Upload
volien
View
228
Download
2
Embed Size (px)
Citation preview
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-1
7 STAKEHOLDER ENGAGEMENT
This Chapter presents a summary of the stakeholder engagement activities as
part of the ESIA process. It serves as a summary of a more detailed
Stakeholder Engagement Programme described in the Stakeholder
Engagement Plan (SEP - refer to Annex C in Part II of this ESIA) and presents
the engagement approach, the stakeholders included in engagement activities,
and the mechanisms through which they were and will continue to be
engaged. The SEP also provides a means to document the stakeholder
engagement process and includes meeting minutes, participant signatures,
photographs etc.
This Chapter has been structured to provide a summary of:
The objectives of stakeholder engagement in the ESIA;
The overall approach to stakeholder engagement;
The engagement undertaken during in the screening phase;
The engagement undertaken during the baseline phase
The engagement undertaken during the draft ESIA consultation phase;
The engagement undertaken during the final ESIA consultation phase;
The next steps related to stakeholder engagement; and
The feedback mechanism.
7.1 OBJECTIVES OF STAKEHOLDER ENGAGEMENT
The objectives of engaging stakeholders during the ESIA process included:
Ensuring Understanding – developing an open, inclusive and transparent
process of culturally appropriate engagement and communication to
ensure that stakeholders are well informed about the proposed Project.
Involving Stakeholders in the Assessment – stakeholders were included
in the scoping of issues, the assessment of impacts, the generation of
mitigation and management measures and the finalisation of the ESIA
report. Stakeholders play an important role in providing local knowledge
and information for the baseline and to inform the impact assessment and
mitigation.
Building Relationships – through supporting open dialogue, engagement
helped establish and maintain a productive relationship between the ESIA
team and stakeholders. This supported an effective ESIA, but also
strengthened the existing relationships between Yara Dallol BV and
stakeholders.
Engaging Vulnerable Peoples – an open and inclusive approach to
consultation increases the opportunity for stakeholders to provide
comment on the proposed Project and to voice their concerns. Some
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-2
stakeholders need special attention in such a process due to their
vulnerability (for example, elderly, female headed households, children,
etc.). Special measures will be considered to ensure that the perspectives of
vulnerable stakeholders are heard and considered.
Managing Expectations – it is important to ensure that the proposed
Project does not create or allow unrealistic expectations to develop
amongst stakeholders with respect to proposed Project benefits. The
engagement process served as a mechanism for understanding and
managing stakeholder and community expectations by disseminating
accurate information in an accessible way.
Ensuring Compliance - the engagement process is designed to ensure
compliance with both local regulatory requirements and international best
practice.
One of the key outcomes of engagement should be free, prior and informed
consultation of stakeholders, where this can be understood to be:
Free – engagement free of external manipulation or coercion and
intimidation;
Prior – engagement undertaken in a timely way, for example the timely
disclosure of information early in the ESIA process; and
Informed – engagement enabled by relevant, understandable and
accessible information.
7.2 APPROACH TO STAKEHOLDER ENGAGEMENT
Stakeholder engagement for the ESIA was undertaken using a staged
approach in line with the various phases of the ESIA process. All engagement
has been developed according to Ethiopian legislative requirements and with
consideration of IFC Performance Standards.
Stakeholder engagement for an ESIA has five key phases, shown in Figure
7.1below.
Figure 7.1 ESIA Engagement Phases
The objectives of each engagement phase are presented below in Table 7.1.
Screening Scoping Baseline
Data Gathering
Draft ESIA Final ESIA Disclosure
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-3
Table 7.1 Phases of Stakeholder Engagement
Phase Objective Key Activities Key Outputs
Screening
Engagement
To gain a preliminary understanding of the scope of the proposed Project, it’s likely impacts and relevant stakeholders.
Inception meeting with Yara Dallol BV and personnel involved in the stakeholder engagement activities;
Site screening field visit; and
Stakeholder identification process.
SEP for the ESIA;
Summary of screening issues raised and stakeholders identified.
Notification and
Scoping
Engagement
To meet key stakeholders and discuss the proposed Project and ESIA;
To generate feedback on the Draft Scoping Report, including the scope, approach and key issues to be investigated further in the ESIA process; and
To consult key stakeholders on the next steps in the ESIA process.
Formal submission of Draft Scoping Report to Authorities;
Distribution of draft Scoping Report and /or Background Information Document (BID) to key stakeholders;
Stakeholder consultation on the proposed Project and associated ESIA through meetings and workshops with identified stakeholders. Details may include: Contextualisation of the proposed Project
with respect to other neighbouring projects and any previous consultation undertaken;
Nature, purpose and scale of the proposed Project;
Discussion of the ESIA and stakeholder engagement process;
Disclosure of scoping findings, including identification of preliminary impacts;
Feedback regarding findings; and Dissemination of engagement materials
(BID, posters etc.).
Updated SEP;
Stakeholder database;
Engagement tools and records of their dissemination;
Final Scoping Report with record of stakeholder issues;
Non-technical presentation and posters summarising the draft Scoping Report including list of preliminary identified impacts;
Meeting minutes; and
Updates to project website.
Baseline Data
Gathering
Engagement
To gather data to form a comprehensive understanding of existing baseline conditions of the socio-economic environment; and
To allow stakeholders to raise concerns and expectations regarding the proposed Project.
Further engagement for the purposes of additional baseline data gathering through:
Workshops Focus Group Discussions (FGD) Key Informant Interviews (KII)
Updated SEP;
Updated stakeholder database;
Engagement tools;
Updated socio-economic baseline;
Meeting minutes; and
Updates to project website.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-4
Phase Objective Key Activities Key Outputs
Draft ESIA
Consultation and
Disclosure
Engagement
To discuss the identified impacts and proposed mitigation measures with stakeholders allowing for their input; and
To provide stakeholders with the opportunity to comment on the Draft ESIA report.
Dissemination of the Draft ESIA to Authorities and key stakeholders;
Dissemination of engagement materials (BID, posters etc.) disclosing findings of the draft Impact Assessment Report;
Consultation on the draft ESIA Report. This included: Identification of impacts in the draft ESIA
and proposed mitigation; Identification of stakeholder concerns and
opinions on the impacts identified; Involvement of stakeholders in assessing the
efficacy and suitability of the proposed mitigation measures; and
Identification of revisions or additions to the draft ESIA report where necessary.
