor cooler wheel from factory:

18.6.2.1. See installation detail SKM-02 for:

Page 31: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 31

18.6.2.1.a. Back flow or cross flow prevention between make-up water and the water reservoir.

18.6.2.1.b. Type of drain timer to facilitate maximum water conservation features, and

18.6.2.1.c. Accessibility to drain timer and drain valve.

18.6.2.2. Construct the water reservoir (drum) of stainless steel.

18.6.3. Details SKM-03, -04, -05, -08, -09, and -10 provide sample installation, control and sequence of operation.

18.6.4. Consider swamp coolers or media coolers when the required CFM is below 2,000, or if the EIC approves beforehand.

18.7. UNITARY AIR CONDITIONING EQUIPMENT

18.7.1. As a consequence of temperatures in excess of 115° F and dry outdoor conditions: Air-cooled condenser units, including packaged or split air conditioning units above five tons nominal capacity, are not permitted. Energy consumption of air-cooled condenser units is about 25% to 30% higher than water cooled type chiller units. Use chilled water systems when existing chilled water distribution piping is available adjacent to the project location.

18.8. SPACE TEMPERATURE CONTROL SYSTEMS

18.8.1. Specify two-way modulating HTHW control valves as follows:

18.8.1.1. Industrial type valves for HTHW service of minimum 350° F. Valve bodies shall conform to ASME/ANSI B16.34 of minimum Class 300. Industrial valve and industrial pneumatic actuator combination to be normally closed type. Valve bodies shall be carbon steel or stainless steel, globe type with flanged or threaded ends. Internal valve trim to be Type 316 or 304 stainless steel.

18.8.1.2. Heating, mid-temperature, hi-temperature and steam valves shall be spring fail closed upon loss of power or loss of control signal. Steam, mid- and hi-temperature systems shall incorporate a mechanical fail safe shut down preventing the systems from exceeding 20° F above set point.

18.8.2. Note that:

18.8.2.1. Non-industrial type control valves, such as standard HVAC, hydronic, or commercial application type, are not acceptable for HTHW applications.

18.8.2.2. Industrial type control valves and industrial pneumatic actuators, by Honeywell, Fisher, Baumann or a pre-approved equal of Class 300 minimum to withstand pressure and temperature, are acceptable.

18.8.2.3. Due to temperatures in excess of 350° F, conduction of heat from a valve’s stem to its actuator occurs. Since heat damages electronic and electrical components, the use of electronic or electric type actuators is not acceptable.

18.8.2.4. Experience demonstrates that pneumatic actuators work well with HTHW control valves.

18.8.2.5. Selection of the valve flow coefficient (Cv) is very important to achieve finite control at low GPM.

Page 32: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 32

18.8.2.6. SKM-06 and SKM-07 are sample details for HTHW heating coil piping. SKM-06, with two control valves, shows the “Split Range Concept” or the “1/3 and 2/3 Flow Concept”, which enables finite control at very low GPM demand while satisfying the maximum high GPM demand.

19. INTEGRATED AUTOMATION (DIVISION 25)

19.1. DIRECT DIGITAL CONTROL SYSTEMS

19.1.1. MCAGCC uses a collection of networked Direct Digital Control (DDC) systems deployed at multiple buildings throughout the base. This Public Works EMCS wireless network (PWN) is comprised of multiple wireless network devices mounted on building rooftops performing network connectivity functions operating in the 5 Ghz frequency, operator workstations, and extended application and data servers (ADXs). Channel assignments used by the various devices at different locations use non-overlapping, non-conflicting public frequencies and shall not interfere with any devices currently used at MCAGCC. The PWN system utilizes controllers manufactured by Johnson Controls, Incorporated (JCI) and all new equipment shall provide communication interfaces with full connectivity to the existing PWN ADX servers. Consult with the EIC for current information whenever a project will add to or affect the PWN in any way.

19.1.2. Requirements for new construction: direct digital control (DDC) systems require the following:

19.1.2.1. An outside air (OSA) temperature sensor to facilitate an automatic changeover from heating to cooling—cooling above 65° F OSA temperature and heating below 65° F OSA temperature. Install OSA temperature sensors on a building’s north façade or elevation

19.1.2.2. Supply and return air temperature control.

19.1.2.3. Heat or cool indicators.

19.1.2.4. Compressor, fan or valve indicators.

19.1.2.5. Controls to limit temperature and fan speed.

19.1.2.6. Two-hour timer bypass feature for buildings of large area.

19.1.2.7. An “ON” feature for air circulation purposes for units controlling more than one room with a single fan.

19.1.2.8. Fan cycle operation for units controlling only one room.

19.1.2.9. Remote operation of main units, capable of being monitored by or from the existing Johnson Controls system, and

19.1.2.10. Backup capability of programming.

19.1.3. Requirements for remodel, retrofit, replacement, or renovation type projects:

19.1.3.1. Consult with the EIC about existing control systems that need to be upgraded.

19.1.3.2. If upgrading is needed, then the requirements are the same as for new construction.

19.1.4. Other special considerations:

Page 33: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 33

19.1.4.1. New DDC building profiles shall be loaded by the contractor at existing PWD main monitoring facilities under the supervision of designated PWD personnel.

19.1.4.2. All systems shall have valid DIACAP accreditations.

19.1.5. Provide utility metering for all mechanical utilities: natural gas, cold water, chilled water, HTHW, etc.

19.2. SMOKE DETECTORS

19.2.1. When duct smoke detection is required, upon detecting smoke, duct detectors shall cause the HVAC system to shut down and transmit a supervisory signal to fire dispatch.

19.3. MISCELLANEOUS REQUIREMENTS

19.3.1. Provide a shutoff valve near each utility main on HTHW & chilled water supply and return lines.

19.3.2. Provide pressure and temperature gauges on HTHW and chilled water supply and return lines as they enter a building or immediately prior to the main equipment.

19.3.3. Provide shutoff valves on both sides of all equipment. Provide pressure and temperature gauges on both sides of any pump.

19.3.4. Do not distribute HTHW through or over buildings. Locate HTHW exchangers at ground level. Hot water distribution to each building shall be at low temperature and pressure.

19.3.5. Label utility lines with the year of installation.

20. ELECTRICAL (DIVISION 26)

20.1. BASIC ELECTRICAL MATERIALS AND METHODS

20.1.1. Electrical Power Distribution System Design

20.1.1.1. Comply with all federal, state, and local codes, standards, regulations and ordinances, including the latest revision or edition of the National Electrical Code and all applicable codes and standards listed in Appendix B – References.

20.1.1.2. Emergency power is required at all facilities considered ‘critical’, as determined the base. Additionally, emergency power systems shall be a part of the design of the electrical system for egress lighting, fire alarm, security, public address and telephone systems.

20.1.1.3. Design the electrical system to isolate faults with minimum disturbance to the system and with features that give the maximum dependability consistent with specific project requirements.

20.1.1.4. Locate new underground electrical distribution system lines, hardware and substructures such as transformer pads, manholes, pullboxes, vehicular barriers, etc., in accessible areas for maintenance purposes and outside of any areas intended for future construction. Protect substructures, such as transformers, transformer pads, manholes, and service entrance panels, with vehicular barriers such as bollards. Design primary conduit systems with 100% reserve capacity. For example, if the design requires one 4-inch conduit to meet the requirements of the facility, then provide two 4-inch conduits.

Page 34: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 34

20.1.1.5. Electrical manhole size at MCAGCC shall be 7’D x 8’W x 8’L for systems rated up to 15 kV.

20.1.1.6. The electrical distribution system shall be as simple as possible to meet system requirements, as simplicity of the operation is very important to the safe and reliable operation and maintenance of the electrical system.

20.1.1.7. Include preventative maintenance requirements in the electrical distribution system design. Accessibility and availability for inspection and repair with safety are important considerations in selecting equipment. Provide space for inspection and adjustment. Provide space for performing repairs that is clean, well-lighted, and temperature-controlled. Provide working spaces and access doors in front of all electrical equipment as required by the National Electrical Code.

20.1.1.8. Consider flexibility of the electrical distribution system during the design phase to provide expansion as well as flexibility to meet requirements such as service voltage, equipment ratings, space for future additional equipment, and capacity for increased load.

20.1.1.9. Provide a dedicated neutral at all branch circuits serving computer equipment.

20.1.1.10. Provide panelboard neutral bus bars for all non-linear loads rated at 200% of the phase bus current rating.

20.1.1.11. Include at all switchboards, motor control centers and panelboards, one main circuit protective device per panel. Provide copper bussing. Direct feed through panels are not acceptable.

20.1.1.12. Install conductors in metallic conduit above ground and in Schedule 40 PVC underground. Comply with the following additional requirements:

20.1.1.12.a. Use rigid steel conduit at all exposed locations and where conduit may be subjected to damage.

20.1.1.12.b. Use EMT only indoors and where concealed.

20.1.1.12.c. Flexible metal conduit is acceptable for recessed and semi-recessed lighting fixtures if limited to 6 feet in length. Use liquid-tight flexible steel conduit for final connections to motors.

20.1.1.13. Make 600-volt wire circuit splices and connections of unshielded cable in underground pullboxes using a waterproof type, U.L.-approved, pressure connector. Do not use wire nut connectors.

20.1.2. Electrical Power Distribution System Design

20.1.2.1. Identify all loads such as lighting, HVAC equipment, kitchen equipment, shop equipment, computer equipment, and general receptacle loads, in kVA.

20.1.2.2. Select locations for service and distribution equipment, transformers, switchboards, panelboards, and motor control centers. The selection may be done with the approval of an electrical engineer from PWD’s Engineering Branch for the main electrical service and by coordination with the EIC for the electrical equipment rooms or spaces.

