6511- CPA FVR_26Jun2012

Embed Size (px)

Citation preview

  • 7/30/2019 6511- CPA FVR_26Jun2012

    1/58

    CPAVALIDATION REPORT

    DET NORSKE VERITAS

    Title of CPA:

    SOCFINDO EFB PLUS POMECO-COMPOSTING PROJECT (CPANO.001)

    Title of PoA to which CPA is to be included:

    CO-COMPOSTING AND COMPOSTING

    PROGRAM OF ACTIVITIES FORPALM OIL

    MILLS IN INDONESIA

    REPORT NO. 2011-9535/01REVISIONNO.01

  • 7/30/2019 6511- CPA FVR_26Jun2012

    2/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    4_Socfindo_CPA_FVR_01_WONGS_Brinks_FA_WONGYS_mleh_FA_mleh_FA_20120613_mleh20120615_FA_20120620_clean.docx

    DNVCLIMATE CHENGE

    SERVICES AS

    Climate Change & EnvironmentalServicesVeritasveien 1,1322 HVIK, NorwayTel: +47 67 57 99 00Fax: +47 67 57 99 11http://www.dnv.comOrg. No: NO 994 774 352 MVA

    Date of first issue: Pro ect No.:

    31 January 2012 PRJC-314605-2011-CCS-MYSApproved by: Organisational unit:

    Michael Lehmann DNV KEMA Energy & Sustainability

    Accredited Climate Change ServicesClient: Client ref.:

    PT. Socfin Indonesia Harold Williams

    Identification of CPA: Socfindo EFB plus POME Co-composting Project (CPA No. 001)

    Issue date of CDM-SSC-CPA-DD: 31 May 2012 (Version: 03)

    Host Party: Indonesia

    PoA: Co-composting and Composting Program of Activities for Palm Oil Mills in Indonesia

    Methodology: AMS-III.F Version: 10

    CPA ER estimate: 70 910 tCO2eover 7 years or 10 130 tCO2e on average yearlyGHG reducing Measure/Technology: Avoidance of methane emissions through composting

    Size: Large Scale Small Scale

    Validation Phases:

    Desk Review Follow up interviews

    Resolution of outstanding issues

    Validation StatusCorrective Actions Requested Clarifications Requested

    Full Approval and request for inclusion Rejected

    In summary, it is DNVs opinion that the CPA Socfindo EFB plus POME Co-compostingProject (CPA No. 001) as described in the CDM-SSC-CPA-DD of31 May 2012 requesting

    to be included in the PoA Co-composting and Composting Program of Activities for Palm

    Oil Mills in Indonesia, meets the eligibility criteria established in the PoA and all relevant

    UNFCCC requirements for including CPAs in a PoA and correctly applies the baseline and

    monitoring methodology AMS-III.F, version 10. DNV thus requests the inclusion of the CPA

    in the PoA.

    Re ort No.: Date of this revision: Rev. No. Ke words:

    2011-9535/01 2012-06-20 01 CDM

    Kyoto Protocol

    Programme of Activities

    Re ort title:

    Socfindo EFB plus POME Co-composting

    Project (CPA No. 001)

    Work carried out b :

    Simon Wong Yon Sing, Fathullah Akmal

    Khalid, Foo Wei Yee, Denise Lai Siew Sit

    No distribution without permission from

    the Client or responsible organisational

    unit

    Work verified b :

    Hendrik W. Brinks, Michael Lehmann Limited distribution

    Unrestricted distribution

  • 7/30/2019 6511- CPA FVR_26Jun2012

    3/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page i

    Abbreviations

    ABC Aerated Bunker Co-composting Plant

    AMWS Animal Waste Management System

    CAR Corrective Action Request

    CDM Clean Development MechanismCDM-SSC-CPA-DD CDM small-scale programme activity design documentCDM-SSC-POA-DD CDM small-scale programme of activities design documentCH4 Methane

    CL Clarification request

    CME Coordinating/Managing Entity

    CO2 Carbon dioxide

    CO2e Carbon dioxide equivalentCOD Chemical Oxygen DemandCPA CDM programme activityCPO Crude Palm OilDNA Designated National Authority

    DNV Det Norske Veritas

    EFB Empty Fruit Bunch

    EIA Environment Impact Assessment

    EMMP Environmental Management and Monitoring Plan

    FAR Forward Action Request

    FFB Fresh Fruit Bunch

    GHG Greenhouse gas(es)GPS Global Positioning System

    GWP Global Warming Potential

    IPCC Intergovernmental Panel on Climate Change

    MCF Methane Correction Factor

    MP Monitoring Plan

    NCV Net Calorific Value

    NGO Non-governmental Organisation

    NPV Net Present Value

    ODA Official Development Assistance

    PERTAMINA Indonesian National Oil Company

    PKS Palm Kernel ShellsPoA Programme of activitiesPoA-DD Programme of activities Design Document

    POME Palm Oil Mill Effluent

    RSPO Roundtable on Sustainable Palm Oil

    SWDS Solid Waste Disposal Site

    UNFCCC United Nations Framework Convention on Climate Change

    WWTS Wastewater Treatment System

  • 7/30/2019 6511- CPA FVR_26Jun2012

    4/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page ii

    TABLE OF CONTENTS

    1 INTRODUCTION ........................................................................................................ 11.1 Objective 11.2 Scope 12 METHODOLOGY ....................................................................................................... 22.1 Desk Review of the Project Design Documentation 22.2 Site visit and follow-up Interviews 52.3 Resolution of Outstanding Issues 52.4 Internal Quality Control 62.5 Validation Team 63 VALIDATION FINDINGS ......................................................................................... 7Appendix A: Protocol for Assessing Compliance of Specific CDM Programme Activities

    with the Programme of Activities

    Appendix B: Curriculum Vitae of validation team

  • 7/30/2019 6511- CPA FVR_26Jun2012

    5/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 1

    1 INTRODUCTIONPT. Socfin Indonesia has commissioned DNV Climate Change Services AS (DNV) to assess

    the information in the CDM-CPA-DD for the CPA titled Socfindo EFB plus POME Co-

    composting Project (CPA No. 001)(hereafter called the CPA) against the requirements for

    including CPAs to the PoA Co-composting and Composting Program of Activities for Palm

    Oil Mills in Indonesia and further documentation requirements for including CPAs to a PoA.

