Upload
in-jae-jeong
View
217
Download
4
Embed Size (px)
Citation preview
Int. J. Production Economics 131 (2011) 561–567
Contents lists available at ScienceDirect
Int. J. Production Economics
0925-52
doi:10.1
n Tel.:
E-m
journal homepage: www.elsevier.com/locate/ijpe
A dynamic model for the optimization of decoupling pointand production planning in a supply chain
In-Jae Jeong n
Department of Industrial Engineering, Hanyang University, 17 Haengdang-dong, Seongdong-gu, Seoul 133-791, Republic of Korea
a r t i c l e i n f o
Article history:
Received 22 February 2010
Accepted 21 January 2011Available online 18 February 2011
Keywords:
Optimal control theory
Production smoothing
Zero-inventory
Forecast error
73/$ - see front matter & 2011 Elsevier B.V. A
016/j.ijpe.2011.02.001
+82 2 2220 0412.
ail address: [email protected]
a b s t r a c t
In this paper, we propose a dynamic model to simultaneously determine the optimal position of
the decoupling point and production–inventory plan in a supply chain such that the total cost of the
deviation from the target production rate and the target inventory level is minimized. Using the
optimal control theory, we derive the closed form of the optimal solution when the production
smoothing policy and the zero-inventory policy are applied. The result indicates that under the
production smoothing policy, the overestimation of demand rate during the pre-decoupling stage
guarantees the existence of the optimal decoupling point; meanwhile the optimal decoupling point
exists under zero-inventory policy when the demand rate is underestimated. Also we perform
mathematical analysis on the behavior of the optimal production rate and the inventory level and
the effect of problem parameters such as the length of the product life cycle and the forecast error on
the performance.
& 2011 Elsevier B.V. All rights reserved.
1. Introduction
A decoupling point is a push–pull boundary in the supplychain. From the upstream of the supply chain (i.e., the rawmaterial supplier) to the decoupling point, the supply chain planis scheduled based on the demand forecast which is a pushstrategy; meanwhile, from the decoupling point to the down-stream of the supply chain (i.e., the end customer), the supplychain operations are driven by the customer orders rather thanforecasts which is a pull strategy. In terms of the product deliverystrategy, it is also known as a make-to-stock (MTS) (a make-to-order (MTO)) strategy in the push (pull) range of the supply chain.The appropriate positioning of the decoupling point is an impor-tant design issue in the realm of the supply chain management.As shown in Fig. 1, the candidate positions of the decoupling pointexist on any stage of the supply chain.
As Olhager (2003) mentioned, there are many reasons andeffects of shifting the decoupling point forward or backward tothe end customers. For example, if the decoupling point movesbackward to the customers, the response time to customer isincreased and the manufacturing efficiency improves; meanwhilethe forward shifting will cause the increase of WIP and thereduction in the product customization. The advantages of theforward shifting are the disadvantages of the backward shifting ofthe decoupling point and vice versa.
ll rights reserved.
There exist two different approaches in determining theposition of the decoupling point, strategic approaches and analy-tic approaches. The strategic approaches intend to provide guide-lines using knowledge-based systems or conceptual models forselecting decoupling point. The analytic approaches use mathe-matical models or simulation models to find an optimal positionof the decoupling point. Most of the mathematical model-basedapproaches tried to minimize the manufacturing related costssubject to satisfy the certain level of customer response time.
Most of the previous mathematical models assume that thedecoupling point is the unique decision variable. However theproduction planning, inventory policy and operational decisionssuch as scheduling and sequencing also affect to the performanceof the supply chain. It is obvious that the supply chain can beoptimized if all these issues can be handled simultaneously if theproblem complexity is not considered. In addition, previousmodels analyze either a static or steady state equilibrium ofsupply chains considering the minimization of average cost withthe infinite planning horizon. However, the nature of the problemis dynamic and the planning horizon is finite. The consideringproblem is dynamic since the true demand is realized in the post-decoupling point, thus the operations (e.g., production rate orinventory level) may be adjusted using the available demandinformation. Today it is widely accepted that the product marketundergo a life cycle of introduction, growth, maturity and even-tual decline not entering toward a stationary state. Therefore theassumption of the finite planning horizon is more realistic in realworld scenario.
