6MSD Weekly Scheduling Meeting
Wednesday’s 1:30, MCC Conference Room
May 25, 2011
1) Glance Back and 2-Week Look Ahead (W. Oren) .................................................. 5 mins
2) PMI Report (P. Collins) ........................................................................................... 5 mins
3) Critical Path Service Provider Reports .................................................................. 20 mins a) Alignment (Curtis) b) Magnet Refurbishment (Baggett) c) Installation/Alignment (Wilson) d) Radcon (Hamlette)
4) Halls Status Report (Ed Folts) .............................................................................. 10 mins
5) Special Topics –Weekend Success (M. Wright for J. Creel) ................................... 5 mins
6) Safety Report (Logue) ............................................................................................ 5 mins
7) Meeting Recap and Action Items (All) ..................................................................... 5 mins
6MSD:6MSD: Glance back & look ahead
Will Oren for Fulvia Pilat
6MSD Meeting
M 25 2011May 25, 2011
Glance Back May 18 - 24
Catching our Stride!Call Outs to:
• W. Arc Dipole removal effort– started 1 week ago, ½ of arc is already out. Baseline removal was to start this Friday!this Friday!
• Site power outage work –
– tremendous amount of electrical work completedtremendous amount of electrical work completed including June 4 outage avoidance
– wonderful preparation and recovery efforts –p p ywork planning paid off!
• R100 installation & cooldown – testing begins tomorrow.
2-week Look Ahead
6 Month Down SAD Calendar6 Month Down SAD Calendar
2 week look ahead – hot topics -updateWhat we want to learn:
H th l f t l d f bi h• How the early process of magnet removal and refurbish goes (to readjust our projections if needed) – looks good need to watch egress challenges during reinstallation & alignment.
• Test results for R100 to later compare with C100, and decide on future cryomodule production ongoingdecide on future cryomodule production ‐ ongoing
• About the water drenched adjustable jaw for the new FEL wiggler – still being evaluated. May be September. Considering restarting with IR operations on the original operations schedule.
“Change Requests/Notes to File” Report
• Approved:– “Blockhouse Demolition and Block Crushing” – 1st 2
k f J Mi h i d d i t kweeks of June. Microphonics dependencies take “priority”
• Pending/Working:Pending/Working:– “LCW Draining & Refilling/Recommissioning” ‐draining in progress but refilling/recommissioningneeds further consideration
– “Tunnel Penetration Repair” – penetration selection in progressprogress
– “Hall C Work Definition and Schedule Adjustments” –being evaluated by effected parties.
&PM&IP
6MSD 5/25/11 Weekly Progress Meeting(5/20/11 Data)
PM&IP• FEL LCW Contract Complete projected ~17 days behind
schedule• Hall D LCW Manifold Installation is 4 days behind• Hall D LCW Manifold Installation is 4 days behind
schedule.• Resource issues next 2 weeks
– Mech Vac Tech 25July, 27 and 28July utilization > 0.8 (Hall A G2P and 12GeV work) DC El T h 24M Th 27 M– DC Elec Tech 24May Thru 27 May (Hall A G2P,12GeV and PEPPo work)
PM&IP• Other Schedule Information at
https://www.jlab.org/6MSD_Integrated_Schedule/SCHEDULES/– Two Week Look Ahead - Shows all activities that have started
that are not complete and any activities due to start in the next two weeks
– Critical Path – Shows all MUST activities that have 2 days or less yfloat.
– Schedule Variance - Shows all MUST activities that are not 100% complete and that the Start/Finish dates have slipped by at p pp yleast 5 days.