Draft ESIA Report;
Non-Technical Summary of identified impacts and mitigation measures;
Updated SEP; and
Updates to Project website.
Final ESIA
Disclosure
Engagement
To get sign–off and formally submit the Final ESIA to the authorities and key stakeholders with comments incorporated from the Scoping and draft ESIA engagement and disclosure stages.
Disclosure of the Final ESIA Report with stakeholders.
Final ESIA Report; and
Final SEP.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-5
7.2.1 Differentiated Approach to Engagement
It is important to note that a significant proportion of stakeholders within the
communities identified within the Project Area may have been previously
engaged either directly by Yara Dallol BV or by other companies operating in
the greater Project Area.
Work to date on neighbouring projects already points to stakeholder fatigue
and despondency amongst key stakeholders in whom expectations have been
raised for benefits and assistance from developers and mining companies. The
risk of baseline survey and engagement teams finding stakeholder fatigue and
or unmet expectations influencing the ability to engage stakeholder in a
comprehensive manner has been considered in the design of the SEP.
In response to this risk a two pronged process for stakeholder engagement has
been designed that is outlined in Figure 7.2, and includes the following:
Courtesy and Confirmatory engagement and disclosure for those that
have been engaged previously with respect to potential impacts of
neighbouring projects (and will be less impacted by this Project).
Detailed Engagement and Disclosure for those newly identified
stakeholders in additional locations, which fall specifically within the Yara
Dallol BV area of influence (the socio-economic area of influence is defined
in Chapter 9). The area of influence can be defined as an area likely to be
disturbed by the Project activities during the pre-construction,
construction and operation phases. The effects can be positive or negative,
short or long term or permanently, direct / and in-direct.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-6
Figure 7.2 Approach to Stakeholder Engagement
7.2.2 Project Stakeholders
For the purposes of the stakeholder engagement, a stakeholder is defined as
any individual or group which is potentially affected by the proposed Project
or who has an interest in the proposed Project and its potential impacts. A
diverse range of stakeholders were identified and involved in the stakeholder
engagement process. Furthermore, different issues are likely to concern
different stakeholders, and so different types of stakeholder have been
grouped for engagement and consultation based on their connections or
interests in the proposed Project.
Table 7.2 identifies the range of stakeholder groups that are likely to be
interested and / or affected by the proposed Project.
Different issues are likely to concern different stakeholders, and so different
stakeholder groups have been established based on their anticipated interest
in the proposed Project.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-7
Table 7.2 Project Stakeholders
Stakeholder
Categories
Stakeholder Groups Stakeholder
Government Federal, regional and local government:
political
ANRS Council
Woreda administrators for Dallol and Berahale
Kebele leaders for project affected Kebeles in Dallol and Berahale Woredas
Federal, regional and local government:
administrative and technical
Ministries at federal level (including Ministry leads and technical support e.g. Ministry of Mines and associated offices at the regional and local level)
Bureaus at regional level
Offices at woreda level
Government agencies Ethiopian Wildlife Conservation Authority
Directly Affected
Stakeholders*
Customary authorities (per village) Clan leaders
Religious leaders
Elders
Community associations (per village) Women’s Federation
Youth Groups
Palm Association
Berahale Salt Association
Community members, including men,
women, youth, artisanal salt workers
Bada
Asabuya
Musley
New Alai lai and Mororo
Hamad Ela
Asabolo
Ambule
Morror
Berahale Town Business Mining companies in the northern Danakil
Potential suppliers
Salt related business: Berahale Salt Selling Mekele Salt Buying Associations Subsidiary services including local restaurants, hotels, accommodation etc. in
Berahale, Asabolo, Hamad Ela
Tourism operators working in the Danakil Depression
National Tourism Operator and Travel Agency (NTO)
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-8
Stakeholder
Categories
Stakeholder Groups Stakeholder
Civil Society Federal / national and regional NGOs Forum for the Environment
MELCA
Matrix Development Solutions
Afar Pastoralist Development Association
International NGOs (working or with an
interest in the Danakil Depression)
AMREF
The International Red Cross
Farm Africa
SOS Sahel
Other international NGOs e.g. Norwegian organisations
Academics and research institutes Ethiopian Authority for Research and Conservation of Cultural Heritage
Addis Ababa University
Ethiopian Biodiversity Research Institute
Mekele University
Semera University
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-9
An outline of the stakeholder engagement activities undertaken in each phase
of the ESIA is provided in Sections 7.3 to Error! Reference source not found.,
and a summary of the engagement is provided in Table 7.1.
7.3 SCREENING ENGAGEMENT
Screening phase engagements were undertaken between 11th and 15th
November 2013. The primary objective of the engagements were to identify
social receptors in the project Area of Influence and ‘map’ stakeholders
including directly Project affected people, other stakeholders and social
sensitivities in areas selected for mine related development. The following
activities were undertaken:
Meetings and interviews with key stakeholder groups including local
leaders, men and women; and
General site reconnaissance through driving and walks, transect walks,
taking GPS reading for mapping purposes, observation and capturing
photography with a Yara representative.
Table 7.3 provides a schedule of screening activities that were undertaken.
Table 7.3 Schedule of Screening Activities Undertaken
Day Schedule Data Collection Activities
11 November 2013 Camp induction
Planning of forthcoming
activities
NA
12 November 2013 Site visit and overview
Asabuya village
identification
Recording geo-spatial
information (1) Photographs
Preliminary engagement
13 November 2013 Bada Town identification
and
Musley village
identification
Recording geo-spatial
information
Photographs
Preliminary engagement
14 November 2013 Natural resource transect
walk
Village identification
Interview with Site
Manager
Recording geo-spatial
information
Photographs
Preliminary engagement
Natural resource ranking
15 November 2013 Provisioning ecosystem
services identification
Recording geo-spatial
information
Photographs
More information about the engagement activities undertaken during each of
these phases as well as the outcomes of these visits are described in the SEP
(refer to Annex C in Part II of this ESIA) and its associated appendices.