    This report summarises the findings of the validation of the specific small-scale CDM

    Programme of Activities Design Document (CDM-SSC-CPA-DD).

    1.1

    ObjectiveThe assessment of a CPA requesting to be included in a PoA shall ensure that all therequirements determined in the PoA are met.

    The assessment was performed on the basis of the eligibility criteria established in the PoA

    and the UNFCCC criteria for including CPAs to programme of activities under the Clean

    Development Mechanism (CDM), as well as criteria given to provide for consistent project

    operations, monitoring and reporting according to AMS-III.F Avoidance of methane

    emissions through composting, version10.

    1.2 ScopeThe validation scope is defined as an independent and objective review by a Designated

    Operational Entity (DOE) of the specific CDM-SSC-CPA-DD to be included in the PoA. The

    DOE shall scrutinize the information in the CDM-SSC-CPA-DD to assess compliance with

    the eligibility criteria established by the PoA, to check correctly application of AMS-III.F

    (Version 10) and to check compliance with documentation requirements for CPAs.

    The validation is not meant to provide any consulting towards the programme participants.

    However, stated requests for clarifications and/or corrective actions may have provided input

    for improvement of the project design.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    6/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 2

    2 METHODOLOGYThe validation consisted of the following three phases:I a desk review of the specific CDM-SSC-CPA-DD with relevant information to be

    included in the PoA;

    II follow-up interviews with programme stakeholders

    III the resolution of outstanding issues and the issuance of the final validation report and

    opinion.

    The following sections outline each step in more detail.

    2.1 Desk Review of the Project Design DocumentationThe following table lists the documentation that was reviewed during the validation:

    2.1.1 Documentation provided by the project participants/1/ PT. Carbon Agro Indo: CDM-SSC-PoA-DD for PoA titled Co-composting and

    Composting Program of Activities for Palm Oil Mills in Indonesia, Version 01 dated

    28 June 2011 published for comments and Version 03 dated 17 January 2012 for final

    report

    /2/ PT. Carbon Agro Indo: Generic CDM-SSC-CPA-DD for PoA titled Co-compostingand Composting Program of Activities for Palm Oil Mills in Indonesia, Version 01

    dated 28 June 2011 published for comments and Version 03 dated 31 May 2012 for

    final report

    /3/ PT. Carbon Agro Indo:CDM-SSC-CPA-DD for CPA titled Socfindo EFB plus POMECo-composting Project (CPA No. 001), Version 01 dated 28 June 2011 published for

    comments and Version 03 dated 31 May 2012 for final report

    /4/ PT. Carbon Agro Indo:Financial Analysis Spread Sheet for CPA titled Socfindo EFBplus POME Co-composting Project (CPA No. 001), Version 01 dated 28 June 2011

    published for comments and CPA BB FInancial Analysis ver_3.xls for final report

    Fertilizer savings calculation:Fertilizer Savings_template CPA inclusion_Option A.xls

    Fertilizer savings calculation:Fertilizer Savings_template CPA inclusion_Option B.xls

    /5/ PT. Carbon Agro Indo:Emission Reduction Spread Sheet for CPA titled Socfindo EFB

    plus POME Co-composting Project (CPA No. 001), Version 01 dated 28 June 2011

    published for comments and CPA BB Emission Reduction spreadsheet ver_4.xls forfinal report

    /6/ PT. Socfin Indonesia: Environmental Management and Monitoring Plan (ref. number

    660/084/Tarukim-SB/2005), approved on 20 June 2005

    /7/ Roundtable on Sustainable Palm Oil : RSPO Principles and Criteria for Sustainable

    Palm Oil ProductionIncluding Indicators and Guidance, dated October 2007

    /8/ PT. Socfin Indonesia:Fertilizer Supply Agreements for Dolomite, Muriate of Potash,

    Rock Phosphate Egypt and Urea, for the year 2009

    /9/ PT. Socfin Indonesia: Socfindo Standard Fertilisation Programme, version 09-30 for

    the year 2009

    /10/ PT. Socfin Indonesia:Palm Oil Tree Census for Fertiliser Usage, for the year 2009/11/ PT. Socfin Indonesia:Sales and Purchase Agreement for Dolomite, Urea, Potassium

    nd Rock Phosphate between PT. Socfin Indonesia and various fertilizer suppliers, for

  • 7/30/2019 6511- CPA FVR_26Jun2012

    7/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 3

    the year 2009

    /12/ PT. Socfin Indonesia:Diesel Purchase Invoices, for the months of January 2010 toMarch 2010

    /13/ Carbon Conservation:Proposal for Carbon Services for PT Socfin Indonesia, dated 9

    April 2010

    /14/ PT. Socfin Indonesia:Feasibility Study Co-Composting at Bangun Bandar Mill, dated

    27 April 2010

    /15/ PT. Socfin Indonesia:Minutes of Meeting of the Board of The Commissioners of the

    P.T. Socfin Indonesia (Socfindo) held in Jakarta, dated 28 April 2010

    /16/ PT. Socfin Indonesia:Declaration of No ODA for project activity CPA001- Socfindo

    EFB plus POME Co-composting Project

    /17/ Burden et al: A Business Case for the Aerated Bunker Composting (ABC) System,published in 2010

    /18/ PT. Socfin Indonesia: Report on Stakeholder Consultation Meeting, dated 27

    September 2010

    /19/ UNFCCC Secretariat: Submission of Prior Consideration of CDM Form for PT Socfin

    Indonesia, dated 1 October 2010

    /20/ Indonesian CDM Designated National Authority:Receipt of Document from P.T. Socfin

    Indonesia, dated 12 October 2010

    /21/ North Sumatra Provincial Authority: Wastewater Test Reports for the year 2008, 2009

    and 2010, dated December 2010

    /22/ PT. Socfin Indonesia:Wastewater and Production Records for the year 2008, 2009 and2010, dated December 2010

    /23/ PT. Socfin Indonesia:Contract for Piling Works between PT. Socfin Indonesia and PT.