20.1.2.3. Include a complete single-line diagram as part of the design that presents sufficient data to build the electrical power system. Indicate the following items on

Page 35: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 35

the single-line diagram:

20.1.2.3.a. Power sources including voltages and available circuit currents.

20.1.2.3.b. Size, type, number of conductors, raceway size, length and voltage drop of all feeders.

20.1.2.3.c. Size of feeder loads in kVA.

20.1.2.3.d. Capacities, voltages, connections, impedances, and grounding methods of all transformers.

20.1.2.3.e. Type and size of protective devices.

20.1.2.3.f. Instruments, transformers, and meters.

20.1.2.3.g. Identification of all loads.

20.1.2.4. Include short circuit calculations available at all system components and indicate them on the single-line diagram.

20.1.2.5. Consider future system expansion during design. Accommodate subsequent increases in load by adding capacity to the initial system rather than by redesigning the electrical system. Do not design a system in a manner that would make it difficult or impossible to expand its capacity.

20.1.2.5.a. Consider future expansion of the electrical system when allocating space for the electrical equipment. Assume that additional electrical equipment will be added at some time in the future.

20.1.2.5.b. Do not locate switchgear, switchboards or panelboards outside of building structures, however substation equipment can be outside with proper switchgear enclosure rating. Locate a dedicated electrical room within each building and size it to provide sufficient space for proper maintenance of electrical equipment in accordance with the latest edition of NEC, NFPA-70. If electrical equipment is located in an existing combination electrical-mechanical equipment room, reserve adequate space for existing, new and future electrical equipment.

20.1.3. System Grounding Design

20.1.3.1. Effectively ground all metallic objects at the site that enclose electrical conductors or that are likely to be energized by electrical currents.

20.1.3.2. Design a continuous electrically conductive system so that all metal equipment parts such as enclosures, raceways, equipment, grounding conductors and all earth grounding electrodes are solidly joined together.

20.1.3.3. Solidly interconnect all metallic objects and equipment to the electrical system as provided by the service entrance and for each grounded separately derived system that is installed.

20.1.4. Wiring System Design

20.1.4.1. Before selecting conductors for wiring systems consider the following:

20.1.4.1.a. The ampacity tables in the National Electrical Code for low and medium voltage cables. Ampacity tables show the minimum conductor size required based on the temperature rating of the conductor. The Designer shall consider future load

Page 36: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 36

growth, voltage drop, short circuit heating, number of conductors within the raceway and ambient conditions.

20.1.4.1.a.1. For indoor installations and within air-conditioned spaces, the ampacity

tables for low voltage conductors in the National Electrical Code based on 30 C. ambient temperature may be used without temperature derating of the conductor. In

areas such as equipment rooms where the ambient temperature will exceed 30 C., derating of the conductors shall be calculated to the most extreme possible ambient temperature condition.

20.1.4.1.a.2. For outdoor installations and for low voltage conductors installed within metallic raceway in the shade, the ampacity tables in the National Electrical Code

shall be used with a derating factor for an ambient temperature of 45 C. Similarly, for conductors within metallic raceway installed in the sun, use a derating factor for

an ambient temperature of 50 C. Assume that the maximum load occurs during the time when the ambient temperature will be as noted above.

20.1.4.1.a.3. For underground installations, the ambient, temperature used for

conductors within a raceway is to be 30 C. This means the appropriate ampacity from the tables in the California Electrical code shall be derated to this temperature. The thermal characteristics of the medium surrounding the conductors are important to determine the current carrying capacity of the conductors. Factors affecting the current carrying capacity of the conductor include:

20.1.4.1.a.3.i. The type of soil in which the duct bank is buried and its thermal resistivity. Consider this when sizing conductors.

20.1.4.1.a.3.ii. The moisture content of the soil. The designer shall derate conductors in dry soil to compensate for the increase in thermal resistance due to the lack of moisture.

20.1.4.1.a.3.iii. The type and number of raceways and the number of conductors per raceway within an overall concrete duct bank.

20.1.4.1.b. The maximum voltage drop in each 600-volt rated power feeder shall be no more than 2% and the total voltage drop including feeders and branch circuits shall be no more than 5% overall.

20.1.4.2. Use metallic conduit for conductors installed above ground and schedule 40 PVC underground. Designs shall comply with the following additional requirements:

20.1.4.2.a. Use rigid steel conduit in all exposed locations and where conduit may be damaged.

20.1.4.2.b. Only use EMT indoors and where concealed.

20.1.4.2.c. Do not use flexible steel conduit for computer networking systems.

20.1.4.2.d. Use liquid-tight flexible steel conduit for final connections to motors.

20.1.4.2.e. Encase all underground conduits for medium voltage (5 kV – 35 kV) feeders in concrete (refer to SKE-8).

20.1.5. Lighting System Design

Page 37: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 37

20.1.5.1. Interior lighting system designs shall:

20.1.5.1.a. Provide illumination without discomfort caused by glare.

20.1.5.1.b. Minimize ceiling reflections in task details.

20.1.5.1.c. Use light sources with high color rendering index (CRI) that enhance the appearance of objects and a person’s ability to recognize people and spaces.

20.1.5.1.d. Consider reflectance of room surfaces, finishes on walls, floors, and ceilings.

20.1.5.1.e. Consider illumination quantity in foot-candles for each task and space.

20.1.5.1.f. Select light for each space and task.

20.1.5.1.g. Maintain a uniform light distribution in all spaces.

20.1.5.1.h. Select energy efficient light sources.

20.1.5.1.i. Minimize light pollution from exterior lighting for new construction and major renovation, (refer to Night Sky Ordinance reference in Appendix B)

20.1.5.1.j. Provide combination motion/photo sensors to control lighting.

20.1.5.1.k. Consider maintainability of lighting systems, susceptibility of dust collection, ease of cleaning, ease of re-lamping, durability, and exposure to vandalism.

20.1.5.1.l. Use low wattage ballasts for optimal efficiency.

20.1.5.1.m. Include motion sensors in interior rooms and offices.

20.1.5.2. Outdoor lighting system designs shall:

20.1.5.2.a. Light parking areas and building perimeters sufficiently to provide for the safety of people and the security of property. Provide an adequate amount of properly distributed light to reveal such hazards as curbs and steps and to illuminate dark and potentially dangerous areas. Luminaries installed in these areas shall minimize glare.

20.1.5.2.b. Provide LED-type exterior light fixtures above 8’ mounting height, and LED or CFL-type fixtures over doors. Use combination photocell/motion sensors to control exterior security and safety lights.

20.1.5.2.c. For additional information, see City of Twentynine Palms Development Code, Chapter 19.70 Lighting Standards (Night Sky Ordinance), at web link provided in Appendix B - References. All fixtures shall comply with Night Sky Ordinance guidelines

20.1.5.3. Lighting panelboards are to be 208Y/120 volt, 3 phase, 4 wire, or 480Y/277 volt, 3-phase, 4 wire, as required, with thermal-magnetic branch circuit breakers. Provide approximately 30% spare capacity in all panels.

20.1.5.4. Electrical Power Distribution System Design

20.1.5.4.a. Design electrical power distribution systems in accordance with sound practices, comply with all Federal, State, and local codes, standards, regulations, ordinances, including the latest revision or edition of the National Electrical Code and all applicable codes and standards listed in Appendix B - References.

20.1.5.4.b. Design main and distribution switchboards and motor control centers with

Page 38: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 38

30% to 40% spare capacity above the connected load.

20.1.5.4.c. Design panelboards with 30% spare capacity above the connected load.

20.1.5.4.d. All switchboards, motor control centers, and panelboards shall have a main circuit protective device and copper bussing.

20.1.5.4.e. Provide a fused disconnect switch at all HVAC units including heat pumps, condensing units, chillers, package units, etc. If HVAC equipment is furnished with an internal circuit breaker or fused switch, a separate fused disconnect switch is not required.

20.1.5.4.f. Provide a combination fused switch-starter for all pump motors, cooling towers, and fan motors. Such a starter shall have a control circuit transformer with 120-volt secondary, hand-off-auto selector switch and on-off indicating lights. In motor control centers and panel boards use bolt-on type circuit breakers only (no plug-ins).

20.1.5.4.g. Provide control wiring and interlocking for operation of motor loads as required by each motor circuit. Electrical contractor to coordinate HVAC control wiring with the mechanical contractor. Provide conduit for HVAC control wiring in accordance with UFGS Division 23.

20.1.5.4.h. Provide separate branch circuits for duplex receptacles. Connect a maximum of 4 general purposes duplex receptacles to a single 120-volt, 20-ampere circuit.

20.2. THREE-PHASE PAD-MOUNTED TRANSFORMERS

20.2.1. Primary and secondary windings shall be copper.

20.2.2. Design all transformers for loop-feed applications.

20.2.3. Use only dead-front type transformers. (See SKE-34 and 35.)

20.2.4. Separate high and low-voltage compartments by steel isolating barriers extending the full height and depth of the compartments.

20.2.5. Provide load break loop feed sectionalizer switch with three, two-position, oil-immersed type switches to permit closed transition loop feed and sectionalizing. Provide bayonet type, oil-immersed expulsion switches in series with oil-immersed, partial-range, current-limiting fuses.

20.2.6. Bases and cabinets of transformers shall be corrosion resistant and shall be fabricated of Type 304 or 304L stainless steel, no less than #18 U.S. gauge, conforming to ASTM A167.

20.2.7. Provide fault indicators on the outgoing primary leads of the loop feed transformer and test points on the load break elbows at the end of radial lightning arrestors on outgoing bushings.

