98
SFUND RECORDS CTR 75406 CASMALIA SITE REMEDIATION PROJECT Corey Bertdsen Project Manager January 18,2000 To: DanNHes-RWQCB Subject: Sampling and Analysis Plan for Compliance Monitoring NPDES Permit no. 99-034 On behalf of the Casmalia Steering Committee (CSC), I have attached a proposed Sampling and Analysis Plan (SAP) for compiiance monitoring pursuant to Permit No. 99-034. As we discussed and agreed with you earlier, the SAP the CSC is submitting to comply with the RWQCB's Permit 99-034 is identical to the "Final" SAP of the Routine Groundwater Monitoring Work Plan which we are currently using to conduct the Routine Groundwater Monitoring Element of Work at the she. This Final SAP/QAPP was previously submitted to EPA for the Casmalia project in January, 1998. The SAP addresses the chemical quality sampling (i.e. VOC, Halogenated VOC, SVOC, Pesticides/Herbicides, pH, Coliform Bacteria, total Petroleum) which the CSC win perform: semi annuallyfor the RCF and A-Series Pond (as defined in Table I of the approved permit) as required in the event of a discharge at least 14 days prior to and during a discharge of the treated effluent at the outfall (as defined in Table II of the approved permit) as required in the event of a discharge of the Casmalia Creek Please note that the attached SAP does not include any discussion of the Acute or Chronic Toxicity testing required by the permit and listed in Table I or Table II. The Acute and Chronic Toxicity tests will be done in accordance with EPA guidance document "Short Term Methods for Estimating the Chronic Toxicity of Effluents and receiving Waters to Freshwater Organisms " (EPA/600-4-91-002, 1994). Finally, Note 2 of Table I of Permit No 99-034 indicates that the semi annual monitoring of the ponds "shall commence on April 15 th and October 15 th ". The CSC is interpreting that note to mean we must conduct the semi annual monitoring some time between these two dates (in other words, we are not planning to conduct the pond monitoring on these exact dates). If that is not correct, please let me know as soon as possible. regards, V*"t ' Corey Bertelsen / Casmalia Project Coordinator cc JimDragna-MDBE derm Anderson - Texaco Mary Blevins-EPA CSA015328

75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

SFUND RECORDS CTR75406

CASMALIA SITE REMEDIATION PROJECTCorey BertdsenProject Manager

January 18,2000

To: DanNHes-RWQCB

Subject: Sampling and Analysis Plan for Compliance MonitoringNPDES Permit no. 99-034

On behalf of the Casmalia Steering Committee (CSC), I have attached a proposed Sampling andAnalysis Plan (SAP) for compiiance monitoring pursuant to Permit No. 99-034. As we discussed andagreed with you earlier, the SAP the CSC is submitting to comply with the RWQCB's Permit 99-034is identical to the "Final" SAP of the Routine Groundwater Monitoring Work Plan which we arecurrently using to conduct the Routine Groundwater Monitoring Element of Work at the she. ThisFinal SAP/QAPP was previously submitted to EPA for the Casmalia project in January, 1998.

The SAP addresses the chemical quality sampling (i.e. VOC, Halogenated VOC, SVOC,Pesticides/Herbicides, pH, Coliform Bacteria, total Petroleum) which the CSC win perform:

• semi annually for the RCF and A-Series Pond (as defined in Table I of the approved permit)

• as required in the event of a discharge at least 14 days prior to and during a discharge of the treatedeffluent at the outfall (as defined in Table II of the approved permit)

• as required in the event of a discharge of the Casmalia Creek

Please note that the attached SAP does not include any discussion of the Acute or Chronic Toxicitytesting required by the permit and listed in Table I or Table II. The Acute and Chronic Toxicity testswill be done in accordance with EPA guidance document "Short Term Methods for Estimating theChronic Toxicity of Effluents and receiving Waters to Freshwater Organisms " (EPA/600-4-91-002,1994).

Finally, Note 2 of Table I of Permit No 99-034 indicates that the semi annual monitoring of the ponds"shall commence on April 15th and October 15th". The CSC is interpreting that note to mean we mustconduct the semi annual monitoring some time between these two dates (in other words, we are notplanning to conduct the pond monitoring on these exact dates). If that is not correct, please let meknow as soon as possible.

regards,V*"t 'Corey Bertelsen /

Casmalia Project Coordinator

cc JimDragna-MDBEderm Anderson - TexacoMary Blevins-EPA

CSA015328

Page 2: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Harding Lawson Associates

Sampling and Analysis Plan forCompliance MonitoringNPDES Permit No. 99-034

Page 3: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Sampling and Analysis Plan forCompliance MonitoringNPDES Permit No. 99-034

Prepared for

Casmalia Resources Site Steering Committee

Prepared by:

Harding Lawson Associates10265 Rockingham Drive, Suite 150Sacramento, California 95827

January 4,2000

CSA015330

Page 4: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

TABLE OF CONTENTS

PAGE1.0 INTRODUCTION............................................................................................................................... 1-1

1.1 PURPOSE..............................................................................................................^^1.2 SAP ORGANIZATION ...............................................................................................................1-1

2.0 SITE BACKGROUND AND SETTING ...........................................................................................2-1

3.0 SAMPLE LOCATIONS AND FREQUENCY ...................................................................................3-1

3.1 CHEMICAL OF POTENTIAL CONCERN...............................................................................3-13.2 ANALYTICAL METHODS .......................................................................................................3-13.3 SAMPLE ANALYSIS.................................................................................................................3-13.4 SAMPLE COLLECTION SCHEDULE .....................................................................................3-23.5 QUALITY CONTROL SAMPLES.............................................................................................3-2

3.5.1 Field Duplicate Sample...................................................................................................3-23.5.2 Field Blank and Equipment Blank Samples ..................................................................3-23.5.3 Trip Blank.......................................................................................................................3-23.5.4 Laboratory QC Samples .................................................................................................3-2

4.0 SAMPLE DESIGNATION.................................................................................................................4-1

4.1 DATAMANAGEMENT.............................................................................................................4-14.2 SAMPLE DESIGNATION..........................................................................................................4-1

5.0 SAMPLING EQUIPMENT AND PROCEDURES............................................................................5-1

5.1 WATER QUALITY SAMPLING FROM PONDS....................................................................5-15.2 FIELD EQUIPMENT..................................................................................................................5-25.3 DECONTAMINATION PROCEDURES...................................................................................5-25.4 INVESTIGATION DERIVED WASTE.....................................................................................5-35.5 SAMPLE CONTAINERS, PRESERVATIVES, AND HOLDING TIMES.............................5-35.6 SAMPLE HANDLING, SHIPPING, AND CUSTODY PROCEDURES ................................5-35.7 ANALYTICAL METHODS .......................................................................................................5-4

6.0 REFERENCES....................................................................................................................................6-1

CSA015331

1/4/00-Revision 1.0 TOC-i L:\40000\47588\WP\SAP\47588W20.doc

Page 5: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

LIST OF FIGURES

FIGURE 2-1 SITE MAP LOCATIONFIGURE 2-2 SITE FEATURES AND SURROUNDING AREA

LIST OF TABLES

TABLE 3-1 LIST OF CHEMICALS OF POTENTIAL CONCERN, ANALYTICALMETHODS, METHOD DETECTION LIMITS, AND AVAILABLE MCLsAND REGION IX PRGS

TABLE 3-2 CHEMICAL ANALYSES TO BE PERFORMED ON WATER SAMPLESCOLLECTED FROM EACH LOCATION DURING RGMEW

TABLE 3-3 QUALITY CONTROL SAMPLING FREQUENCY

LIST OF APPENDICES

APPENDIX A QUALITY ASSURANCE PROJECT PLAN (without BC Laboratories standardoperating procedures, see work plan dated January 1998)

CSAO15332

1/4/00-Revision 1.0 TOC-11 L:\40000\47588\WP\SAP\47588W20.doc

Page 6: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Field Sampling Plan

LIST OF ACRONYMS

COPC Chemical of Potential ConcernCSC Casmalia Steering CommitteeC/T/D Collection/Treatment/DisposalCirrus Cirrus Environmental LaboratoryCLCW Contaminated Liquids Component of WorkCW Component of WorkDNAPL Dense Non-Aqueous Phase LiquidDQO Data Quality ObjectiveEE/CA Engineering Evaluation/Cost AnalysisEPA United States Environmental Protection AgencySAP Field Sampling PlanHSU Hydrostratigraphic UnitMIS Management Information Systemmsl mean sea levelQAPP Quality Assurance Project PlanQC Quality ControlRI/FS Remedial Investigation/Feasibility StudyRGMEW Routine Groundwater Monitoring Element of WorkSCM Site Conceptual ModelSite Casmalia Resources Hazardous Waste Management FacilitySOP Standard Operating ProcedureSOW Statement of WorkSVOC Semi-Volatile Organic CompoundTEPH Total Extractable Petroleum HydrocarbonTM Technical MemorandumVOC Volatile Organic CompoundWork Plan RGMEW Work Plan

CSA015333

Toe-in L:\40000\47588\WP\SAP\47588W20.doc

Page 7: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

1.0 INTRODUCTION

This Sampling and Analysis Plan (SAP) describes activities to be conducted for Compliance Monitoringpursuant to Permit No. 99-034 for the Casmalia Resources Landfill (Site) in Casmalia, California. ThisSAP is designed to be a stand alone document for use by the Field Sampling Team. As previously discussedand agreed to by the Regional Water Quality Control Board - Central Coast Region (RWQCB), this SAP isessentially identical to the "Final" Sampling Analysis Plan (SAP) for the Routine Groundwater MonitoringElement of Work (RGMEW) previously submitted to EPA in January 1998.

1.1 PURPOSE

The purpose of the SAP is to describe the field data collection effort to be performed for the compliancemonitoring. The SAP presents Site-specific sampling techniques, sample media, proposed samplinglocations and frequency, and sample analyses to be employed.

This document provides guidance to the field sampling team so that data collection activities will beperformed consistent with the data quality objectives (DQOs) for the acquisition of data. Detailedmethods for completing field activities are described in Section 5.0. The data obtained must meet specificDQOs as specified in the Quality Assurance Project Plan (QAPP) which is included in Appendix A.

1.2 SAP ORGANIZATION

This plan is intended to be used for all surface water sampling events performed by the Casmalia SteeringCommittee (CSC). This plan will be updated and amended as necessary. Recommendations to modify thisplan will be submitted to United States Environmental Protection Agency (EPA) via the TechnicalMemorandum (TM) process as outlined in the SOW. The plan is written for use as both a planningdocument and a field procedures guidance document.

The remainder of this SAP is organized as follows:

2.0 Site Background and Setting3.0 Sample Locations And Frequency4.0 Sample Designation5.0 Sampling Equipment And Procedures6.0 References

CSA015334

1/4/00 1-1 L:\40000\47588\WP\SAP\47588W20.doc

Page 8: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

2.0 SITE BACKGROUND AND SETTING

The Site consists of an approximately 250 acre parcel within the 4,645 acres owned by CasmaliaResources. The Site is located in hilly south-facing terrain in the Casmalia Hills, approximately 1.5 milesnorth of the Town of Casmalia, Santa Barbara County, California (Figure 2-1). Site elevations rangefrom 835 feet above mean sea level (msl) at the northern boundary to 375 msl at the southern boundary.Figure 2-2 shows the Site's topography, drainage patterns, and features.

The Work Plan, dated September 4, 1997 (Revision 1.0, January 1998), provides discussions pertaining toSite History, Hydrogeologic Conditions, and Groundwater Quality. The General Work Plan (TRCEnvironmental Solutions, Inc., 1997) contains a detailed Site history, including operating background andphysiographic and hydrologic conditions.

CSA015335

1/4/00 2-1 L:\40000\47588\WP\SAP\47588W20.doc-

Page 9: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

3.0 SAMPLE LOCATIONS AND FREQUENCY

This section of the SAP describes the location and frequency of sampling, the analytical approach, and thesampling rationale. Section 5.0 describes the methodology for sampling.

The SAP addresses the chemical quality sampling which the CSC will perform as outlined below:

• Semi-annually for the RCF and A-Series Pond (as defined in Table I of the approved permit),

• As required in the event or a discharge at least 14 days prior to and during a discharge of thetreated effluent at the outfall (as defined in Table II of the approved permit), and

• As required in the event of a discharge to the Casmalia Creek.

3.1 CHEMICAL OF POTENTIAL CONCERN

The Chemicals of Potential Concern (COPCs) include the 206 compounds found in the 40 CFR, Part 264,Appendix IX-Groundwater Monitoring List, and twenty-three additional unlisted compounds detected insamples collected from the Gallery Well, Sump 9B, and PSCT-1. COPCs are summarized in Table 3-1.

3.2 ANALYTICAL METHODS

Cirrus Environmental (Cirrus), or BC Analytical, will perform laboratory analyses using EPA TestMethods for Evaluating Solid Waste Physical/Chemical Methods (SW-846) (1994). Cirrus willsubcontract analyses requiring EPA Methods 8290 and 8150 to Quantum Laboratory and SequoiaAnalytical, Inc., respectively. All laboratories are certified for the methods described in the QAPP. Table3-2 presents specific methods and the requirements for sample collection, handling, and preservation.

In addition to chemical analyses, the CSC will collect measurements of physical parameters for pondsamples. Physical parameters will include pH, specific conductance, temperature, turbidity, and dissolvedoxygen. These parameters will be measured primarily in the field during sampling.

3.3 SAMPLE ANALYSIS

The following analytical methods are identified: Volatile Organic Compounds (VOCs); Semi-VolatileOrganic Compounds (SVOCs); Metals (total and dissolved); PCB/Pesticides; Chlorinated Herbicides,Penta-, Tetra-, Hexa-chlorodibenzo-p-dioxins/furans, (Dioxins/Furan); pH; Cyanide (total and amenable);general minerals; and Total Extractable Petroleum Hydrocarbons (TEPH).

Table 3-3 provides a summary of the number of field samples to be submitted for each analytical methodand the corresponding number of Quality Control (QC) samples by method. A discussion of the QCsample selection criteria is presented in Section 3.5.

CSA015336

1/4/00 3-1 L:\40000V47588\WP\SAP\47588W20.doc

Page 10: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

3.4 SAMPLE COLLECTION SCHEDULE

The two-day sample collection schedule is an estimate based on an anticipated sampling rate. The pondswill be sampled during the RGMEW events.

3.5 QUALITY CONTROL SAMPLES

The Field Sampling Team will collect pond samples for various analyses over approximately 2 days.Quality control samples may be collected, which way consist of duplicates, equipment blanks, fieldblanks, trip blanks, and laboratory QC extra volume samples. These samples are introduced into thesample train in the field to monitor sample collection activities, shipping, and analytical laboratoryperformance. The collection rate for QC samples is discussed below. Laboratory and field QC sampleswill be used to monitor and quantify the performance of analytical methods and field procedures. Asstated in the QAPP, laboratory QA samples monitor and quantify the laboratory's performance.

3.5.1 Field Duplicate Sample

Field duplicates are specified at a collection rate of one (I) for every ten (10) field samples, per samplemedium. The duplicate sample will have a unique sample number and station location number and willbe sent "blind" to the laboratory.

3.5.2 Field Blank and Equipment Blank Samples

Blank samples are specified at a rate of one (I) for every day a parameter suite is collected. However, thetotal number of blanks collected will not exceed 10 percent of the total number of water quality samplescollected for each parameter. When samples are collected using a piece of sampling equipment, anequipment blank will be collected by pouring or pumping blank water through or over the piece ofsampling equipment. When all samples on a given day are collected from dedicated sampling sources(pumps), a field blank will be collected by pouring the deionized water directly into the samplecontainers. Blanks will be labeled in the same manner as other samples and will be sent "blind" to thelaboratory.

3.5.3 Trip Blank

A trip blank is submitted at a frequency of one (I) per sample shipment sent to the laboratory containingsamples for VOC analysis. The trip blank is shipped to and from the field with the sample containers. Itis not opened in the field, thereby providing a test for contamination from sample preservation; siteconditions; and transport; as well as sample storage; preparation; and analysis. Trip blanks are used todetect cross-contamination of VOCs, and therefore, are only analyzed for VOCs.

3.5.4 Laboratory QC Samples

Laboratory QC samples are specified at a rate of one (I) for every 20 samples submitted for analysis(including duplicates and field blanks) per sample medium. The first laboratory QC sample is designatedfrom the first day the sample set collected. If additional laboratory QC samples are needed, they areselected from the succeeding sample delivery groups (twenty samples). Extra volumes will be collectedfor laboratory quality control tests.

CSA0153371/4/00 3-2 L:\40000\47588\WP\SAP\47588W20.doc

Page 11: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

4.0 SAMPLE DESIGNATION

4.1 DATA MANAGEMENT

The CSC will evaluate the adequacy and completeness of the chemical water quality sampling locationsafter reviewing the data from each sampling event. The CSC will recommend modifications to samplinglocations using the criteria presented in Section 4.0 of the Work Plan.

Data collected for the chemical analysis portions will be entered into a database. Each datum will have aunique identification number. The Project Data Manager will manage and update the database inaccordance with Section 4.0 of the Work Plan.

4.2 SAMPLE DESIGNATION

A unique sequential sample number will be generated by the database prior to sampling. The numericsample identification number will be the primary sample designation. However, to ensure consistencywith previous EPA numbering conventions, the CSC will also use the following field sampleidentification system for labeling samples in the field.

The field sample designation system for compliance monitoring samples will follow the conventionbelow:

MMDDYY-XXXXXX-XX

Where: MM = Month sampledDD = Day sampledYY = Year sampled

XXXXXX = Sample location (well number, location, etc.)XX = Blank or duplicate sample designator where:

01 = field sample02 = duplicate03 = Field Blank04 = Trip Blank05 = Equipment Blank

Sample labels will include the following information:

Sample IDDate and timeAnalysis requestedPreservativeSampler's initials

CSA015338

1/4/00 4-1 L:\4000CM7588\WP\SAP\47S88W20.doc

Page 12: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

5.0 SAMPLING EQUIPMENT AND PROCEDURES

This section discusses specific sampling equipment and procedures.

The following general guidelines govern performance of field sampling activities:

• Appropriate protocols in the HASP will be followed to minimize exposure to potentiallycontaminated media.

• Samples will be collected in clean, laboratory-certified containers provided by thelaboratory.

• Field sample collection, labeling, handling, and analysis procedures as described in theSAP and QAPP will be followed.