    Perintis Pondasi Teknotama, dated 4 July 2011

    /24/ PT. Socfin Indonesia:Contract for Concrete, Steel & Roof Works between PT. Socfin

    Indonesia and CV Cikini Raya, dated 4 July 2011

    /25/ PT. Socfin Indonesia: Contract for Precast Concrete Panel between PT. Socfin

    Indonesia and Wijaya Karya Beton, dated 4 July 2011

    /26/ Technical Department of PT. Socfin Indonesia: Clarification on the choice of MCC

    Panel and Bunker Filler, dated 15 August 2011

    /27/ Sucofindo: Wastewater Analysis Certificate for the Wastewater MeasurementCampaign from 11 August 2011 to 23 August 2011, dated 27 August 2011

    /28/ PT. Carbon Agro Indo and PT Socfin Indonesia: Cooperation Agreement to join CDM

    Program of Activities, Co-composting Programme of Activities in Indonesia, dated 3

    October 2011

    /29/ PT. Carbon Agro Indo:Co-composting and Composting Program of Activities for PalmOil Mills in Indonesia Management Plan for the Inclusion of CDM Program of

    Activities (CPAs), dated 16 December 2011

    /30/ Dr John Burden and Rodney Barrett: Commissioning of the Aerated Bunker

    Composting Facility on 8 March 2012, letter dated 14 March 2012

    /31/ PT. Socfin Indonesia: Sample Employee Payslips for the months of January 2010 toMarch 2010, printed on 12 June 2012

  • 7/30/2019 6511- CPA FVR_26Jun2012

    8/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 4

    2.1.2 Methodologies, tools and other guidance by the CDM Executive Board/32/ CDM Executive Board: Validation and Verification Manual, EB44 Annex 1 version 1.2/33/ CDM Executive Board:Baseline and monitoring methodology Avoidance of methane

    emissions through compostingAMS-III.F, EB59 version 10

    /34/ CDM Executive Board: Guidelines on the assessment of investment analysis, EB62

    Annex 5 version 05

    /35/ CDM Executive Board: Information on Additionality (Attachment A of Appendix B of

    4/CMP.1 Annex II), EB63 Annex 24 version 08

    /36/ CDM Executive Board: CDM-SSC-PoA-DD Small Scale CDM Programme of Activities

    Design Document form, EB33 Annex 43 version 01.0

    /37/ CDM Executive Board: General Guidelines to SSC CDM methodologies, EB61 Annex

    21 Version 17/38/ CDM Executive Board: Tool to determine the remaining lifetime of equipment, EB 50

    Annex 15 version 01

    /39/ CDM Executive Board: Standard for Demonstration of Additionality, Development of

    Eligibility Criteria and Application of Multiple Methodologies for Programme of

    Activities, EB65 Annex 3 version 01.0

    /40/ CDM Executive Board: Co-composting Programme of Activities in Indonesia,

    http://cdm.unfccc.int/ProgrammeOfActivities/Validation/DB/2MJW8CICWDNRL1F7

    2DM11M3M8A6Q8M/view.htmllast accessed 20 December 2011

    /41/ CDM Executive Board: Emissions from solid waste disposal sites, EB65 Annex 19

    version 06.0.0/42/ CDM Executive Board:Baseline and monitoring methodology Methane recovery in

    wastewater treatment AMS-III.H, EB58 version 16

    /43/ CDM Executive Board: Tool to calculate baseline, project and/or leakage emissions

    from electricity consumption, EB39 Annex 7 version 01

    /44/ CDM Executive Board: Tool to calculate project or leakage CO2 emissions from fossil

    fuel combustion, EB41 Annex 11 version 02

    2.1.3 Documentation used by DNV to validate / cross-check the informationprovided by project participants

    /45/ Ministry of Environment of Indonesia:EIA Requirements for Projects and/or Activities,

    dated 2 October 2006

    /46/ Intergovernmental Panel on Climate Change: 2006 IPCC Guidelines for Natinoal

    Greenhouse Gas Inventories, published in year 2006

    /47/ Stichnothe and Schuchardt: Greenhouse gas reduction potential due to smart palm oil

    mill residue treatment, published in 2010.

    /48/ Wong Wei-Shen, The Star:Natural BoosterSumatra Bioscience advocates the use of

    organic fertiliser in oil palm plantations for higher yield and environmental

    preservation, dated 4 June 2012

    http://cdm.unfccc.int/ProgrammeOfActivities/Validation/DB/2MJW8CICWDNRL1F72DM11M3M8A6Q8M/view.htmlhttp://cdm.unfccc.int/ProgrammeOfActivities/Validation/DB/2MJW8CICWDNRL1F72DM11M3M8A6Q8M/view.htmlhttp://cdm.unfccc.int/ProgrammeOfActivities/Validation/DB/2MJW8CICWDNRL1F72DM11M3M8A6Q8M/view.htmlhttp://cdm.unfccc.int/ProgrammeOfActivities/Validation/DB/2MJW8CICWDNRL1F72DM11M3M8A6Q8M/view.htmlhttp://cdm.unfccc.int/ProgrammeOfActivities/Validation/DB/2MJW8CICWDNRL1F72DM11M3M8A6Q8M/view.html
  • 7/30/2019 6511- CPA FVR_26Jun2012

    9/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 5

    2.2 Site visit and follow-up InterviewsOn 8 August 2011, DNV visited the project site of PT. Socfin Indonesia and performed

    interviews with project stakeholders.

    Date Name Organization Topic

    /49/ 2011-08-08 Mr. Lufaldy

    Ernanda

    Mr. Mark

    Harding

    Carbon

    Conservation /

    PT. Carbon

    Agro Indo

    Project technology. Project participants. Applicability criteria. Additionality. CDM consideration. Baseline, Project and

    Emission reductioncalculations.

    Stakeholder consultationprocess.

    /50/ 2011-08-08 Mr. P. Sinurat

    Mr. Julians

    Sinuraya

    PT. Socfin

    Indonesia

    Project technology. POME generation COD of wastewater Mill licenses. Legal and environmental

    issues.

    Stakeholder consultationprocess.

    Monitoring plan and projectmanagement

    2.3 Resolution of Outstanding IssuesThe objective of this phase of the validation was to resolve any outstanding issues which

    needed to be clarified prior to DNV's positive conclusion on the CPA. In order to ensure

    transparency a validation protocol was customised for assessing CPAs. The protocol shows in

    a transparent manner the criteria (requirements), means of verification and the results from

    validating the identified criteria. The validation protocol serves the following purposes:

    It organises, details and clarifies the requirements a CPA requesting inclusion is expectedto meet;

    It ensures a transparent validation process where the validator will document how aparticular requirement has been validated and the result of the validation.