In this paper, we consider a problem of determining theposition of the decoupling point and the production planning
Fig. 1. Candidate positions of a decoupling point.
I.-J. Jeong / Int. J. Production Economics 131 (2011) 561–567562
and inventory strategy simultaneously under different planningpolicies. The proposed model is a continuous and dynamic modelsuch that the objective function is the minimization of the totalcost of the deviation from the target production rate and thetarget inventory level. The optimal position of the decouplingpoint, the optimal path of the production rate and the inventorylevel are the decision variables. The problem is solved usingoptimal control theory. Also we will examine the effect of theaccuracy of the forecasting error in pre-decoupling point, theeffect of the assumption of the finite planning horizon and thesensitivity analysis of the problem parameters.
The paper is organized as follows: Section 2 reviews therelevant literature. In Section 3, we describe the consideringproblem and propose dynamic models. The closed form ofoptimal solutions are presented when target parameters are givenin Section 4. We present some theoretical results for the produc-tion smoothing policy in Section 5. Section 6 represents results forthe zero-inventory policy. Finally some concluding remarks aregiven in Section 7.
2. Literature survey
For strategic positioning of a decoupling point, Olhager (2003)proposed a P/D (production lead time/delivery lead time) ratioand the relative demand volatility. MTO corresponds to a P/D ratiothat is less than one and MTS is a viable option for low relativedemand volatility. For low relative demand volatility, we mayemploy an MTS policy for the economies of scale even in therange of P/Do1. Naylor et al. (1999) combined the lean thinkingand agile manufacturing paradigms with the positioning of thedecoupling point. Authors insisted that the lean paradigm (agileparadigm) can be applied to the pre-decoupling point (post-decoupling point). Kundu et al. (2008) proposed a knowledge-based approach in determining the position of the decouplingpoint. They considered the tradeoff between the physical effi-ciency of the supply chain and the market responsiveness. Theresearch suggested that as the order volume and the product lifecycle increase and the unit transportation cost decreases, thedecoupling point must be shifted backward to the upstream. VanDonk (2001) proposed a guideline for choosing the position of thedecoupling point for food processing industries.
Yanez et al. (2009) proposed a simulation platform built on anagent-based planning system in order to determine an appro-priate position of the decoupling point in the timber industry. Theperformances of the different decoupling points are measuredusing the daily average inventory WIP and the weighted fill rateof demands. Jammernegg and Reiner (2007) considered thetradeoff between the inventory reduction and the increase inorder fulfillment cycle time. They studied a three-stage suppliernetwork using a stochastic simulation. Another type of simulationis based on generalized stochastic Petri nets by Viswanadham andRaghavan (2000). The objective of the Petri nets model is theminimization of the sum of inventory carrying cost and thedelayed delivery cost.
For the mathematical model-based approaches, Gupta andBenjaafar (2004) considered a model such that the objectivefunction is the minimization of the sum of inventory holding costand the product/process redesign cost subject to a service-levelconstraint. The problem is solved by the queuing theory. Sun et al.
(2008) considered the problem of positioning multiple decouplingpoints based on the bill of material of a product in a supplynetwork. They proposed a mathematical model with the mini-mization of supply chain cost which is the sum of the setup,inventory, stock-out and asset specificity cost subject to thedelivery time constraint required by the customer. The model is0–1 integer programming which can be solved by a commercialsoftware package.
Soman et al. (2004) pointed out that the decoupling pointdecision is closely related to the production planning, inventorypolicy and operational decisions. In a hybrid MTO–MTS system,important questions are as follows: the capacity allocation amongMTO and MTS products, the determination of the safety stock forMTS products, the order acceptance/rejection decision for MTOproducts and the scheduling and sequencing of products. How-ever the handling of the whole issues along with the problem ofthe positioning the decoupling point is very complex. Thus Somanet al. (2004) proposed a hierarchical planning framework for foodproduction system.