20.2.8. Provide Energy Management Control System (EMCS) – compatible kWh demand meter and communications

20.2.9. Consult EIC for MCAGCC Three Phase Pad-Mount Transformer specification

Page 39: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 39

20.3. SINGLE-PHASE PAD-MOUNTED TRANSFORMERS

20.3.1. Primary and secondary windings shall be copper.

20.3.2. Design all transformers for loop-feed applications.

20.3.3. Use only dead-front type transformers (See SKE-36 and 37).

20.3.4. The transformer housing shall have a combination high and low-voltage compartment of the clamshell type with provision for pad-locking.

20.3.5. Provide fault indicators on the outgoing primary leads of the loop fed transformer lightning arrestors on outgoing bushings.

20.3.6. Fabricate the fault sill, hood and tank base of single compartment transformers of Type 304 or 304L stainless steel, no less than #13 U.S. gauge, conforming to ASTM A167.

20.3.7. Provide Energy Management Control System (EMCS) – compatible kWh demand meter and communications.

20.3.8. Consult EIC for MCAGCC Single Phase Pad-Mount Transformer specification.

20.4. OVERHEAD TRANSMISSION AND DISTRIBUTION

20.4.1. For all new overhead 15-50 kV medium-voltage distribution conductors, use 336.4 aluminum conductor steel reinforced with 26/7 strand.

20.4.2. If the design includes wood power poles, always use full-length pressure treated Douglas fir poles.

20.4.3. An Avian Protection Plan (APP) is required to reduce the operational and avian risks that result from avian interactions with electric utility facilities. Consult EIC for MCAGCC APP guidelines.

20.4.4. Consult EIC for MCAGCC Overhead Distribution specification

20.5. UNDERGROUND TRANSMISSION AND DISTRIBUTION

20.5.1. For all new underground medium-voltage (5 kV – 50 kV) distribution cable, use EPR insulation with a 133% insulation level.

20.5.2. Include a minimum of 1 – 4" spare duct in all underground duct banks for primary distribution (laterals) and secondary distribution.

20.5.3. Include a minimum of 1 – 6" spare duct (concrete-encased) in all underground duct banks for primary distribution (along main run between underground structures).

20.6. SECONDARY UNIT SUBSTATIONS

20.6.1. All secondary unit substations shall be of the pad-mount type. Refer to SKE-01.

20.6.2. All protective relays shall match existing relays. Existing protective relays are manufactured by Schweitzer Engineering Laboratories, (SEL) Inc. (See SKE-04.)

20.6.3. Provide microprocessor based protective relays for each vacuum circuit breaker that match existing microprocessor based protective relays. Existing microprocessor based protective relays are manufactured by Schweitzer Engineering Laboratories, Inc. (See SKE-04.)

20.6.4. Provide metering for all electrical power and emergency power.

Page 40: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 40

20.6.5. Provide a digital power instrumentation package for all utilities. Central Control System (CCS)-compatible power flow meters are required. Use either in-line magmeters or external ultrasonic-type, with kWh-kW demand monitoring and metering, located in the switchgear.

20.6.6. Consult EIC for MCAGCC Substation specification.

20.7. LIGHTING

20.7.1. Design illumination levels and distribution in accordance with IES recommendations and UFC 3-530-01. See Appendix B - References.

20.7.2. Base the selection of lighting fixtures on cost, maintenance, function and light characteristics, including uniform distribution, ruggedness, glare, resistance to vandalism, and energy efficiency.

20.7.3. All buildings require security lighting on exterior walls, building entrances, and wherever specific project requirements indicate.

20.7.4. Fluorescent lighting fixtures shall have T8-32W (U.O.N.) lamps and energy-efficient electronic high-frequency ballasts, UL-listed and ETL-certified, Class “P” high power factor (not less than 0.90), with “A” sound rating or better and less than 20% total harmonic distortion (THD).

20.7.5. Provide 20-ampere lighting branch circuits, each with a 20-ampere circuit breaker.

20.7.6. Means of Egress:

20.7.6.1. Provide means of egress, egress lighting, emergency lighting and exit signs in accordance with NFPA 101, Chapter 7.

20.7.6.2. Emergency lighting equipment shall be UL listed with a self-diagnostic feature and a trouble/failure indicator light. Times and durations of self-diagnostics shall be in accordance with NFPA 101, 7.9.3.

20.7.6.3. Exit signs and emergency lighting require an alternate power source through either battery backup or by a generator with an automatic transfer switch that provides secondary power within 10 seconds of primary electrical failure.

20.7.6.4. Provide LED type, vandal-resistant exit signs with a recessed base of durable, industrial quality and a solid mount; with a self-diagnostic test feature and a trouble/failure indicator light. Times and durations of self-diagnostics shall be in accordance with NFPA 101 7.10.9.2 and NFPA 101, 7.9.3.

20.8. SOLAR PHOTOVOLTAIC SYSTEMS

20.8.1. Refer to CCFD “Solar Photovoltaic Construction Guidelines” for requirements on solar array installations.

20.9. CATHODIC PROTECTION SYSTEM

20.9.1. Coordinate requirements with the EIC.

20.9.2. Provide cathodic protection to all underground steel piping in direct contact with soil.

20.9.3. Provide cathodic protection to all above ground steel tanks.

Page 41: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 41

21. COMMUNICATIONS (DIVISION 27)

21.1. TELECOMMUNICATIONS STANDARDS

Refer to CCO 2010.1 “MARINE AIR GROUND TASK FORCE TRAINING COMMAND (MAGTFTC), MARINE CORPS AIR GROUND COMBAT CENTER (MCAGCC) TELECOMMUNICATIONS DESIGN STANDARDS.”

22. ELECTRONIC SAFETY AND SECURITY (DIVISION 28)

22.1. FIRE ALARM SYSTEM

22.1.1. During the design phase of a utility or improvement project, it will be the DOR’s responsibility to get approval of valve locations from the MGAGCC Fire Department, and to coordinate with the EIC. Contractors shall coordinate the design of the project with the MCAGCC Fire Department’s Fire Prevention Office.

22.1.2. MCAGCC fire alarm systems use a Digital Alarm Communicator Transmitter (DACT), or optionally, a King Fisher system to transmit signals. Panels and components shall be fully compatible with the existing Bosch D6600 DACR receiver and the Simplex True Site Workstation signaling systems software controlled by the Base Fire Department.

22.1.3. Certification of Fire and Life Safety systems by the contractor, shall be done by either the FPE of record or the system manufacturer’s representative.

22.1.4. Fire alarm (FA) is required anywhere a fire suppression sprinkler system, or a fire suppression hood system is required and all locations that require a Mass Notification System (MNS). Locations that require MNS include inhabited locations with 11 or more personnel in an occupant density of greater than 430 square feet per person (UFC 3-600-01 and UFC 4-021-01). The Contractor is fully responsible for investigating, testing, and demonstrating full system compatibility and delivering a fully functional, turn-key FA and MNS.

22.1.5. Smoke detectors in sleeping rooms shall be system monitored for security, will sound a single alarm in the sleeping rooms, and be tied in to the fire alarm so that if more than two detectors activate it will cause the system to initiate a building alarm.

22.1.6. Fire alarm components will be keyed CAT15 to include all pull stations, FACP, locking junction boxes, etc.; duct detector test switches are to be CAT45.

22.1.7. System shall pass 60 hour battery test with 15 minute ring down.

22.1.8. Duct detectors shall cause HVAC system shut down and transmit a supervisory signal to fire dispatch.

22.1.9. The FACP and all system components are to be fully compatible with MCAGCC’s existing receivers, the “Bosch D6600” receiver/gateway, and the signaling systems receiving software, “Simplex True Site” graphical command center workstation. The FACP is to transmit via Digital Alarm Communicator/Transmitter (DACT), or optionally, by King Fisher system, be certified by the manufacturer’s representative, and have the following minimum features:

22.1.9.1. Contact ID, walk test, individual addressable devices, individual point disconnect/disable, optional Digital Voice Evacuation (DVC) support, on-site upload and download of panel program, support for remote LCD annunciators, four operator

Page 42: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 42

access levels with event historical log, networkable utilizing CAT-5 and fiber optic cables, and be backward and forward compatible.

22.1.9.2. Operational and technical training is to be provided to the Government along with any proprietary software, licenses and certifications required to access said software and fully support the system. All manuals, technical drawings, technical data, programming codes and disks are to be turned over to the government prior to system acceptance.

22.1.9.3. Provide a laptop computer, complete with the project’s FACP programming software, technical drawings, manuals and graphics to fully troubleshoot, modify and program the project’s FA system and all associated devices. Laptops for web-based systems do not require this installed software, provided they have the ability to connect locally in real time, view all graphics, and fully troubleshoot, modify and program all FA system devices. Provide an appropriate laptop carrying case constructed of ballistic nylon with a shoulder strap (on wheels with a telescoping handle), all necessary cables, interface hardware, modules and standalone programmers needed for setup and communication with the FACP and all system components. Note: the Government will not use FSRM funds to purchase this equipment, but will likely use O&M funds.

22.1.9.4. The laptop computer should meet or exceed all hardware requirements as dictated by the application software manufacturer. Provide the laptop manufacturer’s 3-year warranty with the Government as the warranty owner. Note: the Government will not use FSRM funds to purchase this equipment, but will likely use O&M funds.

22.1.9.5. Programming protocol for DACT is to be “contact ID” with all points identified and submitted to the government electronically in an Excel or .csv file format at least two weeks prior to final testing. Building number is to be used as account number for programming, and phone numbers to program are 760-830-7230 and 760-830-7231. Phone lines are not to be left attached to the FA panel until all programming and testing has been completed and system is functioning normal. The phone lines shall be installed in conduit from the DACT to the telephone backboard.

