Leading the way in sustainable infrastructure:
A Case Study
Surrey Biofuel Processing Facility
Contents
• Background
• Procurement
• Lessons learned
• Takeaways
3
September 15, 2015
Where did the Project start?
• Metro Vancouver targets
• Rethink Waste strategy
4
September 15, 2015
At least 70%
diversion by 2015.
Rethink Waste - The Green Bin
5
September 15, 2015
Project Objectives
• Diversion
• Sustainability
• State of the art facility
• Economic viability
6
September 15, 2015
Documenting the business rationale
7
September 15, 2015
8
September 15, 2015
The City’s vision – “the Closed Loop”
How was it procured?
• Request for Qualifications
• Request for Proposals
• Legal agreement
9
September 15, 2015
RFQ
• Technical capability
• Financial capacity and strength
• Proven technology
10
September 15, 2015
RFP
• Evaluation criteria – not just lowest cost
• Collaborative meetings to get robust bids
• Peak demand issues
11
September 15, 2015
Risk allocation
• Facility size
• Revenue sharing
• Performance regime
12
September 15, 2015
City success factors
• Resourcing
• Focus on end goal
• Allocate the risks wisely
13
September 15, 2015
Takeaways
• Learn from others mistakes
• Be flexible
• Small projects are deliverable
14
September 15, 2015
Thank you!
Catherine Peacock
Infrastructure & Project Finance
Tel: 604 806 7207Email: [email protected]