In this paper, we attack the problem of the determining theposition of the decoupling point, the production planning andinventory strategy simultaneously. It is also seen that the pro-posed solution is based on the mathematical model that can beoptimally solved using the optimal control theory. In addition, weaddress the issue of the effect of the forecasting error and thelength of product life cycle on the performance measure.
3. Problem description
Notations:
T decoupling point in a supply chainP0 estimated demand rate (i.e., production rate) during the
pre-decoupling pointP(t) production rate at time t during the post-
decoupling pointT0 length of product life cycleF(t) cumulative customer demands at time t where F(T0)¼N
D(t)¼F0(t) demand rate at time t
O constant target production rate during post-decoupling point
I(t) inventory level at time t during post-decoupling pointy constant target inventory level during post-
decoupling pointK constant cost per unit deviation from target
production rateh constant cost per unit deviation from target
inventory level
Consider time t over a finite product life cycle of a singleproduct. At t¼0, the production planner estimates the demandrate of the product, P0. The production starts with the productionrate P(t)¼P0 from the raw material procurement at t¼0 to thedecoupling point at t¼T. At the decoupling point, the truedemand rate D(t) is realized during the product life cycle fromtime t¼T to T+T0. When the production during the pre-decou-pling point is finished, the inventory level would be I(L)¼P0T
where L is the throughput time of the supply chain.
Fig. 2. Inventory level for production smoothing policy.
Fig. 3. Inventory level for zero-inventory policy.
I.-J. Jeong / Int. J. Production Economics 131 (2011) 561–567 563
Without loss of generosity, we can shift the time axis so thatt¼L becomes t¼0. Then the problem transforms to the optimiza-tion during the planning horizon, tA[0,T0] with the initial inven-tory condition, I(0)¼P0T.
The objective of this paper is to provide appropriate produc-tion plan so that it can balance between the frequent change ofproduction rate and the inventory holding cost for the giventarget production rate and the target inventory level. We canclassify the inventory management into two classes, the mini-mizing inventory cost and the maintaining inventory level. If weconsider a time-varying demand, we may develop a precisemathematical model in determining the exact inventory level atany time. Thus in this model, it would be appropriate to considerminimizing inventory cost (e.g., inventory holding cost and back-log cost) even though we have a complicated model. However theexact total inventory (i.e., the integration of inventory levelduring a certain period of time) may not be calculated in a closedform for a general function of inventory level. In this case, we mayachieve the minimization of inventory cost via an indirectapproach. That is, the maintaining of the target inventory levelcan be regarded as the minimization of inventory cost.
The general dynamic model (GEN) can be described as follows:
GENmin
Z T0
0fK PðtÞ�Oð Þ
2þh IðtÞ�yð Þ
2g dt
st: _IðtÞ ¼ PðtÞ�FuðtÞ
The objective of the model is to determine the production rateP(t) such that the deviation from the target production rate O, i.e.,K(P(t)�O)2 is minimized. Also the deviation of the inventory levelI(t) from the target inventory level, y, i.e., h(I(t)�y)2 must beminimized. The objective function is widely used quadraticobjective function of Holt et al. (1960) called HMMS model. Theconstraint implies that the inventory rate is equal to the produc-tion rate minus demand rate. For the proposed GEN model, wehave two main issues, the determination of the target productionrate and the target inventory level and the product life cyclerepresented as F(t).
3.1. Target settings
An important issue in the proposed GEN model is the deter-mination of the target production rate and the target inventorylevel which are highly dependent on the planning policy. Fig. 2shows the cumulative production quantity under the productionsmoothing policy. As shown in the figure, the production smooth-ing policy tries to keep the constant rate of production. Thesmoothed production rate may cause unnecessary inventoryand shortage if the target production rate is not appropriatelydetermined.