22.1.9.6. The FACP is to be integrated with the required MNS and two-way combination speaker strobes (strobes only where appropriate) marked “Alert” are to be utilized throughout project.

22.1.9.7. All doors leading to FA equipment will be marked with permanent signage.

22.1.9.8. A system emergency shutdown button is required with an operational information plaque posted at the button.

22.1.10. All FA equipment shall be submitted for review and final approval with the following of equipment preferred (most current models only):

22.1.10.1. Simplex.

22.1.10.2. Edwards.

22.1.10.3. Notifier.

22.1.10.4. King Fisher.

22.1.10.5. Bosch (small projects only).

Page 43: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 43

22.1.11. Provide a graphical user interface (GUI) at dispatch, which is compatible with the base receiver.

22.1.12. The FACP shall have the capability to silence fire alarm audible signals including waterflow signals.

22.1.13. A building floor plan is to be located and permanently mounted next to the FACP. The floor plan shall be, at a minimum, laminated, show all initiating devices, all room numbers/names and device addresses.

22.2. MASS NOTIFICATION SYSTEM

22.2.1. Where MNS is required it will be installed per SPAWARSYSCEN guidance of 23 Jun 2010.

22.2.2. Provide a Wireless Audio Visual Alerting Emergency System (WAVES). This system is available through “MadahCom, Inc.,” “Wheelock Industries,” “Cooper Industries,” “Cooper Notification,” and “SGIS” (value added reseller).

22.2.3. All equipment submitted for approval shall provide, at minimum, a standalone combination fire/voice evacuation panel, capable of live and pre-recorded audio, full integration with the building fire alarm control panel, with an auxiliary line level audio input and be capable of integration with the MCAGCC local transceiver located at the Provost Marshal’s dispatch office (coordinate with PMO’s MNS representative,). The following list of equipment is SPAWARS preferred equipment:

22.2.3.1. Voice Panel – “Cooper Notification” ACU-340 (previously marketed as “Wheelock Safepath” 40 – SP40S) to connect back to FACP.

22.2.3.2. MNS Radio Transceiver – “Cooper Notification” TRX-401 (previously “MadahCom” brand name – still WAVES) with UPS-901 battery backup and RF cable, both located within 15 to 25 feet of the panel. RF cable to be installed in 1-½ inch diameter rigid conduit from the transmitter to a weather head located at a point 3 feet above the apex of the roof.

22.2.4. Contact either Mr. Robert (Biff) Brown at SPAWARS (843) 218-6292, or Mr. Jeff Wooddard (843) 218-5549 for block diagram and further technical guidance.

23. EARTHWORK (DIVISION 31)

23.1. EARTHWORK, EXCAVATION, BACKFILLING AND COMPACTING, EXCAVATION AND FILL

The maximum fill slope for general site fill is 5 H : 1 V (20%), unless PWD’s civil engineer specifically designates otherwise.

24. EXTERIOR IMPROVEMENTS (DIVISION 32)

24.1. FIRE ACCESS AND FIRE LANES

24.1.1. Design fire lanes to support minimum 27 ton apparatus.

24.1.2. Per the UFC 3-600-01, design fire lane turn-around in accordance with NFPA 1. The angle of approach and departure shall not exceed 1 foot drop in 20 feet (5%). Minimum turning inside radius of 20 feet, minimum curb to curb radius of 40 feet, and minimum wall to wall radius of 50 feet (outside).

24.1.3. Set back fire lanes along interior perimeter of building footprint to avoid sharp

Page 44: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 44

turns in the fire lane but maintain maximum travel distances required to meet UFC 3-600-01.

24.1.4. Provide obvious markings along fire lane to indicate dedicated use. Design in accordance with the specification sheet and minimum and maximum radius requirements.

24.1.5. All new fire access roadways to be located a minimum of 15 feet from new or existing buildings.

24.2. MARKERS FOR FIRE HYDRANTS

24.2.1. Install two-way blue “Stimson Sonite Lifelite” 88a13 or equal markers where visible on the adjacent access roadway in close proximity to each fire hydrant.

24.2.2. Provide blue reflective marker recessed into pavement at street for fire hydrants.

24.3. ASPHALT PAVING

24.3.1. Asphalt materials and installation shall conform to California Department of Transportation Standard Specifications (SS-1).

24.3.2. Aggregate base course layer beneath asphaltic concrete pavement shall conform to Section 26 of SS-1, Class 2 for ¾-inch maximum size gradation. Aggregate for asphalt concrete shall conform to Section 39 of SS-1, Type B for ½ inch maximum size gradation, medium.

24.3.3. Asphalt cement shall conform to Section 92 of SS-1, Grade PG-70 to resist extreme desert temperatures.

24.3.4. Liquid asphalt for use as crack sealer and primer shall conform to Section 93 of SS-1, Grade SC-250.

24.3.5. Asphaltic emulsion for paint binder shall conform to Section 94 of SS-1, Grade SS-1.

24.3.6. For pavement marking use water-base type paint conforming to FS TT-P-1952, fast dry or rapid dry type. Paint shall contain reflectorized glass beads or any other manner of reflective material unless the EIC directs otherwise.

24.3.7. Pave any required fire lanes with asphalt cement in accordance with NFPA-1, and provide a turn-around per Drawing SKC-21 and UFC 3-250-10 FA criteria.

24.4. CONCRETE PAVING

24.4.1. For large-scale paving projects or airfield paving projects refer to criteria in “Design of Concrete Airport Pavement” (EB050.03P), Portland Cement Association, 1973, and NAVFAC specifications. Portland cement for concrete shall be Type I or Type II. Minimum concrete flexural strength for pavements shall be 650 pounds psi.

24.4.2. Minimum thickness for pavement conveying tanks or tracked vehicles shall be not less than 9-¼ inches.

24.5. PARKING STALL STRIPING

24.5.1. Provide 10 foot wide stalls within parking structures. See the BEAP for further guidance.

Page 45: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 45

24.6. PAVEMENT MARKING

24.6.1. Repaint street and parking lot markings after resurfacing as well as those that have been damaged by construction. Paint shall be water-based pavement marking paint and shall conform to FS TT-P-1952 fast dry or rapid dry type.

24.6.2. Paint may contain reflectorized glass beads or any other manner of reflective material when PWD’s Civil Engineer so directs.

24.7. CHAIN LINK FENCES AND GATES

24.7.1. Use only galvanized chain link fabric conforming to RR-F-191. Fence fabric shall be 9-gauge weight with 2-inch mesh size. Selvage shall be knuckled at one selvage and twisted and barbed at the other. Line posts shall be Class 1 steel pipe, Grade A, conforming to RR-F-191/3.

24.7.2. When provided, barbed wire shall also be galvanized.

25. UTILITIES (DIVISION 33)

25.1. WATER DISTRIBUTION

25.1.1. Water mains (i.e., 4-inch size and larger) shall be polyvinyl chloride (PVC), AWWA C900, Class 150. Asbestos cement pipe is not acceptable. Minimum water main size is 8-inch diameter for mains serving multiple buildings or serving multiple connections. PVC piping shall have Standard Dimension Ratio SDR = Average O.D/wall thickness (rounded to the nearest integer) rating to match 150 psi minimum pressure rating.

25.1.2. Under special conditions, such as at utility crossings, locations with excessively deep cover depths or unstable soil conditions, water mains shall be constructed of ductile iron pressure pipe conforming to AWWA C151, in lieu of PVC pipe. Flanged ductile iron pipe shall be used where restrained joint pipe is required. Restrained joint pipe shall be capable of resisting hydraulic thrust forces directed along the pipeline. Restrained joints can include grooved joints, restrained couplings, and special factory-made joints.

25.1.3. Water service lines shall include:

25.1.3.1. Copper tubing Type “K” conforming to ASTM B88; or,

25.1.3.2. Polyvinyl chloride (PVC) plastic pipe, Schedule 80, conforming to ASTM D1785, with fittings conforming to ASTM F439. Provide solvent cement for joint assembly conforming to ASTM D2564, or

25.1.3.3. Polypropylene conforming to ASTM D635, E84, F2023 and F2389, BNQ 3660-950, CSA B214 and B1371.11, and ISO 15074ff.

Provide filtered cold water supply lines to each building being supplied. Submit filter type and system for EIC approval.

25.1.4. A water supply for fire protection, either temporary or permanent, shall be available as soon as combustible material accumulates. Where new underground water mains and fire hydrants are part of the design, they shall be installed, completed and in service prior to construction work (see NFPA 241 6.7.2.2).

25.1.5. Hydrant laterals shall be 6-inch minimum size, shall not exceed 50 feet in length,

Page 46: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 46

and shall have an underground shutoff valve.

25.1.6. Protect buried ductile iron pipe against corrosion by using polyethylene tube or sheet conforming to AWWA/ANSI C105/A21.5, class A or C.

25.1.7. Provide resilient wedge gate valves for water main valves conforming to AWWA C509. Water service valves shall conform to AWWA C509. Provide flanged water main valves; water service valves shall be threaded. All valves shall be of one manufacturer. Provide above ground access to all valves using cast iron valve boxes, including section valves, gate valves and hydrant valves. Locate section valves at approximately 350 foot to 500 foot intervals along each pipeline.

25.1.8. Provide underground hydrant shutoff valves in cast-iron valve boxes within 10 feet of the hydrant and where there will be no obstructions such as parked vehicles, shrubbery, etc. Provide 2’ x 2’ x 6” concrete slabs around valve box covers. Valve box covers shall be painted blue.