• Appropriate containers and preservatives will be used, and analytical holding times listedin Table 3-2 will be met.

• Sample packaging and chain-of-custody procedures will be followed to ensure thatsamples are stored appropriately and delivered to the analytical laboratory.

• Adequate documentation of sampling and analysis activities will be maintained.

5.1 WATER QUALITY SAMPLING FROM PONDS

Field samplers will use a boat located on the Site to collect water samples from the ponds. Field samplerswill follow the procedures below to collect samples.

• The boat should be anchored at the geographic center of the pond. A measuring tape willbe used to take a total depth measurement from the top of the pond surface.

• After a total depth measurement has been made, a discrete interval sampler will belowered to a depth approximately halfway between the pond surface and pond bottom.The sampler will then be opened, a sample collected, and the sampler closed. Afterclosing the sampler to prevent the mixing of the captured sample with water from otherdepths, the sampler will be brought into the boat where the captured sample will betransferred into designated sample bottles.

• The sample collection procedure will be repeated until all sample bottles have been filled.Samples should be collected in the following order:

1. VOCs2. SVOCs3. Metals4. PCB/Pesticides5. Chlorinated Herbicides

CSA015339

1/4/00 5-1 L:\40000\47588\WP\SAP\47588W20.doc

Page 13: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

6. Dioxins/Furans7. Cyanide (total and amenable)8. General Minerals9. TEPH10. pH

All samples will be stored on ice as soon as possible after collection.

• Equipment blanks will be collected from the discrete interval sampler by runninglaboratory prepared organic-free water through a clean bailer. Filled sample bottles willbe labeled and placed directly on ice in a cooler, or in a sample-only refrigerator.

• Samples will be clearly labeled with indelible ink using the proper identifier.Documentation will be completed and samples will be packaged and shipped as describedin Section 6.0.

5.2 FIELD EQUIPMENT

Several equipment items support sample collection and provide baseline worker safety. The materialsrequired for the water level monitoring and sampling are separated into the following two primary groups:general equipment that is reusable for several samplings; and disposable materials:

General:Health and safety equipmentSteel-toed boots, safety glasses, hard-hatsField data sheets and/or logbookBuckets and sampling beakersCoolers/refrigeratorPortable Redi-flo pumpPortable trailer-mounted poly- tankDiscreet interval samplerpH/Temperature/Conductivity/turbidity/Dissolved Oxygen meters

Expendable Materials:GlovesPaper towelsPreservativesTyvekBailersIce for cooling/blue ice pack

5.3 DECONTAMINATION PROCEDURES

Prior to sampling and between subsequent uses, non-disposable sampling equipment and tools will bedecontaminated.

All field samplers will be required to wear latex gloves during sampling. The latex gloves will be rinsedand disposed of after each well is sampled.

CSA015340

1/4/00 5-2 L:V40000\47588\WP\SAP\47588W20.doc

Page 14: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

5.4 INVESTIGATION DERIVED WASTE

All decontamination water will be collected in a portable trailer-mounted poly- tank and deposited in thePSCT Treatment System. All adequately decontaminated PPE and disposable sampling equipment willbe rinsed with water and managed by the CSC as nonhazardous waste.

5.5 SAMPLE CONTAINERS, PRESERVATIVES, AND HOLDING TIMES

Sample containers for the sampling event will be obtained from the analytical laboratory and certified tobe clean. Bottle certifications will be kept in the field file and retained as part of the field sampling notes.Each sample container will be labeled with the initials of the person taking the sample; date and time;sample identifier; sample type; preservation method; and analyses to be performed. Table 3-2 providesthe types and quantities of containers, and the holding time for each type of analysis.

As noted in Table 3-2, samples for metals analysis will be preserved with nitric acid. For dissolvedmetals analysis, samples will be collected and filtered by the laboratory prior to acidification.

Holding times vary by analyses. The holding time for each analysis is summarized below.

pH Analyze ImmediatelyVOCs 14 daysCyanide 14 daysTPH 14 daysSVOCs 7 daysPesticides/PCBs 7 daysDioxins/Furans 7 daysChlorinated Herbicides 7 daysMetals 6 months

Samples will be shipped daily to avoid exceeding holding times. Each sample bottle shipped will belabeled with a sample number, the requested analysis, the date and time sampled, the preservative, and thesampler's initials.

5.6 SAMPLE HANDLING, SHIPPING, AND CUSTODY PROCEDURES

Samples will be packed and shipped according to the procedure specified in the QAPP. Each samplecontainer will be placed in a scalable plastic bag and then placed on ice in a cooler. Chain-of-custodyprocedures will be used to maintain and document sample possession. To maintain custody of samplesshipped by courier, the sampler will secure the samples in a cooler with custody seals on two sides. Thecoolers will be hand-delivered or shipped via overnight courier to the laboratory at the end of each day'ssampling. Samples will be shipped in a manner such that the laboratory will receive them in sufficienttime to document and extract aliquots for analysis.

CSA015341

1/4/00 5-3 L:\40000\47588\WP\SAP\47588W20.doc

Page 15: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

The chain-of-custody form will be initiated at the time of sampling and will contain the sample identifier,date and time of sampling, and name and dated signature of the person taking the sample, as well as themethods by which each sample will be analyzed, and other pertinent information. Standardized chain-of-custody forms will be used for tracking samples from the point of origin in the field through laboratoryprocessing and disposal. The chain-of-custody form will accompany the samples to the laboratory

The Chemicals of Potential Concern (COPCs) include the 206 compounds found in the 40 CFR, Part 264,Appendix IX-Groundwater Monitoring List, and twenty-three additional unlisted compounds detected insamples collected from the Gallery Well, Sump 9B, and PSCT-1. COPCs are summarized in Table 3-1.

5.7 ANALYTICAL METHODS

The analytical contractor selected will perform laboratory analyses using EPA Test Methods forEvaluating Solid Waste Physical/Chemical Methods (SW-846) (1994). BC Laboratory may subcontractsome targeted analysis. All laboratories are certified for the methods described in the QAPP. Table 3-2presents specific methods and the requirements for sample collection, handling, and preservation. TheCSC has selected the methods to monitor for COPCs.

CSA015342

1/4/00 5-4 L:\40000\47588\WP\SAP\47588W20.doc

Page 16: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Field Sampling Plan

6.0 REFERENCES

Canonie Environmental, 1987. Hydrogeologic Assessment Report, Casmalia Class I Hazardous WasteManagement Facility, Revision 1. Canonie, November 1987.

Casmalia Resources, 1991. Annual Monitoring Report, Casmalia Resources Hazardous WasteManagement Facility. February 1992.

ill, 1997. Well Inventory Report, Casmalia Resources Hazardous Waste Management Facility,Santa Barbara County, California. EPA Contract No. 68-W9 1-003 1/WA No. 3 1-56-943H. January 22,1996.

CH2MHill, 1996. Technical Memorandum, December 1994 Ground Water Sampling Results, CasmaliaHazardous Waste Management Facility, EPA Contract No. 68-W9-003 1/ WA No. 3 1-56-94H. January22, 1996.

EPA. 1994. Test Methods for Evaluating Solid Waste Physical/Chemical Methods (SW-846).

ICF Kaiser, 1996. Working Draft - Agency Review: Health and Safety Plan (and Emergency ResponsePlan). October 25, 1996.

ICF Kaiser, 1997. Routine Groundwater Monitoring Element o/Work, Part I - Work Plan, Part II-Sampling and Analysis Plan (Revision 1.0, January 1998), September 4, 1997.

Woodward-Clyde Consultants, 1988. Hydrogeologic Site Characterization and Evaluation Report,Casmalia Resources Hazardous Waste Management Facility. May 11, 1988.

Woodward-Clyde Consultants and Canonie Environmental Services, Inc., 1989. Hydrogeologic SiteInvestigation Report for CAO-98-61, Casmalia Resources Hazardous Waste Management Facility. April18, 1989.

CSAO15343

6-1 L:V40000U7S8»VmSAIM7M8W20.doc

Page 17: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Hm

CSA015344

Page 18: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

PLATES

CSAO15345

Page 19: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

1/2ItSalt

CSA015346Source: U.S. Department of the Interior. Geological Survey.CASMALIA Quadrangle 7.5 Minute Series (Topographic) 19S2

HARDINQ LAWSON ASSOCIATESEngineering andEnvironmental Services10265 Rockinqham Drive. Suit* 150Sacramento. California 95827(916) 36+-079J

Site LocationCasmalia Hazardous WasteManagement Facility

PLATE

DRAWNYVG

PROJECT NUMBER47588

APPROVED DATE1/00

REVISED DATE

Page 20: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

V4i miimmm^

LEGENDCONCRETE DITCH

DEBRIS AREA

FACILITY AND ZONE 1 BOUNDARY

PERIMETER SOURCE CONTROL TRENCH (PSCT)

PLUME CAPTURE COLLECTION TRENCH (PCT)

CLAY BARRIER

ESTIMATED EXTENT OF SURFACEDRAINAGE AREA

CREEK

EXTRACTION POINTS

Notes:

Topographic contour Interval Is 10 feet.

Topography (Iayer=contour_add_pre98) along periphery from previous topographic survey(s).

Central Topography based on 5 January 1998 Aerial Photography by Golden Slate Aerial Surveys, Incof San Luls Oblspo, CA. Data provided by VRR & Associates of Santa Maria, California.

Revision 3/98: Topography from P/S Landfill Butress and Borrow Areas updated based onTopographic Survey conducted by Pacific Engineering (of Santo Maria, California) during the firstweek of October 1998.

HARDINQ LAWSON ASSOCIATESEngineering andEnvironmental Services10265 Rockingham Drive, Suite 150Sacramento, California 95827(916) 364—0793

Sampling and Analysis Planfor Compliance MonitoringCasmalia Hazardous WasteManagement Fatility

PLAT

DRAWNYVG

PROJECT NUMBER47588

APPROVED DATE1 /on

REVISED DA

Page 21: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

TABLES

oo^fr~>>oO<00U

Page 22: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

TABLES

CSA015349

Page 23: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

jijiiJSi;lNyji|efr:::s

67-64-175-05-8107-02-8107-13-171-43-275-27^75-25-274-83-975-15-056-23-5126-99-8108-90-775-00-367-66-374-87-3107-05-196-12-8124-48-1106-93^74-95-395-50-1541-73-1

iifiiiiiililllllSiiS

liJ sll! §Bi lsiSSiAcetoneAcetonitrileAcroleinAcrylonitrileBenzeneBromodichloromethaneBromoform (Tribromomethane)Methylbromide (Bromomethane)Carbon disulfideCarbon tetrachloride2-Chloro-1 ,3-butadieneChlorobenzeneChloroethaneChloroformChloromethane (Methyl chloride)3-Chloropropylene1 ,2-Dibromo-3-chloropropaneChlorodibromomethaneEthylene dibromide (1 ,2-Dibromoethane)Dibromomethaneo-Dichlorobenzenem-Dichlorobenzene

;::Appi

XXXXXXXXXXXXXXXXXXXXXX

fiiiliiDetected

ChemicalsGroup

vocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvoc

Method

8260826082608260826082608260826082608260826082608260826082608260801182608011826082608260

Ilillli*!!IHiiiilLimit (jjg/L)

205025301

0.51.22.50.60.56

0.60.80.51.53

0.20.5

0.050.50.50.5

•'••'•• •-• •• : : ::::::::::::::::::::::::::::: ::: :

1

100100

0.5

70

100

0.21000.05

600

iidMii:!:i9llj

5100100

5

100

100

0.21000.05

600

pp|; ||!l

608.3370.690.043.740.390.188.518.6620.740.1714.3139.46705.310.161.5118250.051.01

365370.14

183

1/3/00 - Revision 1.0 CSA015350 1 of 12 3-1_fsp.xls

Page 24: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

::-:-:--.-:-::. .'. ,:.:::.".T*;|3fci;.e.. :*»•.• ..J • . • . • . • . • • • • . • . • . • . • . • . • . - • : : • >•:•.•:•.•:•:•:•:::•:•:-:•.•:• • • : • - . • •:• .:.^:.^-^-.-.-:-.-^^-^^-^^^-^-^^^:V;-;:;-;:hv;i;-;-;Y;J;^^^

wi^i^iiiM

106-46-775-71-875-34-3107-06-275-35-4156-60-578-87-510061-01-510061-02-6110-57-6123-91-197-63-2100-41-487-68-3591-78-674-88-478-83-1126-98-778-93-380-62-6108-10-175-09-2

llliii!ii::i::;::iiiiliili:

p-DichlorobenzeneDichlorodifluoromethane1,1-Dichloroethane1 ,2-Dichloroethane1 , 1 -Dichloroethylenetrans-1 ,2-Dichloroethylene1 ,2-Dichloropropanecis-1 ,3-Dichloropropylenetrans-1 ,3-Dichloropropylenetrans-1 ,4-Dicholoro-2-butene1 ,4-DioxaneEthyl methacrylateEthylbenzeneHexachlorobutadiene2-HexanonelodomethaneIsobutyl alcoholMethacrylonitrileMethyl ethyl ketoneMethyl methacrylateMethyl isobutyl ketoneMethylene chloride

SBli

XXXXXXXXXXXXXXXXXXXXXX

fisR ii:^::0| i!i:iChemicals

iliiiiiii

vocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvoc

Method

8260826082608260826082608260826082608260826082608260826082608260826082608260826082608260

Iss ioi;!:lllteiHOttvLimit (pg/L)

0.72.50.50.50.60.50.50.50.6671100.60.7355

65455.34

2.65

liKiiiIIBili

5

50.56105

700

5

pSHIlilHii

75

57

1005

700

5

0.47394.59811.11

0.120.05

121.670.16

6.11547.501339.87

0.86

18251.04

1904.35486.67157.84

4.28

1/3/00 - Revision 1.0 CSA015351 2 of 12 3-1_fsp.xls

Page 25: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

Ulmim

91-20476-01-7109-06-8100-42-5630-20-679-34-5127-18-4108-88-3120-82-171-55-679-00-579-01-675-69-496-18-4108-05^75-01-41330-20-783-32-9208-96-898-86-253-96-392-67-1

|||i:llllllllllll|l|l|||||lllllilll ^V:;':':':';;: .',';'.:.:.:.:.:.:.:.:.:.:.:.: .'••• - • - • : • ;":':':':':';'x';:.'':.: ' '--' ':::':::':::; :::::::::::::::;:.:::.:::.:.:.:.:.:::.:,:.:.:.;.;:: :. : :: ::::x: • • • • • • •:

:' ''•:•: :-:~:-:,'.\ :.f :;:V:;V.':'::::::. '-.'•'.'•.'•.'•:'•.'.•.•.• •'.'•.- - -'• •'• • • •••••••••••• •-- •'•_ :":-:::::": • :'; :'; x'x'x'x'xYx'x'x^x^i^.V.v/.v :.:;;:

NaphthalenePentachloroethane2-PicolineStyrene1,1,1 ,2-Tetrachloroethane1 , 1 ,2,2-TetrachloroethaneTetrachloroethyleneToluene1 ,2,4-Trichlorobenzene1,1,1-Trichloroethane1 , 1 ,2-TrichloroethaneTrichloroethyleneTrichloromonofluoromethane1 ,2,3-TrichloropropaneVinyl acetateVinyl chlorideXylenes-mixed isomersAcenaphtheneAcenaphtyleneAcetophenone2-Acetylaminofluorene4-Aminobiphenyl

XXXXXXXXXXXXXXXXXXXXXX

Chemicals

VOCvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocvocsvocPAHssvocsvocsvoc

iiil•-:''::'::::'':':':::':':":':::":':':';-;-;-

8260826082708260826082608260826082608260826082608260826082608260826082708310827082708270

Detection

1.58

2.80.60.60.60.51

0.80.80.60.5212

0.51.34107

203

CalMCL

iiiiii

100

15

15070200

55

150

0.51750

Y*^^f"-:-fiWVMj«..

100

510007020055

210000

243.33

1641.090.430.061.08

723.42194.44792.250.201.64

1288.240.00

412.430.02

1431.37365

0.04

1/3/00 - Revision 1.0 CSA015352 3 of 12 3-1_fsp.xls

Page 26: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

:;::1;:!1!::'1;:;:::::;::::::.;-;-;-;:;-Xv:v:-x

||P

62-53-3120-12-7140-57-856-55-350-32-8205-99-2191-24-2207-08-9100-51-6101-55-385-68-759-50-7106-47-8510-15-6111-91-1111-44^108-60-191-58-795-57-87005-72-3218-01-9108-39-4

I:::.:.:::;i::;i|| ^

:jMiiiji^wi:^M^

AnilineAnthraceneAramiteBenzo(a)anthraceneBenzo(a)pyreneBenzo(b)fluorantheneBenzo(g,h,i)peryleneBenzo(k)fluorantheneBenzyl alcohol4-Bromophenyl phenyl etherButyl benzyl phthalatep-Chloro-m-cresolp-ChloroanilineChlorobenzilatebis(2-Chloroethoxy) methanebis(2-Chloroethyl)etherbis(2-Chloroisopropyl)ether2-Chloronaphthalene2-Chlorophenol4-Chlorophenyl phenyl etherChrysenem-Cresol

W:'-''^S^MMi^li^M^iSim

^ • iii iiiiimQN ISHWTS; *ND AVAIiABIi

XXXXXXXXXXXXXXXXXXXXXX

DetectedChemicals

SVOCSVOCSVOCPAHsPAHsPAHsPAHsSVOCSVOCSVOCSVOCSVOCSVOCSVOCsvocsvocsvocsvocsvocsvocPAHssvoc

E MCLs /

Method

8270827082708310831083108310827082708270827082708270827082708270827082708270827083108270

SiiiiilDetectioniiiiiii

24200.10.1

0.250.25

74657920734433

0.25

0.2

Wiliiiife

0.120.2

0.22

1002

0.22

ipjlll

10.5918252.690.090.010.09

0.9210950

7300

1460.25

0.010.96

486.6738.42

9.211825

1/3/00 - Revision 1.0 CSA015353 4 of 12 3-1_fsp.xls

Page 27: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

1 ) 1 1 1

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

S^^^^^^^^^^^^Si^^^^S^S^iilB§HSS^^^^^^^^^^^^^

i|: ujnt|ii:?:

95-48-7106-44-584-74-2117-84-02303-16-453-70-3132-64-991-94-1120-83-287-65-060-57-184-66-260-51-557-97-6119-93-7105-67-9131-11-3534-52-199-65-051-28-5121-14-2606-20-2

:':':':':::':::':';:::;Y," ' ::.:;:.:.:;-::.-.-.: :.:.; •.• • .: ••^^^^•••••'•••'••-'••-••'-'•'•'-•- i-:-: :: : ' ::-: :: :: ::Y:Y:^Y"Y:y:Y:Y:Y:Y:1f:1:1.1; :" :;-: :: ::-: :: :; :

•:-:-:-.-:-:•:••-.•••• •• • ' • ' • : • ' • • • • • • • • • : • : - : • : " . : • • • • ' : : : : : : : - ; : ; ; - : ; - : : ; .-,-,-,- -:•.-.•.•.•.•.•.•.•.•.•.-.•.•.•.• • • • • - . . ... • • • - . - • • .-.-.•.-.•.•

o-Cresolp-CresolDi-n-butyl phthalateDi-n-octyl phthalateDiallateDibenzo(a, h)anthraceneDibenzofuran3,3'-Dichlorobenzidine2,4-Dichlorophenol2,6-DichlorophenolDieldrinDiethyl phthalateDimethoate7, 12-Dimethylbenz[a]anthracene3,3'-Dimethylbenzidine2,4-Dimethyl phenolDimethyl phthalate4,6-Dinitro-o-cresolm-Dinitrobenzene2,4-Dinitrophenol2,4-Dinitrotoluene2,6-Dinitrotoluene

51111;

XXXXXXXXXXXXXXXXXXXXXX

siiii ii•rtieiiiitectffl:Chemicals

Group

svocsvocsvocsvocsvocsvocsvocsvocsvocsvoc

PesticideSVOCSVOCsvocsvocsvocsvocsvocsvocsvocsvocsvoc

Method-• '-:- ::-.-:-::: :-:-'.-;, '.','-, i.,'.,i.'m:\:':\i.