    The completed validation protocol for the CDM-SSC-CPA-DD titled Socfindo EFB plus

    POME Co-composting Project (CPA No. 001) is enclosed in Appendix A to this report.

    A corrective action request (CAR) is raised if one of the following occurs:

    (a)The project participants have made mistakes that will influence the ability of theproject activity to achieve real, measurable additional emission reductions;

    (b)The CDM requirements have not been met;(c)There is a risk that emission reductions cannot be monitored or calculated.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    10/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 6

    A clarification request (CL) is raised if information is insufficient or not clear enough to

    determine whether the applicable CDM requirements have been met.

    It must be noted that the CPA titled Socfindo EFB plus POME Co-composting Project (CPA

    No. 001) was submitted for validation together with the PoA-DD for the PoA Co-

    composting and Composting Program of Activities for Palm Oil Mills in Indonesia. The

    validation of the PoA-DD also raised issues relevant to the CPA titled Socfindo EFB plus

    POME Co-composting Project (CPA No. 001). Hence, findings relevant to the CPA titled

    Socfindo EFB plus POME Co-composting Project (CPA No. 001) are included in the

    validation protocol of the validation report (DNV report no. 2011-9535) for the PoA Co-

    composting and Composting Program of Activities for Palm Oil Mills in Indonesia.

    2.4 Internal Quality ControlThe CPA validation report underwent a technical review before requesting inclusion of the

    CPA. The technical reviews were performed by a technical reviewer qualified in accordance

    with DNVs qualification scheme for CDM validation and verification.

    2.5 Validation Team

    Role Last Name F ir st Name Countr y

    Type of involvement

    Deskreview

    Sitevisit/Interviews

    Reporting

    Supervision

    ofwork

    Technicalrev

    iew

    TA13.1competence

    Financialexp

    ertise

    Team leader

    (Validator)

    Wong Yon Sing

    (Simon)

    Malaysia

    Assessor under

    training / Financial

    expert after from

    28 October 2011

    onwards)

    Khalid Fathullah

    Akmal

    Malaysia

    Assessor under

    training

    Foo Wei Yee Malaysia

    Financial expert

    (before 28 October

    2011)

    Lai Siew Sit

    (Denise)

    Malaysia

    Technical

    reviewer

    Brinks Hendrik Norway

    Technical

    reviewer

    Lehmann Michael Norway

  • 7/30/2019 6511- CPA FVR_26Jun2012

    11/58

    DET NORSKE VERITAS

    Report No: 2011-9535/01, rev. 01

    CPAVALIDATION REPORT

    Page 7

    3 VALIDATION FINDINGSThe CPA titled Socfindo EFB plus POME Co-composting Project (CPA No. 001), as

    described in the CDM-SSC-CPA-DD of31 May 2012, meets the requirements to be included

    in the PoA Co-composting and Composting Program of Activities for Palm Oil Mills in

    Indonesia and correctly applies the baseline and monitoring methodology AMS-III.F, version

    10.

    DNV thus requests the inclusion of the CPA titled Socfindo EFB plus POME Co-composting

    Project (CPA No. 001) in the PoA Co-composting and Composting Program of Activities

    for Palm Oil Mills in Indonesia.

    The total emission reductions from the CPA titled Socfindo EFB plus POME Co-compostingProject (CPA No. 001) are estimated to be on the average 10 130 tCO2e per year over the

    selected 7 year crediting period. The emission reduction forecast has been checked and it is

    deemed likely that the stated amount is achieved given that the underlying assumptions do not

    change.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    12/58

    DET NORSKE VERITAS

    Page 8

    APPENDIX A

    PROTOCOL FOR ASSESSING COMPLIANCE OF SPECIFIC CDMPROGRAMME ACTIVITIES WITH THE PROGRAMME OF

    ACTIVITIES

  • 7/30/2019 6511- CPA FVR_26Jun2012

    13/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-1

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    A. General description of CPAA.1. Project boundaries

    A.1.1 Are the CPAs spatial boundaries (geographical)clearly defined, allowing the unique identification of

    the CPA?

    /3/ DR The CPAs spatial boundaries are clearly

    defined in the SSC-CPA-DD. It allows for

    unique identification of the CPA.

    OK

    A.1.2 Are the CPAs system boundaries (components andfacilities used to mitigate GHGs) clearly defined?

    /3/ DR Components and facilities used to mitigate

    GHGs are clearly defined in the projectdocument.

    OK

    A.1.3 Has it been demonstrated that the CPA is within thegeographical borders of the PoA?

    /1/

    /3/

    DR According to the project document, the CPA

    is located in Medan, Sumatera Island, which

    within the geographical and political

    boundaries of the PoA.

    OK

    A.1.4 Has it been confirmed that no part of the CPA isregistered as a CDM project or included in a

    registered POA?

    /3/

    /28/

    DR

    I

    It has been confirmed that the CPA is not

    registered as a CDM project or included in

    another registered PoA.

    This was crosschecked with the information

    available on UNFCCC website and also the

    confirmation from the CPA owner, PT Socfin

    Indonesia in the agreement signed with the

    CME.

    OK

    A.2. Participation requirementsA.2.1

    Which Parties and CPA implementer are participatingin the CPA? Are they included in the PoA? /3/ DR The Host Party is the Republic of Indonesiaand this is mentioned in the SSC-PoA-DD.

    The implementer is PT Socfin Indonesia.There is no Annex I Party for the CPA and

    PoA.

    OK

    A.3. Duration of the CDM programme activity,Crediting Period

    A.3.1Are the CPAs starting date and operational lifetimeclearly defined and evidenced?

    /3/

    /23/

    DR

    IThe CPAs starting date is specified as 4 July

    2011, as evidenced from the contracts signed.

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    14/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-2

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    /24/

    /25/

    The operational lifetime is 20 years. They are

    clearly defined and evidenced.

    A.3.2Has the crediting period been clearly defined and isthe start of the crediting period deemed to be

    reasonable?

    /3/ DR The project selects a 7-year, twice renewable

    crediting period with a total length of 21

    years.

    OK

    A.3.3Has it been confirmed that the length of the CPAcrediting period does not exceed the end of PoA?