25.1.9. Check valves shall be swing-check type, conforming to AWWA C508. Check valves shall be weighted or spring-loaded.

25.1.10. Hydrants shall be Underwriters Laboratories (UL) listed or Factory Mutual (FM) approved, conforming to AWWA C503 and NFPA 24, wet-barrel type with “tell tale” feature and breakaway safety fitting. Each hydrant shall provide one 6-inch inlet, one 4-inch pumper connection and two 2-½-inch hose connections.

25.1.11. Space all new fire hydrants at intervals not to exceed 500 feet along the street, driveway or designated fire access lane, set back at least 3 to 7 feet from curb or road edge, at least 40 feet from adjacent buildings and located to limit hose layouts so that they do not exceed 350 feet to all parts of the building.

25.1.12. Hydrant discharge outlet threads shall have NH standard external threads to match all other hydrants at MCAGCC.

25.1.13. Orient fire hydrants with 4-inch pumper connections to be perpendicular to adjacent access roadways.

25.1.14. Set the height of fire hydrants at 18 inches above the final grade to the center of the 4-inch pumper connection.

25.1.15. Provide a 3’ x 3’ x 6” concrete slab, centered on each hydrant, 2 inches below the shear spool cut.

25.1.16. Provide guard posts at hydrants (bollards set in concrete, see SKC-24) where there is no curb. Bollards shall not obstruct access to pumper discharge outlets. Paint bollards Safety Yellow color.

25.1.17. Provide a minimum 3-foot radius unobstructed working area around each hydrant.

25.1.18. Paint body of hydrants safety yellow color and color code caps (blue = 1,500+ GPM; green = 1,000 to 1,500 GPM; yellow = 500 to 1,000 GPM and red = less than 500 GPM) and top of hydrant to indicate the GPM measured in accordance with NFPA 24. Hydrostatically pressure test hydrants. Color coding allows the fire tanker’s driver to know what kind of volume the driver can expect from the hydrant.

25.1.19. Certify hydrants to 300 pounds psi in accordance with NFPA 291.

Page 47: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 47

25.1.20. Provide reduced-pressure type backflow preventers for all domestic activities. Backflow preventers are typically not required for housing units unless the housing unit is supplied by a fire sprinkler connection.

25.1.21. Provide insulation for exposed backflow preventer piping to protect the entire backflow preventer assembly from extreme desert high and low temperatures. Provide guard posts (bollards set in concrete, see SKC-24) to protect exposed backflow preventers against damage. Paint bollards Safety Yellow color.

25.1.22. The contractor shall sequence construction activities such that if any existing fire hydrant will be out of service at any time, the Contractor shall receive prior approval from the Contracting Officer, who will notify the Fire Department prior to such outages. Firmly secure a black bag over any hydrant that is or becomes out of service.

25.2. HYDRANTS

25.2.1. Hydrants will be California wet barrel, with 4-inch pumper connection facing street way.

25.2.2. Shall be within 3 to 7 feet from the drivable surface, and place watch valve in paved surface.

25.2.3. Pressure test and color code hydrant per NFPA 291.

25.2.4. Provide “TELL-TALE” break away feature auto shut off device for damaged hydrant.

25.2.5. Hydrant specification sheet modified.

25.3. NON-POTABLE WATER DISTRIBUTION

25.3.1. There are currently two classes of non-potable water used at MCAGCC: “non-pot” which is naturally-occurring ground water that has a mineral content exceeding DHS standards for water to be used for domestic consumption; this type of no-potable water is often used on base for construction water and has no special regulatory requirements for its use other than permission by the MCAGCC PWD and ROICC. The second type of non-potable water is “reclaimed water” which is domestic sewage that has been treated, filtered, and disinfected at the MCAGCC sewage treatment facility prior to reuse; this recycled water is used principally for landscape and golf course irrigation and its handling is strictly regulated by PWD under DHS permit to limit civilian exposure.

25.3.2. All proposed use of non-potable water is “reclaimed water” shall be approved by PWD’s Civil Engineer before design or installation commences. If PWD’s Civil Engineer approves the use of reclaimed water, the design specifications shall be reviewed and approved by that PWD Civil Engineer or the Base Cross-Connection Specialist to ensure that the proper components and fittings are specified before construction begins. All work shall conform to California Department of Public Health rules and regulations and MCAGCC requirements. Upon completion of work on the reclaimed water system and before activating the system, test it for cross-connections and improper sprinkler operation by the Contractor’s Cross-Connection Specialist certified by California-Nevada American Water Works Association (Cal-Nevada AWWA) or an equivalent Cross-Connection Control Specialist certification

Page 48: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 48

acceptable to PWD’s Civil Engineer. Before the new reclaimed water system may be put into service PWD’s Civil Engineer or the Base Cross-Connection Specialist shall submit the entire cross-connection test results to the California Department of Public Health (DPH) for formal acceptance. This procedure shall not supersede the processing of the use permit by NERA.

25.3.3. Before the Base accepts any recycled water system modification or addition the system shall successfully pass a recycled water cross-connection control shut down test. The test shall be conducted by an individual who holds a current California – Nevada American Water Works Association Cross-Connection Control Specialist certification or an American Backflow Prevention Association Cross-Connection Control Specialist certification.

25.3.4. The initial recycled water cross connection control shut down test shall be performed using potable water.

25.3.5. No site may be converted to recycled water use without the prior approval of PWD’s Civil Engineer or the Base Cross-Connection Control Specialist and the successful completion of all requirements for the use of recycled water.

25.3.6. On sites having both potable and recycled water service, protect the potable water service with a reduced pressure principle backflow prevention assembly located as close as possible to the potable water point of connection. Recycled and potable water lines shall be located a minimum horizontally of ten feet apart, measured between outside pipe walls.

25.3.7. Protect drinking water fountains and designated outdoor eating areas against contact with recycled water spray, mist or runoff.

25.3.8. Hose bibs on the recycled water system are strictly prohibited.

25.3.9. Color code recycled water systems and all appurtenances, such as pipes, sprinkler heads, valve boxes, etc., purple per AWWA guidelines and Section 116815 of the California Health and Safety Code.

25.3.10. All recycled water irrigation valves shall be tagged with recycled water tags.

25.3.11. Locate all on-site, post meter, potable water lines, sewer lines and constant pressure disinfected tertiary recycled water lines a minimum of 4 feet apart. Measurements shall be between facing surfaces, not between pipe center lines.

25.3.12. Constant pressure recycled water lines shall cross perpendicularly at least 12 inches below potable water lines.

25.3.13. If a constant pressure recycled water line shall be installed above a potable water line or less than 12 inches below a potable water line, then the recycled water line shall be installed within an approved protective sleeve. Color-code the sleeve purple and extend the sleeve a minimum distance of 10 feet from both sides of the crossing.

25.3.14. Quick coupler valves on a recycled water irrigation system shall be of ACME threaded type design and of a different design than those quick couplers used on potable water systems. The recycled water quick coupler cap shall be purple and designated for the use of recycled water only. Color all recycled water piping and above ground appurtenances purple or mark them for the use of recycled water only.

Page 49: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 49

25.3.15. Allow no substitutions of pipe materials without the prior approval of PWD’s Civil Engineer or the Base Cross-Connection Control Specialist.

25.3.16. Cross-connections between recycled water lines and potable water lines are strictly prohibited.

25.3.17. Permanently identify by decal the irrigation controller box as a recycled water controller.

25.3.18. Provide a physical separation between adjacent areas irrigated with recycled water and potable water. Use distance, concrete mow strips or other approved methods. Provide a minimum of 4 feet between potable & recycled sprinkler heads.

25.3.19. Call out the design and location of recycled water warning signs on the plans.

25.3.20. Recycled water mains (i.e., 4-inch size and larger) shall be polyvinyl chloride (PVC), AWWA C900, Class 150. Asbestos cement pipe is not acceptable. PVC piping shall have SDR rating to match the 150 psi minimum pressure rating and be colored purple per AWWA guidelines and Section 116815 of the California Health and Safety Code.

25.3.21. Under special conditions, such as at utility crossings, locations with excessively deep cover depths or unstable soil conditions, water mains shall be constructed of ductile Iron pressure pipe conforming to ANSI/AWWA 151/ A21.51, in lieu of PVC pipe. Use flanged ductile iron pipe where restrained joint pipe is required. Restrained joint pipe shall be capable of resisting hydraulic thrust forces directed along the pipeline. Restrained joints can include grooved joints, restrained couplings, and special factory-made joints. Color-code detectable utility marking tape purple to designate the presence of a recycled water line.

25.3.22. Recycled water service lines shall be PVC plastic pipe, Schedule 80, conforming to ASTM D1785, with fittings conforming to ASTM F439. Color pipe purple per AWWA guidelines and Section 116815 of the California Health and Safety Code. Solvent cement for joint assembly shall conform to ASTM D2564.

25.3.23. Water main valves shall be resilient-wedge gate valves conforming to AWWA C509. Water service valves shall conform to AWWA C509. All valves shall be products of the same manufacturer. All valves shall have cast iron valve boxes, painted purple, to provide above ground access, and to designate them for recycled water use.

25.4. SANITARY SEWER SYSTEMS

25.4.1. Gravity sanitary sewer laterals serve a single building only and convey the collected sewage to a larger sewer main for transport to the sewage treatment plant. Gravity sewer laterals shall be a minimum of 6 inches in diameter and provide a minimum self-cleaning velocity of 2.5 feet per second at some point in the flow regime each day, in accordance with NAVFAC design policy. Maximum allowable velocity shall be 10 feet per second Gravity sewer mains shall be a minimum of 8 inches in diameter. Design of both sewer laterals and sewer mains shall conform to UFC 3-240-01, Wastewater Collection requirements.