Fig. 3 shows the production plan and the inventory level of thezero-inventory policy. The zero-inventory policy is one of themost important philosophies in Toyota Production System (TPS)along with the Just In Time (JIT) production. In order not to incurunnecessary inventory, the production does not start until theinitial inventory is exhausted which was produced during thepre-decoupling stage. When the inventory level drops to zero, theproduction rate follows the exact form of the demand rate whichwill cause no inventory. However, the zero-inventory will causethe continuous changes of production rate in order to meetthe exact customer demands which may be technologicallyimpossible.
One possible setting of the target production rate and thetarget inventory level for production smoothing policy is asfollows:
O¼ P0 and y40 ð1Þ
Since the initial forecast of the demand rate is P0, keeping theinitial production rate during the product life cycle is importantfor the production smoothing policy. Under the productionsmoothing policy, we need safety stocks (i.e., y40) in order toprevent the shortage due to the lack of production if the demandis underestimated.
Another possible setting for zero-inventory policy is as fol-lows:
O¼ FuðtÞ and y¼ 0 ð2Þ
The ideal production rate is the demand rate so that it cannotproduce unnecessary inventory. The target inventory level couldbe zero which is the ideal inventory level.
3.2. Product life cycle
The following is the logistic model which is widely used for thedescription of a product life cycle:
FðtÞ ¼a
ð1þae�btÞþb ð3Þ
where a and b are parameters. a and b are constants such thatF(0)¼0 and F(T0)¼N are satisfied. However it is not easy to solvethe GEN model with the logistic function as a product life cycle.It is relatively easy to plan production in traditional staticinventory problems with a constant demand for example, EOQtype problems. However, in some cases, it is still difficult to solve
I.-J. Jeong / Int. J. Production Economics 131 (2011) 561–567564
the problem even with a constant demand. One example is SingleWarehouse Multiple Retailer (SWMR) problem. Even though thedemand is constant, most studies have restricted their attentionto stationary and nested policies (Schwarz and Schrage, 1975,Graves and Schwarz, 1977; Maxwell and Muckstadt, 1985). Undera stationary and nested policy, the inventory level can be clarifiedand the optimization procedure can be applied.
Also we have the same difficulty in clarifying the inventorylevel when we deal with a dynamic problem. The derivation of theoptimal time path of the production plan and the inventory levelare not easy tasks in a dynamic model even if we have a constantdemand.
Therefore we consider a special model of GEN (SPC) withconstant demand as follows:
SPCmin
Z T0
0fK PðtÞ�Oð Þ
2þh IðtÞ�yð Þ
2gdt
st: _IðtÞ ¼ PðtÞ�D
In this model, we assume the demand rate is constant that isF(t)¼Dt such that F0(t)¼D(t)¼D. For the proposed model, SPC,we can apply optimal control theory. In addition, the SPC modelcan be used as a building block to solve GEN model. The logisticmodel of F(t) can be linearly approximated with constant demandrates for the separate ranges of introduction, growth, maturityand decline stages of the product life cycle.
The proposed model is a dynamic since the decision variablesare the optimal time paths of the production rate and theinventory level. The model assumes that the position of thedecoupling point is a continuous variable. There exist couples ofpapers dealing with the application of dynamic optimization tothe production–inventory models. Choi and Hwang (1986) stu-died the quadratic penalty between the actual production rate-inventory level and target production rate-inventory level for thedecaying item. Khemlnitsky and Gerchak (2002) considered theinventory holding cost, the shortage cost and the production costfor inventory-dependent demands. Benhadid et al. (2008)extended the quadratic penalty of production and inventory to atime-varying penalty costs.
4. Optimal solution for SPC model for given target parameters
In this section, we derive the optimal time path of theproduction rate, inventory level and the optimal position of thedecoupling point in closed forms for SPC model when the targetproduction rate and the target inventory level are given.