    /3/ DR Yes, it has been confirmed that the length of

    the CPA crediting period does not exceed the

    end of PoA.

    OK

    B. Eligibility of CPA and Estimation of EmissionReductions

    B.1. Eligibility criteria for CDM Programme ActivitiesIt is assessed whether the CPA complies with the criteria for

    inclusion in the registered programme of activities.

    B.1.1 Has it been sufficiently justified that the CPAcomplies with:

    Boundary:

    (i) Physical boundary: The entire boundary of the CPA projectactivity must be physically located within the territory of the

    Republic of Indonesia as set out in section A.4.1.2 of the

    PoA-DD.

    (ii)Time Induced Boundary: No CPA shall commence beforethe Start Date of the PoA, as set out in section B.1. of this

    PoA-DD. In addition, no CPA shall commence later than 28

    years after the start date of the PoA-DD as set out in section

    B.1. of the PoA-DD.

    /1/

    /3/

    /23/

    /24/

    /25/

    /49/

    /50/

    DR

    I

    (i) The CPA project activity is physicallylocated within the territory of the

    Republic of Indonesia. The address of the

    project activity is Bangun Bandar crude

    palm oil mill, Martebing village, Dolok

    Masihul district, Serdang Bedagai

    regency, North Sumatra, Indonesia. The

    GPS coordinates provided by the projectparticipant are 985758.70E -

    99436.33 E and 31624.46 N -32032.54 N.The location and GPS coordinates of the

    CPA have been verified during the site

    visit. Therefore, it is confirmed that the

    CPA meets the criteria for physical

    boundary defined in the PoA.

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    15/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-3

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    (ii)The starting date of the PoA is 8 June2011 which is the date of commencement

    of validation. The starting date of the

    CPA is 4 July 2011 and this is evidenced

    from the contracts signed in relation to

    the project activity. The commencement

    of the CPA is approximately one monthafter the starting date of the PoA.

    Therefore, it is confirmed that the CPA

    meets the criteria for time induced

    boundary defined in the PoA.

    Therefore, it is concluded that the CPA

    complies with eligibility criterion 1 stated inthe PoA-DD.

    B.1.2 Has it been sufficiently justified that the CPAcomplies with:

    Double Counting: To avoid double counting of emission

    reductions each CPA must provide specific geographic GPS

    coordinates for the Project Activity to enable uniqueidentification of the Project Activity.

    /1/

    /3/

    /49/

    /50/

    DR

    I

    The GPS coordinates for the CPA are

    985758.70E - 99436.33 E and31624.46 N - 32032.54 N. In addition,

    the address of the CPA has been provided.

    From address details and GPA coordinates, it

    allows for unique identification of the CPA.

    In addition, the address and GPS coordinates

    have been verified during the site visit.Therefore, it is concluded that the CPA

    complies with eligibility criterion 2 stated in

    the PoA-DD.

    OK

    B.1.3 Has it been sufficiently justified that the CPAcomplies with:

    Cooperation Agreement: Each CPA owner must enter into a

    /1/

    /3/

    /28/

    DR The CPA owner represented by PT Socfin

    Indonesia has entered into a cooperation

    agreement with the coordinating entity

    represented by PT Carbon Argo Indo on 3

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    16/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-4

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    cooperation agreement with the Coordinating entity which

    includes at a minimum the matters set out in section A.4.4.1(iv)

    of the PoA-DD:

    (i) The CPA Owner is aware and voluntarily agrees thatthe CPA will be subscribed to the present PoA under

    the conditions as required by the approved PoA and the

    contractual arrangement between the CPA Owner andthe Coordinating Entity.

    (ii) Certifies the CPA has not been and will not beregistered as a single CDM project activity nor as a

    CPA under another PoA, nor any voluntary scheme and

    warrants on an ongoing basis that they will not seek to

    have the project activity which forms the basis of the

    proposed CPA registered as a CDM project or

    registered under any other scheme that earns carboncredits for the emission reductions achieved while the

    project is included in a CPA or proposed CPA under the

    present PoA.

    (iii) The CPA Owner will certify in writing that theproposed CPA is not a debundled part of a bigger

    project.

    (iv) CPA Owner cedes all rights to independently claim andown emission reductions under the Clean Development

    Mechanism of the UNFCCC or any voluntary scheme

    other than through the managing entity of the present

    PoA as agreed.

    October 2011. Significant matters presented

    in cooperation agreement are:

    (i) PT Socfin Indonesia voluntarilysubscribes to the PoA

    (ii) The CPA cannot be registered in anyother Carbon Credit Scheme

    (iii) Certification by PT Socfin Indonesiathat the CPA is not a debundledcomponent of another project

    (iv) PT Socfin Indonesia cedes all rights toindependently claim and own emission

    reductions.

    Therefore, the signed cooperation agreement

    verified demonstrates and confirms that the

    CPA complies with eligibility criterion 3

    stated in the PoA-DD.

    B.1.4 Has it been sufficiently justified that the CPAcomplies with:

    /3/

    /49/

    /50/

    DR

    I

    There is no existing co-composting or

    composting activities at the site of the

    proposed CPA. Without the proposed project,

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    17/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-5

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    No Pre-existing Co-composting or Composting at Site: Each

    CPA shall be implemented at a Palm Oil Mill site where no

    composting or co-composting activity was taking place before

    the Project Activity.

    POME is treated anaerobically in open

    lagoons and EFB is sent to the plantations for

    disposal. The site visit performed by DNV

    also reveals no evidence of existing co-

    composting or composting activities at the

    site.

    Therefore, the site visit by the validationteam was able to confirm that the CPA

    complies with eligibility criterion 3 stated in

    the PoA-DD.

