Page 1: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Quarterly Communications Meeting on the Long-Term Plan for Achieving Water Quality Goals for the

Everglades Protection Area Tributary Basins

February 2015

Alan Shirkey, P.E. Section Administrator Project Management

A-1 Flow Equalization Basin (FEB)

Page 2: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

A-1 FEB – Location and Existing Conditions

2

Page 3: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

3

G-722W Bypass Structure

EAA A1 Flow Equalization Basin Southeast viewing Northwest

Page 4: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

4

Page 5: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

A-1 FEB

• Design and Construction Schedule: • Preliminary Design – Completed • Intermediate Design Submittal – Completed • Final Design Submittal – Completed • Final Design TRB – Completed • Corrected Final/RTA Design Submittal – Completed • Governing Board – Completed • NTP – Completed • Substantial Completion – April 29, 2015 • Final Completion – June 29, 2015

5

Page 6: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Milestones

6

Milestone Compliance date Status

Initiate design 4/1/2012 Complete

Submit state and federal permits 12/1/2012 Complete

Design status report 3/1/2013 Complete

Complete design 8/1/2013 Complete

Initiate construction 6/30/2014 Complete

Construction status report 3/1/2015 Pending

Construction status report 3/1/2016 Pending

Completion of construction 7/30/2016 Pending

Initial flooding and optimization complete 7/29/2018 Pending

Page 7: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Quarterly Communications Meeting on the Long-Term Plan for Achieving Water Quality Goals for the

Everglades Protection Area Tributary Basins

L-8 Flow Equalization Basin February 2015

Alan Shirkey, P.E. Section Administrator Project Management

Page 8: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Project Location

8

Cell 6

Cell 7

Cell 3

Cells 1&2

Cell 4

Cell 5

Page 9: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

9

Cells 1/2,4,5: -27.0’ NAVD Cell 3: -33.9’ NAVD Cell 6, 7: -27.4’ NAVD

Page 10: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

10

Page 11: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

11

Page 12: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Design/Build Schedule

• Governing Board Approval Completed • NTP Completed • Preliminary Design (Revetment) Completed • Preliminary Design (Pump and Inflow) Completed • Final Design (Revetment) Completed • Final Design (Pump and Inflow) Completed • Revetment Construction – Roller Compacted Concrete

completed, installation of Sod continues • Substantial Completion April 18, 2015 • Final Completion October 15, 2015

12

Page 13: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Milestones

13

Milestone Compliance date Status

Submit state and federal permits 1/31/2014 Complete

Construction status report 3/1/2014 Complete

Construction status report 3/1/2015 Pending

Completion of construction 12/31/2016 Pending

Long term operations 12/31/2022 Pending

Page 14: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Quarterly Communications Meeting on the Long-Term Plan for Achieving Water Quality Goals for the

Everglades Protection Area Tributary Basins

February 2015

Alan Shirkey, P.E. Section Administrator Project Management

L-8 Divide Structure

Page 15: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

L-8 Divide Structure, G-541

L-8 Divide Structure

L-8 FEB Pump

Station

L-8 FEB Inflow

Structure

Page 16: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

L-8 Divide Structure, G-541

Page 17: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

17

Page 18: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

L-8 Divide Structure

18

•Design: Completed

•Construction Schedule:

•Notice to Proceed: October 15, 2014

•Project Substantial Completion: February 7, 2016

•Project Final Completion: April 7, 2016

•Construction activities:

•Bypass Channel – Completed

•Excavation of Subgrade – Completed

•Pre-drilling of Sheet Piles – Underway

Page 19: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Milestones

19

Milestone Compliance date Status

Initiate design 10/1/2012 Complete

Complete design 9/30/2014 Complete

Initiate construction 10/1/2016 Complete

Complete construction 9/30/2018 Pending

Page 20: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Quarterly Communications Meeting on the Long-Term Plan for Achieving Water Quality Goals for the

