Procedures for the commercialisation of existing and committed capacity at the cross border point of Larrau between France and Spain. 7 th SG meeting, South Gas Regional Initiative Madrid, 23 rd September 2008. Summary. Background. Main updates. General principles. Capacities concerned. - PowerPoint PPT Presentation
Citation preview
7th SG meeting, South Gas Regional Initiative
Madrid, 23rd September 2008
Procedures for the commercialisation
of existing and committed capacity at
the cross border point of Larrau
between France and Spain
2
Summary
1. Background.
2. Main updates.
3. General principles.
4. Capacities concerned.
5. Timing of the OSPs.
6. Binding Transmission Capacity Request.
7. Allocation rules.
3
1. Background.
ENAGÁS and TIGF have committed to put in operation by 2009 new capacities in both directions at the cross border point of Larrau, and have agreed ERGEG’s South GRI proposal of evaluating shipper’s interest in existing (non-allocated) capacities and in new capacities at this point, and to allocate the referred capacities through an Open Subscription Period (OSP).
The competent regulatory authorities in both countries have committed to adapt the regulatory framework in force in order to allow the proposed OSPs to take place under the general principles agreed between the TSO and regulators.
The aim of this presentation is to introduce the procedures for subscription and allocation of capacities to be offered under the OSP for long term and short term capacities from 1st April 2009 to 31st March 2013 at the interconnection point of Larrau.
4
2. Main updates.
On 16th September 2008 the Spanish Ministry of Industry, Tourism and Trade (Mityc) published the Ministerial Order ITC/2607/2008 that established the rules to allocated capacity at interconnection points with France.
Enagás and TIGF have developed the procedures for the commercialisation of capacity between France and Spain at Larrau interconnection point, which are consistent with Order ITC/2607/2008.
The Mityc will publish the official announcement for the 2008 OSP for Spanish shippers and eligible customers, and it will be adapted to the procedures developed by the TSOs.
5
3. General principles. Capacities will be sold by ENAGAS and TIGF respectively, and
different contracts will be subscribed respecting the rules of each TSO.
The main results of the OSP will be published by both TSO.
The terms and conditions, including technical rules, applicable to the capacities sold under the OSP will not differ from the rules prevailing in each system at any particular time.
Shippers participating in the OSPs will be required to be a licensed shipper at least in one of the systems. No shipper will be allowed to make a request for capacity in a system where it is not licensed.
Only firm capacities will be sold in the OSP.
80% of the firm the capacities will be reserved for OSP LTC in October 2008.
20% of the firm the capacities will be reserved for OSP STC each year.
6
4. Capacities to be offered.
Capacities in GWh/day
April-Oct 09
Nov 09 - March 10
April-Oct 10
Nov 10 - March 11
April-Oct 11
Nov 11 - March 12
April-Oct 12
Nov 12 - March 13
ENAGÁS TIGF Code: LAR-SUDNOR
Summer Winter Summer Winter Summer Winter Summer Winter
Capacity offered under the OSP (common value)
0,00 0,00 0,00 30,00 50,00 30,00 50,00 30,00
OSP 2008 (LTC) 0,00 0,00 0,00 24,00 40,00 24,00 40,00 24,00
OSP 2008 (STC) 0,00 0,00
TIGF ENAGÁS Code: LAR-NORSUD Summer Winter Summer Winter Summer Winter Summer Winter
Capacity offered under the OSP (common value)
13,00 13,00 13,00 13,00 13,00 13,00 22,48 22,48
OSP 2008 (LTC) 10,40 10,40 10,40 10,40 10,40 10,40 17,98 17,98
OSP 2008 (STC) 2,60 2,60
Note that delays are probable, although no invoices will be receive from the TSOs for the time period between the expected date of put into operation and the date of the effective provision of the capacity service.