    B.1.5 Has it been sufficiently justified that the CPAcomplies with:

    Technology and compliance with Methodology: Each CPA

    must be a newly developed, upgraded or expanded co-

    composting or composting facility using composting technology

    that:

    (i) Uses Palm Oil Mill Organic waste as inputs and via anaerobic composting process within the parameters set out in

    section A.4.2.1 of the PoA-DD produces organic compostfor reapplication to land as organic fertilizer

    (ii) Meets the requirements of approved methodology AMS-III.F version 10, including its relevant assessment tools andguidelines:

    1. This methodology comprises measures to avoid theemissions of methane to the atmosphere from biomass or

    other organic matter that would have otherwise been left

    to decay anaerobically in a solid waste disposal site

    (SWDS), or in an animal waste management system

    (AWMS), or in a wastewater treatment system

    /3/

    /14/

    /49/

    /50/

    DR

    I

    The CPAs compliance with technology and

    methodology is demonstrated as follows:

    (i) The CPA uses Palm Oil Mill Organicwaste as inputs and produces organiccompost via an aerobic composting

    process. The compost produces will be

    applied as organic fertilizer. Palm Oil

    Mill Organic wastes used in the CPA are

    Empty Fruit Bunches (EFB) and Palm

    Oil Mill Effluent (POME). These two

    wastes are co-composted in a process

    which will be controlled aerobically.(ii) The CPA meets the requirements of

    approved methodology AMS-III.F

    version 10, including its relevant

    assessment tools and guidelines. This is

    demonstrated as follows:

    1. The CPA aims to avoid emissions ofmethane to the atmosphere from thedecay of EFB and POME. Without

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    18/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-6

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    (WWTS). In the project activity, controlled aerobic

    treatment by composting of biomass is introduced.

    2. The project activity does not recover or combust landfillgas from the disposal site (unlike AMS-III.G Landfill

    methane recovery), and does not undertake controlled

    combustion of the waste that is not treated biologically

    in a first step (unlike AMS-III.E Avoidance of methaneproduction from decay of biomass through controlled

    combustion, gasification or mechanical/thermal

    treatment). Project activities that recover biogas from

    wastewater treatment shall use methodology AMS-III.H

    Methane recovery in wastewater treatment. Project

    activities involving co-digestion of organic matters shall

    apply methodology AMS-III.AO Methane recoverythrough controlled anaerobic digestion.

    3. Measures are limited to those that result in emissionreductions of less than or equal to 60 ktCO2 equivalent

    annually.

    4. This methodology is applicable to the composting of theorganic fraction of municipal solid waste and biomass

    waste from agricultural or agro-industrial activities

    including manure.

    5. This methodology includes construction and expansionof treatment facilities as well as activities that increase

    capacity utilization at an existing facility. For project

    activities that increase capacity utilization at existing

    facilities, project participant(s) shall demonstrate that

    special efforts are made to increase the capacity

    utilization, that the existing facility meets all applicablelaws and regulations and that the existing facility is not

    this, EFB would be left to decay

    anaerobically in a SWDS and POME

    would be left to decay anaerobically

    in a wastewater treatment system. The

    CPA introduces controlled aerobic

    treatment of EFB and POME. This is

    evidenced from the feasibility studyand has been confirmed during the site

    visit.

    2. The project activity does not involvelandfill gas recovery and combustion,

    controlled combustion of waste,

    gasification or mechanical/thermal

    treatment. AMS-III.H is not

    applicable as the project does notinvolve biogas recovery. AMS-III.AO

    is not applicable as the project does

    not involve anaerobic digestion. This

    has been confirmed from documents

    related to the project design and

    verified from interviews during the

    site visit.

    3. Emission reductions achieved by theCPA is estimated to be on average

    10 130 tCO2e annually. This is less

    than the limit of 60 ktCO2e annually.

    4. The applicability of this methodologyis confirmed as the CPA involves the

    composting of waste from agro-industrial activities. In this case, EFB

  • 7/30/2019 6511- CPA FVR_26Jun2012

    19/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-7

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    included in a separate CDM project activity. The special

    efforts should be identified and described.

    6. This methodology is also applicable for co-compostingwastewater and solid biomass waste, where wastewater

    would otherwise have been treated in an anaerobic

    wastewater treatment system without biogas recovery.

    The wastewater in the project scenario is used as asource of moisture and/or nutrients to the biological

    treatment process e.g. composting of empty fruit

    bunches (EFB), a residue from palm oil production, with

    the addition of palm oil mill effluent (POME) which is

    the wastewater co-produced from palm oil production.

    7. In case of co-composting, if it cannot be demonstratedthat the organic matter would otherwise been left to

    decay anaerobically, baseline emissions related to suchorganic matter shall be accounted for as zero, whereas

    project emissions shall be calculated according to the

    procedures presented in this methodology for all co-

    composted substrates.

    8. The location and characteristics of the disposal site ofthe biomass, animal manure and co-composting

    wastewater in the baseline condition shall be known, in

    such a way as to allow the estimation of its methane

    emissions, using the provisions of AMS-III.G, AMS-

    III.E (concerning stockpile), AMS-III.D Methane

    recovery in animal manure management systems or

    AMS-III.H respectively.

    Project activities for composting of animal manure shall

    also meet the requirements under paragraphs 1, and 2 (c)of AMS-III.D. Further no bedding material is used in the

    and POME from the palm oil mill are

    composted. This is evidenced from the

    feasibility study and confirmed during

    the site visit.

    5. The applicability of this methodologyis confirmed as the CPA involves the

    construction of new treatmentfacilities. There is no expansion or

    capacity increase involved. This has

    been confirmed during the site visit

    and supported by documents related to

    the projects design.

    6. The applicability of this methodologyis confirmed as the project involves

    co-composting of wastewater (POME)and solid biomass waste (EFB).

    POME would otherwise been treated

    anaerobically in open lagoons without

    biogas recovery as per current

    practices. This has been confirmed

    during the site visit. In the project

    scenario, POME is used as a source of

    moisture and nutrients to the

    composting of EFB. This is evidenced

    from design documents related to the

    CPA.

    7. Baseline emission from the decay ofEFB is not claimed for this CPA and

    accounted for as zero. DNV hasconducted a site visit and it was found

  • 7/30/2019 6511- CPA FVR_26Jun2012

    20/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-8

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    animal barns or intentionally added to the manure stream

    in the baseline. Blending materials may be added in the

    project scenario to increase the efficiency of the

    composting process (e.g. to achieve a desirable C/N ratio

    or free air space value), however, only monitored

    quantity of solid waste or manure or wastewater diverted

    from the baseline treatment system is used for emissionreduction calculation. The following requirement shall

    be checked ex ante at the beginning of each crediting

    period:

    a. Establish that identified landfill(s)/stockpile(s)can be expected to accommodate the waste to be

    used for the project activity for the duration of

    the crediting period; or

    b. Establish that it is common practice in the regionto dispose of the waste in solid waste disposal

    site (landfill)/stockpile(s).