Using Pontryagin’s maximum principle of the optimal controltheory, the optimality condition for the inventory level (i.e., astate variable) is as follows:
_lðtÞ ¼ 2h IðtÞ�yð Þ ð4Þ
The optimality condition for the production rate (i.e., a controlvariable) is as follows:
lðtÞ ¼ 2KðPðtÞ�OÞ ð5Þ
The first derivative of (5) on l(t) is
_lðtÞ ¼ 2K _PðtÞ ð6Þ
From Eqs. (4) and (6),
IðtÞ ¼K
h_PðtÞþy ð7Þ
The first derivative of (7) on t is
_IðtÞ ¼K
h€PðtÞ ð8Þ
From the constraint of the model and (8),
K
h€PðtÞ ¼ PðtÞ�D ð9Þ
By solving the second order differential Eq. (9), the generalsolution of the production path can be found as follows:
PðtÞ ¼ c1effiffiffiffiffiffiffiffiffiðh=KÞp
tþc2e�ffiffiffiffiffiffiffiffiffiðh=KÞp
tþD ð10Þ
From (7), the inventory level can be determined as follows:
IðtÞ ¼
ffiffiffiffiK
h
rc1e
ffiffiffiffiffiffiffiffiffiðh=KÞp
t�c2e�ffiffiffiffiffiffiffiffiffiðh=KÞp
t� �
þy ð11Þ
The boundary conditions are as follows:
Pð0Þ ¼ P0 ð12Þ
Ið0Þ ¼ P0T ð13Þ
Eq. (12) means that the planning horizon start with the produc-tion rate with the forecasted demand rate P0. Eq. (13) implies thatthe initial inventory level at the beginning of planning horizon isequal to the production quantity at the decoupling point T withthe estimated demand rate P0.
Replacing (12) and (13) with (10) and (11), we obtain thefollowing equations:
c1þc2 ¼ P0�D ð14Þ
ffiffiffiffiK
h
rc1�c2ð Þ ¼ P0T�y ð15Þ
By solving Eqs. (14) and (15), we can calculate c1 and c2 asfollows:
c1 ¼1
2P0�D�y
ffiffiffiffiK
h
r !þ
1
2
ffiffiffiffiK
h
rP0T ð16Þ
c2 ¼1
2P0�Dþy
ffiffiffiffiK
h
r !�
1
2
ffiffiffiffiK
h
rP0T ð17Þ
Let a1 ¼ ð1=2ÞðP0�D�yffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
pÞ, a2 ¼ ð1=2ÞðP0�Dþy
ffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
pÞ
and b¼ ð1=2ÞffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
pP0 then the optimal production path and
inventory level are as follows:
PðtÞ ¼ a1þbTð Þeffiffiffiffiffiffiffiffiffiðh=KÞp
tþ a2�bTð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
tþD ð18Þ
IðtÞ ¼
ffiffiffiffiK
h
ra1þbTð Þe
ffiffiffiffiffiffiffiffiffiðh=KÞp
t� a2�bTð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
t� �
þy ð19Þ
Let f be the objective function value of SPC model then f can beformalized as follows:
f ¼ K
Z T0
0ða1þbTÞe
ffiffiffiffiffiffiffiffiffiðh=KÞp
tþða2�bTÞe�ffiffiffiffiffiffiffiffiffiðh=KÞp
t�ðO�DÞ� �2�
þ ða1þbTÞeffiffiffiffiffiffiffiffiffiðh=KÞp
t� a2�bTð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
t� �2
�dt
¼ K
ffiffiffiffiK
h
rða1þbTÞ2 e2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�1� �
�ða2�bTÞ2 e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�1� �n
þðO�DÞ2T0 �2ðO�DÞða1þbTÞ effiffiffiffiffiffiffiffiffiðh=KÞp
T0�1� �
þ2ðO�DÞða2�bTÞ e�ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�1� �o
ð20Þ
The optimal decoupling point can be found using the firstderivative of (20) on T as follows:
@f
@T¼ 2
ffiffiffiffiffiffiKhp
b a1e2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0þa2e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �nþb e2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �T
�ðO�DÞ effiffiffiffiffiffiffiffiffiðh=KÞp
T0þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�2� �
�ða1þa2Þ
o
I.-J. Jeong / Int. J. Production Economics 131 (2011) 561–567 565
T� ¼ðO�DÞ e
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�1� �
� a1e2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0þa2e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �n ob e2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �ð21Þ
Theorem 1. Tn satisfying (21) is global optimal if and only if h/Ka0.
