7793457 Project Management Presentation 2008

Embed Size (px)

Citation preview

  • 8/9/2019 7793457 Project Management Presentation 2008

    1/21

    Project Management

    GN Jayanthy

    [email protected]

  • 8/9/2019 7793457 Project Management Presentation 2008

    2/21

    What is a Project ?Perhaps the oldest form of organized activity

    Definition : A set of finite activities that

    is usually performed only once and has

    well defined objectives

  • 8/9/2019 7793457 Project Management Presentation 2008

    3/21

    Project Management Project Management: involves planning and

    controlling a project : its goal is to ensure that the

    project objectives are achieved on time and onbudget

    Objectives and trade offs : Cost , Schedule, and

    Performance : Managing projects often requires

    one to take decisions which involves trade off

    between these 3 parameters

  • 8/9/2019 7793457 Project Management Presentation 2008

    4/21

    Project failure Characteristics

    Cost Overrun

    Time overrun

    Fails to meet its performance objectives

  • 8/9/2019 7793457 Project Management Presentation 2008

    5/21

    Project Life cycle Phases &

    ProcessesA project can typically be divided in to several phases All

    these phase are collectively referred to as PLC. A projectlife cycle serves to define the start and end of a a project.

    Every phase could typically involve the followingprocesses

    1. Initiation

    2. Planning

    3. Execution

    4. Control5. Closure

  • 8/9/2019 7793457 Project Management Presentation 2008

    6/21

    Activities and Decisions in

    Project Management : Planning

    Scheduling

    Control

  • 8/9/2019 7793457 Project Management Presentation 2008

    7/21

    Planning Identify the project customers

    Establish the end product or service

    Set project objectives

    Estimate total resources and time required

    Decide on the form of organization

  • 8/9/2019 7793457 Project Management Presentation 2008

    8/21

    Planning Make key personnel appointments

    Define major tasks

    Establish a budget

  • 8/9/2019 7793457 Project Management Presentation 2008

    9/21

    Scheduling

    Develop a detailed Work Break down

    Structure (WBS)

    Estimate time required for each task

    Sequence the tasks in the correct order

  • 8/9/2019 7793457 Project Management Presentation 2008

    10/21

    Scheduling

    Develop a start /stop time for each task

    Develop a detailed budget for each task

    Assign people to tasks

  • 8/9/2019 7793457 Project Management Presentation 2008

    11/21

    Control Monitor actual time cost and performance

    Compare planned to actual figures

    Determine whether corrective action is

    needed

    Evaluate alternative corrective action

    Take appropriate corrective action

  • 8/9/2019 7793457 Project Management Presentation 2008

    12/21

    A work breakdown structure defines the

    hierarchy of project tasks, subtasks, and

    work package

    Program

    Project 1 Project 2

    Task 1.1

    Subtask 1.1.1

    Work Package 1.1.1.1

    Level

    1

    2

    3

    4

    Task 1.2

    Subtask 1.1.2

    Work Package 1.1.1.2

  • 8/9/2019 7793457 Project Management Presentation 2008

    13/21

    Scheduling Methods - Gantt

    ChartGantt Chart: Utilizes a bar or or milestone chart

    shows not only how much time is required for

    each activity but also when each activity takesplace.

    Advantages : Easy to use and understand

    Disadvantages : Do not show interdependencies

    and relationship between activities , difficult to

    schedule and reschedule for complex projects

  • 8/9/2019 7793457 Project Management Presentation 2008

    14/21

    Network Planning Techniques Network methods use a graph or a network

    to show precedence relations .

    Events , (nodes ) The start or end of an

    activity

    Activity : consume a finite amount of time

    Dummy activities : Consume 0 time

  • 8/9/2019 7793457 Project Management Presentation 2008

    15/21

    Network Planning Techniques Critical Path : represents The set of activities

    which would decide the minimum time required

    for completing the project. Slack( Free /total ) : the amount of time that the

    activity time con be increased without delaying the

    very start of the next activity

    Notations : Conventions used in drawing the

    network- Arrow on Node (AON ) , Arrow on

    Activity(AOA)

  • 8/9/2019 7793457 Project Management Presentation 2008

    16/21

    Critical Path Method (CPM) Constant time network: The time for each

    activity is assumed to be constant

    Deterministic time estimates

    Computations : Earliest Start Time ( EST),

    Earliest Finish Time ( EST), Latest Start

    Time (LST), Latest Finish Time ( EFT). ,Critical Path , slack

  • 8/9/2019 7793457 Project Management Presentation 2008

    17/21

    Program Evaluation and Review Technique

    (PERT)

    y Based on Probabilistic time estimates :

    Optimistic Time Estimate, Pessimistic

    Time Estimate, Most likely Time Estimate,

    Most probable Time Estimate,

    Computations : Expected time of

    completion , Variance on the expected timeof completion

  • 8/9/2019 7793457 Project Management Presentation 2008

    18/21

    CPM Time-

    Cost trade off Assumes that Cost and Time are inversely

    related and hence project completion time

    can be reduced by incurring higher costs .

    Terms : Crash Cost , Crash Time , Normal

    Time , Normal Cost

    Computations : Least cost way to reducethe normal project completion time

  • 8/9/2019 7793457 Project Management Presentation 2008

    19/21

    Alternate Techniques for Project

    scheduling y Critical Chain Method - Based on

    Theory of Constraints

    y Precedence Diagramming Method (PDM)

  • 8/9/2019 7793457 Project Management Presentation 2008

    20/21

  • 8/9/2019 7793457 Project Management Presentation 2008

    21/21