    9. The project participants shall clearly define thegeographical boundary of the region referred in

    paragraph 8 (b), and document it in the CDM-PDD. In

    defining the geographical boundary of the region,

    project participants should take into account the source

    of the waste i.e. if waste is transported up to 50 km, the

    region may cover a radius of 50 km around the project

    activity. In addition, it should also consider the distance

    to which the final product after composting will be

    transported. In either case, the region should cover a

    reasonable radius around the project activity that can bejustified with reference to the project circumstances but

    that currently, EFB is dumped in the

    palm oil plantations.

    8. The location and characteristics of thedisposal site of EFB and POME have

    been defined. EFB is dumped in the

    plantations and POME is treated

    anaerobically in open lagoons. Inaddition, the following requirements

    have been established through

    observations and interviews during the

    site visit:

    a.It is reasonable to assume that thepractices of EFB dumping and

    anaerobic open lagoon POME

    treatment would continuethroughout the duration of the

    crediting period. There is ample

    space in the plantations to

    accommodate the EFB and the

    anaerobic wastewater treatment

    system has been designed to

    accommodate the requirements of

    the palm oil mill.

    b.EFB dumping in plantations and

    anaerobic treatment of POME is the

    common practice in the region of

    the proposed CPA.

    9. The geographical boundary of theregion of the proposed CPA has beenclearly defined in the CPA-DD. It is

  • 7/30/2019 6511- CPA FVR_26Jun2012

    21/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-9

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    in no case it shall be more than 200 km. Once defined,

    the region should not be changed during the crediting

    period(s).

    10.In case produced compost is handled aerobically andsubmitted to soil application, the proper conditions and

    procedures (not resulting in methane emissions) must be

    ensured.11.In case produced compost is treatedthermally/mechanically, the provisions in AMS-III.E

    related to thermal/mechanical treatment shall be applied.

    12.In case produced compost is stored under anaerobicconditions and/or delivered to a landfill, emissions from

    the residual organic content shall to be taken into

    account and calculated as per the latest version of theTool to determine methane emissions avoided fromdisposal of waste at a solid waste disposal site.

    (iii) In addition in order ensure the environmental integrity ofeach co-composting facility that is brought under this PoA

    and to ensure that the co-composting facility does not

    become a source of environmental pollution itself, each

    facility must:

    1. Locate the main composting facility upon animpermeable composting pad / floor of concrete or some

    other impermeable material (This ensures leaching from

    the compost does not take place directly into the soil

    below and improves the composting process);

    2. Incorporates a system / process to adequately deal withany run-off or leachate from the compost itself and / orensure any liquid discharge would be diluted or treated

    the 50 km radius around the proposed

    CPA location. This is justified as the

    maximum distance for transporting

    the waste utilised by the CPA is 50

    km.

    10.The produced compost will be usedfor direct application in the plantation.Therefore, aerobic handling of

    produced compost has been ensured.

    11.The provisions in AMS-III.E relatedto thermal/mechanical treatment are

    not applied. This is because the

    produced compost is not treated

    thermally or mechanically.

    12.The produced compost will not bestored anaerobic conditions or

    delivered to a landfill. According to

    project documents, the produced

    compost will be directly applied to

    landfill. This has been supported by

    interviews with the project participant.

    Therefore emissions from the residual

    organic content are not taken into

    account and calculated and this is

    considered acceptable.

    (iii) The environmental integrity of the CPAhas been ensured as follows:

    1. The main composting facility willinstall a concrete floor to prevent soilcontamination of leachate. This has

  • 7/30/2019 6511- CPA FVR_26Jun2012

    22/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-10

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    to environmentally acceptable levels before entering the

    surrounding environment.

    been confirmed during the site visit.

    2. The composting process involves norun-off leachate leaking to the

    surrounding environment. Excess

    POME or liquid from the composting

    process is stored in a buffer tank and

    recycled back to the compostingprocess. The composting process is

    isolated from rainwater as a roof is

    constructed for this purpose. This is

    evident from the projects design and

    confirmed during the site visit.

    Therefore, the validation team was able toconfirm that the CPA complies with

    eligibility criterion 5 stated in the PoA-DD.

    B.1.6 Has it been sufficiently justified that the CPAcomplies with:

    Start date: Each CPA Owner must be able to provide

    documentary evidence to verify the start date of the CPA.

    /3/

    /23/

    /24/

    /25/

    DR It has been verified that documentaryevidences have been provided. This allows

    the CME to verify the start date of the CPA.

    The start date of the CPA is evidenced by the

    contracts signed with respect to the project

    activity, specifically piling works, concrete,

    steel and roof works and precast concretepanel, where these contracts are all signed on

    the same date and its the earliest of all

    financial commitment.

    Therefore, the validation team was able to

    confirm that the CPA complies with

    eligibility criterion 6 stated in the PoA-DD.

    OK

    B.1.7 Has it been sufficiently justified that the CPA /1/ DR It has been demonstrated that the CPA (c.f. OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    23/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-11

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    complies with:

    Additionality: Each CPA must be able to demonstrate that the

    Project Activity which forms the CPA would not have occurred

    anyway due to an investment barrier by following and applying

    all steps of the additionally assessment as set out in sections

    E.5.1 and E.5.2 of the PoA-DD.

    /3/

    /4/

    /10/

    /11/

    /14/

    /15/

    /23//24/

    /25/

    /34/

    Section B.2 of the CPA protocol) would not

    have occurred due to financial barrier. All

    steps of the additionality assessment set out

    in sections E.5.1 and E.5.2 of the PoA-DD

    have been followed.

    Therefore, the validation team was able to

    confirm that the CPA complies witheligibility criterion 7 stated in the PoA-DD.

    B.1.8 Has it been sufficiently justified that the CPAcomplies with:

    PoA Specific Requirements:

    (i) Environmental Impact Analysis (EIA): Each CPAwhich involves the implementation of a Compost Facility

    with a compost output capacity:

    a. Greater than or equal to 100 tons per day shallprovide a copy of their EIA which has been

    submitted to, and approved by the IndonesianMinistry of the Environment.

    b. Less than 100 tons per day, shall provide a copy ofthe Environmental Management and MonitoringPlan (EMMP) that was submitted and approved by

    the responsible Indonesian authorities.