(1) This included recording information regarding the following social topics – existing settlements, as well as remains of
old settlements, social infrastructure and key resources e.g. water sources.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-10
7.4 ENGAGEMENT DURING THE SCOPING PHASE
In March 2014, the Scoping Report was made available to stakeholders for a
four week comment period. As part of this disclosure and consultation on the
scoping report, a round of stakeholder engagement was conducted by the
ESIA team. The Scoping engagement involved consultation with stakeholders
at the federal, regional, and local levels. The objectives of this phase were to
disseminate accessible Project information and to engage stakeholders
regarding the ESIA process, the likely key issues and how they can be
involved.
The following engagement materials were generated and disseminated that
summarised the ESIA process, the key issues and how stakeholders could get
involved in the process:
PowerPoint presentations for government level engagement and
engagement in formal settings.
A Background Information Document (BID).
A simplified version of the PowerPoint presentation used as a flipchart
presentation for engagement at the local and regional level.
These materials were written in non-technical/accessible language and
translated into local languages, and provided information on the following:
A background and description of the proposed Project;
The environment in which the proposed Project will be developed;
Information on the Yara Dallol BV;
Information on the ESIA process and timelines;
Typical impacts associated with similar Projects; and
Information on ESIA consultants and their independence.
Due to the high instance of illiteracy amongst potentially impacted groups in
the proposed Project Area, and due to a history of social and political
marginalisation of some minorities in this region, the ESIA team developed a
series of alternative techniques for the dissemination of Project information to
vulnerable or marginalised communities. This included a series of Focus
Group Discussions (FGDs) and one-to-one meetings that rely on the
dissemination of information through the materials mentioned above, as well
as verbal discussion with the involvement of cultural translators.
Consultation with stakeholders was undertaken through a series of face-to-
face meetings and workshops with key stakeholders at the federal, regional
and local levels. Two variants of PowerPoint presentations were given at each
of the meetings depending on the anticipated technical understanding of the
stakeholder group met. For instance, a more technical presentation was given
to government officials; whilst at a local village level a simplified version of
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-11
the presentation was given. Copies of the BID (translated into Amharic) were
distributed at all meetings.
A list of stakeholders that were engaged at each level, and schedule of their
engagement is presented in Table 7.4 below.
Table 7.4 Stakeholder Consultation Meetings during the Scoping Phase
Organisation Date Location
Federal Government
Ministry of Environmental Protection and Forestry 3 March 2014 Addis Ababa
Ministry of Mines 3 March 2014 Addis Ababa
Ministry of Culture & Tourism 3 and 4 March 2014 Addis Ababa
Ministry of Water, Irrigation and Energy 3 March 2014 Addis Ababa
Ministry of Federal Affairs 3 March 2014 Addis Ababa
In addition the Ministry of Agriculture, Ministry of Women, Children and Youth Affairs, Ministry of Urban
Development, Housing and Construction were contacted and provided with a copy of the Draft Scoping Report for
comment.
Regional Government
Bureau of Environmental Protection, Rural Land Use
and Administration
6 and 7 March 2014 Semera
Bureau of Finance & Economic Development 6 and 7 March 2014 Semera
Bureau of Water Resources 6 and 7 March 2014 Semera
Bureau of Culture & Tourism 6 and 7 March 2014 Semera
Bureau of Mines and Energy 6 and 7 March 2014 Semera
Local Government
Berahale Woreda Council and offices 13 March 2014 Berahale
Town
Dallol Woreda Administration 13 March 2014 Adiquwa
Dallol Bureau of Justice and Security 13 March 2014 Adiquwa Dallol Bureau for Agriculture and Pastoralism 13 March 2014 Adiquwa Dallol Bureau of Economic Development 13 March 2014 Adiquwa
Dallol Bureau of Health 13 March 2014 Adiquwa
Community Associations
Berahale Salt Selling & Buying Association 12 March 2014 Berahale
Town
Women’s Palm Association 12 March 2014 Berahale
Town
Tourism Operators & Experts
Medir Tours 4 March 2014 Addis Ababa
Marinata Tours 4 March 2014 Addis Ababa
Ethioder Plc 4 March 2014 Addis Ababa
Off Road Ethiopia 4 March 2014 Addis Ababa
Federal NGOs
Forum for the Environment 4 March 2014 Addis Ababa
Research and Academic Institutions
Authority for Research and Conservation of Cultural
Heritage
4 March 2014 Addis Ababa
Addis Ababa University (departments of Biology,
Archaeology, Geology)
4 March 2014 Addis Ababa
Semera University 6 and 7 March 2014 Semera
Settlements/Communities*
Ambule 10 March 2014 Ambule
Musley 10 March 2014 Musley
Beheiti (Asabuya) 10 March 2014 Asabuya
Bada Ermile 11 March 2014 Central Bada
Bada Admeruq 11 March 2014 Central Bada
Asabolo 10 March 2014 Asabolo
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-12
Organisation Date Location
Hamad Ela 12 March 2014 Hamad Ela
Morror 13 March 2014 Morror
Resettled Alai lai and Mororo 13 March 2014 Resettled Alai
lai and
Mororo
* Community consultations involved engagement with the clan leader, local elders and religious leaders as
well as selected women and youth as identified by the local elders and clan leader.
Upon completion of engagement during the scoping phase, the development
of the Final Scoping Report took into consideration the feedback gained from
stakeholders during Scoping engagement. A summary of key comments and
concerns raised during this phase of engagement is provided in Section 7.8.
7.5 BASELINE DATA GATHERING ENGAGEMENT
Baseline data gathering was conducted during a period of two weeks between
28th April and 7th May 2014. Although the primary purpose of this phase was
to gather primary data for the socio-economic baseline, it also involved
engagement with stakeholders, and provided stakeholders an opportunity to
provide feedback or ask any questions regarding the proposed Project.
Stakeholder engagement during this phase included meetings with key
government stakeholders at the Woreda and Kebele levels, community based
organisations and local community members.
Engagement objectives during baseline data gathering included:
To understand the existing environmental and socio-economic context of
the Project Area; which will serve as a benchmark of pre-project
livelihoods and conditions.
To inform impact predictions (positive and negative) and assessments of
the ability of receptors and stakeholders to benefit from, adapt to and
accept change.