7
4. Committed infrastructure and capacity added.
GWh/d Exit TIGFEntry
EnagásCommon
Value Exit Enagás Entry TIGFCommon
ValueCurrent Status Max: 103 Max: 87 0 0 0(Pipeline Falces - Irurzún in operation)
Min: 60 (W); 40 (S)
Min: 60 (W); 40 (S)
4Q-2008 CS Zaragoza (in operation) Max: 103 Max: 87 0 0 0Pipeline Barcelona - Arbós (duplicate)
Min: 50 (W); 40 (S)
Min: 50 (W); 40 (S)
2Q-2009 CS Navarra Max: 165 Max: 100 0 0 0
4Q-2009 Max: 165 Max: 100 0 0 0
Reinforce CS Haro4Q-2010 Max: 165 Max: 100 W: 30 W: 110 W: 30
S: 50 S: 100 S: 50(51 bar at Mont)
4Q-2012 Max: 165 Max: 100 165 W: 110 W:110S: 100 S:100
CS Villar de Arnedo (51 bar at Mont)4Q-2012 Max: 165 Max: 165 165 165 165
(51 bar at Mont)
Notes:
S: summer capacity (July and August are not considered)W: winter capacity
Rev Mars 2008
Pipeline Lussagnet - Lacq (*) and CS Mont (*)
(*): Under study, not yet decided
165 (45 bar at Navarra)
Min: 0 (W); 0 (S)
Min: 0 (W); 0 (S)
Min: 0 (W); 0 (S)
Min: 0 (W); 0 (S)
Pipeline Zarza de Tajo - Villar de Arnedo
100 (45 bar at Navarra)
Min: 0 (W); 0 (S)
Min: 0 (W); 0 (S)
100 (45 bar at Navarra)Pipeline Tivissa -
Castelnou (duplicate) and Reversibility of flow in TIGF network
Pipeline Tivissa - Paterna (duplicate)
100 (45 bar at Navarra)
Pipeline Lemona - Haro (duplicate) Min: 30 (W);
20 (S)Min: 30 (W);
20 (S)
Min: 50 (W); 40 (S)
87 (59 bar at Villar de
Arnedo)100
(45 bar at Navarra)
Min: 50 (W); 40 (S)
France → Spain Spain → France
87 (59 bar at Villar de
Arnedo)
8
5. Timetable.OSP starting date (LTC) 13th Oct 2008
OSP closing date (LTC) 20th Oct 2008
Initial allocation of capacities (LTC)
23rd Oct 2008
FIRST PHASE
Closing date Withdraw of requests (LTC)
30th Oct 2008
Final allocation of capacities (LTC)
5th November 2008
SECOND PHASE
Communication and approval by NRA’s of final allocation (LTC)
10th Nov 2008 FINAL RESULT COMMUNICATION
OSP starting date (STC) 14th Nov 2008
OSP closing date (STC) 21st Nov 2008
Initial allocation of capacities (STC)
26th Nov 2008
FIRST PHASE
Closing date Withdraw of requests (STC)
3rd December 2008
Final allocation of capacities (STC)
10th Dec 2008
SECOND PHASE
Communication and approval by the NRA’s of final allocation (STC).
12th Dec 2008 FINAL RESULT COMMUNICATION
9
6. Binding Transmission Capacity Request.
DRAFT Shippers requesting OSP LTC should fill in the “Binding
Transmission Capacity Request Long-Term Capacity” and shippers requesting OSP STC should fill in the “Binding Transmission Capacity Request Short-Term Capacity”.
Each capacity request should be sent to both TSOs.
The capacity request sent to the TSOs must be identical, except for the signature.
The company requesting access in France (shipper 1) will sign the “Binding Transmission Capacity Request” that must be sent to TIGF, whereas the company requesting access in Spain (shipper 2) will sign the “Binding Transmission Capacity Request” that must be sent to ENAGÁS.
10
LTC allocation
rules1st matchedcapacities
1st multi-annual
2ndmulti-
seasonal
2nd non-matched
capacities
STC allocation
rules1st matchedcapacities
Longestperiod
Earliestdate
Pro-rata2nd non-matched
capacities
Rule 1 Rule 2 Rule 3 Rule 4 Rule 5
Rule 1 Rule 2 Rule 3 Rule 4
Longestperiod
Earliestdate
Pro-rata
7. Allocation rules.
Thank you for your attention