Shutdown Work Summary Organization: Alignment
Name: Chris Curtis
Date: 25 May, 2011
Last Week
Work That Went Better Than Expected:
West Arc dipole as‐founds and levels complete
East Arc magnet as‐founds complete, levels continuing
Work That Went Slower Than Expected, Delays, and Issues: None
Ongoing Shutdown Work
Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Tasks Comments/Concerns
12GeV Linacs X Tue, May 31 C‐100 cryomodule fiducialization Second stage on C‐100 #1 12GeV Linacs X Thu, Jun 2 C‐100 alignment 12GeV Hall D X ??? Location check on photon beam
pipe between Tagger and Hall D. Possible start next week on control setup
&PM&IP
6MSD 5/25/11 Weekly Progress Meeting(5/20/11 Data)
PM&IP• FEL LCW Contract Complete projected ~17 days behind
schedule• Hall D LCW Manifold Installation is 4 days behind• Hall D LCW Manifold Installation is 4 days behind
schedule.• Resource issues next 2 weeks
– Mech Vac Tech 25July, 27 and 28July utilization > 0.8 (Hall A G2P and 12GeV work) DC El T h 24M Th 27 M– DC Elec Tech 24May Thru 27 May (Hall A G2P,12GeV and PEPPo work)
PM&IP• Other Schedule Information at
https://www.jlab.org/6MSD_Integrated_Schedule/SCHEDULES/– Two Week Look Ahead - Shows all activities that have started
that are not complete and any activities due to start in the next two weeks
– Critical Path – Shows all MUST activities that have 2 days or less yfloat.
– Schedule Variance - Shows all MUST activities that are not 100% complete and that the Start/Finish dates have slipped by at p pp yleast 5 days.
Project & Customer Status Completion Tasks Comments/Concerns
Q‐Weak X TBD Hall C monitoring Need to define exact scope; possible start next week
G2p X Oct Stand layout Possible (early) start next week. 12Gev civil x Jul BSY penetrations Layout next week
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Tasks Comments/Concerns
12 Gev Arcs X TBD Alignment of re‐installed dipoles Start Wed 1st June?
New Work Requests Requiring Schedule Changes: Hall B HD‐ice work – to be defined
Permits Not Already in Hand (hot work, lifting, blind penetrations): None
Significant Problems Pending (delays, technical issues, resource issues, scheduling): None
Staffing Outlook: OK, training continuing
Shutdown Work Summary Organization: Magnet Measurement
Name: Ken Baggett
Date: May 25,2011
Last Week
Work That Went Better Than Expected: Magnet Removal ‐ ~2 Stacks/Day Magnet Refurbishment – The condition of the arc magnets are better than expected Magnet Measurement – 6GeV baseline measurements completed
Work That Went Slower Than Expected, Delays, and Issues: Crane problem in magnet measurement area delayed operations (1 day)
Ongoing Shutdown Work
Table 2: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Tasks Comments/Concerns
12GeV x ongoing Remove Stacks 8‐12 12GeV x ongoing Refurbish Stacks 2,3, 4 (part) 12GeV x ongoing Measure Stacks 1,2 12GeV x ongoing Re‐install Stacks 1
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Tasks Comments/Concerns
Project & Customer Status Completion Tasks Comments/Concerns
Injector x August Map 5 magnets Second stepper stand PS will be available soon to help with this.
Hall D x June Chamber measurements Can do on second stepper stand now
New Work Requests Requiring Schedule Changes: None
Permits Not Already in Hand (hot work, lifting, blind penetrations): None
Significant Problems Pending (delays, technical issues, resource issues, scheduling): None
Staffing Outlook: Good
Shutdown Work Summary Organization: MSINST
Name: Neil Wilson
Date: 5/25/11
Last Week
Work That Went Better Than Expected: Dipole Disconnect Mech. & Vacuum FEL GTS Block Removal Stand Grouting
Work That Went Slower Than Expected, Delays, and Issues: N&SLINAC ceiling plate re‐install, waiting on cable pulls.