To further identify stakeholders who are potentially sensitive/ vulnerable
to the proposed Project or able to support in the implementation of
information disclosure and mitigation measures.
To ground-truth stakeholder feedback in order to differentiate between
stakeholder perceived and actual impacts.
Communities engaged were selected based on the following characteristics:
Proximity of the community to the Project footprint;
Type of livelihoods activities engaged in;
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-13
Level of vulnerability;
Dependency of palm leaves products as a main source of income; and
Communities residing in the broader Project Area who enjoy communal
user right on the land in-and-around the Project footprint to harvest
natural resources.
Primary data gathering activities were undertaken using Key Informant
Interviews (KII), Focus Group Discussions (FGDs), and one-to-one meetings.
As part of these engagements, a summary of the proposed Project activities
were presented, BIDs were distributed and a social questionnaire was
administered along with other social data gathering methods, such as
Participatory Rural Appraisal (PRA). Flipchart presentations and maps were
used for the different audiences at the local level and supported the data
gathering engagement activities. These were all produced in non-
technical/accessible language and translated into Amharic.
Table 7.5 provides a list of the meetings undertaken during the data gathering
phase.
Table 7.5 Stakeholder Consultation Meetings during the Social Data Gathering Phase
Date Village/ Gov. Leaders Type of Engagement
28 April
2014
Bada Admeruk FGDs: women, elders and men
Bada Admeruk Kebele leaders
KIIs: Health Care Practitioner
Local guide (to show the team areas used to
collect various natural resources)
29 April 2014 Bada Ermile FGDs: women, elders and men
Bada Ermile Kebele leaders (for health, education,
finance, agriculture, and others)
KIIs: Health Care Practitioner
30 April 2014 Abaa/ Kulili
(Elifan Kebele)
FGD: women and men
KII: Elder
01 May 2014 Dallol Woreda FGD: Woreda Leaders (for health, education,
finance, agriculture, and others)
03 May 2014 Asagosso
Baheita Kebele
FGDs: women, elders and men
Asabuyi FGDs: women, elders and men
05 May 2014 Musley FGDs: women
KII: local man, and elder (woman)
06 May Mororo KII: local household
Hamad’Ela KII: local business woman and man
07 May 2014 Zonal Government FGD/KII: Zone 2 Officials for health, education,
finance, agriculture, and others
A summary of key comments and concerns raised during this phase of
engagement is provided in Section 7.8.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-14
7.6 DRAFT ESIA REPORT CONSULTATION AND DISCLOSURE
Engagement on the contents of the Draft ESIA report was undertaken in
December 2014 over a two week period. This phase of engagement involved
consultation with stakeholders at the federal, regional, and local levels. The
objectives of this round of engagement were to:
Present the key social and environmental impacts identified in the draft ESIA report, and proposed mitigation;
Involve stakeholders in assessing the efficacy and appropriateness of the proposed mitigation measures;
Capture stakeholder concerns and opinions on the identified impacts; and
Identify revisions or additions to the draft ESIA report where necessary.
This phase of engagement seeks to provide stakeholders an insight into the
predicted impacts and mitigation and allow them an opportunity to contribute
their local knowledge to the assessment and mitigation process. This process
also allowed stakeholders the opportunity to discuss their needs, concerns and
aspirations and to incorporate responses into the specialist investigations and
Project design where possible and appropriate.
The following engagement materials were generated and disseminated:
PowerPoint presentations for federal level engagement and engagement in
formal settings.
A Non- Technical Summary of the Draft ESIA, (which was in both English
and Amharic).
These materials were written in non-technical/accessible language and
translated into Amharic, and provided information on the following:
A background and description of the proposed Project;
The potential Project impacts; and
The proposed mitigation measures.
The ESIA team developed a series of specific techniques for the dissemination
of Project information to vulnerable or marginalised communities. This
included a series of Focus Group Discussions (FGDs) and ranking of impacts
approaches that relied on the dissemination of information through
aforementioned materials, as well as verbal discussion with the involvement
of cultural translators.
A list of stakeholders that were engaged at each level, and schedule of their
engagement is presented in Table 7.6 below.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-15
Table 7.6 Stakeholder Consultation Meetings
Organisation Date Location
Federal Government
Ethiopian Wildlife & Natural History Society (EWNHS) 2 December 2014 Addis Ababa
Authority for Research & Conservation of Cultural Heritage (ARCCH) 2 December 2014 Addis Ababa
Ministry of Mines (MoM) 2 December 2014 Addis Ababa
Addis Ababa University (AAU) School of Earth Sciences 2 December 2014 Addis Ababa
Ministry of Environment & Forestry (MoEF) 2 December 2014 Addis Ababa
Ministry of Water, Irrigation & Energy (MWIE) 2 and 3 December 2014 Addis Ababa Ministry of Foreign Affairs (MoFA) 3 December 2014 Addis Ababa Ethiopian Wildlife Conservation Authority (EWCA) 2 and 3 December 2014 Addis Ababa Ethiopian Biodiversity Institute 3 December 2014 Addis Ababa Pastoral Community Development Project (PCDP) 3 December 2014 Addis Ababa Ethiopian Tourism Organisation (ETO) 3 December 2014 Addis Ababa Ministry of Agriculture (Land administration and Use Directorate) 3 December 2014 Addis Ababa
Regional Government
Bureau of Mines and Energy 4 and 5 December 2014 Semera
University of Semera 4 December 2014 Semera Bureau of Pastoral Agriculture Development 4 and 5 December 2014 Semera Bureau of Water Resources 4 and 5 December 2014 Semera Afar Design And Supervision Works Enterprise 4 and 5 December 2014 Semera Bureau of Women, Children and Youth Affairs 4 and 5 December 2014 Semera Afar Integrated Basin Development and Villagization Coordination Office 4 December 2014 Semera Bureau of Regional Health 4 and 5 December 2014 Semera
Bureau of Afar Labour and Social Affairs 4 and 5 December 2014 Semera Bureau of Administration and Security 4 and 5 December 2014 Semera
Zonal administrator , Zone 2 5 December 2014 Semera Local Government
Dallol Woreda Administration 8 December 2014 Adiquwa Dallol Bureau of Justice and Security 8 December 2014 Adiquwa Dallol Bureau for Agriculture and Pastoralism 8 December 2014 Adiquwa Dallol Bureau of Economic Development 8 December 2014 Adiquwa Dallol Bureau of Health 8 December 2014 Adiquwa Dallol Bureau of Public Communication 8 December 2014 Adiquwa Dallol Bureau of Militia 8 December 2014 Adiquwa Dallol Bureau of Parliament 8 December 2014 Adiquwa
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-16
Organisation Date Location
Dallol Party Office 8 December 2014 Adiquwa Dallol Bureau of Water Resources 8 December 2014 Adiquwa Dallol Bureau of Women, Children and Youth Affairs 8 December 2014 Adiquwa Dallol Bureau of Civil Services 8 December 2014 Adiquwa Dallol Bureau of Trade and Small Enterprise 8 December 2014 Adiquwa Dallol Police Office 8 December 2014 Adiquwa Berahale Woreda Council and Offices 9 December 2014 Berahale Town
Settlements/Communities*
Bada Admeruk 7 December 2014 Bada
Hamad Ela 10 December 2014 Hamad Ela
Beheiti Kebele 10 December 2014 Beheiti
Asabolo and Ambule 11 December 2014 Ambule
Asabuyi 11 December 2014 Asabuyi
Musley 12 December 2014 Musley
Bada Ermile 12 December 2014 Bada
Mororo and Alai lai 12 December 2014 Mororo and Alai lai
* Community consultations involved engagement with the clan leader, local elders, youths and women. The communities were divided into two groups based on gender.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-17
During meetings stakeholders were notified of the start of the draft ESIA
comment period, which began on the 2nd of December 2014 and ended on the
2nd January 2015. The availability of the Draft ESIA report was advertised in
two newspapers namely “The Ethiopian Herald” and “The Reporter” (both
adverts were in English). The report was also made available through the
project website.