8270827082708270827082708270827082708270808082708270827082708270827082708270827082708270

iiBlilDetection

Limit (ug/L)

2253

20735710

0.033

20201063

25202533

CalMCL

illiillFedMCLiilill

1825183

36507301.1

0.0124.330.15109.5

292007.3

0.01730

365000

3.657373

36.5

1/3/00-Revision 1.0 CSA015354 5 of 12 3-1_fsp.xls

Page 28: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

s»^^^Iflilllilll

:||4i«ji|f||

122-39-4298-04-4107-12-062-50-0117-81-752-85-7206-44-086-73-7118-74-177-47-467-72-170-30-41888-71-7193-39-5465-73-678-59-1120-58-1143-50-091-80-572-43-566-27-3298-00-0

§|

DiphenylamineDisulfotonEthyl cyanide (Propanenitrile)Ethyl methanesulfonatebis(2-Ethylhexyl) phthalateFamphurFluorantheneFluoreneHexachlorobenzeneHexachlorocyclopentadieneHexachloroethaneHexachloropheneHexachloropropyleneIndeno (1 ,2,3-c,d) pyreneIsodrinIsophoroneIsosafroleKeponeMethapyrileneMethoxychlorMethyl methanesulfonateMethyl parathion

ip l;^;::^:^x::-x-x::-:::

':V:V:viv:':'::::::::::::

XXXXXXXXXXXXXXXXXXXXXX

IliiijiiChemicals

M jisiipi

svocsvocsvocsvocsvocsvocPAHsPAHsSVOCSVOCSVOCSVOCsvocsvocsvocsvocsvocsvocsvoc

PesticideSVOCSVOC

Method

8270827082608270827082708310831082708270827082708270827082708270827082708270808082708270

iSfiBSiiDetection

Limit (ug/L)

10204236

100510910250207

207

20100200.13

20

lalMGi

150

40

sFpMiililiil

150

40

912.51.46

4.8

1460243.33

0.04255.54.8

10.95

0.09

70.77

182.5

9.13

1/3/00 - Revision 1.0 CSA015355 6 of 12 3-1_fsp.xls

Page 29: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

llilSPx;:;

^i^iaai^m

56-49-591-57-6924-16-3621-64-762-75-955-18-586-30-610595-95-659-89-2100-75-4930-55-2130-15-4134-32-791-59-899-55-888-74-499-09-2100-01-698-95-388-75-5100-02-756-57-5

i!ii;:P' ^:•••:•••••••••••:-:-:-:-:-:-:-;-: : - • ; : ; : : : : : : ; : I-:-:-.-.-;-;-.-;-:-. :•.•/.• • _ • • • • • . • • : • • • . . • • . • - • . • . • . : • • . • - • . • . ••:•:-:-:-:-:-:-: .-:-:-:-: : :-:-: : : : : : : : : - . : ; - ; •••::::'::::::::::::::::":"::;".'. ' . ' . • . ' . - . ' . ' :.:.::: '.-; :•:•:-:•'.•:•'.•'.•'•'.•'•'•: ••• • : '•'•'•'•'•'•":':''':'::'':'1y'''''::i::::::::::::::':':':':1:':':':':':':::1::;:::::'"::::::. .-.:; .-;-;

3-Methylcholanthrene2-MethylnaphthaleneN-Nitroso-di-n-butylamineN-Nitroso-di-n-propylamineN-NitrosodidimethylamineN-NitrosodiethylamineN-NitrosodiphenylamineN-NitrosomethylethylamineN-NitrosomorpholineN-NitrosopiperidineN-Nitrosopyrrolidine1 ,4-Naphthoquinone1-Naphthylamine2-Naphthylamine5-Nitro-o-toluidineo-Nitroanilinem-Nitroanilinep-NitroanilineNitrobenzeneo-Nitrophenolp-Nitrophenol4-Nitroquinoline 1 -oxide

1111

XXXXXXXXXXXXXXXXXXXXXX

lilBil*Detected

Chemicals!:::i;:liiiii

svocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvoc

Method

8270827082708270827082708270827082708270827082708270827082708270827082708270827082708270

MethodDetection

Limit (jjg/L)

596331051020620204.631033465

26100

";li;Miis;

BiiBl:;;ii:leliliiliip$iiiii!!

0.01

13.72

0.03

2.042.19

3.4

1/3/00-Revision 1.0 CSA015356 7 of 12 3-1_fsp.xls

Page 30: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

lllliili

56-38-2608-93-582-68-887-86-562-44-285-01-8108-95-2298-02-223950-58-5129-00-0110-86-194-59-795-94-358-90-23689-24-595-53^95-95-488-06-299-35^122-09-860-11-7106-50-3

iSsi::.:-:;;;:-;;;:W:::::::™. :::::.:::S;

ParathionPentach lorobenzenePentachloronitrobenzenePentach lorophenolPhenacetinPhenanthrene QPhenol S£Phorate "Pronamide <>>Pyrene ~J

PyridineSafrole1 ,2,4,5-Tetrachlorobenzene2,3,4,6-TetrachlorophenolTetraethyl dithiopyrophosphateo-Toluidine2,4,5-Trichlorophenol2,4,6-Trichlorophenolsym-Trinitrobenzenealpha, alpha Dimethylphenethylaminep-Dimethylaminoazobenzenep-Phenylenediamine

^••••••••••••••••••••^fiw^^^;;;;;;;;%S;;;;;:B; ^ffiiiECJJililillA&JE iliiiiliiiii

i|XXXXXXXXXXXXXXXXXXXXXX

Chemicals "•rSVOCsvocsvocsvocsvocsvocsvocsvocsvocPAHssvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvocsvoc

iii8270827082708270827082708270827082708310827082708270827082708270827082708270827082708270

MethodDetection

Limit (MgVL)

2053

25443

205

0.320203

201002042

2035420

lillilliiiiii

1 1

SMii^S:Mim

219.0029.20.260.56

219007.3

2737.5182.536.5

11.0109518.25

36506.111.83

6935

1/3/00-Revision 1.0 8 of 12 3-1_fsp.xls

Page 31: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

i!!!!i:::;i i

IliliiiilP

ffiUHiiNumber

297-97-2126-68-188-85-7309-00-2319-84-6319-85-7319-86-858-89-957-74-972-54-872-55-950-29-3959-98-833213-65-91031-07-872-20-87421-93-476-44-81024-57-31336-36-38001-35-294-75-7

SifilK^^^^iiiiiiiiO,O-Diethyl O-2-pyrazinyl phosphorothioateO,O,O-Triethyl phosphorothioate2-sec-Butyl-4,6-dinitrophenol(Dinoseb)Aldrinalpha-BHCbeta-BHCdelta-BHCgamma-BHCChtordane (alpha and gamma isomers)p.p'-DDDp.p'-DDEp.p'-DDTEndosulfan IEndosulfan II —Endosulfan sulfate ^Endrin °Endrin aldehyde £Heptachlor °°Heptachlor epoxideTotal PCBsToxaphene2,4-D (2,4-Dichloro-phenoxyacetic acid)

^ON:iJMis;j*NB:;A iifti!2i;;i

SB

XXXXXXXXXXXXXXXXXXXXXX

'Si- lllillIliiiiii!Chemicals

isiriupss

svocsvoc

HerbicidePCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBsPCBs

Herbicides

Method

8270827081508080808080808080808080808080808080808080808080808080808080808080808080808150

MethodDetection

Limit (jjg/L)

200207

0.010.020.040.010.010.1

0.030.030.030.030.030.040.040.040.010.010.51

70

CalMCL

aiill

7

0.20.1

2

0.010.01

370

FedMCL

7

0.22

2

0.40.2

370

;,;.;.-. -.-.-.•.•.•.;.•.;.•.•.•.•.;.•.;.•.;.;. ;.;.;.;.;. I-:-:-:-;-:-;-:- : -;-;-;-:

'•':':':':1:':1:V:''::':-,:::"''1.:;:;:':':':': :'":':::::::::::::.::::::::::::

36.5

0.010.04

0.050.050.280.20.2

10.95

0.010.010.010.06365

1/3/00-Revision 1.0 9 of 12 3-1_fsp.xls

Page 32: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

Iliilliiili ^

111811Number

93-76-593-72-11746-01-67440-36-07440-38-27440-39-37440-41-77440-43-97440-47-37440-48-47440-50-857-12-557-12-57439-92-17439-97-67440-02-07782-49-27440-22^7440-28-07440-31-57440-62-27440-66-6

:. ;.v,:.v.;. - : • : • . vX:x;x:' ' ' • ' - •••••••":':':':x::::::::'xY ". .'.'.'.'.'.'.'.'.'-.' Y.YxYxYx-x-x-1-1-1 '1 '1 '1 ' • • •••••••-•- i-' :x :: :: :: :: :: :x'x x' : ' : ' :1 : ' : ' .. .v.vXv.v.vx-xY • • •••:':':':''':'::'xv:":":'x':':1:Y:Yx xY.Y;Y:Y.Y.YxYxY:Yx:'-'-'-'-"-' ; • - • • • • • •" ; ' ; " ;"• :Y:Y:Yx'. .-•;.:,:::

lill§;; ^

2,4,5-T2,4,5-TP (Silvex)2,3,7,8-Tetrachlorodibenzo-p-dioxinAntimonyArsenicBariumBerylliumCadmiumChromium (Total)CobaltCopperCyanides (Amenable)Cyanides (Total)LeadMercuryNickelSeleniumSilver O

m

Thallium >= ——————— o —————————Tin £Vanadium £>Zinc

XXXXXXXXXXXXXXXXXXXXXX

SSfiS!l!!!|i<f:::::Chemicals

••liriiPll

HerbicidesHerbicides

DioxinsMetalsMetalsMetalsMetalsMetalsMetalsMetalsMetalsMetalsMetalsMetals

MercuryMetalsMetalsMetalsMetals

TinMetalsMetals

Method

8150815082806010601060106010601060106010601090109010601074706010774060107041601060106010

SBiiSDetection

Limit (ug/L)

2050

0.00161

10021

20401010105

0.3205201

2002010

'•:•''•'.•'.'•• "-' -: : : • xYxYx'x'i'x';'

ffi^^K&x^JA^xXxXx-x.OXOy'.OX

•illaliiii

500.00003

650

10004550

1300200200

210050

2

ililiii

so0.00003

650

200045

100

200200152

50

2

3652920

14.60.0426000.0218.25182.52190

1355.717307304

10.95730

182.5182.5

21900255.510950

1/3/00 - Revision 1.0 10 of 12 3-1_fsp.xls

Page 33: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanField Sampling Plan

iBiliisiiifiisasIIBiii

Number

18496-25-8108-86-174-97-5104-51-8135-98-898-06-6110-75-895-49-8156-59-298-82-899-87-667-63-0103-65-1109-99-987-61-695-63-6108-67-895-47-665-85-01918-00-9120-36-57439-98-7

iiJiiijjj^i^lilliiii B^ ^SulfideBromobenzeneBromochloromethanen-Butylbenzenesec-Butylbenzenetert-Butylbenzene2-Chloroethyl vinyl ether2-Chlorotoluenecis-1 ,2-DichloroetheneIsopropylbenzenep-lsopropyltoluene2-Propanoln-PropylbenzeneTetrahydrofuran1 ,2,3-Trichlorobenzene1 ,2,4-Trimethylbenzene1 ,3,5-Trimethylbenzeneo-XyleneBenzoic Acid O

00Dicamba ><~^Dichloroprop £Molybdenum <£

;llli

X

iiSil;ll«lt»iiili;iChemicals

XXXXXXXXXXXXXXXXXXXXX

•:':':'•: .'•^-.•-.•-••••••••••-•-y " : ": •

Group

InorganicVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCVOCsvoc

HerbicidesHerbicides

Metals

Method

9030826082608260826082608260826082608260826082608260826082608260826082608270815081506010

MethodDetection

Limit (ug/L)

1001

0.50.60.70.51

0.80.50.50.6200.55

0.70.70.50.72511

100

siCal:iiil

6

FedMCL

70121.6760.8318.53

1431.37146000.00

1095

182.5

1/3/00- Revision 1.0 11 of 12 3-1_fsp.xls

Page 34: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

1 §1I a: a:•S3 <X)a ;§tl

<3

i

I

'8

0)

ICO

Io"E

ICO

"roCO(0O

IIt||!Ill

m11':&*m

;:;•«; ;:

::;;(j:;::

m

CM

OT

CN

14—oCN

Ia.a

o£>fljc1£coo>a>

CC

HI

a>a:

CSAO 15361

Page 35: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Field Sampling Plan

TABLE 3-2ANALYTICAL METHODS FOR GROUNDWATER MONITORING

ELEMENT OF WORKAnalytical Parameter

Volatile Organic Compounds

EDB and DBCP

Semi-volatile OrganicCompounds

Poly-nuclear AromaticCompounds (PAHs)

Metals (total and dissolved)

PCB/Pesticides

Dioxins/Furans

Chlorinated Herbicides

PH

Cyanide (total and amenable)

Total Extractable PetroleumHydrocarbons (TEPH)

General Mineral

AnalyticalMethod

EPA 8260

EPA8011/504

EPA 8270

EPA 8310

EPA 6010

EPA 8080

EPA 8290

EPA 81 50

EPA 150.2

EPA 9010

ModifiedEPA 801 5

EPA 300.1

PreparationMethod

EPA 5030A

NA

EPA 351 OB

EPA 3520B

EPA 3005A

EPA 351 OB

EPA 351 OB

EPA 3510B

NA

EPA 335.1,EPA 335.2

EPA 351 OB

NA

Containers

3 x 40 ml glass

1 x 0.5 liter amberglass with Teflon lid

2 x 1 liter amber glass

2x1 liter amber glass

2x1 liter polyethylene

1x1 liter amber glasswith Teflon lid

1 x 1 liter amber glass

1x1 liter amber glasswith Teflon lid

1 x 50 ml glass orpolyethylene

2 x 500 ml polyethylene

1x1 liter amber glass

1 x 250 ml glass orpolyethylene

Minimum SampleVolume Requirements

1x40 ml

1 x 0.5 liter

1 liter

1 liter

500 ml each sample

1 liter

1 liter

1 liter

50ml

500 ml each sample

1 liter

250ml

Preservation

HCI to pH < 2, Cool, 4°C

Cool, 4°C

Cool, 4°C

Cool. 4°C

HNO3topH<2,Cool. 4°C

Cool, 4eC

Cool, 4°C

Cool, 4'C

None

NaOH to pH > 12, plus 0.6 gAscorbic Acid, Cool, 4"C

HCI, Cool, 4CC

Cool, 4eC

H2SO< to pH <2 for N03/N

Holding Times

14 days

20 days

14 days

7 days

6 months

7 days

7 days

7 days

Immediately

14 days

14 days

28 days

14 days for Alkalinity

CSA015362

1/4/00-Revision 1.0 1of1 3-2_fsp.doc

Page 36: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Field Sampling Plan

Analytical Parameter

Volatile Organic Compounds

EDB and DBCP

Semi-volatile OrganicCompounds

Poly-nuclear AromaticCompounds (PAHs)

Metals (total and dissolved)

PCB/Pesticides

Dioxins/Furans

Chlorinated Herbicides

PH

Cyanide (total and amenable)

Total Extractable PetroleumHydrocarbons (TEPH)

General Mineral

AnalyticalMethod

EPA8260

EPA8011/504

EPA 8270

EPA 8310

EPA 6010

EPA 8080

EPA 8290

EPA 81 50

EPA 150.2

EPA 9010

ModifiedEPA 801 5

EPA 300.1

ANALYTJ

PreparationMethod

EPA5030A

NA

EPA 351 OB

EPA3520B

EPA3005A

EPA 351 OB

EPA 351 OB

EPA 351 OB

NA

EPA 335.1,EPA 335.2

EPA 351 OB

NA

: mmCALWifiCMJSFig

• .... :" ' i iiiiiiijContainers

3 x 40 ml glass

1 x 0.5 liter amber glasswith Teflon lid

2x1 liter amber glass

2x1 liter amber glass

2 x 1 liter polyethylene

1 x 1 liter amber glasswith Teflon lid

1x1 liter amber glass

1 x 1 liter amber glasswith Teflon lid

1 x 50 ml glass orpolyethylene

2 x 500 ml polyethylene

1 x 1 liter amber glass

1 x 250 ml glass orpolyethylene

EKi3»'~'*l — " ' "•' ' -Illfe - - - - - ....——-I,GROUNDWATERMCtiiilSi;;; ;:,;-:

Minimum SampleVolume Requirements

1x40 ml

1x0.5 liter

1 liter

1 liter

500 ml each sample

1 liter

1 liter

1 liter

50ml

500 ml each sample

1 liter

250ml

*iipii©Preservation

HCI to pH < 2, Cool, 4°C

Cool, 4°C

Cool, 4°C

Cool, 4°C

HNO3 to pH < 2, Cool, 4°C

Cool, 4°C

Cool, 4°C

Cool, 4°C

None

NaOHtopH>12, plus 0.6 gAscorbic Acid, Cool, 4°C

HCI, Cool, 4°C

Cool, 4°C

H2SO4 to pH <2 for N03/N

, • • -

Holding Times

14 days

20 days

14 days

7 days

6 months

7 days

7 days

7 days

Immediately

14 days

14 days

28 days

14 days for Alkalinity

CSA015363

1/4/00-Revision 1.0 Of1 L:\40000\47588\WP\SAP\3-2_fsp.doc

Page 37: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Field Sampling Plan

Analyses

VOCs

EDB and DBCP

SVOCs

PAHs

PCB/Pesticides

Chlorinated Herbicides

Dioxins/Furans

TEPH

Metals (total and dissolved

Cyanide (total and amenable)

General Minerals

PH

QField Samples*

2

2

2

2

2

2

2

2

2

2

2

2

llAUl QNTROLDuplicates (10% of

RelcTSJirtii|esJ

SAMPLING FREQUEN*Field Blanks (One/Day or

10% of Field Samples)

*\f ' ' . '*T - ../,.-- :-- . ; . . . . . : : - • :,,,,:• ,4i

Total SamplesSubmitted to Lab

2

2

2

2

2

2

2

2

2

2

2

2

;-; ;v^:: ; • rv^-.v":, ' ,,

»•——-;•; .-j^j^-." " " * • "

(5% of Samples to Lab)

QC Samples will be collected and analyzed as part of the Routine Groundwater Monitoring Activities at which time Compliance Monitoring samples will also becollected. QC samples will not necessarily be collected or analyzed from Compliance Monitoring locations.

n00

1/4/00-Revision 1.0 1 Of 1 3-3_fsp.doc

Page 38: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

mzgx

CSA015365

Page 39: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

APPENDIX A

QUALITY ASSURANCEPROJECT PLAN

CSA015366

Page 40: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart 11 - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

TABLE OF CONTENTS

1.0 INTRODUCTION............................................................................................................................ 1

2.0 PROJECT DESCRIPTION AND OBJECTIVES............................................................................... 2

3.0 PROJECT ORGANIZATION AND RESPONSIBILITY .................................................................. 3

4.0 QUALITY ASSURANCE REQUIREMENTS.................................................................................. 4

4.1 Data Quality Objective Process.............................................................................................. 44.2 Required Level of Analysis and Review.................................................................................44.3 Quality Control requirements................................................................................................. 54.4 Chemicals of Concern and Analytical Groupings.................................................................... 54.5 Data Quality Parameters........................................................................................................ 5

4.5.1 Accuracy.................................................................................................................. 64.5.2 Precision ..................................................................................................................64.5.3 Completeness ...........................................................................................................74.5.4 Representativeness....................................................................................................?4.5.5 Comparability...........................................................................................................?

4.6 Accuracy and Precision Limits............................................................................................... 84.7 ProjecT Required DETECTION Limits.................................................................................. 8

5.0 SAMPLING PROCEDURES............................................................................................................9

5.1 Sampling Rationale and Procedures....................................................................................... 95.2 Sampling Preservation and Holding Times............................................................................. 95.3 Sample Labels....................................................................................................................... 95.4 Decontamination................................................................................................................... 95.5 Inspection/Acceptance Requirements for Supplies and Consumables .................................... 10

6.0 SAMPLE CUSTODY..................................................................................................................... 11

6.1 Laboratory Custody Procedures........................................................................................... 116.2 Documentation.................................................................................................................... 12

6.2.1 Sample Identification.............................................................................................. 126.2.2 Daily Logbooks...................................................................................................... 126.2.3 Correction to Documentation................................................................................... 126.2.4 Photographs........................................................................................................... 136.2.5 Sample Classification, Handling, Packaging and Shipping........................................ 13

6.3 Project Files........................................................................................................................ 137.0 CALIBRATION PROCEDURES.................................................................................................... 14

7.1 FieldEquipmentCalibration................................................ ........ 147.2 Laboratory Equipment Calibration..................................... ....... 14

CSA015367

1/4/00 TOC-i L:\4000(M758»WP\SAP\47»»y20.doc

Page 41: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

8.0 ANALYTICAL PROCEDURES..................................................................................................... 15

8.1 volatile Organic Compounds................................................................................................ 158.2 Semi-Volatile Organic Compounds...................................................................................... 158.3 Metals................................................................................................................................. 158.4 Chloriiatedlferbicides........................................................................................................ 158.5 PESTICIDES/PCBS............................................................................................................168.6 DIOXINS/FURANS........................................................................................................... 168.7 ETHYLENE DIBROMIDE (EDB) AND l,2-DIBROMO-3-CHLOROPROPANE

(DBCP).............................................................................................................................. 168.8 Polynuclear aromatic hydrocarbons (pahS)........................................................................... 168.9 TOTAL EXTRACTED PETROLEUM HYDROCARBONS CTEPlf)................................... 168.10 General Minerals, pH and cyanide ....................................................................................... 168.11 Water Quality Monitoring.................................................................................................... 17

9.0 DATA REDUCTION, VALIDATION AND REPORTING ............................................................ 18

9.1 Analytical laboratory data review and reporting.................................................................... 189.2 Independent Data Validation Process.... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

9.2.1 Full Data Validation Sample Data Packages............................................................. 219.3 Analytical Results in Database Checking.............................................................................. 229.4 Data Tracking ..................................................................................................................... 229.5 Field Data Reduction........................................................................................................... 23

9.5.1 Field and Technical Data Reduction........................................................................ 239.5.2 Field and Technical Data Validation........................................................................ 23

9.6 Reconciliation with User Requirements................................................................................ 2310.0 INTERNAL QUALITY CONTROL............................................................................................... 24

10.1 Quality Control Assessment Procedure................................................................................. 2410.2 Field QC Checks................................................................................................................. 24

10.2.1 Field Duplicate....................................................................................................... 2410.2.2 Field Blanks and Equipment Blanks........................................................................ 2510.2.3 Trip Blank.............................................................................................................. 25

10.3 Laboratory QC Checks........................................................................................................2510.3.1 Matrix Spike/Spike Duplicate.................................................................................. 2610.3.2 Method Blank......................................................................................................... 2610.3.3 Laboratory Control Sample or Duplicate Control Sample......................................... 26

11.0 PRECISION, ACCURACY, AND COMPLETENESS ASSESSMENT .......................................... 28

11.1 Accuracy............................................................................................................................ 2811.2 Precision............................................................................................................................. 2911.3 Completeness...................................................................................................................... 29

12.0 PERFORMANCE AND SYSTEM AUDITS................................................................................... 31

12.1 Performance Audits............................................................................................................. 3112.2 Systems Audits.................................................................. .......31

13.0 PREVENTATIVE MAINTENANCE............................................ CSA015368 •--32

1/4/00 TOC-il L:\40000U7588VWlASAIM7S8gy20.doc

Page 42: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

13.1 Field Instruments................................................................................................................. 3213.2 Laboratory Instruments........................................................................................................ 32

14.0 CORRECTIVE ACTION................................................................................................................ 33

14.1 Laboratory Corrective Actions............................................................................................. 3314.2 Immediate Corrective Action............................................................................................... 34

15.0 QUALITY ASSURANCE REPORTS............................................................................................. 35

16.0 REFERENCES............................................................................................................................... 36

CSA015369

1/4/00 TOC-lii L:\4000<M7588\WPBAPVI7588y20.doc

Page 43: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

LIST OF ACRONYMS

C/T/DCERCLA

CirrusCLCWCOCCSCCVCWDCSDHSDQOsEE/CAEPAFIDFSPGC/MSHRGC/LRMS

LCSLIMSMCLMDLMPsMSMSDPCBsPQLsQAQAPPQA/QCRGMEWRI/FSRPDSOPsSVOCsTEPHVOCsWork Plan

Collection/Treatment/DisposalComprehensive Environmental Response, Compensation, and LiabilityActCirrus Environmental LaboratoryContaminated Liquids Component of Workchain-of-custodyCasmalia Steering CommitteeComplete ValidationComponent of WorksDuplicate Control SampleCalifornia Department of Health ServicesData Quality ObjectivesEngineering Evaluation/Cost AnalysisUnited States Environmental Protection Agencyflame ionization detectorField Sampling Plangas chromatographic analysis using mass spectroscopyhigh resolution capillary column gas chromatography/low resolution massspectrometryLaboratory Control SampleLaboratory Information Management Systemmaximum contaminant levelmethod detection limitMethod Proceduresmatrix spikematrix spike duplicatePesticides/Polychlorinated biphenylspractical quantitation limitsQuality AssuranceQuality Assurance Project PlanQuality Assurance/Quality ControlRegional Groundwater Monitoring Element of WorkRemedial Investigation/Feasibility Studyrelative percent differenceStandard Operating ProceduresSemi-Volatile Organic CompoundsTotal Extractable Petroleum HydrocarbonsVolatile Organic CompoundsRoutine Groundwater Monitoring Work Plan

CSA015370

1/4/00 TOC-iv L:\40000V47S8»WP«AIM7»Sy20.ek>c

Page 44: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

LIST OF TABLES

TABLE 4-1

TABLE 4-2TABLE 4-3TABLE 4-4

TABLE 4-5

TABLE 4-6

TABLE 4-7TABLE 4-8

TABLE 4-9

TABLE 4-10

TABLE 7-1TABLE 9-1

MEASUREMENT QUALITY REQUIREMENTS -GROUNDWATER SAMPLESEPA METHOD 8260: VOCs PRACTICAL QUANTITATION LIMITSEPA METHOD 8270: SEMI-VOCS PRACTICAL QUANTITATION LIMITSEPA METHOD 601OA, AND 7000 SERIES: METALS PRACTICALQUANTITATION LIMITSEPA METHOD 8150: CHLORINATED HERBICIDES PRACTICALQUANTITATION LIMITSEPA METHOD 8080: PESTICIDES / PCBs PRACTICALQUANTITATION LIMITSEPA 8290A DIOXINS/FURANS PRACTICAL QUANTITATION LIMITSEPA METHOD 8011 AND EPA METHOD 502: EDB/DBCP PRACTICALQUANTITATION LIMITSEPA METHOD 8310: POLYNUCLEAR AROMATIC HYDROCARBONSPRACTICAL QUANTITATION LIMITSEPA METHOD 9012: FOR CYANIDE, AND 9030: FOR SULFIDEPRACTICAL QUANTITATION LIMITSLABORATORY QA PROCEDURESSAMPLE PRESERVATION AND HOLDING TIME

CSA015371

1/4/00 TOC-v LA40000V47588\WP\SAPN47588y20.doc

Page 45: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

1.0 INTRODUCTION

The Casmalia Steering Committee (CSC) has prepared this Quality Assurance Project Plan(QAPP) for the Routine Groundwater Monitoring Element of Work (RGMEW) at the CasmaliaResources Hazardous Waste Disposal Facility (Site). The procedures discussed in this QAPPare applicable to the tasks described in the Routine Groundwater Monitoring Work Plan (WorkPlan). This QAPP outlines the procedures to be used to assure the data acquired duringsampling and analyses activities are sufficiently accurate and representative for the project.The CSC has prepared the QAPP to serve as a stand-alone document.

The QAPP complies with the following EPA guidance documents.

• Draft Supplement to Interim Guidelines and Specifications for Preparing QualityAssurance Project Plans (1986);

• U.S. EPA Region IX Guidance for Preparing Quality Assurance Project Plans forSuperfund Remedial Projects (1989);

• EPA Requirements for Quality Assurance Project Plans for Environmental DataOperations (1994):

• EPA Guidance for Conducting Remedial Investigations and Feasibility Studies(RI/FS) under CERCLA Interim Final (1988);and

• EPA Data Quality Objectives (DQO) Process for Superfund. Interim FinalGuidance (1993).

The remainder of the QAPP is organized as follows:

Section 2.0 - Project Description and ObjectivesSection 3.0 - Project Organization and ResponsibilitySection 4.0 - Quality Assurance ObjectivesSection 5.0 - Sampling ProceduresSection 6.0 - Sample CustodySection 7.0 - Calibration ProceduresSection 8.0 - Analytical ProceduresSection 9.0 - Data Reduction, Validation, and ReportingSection 10.0 - Internal Quality ControlSection 11.0 - Precision, Accuracy, and Completeness AssessmentSection 12.0 - Performance and System AuditsSection 13.0 - Preventative MaintenanceSection 14.0 - Corrective ActionsSection 15.0 - Quality Assurance ReportSection 16.0 - References

CSA015372

1/4/00 APPENDIX A - 1 L:\40000U758»WP\SAPM7M8y20.doc

Page 46: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

2.0 PROJECT DESCRIPTION AND OBJECTIVES

Section 2 of the Work Plan provides a description of the Site. Section 3.0 of the Work Planpresents the specific Objectives of the RGMEW. The two Components of Work- Water LevelMonitoring and Chemical Quality Monitoring-have the following Objectives:

Water Level Monitoring Component:

• Monitor the groundwater flow system conditions at the Site• Monitor the changes in groundwater storage• Monitor the hydraulic effectiveness of response systems• Monitor the vertical distribution of hydraulic head

Chemical Quality Monitoring Component:

• Locations with Site-related hazardous substances, pollutants, or contaminants• Quality of extracted water• Efficacy of response actions• Areas potentially affected by Site-related releases

The CSC will use the data collected during the RGMEW to achieve the above Objectives andintegrated it with other Elements of Work for the Site. Valid, appropriate data collected for otherElements of Work that meet DQOs will be included in the RGMEW to avoid samplingduplication. The Work Plan contains a more detailed discussion of Project Objectives andrationale.

CSA015373

1/4/00 APPENDIX A - 2 L:\«OOm4738»WWSAPV47M8yM.doc

Page 47: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

3.0 PROJECT ORGANIZATION AND RESPONSIBILITY

The CSC Contractor, with oversight from the CSC Project Coordinator, will implement theGroundwater Monitoring Work Plan, Field Sampling Plan (FSP) and QAPP. Figure 3-1 presentsthe lines of authority and communication. The Project organization and specific staffresponsibilities are discussed below.

The CSC Project Coordinator, Mr. Corey Bertelsen, is responsible for providing contractoversight. He is the sole point of contact for interfacing with EPA and other regulatory agencies.

The Contractor's Senior Project Manager, Ms. Sue Kraemer, is responsible for overall technicalquality and the Quality Assurance/Quality Control (QA/QC) of project deliverables submitted tothe Project Coordinator. Ms. Kraemer is also responsible for allocating the proper resources tothe Project to ensure successful performance. She is also responsible for implementing andadministrating the Project's Work Plan, FSP, and QAPP, and for ensuring that the Objectives ofthe Work Plan are met.

The Contractor's Field Work Manager, Mr. Scott Elkind, is responsible for field coordination andwill supervise the Site field technicians conducting the sampling activities.

The Contractor's QA/QC Officer, Ms. Kathy Phalen, will be responsible for overseeing fieldsampling and analysis activities and assuring that they are performed in accordance with theQAPP.

The Contractor's Health and Safety Officer, Rudy Von Burg, will be responsible for overseeingthe health and safety program for field and sampling activities.

CSA015374

1/4/00 APPENDIX A - 3 L.\40000\4758»\mSAl'\47»8y20.<loc

Page 48: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

4.0 QUALITY ASSURANCE REQUIREMENTS

4.1 Data Quality Objective Process

The DQO process (EPA, 1993) was used to define the data requirements to meet specificObjectives and Quality Assurance (QA) requirements for the RGMEW. The CSC qualitativelyapplied this process in the Work Plan and incorporated identification of decision types, datauses and needs in the design of the data collection program. Section 3.0 of the Work Planprovides a detailed discussion of the process.

QA is defined as the ability to ensure that the field and laboratory activities are performedcorrectly, and that the data can be confidently used to make decisions. The DQOs thatmandate the level of QA/QC for the Project include providing data of known and appropriatequality regarding groundwater and surface water characterization efforts; aquifer properties; andthe impact of extraction on the groundwater flow system. These data will be used to accomplishthe following objectives:

• characterize the groundwater flow system and quality of water;• evaluate the effectiveness of the response systems;• estimate the areas potentially affected by Site-related releases, and• aid in scoping future Remedial Investigation Feasibility Study (RI/FS) and

Engineering Evaluation/Cost Analysis (EE/CA) Component of Works (CW).

The most stringent use of these data is expected during the risk assessment component of theEE/CA CW and RI/FS CW. Therefore, the QA and quantification limits required for riskassessment purposes are considered adequate for other data uses. For this reason,quantification limits have been evaluated with respect to California wastewater treatmentstandards, and to regulated Federal and California maximum contaminant levels (MCLs).

4.2 Required Level of Analysis and Review

The specific project Objectives and data needs and uses are described in detail in Sections 3.0and 4.0 of the Work Plan, and summarized in Section 2.0 of the QAPP. Analytical data to becollected will potentially be used in site characterization, risk assessment, and treatmentresponse evaluations. The CSC will generate data of sufficient quality to be used for sitecharacterization and risk assessment by adhering to the following Project requirements.

• EPA analytical methods will be used when available. Section 8.0 summarizesanalytical methodologies for sample preparation and extraction and analysismethods for each procedure are summarized in Section 8.0. Section 16.0provides method references, and Appendix A includes the laboratory StandardOperating Procedures (SOPs).

CSA015375

1/4/00 APPENDIX A - 4 L:\4000(M7S8gWP\SAI'V«7M*yW.<loc

Page 49: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

• Internal QC sample frequencies (i.e., minimum QC sample frequencies) andprocedures to be utilized by the laboratories described in Section 10.0. QCsample frequencies and procedures are further specified in Appendix A.

• Completing data validation on 10 percent of the data. In addition, data packagesfrom the remaining data sets will be reviewed to ensure that the data are ofknown and appropriate quality, and are technically acceptable and representativeof site conditions.