Proof. The following inequality holds if and only if h/Ka0 sincethe planning horizon T0 is strict positive:
@2f
@T2¼ 2
ffiffiffiffiffiffiKhp
b2 e2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �40 &
4.1. Effect of the length of product life cycle, T0
In SPC model, we assume the finite length of product life cycle.For infinite length of product life cycle, the following theoremholds:
Theorem 2. When T0-N, the optimal Tn is as follows:
T� ¼y� P0�Dð Þ
ffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
p� �P0
ð22Þ
Proof. In Eq. (21), divide the numerator and the denominator bye2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0 then
T� ¼O�Dð Þ e�
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0þe�3ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �� a1þa2e�4
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �n ob 1�e�4
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �ð23Þ
Take T0-N in Eq. (23) then Tn¼(�a1/b) which is equivalent to
Eq. (22). &
Theorem 2 implies when T0-N, the optimal decoupling pointis determined without the consideration of the targetproduction rate.
5. Optimal solution for SPC model under the productionsmoothing policy
In this section, we derive optimal decoupling point andproduction plan of SPC under the production smoothing policy.
Under the production smoothing policy, O¼P0 and the produc-tion rate must be maintained equal to the target production rateduring the whole planning, that is P(t)¼P0. Thus the penalty term forthe deviation from the target production rate is eliminated from theSPC model and a new dynamic model can be developed as follows:
min
Z T0
0h IðtÞ�yð Þ
2 dt
st: _IðtÞ ¼ PðtÞ�D
Using the same logic through (4)–(13), the optimal inventorylevel can be determined as follows:
IðtÞ ¼ ðP0�DÞtþP0T ð24Þ
Then the objective function value is calculated as follows:
f ¼h
3 P0�Dð ÞP0�Dð ÞþP0T�yð Þ
3� P0T�yð Þ
3n o
The first derivate of f on T becomes
@f
@T¼ P0hT0 P0�Dð ÞT0þ2 P0T�yð Þ
� �The optimal the coupling point can be determined as follows:
T� ¼2y� P0�Dð ÞT0ð Þ
2P0ð25Þ
Theorem 3. Under the production smoothing policy, Tn satisfy-
ing (25) is global optimal if and only if P04D.
Proof. ð@2f=@T2Þ ¼ 2P0T0 P0�Dð Þ40 if and only if P04D. &
Theorem 3 implies that the condition of the existence of theoptimal decoupling point under the production smoothing policyis the overestimation of the demand rate, P0 during the pre-decoupling stage.
6. Optimal solution for SPC model under zero-inventorypolicy
In this section, we derive the optimal time path of theproduction rate, inventory level and the optimal position of thedecoupling point in closed forms under zero-inventory strategy,that is O¼F0(t)¼D and y¼0.
Theorem 4. Under the zero-inventory policy, Tn exists if and only if
P0oD.
Proof. Using (21), O¼F0(t)¼D and y¼0, the optimal decouplingpoint can be derived from (21) as follows:
T� ¼�ð1=2Þ P0�Dð Þ e2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0þe�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� �ffiffiffiKh
qP0 e2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� � & ð26Þ
Contrary to the implication of Theorem 3, Theorem 4 impliesthat the optimal decoupling point exists under zero-inventorypolicy when the demand rate is underestimated during the pre-decoupling stage that is P0oD.