Upon completion of engagement activities, the ESIA Report was revised to
take into consideration the feedback gained from stakeholders. A summary of
key comments and concerns raised during this phase of engagement is
provided in Table 7.7.
7.7 FINAL ESIA REPORT CONSULTATION AND DISCLOSURE
The Final ESIA report was supplemented by additional stakeholder
engagement efforts during February 2015, namely dislocsure and consultation
of the Final ESIA Report. The objective of this phase consultation was to close
out the stakeholder engagement process and generate ‘sign-off’ by affected
community members on their position in response to the proposed Project as
well verifying the engagement process undertaken.
During this phase of engagement the following activities were completed:
Incorporated Feedback and Updated Final ESIA Report – all feedback received from stakeholders was documented, considered and where relevant incorporated within the Final ESIA Report. This included updating of the Stakeholder Engagement Plan (this document) and the ESIA Stakeholder Enagagement Chapter with records of engagement activities including:
Meeting minutes; Attendance registers; Engagement tools; and Updated comment and response report.
Presentation of the Final ESIA Report for ‘sign-off’ by the by the local
Authorities (Woreda and Kebele leaders) and communities.
Disclosure of the Final ESIA Report – the final updated ESIA documents
were submitted to the relevant Authorities for approval.
All engagement tools and materials are appended to Appendix F.
Engagement activities during this phase were undertaken through a series of
consultation events with local stakeholders that seeked to:
Describe where stakeholder revisions to the Draft ESIA were made;
Provide a description of the final impacts identified in the ESIA;
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-18
Receive sign-off from local stakeholders on their position in response to
the proposed Project as well verifying the engagement process
undertaken; and
Identify the completion of the ESIA stakeholder engagement process.
The details for this phase of engagement is provided in detail in Appendix F.
7.8 KEY ISSUES RAISED DURING STAKEHOLDER ENGAGEMENT
The key issues identified during stakeholder engagement (namely Screening,
Scoping, baseline data collection and Draft ESIA) are summarised in Table 7.7
and Table 7.8. These issues together with the findings of baseline data
collection have been considered when compiling the Social Impact
Assessment presented in Chapter 11 (Part I of the ESIA).
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-19
Table 7.7 ESIA Related Issued Raised During the Scoping Phase
Issue Category Issue Details on the Issue Stakeholder Raising Issue
Anticipated
Impacts
Water resources Stakeholders’ at all three levels identified significant concerns around the
perceived scarcity of water in the local area, and potential impacts for
abstraction of water for mining related activities, which may result in
decline of water resources available for the local population and animals.
The abstraction of groundwater could result in a decline of water
recharging the pools located on Mount Dallol (which are key tourist
attractions).
The potential decline in groundwater levels caused by abstraction of
water by Yara could result in the decline in important vegetation in the
area, including plants that livestock and camels feed on, as well as doum
palms that are a key source of income for local women, and hold cultural
value for the Afar people.
All stakeholder groups
Tourism The overall development of the area will deter tourists from visiting the
area, in particular if the area becomes industrialised.
Concerns were raised over the proximity of Yara Dallol BV’s license area,
as well as other developments in the area to Mount Dallol.
The increases in traffic that have already been reported in the local area
from mining companies is reported to be causing pollution (dust) and
disturbance to tourists that stay in Hamad Ela.
The potential decline in water resources will have secondary impacts on
surface water bodies located on and around Mount Dallol, which form
key tourist attractions.
The development of infrastructure (mainly the road) by the federal
government for mining companies in the Danakil Depression will lead to
increases in-migration, resulting in disturbance and pollution of
important landmarks and tourist attractions.
Federal government
Regional government
Local government
Tourism operators
Local communities
In-migration The development of infrastructure in the local area, as well as the
presence of mining companies in the area is likely to result in in-
migration. Concerns were raised over the secondary impacts such as
pressure on existing infrastructure, localised inflation and competition
over land and resources.
In-migration and resulting changes in the local health profile
(communicable diseases including sexually transmitted diseases) is a key
concern. A lot of case studies from the extractives sector elsewhere in
Ethiopia were referenced where increases in the communicable disease
Federal government
Regional government
Local government
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-20
Issue Category Issue Details on the Issue Stakeholder Raising Issue
have not been managed adequately.
Traffic Increases in traffic have been noted in the local area, much of which is
attributed to mining companies including Yara Dallol BV. The increase in
traffic is reported to have led to increased pollution and disturbance to
local residents and tourists.