Everglades Protection Area Tributary Basins

February 2015

Alan Shirkey, P.E. Section Administrator Project Management

S-5AS Divide Structure

Page 21: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

S-5AS Divide Structure

S-5AS

Page 22: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

S-5AS Divide Structure

22

Page 23: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

S-5AS Divide Structure

23

Page 24: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

S-5AS Divide Structure

24

•Design and Construction Schedule:

• Comprehensive Fluid Dynamic Model: Complete

• Structure Stability Review: Complete

•Preliminary design due: Complete

•Final design package due: Complete

•Project out for Bid: Complete

•Governing Board Approval : Complete

•Notice to Proceed : Complete

•Project Substantial Completion : Feb 28, 2016

•Project Final Acceptance: April 28, 2016

Page 25: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

S-5AS Divide Structure Milestones

25

Milestone Compliance date Status

Initiate design 10/1/2012 Complete

Complete design 9/30/14 Complete

Initiate construction 10/1/14 Complete

Complete construction 9/30/16 Pending

Page 26: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Quarterly Communications Meeting on the Long-Term Plan for Achieving Water Quality Goals for the

Everglades Protection Area Tributary Basins

February 2015

Alan Shirkey, P.E. Section Administrator Project Management

G-716 Structure (S-375 Expansion)

Page 27: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

G-716 Structure

G-716

Page 28: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

G-716 Structure

28

Page 29: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

G-716 Structure

29

•Design and Construction Schedule:

• Structure Type Evaluation: Complete

• Structure Flow Calculations : Complete

•Preliminary design due: Complete

•Final design package due: June 30, 2015

•Project out for Bid: July 16, 2015

•Governing Board Approval: September 10, 2015

•Notice to Proceed: September 20, 2015

•Project Substantial Completion: April 1, 2017

•Project Final Acceptance: June 1, 2017

Page 30: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

G-716 Structure

30

Milestone Compliance date Status

Initiate design 9/30/2013 Complete

Complete design 7/30/2015 Pending

Initiate construction 1/31/2016 Pending

Complete construction 12/31/2018 Pending

Page 31: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Quarterly Communications Meeting on the Long-Term Plan for Achieving Water Quality Goals for the

Everglades Protection Area Tributary Basins

February 2015

Alan Shirkey, P.E. Section Administrator Project Management

STA 1W Expansion # 1

Page 32: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

STA 1W Expansion #1 – Location Map

32

Page 33: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

STA 1W Expansion #1

• Design and Construction Schedule: • Hydraulic Study – Complete • Preliminary Design Plan Set – Complete • Preliminary Design Full Submittal – Complete • Intermediate Design Submittal – April 17, 2015 • Final Design Submittal – June 12, 2015 • Final Design TRB – July 8, 2015 • Corrected Final/RTA Design Submittal – July 30, 2015 • Governing Board – October 8, 2015 • NTP – January 31, 2016 • Substantial Completion – September 30, 2018 • Final Completion – December 31, 2018 33

Page 34: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Milestones

34

Milestone Compliance date Status

Complete land acquisition 9/30/2013 Complete

Initiate design 9/30/2013 Complete

Submit state and federal permits 7/30/2014 Complete

Complete design 7/30/2015 Pending

Initiate construction 1/31/2016 Pending

Construction status report 3/1/2017 Pending

Construction status report 3/1/2018 Pending

Completion of construction 12/31/2018 Pending

Initial flooding and optimization complete 12/30/2020 Pending

Page 35: A-1 Flow Equalization Basin (FEB) · A-1 Flow Equalization Basin (FEB) A-1 FEB – Location and Existing Conditions 2 . 3 G-722W Bypass Structure EAA A1 Flow Equalization Basin

Exist. STA Improvements Independent Western Flow way

• Provide the Western Flow-way with an independent inflow source

• Construction of approx. 5,000 linear feet of levees and berms

• Use existing G-255 and G-303 Structures

• Final Design February 2015 • Proposed Project Completion July 2015