4.3 Quality Control requirements

Field duplicates, field blanks, equipment blanks, and trip blanks will be collected and submittedto the analytical laboratory to provide the means to assess the field sampling program's dataquality. Field duplicate samples will be analyzed to check for sampling and laboratoryrepresentativeness. Field, equipment, and trip blank samples will be analyzed to check forprocedural contamination, cross-contamination, and laboratory contamination during shipmentand storage of samples. Matrix spike (MS), matrix spike duplicate (MSD), and laboratorycontrol samples will be analyzed to assess if recoveries falling outside acceptance windows areattributable to sample matrix interferences as opposed to laboratory analytical errors, in additionto measuring the accuracy of the analysis. Specific QC sample descriptions and minimumfrequency requirements are provided in Section 10.0 of the QAPP and in Section 4.0 of theFSP.

4.4 Chemicals off Concern and Analytical Groupings

Tables 4-2 through 4-10 provide the list of chemicals to be screened for each analytical method.The list of chemicals includes those identified for the Site in Section 3.0 of the Work Plan.Based on the laboratory methods, the following are the analytical groups:

1) Volatile Organic Compounds (VOCs)2) Semi-Volatile Organic Compounds (SVOCs)3) Metals4) Chlorinated Herbicides5) Pesticides/Polychlorinated biphenyls (PCBs)6) Dioxins/Furans,7) General Minerals8) EDB and DBCP9) Polynuclear Aromatic Hydrocarbons (PAHs).

4.5 Data Quality ParametersCSA015376

All data are potentially subject to some uncertainty and errors as they transition throughsampling, analysis, and reporting. Control and recognition of errors are important in assessingdata quality and preparing technical reports. The impact of data uncertainty and errors on the

1/4/00 APPENDIX A - 5 L:WWCM7588\WP\SAFVI7588y20.doc

Page 50: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

Project can be reduced in two ways: 1) through QC measures, and 2) through documentationof the quality or nature of the data error or uncertainty for the data generated.

To evaluate if the analytical data are consistent with the requirements of each task, anassessment of the performance of five data quality parameters must be conducted. These dataquality parameters are accuracy, precision, completeness, representativeness, and compatibilityand are discussed in this section. Quantitative limits for acceptable precision, accuracy, andcompleteness are also included in the assessment.

4.5.1 Accuracy

Accuracy is a measure of system bias and can be defined as the degree of agreement betweena measurement and an accepted reference or true value. The exact bias of a system is neverknown since the true values are inaccessible. However, inferences can be drawn from anevaluation of various analyses. The accuracy or bias of a laboratory analysis is evaluated byanalyzing standards of known concentration both before, and during sample analysis. Bias isalso evaluated by spiking a sample with a known quantity of a chemical and measuring itsactual, versus expected, recovery in analysis. Similarly, any bias introduced by laboratorycontaminants are detected during blank analysis. Analytical QC samples that will be used tocontrol analytical accuracy are discussed in Section 9.0. Analytical accuracy is also measuredthrough procedures presented in the SOP of most analytical methods. Section 11.1 of theQAPP details the formula for calculating accuracy as a percentage recovery (%R) of spikedsamples.

The accuracy of sampling procedures is also evaluated through use of blanks. Field blanks orequipment rinsate blanks demonstrate any bias introduced by contaminated samplingequipment, sample containers, or sample handling. Section 9.0 discusses QC samplescollected in the field that will be used to control the accuracy of the data.

4.5.2 Precision

Precision is the measure of variability between individual sample measurements of the sameproperty under prescribed similar conditions. The measurement of precision is made throughthe use of duplicate samples (also known as sample splits) taken at a regular, specifiedfrequency. Duplicate samples will be collected in the field and are expected to contain identicalcontaminant concentrations. Therefore, any variability in the reported analyses is attributable tovariability introduced by sampling, handling, or analytical procedures. Analysis of field duplicatesamples provides an estimate of overall sampling and analysis precision. Frequency ofcollection of field duplicate samples is discussed in Section 9.0. The precision of field duplicateanalyses is expressed as relative percent difference (RPD). Section 11.2 of this QAPP detailsthe formula for calculating RPD.

CSA015377

1/4/00 APPENDIX A - 6 L:\«OOOU7S8S\WP\SAPU7S88y20.doc

Page 51: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II • Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

4.5.3 Completeness

Analytical completeness is defined as the percentage of valid analytical results (includingestimated values) obtained from the measurement system compared to the total number ofanalytical results requested on samples submitted for analysis after review of the analyticaldata. The overall analytical completeness goal is 90 percent. Section 11.3 of the QAPP detailsthe formula for calculating analytical completeness.

If the overall analytical completeness goals are not met, the Project Manager will decide if themissing data are crucial or necessary to meeting project Objectives. The decision will be madeafter consulting the project QA/QC Officer and other senior project personnel. If it is decidedthat the data are insufficient, additional field samples will be collected and analyzed. Generally,necessary changes will be recommended for the subsequent sampling period and will besubmitted to EPA through the quarterly reporting process described in Section 4.0 of the WorkPlan.

4.5.4 Representativeness

Representativeness is the degree to which a set of data accurately and precisely represents acharacteristic of a population, parameter conditions at a sample point, or an environmentalcondition. Representativeness will be assessed by evaluating sample locations, frequency, andsample analysis. Representativeness will also be maintained during the sampling effort bycompleting sampling in compliance with procedures described in Section 5.0 of this documentand in respective sections of the FSP. Detailed descriptions of sampling procedures arecontained in the FSP.

4.5.5 Comparability

Comparability expresses the confidence with which one set of data can be compared(measuring the same property) to another set Data can be compared to the degree that theiraccuracy, precision, and representativeness are known and documented. Data are comparableif QC measures such as collection techniques, measurement procedures, methods, andreporting units are equivalent for the samples within a sample set. Data subject to QA/QCmeasures are deemed more reliable and therefore, more comparable, than data generatedwithout such measures.

CSA015378

1/4/00 APPENDIX A • 7 L:\«IOO(M758SWIASAPV475My20.doc

Page 52: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

4.6 Accuracy and Precision Limits

Laboratory accuracy and precision limits were selected to meet the project requirements and tobe cost-effectively performed by contract laboratories. The data will be used for riskassessment. The precision and accuracy limits were selected to be at least as stringent asthose contained in the EPA Contract Laboratory Program methods which are used for CERCLArisk assessment. The specified limits are well within the contract laboratory's capability, and willtherefore not impede project schedule or completeness requirements.

Table 4-1 specifies the anticipated accuracy (Percent Recovery) limits for laboratory controlsamples and matrix spikes are specified in Table 4-1. The limits will be used during QC reviewof data validation as specified in Section 9.0. Actual accuracy limits will be determined duringthe methods validation process for each matrix.

Precision limits for laboratory control samples and matrix spike recoveries are specified inTable 4.1. The limits will be used during QC review of data as specified in Section 9.0.

4.7 ProjecT Required DETECTION Limits

Tables 4-1 through Table 4-10 list the practical quantitation limits (PQLs) for each analyticalmethod referenced under the QAPP. The PQL is the lowest level that can be reliably achievedwithin specified limits of precision and accuracy during routine laboratory operating conditions.These PQLs were compared with potential regulatory levels (California Wastewater TreatmentStandards, and Federal and California MCLs) based on the potential future use of the data forrisk evaluation purposes. The laboratory must meet these limits using the analytical methodsspecified in Section 8.0.

Laboratory control percent recovery and precision limits are based on measurements ofduplicates, laboratory control samples, and/or matrix spike duplicates for quantitative tests.Prior to sample analysis, the contract laboratory will run method detection limit (MDL) studies forall analyses. MDLs will be established according to procedures contained in 40 CFR 136Appendix B. The MDL is the detection limit that takes into account the reagents, sample matrix,and preparation steps applied to a sample in specific analytical methods.

CSA015379

1/4/00 APPENDIX A - 8 L:WOOO<W7588\WP\SAP\475S8y20.d«

Page 53: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

5.0 SAMPLING PROCEDURES

This Section discusses sampling procedures.

5.1 Sampling Rationale and Procedures

Section 3.0 of the Work Plan provides the rationale for sample locations, sampling frequency,and analytical parameters. Tables 4-3 of the FSP list the locations, frequencies, and analyticalmethods for groundwater sample collection. Section 6.0 of the FSP describes samplingequipment and procedures.

5.2 Sampling Preservation and Holding Times

Proper sample preservation ensures sample integrity and prevents or minimizes degradation ortransformation of the constituents to be analyzed. Table 9-1 of the QAPP specifies thepreservation and holding time criteria for the chemical analyses. Section 7.0 of the FSPprovides further detail on sample preservation procedures and holding times.

5.3 Sample Labels

Adhesive-backed sample labels will be written with indelible ink and affixed to the containers. Ata minimum, the following information will be provided on each sample label:

• Sample identification number• Date and time of sample collection• Sampler's initials• Sample preservative

Additional information, as appropriate, will be included for sample types required by theapplicable sampling procedures designated in Section 6.0 of the FSP. Section 5.2 of the FSPspecifies sample designation procedures.

5.4 Decontamination

Decontamination of sampling equipment will be performed to prevent cross-contamination ofsamples. Decontamination will be performed before, between, and after each use of thesampling equipment unless disposable or dedicated sampling equipment is used. Section 6.4of the FSP describes the decontamination procedures for sampling.

CSA015380

1/4/00 APPENDIX A - 9 LA40000U75WWPSAIM7»8y20.doc

Page 54: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

5.5 Inspection/Acceptance Requirements for Supplies and Consumables

Items purchased for use on the Project will be accepted only after inspection by field personnel.Items will not be placed into use until they have been determined acceptable. Nonconformingitems will be physically segregated or clearly marked to avoid inadvertent use.Nonconformances identified during the receiving inspection process will be documented andresolved so that data quality will not be adversely affected.

CSA015381

1/4/00 APPENDIX A - 1 0 LMOOOOU758»WP\SAPU7S88y20.d«!

Page 55: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

6.0 SAMPLE CUSTODY

A sample is defined as physical evidence collected from a hazardous waste site, immediateenvironment, or another source. Because of the potential evidentiary nature of samples, thepossession of samples must be traceable from the time the samples are collected until they areintroduced as evidence in enforcement proceedings.

Chain-of-custody (COC) procedures are used to maintain and document sample possession.The principal documents used to identify samples and possessions can include:

COC records.Air bills or shipping records (e.g., Federal Express, Purolator, etc.)Field notebooksPhotographs of the investigationLaboratory logs.

A COC will be maintained for samples. All sample containers will be appropriately labeled andsealed as described in Section 7.0 of the FSP.

6.1 Laboratory Custody Procedures

The following laboratory custody procedures will be followed throughout the duration of theProject:

• A designated sample custodian will accept custody of the shipped samples andverify that the samples received match those on the COC record. The samplecustodian will properly document receipt of all arriving samples and note anyproblems or discrepancies between the COC record and the container and seal.Discrepancies will be immediately reported to the Field Work Manager. Pertinentinformation concerning as to shipment, pickup, and/or courier will be should beentered the "Remarks" section of the COC record's "Remarks" section. Thelaboratory custodian will enter the COC record's sample number(s) into alaboratory logbook. The laboratory custodian may use the sample identificationlabel number or assign a unique laboratory number to each sample.

• The laboratory custodian must assure that all samples are transferred to theproper analyst or stored in the appropriate secured area.

• Laboratory personnel are responsible for the care and custody of samples fromthe time they are received until the sample is exhausted or returned to thecustodian. The data of sample analysis are recorded on the laboratory reportform.

CSA015382

1/4/00 APPENDIX A - 1 1 L:\40000V47588\WIASAIM7588y20.doc

Page 56: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

• When sample analyses and necessary QA checks have been completed in thelaboratory, the unused portion of the sample and the container must be properlydisposed. All data sheets and laboratory records are retained as part of thepermanent documentation program. Concurrent with data reporting, a copy ofthe completed COC record will be returned to the Project Manager for inclusionin the Project file. The sample custodian will retain the original COC record.

6.2 Documentation

The following subsections describe documentation procedures that will be followed during fieldactivities.

6.2.1 Sample Identification

Samples collected during field activities will be identified according to the sample identificationschedule presented in Section 5.2 of the FSP.

6.2.2 Daily Logbooks

In addition to the COC records, bound field logbooks must be maintained by field personnel toprovide a daily record of significant field events, observations, and measurements. Entriesshould be signed and dated. Records maintained in the field logbook include, but may not belimited to the following observations:

Weather conditionsLocationField Team membersSample proceduresSample times, depths, identification numbers

Field logbooks are intended to provide data and observations that will enable participants toaccurately reconstruct events that occurred during the Project, particularly if field personnel arecalled upon to give testimony during legal proceedings.

All entries will be made in blue or black waterproof ink. Each page in the field logbook will besigned and dated by the person(s) making entries on that page. Field logbooks will be identifiedby the project number and stored in the field Project files when not in use. At the completion offield activities, the logbooks will be maintained in the permanent Project file.

6.2.3 Correction to Documentation

Unless prohibited by weather conditions, original data recorded in field logbooks, sampleidentification labels, and COC records are written in waterproof ink.

CSA015383

1/4/00 APPENDIX A - 12 LA«<XHM758awP\SAJ>U7588y20.doc

Page 57: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

Field personnel will correct entries by crossing a single line through the error and entering thecorrect information. Erroneous information should not be obliterated. Corrections must beinitialed and dated.

6.2.4 Photographs

Representative photographs of the Site may be taken. The picture number and roll number willbe logged in the field logbook to identify the area depicted in the photograph.

6.2.5 Sample Classification, Handling, Packaging and Shipping

Appropriate procedures will be used for sample handling activities as specified in Section 7.0 ofthe FSP. These procedures will be followed to ensure integrity of the samples that are shippedfor laboratory analysis.

6.3 Project Files

A Project file containing complete documentation of the activities associated with the Site will bemaintained in accordance with ICF Kaiser Engineers', or CSC's Policy and Procedures. TheProject files, at a minimum, will include the following:

• Project plans and specifications• Field logbooks and data records• Photographs, maps, and drawings• Sample identification documents• Completed COC records• The entire analytical data package provided by the laboratory, including QC

documentation• Data review notes• References and literature• Report notes and calculations• Quarterly reports• Correspondence and other pertinent information.

Project documentation will be indexed and checked for completeness, legibility, andidentification prior to inclusion in the Project file. The RGMEW files will be integrated with theShort-Term C/T/D CLCW for the Site.

CSA015384

1/4/00 APPENDIX A - 1 3 LMOOOOV»758*\WP\SAP\47588y20.doc

Page 58: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

7.0 CALIBRATION PROCEDURES

7.1 Field Equipment Calibration

All field equipment used on the Project will be calibrated and maintained in accordance withmanufacturer's instructions. Field checks and field calibration activities will be recorded in thefield log on a daily basis.

7.2 Laboratory Equipment Calibration

Calibration of all analytical instrumentation is necessary to ensure that the analytical system iscorrectly operating and functioning at the required sensitivity to meet project-specific DQOs.Each instrument will be calibrated in accordance with the manufacturer's recommendationsusing appropriate standard solutions. Appendix A's method-specific SOPs describe the types oflaboratory equipment and calibration procedures necessary to ensure achievement of DQOs.Table 7-1 summarizes the calibration procedures including frequency of analysis, quantitativecontrol limits, and corrective action requirements for each specific analytical method.Calibration procedures and analysis of samples for all proposed analytical methods will followU.S. EPA requirements specified in Tesf Methods for Evaluating Solid Waste - SW-846 (SW-846 [EPA, 1994]). Corrective action requirements for calibration problems are described inSection 14.0 of the QAPP. Corrective action may include, but may not be limited to: 1)reanalyzing samples; 2) recalibrating analytical instruments, and 3) preparing re-extractionsample batches. The laboratory notes will narrate data outliers. Laboratory equipmentcalibration is also briefly discussed in Section 9.0 of the QAPP. The laboratory performing theanalyses will be certified by the California Department of Health Services (DHS).

Documentation of all calibration activities will be maintained by the laboratory and will also besubmitted with the data packages. The documentation will become part of the permanentProject record and retrievable as necessary.

CSA015385

1/4/00 APPENDIX A - 14 L:V40000U7588\WP\SAlA475g8y20.doc

Page 59: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmolia Hazardous Waste Management Facility Quality Assurance Project Plan

8.0 ANALYTICAL PROCEDURES

Table 4-1 specifies the analytical and extraction preparation methods to be used for samplescollected from the Site. Section 9.0 presents the accompanying data validation procedures.Analyses for each analytical method will be performed following SW-846 requirements (EPA,1994).

Chemical analyses will be performed by Cirrus Environmental Laboratory (Cirrus) or BCLaboratories. Appendix A provides standard operating procedures for each referencedanalytical method. Any alternative laboratories used will meet at a minimum the requirements ofthis QAPP.

8.1 volatile Organic Compounds

VOCs include compounds from various classes, such as halogenated organics, volatilepesticides, non-halogenated organics, and aromatic organics. VOCs will be analyzed by EPAMethod 8260 as specified in Table 4-1. Section 4.0 (Table 4-2) lists the chemicals and PQLs.EPA Method 8260 method employs gas chromatographic analysis using mass spectroscopy(GC/MS). The volatile compounds are introduced into the gas chromatograph by the purge-and-trap method, or by direct injection in limited applications.

8.2 Semi-Volatile Organic Compounds

SVOCs will be analyzed by GC/MS using EPA Method 8270. Samples will be extracted withmethylene chloride using a pH-adjusted liquid, liquid extraction procedure (EPA method 351 OB).The PQLs for SVOCs are listed in Section 4.0 (Table 4-3).

8.3 Metals

Groundwater samples will be analyzed by EPA Method 6010A and 7470/7471 for the metalslisted in Table 4-4. Sample preparation and extraction will consist of solubilization and aciddigestion (EPA Method 3005A). Table 4-4 lists PQLs for these metals.

8.4 Chlorinated Herbicides

Chlorinated herbicides will be analyzed by EPA Method 8150. The chemicals and PQLs arelisted in Section 4.0 (Table 4-5). EPA Method 8150 employs a GC/electron capture technique,and is prepared using a separatory funnel and continuous liquid extraction similar to EPAMethod 351 OB.

CSA015386

1/4/00 APPENDIX A - 15 L:\4XWm4758RWPiSAF\47588y20.doc

Page 60: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

8.5 PESTICIDES/PCBS

PCBs and pesticides will be analyzed by EPA Method 8080 (organochlorine pesticides). Thismethod employs various HPLC or GC analyses. A measured volume or sample weight(approximately 1 liter) is extracted at neutral pH with methylene chloride using either aseparatory funnel (EPA Method 351 OB) or a continuous liquid-liquid extractor (EPA Method3520B). Table 4-6 lists the PQLs for each compound.