25.4.2. Gravity sanitary sewer pipe shall be PVC plastic and conform to ASTM D3034, type SDR 35, or ASTM F949 for larger diameter pipe (i.e., 12-inch diameter and

Page 50: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 50

larger). Ribbed PVC sewer pipe, used for deeper burial or increased strength situations, shall conform to ASTM F794 for sizes 8-inch through 48-inch diameter. Joints shall be elastomeric type.

25.4.3. Pressure sewer pipe shall be PVC plastic and shall conform to AWWA C900, Class150. Joints shall have a pressure rating at least equal to the pipe being joined (i.e., 350 pounds psi). Pressure fittings shall be ductile iron push-on joint type ANSI/AWWA C111/A21.11. When crossing water lines use pressurized pipe for at least 10 feet on both sides of the crossing.

25.4.4. Sewer manholes shall be joined to interconnecting sewers through elastomeric type joints. Manholes shall provide a minimum internal diameter of 5 feet and a minimum ground-level entry diameter of 3 feet. Construct manholes of precast structural concrete rings and cast-in-place concrete base slabs. Provide internal manhole ladder rungs consisting of rubber-coated steps for manholes deeper than 4 feet.

25.4.5. Sewer manhole covers shall be cast iron or ductile iron, Traffic-Weight, with frame, and all conforming to CID A-A-60005.

25.5. STORM DRAINAGE

25.5.1. Gravity storm drain pipe shall be PVC plastic pipe conforming to ASTM D3034, SDR 35. Joints shall be elastomeric type, conforming to ASTM D3212. PVC fittings shall have elastomeric type gasketed joints and conform to ASTM D2855 and ASTM F402. Minimum storm drain size shall be 15-inch diameter.

25.5.2. For large-scale storm drainage projects, pipe shall be reinforced concrete conforming to ASTM C76, with a minimum D-load rating of not less than 1,500 pounds per lineal foot of diameter. Joints shall be elastomeric type conforming to ASTM C443. Gaskets shall be suitable for use with sewage.

25.5.3. Storm drain manhole covers shall be cast-iron or ductile-iron, Traffic-Weight, with frame, all conforming to CID A-A-60005

END OF A-E DESIGN MANUAL

Page 51: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 51

APPENDIX A - DETAILS AND DIAGRAMS

Page 52: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 52

26. APPENDIX A - DETAILS AND DIAGRAMS

26.1. GENERAL

SKG-00 ABREVIATION

26.2. CIVIL

SKC-01 UTILITY TRENCH

SKC-02 FIRE HYDRANT ASSEMBLY

SKC-03 WATER SERVICE LATERAL CONNECTION

SKC-04 SECTION VALVE

SKC-05 TYPICAL WATER PIPE UTILITY CROSSING

SKC-06 AIR RELEASE / VACUUM VALVE ASSEMBLY

SKC-07 BLOW OFF VALVE

SKC-08 REDUCED PRESSURE BACKFLOW PREVENTION ASSEMBLY - 4” TO 8”

SKC-09 REDUCED PRESSURE BACKFLOW PREVENTION ASSEMBLY - 1/2” TO 2”

SKC-10 REDUCED PRESSURE BACKFLOW PREVENTION ASSEMBLY - 2.5” TO 3”

SKC-11 JOINT TRENCH UTILITIES

SKC-12 DOUBLE CHECK VALVE ASSEMBLY FOR FIRE CONNECTION

SKC-13 PIPE CONCRETE ENCASEMENT & PLUG / CAP

SKC-14 THRUST BLOCKS

SKC-15 SEWER MANHOLE

SKC-16 CLEANOUT

SKC-17 POST INDICATOR VALVE

SKC-18 MAIN CONCRETE CHANNEL

SKC-19 CONCRETE CURB & GUTTER AND CONCRETE CURB

SKC-20 CONCRETE SIDEWALK

SKC-21 FIRE LANE TURN-AROUND

SKC-22 EXPANSION AND WEAKENED PLANE JOINTS

SKC-23 PAVEMENT REPAIR

Page 53: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 53

SKC-24 BOLLARD

SKC-25 CHAIN LINK FENCE

SKC-26 PIPE SUPPORT FOR WATER PIPE

SKC-27 MONUMENT WELL AND BRASS CAP

SKC-28 WIND ROSE

SKC-29 MATCH PAVEMENT TO VAULT

SKC-30 RECYCLED WATER UTILITY TRENCH

SKC-31 RECYCLED WATER SERVICE LATERAL CONNECTION

SKC-32 RECYCLED WATER SECTION VALVE

SKC-33 RECYCLED WATER BLOW-OFF VALVE

SKC-34 RECYCLED WATER PIPE CONCRETE ENCASEMENT AND PLUG / CAP

SKC-35 RECYCLED WATER THRUST BLOCKS

SKC-36 RECYCLED WATER WARNING SIGN

SKC-37 RECYCLED WATER USE SITE INSPECTION FORM

SKC-38 AT / FP ANTI-TERRORISM FORCE PROTECTION

SKC-39 4 WAY INTERSECTION STOP SIGN

26.3. ARCHITECTURAL

SKA-01 MODIFIED BITUMEN ROOFING AT PARAPET DETAIL

SKA-02 BUILT-UP ROOFING AT PARAPET DETAIL

SKA-03 MODIFIED BITUMEN ROOFING AT EQUIPMENT PLATFORM DETAIL

SKA-04 BUILT-UP ROOFING AT EQUIPMENT PLATFORM DETAIL

SKA-05 MODIFIED BITUMEN ROOFING AT EQUIPMENT CURB DETAIL

SKA-06 BUILT-UP ROOFING AT EQUIPMENT CURB DETAIL

SKA-07 MODIFIED BITUMEN ROOFING AT PIPE, VENT OR CONDUIT PENETRATION DETAIL

SKA-08 BUILT UP ROOFING AT PIPE, VENT OR CONDUIT PENETRATION DETAIL

SKA-09 MODIFIED BITUMEN ROOFING AT EQUIPMENT SUPPORT DETAIL

Page 54: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 54

SKA-10 BUILT-UP ROOFING AT EQUIPMENT SUPPORT DETAIL

SKA-11 KNEE AT EAVE (TYP)

SKA-12 RIDGE DETAIL (TYP)

SKA-13 VALLEY DETAIL (TYP)

SKA-14 GABLE END DETAIL (TYP)

SKA-15 PANEL END LAP DETAIL (TYP)

SKA-16 EAVE HEM DETAIL (TYP)

SKA-17 EAVE DETAIL (TYP)

SKA-18 PIPE FLASHING DETAIL

SKA-19 CAP SPLICE DETAIL (TYP)