Concerns over the increases in traffic will lead to disturbance to important
areas, such as those used for salt collection and where important
vegetation is found.
Tourism operators
Federal government
Local communities
Ecology The Danakil is identified to be an area that has not been studied in detail;
therefore there are concerns that species (flora and fauna) exist that are
specific to the Danakil and may be threatened by project activities.
The potential decline in water resources due to groundwater abstraction
by Yara Dallol BV may threaten local biodiversity.
Further studies should be conducted with regards to the ecological nature
of the area, taking into account potential seasonal variations in the local
ecology.
Academic and research
institutions
Regional government
Local government
Health Potential impacts on the health and safety of people recruited by Yara
Dallol BV, in particular local people who may not be accustomed to
working for a mining company.
Changes to the community health profile (increases in communicable and
sexually transmitted diseases) due to potential in-migration of people, as
well as the introduction of a workforce by Yara Dallol BV.
The potential decline in water resources due to mining activities may
have consequences on community health, as they access water through
hand dug wells. In addition there maybe secondary impacts to key
resources (salt, palms) that are used to generate income.
Federal government
Regional government
Local government
Local communities
Community associations
Military There is reported to be an unnecessary use of the military in the local area,
as well as recruitment of militia.
Reports of the military being used to threaten stakeholders (in particular
local communities).
Regional government
Local communities
Access and use of land (and natural resources)
Land use and access is still administered through a common property
regime, although government policies contradict this.
People in the local area are mobile, and are accustomed to accessing land
and resources in a seasonal nature. The movement of people and
pastoralist activities need to be considered by Yara Dallol BV, as well as in
the ESIA process.
Pastoralists were identified as a potentially vulnerable group, and
measures need to be developed to ensure that pastoralists are able to
Regional government
Local government
Academic and research institutes
Local communities
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-21
Issue Category Issue Details on the Issue Stakeholder Raising Issue
adapt and benefit to any changes that the proposed Project brings.
Archaeology and cultural heritage
There are numerous locations across the local area that are used for
burials.
In addition there are important cultural landmarks such as Mount Dallol
and Ashe Ale that need to be protected from potential disturbance and
damage.
Local communities
Regional government
Local government
Academic and research institutes
Gender The impacts to women need to be considered in the ESIA process.
Women are a potentially vulnerable group due to their position in Afar
society. In addition they chiefly rely on the collection of palms to generate
an income, thus protection of this resource is key.
Women should look to benefit from the proposed Project through
community development activities and employment opportunities.
Regional government
Local government
Community associations
Process Related Engagement Further engagement should be conducted with stakeholders, in particular
with local stakeholders to ensure that they are aware of the proposed
Project, its stages and activities.
Regional government
Local government
Local communities
Methodologies for specialist studies
Request for detailed methodologies around specialists’ studies and their
results should be presented in the ESIA report, in particular the
hydrological studies.
Federal government
Regional government
Academic and research institutes
Communication
and engagement
Consistency in
communication
Inconsistencies in communication with stakeholders were identified at the
local level in particular. This predominantly revolved around
communication regarding labour and recruitment opportunities.
Regional government
Local government
Local communities
The proposed
Project
There are several misconceptions around the proposed Project including:
Ownership of the Project.
Stage of the Project.
Location of the Project.
Regional government
Local government
Local communities
Existing impacts Labour and
recruitment
Numerous concerns were raised with regards to labour and recruitment
practices (actual or perceived) including:
Inconsistency in the way in which contracts are terminated, including
communication around this.
Preferential recruitment and treatment of non-Afar employees.
Inequalities in the positions and salaries offered to Afari employees.
Regional government
Local government
Local communities
Water Concerns were raised that the presence of mining companies in the area
over the past three years has led to a decline in water resources.
Local communities
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-22
Issue Category Issue Details on the Issue Stakeholder Raising Issue
Traffic Complaints raised that Yara Dallol BV (and other mining companies working
in the area) has led to an increase in traffic in the local area, with resulting
impacts to:
Air pollution (dust emissions).
Damage to local vegetation.
Potential accidents with communities and livestock.
Disturbance to tourists.
Local government
Local communities
Tourism operators
Anticipated
benefits
Employment There is considerable expectation for local stakeholders to benefit from
employment opportunities arising from the proposed Project.
The importance of local communities benefiting from the proposed
Project was highlighted at all levels.
Regional government
Local government
Local communities
Community
development
initiatives
Expectation that in addition to employment opportunities, stakeholders will
benefit from community development initiatives.
It was acknowledged that local stakeholders are not likely to largely benefit
from employment opportunities, in particular skilled positions. Therefore it is
expected that local stakeholders should benefit from proposed community
development initiatives including:
Access to potable water;
Support and improvement to health and educational facilities;
Capacity building and skills training.
Federal government
Regional government
Local government
Local communities
Table 7.8 Issued Raised During the Draft ESIA Phase
Issue Category Issue Further Detail on the Issue Stakeholder Raising Issue
Labour and
employment
Recruitment Numerous questions were raised about employment and
recruitment, including:
The number of jobs that will be created.
The number of jobs that will be reserved for the local
population (Afar people).
Future plans to increase the number of Afar people
employed by the Project.
Inequalities in the salaries offered to Afari employees
compared to non-Afari.
Regional government
Local communities
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-23
Issue Category Issue Further Detail on the Issue Stakeholder Raising Issue
Conditions of employment Comments were made from stakeholders regarding the need:
For allowances for the workforce to become part of a
trade union should they wish.
To ensure the presence of a recruitment and employment
policy.
To ensure that all employees have signed contracts and
that the contracts are explained to the workforce.
Regional government
Workforce health and safety Numerous issues/ comments were raised at a regional level
regarding the conditions of employment of the workforce. The
key health and safety considerations suggested included:
Ensure the presence of a recruitment and employment
policy.
Ensure that the availability of equipment for the
workforce.
Ensure the presence of a workforce compensation plan
for on-the-job injuries.
Ensure the presence of a workforce HIV/AIDs policy.
Provision of workforce accommodation with accepted
standard for the workforce.
Regional government
Skills development Stakeholders wanted to know the following regarding skills
development and training:
If Yara Dallol BV will be providing training;
The type of training that will be provided; and
The potential recipients of training.