8.6 DIOXINS/FURANS

Dioxins/Furans will be analyzed by EPA Method 8290 using a matrix-specific extraction, analytespecific cleanup, and high resolution capillary column gas chromatography/low resolution massspectrometry (HRGC/LRMS) techniques. Sample preparation and extraction will consist ofcontinuous liquid-liquid extraction (EPA Method 3510B). Table 4-7 presents the PQLs for thisanalysis.

8.7 ETHYLENE DIBROMIDE (EDB) AND 1.2-DIBROMO-3-CHLOROPROPANE(DBCP)

EDB and DBCP will be analyzed by EPA Method 8011 or EPA method 504 depending on thelaboratory used. This specific analysis is run to achieve method detection limits that are at orbelow regulatory levels for drinking water. Table 4-8 presents the PQLs for these analyses.

8.8 Polynuclear aromatic hydrocarbons (pahS)

PAHs will be analyzed by EPA Method 8310. Samples will be extracted with methylene chlorideusing a pH-adjusted liquid-liquid extraction procedure (EPA Method 3510). The PQLs for PAHsare listed in Table 4-9.

8.9 TOTAL EXTRACTED PETROLEUM HYDROCARBONS (TEPH)

TEPHs will be analyzed by EPA Method 8015 and extracted by EPA Method 3510B. The PQLsfor this analysis are presented in Table 4-1. Extracted compounds will be introduced into theGC by direct injection and detected by a flame ionization detector (FID).

8.10 General Minerals, pH and cyanide

General minerals will be analyzed by EPA 300 series methods. Analysis for pH will beperformed by EPA Method 150.2. Cyanide will be analyzed by EPA Method 9010/9012.Samples are acidified and combined with magnesium chloride reagent and vacuum distilled.The quantitation limits for these analyses are listed in Table 4-1 and 4-10.

CSA015387

1/4/00 APPENDIX A - 16 L:\4000(M75»WP\SAJM7SWy20.doc

Page 61: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

8.11 Water Quality Monitoring

During well purging activities, water quality measurements will be collected to verify thatgroundwater, representative of that held in the formation, is obtained for sample analysis. Asdescribed in the FSP, water quality parameters such as temperature, pH and conductivity will bemeasured until they stabilize to within 10 percent over two successive readings. Because alow-flow purge technique will be used, it is anticipated that less than three well volumes will bepurged to obtain a representative sample.

CSA015388

1/4/00 APPENDIX A - 1 7 L:\40000\47S88\WP\SAP\47S88y20.do<!

Page 62: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

9.0 DATA REDUCTION, VALIDATION AND REPORTING

Cirrus or BC Laboratory will provide analytical services for the Project. The Laboratory Manageror designee will check the analytical data generated by the laboratory for accuracy andcompleteness.

The data validation process for the Project will consist of data generation, reduction, and twolevels of review. The analytical laboratory will conduct the first level of review, and the CSC'scontractor will independently conduct the second. The analytical data generated by thelaboratory will be reviewed by the CSC's contractor for 1) accuracy; 2) precision;3)completeness; 4) representativeness, 4) compatibility; and 5) additional parameters outlinedbelow.

9.1 Analytical laboratory data review and reporting

The analytical laboratory data reviewer with initial responsibility for verifying the completeness ofthe data will conduct the first level of review. This review may contain multiple sub-levels. Alldata are generated and reduced in accordance with protocols specified in the analyticalmethodology. The laboratory data reviewer will evaluate the quality of the work based on anestablished set of laboratory guidelines and this QAPP. This person will review the datapackage to ensure:

Sample preparation information is correct and complete.Analysis information is correct and complete.The appropriate SOPs have been followed.Analytical results are correct and complete.QC samples are within appropriate QC limits.Special sample preparation and analytical requirements have been met.Documentation is complete (i.e., all anomalies in the preparation and analysishave been documented; and holding times have been documented).

The laboratory will perform the in-house analytical data reduction and QA review under thedirection of the laboratory Data Review Supervisor. The laboratory Program Administrator isresponsible for assessing data quality. The laboratory Program Administrator is also chargedwith advising the Project Manager of any data that were rated "preliminary", "unacceptable", or,contained other notations that would caution the data user of possible unreliability. Datareduction, QA review, and reporting by the laboratory will be conducted according to thefollowing guidelines.:

• Raw data produced by the analysis is processed and reviewed for attainment ofQC criteria as outlined in the QAPP, established EPA methods, and overallreasonableness.

CSA015389

1/4/00 APPENDIX A - 1 8 LWOO<M75»WP\SAJM7»8y20.doc

Page 63: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

• After entry into the Laboratory Information Management System (LIMS), acomputerized report is generated and sent to the laboratory data reviewer.

• The Data Reviewer will decide if further analysis of any sample is required.

• Upon acceptance of the preliminary reports by the data reviewer, final reports willbe generated.

• Laboratory data reduction procedures will be those specified in the respectivemethods and those described in the laboratory SOPs.

The laboratory will prepare and retain full analytical and QC documentation. The laboratory willreport the data as a delivery package consisting of a group of 20 environmental samples orfewer, along with the supporting QC data. Groupings of samples (Sample Delivery Group) willbe assigned by the field sampling personnel. The laboratory will provide the following hard copyinformation in each analytical data package. The package will be submitted in accordance withQA requirements for the Project and the Laboratory Documentation Requirement for DataValidation (EPA 1993):

• Laboratory delivery group number.

• COCs.

• Cover sheet listing the samples included in the report and narrative commentsdescribing problems encountered in analysis. The cover sheet will also identifyanalyses not meeting QC criteria, including holding times as specified in Table 9-1.

• Analytical results of target compounds arranged by analytical testing method,identified and quantified with appropriate qualifiers.

• Reporting quantification limits related to each of the sample analytes.

• Data summary tables for all laboratory control samples by matrix and analysistype.

• Analytical results for QC sample spikes; sample duplicates; initial calibration andcontinuing calibration verification of standards and blanks; standard proceduralblanks; and laboratory control samples.

• Tabulated analytical results of the project samples in electronic format includingdetection limits, qualifiers, and corresponding measurement units.

• Raw data system printouts (or legible photocopies) and chromatograms thatidentify

a) - sample identification

CSA015390

1/4/00 APPENDIX A - 1 9 t:\40000\4758gWP\SAlA47388y20.doc

Page 64: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalki Hazardous Waste Management Facility Quality Assurance Project Plan

b) - date of reported analysisc) - analyst, parameters analyzedd) - initial calibration curvee) - calibration verificationsf) - method blanksg) - reported sample dilutions, if anyh) - spikes, and control samplesi) - sample spiking levelsj) - preparation and extraction logsk) - run logs.

• Summary reports for initial and continuing calibrations listing 1) relative responsefactors and percent relative standard deviations; 2) MS/MSD percent recoveriesand spike amounts; 3) laboratory blank results; and 4) a method blank summarylisting method blanks and associated samples.

The data reduction and the QC review steps will be documented, signed, and dated by theProject Administrator.

All laboratory qualifiers assigned by the laboratory will be described in the narrative thataccompanies the data package. This narrative will include the identification of samples notmeeting total QC criteria as specified in this QAPP and cautions regarding non-quantitative useor unusability due to out-of-control results.

9.2 Independent Data Validation Process

The second level of review and validation will be completed by Project QA/QC Officer ordesignee to provide an independent review of the data package. The reviewer will assess alldata packages provided by the laboratory for completeness and compliance with stipulatedrequirements in the QAPP. This review will not be a quantitative validation of the data. A goalof 10 percent of the data will undergo a more rigorous Data Validation as described in Section9.2.1 of this QAPP.

Results from the validation process will be used to provide an evaluation of overall laboratoryperformance. The QC Review will assess the laboratory's:

• Accuracy, by evaluating spike sample recoveries, laboratory control sampleanalyses, and surrogate spike recoveries.

• Precision of analysis, by evaluating matrix duplicate or matrix spike duplicateanalytical results.

• Representativeness, through evaluation of collocated duplicate sample results.

• Comparability, by evaluating sample-specific reporting limits, units of measure,and adherence to specified analytical methodology.

CSAO15391

1/4/00 APPENDIX A - 20 L:\«000\47J8»WP\SAIM7588y20.d«

Page 65: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmoiia Hazardous Waste Management Facility Quality Assurance Project Plan

• Completeness, by evaluating overall analytical completeness and the presenceof valid sample data for collected samples.

The sample analysis data packages will contain all information necessary to perform aComplete Validation (CV) so that any data undergoing a QC review can later be subjected to aCV if warranted by subsequent events. Samples analyzed will follow the appropriate SW-846(EPA, 1994) procedures and will be validated in accordance with EPA validation procedures.

9.2.1 Full Data Validation Sample Data Packages

9.2.1.1 Validation off Volatile Organic Analyses

Volatile organic data for critical samples will undergo validation of the following requirements inaccordance with EPA Contract Laboratory Program National Functional Guidelines for OrganicData Review, February 1994:

Sample Handling and CustodyHolding TimesGC/MS Instrument Performance CheckInitial CalibrationContinuing CalibrationBlanksSystem Monitoring CompoundsMatrix Spikes/Matrix Spike DuplicatesInternal StandardsTarget Compound IdentificationCompound Quantitation and Reported Contract Reported Quantitation LimitsTentatively Identified CompoundsSystem PerformanceOverall Assessment

9.2.1.2 Validation off Pesticides

Pesticides' data for critical samples will undergo validation of the followingrequirements in accordance with EPA Contract Laboratory Program NationalFunctional Guidelines for Organic Data Review, February 1994 Sample Handlingand CustodyHolding TimesPesticide Instrument PerformanceInitial CalibrationBlanksSurrogate SpikesMatrix Spikes/Matrix Spike DuplicatesPesticide Cleanup Checks CSA015392

1/4/00 APPENDIX A-21 L:\«M<M758S\WI'\SAJM7588y20.doc

Page 66: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

• Target Compound Identification• Compound Quantitation and Reported Contract Reported Quantitation Limits• Overall Assessment

9.2.1.3 Validation of Other Analytical Data

Other analytical data, including SVOCs, PCBs, Oioxins/Furans, and metals, will undergovalidation of the following requirements using guidance from "ERA Contract Laboratory ProgramNational Functional Guidelines for Organic Data Review," February 1994, pertinent to theanalytical method:

• Sample Handling and Custody• Holding Times• Calibration/Instrument Performance Monitoring• Blank Contamination• Spike Recoveries (matrix spikes, surrogate spikes, and laboratory control

samples as specified in the QAPP).• Duplicate analysis precision (field duplicates, laboratory duplicates and matrix

spike duplicates).• Target Compound Identification• Compound Quantitation and Reported Detection Limits• Overall Assessment

9.3 Analytical Results in Database Checking

The data will be stored in a database created with Microsoft Access®, a Windows-baseddatabase platform. The data will be formatted to comply with the Data Management Section ofthe Work Plan. Inconsistent or incomplete data are problems common to all databaseapplications. Accordingly, the database will incorporate error-checking and correction routinesand data inventory printouts will be manually checked. Data checks will confirm that:

• the data is free of viruses;• the data has been entered in the correct format;• all necessary fields contain entries; and.• fields do not contain illogical entries.

The CSC's contractor will identify problems and correct or arrange for the proper party to makethe correction(s) as appropriate. When an inconsistency in a data points identified, it must beconfirmed as an error in order to be corrected.

9.4 Data TrackingCSA015393

Analytical data will be delivered from the laboratory electronically and incorporated into thedatabase. Sample designation information collected on the sample integrity sheets will be

1/4/00 APPENDIX A - 22 L:\«00<A4758»WP«AI>U7S88y20.doc

Page 67: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

included. Database files will be created and the data will be processed in accordance with theprocedures outlined in the Work Plan. The CSC and its contractor will have access to the databased on need.

9.5 Field Data Reduction

The field and technical (non-laboratory) data generated at the Site can generally becharacterized as either objective or subjective. Objective data include all direct measurements,such as field screening and analytical parameters, and water level measurements. Subjectivedata include certain descriptions and observations (e.g., clarity of a water sample).

9.5.1 Field and Technical Data Reduction

Field personnel will record field data in bound field notebooks and on standard forms. Forexample, field team members will keep a chronological log of sampling activities, a descriptivelog of depth to water in each well, and other pertinent well information (i.e., visibly checkedcasing, recharge problems, missing well caps, etc.). It will be the field personnel's responsibilityto photocopy field logs, (including notebook pages and standard forms). Field personnel willprovide photocopies to the Field Work Manager who, in turn, will maintain field log files.

After checking the validity of data in the field notes and on standard forms, the Field WorkManager will set up data files for direct input into the Project database. Subjective data will befiled in hard copy for subsequent review by the Project Manager and appropriate incorporationin technical reports.

9.5.2 Field and Technical Data Validation

Validation of objective field and technical data will be performed at two different levels. The firstlevel of data validation will be performed at the time of collection following standard proceduresand QC checks to ensure that the correct codes and units have been included. Anyinconsistencies or variances discovered by the Field Work Manager will be resolvedimmediately, if possible, by seeking clarification from the field personnel responsible forcollecting the data. Subjective field and technical data will be validated by the Project Managerduring a review of field reports for reasonableness and completeness. In addition, randomchecks of sampling and field conditions will be made by the Field Work Manager and theQA/QC Officer.

9.6 Reconciliation with User Requirements

Data will be assessed by comparing validated data results with the DQOs identified in Section4.0 of the Work Plan. In the event that an Objective has not been achieved, the CSC ProjectCoordinator will be notified. Limitations and sources of the data will be clearly identified in theSemi-annual Report

CSA015394

1/4/00 APPENDIX A - 23 L:\40000\475»WP«SAIM7»Sy20.<loc

Page 68: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

10.0 INTERNAL QUALITY CONTROL

10.1 Quality Control Assessment Procedure

Field duplicates, trip blanks, and rinsate blanks will be collected and submitted to the analyticallaboratory to assess the quality of the data resulting from the field sampling program. Likewise,the laboratory will produce internal samples consisting of laboratory control samples, laboratoryduplicates, and method blanks to assess the quality of data resulting from laboratoryprocedures.

Field duplicate samples will be analyzed to check for sample and laboratory reproducibility. Tripblank samples will be analyzed to check for procedural contamination, cross-contamination, andlaboratory contamination during shipment and storage of aqueous samples. The rinsate blankswill be used as a measure of contamination of samples from the sampling equipment. Thematrix spike and laboratory control samples will be analyzed to assess if recoveries that falloutside acceptable ranges are attributable to sample matrix interference, or, laboratoryanalytical errors. The accuracy of the analysis will also be measured. Laboratory duplicates forpesticide analyses and matrix spike duplicates for organic analytes will be analyzed to evaluatelaboratory reproducibility. The following sections present specific QC sample descriptions andfrequency minimums for collection requirements. Appendix A provides the Project analyticallaboratory's QA/QC documentation.

10.2 Field QC Checks

The following subsections outline the field QC samples that will be collected and analyzedduring field efforts.

10.2.1 Field Duplicate

A field duplicate is an environmental sample that is divided into two separate aliquots. Thealiquots are processed separately and the results are compared to evaluate the effects of thematrix on the precision of the analysis. Results are expressed as RPD between the duplicatealiquots analyzed. Duplicate field samples will be obtained at a rate of 10 percent of the totalnumber of original samples collected. Field duplicate samples will be identified and labeled inaccordance with the sample nomenclature procedures described in Section 5.2 of the FSP.Consequently, field duplicate samples will be submitted "blind" to the analytical laboratory. If theresults of field duplicates differ dramatically, an analytical problem may exist, or, the matrix isnot homogeneous and data must be critically assessed.

CSA015395

1/4/00 APPENDIX A - 24 L:\4000<M758»vmSAPV47»8y20.ctoc

Page 69: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

10.2.2 Field Blanks and Equipment Blanks

Field blanks are used to evaluate the adequacy of field decontamination procedures. Fieldblanks are prepared by pouring blank water directly into sample containers. Equipment blanksare prepared in the field by pouring "clean" deionized, distilled, or laboratory preparedorganic-free water over or through sample collection devices or equipment. An equipment blankis prepared at a frequency of one per sampling day per equipment type per environmentalmedia, but no more than 10 percent of the total number of samples.

10.2.3 Trip Blank

A trip blank is a pre-cleaned and pre-certified, 40 ml VOC sample vial filled with contaminant-free water at the laboratory. The trip blank is shipped to and from the field with the samplecontainers. It is not opened in the field, and therefore, provides a test for contaminationresulting from sample preservation, site conditions, transport, or, sample storage, preparationand analysis. Trip blanks are used to detect cross-contamination of VOCs, and therefore, areonly analyzed for VOCs. A trip blank is submitted at a frequency of one per sample shipped tothe laboratory.

10.3 Laboratory QC Checks

The following are the QA/QC Program's stated requirements:

• verify that procedures are documented, inclusive of any changes inadministrative and/or technical procedures;

• document that analytical procedures have complied with sound scientificprinciples, and have been validated;

• monitor the performance of the laboratory by a systematic inspection program,and provide for corrective action as necessary;

• verify that data are properly recorded and archived; and

• validate the analytical procedures and extractions (if performed), on surrogatesanalyzed by the lab for all organic parameters.

Two types of QA checks will be used to assess the production of analytical data of known anddocumented quality. These include:

• Program quality assurance• Analytical method quality control

All laboratory procedures are documented in writing as either SOPs or Method Procedures(MPs), and are edited and controlled (see Appendix A). Internal QC procedures for analytical

1/4/00 APPENDIX A - 25 L:\40000\475S8\VmSAP\475S8y20.doc

Page 70: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

services will comply with the analytical laboratory's SOPs. These procedures specify the typesof QC samples required (sample spikes, method spikes, reference samples, controls, blanks);the frequency of each QC sample; the compounds to be used for sample spikes; and the QCacceptance criteria.

In each data package, the laboratory will document that analytical QC functions have been metAny analyzed samples that fail to meet QC criteria will be reanalyzed by the laboratory, if thelaboratory control procedures indicate that the laboratory procedures were not within anacceptable range. Reanalyzation of samples will occur if sufficient sample volume is availablefor reanalysis. QC check samples (method blanks, MS/MSD, duplicates, etc.) will be analyzedconcurrent with the sample batch to which they are assigned. Any deviations or modificationsfrom the published EPA procedures or the SOP must be documented and clearly noted in thecase narrative. A description of the laboratory produced QC samples is given below.