6.1. Behavior of the optimal P(t) and I(t)
Using (21), O¼F0(t)¼D and y¼0, we can calculate (a1+bTn)and (a2�bTn) as follows:
a1þbT� ¼� P0�Dð Þe�2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
e2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� � ð27Þ
a2�bT� ¼P0�Dð Þe2
ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
e2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0�e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
T0
� � ð28Þ
The first and the second derivative of P(t) and I(t) for optimalTn in (21) can be calculated as follows:
@PðtÞ
@t
T ¼ T�
¼
ffiffiffiffih
K
ra1þbT�ð Þe
ffiffiffiffiffiffiffiffiffiðh=KÞp
t� a2�bT�ð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
tn o
ð29Þ
@2PðtÞ
@t2
T ¼ T�
¼h
Ka1þbT�ð Þe
ffiffiffiffiffiffiffiffiffiðh=KÞp
tþ a2�bT�ð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
tn o
ð30Þ
@IðtÞ
@t
T ¼ T�
¼ a1þbT�ð Þeffiffiffiffiffiffiffiffiffiðh=KÞp
tþ a2�bT�ð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
tn o
ð31Þ
@2IðtÞ
@t2
T ¼ T�
¼
ffiffiffiffih
K
ra1þbT�ð Þe
ffiffiffiffiffiffiffiffiffiðh=KÞp
t� a2�bT�ð Þe�ffiffiffiffiffiffiffiffiffiðh=KÞp
tn o
ð32Þ
Because of Theorem 4, P0oD. In this case, P(t) is an increasingfunction since (31) is strict positive and I(t) is a convex functionsince (32) is strict positive. These results imply if we under-estimate demand during the pre-decoupling point, then theoptimal production rate increases and the corresponding optimalinventory level forms a convex function during the post-decou-pling point.
Fig. 4. Effect of e on PI.
I.-J. Jeong / Int. J. Production Economics 131 (2011) 561–567566
6.2. Effect of the length of planning horizon, T0
For infinite length of the product life cycle under zero-inventory policy, the optimal decoupling point can be found fromthe Theorem 1 with y¼0 as follows:
T� ¼� P0�Dð Þ
ffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
pP0
ð33Þ
The results also imply that the optimal decoupling point existsunder zero-inventory policy when the demand rate is under-estimated during the pre-decoupling stage.
6.3. Effect of forecast error
For the infinite length of the product life cycle under zero-inventory policy, when we take T0-N for Eqs. (27) and (28),following equations hold:
a1þbT� ¼ 0 ð34Þ
a2�bT� ¼ P0�D ð35Þ
The optimal objective function value in equation (20) can bemodified as follows:
f ¼ K
Z 10
2 P0�Dð Þ2e�2
ffiffiffiffiffiffiffiffiffiðh=KÞp
t dt¼ �K
ffiffiffiffiK
h
rP0�Dð Þ
2e�2ffiffiffiffiffiffiffiffiffiðh=KÞp
t
" #10
¼ K
ffiffiffiffiK
h
rP0�Dð Þ
2ð36Þ
Since the optimal decoupling point exist when P0oD underzero-inventory policy, we say that the forecast error is a ifP0¼(1+a)D where �1rar0.
Theorem 5. For the infinite length of the product life cycle under
zero-inventory policy, if the forecast error is improved from a to a0where �1rara0r0 then the percent improvement of the objec-
tive function value is as follows:
a2�ðauÞ2
ðauÞ2
!� 100 ð37Þ
Proof. Let f(a) and f(a0) be the objective function value when theforecast error is a and a0, respectively. Then f ðaÞ ¼ K
ffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
pðaDÞ2
and f ðauÞ ¼ KffiffiffiffiffiffiffiffiffiffiffiffiðK=hÞ
pðauDÞ2 due to (36). Therefore the percent
improvement (PI) of the objective function value by the improvedforecast error is PI¼ ðf ðaÞ�f ðauÞÞ=ðf ðauÞÞ � 100¼ ðða2�ðauÞ2Þ=ðauÞ2Þ�100: &
Let a0 ¼ea where e�100(0rer1) is the PI of forecast errorfrom a. Fig. 4 shows the behavior of PI on e. The Figure impliesthat the reduction of forecast error exponentially improves theobjective function value of the model.
7. Conclusion
In this paper, we proposed a dynamic model to simultaneouslydetermine the optimal position of the decoupling point andproduction–inventory plan. We considered a special case ofconstant demand rate of a product life cycle. Using the optimalcontrol theory, we derived the closed form of the optimal solutionunder the production smoothing policy and the zero-inventorypolicy.
