734073 Bridge Abutment Repair
Old King’s Road
734073 Location; Old King’s Road
N734063
Old King’s Road Bridge (734073) existing structure
Built in 1962
September 26, 2014 Rainstorm
Repaired in 2 Phases
Fill and compact the voids as much as possible and restore the concrete flume over the damaged area … Done.
Phase 1
Inject a soil stabilizing chemical grout under the repair to force water out, fill all the voids that could not be reached and consolidate and bind the soil together.
Phase 2
Before the rain event
Lehigh Canal
Native Soil
Fabriform Slope Protection
Erosion after the rain event
Lehigh Canal
Native Soil
Erosion behind slope protection
Fabriform Slope Protection
Flume removed to repair erosion
Phase 1 Repair
Lehigh Canal
Native Soil
Void filled with road base
Fabriform Slope Protection
Flume repaired
Phase 2 Repair (Chemical Grout Installed)
Lehigh Canal
Native Soil
Chemical Grout injected into fill
Fabriform Slope Protection
Uretek Holdings was selected to perform the work subject to the terms, conditions and pricing of the FDOT Contract No. BDV76, which is a statewide contract that was competitively bid.
Uretek Holdings has agreed to perform the work with a not to exceed cost of $39,600 with 36,000 pounds of material.
2015 Approved Budget
Budgeted $50,000Uretek Contract $39,600
Remaining: $10,400
As soon as possible
Tentative Schedule
Should be a one day job and as soon as the contractor can work the project
into their schedule