SKA-20 PRE-ENGINEERED CURB DETAIL

SKA-21 EXTERIOR CMU WALL DETAIL

SKA-22 WALL AT ROOF / UNDERSIDE OF DECK

SKA-23 PIPE / DUCT PENETRATION OF FIRE / SMOKE BARRIERS

SKA-24 BUILDING IDENTIFICATION SIGNAGE

SKA-25 INTERIOR SIGNAGE DETAIL

SKA-26 FREESTANDING SIGNAGE DETAIL

SKA-27 FACILITY RECOGNITION PLAQUE

26.4. MECHANICAL

SKM-01 SAMPLE SCHEDULES FOR ROTARY EVAPORATIVE COOLER UNITS

SKM-02 SAMPLE ROTOR COOLER CONNECTION DETAIL

SKM-03 SAMPLE STRUCTURAL SUPPORT ASSEMBLY FOR GRADE MOUNTED EQUIPMENT

SKM-04 SAMPLE SCHEDULES FOR A 2-SPEED ROTARY COOLER UNIT

SKM-05 SAMPLE SEQUENCE OF OPERATION FOR A 2-SPEED ROTARY COOLER UNIT

SKM-06 SAMPLE HIGH TEMPERATURE HOT WATER HEATING COIL PIPING DIAGRAM WITH TWO CONTROL VALVES

SKM-07 SAMPLE HIGH TEMPERATURE HOT WATER HEATING COIL PIPING DIAGRAM WITH ONE CONTROL VALVE

Page 55: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 55

SKM-08 SAMPLE HIGH TEMPERATURE HOT WATER HEATING / EVAPORATIVE COOLING CONTROL DIAGRAM

SKM-09 SAMPLE HIGH TEMPERATURE HOT WATER HEATING / EVAPORATIVE COOLING AIR FLOW DIAGRAM

SKM-10 SAMPLE SEQUENCE OF OPERATION FOR A HIGH TEMPERATURE HOT WATER HEATING / EVAPORATIVE COOLING UNIT

SKM-11 CHILLED WATER PIPING DETAILS

SKM-12 CHILLED WATER PIPING DETAILS

SKM-13 CHILLED WATER PIPING DETAILS

SKM-14 CHILLED WATER & HIGH TEMPERATURE HOT WATER PIPING DETAILS

SKM-15 HIGH TEMPERATURE HOT WATER PIPING DETAILS

SKM-16 HIGH TEMPERATURE HOT WATER PIPING DETAIL

SKM-17 HTHW AND CHW PIPING INSULATION DETAILS

SKM-18 HTHW AND CHW PIPING INSULATION DETAILS

SKM-19 HTHW PIPING DETAILS

SKM-20 HTHW PIPING DETAILS

SKM-21 HTHW PIPING DETAILS

SKM-22 NOTES

SKM-23 NOTES

26.5. ELECTRICAL

SKE-01 TYPICAL SUBSTATION EQUIPMENT LAYOUT

SKE-02 REINFORCING DETAIL SUBSTATION PAD

SKE-03 TYPICAL SUBSTATION FENCE DETAIL

SKE-04 TYPICAL SUBSTATION GROUNDING LAYOUT

SKE-05 TYPICAL SUBSTATION PAD GATE GROUNDING

SKE-06 65’ POLE DETAIL

SKE-07 60’ POLE DETAIL

SKE-08 55’ POLE DETAIL

SKE-09 TYPICAL ANCHOR AND GUYING DETAIL

SKE-10 ALLOCATION OF SPACE ON JOINT-USE POLES

Page 56: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 56

SKE-11 MARKING AND IDENTIFICATION OF DISTRIBUTION POLES

SKE-12 POLE NUMBERING TAG

SKE-13 INSTALLATION OF A CUSTOMER OWNED SERVICE & METER POLE

SKE-14 KEYED NOTES FOR CUSTOMER OWNED SERVICE & METER POLE

SKE-15 GENERAL NOTES FOR CUSTOMER OWNED SERVICE & METER POLE

SKE-16 CABLE TERMINATION

SKE-17 FUSED DISTRIBUTION CABLE POLE RISER

SKE-18 MATERIAL LIST FOR FUSED DISTRIBUTION CABLE POLE RISER

SKE-19 14.4kV SCADA-MATE SECTIONALIZING SWITCH

SKE-20 120/240V, SINGLE PHASE TRANSFORMER

SKE-21 MATERIAL LIST FOR 120/240V, SINGLE PHASE TRANSFORMER

SKE-22 TYPICAL DUCT BANK FOR 5kV-35kV FEEDERS

SKE-23 TYPICAL DUCT BANK FOR 600 VOLT FEEDERS

SKE-24 TYPICAL DUCTBANK INSTALLATION VEHICULAR TRAFFIC AREAS

SKE-25 HANDHOLE DETAIL

SKE-26 TYPICAL PRECAST CONCRETE SPLICE BOX

SKE-27 GRADE MOUNTED JUNCTION / PULLBOX

SKE-28 CABLE TAG DETAIL

SKE-29 PRECAST PAD

SKE-30 TYPICAL GROUND ROD LAYOUT

SKE-31 TYPICAL FENCE DETAIL FOR (NON-SUBSTATION) ELECTRICAL EQUIPMENT

SKE-32 SEISMIC RESTRAINT DETAIL ANGLE TYPE

SKE-33 SEISMIC RESTRAINT DETAIL FLAT CLIP TYPE

SKE-34 ELEVATION THREE PHASE PAD MOUNTED TRANSFORMER

SKE-35 LEGEND FOR THREE PHASE PAD MOUNTED TRANSFORMER

Page 57: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 57

SKE-36 ELEVATION SINGLE PHASE PAD MOUNTED TRANSFORMER

SKE-37 LEGEND FOR SINGLE PHASE PAD MOUNTED TRANSFORMER

SKE-38 200A-15kV LOADBREAK ELBOW CONNECTOR

SKE-39 200A-15kV LOADBREAK JUNCTION CONNECTOR

SKE-40 JUNCTION INSTALLATION

SKE-41 SEALING DETAIL

SKE-42 MEDIUM VOLTAGE 15kV SPLICE

SKE-43 TYPICAL 600V CABLE SPLICE

SKE-44 LOCATION FOR MOUNTING kWh-DEMAND METER

SKE-45 DIGITAL KILOWATT HOUR – DEMAND METER

SKE-46 DETAIL METER BOX

SKE-47 120V 4-JAW METER SOCKET

SKE-48 120/240V 4-JAW METER SOCKET

SKE-49 TELECOMMUNICATIONS POWER METERING CABINET

SKE-50 DISTRIBUTION GUTTER DETAIL

SKE-51 DISCONNECT SWITCH MOIUNTING DETAIL

SKE-52 SWITCH MOUNTING DETAIL

SKE-53 PANEL INSTALLATION DETAIL

SKE-54 TYPICAL LIGHT POLE DETAIL

SKE-55 TYPICAL WEATHERPROOF COVER

Page 58: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 59: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 60: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 61: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 62: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 63: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 64: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 65: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 66: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 67: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 68: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 69: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 70: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 71: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 72: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 73: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 74: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 75: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 76: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 77: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 78: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 79: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 80: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 81: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 82: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 83: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 84: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 85: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 86: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 87: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 88: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 89: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 90: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 91: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 92: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 93: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 94: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 95: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

Recycled Water Use Site Inspection Form 29 Palms Marine Corp Base

Date: Use Site: Address:

Bldg #: Contact:

THIS SITE PASSED FAILED POTABLE SHUTDOWN TEST

THIS SITE PASSED FAILED FUTURE RECYCLED SHUTDOWN TEST

TEST PERFORMED BY:

CROSS-CONNECTION CONTROL SPECIALIST CERT. #:

INSPECTION ITEM COMPLETE COMMENTS

Each irrigation station is run to ensure there are no broken or misadjusted heads and no leaks or breaks in the irrigation system.

Yes No

There is no overspray or misting onto unapproved use areas, such as neighboring properties, eating areas, sidewalks, etc.

Yes No

Irrigation discharge is confined to the use area. Yes No No signs of ponding, such as puddles, algae, etc. are present.

Yes No

All sprinkler heads on the recycled water system are marked with purple.

Yes No

The necessary recycled water signs are posted and in good repair.

Yes No

Recycled water meter boxes, valve boxes and covers are purple.

Yes No

Sprinkler valves are tagged with “Recycled Water – Do Not Drink” tags.

Yes No

Recycled water quick couplers have recycled water labeled locking covers.

Yes No

Impoundments and areas irrigated with recycled water meet minimum separation requirements from domestic water wells and reservoirs.

Yes No

The use area is maintained so as to prevent the breeding of flies, mosquitoes and other vectors.

Yes No

DESCRIBE SHUTDOWN TEST METHOD AND ATTACH DOCUMENTATION.

System: Meter Info: Backflow Prevention Assembly Info:Potable System:

Recycled System:

Page 96: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 97: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 98: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 99: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 100: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 101: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 102: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 103: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 104: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 105: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 106: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 107: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 108: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 109: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 110: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 111: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 112: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 113: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 114: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 115: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 116: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 117: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 118: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 119: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 120: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 121: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 122: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 123: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 124: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 125: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 126: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 127: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 128: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 129: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 130: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 131: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 132: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 133: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 134: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 135: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 136: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 137: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 138: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 139: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 140: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 141: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 142: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 143: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 144: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 145: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 146: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 147: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans
Page 148: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-01EQUIPMENT LAYOUTTYPICAL SUBSTATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 149: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-02

REINFORCING DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

SUBSTATION PAD

Page 150: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-03TYPICAL SUBSTATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

XXXX

XXXX

XXXX

XXXXXXX X

XXXXXXX

XXXXXXX

XXX

XXX

XXX

XX

X

X X X X

X X X X

X X X X

X X X X X X XX

X X X X X X X

X X X X X X X

X X X

X X X

X X X

XX

X

X X

X X

X X

XX

FENCE DETAIL

NOTE:

Page 151: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-04GROUNDING LAYOUTTYPICAL SUBSTATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 152: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-05GATE GROUNDINGTYPICAL SUBSTATION PAD

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 153: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-0665' POLE DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 154: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-0760' POLE DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 155: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-0855' POLE DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 156: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-09GUYING DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

1

3

4

6

7

C-2

C-1

1

7

3

4

C-2

6

C-1

4

TYPICAL ANCHOR AND

Page 157: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

55 FT. POLE 50 FT. POLE 45 FT. POLE 40 FT. POLE

GENERAL NOTES:

SKE-10JOINT-USE POLESALLOCATION OF SPACE ON

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 158: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

NOTE:

SKE-11OF DISTRIBUTION POLESMARKING AND IDENTIFICATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 159: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MCB1234

34

M

1B

2

12.47 kVDISTRIBUTION POLES

34.5 kVDISTRIBUTION POLES

NOTES:

SKE-12POLE NUMBERING TAG

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 160: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-13OWNED SERVICE & METER POLEINSTALLATION OF A CUSTOMER

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 161: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-14KEYED NOTES FOR CUSTOMER

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

OWNED SERVICE & METER POLE

Page 162: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-15

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

GENERAL NOTES FOR CUSTOMEROWNED SERVICE & METER POLE

Page 163: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-16CABLE TERMINATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

ELECTRICAL NOTES:

Page 164: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-17FUSED DISTRIBUTION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

CABLE POLE RISER

1413

12

14

11

8

6

21 22

19

C1

1 A1

7 15

16

20

2

3

4

6

19

1

5

9

10

116

C2

8

17

16

11

23

Page 165: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

A1

SKE-18MATERIAL LIST FOR FUSED

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

DISTRIBUTION CABLE POLE RISER

Page 166: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-1914.4kV SCADA-MATE

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

SECTIONALIZING SWITCH

1

2

3

4

5

Page 167: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-20120/240V, SINGLE PHASE

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

TRANSFORMER

12

10

1314

A2

A1

C5

3

17

13

62

C3

9

C1

C5

C7

13

11

4C4

C6

C2

8

15

Page 168: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

1

2

3

4

5

6

7

8

9

10

11

12

13

14

C1

C2

C3

C4

C5

C6

C7

A1

A2

15

SKE-21MATERIAL LIST FOR 120/240V,

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

SINGLE PHASE TRANSFORMER

Page 169: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

FOR 5kV-35kV FEEDERSTYPICAL DUCT BANK

SKE-22FOR 5kV-35kV FEEDERSTYPICAL DUCT BANK

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 170: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

FOR 600V FEEDERSTYPICAL DUCT BANK

SKE-23FOR 600 VOLT FEEDERSTYPICAL DUCT BANK

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 171: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

NOTES:

SKE-24VEHICULAR TRAFFIC AREASTYPICAL DUCTBANK INSTALLATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 172: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-25HANDHOLE DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

SECTION

BASESECTION

TOP RING

Page 173: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-26TYPICAL PRECAST

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

CONCRETE SPLICE BOX

Page 174: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-27GRADE MOUNTED

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

JUNCTION / PULLBOX

Page 175: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-28CABLE TAG DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 176: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-29PRECAST PAD

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

PLAN

Page 177: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-30LAYOUTTYPICAL GROUND ROD

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 178: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-31TYPICAL FENCE DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

FOR (NON-SUBSTATION) ELEC. EQPT.