10.3.1 Matrix Spike/Spike Duplicate

MS/MSD sample analyses are used to evaluate the effect of the sample matrix on the accuracyand precision of the laboratory method. An MS/MSD is an environmental sample to whichknown concentrations of analytes have been added. The MS/MSD is taken through the entireanalytical procedure and the recovery of the analytes calculated. Results are expressed as apercentage of the recovery of the known amount spiked. The laboratory will be required to runa blank spike at the same level as the MS. MS/MSD analysis will be conducted at a rate of onefor every matrix batch of 20 samples. The sample for MS/MSD analysis will be designated onthe COC by field sampling personnel as laboratory a QC sample; extra sample volume will becollected for MS/MSD samples. A determination will be made in the field concerningrepresentative matrices. Table 4-1 lists QC Acceptance limits for MS/MSD percentagerecoveries and RPDs.

10.3.2 Method Blank

A method blank consists of analyte-free deionized water. The method blank is carried througheach step of the analytical methodology. Method blanks will be analyzed at a rate of one forevery 20 environmental samples or analytical batch, whichever is greater.

10.3.3 Laboratory Control Sample or Duplicate Control Sample

A Laboratory Control Sample (LCS), otherwise referred to as a Duplicate Control Sample(DCS), is a standard reference material of similar matrix to the environmental samples beingprepared and analyzed in a batch. It is used to both validate the preparation method andcontrol instrument precision and accuracy. LCSs or DCSs are analyzed at a rate of one 1 forevery 20 samples or one for every analytical batch, whichever is greater. At least 80 percent ofthe compounds in the LCS/DCS must meet acceptance criteria as described in Section 4.0.Otherwise, affected samples will be reanalyzed, or resampled and reanalyzed.

CSA015397

1/4/00 APPENDIX A - 26

Page 71: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

Table 7-1 provides a summary of the laboratory internal QC checks, frequency of runs, andquantitative control limits. Appendix A presents specific internal QC procedures and correctiveaction requirements (Section 14.0) for specific analytical methods.

CSA015398

1/4/00 APPENDIX A - 27 L:\«00(M75»WP«5AlM75Wy20.*>«

Page 72: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

11.0 PRECISION, ACCURACY, AND COMPLETENESS ASSESSMENT

The reliability and credibility of analytical laboratory results are established through a program ofutilizing randomly selected duplicate analyses and trip and field blanks, and analyzing standardsor spiked samples.

Accuracy is reported as the percent recovery of a parameter from a sample of known valuewithin a given analytical procedure. Precision of analytical results may be established as therelative percentage difference from true values, or, from the mean of replicate analyses.

The procedures described herein are designed for the acquisition of accurate and precise datafor each analytical method and analyst. To ensure that reliable data continue to be produced,systematic checks must show that test results remain reproducible, and that the methodology isactually measuring the quantity of analyte in each sample. Quality assurance begins withsample collection and only ends when the resulting data have been reported.

The following procedures will be used to evaluate data accuracy, precision, and analyticalcompleteness.

11.1 Accuracy

Accuracy protocols determine bias in a measurement system. Sources of errors include thesampling process; field contamination; handling; sample matrix; sample preparation; andsample analysis techniques. Analytical accuracy may be assessed using QC samples(laboratory control samples and surrogates) and matrix samples. Accuracy is expressed aspercent recovery for laboratory control samples and surrogates as follows:

Percent Recovery = X * 100T

where X = the observed value of measurements

T = "true" value

These recoveries will be compared with the control limits (Table 4-1). Outliners will beassessed in conformance with other QC data. If the surrogate percent recovery limits areexceeded, the data will be assessed as specified in Section 9.1.

The matrix spike and matrix spike duplicate sample results will be used to calculate the percentrecovery as an indicator of matrix effects as follows:

Percent Recovery = X-S x 100

(for matrix spikes) CSA015399

1/4/00 APPENDIX A - 28 L:\40000U7588\WP»SAIM7588y20.doc

Page 73: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart 11 - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

where X = observed value after spike

S = sample value

T = amount spiked

The matrix spike and matrix spike duplicate percent recoveries will be compared withlimits shown in Table 4-1 and data assessed in accordance with Section 9.0.

11.2 Precision

Precision measures the reproducibility of measurements under a given set of conditions. It is aquantitative measurement of the variability of a group of measurements compared to theiraverage value.

Precision will be expressed as relative percent difference (RPD) for duplicate environmentalsamples, duplicate control samples, and for MS/MSD samples, as follows:

RPD(%) = S-D X10Q

(S + D) 12

where S = first sample value (original)

D = second sample value (duplicate)

The RPDs will be compared with the limits in Table 4-1 and data assessment conducted inaccordance with Section 9.0.

11.3 Completeness

The Project Manager will assess the data's usefulness and fulfillment of QA requirements afterreviewing the data packages. The assessment will address sample collection; sample handling;field data; consideration of blank values and field duplicate values; and additional flagging ofqualified data for use at each Site location.

The analytical completeness will be calculated by deriving the ratio of the sum of the acceptableand estimated analytical results to the total number of analytical results requested on samplessubmitted for analysis. The calculation is as follows.

% Completeness = ____Accepted Analytical Results_______Total Number of Analytical Results Requested

CSAO15400

1/4/00 APPENDIX A - 29

Page 74: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

If the 90 percent confidence goal is not met, the Project Manager will decide if the data aresufficient for characterization or other purposes. If the data are inadequate, additional fieldsamples may need to be collected to accomplish Project goals. The CSC's Project Coordinatorwill be involved in making decisions to resample and reanalyze data based on the extent of thedata's deficiencies and importance in the overall context of the Project.

CSA015401

1/4/00 APPENDIX A - 30 L:\4000<M758»WIASAIM7588y20.doc

Page 75: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

12.0 PERFORMANCE AND SYSTEM AUDITS

Two types of audits may be conducted to monitor implementation of the QAPP and SOPs. Aperformance audit involves submittal of a blind sample of known composition to the laboratory,or submittal of a replicate sample to an alternate laboratory for quantitative comparison with thedata routinely obtained by the measurement system. A systems audit involves on-siteevaluation of the laboratory or other project activities for compliance with the QAPP and SOPs.

12.1 Performance Audits

A performance evaluation sample may be submitted to the laboratory if problems are identifiedin the analytical results. Additional performance audits will be performed at the request of theAnalytical Chemist, QA Manager, or Project Manager. These audits will be conducted whenany one of these individuals decide that laboratory data packages contain discrepancies thatwarrant further investigation. Any discrepancies identified in performance audit results will beresolved with the laboratory before submitting additional Project samples for analysis.

12.2 Systems Audits

One systems audit will be performed during the field activities to allow for meaningful and timelycorrective actions, if warranted. At the direction of the QA Manager, and dependent on theresults of the initial audit, follow-up audits of field activities may be performed to confirmeffectiveness of corrective actions. Additional systems audits may also be performed at therequest of the client or the Project Manager. Systems audits of the laboratory may also beperformed. Audits will be scheduled with the Laboratory Manager and care will be taken tominimize interference with work activities.

CSA015402

1/4/00 APPENDIX A - 31 L:VWOO<M758»WF\SAJM75»8y20.doc

Page 76: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

13.0 PREVENTATIVE MAINTENANCE

Equipment and instruments used in the Site investigations will have prescribed routinemaintenance and calibration schedules. Qualified personnel will perform preventivemaintenance. These actions will assist in efforts to provide analytical data that are of sufficientquality to meet quality assurance requirements.

13.1 Field Instruments

All field instrumentation, sampling equipment, and accessories will be maintained in operatingorder. Calibrations will be made in the field daily or at the manufacturer's recommendedfrequency. Maintenance will be performed according to the manufacturer's specifications asnecessary.

13.2 Laboratory Instruments

The laboratory will follow the method-specific procedures for preventative and unscheduledmaintenance, calibration, and corrective action. This section identifies the general maintenanceroutines that must be followed by the laboratory to meet the Project's minimum requirements.

The laboratory is responsible maintaining its laboratory equipment. Preventive maintenance willbe provided on a scheduled basis to minimize down time and interruption of analytical work. Allinstruments will be maintained in accordance with manufacturer's recommendations and goodlaboratory practice.

Designated laboratory personnel will be trained in routine maintenance procedures for all majorinstrumentation. Repairs will be made by either qualified staff or the instrument manufacturer'sservice engineers and technicians. The laboratory will have back up instruments to minimizedown time potential. All maintenance and analytical runs will be documented and kept inpermanent logs. These logs will be available for review by auditing personnel.

The laboratory will record both scheduled and unscheduled maintenance, includingmaintenance related to operational failures. The designated laboratory Operations Coordinatorwill regularly review maintenance records to ensure that required maintenance is occurring.Details of these procedures are provided in the method-specific SOPs located in Appendix A ofthis QAPP.

CSA015403

1/4/00 APPENDIX A - 32 L:\40000\47SW\WP\SAP\47588y20.doc

Page 77: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

14.0 CORRECTIVE ACTION

Any nonconforming conditions identified during performance or system audits that cannot beimmediately corrected to the investigator's satisfaction will be documented and resolved at theearliest opportunity by the QA Manager. The QA Manager will confirm completion of allrequired actions.

14.1 Laboratory Corrective Actions

The laboratory department supervisors will review the data generated to verify that all QCsamples have been run according to protocol. Recoveries of matrix spike and matrix spikeduplicate samples will be evaluated for consistency with method accuracy and methodprecision, respectively, using the data quality goals discussed in Section 4.0. Data from thelaboratory control samples will be evaluated according to the Laboratory SOP (Appendix A).Analytical data generated with laboratory control samples that fall within the established controllimits will be judged as being in control. Data generated with laboratory control samples that donot fall within control limits are considered suspect. The analysis will be repeated, or, theresults will be reported with qualifiers.

Laboratory personnel will be alerted that corrective actions may be necessary if when thefollowing conditions occur:

• QC data are outside the warning or acceptable range for precision andaccuracy established for laboratory control samples.

• Blanks contain contaminants at concentrations above the levels specifiedin the QAPP for any target compound.

• Undesirable trends are detected in matrix spike recoveries or RPDbetween matrix spike duplicates.

• There are unusual changes in detection limits.

• Deficiencies are detected by the laboratory QA Director during internal orexternal audits, or, after reviewing results of performance evaluationsamples.

Corrective actions will be immediately implemented if any nonconformities in analyticalmethodologies or QC sample results are identified.

Corrective action procedures will be handled initially at the bench level by the analyst. Theanalyst will review the preparation or extraction procedure for possible errors; and check theinstrument calibration; spike and calibration mixes; and instrument sensitivity. The analyst will

_______________________________________ CSAO154041/4/00 APPENDIX A - 33 L:V«000\47$S»WP\SAP\47Jg8y20.doc

Page 78: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

immediately notify his/her supervisor of any identified problems and the methods used forconducting the identification. If the problem persists or cannot be identified, the matter will bereferred to the laboratory supervisor and Laboratory Program Administrator for furtherinvestigation. Once resolved, full documentation of the corrective action procedures will be filedwith the Laboratory Project Administrator and the Project QA/QC Officer. Documentation isprovided a corrective action memo for inclusion into the project file if data are affected.

Corrective action may include, but may not be limited to:

• Reanalyzing suspect samples.• Resampling and analyzing new samples.• Evaluating and amending sampling and/or analytical procedures.• Accepting data with an acknowledged level of uncertainty.• Recalibrating analytical instruments.• Discarding irrelevant or incorrect data.

Data deemed unacceptable following implementation of the required corrective action measureswill not be accepted by the Laboratory Project Manager, who will explore follow-up correctiveactions.

14.2 Immediate Corrective Action

Any equipment and instrument malfunctions will require corrective action. The field andlaboratory quality control measures and QA audits are working tools that identify appropriatecorrective actions to be taken in the event of non-conformance to plan or QC limits. Theseprocedures provide the framework for uniform actions as part of normal operating procedures.Corrective actions taken will be recorded in field or laboratory logbooks, and will be applied on-the-spot as required.

CSA015405

1/4/00 APPENDIX A - 34 L:\40W<A4758»WP\SAP\47»8y20.<kx!

Page 79: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

15.0 QUALITY ASSURANCE REPORTS

The Field Work Manager will report to the Project Manager on a daily basis regarding field workprogress and field-related quality control issues. The Laboratory Analytical Program Manager,Laboratory QA coordinators, QA/QC Officers, and data validation personnel will communicatewith each other as needed to evaluate performance of QA/QC and to review potential problemareas. Data anomalies will be investigated to assess if they are a result of operator orinstrument deviation, or, if they are a true reflection of the Site or task function.

Reports will contain a discussion of Project-appropriate QA/QC evaluations summarizing thequality of the data collected. The QA/QC summary will summarize the sufficiency of data qualityand quantity necessary to support the RGMEW Objectives. The QA/QC summary will bemaintained in the Project files, and will discuss the following items, as appropriate:

1. Tabulated results of the validated analytical data.

2. Reports from the QA Manager evaluating the results of appropriate field andlaboratory audits described in Section 12.0.

3. Tabulation of the data validation reports for each batch analysis thatdocument the validity of the analytical data with respect to accuracy,precision, and completeness.

4. Summaries of significant QA problems and corrective actions.

5. Reports by the Analytical Chemist summarizing the validity of the analyticaldata with respect to accuracy, precision, completeness, representativenessand comparability.

6. Copies of descriptions of Field Change Requests.

CSAO15406

1/4/00 APPENDIX A - 35 LA«OOOV4758»WP«AlM7588yM.doc

Page 80: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

FinalPart II - Sampling and Analysis Plan

Casmalia Hazardous Waste Management Facility Quality Assurance Project Plan

16.0 REFERENCES

U.S. EPA, 1986. Draft Supplement to Interim Guidelines and Specifications for Preparing QualityAssurance Project Plans. January 1986. EPA/QAMS-005/80.

U.S. EPA, 1988. Guidance for Conducting Remedial Investigations and Feasibility Studies(RI/FS) Under CERCLA. Interim Final. OSWER Directive 9355.3-01. October 1988. EPA/540/g-89/004.

U.S. EPA. 1989. U.S. EPA Region IX Guidance for Preparing Quality Assurance Project Plans forSuperfund Remedial Projects.

U.S. EPA, 1993. Data Quality Objectives Process for Superfund Interim Final Guidance.September 1993. EPA/540/g-93/071.

U.S. EPA, 1994. Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)Third Edition. September 1994.

U.S. EPA, 1994. Requirements for Quality Assurance Project Plans for Environmental DataOperations.

CSA015407

1/4/00 APPENDIX A - 36

Page 81: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalig Hazardous Waste Management Facility

FinalPart II - Sampling And Analysis Plan

Quality Assurance Project Plan

Volatile Organic Compounds GC/MS ERA Method 8260 5030A see Table 4-2* 30 80-120 90EDB and DBCP GC EPA Method 8011/504 NA see Table 4-103 20 80-120 90Semi-volatile Organic Compounds GC/MS EPA Method 8270 351 OB see Table 4-3* 30 50-125 90PAHs HPLC EPA Method 8310 3520B see Table 4-ST 40 40-140 90Metals (unfiltered and filtered) ICP/GFAA EPA Method 601OA 3005A see Table 4-4' 30 75-125 90Chlorinated Herbicides GC-ECD or ELCD EPA Method 8150 351 OB see Tabte 4-53 30 80-120 90Pesticides/PCBs GC/ECD EPA Method 8080 351 OB see Table 4-e3 30 80-120 90Dioxins/Furans HRGC/LRMS EPA Method 8290 351 OB see Table 4-T3 50 40-120/50-150 90TEPH GC-FID Modified EPA

Method 80153510/8015 Mod 30 50-125 90

Cyanide and Sulfide cokximetric EPA Method9010/9012

335.1335.2 See Table 4-8 30 75-125 90

pH pH meter EPA Method 150.2 0.1 40 85-115 90Field Measurements a field field measurements NA 30 85-115 90General Minerals ion

chromatographyE 300.0 0.05 to 0.8 mg/L 30 85-115 90

alkalinity Motion E 310.1 1.0 mg/L 30 85-115 90chloride tttration E 300.0 0.3 mg/L 30 85-115 90fluoride cotorimetrtc E340.2 0.10 mg/L 30 85-115 90nitrate trtration E 300.0 0.05 mg/L 30 85-115 90sulfate trtration E 300.0 1.0 mg/L 30 85-115 90

1. Precision expressed as relative percent difference between duplicate sample results2. Accuracy expressed as percent recovery of the matrix spike. Parameters noted as N/A indicate that accuracy data, in the form of spikes, are not avaRabte for these methods.3. Quantitation limits vary with compound.4. pH, temperature, conductivity, turbidity.5. Estimation based on previous field experience.

GC/ECD ELCD - gas chromatography/etectron capture or electrolytic conductivityGC/FID - gas chromatograph/flame ionizationGC-FPD NPD - gas chromatography/name photometric detector or nitrogen phosphorous detectorGC/MS - gas chromatography/rnass spectrometryGFAA - graphite furnace atomic absorptionHRGC/LRMS - high resolution gas chromatography/low resolution mass spectrometryICP - inductively coupled plasma spectroscopyTEPH - Total Extractabte Petroleum HydrocarbonsNA * Not applicable or available for method

1/3/00-Revision 1.0 CSAO15408 1of1 4-l_qapp.doc

Page 82: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

i:|:;:;:;::: :::::::j:::::::::-:::::::::::o:::;:K:;: :>:::::::::|:::::::::::::;:: :::::::::::i:::::::::::::::::::::::::::::::::::::::::::::::::::::::::;:i::::::

BenzeneBromobenzeneBromochloromethaneBromodichloromethaneBromoformBromomethanen-Butylbenzenesec-Butylbenzenetert-ButylbenzeneCarbon TetrachlorideChlorobenzeneChloroethane2-Chloroethylvinyl etherChloroformChloromethane2-ChlorotolueneDibromomethane1 ,2-Dichlorobenzene1,3-Dichlorobenzene1 ,4-DichlorobenzeneDichlorodifluoromethane1,1-Dichloroethane1 ,2-Dichloroethane1,1-Dichloroethenecis-1 ,2-Dichloroethenetrans-1 ,2-Dichloroethene1,2-Dichloropropanecis-1 ,3-Dichloropropenetrans-1 ,3-DichloropropeneEthyl BenzeneHexachlorobutadieneIsopropylbenzenep-lsopropyltolueneMethylene ChlorideNaphthalenen-PropylbenzeneStyrene1 ,1 ,1 ,2-Tetrachloroethane1 ,1 ,2,2-TetrachloroethaneTetrachloroetheneToluene1 ,2,3-Trichlorobenzene1 ,2,4-Trichlorobenzene

1 Hi ||! || Illllll

0.50.50.50.50.50.50.50.50.50.50.50.520.0.50.50.50.50.50.50.50.50.50.50.50.50.50.50.50.50.50.50.50.51.