Regional government
Local government
Local communities
Community Benefits
(excl. jobs)
Community development
initiatives
Issues of community development were raised with the
majority of stakeholders acknowledging that the local people
are likely not going to benefit from employment
opportunities, in particular skilled positions. Therefore, it is
expected that local population should benefit from proposed
community development initiatives including:
Improved access to potable water;
Support and improvement to health and educational
facilities; and
Capacity building and training.
Federal government
Regional government
Local government
Local communities
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-24
Issue Category Issue Further Detail on the Issue Stakeholder Raising Issue
Water
Water abstraction Stakeholders raised concerns related to:
The potential decline in groundwater levels caused by
abstraction of water by Yara Dallol BV could result in the
decline in important vegetation in the area, including
plants that livestock and camels feed on, as well as doum
palms that are a key source of income for local women,
and hold cultural value for the Afar people.
How the abstraction of water for the project could affect
the sulphur pools on Mount Dallol.
Whether the water abstraction model considered the
impacts of climate change.
Whether the abstraction of water (saline and fresh
water) will reduce the natural production of salt.
Federal government
Regional government
Local government
Local communities
The need for Yara Dallol BV to further engage with the
Ministries and Bureaus responsible for water management
was highlighted.
Federal government
Regional government
Local government
Local communities
Yara Dallol BV was requested to bring the water specialist
team to present their finding to the Ministry responsible for
water management as well as share the data that has been
collected for the purposes of the study.
Federal government
The need to understand if the mining companies in Dallol will
be abstracting water from the same fans was highlighted.
Federal government
Blockage of surface runoff Stakeholders raised concerns related to:
The construction of Yara Dallol BV roads blocking water
from reaching the palms, and salt ponds.
That all three mining companies have to varying degrees
blocked surface runoff from reaching palms; with their
secondary roads to the drilling wells and some palm trees
are dying.
The access roads to the testing wells of all three mining
companies are blocking salty surface water from reaching
the salt area. If nothing is done now, there will be no
more salt to mine.
Local government
Local communities
Cumulative Impacts Concerns over the cumulative impacts of water abstraction by
multiple mining companies have the potential to deplete the
Federal government
Regional government
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-25
Issue Category Issue Further Detail on the Issue Stakeholder Raising Issue
water that communities' rely on. Local communities
Air pollution
Increased generation of dust Although the population of Musley is small at present, after
the rains the population increases as people move to the area
for grazing; as such higher numbers of people may be affected
by changes in air quality as a result of the project.
Local communities
Air quality The proposed processing plant contributed to concerns with
changes in air quality particularly the health implications of
constructing a processing plant and perceptions it could
increase emissions. Stakeholders also stated that when there
are high winds they can smell the sulphur from Mt Dallol all
the way in Hamad Ela.
Regional government
Local government
Local communities
Waste
Waste management Concerns were raised regarding the quantities, handling
and disposal of solid and hazardous waste by the
company, with the stakeholders stating that one of the
companies in the area had dumped some chemical on the
surface. This waste chemical is said to be moving closer to
an area where salt collection is being undertaken.
The communities were not sure which company had
disposed of the chemical in the area.
Other stakeholders raised comments regarding the
absence of local waste disposal and treatment areas.
Federal government
Regional government
Local government
Local communities
Radioactive chemicals Concerns with the potential use of radioactive chemicals in the
plant were raised.
Federal government
Biodiversity
Impact on palms Stakeholders raised the following concerns:
Palms are dependent on both saline and fresh water; as
such the decrease in any of these water types has the
potential to affect the palm trees.
The relocation of any palm tree should be undertaken
with guidance of a local person as they have a better
understanding of the plants than experts from abroad.
Local stakeholders have never seen a successfully
relocated palm tree in the area.
Federal government
Regional government
Local government
Local communities
Impacts on salt Concerns were raised regarding the potential contamination
of salt collection areas by chemicals from the project.
Regional government
Local government
Local communities
Fauna Stakeholders raised the following concerns:
Federal government
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-26
Issue Category Issue Further Detail on the Issue Stakeholder Raising Issue
Ensure that wildlife such as the dessert fox, Egyptian
vulture, wild-ass and killifish are not lost due to the
project and its activities.
The project site is a potential wild-ass habitat and this is
an endangered species particularly sensitive to
interference.
In-migration
Increased burden of diseases Stakeholders expressed concerns related to potential changes
to the community health profile (increases in communicable
and sexually transmitted diseases) due to potential in-
migration of people, as well as the introduction of a workforce
by Yara Dallol BV.
Local communities
Cultural heritage
Disruption of burial and
prayer sites
There are numerous locations across the Project Area and
surrounds that are used for burials and prayers and these
should not be disturbed.
Federal government
Local communities
Visual
Change in sense of place Stakeholders at a local level were divided regarding the visual
impacts of the project, especial the proposed processing plant.
Comments varied including:
Measures should be put in place to ensure minimum
changes in the landscape of the area.
There is no need for Yara Dallol BV to use colours that
blend with the natural surroundings, bright colours and
large structures will be acceptable and will transform the
area.
Local communities
ESIA Process
Specialists All people undertaking the study are experts in their fields
and the communities’ trust that the specialist know best.
Local communities
Content of ESIA Some concerns were raised regarding the content of the draft
ESIA which included:
The ESIA should address cumulative impacts;
The social impact assessment should use qualitative and
quantitative data in its analysis of impacts; and
Issues of occupational health and safety should be
highlighted in the ESIA.
Federal government
Perceptions of Yara
Dallol BV
Perceptions of Yara Dallol BV In numerous meetings stakeholders stated that Yara Dallol BV
is a good company and those they have not heard anything
bad about the company.
Regional government
Local government
Local communities
Noise Increased noise levels Stakeholders raised the following concerns: Local communities
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-27
Issue Category Issue Further Detail on the Issue Stakeholder Raising Issue
Project vehicles should not travel at night as they will
increase the noise levels in the area and people will not be
able to sleep.
Although the population of Musley is small at present,
after the rains the population increases as people move to
the area for grazing; as such higher numbers of people
may be affected by changes in noise levels as a result of
the project.