X X X X X X X X X X

X X X X X X X X X X

X X X X X X X X X X

X X X X X X X X

X X X X X X X

X X X X X X X

X

X

X

XX

X XXX

X X

X X X

X X X

X X X

XX

X

NOTE:

Page 179: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

ANGLE TYPE

SKE-32SEISMIC RESTRAINT DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

ANGLE TYPE

Page 180: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

FLAT CLIP TYPE

SKE-33SEISMIC RESTRAINT DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

FLAT CLIP TYPE

Page 181: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

THREE PHASE PAD MOUNTED TRANSFORMER

SKE-34THREE PHASE PAD MOUNTED XFRMR.ELEVATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 182: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

ELECTRICAL LEGEND FOR THREE PHASE TRANSFORMER:

SKE-35THREE PHASE PAD MOUNTED XFRMR.LEGEND FOR

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 183: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SINGLE PHASE PAD MOUNTED TRANSFORMER

SKE-36SINGLE PHASE PAD MOUNTED XFRMR.ELEVATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 184: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

ELECTRICAL LEGEND FOR SINGLE PHASE TRANSFORMER:

SKE-37SINGLE PHASE PAD MOUNTED XFRMR.LEGEND FOR

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 185: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-38ELBOW CONNECTOR200A-15kV LOADBREAK

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

ELECTRICAL NOTES:

Page 186: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-39JUNCTION CONNECTOR200A-15kV LOADBREAK

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

ELECTRICAL NOTES:

Page 187: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-40JUNCTION INSTALLATION

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

REINFORCEMENT

INSTALLATION

NOTE:

TOP SECTION W/TRAFFIC COVER

MIDDLESECTION

BOTTOMSECTION

PULLINGEYE

SUMP PUMPRECESS

Page 188: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-41SEALING DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 189: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-4215kV SPLICEMEDIUM VOLTAGE

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

NOTE:

Page 190: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-43CABLE SPLICETYPICAL 600V

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 191: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

PAD MOUNTED TRANSFORMER

SKE-44kWH-DEMAND METERLOCATION FOR MOUNTING

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 192: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

CURRENT SENSOR

E.

D.

C.

B.

NEUTRAL

KNIFE SWITCH:

TEST PLUG RECEPTACLE:

TEST PLUG RECEPTACLE:

A.

NOTE:

3

1

2

21

CONTACTS:

LOAD

3

BLOCKTEST-BYPASS

3 PH 4W

LINE VOLT

3

3LINE

METER TERM. BLOCK

SKE-45DEMAND METERDIGITAL KILOWATT HOUR-

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 193: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

KILOWATT HOUR - DEMAND METER BOX

SKE-46METER BOXDETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 194: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

120 VOLT SINGLE-PHASE, 2-WIRE CIRCUIT

SKE-47120V 4-JAW METER SOCKET

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 195: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

120/240 VOLT SINGLE-PHASE, 3-WIRE CIRCUIT

SKE-48120/240V 4-JAW METER SOCKET

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 196: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

WIREWAY PULL SECTION

HINGED DEMAND RESET COVERW/ POLYCARBONATE VIEWING WINDOW

FRONT VIEW SIDE VIEW

SKE-49POWER METERING CABINETTELECOMMUNICATIONS

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 197: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-50DISTRIBUTION GUTTER DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 198: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-51MOUNTING DETAILDISCONNECT SWITCH

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 199: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-52SWITCH MOUNTING DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 200: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-53PANEL INSTALLATION DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 201: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-54TYPICAL LIGHT POLE DETAIL

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

Page 202: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

SKE-55TYPICAL WEATHERPROOF COVER

MAGTFTC- MCAGCC TWENTYNINE PALMS, CALIFORNIAA-E DESIGN MANUAL

N.T.S.

TOP VIEW SIDE VIEW

END VIEW

Page 203: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 203

APPENDIX B - REFERENCES

Page 204: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 204

27. APPENDIX B - REFERENCES

Designs shall include and comply with the latest edition of the following references:

All United Facilities Criteria (UFC’s) including but not limited to:

UFC 1-200-01: General Building Requirements

UFC 1-200-02: High Performance and Sustainable Building Requirements

UFC 1-201-01: Non-Permanent DoD Facilities in Support of Military Operations

UFC 1-300-07A: Design Build Technical Requirements

UFC 1-300-08: Criteria for Transfer and Acceptance of DoD Real Property Handbook

UFC 1-300-09N: Design Procedures

UFC 1-900-01: Selection of Methods for the Reduction, Reuse, and Recycling of Demolition Waste

UFC 3-101-01: Architecture

UFC 3-120-10: Interior Design

UFC 2-201-02: Landscape Architecture

UFC 3-210-01A: Area Planning, Site Planning, and Design

UFC 3-210-06A: Site Planning and Design

UFC 3-220-01: Geotechnical Engineering

UFC 3-230-01: Water Storage, Distribution, and Transmission

UFC 3-230-03: Water Treatment

UFC 3-240-01: Wastewater Collection

UFC 3-240-02: Domestic Wastewater Treatment

UFC 3-250-01FA Pavement Design for Roads, Streets, Walks, and Open Storage Areas

UFC 3-301-01: Structural Engineering

UFC 3-310-04: Seismic Design for Buildings

UFC 3-400-10N: Mechanical Engineering

UFC 3-410-01FA: Heating Ventilation, and Air Conditioning

UFC 3-410-02: Lonworks (R) Direct Digital Control for HVAC and Other Local Building Systems

UFC 3-420-01: Plumbing Systems

Page 205: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 205

UFC 3-501-01: Electrical Engineering

UFC 3-520-01: Interior Electrical Systems

UFC 3-530-01: Design: Interior and Exterior Lighting and Controls

UFC 3-550-01: Exterior Electrical Power Distribution

UFC 3-560-01: Electrical Safety, O&M

UFC 3-570-02A: Cathodic Protection

UFC 3-570-02N: Electrical Engineering Cathodic Protection

UFC 3-570-06: O&M: Cathodic Protection Systems

UFC 3-600-01: Fire Protection Engineering for Facilities

UFC 4-010-01: DoD Minimum Antiterrorism Standards For Buildings

UFC 4-010-02: DoD Minimum Antiterrorism Standoff Distances for Buildings (FOUO)

UFC 4-021-01: Design and O&M: Mass Notification Systems

International Building Code

California Standards Building Code

NAVMED P-5010

ANZI Z359 Fall Protection

MCAGCC Dig Permit Procedures

Safe Drinking Water Act

National Fire Protection Association Codes and Standards:

NFPA 1, Fire Prevention Code

NFPA 10, Standard on Portable Fire Extinguishers

NFPA 13, Standard for the Installation of Sprinkler Systems

NFPA 24, Installation of Private Fire Service Mains and Their Appurtenances

NFPA 54, National Fuel Gas Code

NFPA 58, Liquefied Petroleum Gas Code

NFPA 70, National Electric Code

NFPA 72, Standard on Fire Alarm Systems

NFPA 90A, Standard for the Installation of Air-Conditioning and Ventilation Systems

NFPA 101, Life Safety Code

NFPA 110, Emergency Power Systems

Page 206: A-E DESIGN MANUALdlfci.com/8a/NAVFAC BOA/16012 - Renovate Restrooms...1.5. FIRE AND LIFE SAFETY DATA 1.5.1. The life safety plan, fire alarm system, and fire suppression system plans

MAGTFTC-MCAGCC, 29 PALMS 206

NFPA 1221, Communications, Emergency Services

National Electrical Safety Code (NESC); ANSI –C2

California Energy Commission Energy Efficiency Standards

General Orders No. 95/128 State of California Public Utilities Commission

Energy Policy Act (EPAct)

Energy Independence and Security Act (EISA)

Explosive Safety Technical Manuals

Federal Leadership in High Performance and Sustainable Building MOU

City of Twentynine Palms Development Code, Chapter 19.70 Lighting Standards (Night Sky Ordinance)

Illuminating Engineering Society Standards – IESNA Lighting Handbook

Marine Corps Physical Security Program Manual – MCO 5530.14A

PV Installation Guide

CCFD “Solar Photovoltaic Construction Guidelines”

CCO 2010.1 “Marine Air Ground Task Force Training Command (MAGTFTC), Marine Corps Air Ground Combat Center (MCAGCC) Telecommunications Design Standards”

United Facilities Guide Specifications (UFGS)

California Food Code

Code of Federal Regulations (CFR)

Corp of Engineers (COE) – 2008 Consolidated EM-385-1-1: Safety and Health Requirements Manual (including Errata and changes)

American Water Works Association Manual M31: Distribution System Requirements for Fire Protection

For the requirement for justification to use brand names in plans or specifications, see FAR 5.102(a)(6).

For the format for brand name justification documentation, see FAR 6.302-2.