0.50.50.50.50.50.50.50.50.5 CSAO15409

_, 1/3/00-Revision 1.0 1 of 2

Page 83: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

1,1,1-Trichloroethane 0.51,1,2-Trichloroethane 0.5Trichloroethene 0.5Trichlorofluoromethane 0.51,2,3-Trichloropropane 0.51,2,4-Trimethylbenzene 0.51,3,5-Trimethyl benzene 0.5Vinyl Chloride 0.5Total Xylenes 1.o-Xylene 0.5Acetone 10.Acetonitrile 100.Acrolein 50.Acrylonitrile 50.Carbon Disulfide 5.2-Chloro-1,3-butadiene 5.Chlorodibromomethane 0.53-Chloropropylenetrans-1,4-Dichloro-2-butene 5.1,4-Dioxane 1000.Ethyl Methacrylate 20.2-Hexanone 20.lodomethane 0.5Isobutyl alcohol 100.IPA 100.Methacrylonitrile 100.Methyl Ethyl Ketone 20.Methyl Isobutyl Ketone 20.Methyl Methacrylate 100.Pentachloroethane 5.Propionitrile 20.Tetrahydrofuran 20.Vinyl Acetate 20.

CSA015410

_ 1/3/00-Revision 1.0 2 of 2

Page 84: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

AcenaphtheneAcenaphthyleneAnilineAnthraceneBenzo-k-fluorantheneBenzoic-acidBenzylalcoholbis-2-chloroethyl-etherbis-2-chloroethoxy-methanebis(2-chloro-1 -methylethyl) etherbis-2-ethylhexyl-phthalate4-Bromophenyl-phenyl-ether4-Chloroaniline2-Chloronaphthalene4-Chlorophenylphenyl-etherDibenzo (a,h) anthraceneDibenzofuranDi-n-butyl-phthalate3,3-DichlorobenzidineDiethyl-phthalateDimethyl-phthalate2,4-Dinitrotoluene2,6-DinitrotolueneDi-n-octylphthalateHexachlorobenzeneHexachlorocyclopentadieneHexachloroethanelndeno-1,2,3-cd-pyreneIsophorone2-Methylnaphthalene2-Naphthylamine2-Nitroaniline3-Nitroaniline4-NitroanilineNitrobenzeneN-NitrosodimethylamineN-NitrosodiphenylamineN-nitrosodi-n-propylaminePhenanthrene4-Chloro-3-methylphenol2-Chlorophenol2,4-Dichlorophenol2,4-Dimethylphenol

2.2.5.2.2.10.2.2.2.2.5.2.2.2.2.3.2.2.5.2.2.2.2.2.2.2.2.2.2.2.20.2.2.5.2.2.2.2.2.5.2.2.2.

CSA015411

1/3/00-Revision 1.0 1 of 3

Page 85: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

2,4-Dinitrophenol2-Nitrophenol4-NitrophenolPentachlorophenolPhenol2,4,5-Trichlorophenol2,4,6-TrichlorophenolAcetophenone2-Acetylaminofluorene4-AminobiphenylAramiteN-ButylbenzylphthalateChlorobenzilatem-Cresolo-Cresolp-CresolDiallate2,6-DichlorophenolDimethoateDimethylaminoazobenzene7,12-Dimethylbenz (a) anthracene3,3'-Dimethylbenzidinea,a-Dimethylphenethylaminem-Dinitrobenzene4-6-Dinitro-2-methylphenolDiphenylamineDisulfotonEthyl methanesulfonateFamphurHexachloropheneHexachloropropeneIsodrinIsosafroleKeponeMethapyrilene3-MethylcholanthreneMethyl methanesulfonateMethyl parathion1,4-Napthoquinone1-Napthylamine5-Nitro-o-toluidineNitroquinoline-1-oxiden-Nitrosodibutylamine

10.2.5.10.2.5.5.10.10.10.10.10.10.2.2.2.10.10.20.10.10.10.10.10.2.10.10.10.20.10.10.10.10.20.10.10.10.10.10.20.10.10.10.

CSA015412

1/3/00-Revision 1.0 2 of 3

Page 86: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

n-Nitrosodiethylaminen-Nitrosomethylethylamine 10.n-Nitrosomorpholine 10.n-Nitrosopiperidine 10.n-Nitrosopyrrolidine 10.Parathion 10.Pentachlorobenzene 10.Pentachloronitrobenzene 10.Phenacetin 10.1,4-Phenylenediamine 10.Phorate 10.2-Picoline 10.Pronamide 10.Pyridine 2.Safrole 10.1,2,4,5-Tetrachlorobenzene 10.2,3,4,6-Tetrachlorophenol 10.Tetraethyl pyrophosphate 10.Thionazin 10.o-Toluidine 10.0,0,0-Triethyl phosphorothioate 10.1,3,5-Trinitrobenzene 10.

CSA015413

1/3/00-Revision 1.0 3 of 3

Page 87: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

Total AntimonyTotal ArsenicTotal BariumTotal BerylliumTotal CadmiumTotal ChromiumTotal CobaltTotal CopperTotal LeadTotal MercuryTotal MolybdenumTotal NickelTotal SeleniumTotal SilverTotal TinTotal ThalliumTotal VanadiumTotal Zinc

2.100.10.10.10.50.10.5.0.250.50.2.10.15.1.10.50.

CSA015414

_ 1/3/00-Revision 1.0 1 Of 1

Page 88: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

2,4-DDicambaDichloropropOinoseb2.4,5-T2,4,5-TP (Silvex)

0.20.050.50.1

0.050.05

CSA015415

1/3/00-Revision 1.0 1 Of 1

Page 89: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

Aldrinalpha-BHCbeta-BHCdelta-BHCgamma-BHCChlordane (Technical)4,4-DDD4,4-DDE4,4-DDTDieldrinEndosulfan IEndosulfanEndosulfan SulfateEndrinEndrin AldehydeHeptachlorHeptachlor epoxideMethoxychlorToxapheneTotal PCB's (Summation)

0.0050.0050.0050.0050.005

0.20.0050.0050.0050.0050.0050.0050.0050.0050.010.0050.0050.005

0.20.2

CSA015416

1/3/00-Revision 1.0 Of1

Page 90: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

___Quality Assurance Project Plan

2,3,7.8-TCDD2,3,7,8-TCDF 10

1.2,3.7.8-PeCDF 251,2.3.7.8-PeCDD 252,3,4,7.8-PeCDF 25

1,2.3,4.7,8-HxCDF 251,2,3,6,7,8-HxCDF 251,2.3,4.7.8-HxCDD 251,2,3,6.7.8-HxCDD 251.2.3.7.8.9-HxCDD 252,3,4.6.7,8-HxCDF 251.2,3.7.8.9-HxCDF 25

1,2,3,4,6.7,8-HpCDF 251.2,3,4,6.7,8-HpCDD 251.2,3,4,7,8.9-HpCDF 25

OCDD 50OCDF 50

1. Proposed quantitation limits. Limits may change as required. Reporting limit based on clean samples without matrixinterference.

CSA015417

1/3/00 -Revision 1.0 1 Of 1 4-7_qapp.doc

Page 91: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

1. Proposed quantitation limits. Limits may change as required.Reporting limit based on clean samples without matrix interference.

CSA015418

1/3/00-Revision 1.0 Of1

Page 92: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

Benzo(a)anthracene 0.05Benzo(b)fluoranthene 0.25Benxo(g,h.i)perylene 0.25Benzo(a)pyrene 0.1Chrysene 0.2FluorantheneFluorene 10Pyrene 0.1

1. Proposed quantitation limits. Limits may change as required. Reporting limit based on clean samples without matrixinterference.

CSA015419

1/3/00 -Revision 1.0 1 Of 1 4-8.qp.doc

Page 93: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management FacilityFinal

Part II - Sampling and Analysis PlanQuality Assurance Project Plan

Cyanide Amenable to Chlorination

CSAO15420

1/3/00-Revision 1.0 1 Of 1

Page 94: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

Metals (Method 601OA,7470/7471)

Calibration Curve At start of analysis or when continuing calibrationverification standard is out of control.

R*> 0.995

Initial Calibration VerificationStandard

After calibration and before sample analysis 90-110 percent recovery

Calibration Blank Every 10 samples <Method reporting limitContinuing CalibrationVerification Standard

Every 10 samples ±10 percent of expected value

Instrument Blank 1 every 10 samples < Method reporting limitMethod Blank 1 every 20 samples < Method reporting limitLaboratory Duplicate 1 every 20 samples Precision (%)

Accuracy (%)Completeness (%)

3075 to 12590

Laboratory Control SampleMS/MSD

1 every 20 samples 75 to 125 percent recovery

Volatile OrganicCompounds(Method 8260)

O00

to

Calibration Curve At start of analysis or when continuing calibrationverification standard is out of control.

30 percent relative standard deviation CCC

Initial Calibration VerificationStandard

After calibration and before sample analysis ± 25 percent recovery

Calibration Blank Every 10 samples ± 25 percent recoveryContinuing CalibrationVerification Standard

Every 10 samples ± 25 percent RSD CCC

Instrument Blank 1 every 10 samples < Method reporting limitMethod Blank 1 every 20 samples < Method reporting limitMS/MSD and LCS 1 every 20 samples 80 to 120 percent recoveryMS/MSD and LCS 1 every 20 samples Precision (%)

Accuracy (%)Completeness (%)

3080 to 12090

Surrogate Compound Every sample DibromomethaneToluene d-8

70 to 130 percent recovery70 to 130 percent recovery

NOTE: MS = Matrix SpikeMSD = Matrix Spike DuplicateLCS = Laboratory Control Sample

1/3/00 -Revision 1.0 1 of 4 7-1_qapp.doc

Page 95: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

•>>>>>>>>>>>>>>>>>> !J[ j}ij J:lifr >>j>>H'X-:':'M-'wX.;<.;.x-:.:<< x.:o.x.:.fl3W\WMfr:-: :-x¥:-:;>::x-:-:-:-:-:-:-:

EDB and DBC(Methods 801 1/504)

Semivolatite OrganicCompounds(Method 8270)

O

0

K>

Calibration Curve (5 point)

Initial CalibrationVerification StandardCalibration BlankContinuing CalibrationVerification StandardMethod BlankMS/MSD and LCS

MS/MSD and LCS

Calibration Curve (5 point)

Initial CalibrationVerification StandardCalibration BlankContinuing CalibrationVerification StandardMethod BlankMS/MSD and LCS

MS/MSD and LCS

Surrogate Compound

1 every 20 samples

1 every 20 samples

Every 10 samplesEvery 10 samples

1 every 10 samples1 every 10 samples

1 every 20 samples

At start of analysis or when continuing calibrationsverification standard is out of control.

After preparation of new calibration verificationstandards. Standard is from an independent.Every 10 samplesEvery 10 samples

1 every 20 samples1 every 20 samples

1 every 20 samples

Every sample

20 percent RSD

±20 percent

< Method reporting limit± 20 percent

< Method reporting limitEDB 59-1 48 percent recoveryDBCP 57-1 48 percent recoveryPrecision (%) 36Accuracy (%) 55 to 148Completeness (%) 9030 percent RSD CCC

30 percent recovery

< Method reporting limit30 percent recovery, 30 percent RPD

< Method reporting limit2,4,6-Tribromophenol 1 0-1 23 percent recovery2-Fluorobiphenyl 43-1 1 6 percent recovery2-Fluorphenol 21 -1 00 percent recoveryNitrobenzene-d5 35-1 14 percent recoveryPhenol-d6 10-94 percent recoveryTerphenyl-d1 4 33-1 41 percent recoveryPrecision (%) 30Accuracy (%) 50 to 1 25Completeness (%) 902, 4, 6-Tribromophenol 10 to 123 percent recovery2 - Fluorobiphenyl 30 to 115 percent recovery2 - Fluorophenol 25 to 1 21 percent recovery4-Terphenyl-d14 18 to 144 percent recoveryNitrobenzene-dS 23 to 120 percent recoveryPhenol-d6 24-1 13 percent recovery

NOTE: MS = Matrix SpikeMSD = Matrix Spike DuplicateLCS = Laboratory Control Sample

1/3/00 -Revision 1.0 2 of 4 7-1_qapp.doc

Page 96: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

Pestfcktes/PCBs(Method 8310)

Calibration Curve (5 point) At start of analysis or when continuing calibrationverification standard is out of control.

20 percent

Initial CalibrationVerification Standard

Alter preparation of new calibration verificationstandards. Standard is from an independent.

± 20 percent recovery

Calibration Blank Every 10 samples < Method reporting limitContinuing CalibrationVerification Standard

Every 10 samples ± 15 percent of expected value or within limits set by method± 20 percent recovery____________________

Method Blank 1 every 20 samples < Method reporting limitMS/MSD and LCS 1 every 20 samples 19 to 173 percent recoveryMS/MSD and LCS 1 every 20 samples Precision (%)

Accuracy (%)Completeness (%)

3080 to 12090

Surrogate Compound Every sample D-120 11 to 141

n00

toU)

Pesticides/PCBs(Method 8080)

Calibration Curve (5 point) At start of analysis or when continuing calibrationverification standard is out of control.

Per method

Initial CalibrationVerification Standard

After preparation of new calibration verificationstandards. Standard is from an independent.

+.20 percent recovery

Calibration Blank Every 10 samples <Method reporting limitContinuing CalibrationVerification Standard

Every 10 samples ± 15 percent of expected value or within limits set by method± 20 percent recovery___________________

Method Blank 1 every 20 samples < Method reporting limitMS/MSD and LCS 1 every 20 samples PCB-1254

PCB-126080 to 120 percent recovery80 to 120 percent recovery

MS/MSD and LCS 1 every 20 samples Precision (%)Accuracy (%)Completeness (%)

3080 to 12090

Surrogate Compound Every sample TCMX 50 to 138 percent recoveryChlorinated Herbicides(Method 8150)

Calibration Curve (5 point) At start of analysis or when continuing calibrationverification standard is out of control.

Per method

Initial CalibrationVerification Standard

Alter preparation of new calibration verificationstandards. Standard is from an independent.

± 20 percent recovery

Calibration Blank Every 10 samples <Method reporting limitContinuing CalibrationVerification Standard

Every 10 samples ± 15 percent of expected value or within limits set by method± 20 percent recovery___________________

Method Blank 1 every 20 samples <Method reporting limit

NOTE: MS = Matrix SpikeMSD = Matrix Spike DuplicateLCS = Laboratory Control Sample

1/3/00 -Revision 1.0 3 of 4 7-1_qapp.doc

Page 97: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

Quality Assurance Project Plan

CSAO

15424

(Continued)Chlorinated Herbicides(Method 81 50)

Dioxins/Furans (Method8290)

TEPH (Method 801 5)

Inorganic TDS and Nitrate

Cyanide

WlSii JAitiiiBRATIflSK iiiiSiJ

MS/MSD and LCS

MS/MSO and LCS

Surrogate CompoundMethod blank

Internal StandardsDuplicateMS/MSDMBNS/MBNSD (DCS)Calibration CurveInitial CalibrationMethod BlankLCS

MS/MSDCalibration Blank

Duplicate SampleAnalysisCalibration Blank

Duplicate SampleAnalysis

1 every 20 samples

1 every 20 samples

Every sample1 per batch, not to exceed 20 samples

every sample1 every 20 samples1 every 20 samples1 per batch, not to exceed 20 samplesAt start of analysisAt start of analysis1 every 10 samples1 per batch or 1 every 10 samples

1 per batch or 1 every 10 samplesEach calibration at beginning of each run or 1 every20 samples.1 every 20 samples

Each calibration at beginning of each run or 1 every20 samples.1 every 20 samples

innit11!

2,4-D 80 to 1 20 percent recovery2,4,5-T 80 to 1 20 percent recovery2,4,5-TPPrecision (%) 30Accuracy (%) 80 to 120Completeness (%) 90Dichlorophenylaceticacid 30 to 1 21 percent recovery<method detection limit

standard recovery > 40%% RPD < 50%60 to 140 percent recovery40 to 1 20 and 50 to 1 50 percent recoveryPer method% RSD < 20%< method reporting limitPrecision (%) 30Accuracy (%) 50 to 125Completeness (%) 9050 to 1 25 percent recovery< Method reporting limit

± 30 percent relative difference

< Method reporting limit

± 30 percent relative difference

NOTE: MS = Matrix SpikeMSD = Matrix Spike DuplicateLCS = Laboratory Control Sample

1/3/00- Revision 1.0 4 of 4 7-1_qapp.doc

Page 98: 75406 CASMALIA SITE REMEDIATION PROJECTThe SAP addresses the chemical quality sampling which the CSC will perform as outlined below: • Semi-annually for the RCF and A-Series Pond

Casmalia Hazardous Waste Management Facility

FinalPart II - Sampling and Analysis Plan

___Quality Assurance Project Plan

ORGANICSVOCs

EPA 8260HCI to pH < 2, Cool, 4°C 14 days

EDB and DBCPEPA Methods 8011/504

HCI to pH < 2, Cool, 4°C 14 days

SVOCsEPA 8270

Cool, 4°C 14 days

PAHsEPA 8310

Cool, 4°C 7 days

Pesticides/PCBsEPA 8080

Cool, 4°C 7 days

Chlorinated HerbicidesEPA 8150

Cool, 4°C 7 days

Dioxins/FuransEPA 8290

Cool, 4°C 7 days

TEPH 8015M HCI. Cool, 4°C 14 daysINORGANICS

MetalsEPA 601OA

HNO3 to pH < 2, Cool, 4°C 6 months

CyanideEPA 9010

NaOH to pH > 12, Cool, 4°C 14 days

General MineralsEPA 300.1

Cool, 4°CH2S04 to pH < 2 for

28 days14 days forAlkalinity

GENERAL CHEMISTRYPH

EPA 150.2None Immediately

CSA015425

1/3/00 -Revision 1.0 1of 1 9-1_qapp.doc