Stakeholder
Feedback
Communication There have been no responses on the issues raised as part of
the Scoping phase of the project.
Federal government
Stakeholder
Engagement
Language of materials Considerations should be made to translate the project
booklets into Afar as a limited number of people can read
Amharic at community level.
Local communities
Presentation The consultants were thanked for presenting detailed findings
of their study in a clear and concise manner.
Local communities
Participation Stakeholders raised concerns that there is a need for better
government participation in the ESIA meetings as the
implementation of the projects will require collaboration
between various government offices.
Federal government
Project Design
Source of electricity Many stakeholders questioned the use of electricity from the
national grid instead of the solar energy which is in
abundance in the area.
Federal government
Regional government
Climate change Some concerns were raised regarding the extent to which
climate change has been considered in the planning for the
project.
Regional government
Seismic Concerns were raised regarding whether the engineering and
planning have undertaken the necessary precautions
regarding seismic activity.
Federal government
Processing plant A concern was raised regarding no mention of the impact
associated with the processing plant in the project
presentation.
Federal government
Regional government
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-28
The key outcomes of draft ESIA engagement are discussed in the SEP Annex C of Part II of this ESIA, which also provides the responses given to the issues and comments raised.
7.9 NEXT STEPS IN THE STAKEHOLDER ENGAGEMENT PROCESS
Following the submission of the final ESIA report the records of engagement
including the endorsement letter verifying the community’s position on the
proposed Project will be appended to the report. This will be reviewed by the
competent authority who will inform Yara Dallol BV of their Record of
Decision (RoD). Following receipt of the RoD Yara Dallol BV will make this
available to stakeholders as well as provide information on the appeals
process. Following the completion of ESIA engagement process ERM’s
stakeholder engagement team will arrange for a handover to Yara Dallol BV of
key project information including the stakeholder database and issues table.
7.10 FEEDBACK MECHANISM
Each round of engagement undertaken has provided stakeholders with an
opportunity to provide input and feedback on the proposed Project and ESIA
process. A feedback mechanism has been put in place for use throughout the
ESIA process to ensure that potential concerns raised by stakeholders during
engagement are acknowledged and addressed in a timely, structured and
culturally appropriate manner. These have been captured by the ESIA team.
It remains important to offer stakeholders an opportunity to both provide
feedback and receive responses after the completion of the ESIA process. In
light of this, Yara Dallol BV has developed an External Feedback and
Grievance Mechanism.
The ESIA feedback mechanism is discussed in further detail in Section 7.10.1,
Yara Dallol BV’s Grievance Mechanism is outlined in Section 7.10.2.
7.10.1 The ESIA Feedback
An ESIA feedback mechanism was communicated to the stakeholders during
the Scoping Phase and it is being managed by ERM and it’s in country
partners TS Environmental Technology. The feedback mechanism seeks to:
Provide Opportunities to Provide Feedback
Record Feedback – all input received through the engagement process
and other communication channels are recorded via meeting records and
the feedback log.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-29
Generate Responses – the ESIA team together with Yara Dallol BV review
comments received and generate comments after each phase of
engagement.
Communicate Responses to Stakeholders who have Raised Comments –
all opinions and concerns noted during stakeholder engagements are
recorded and a summary of the feedback and comments is maintained.
The following feedback channels have been available to stakeholders through
the course of the ESIA process:
Electronic and telephone feedback, email and telephone contact details
have been made available to stakeholders for the ESIA team and two Yara
Dallol BV contact persons; and
Engagement activities undertaken directly with stakeholders during the
draft ESIA and disclosure phases.
7.10.2 Summary of Yara Dallol BV’s External Feedback and Grievance Mechanism
Yara Dallol BV have recently developed and implemented an External
Feedback and Grievance Mechanism. The mechanism outlines Yara Dallol
BV’s approach to accepting, assessing, communicating, resolving and
monitoring grievances from those affected by Project activities including
contractors’ activities. This mechanism has been implemented in parallel to
the ESIA and will continue to be used by Yara Dallol BV post the ESIA
process. Furthermore, the mechanism is designed to complement the ESIA
engagement process and grievances related to the ESIA can be submitted to
this mechanism.
The section below provides a brief description of Yara Dallol BV’s External
Feedback and Grievance Mechanism.
The mechanism has been designed to meet the requirements of the IFC in
relation to Performance Standards 1, 5 and 7 and it has the following
objectives:
To provide a simple, fair and transparent process for all external parties to
submit feedback and to raise grievances. This shall result in outcomes that
are fair, effective and lasting.
To provide a simple process for company personnel to redress any issues
and concerns raised by stakeholders in a methodical and time bound
manner.
To mitigate risks and impacts to all external stakeholders due to project
operations, demonstrating company care for the wellbeing of its
stakeholders.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-30
To build trust and goodwill as an integral component of the stakeholder’s
relation activities, and promote trust and respect with stakeholders,
particularly at a community level.
To enable for the systematic identification of emerging issues and trends,
facilitating corrective and pre-emptive engagement.
The mechanism sets out roles and responsibilities for implementation, from
corporate to site level. The document also describes the process for responding
to and dealing with feedback and grievances. Figure 7.3 illustrates the process
described in detail in the Grievance Mechanism.
The Grievance Mechanism stipulates the need for the following:
Training – those responsible for responding to feedback and grievances
must have detailed knowledge on how the project’s feedback and
complaints mechanism.
Record Keeping – all aspects of the feedback and grievance management
process must be comprehensively documented and accurate records
should be maintained.
Reporting - each Yara Dallol BV offices / business unit (site, Mekele,
Addis Ababa) will compile information relating to engagement activities
as appropriate for the weekly social and environmental reports.
Review - the Grievance Mechanism will be periodically audited and
reviewed to determine its accuracy and relevance with regard to
legislation, education, training and technological changes.
The Feedback and Grievance Mechanism states that the Procedure are linked
to the Stakeholder Engagement Plan as both involve interaction with Yara
Dallol BV’s stakeholders.
ENVIRONMENTAL RESOURCES MANAGEMENT YARA DALLOL BV
7-31
Figure 7.3 Operational Process for Grievance Resolution
Source: Yara Dallol BV Feedback and Grievance Mechanism Procedure – Version 1