Ongoing Shutdown Work
Table 3: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Tasks Comments/Concerns
12GeV X 5/26 Beam Pipe Disconnect 12GeV X Cartridge & Stem Work Interferences with Dipole removal
will prevent completion until all dipoles removed
6GeV X 5/27 Septa & RF Separator Blow Out Working
Project & Customer Status Completion Tasks Comments/Concerns
G2P X 5/27 Equipment/Pb removal 12GeV X 6/1 EESDC Pene. Emptying 12GeV X 6/1 Build New Warm Region Girders Working 12GeV X 10/1 N&SAB LCW Upgrade Working 6GeV X 6/1 Swapping Out Vacuum Valves
Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Tasks Comments/Concerns
12GeV X SL22 CPS Installation Delivery Date 5/31??12GeV X Secure Klystron Racks After SL22 CPS Installed12GeV X Dipole Hook UpG2P X Stand Installation ????FEL X Vacuum Support
New Work Requests Requiring Schedule Changes: EESDC Pene. Work
Permits Not Already in Hand (hot work, lifting, blind penetrations): None
Significant Problems Pending (delays, technical issues, resource issues, scheduling): None
Staffing Outlook: All Slots Filled
Shutdown Work Summary Organization: RADCON
Name: David Hamlette
Date: 05/24/11
Last Week
Major Milestones Reached on Continuing or Completed Projects: Completed surveys and labeling of dipoles in the West arc North East stub area downgraded to Radioactive Materials Area Beamlines removed for NE construction to begin SL girders surveyed/removed with disassembly/tagging of RAM ongoing Hall A Target removal
Ongoing Shutdown Work ( green = no concerns; yellow = some concerns; red = serious concerns)
Project & Customer Status Completion Upcoming Milestones Comments/Concerns
12 GeV Hall D X Complete De‐post NE portion of accelerator Area RCA de‐posted to RMA.
12 GeV Magnet rework X Ongoing Posting of NAB/SAB SAB area partially posted RMA for dipole magnet staging.
Hall A Target work X Ongoing Begin reconfiguration of target chamber Target work is ongoing w/RadCon support
Hall A support X Ongoing Release survey Several surveys to accommodate users and staff for equipment removal.
Hall C support x Ongoing Release surveys Several surveys to accommodate users and staff for equipment removal.
Soil Density Testing x Ongoing Support of SDT Processes are flowing smoothly
Project & Customer Status Completion Upcoming Milestones Comments/Concerns
Q‐weak Rad cool down X Ongoing SOS removal/bellows‐beamline mod Decaying slowly – dose rate@dump still >1R/hr wb
LCW piping(downstairs) X Ongoing Disposal of downstairs old piping Survey/smear taken and presently being analyzed
New Work Requests Requiring Schedule Changes: N/A
Permits Not Already in Hand (hot work, lifting, blind penetrations): N/A
Significant Problems Pending (delays, technical issues, resource issues, scheduling): Minor posting issues raised by recent DOE walkdown(taped‐off rad‐impacted /high traffic areas)
Staffing Outlook: Positive
G2PTarget installation and Beyond
ScheduleSchedule
Pivot beforePivot before
• How it looks now
Installed
Ep beforeEp before
• Coming out
• How it looks now
Slow rasterSlow raster
• Going in
• How it looked before
• How it looks now
Upside down girder afterUpside down girder after
• Going In
Long girder beforeLong girder before
• Coming out
• How it looks now
Chicane afterChicane after
• Going in
Chicane power supply and equipment area
Septum statusSeptum status
• Final assembly and magnetic field testing
Questions?
First Aid Injury 31Good Day!
First Aid Injury*Click on symbol in calendar for details
28 29 30Recordable Injury*Click on symbol in calendar for
9
28 30ydetails
Other Noteworthy
22 24926
Events *Click on symbol in calendar for details
13 152517 19
21 2322 24 26
271913 15
1814 1617 19 20
19
Safety Observations Through 5/24/11Safety Observations Through 5/24/11
• 62 Observations made62 Observations made of 6MD related work
• 63% were all‐safe
Category Number of Observations
Percent of Observations
All Safe 39 63%
Ladders 7 11%
– Consistent with experience with on‐site
i i i
PPE 5 8%
Housekeeping 4 6%
Excavations 3 5%
E i t 2 3%construction activity Equipment 2 3%
Heights 2 3%
IssuesIssues
• Hot Work PermitsHot Work Permits
• Eating/Drinking in RMA