The analysis showed that under the production smoothingpolicy, the overestimation of demand rate guarantees the exis-tence of the optimal decoupling point; meanwhile the optimaldecoupling point exists under zero-inventory policy when thedemand rate is underestimated during the pre-decoupling stage.Also we performed analysis on the behavior of the optimalproduction rate and the inventory level and the effect of problemparameters such as the length of the product life cycle and theforecast error on the performance.
It is possible to extend the results of this research in severaldifferent directions. For instance, we can consider the applicationof logistic model to represent the product life cycle for GENproblem. In this case, we believe that a heuristic approach such asa linear approximation of the logistic model may be required.Another issue is the development of a tradeoff policy between theproduction smoothing policy and the zero-inventory policy forSPC problem. The determination of an appropriate target produc-tion rate and a target inventory level is an important issue.Finally, the inclusion of more realistic assumption is necessarysuch as the time-varying penalty costs and the delivery lead timeto customer.
References
Benhadid, Y., Tadj, L., Bounkhel, M., 2008. Optimal control of production inventorysystems with deteriorating items and dynamic costs. Applied MathematicsE—Notes 8, 194–202.
Choi, S.-B., Hwang, H., 1986. Dynamic optimization of production planningproblem with periodic operation. International Journal of Systems Science17, 1163–1174.
Graves, Stephen C., Schwarz, L.B., 1977. Single cycle continuous review policies forarborescent production/inventory system. Management Science 23, 529–540.
Gupta, D., Benjaafar, S., 2004. Make-to-order, make-to-stock, or delay productdifferentiation? A common framework for modeling and analysis. IIE Transac-tions 36, 529–546.
Holt, C.C., Modigliani, F., Muth, J.F., Simon, H.A., 1960. Planning Production,Inventories, and Work Force. Prentice-Hall, Englewood Cliffs.
Jammernegg, W., Reiner, G., 2007. Performance improvement of supply chainprocesses by coordinated inventory and capacity management. InternationalJournal of Production Economics 108, 183–190.
Khemlnitsky, E., Gerchak, Y., 2002. Optimal control approach to productionsystems with inventory-level-dependent demand. IEEE Transactions on Auto-matic Control 47, 289–292.
Kundu, S., McKay, A., Pennington, A., 2008. Selection of decoupling points insupply chains using a knowledge-based approach. Proceedings of the
I.-J. Jeong / Int. J. Production Economics 131 (2011) 561–567 567
Institution of Mechanical Engineering Part B: Journal of Engineering Manu-facture 222, 1529–1549.
Maxwell, William L., Muckstadt, John A., 1985. Establishing consistent and realisticreorder intervals in production–distribution systems. Operations Research 33,1316–1341.
Naylor, J.B., Naim, M., Berry, D., 1999. Leagility: integrating the lean and agilemanufacturing paradigms in the total supply chain. International Journal ofProduction Economics 62, 107–118.
Olhager, J., 2003. Strategic positioning of the order penetration point. InternationalJournal of Production Economics 85, 319–329.
Schwarz, L.B., Schrage, L., 1975. Optimal and system myopic policies for multi-echelon production/inventory assembly systems. Management Science 21,1285–1294.
Sun, X.Y., Ji, P., Sun, L.Y., Wang, Y.L., 2008. Positioning multiple decoupling points in asupply network. International Journal of Production Economics 113, 943–956.
Soman, C.A., Van Donk, D.P., Gaalman, G., 2004. Combined make-to-order andmake-to-stock in a food production system. International Journal of Produc-tion Economics 90, 223–235.
Van Donk, D.P., 2001. Make to stock or make to order: the decoupling point in the foodprocessing industries. International Journal of Production Economics 69, 297–306.
Viswanadham, N., Raghavan, N.S., 2000. Performance analysis and design of supplychains: a Petri net approach. Journal of the Operational Research Society 51,1158–1169.
Yanez, F.C., Frayret, J.M., Leger, F., Rousseau, A., 2009. Agent-based simulation andanalysis of demand-driven production strategies in the timber industry.International Journal of Production Research 47, 6295–6319.