    (ii) Compliance with Relevant National Standards: EachCPA Project Activity must comply with the relevant

    Indonesian National or Regional Environmental Standard.

    (iii) Stakeholder Consultation: Each CPA must be able todemonstrate with appropriate documentary evidence that

    /3/

    /6/

    /18/

    /45/

    DR (i) It has been sufficiently justified that theCPA complies with the Environmental

    Impact Analysis (EIA) requirements of

    the PoA-DD and the host party of

    Indonesia. Since the output capacity of

    the project is 23 tons per day, the CPAhas provided its approved

    Environmental Management and

    Monitoring Plan (EMMP).

    Therefore, it is confirmed that the CPA

    meets the criteria for environmental

    impact analysis (EIA) defined in thePoA.

    (ii) The CPAs compliance with national orregional environmental standard is

    evidenced from the EMMP.

    Environmental requirements from the

    Indonesian Ministry of Environment

    have also been reviewed.

    Therefore, it is confirmed that the CPA

  • 7/30/2019 6511- CPA FVR_26Jun2012

    24/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-12

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    Stakeholder Consultation has been undertaken in

    accordance with the requirements of CDM rules and

    procedures.

    meets the criteria for compliance with

    relevant national standards defined in

    the PoA.

    The CPA has provided documentary

    evidence to support that the stakeholder

    consultation has been undertaken. It

    allows the CME to determine that it isdone in accordance with the

    requirements of CDM rules and

    procedures.

    Therefore, it is confirmed that the CPA

    meets the criteria for stakeholder

    consultation defined in the PoA.

    Therefore, the validation team was able to

    confirm that the CPA complies with

    eligibility criterion 8 stated in the PoA-DD.

    B.1.9 Has it been sufficiently justified that the CPAcomplies with:

    Debundling: To ensure a CPA is not a debundled component ofa large scale activity, the Project Activity under each CPA must

    not have the same activity implementer as the proposed smallscale CPA or a coordinating or managing entity, which also

    manages a large scale PoA of the same technology/measure

    which is within 1 km of the boundary of the proposed small-

    scale CPA, at the closest point.

    /3/

    /37/

    /49/

    /50/

    DR

    I

    The CPA is not a debundled component of

    another project activity. It has been

    confirmed through site visit that there is no

    other project activity within 1 km of the

    boundary of the proposed CPA at the closest

    point.Therefore, the validation team was able to

    confirm that the CPA complies with

    eligibility criterion 9 stated in the PoA-DD.

    OK

    B.1.10 Has it been sufficiently justified that the CPAcomplies with:

    SSC Threshold Criteria: Each CPA shall not reduce more than

    /3/

    /4/

    /5/

    DR The CPA is estimated to reduce 10 130

    tCO2e on average yearly. This is less than the

    limit of 60 ktCO2e annually.

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    25/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-13

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    60 ktCO2e annually. Therefore, the validation team was able to

    confirm that the CPA complies with

    eligibility criterion 10 stated in the PoA-DD.

    B.1.11 Has it been sufficiently justified that the CPAcomplies with:

    Use of Development or Assistance Funds: Each CPA mustcertify in writing whether any Development Aid or Assistance

    funds have been used for funding the construction and operation

    of the Project Activity which forms the PoA. If any

    Development Aid or Assistance funds have been used, then

    before inclusion in the PoA, the CPA owner must provide

    evidence to confirm that such funds do not result in a diversion

    of any official development assistance funds.

    /3/

    /15/

    /49/

    /50/

    DR

    I

    Interviews conducted during the site visit

    also revealed that the CPA does not use anyDevelopment Aid or Assistance funds for its

    construction or operation. Confirmation ofsuch was received from the project owner,

    PT Socfindo in a form of a declaration.

    Therefore, the validation team was able to

    confirm that the CPA complies with

    eligibility criterion 11 stated in the PoA-DD.

    OK

    B.2. AdditionalityAdditionality of a CPA is assessed through eligibility criteria 7

    above.

    B.2.1 Is it demonstrated that the IRR of the CPA islower than 12.5% (before tax)?

    /1/

    /3/

    /4/

    /10/

    /11//12//14/

    /15/

    /16/

    /17/

    /23/

    /24/

    /25/

    DR To demonstrate the additionality, the CPA

    uses an investment analysis. It has been

    shown below that the project is not

    financially attractive. Hence, it has been

    justified that the CPA complies withadditionality criteria 1.

    Choice of approach:As the proposed CPA generates benefits

    through savings from reduced fertilizer

    imports, and the alternative to the project

    (baseline scenario) does not involve

    investments, benchmark analysis was chosen

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    26/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-14

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    /30/

    /31/

    /34/

    /48/

    as an appropriate analysis method. Financial

    attractiveness of the project without CER

    revenues has been demonstrated. It is

    confirmed that this choice of approach is

    consistent with the requirements of section

    E.5.2 of the PoA-DD.

    Input parameters:

    Key parameters applied in the projects

    financial analysis are listed as per the PoA-

    DD section E.5.2. They are assessed as

    follows:

    Technical lifetime of 20 years: This wascrosschecked against the technical

    providers estimation included in the

    Feasibility Study Report. Therefore, this

    is considered to be in line with the

    requirements of the PoA-DD.

    Investment decision date of 28 April2010: This is evidenced through minutes

    of meeting of the board of the

    commissioners of the P.T. Socfin

    Indonesia (Socfindo) held in Jakarta on

    the same date. Therefore the investment

    decision date of 28 April 2010 is accepted

    and this is consistent with the

    requirements of the PoA-DD.

    Date project starts operating of 8 March2012: This was crosschecked against the

    technical providers estimation.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    27/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-15

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    Therefore, this is considered to be in line

    with the requirements of the PoA-DD.

    Annual compost production of 30 000tons: This is sourced from the technology

    provider as evidenced in the feasibility

    study. Therefore, this is considered to be

    in line with the requirements of the PoA-DD.

    The price of compost is not specified inthe CPA-DD: Compost produced by the

    CPA will be used internally and is not

    aimed to be sold to a third party.

    Therefore, this exclusion is considered

    acceptable and in line with the

    requirements of the PoA-DD.

    Estimated fertilizer savings of 2 256.36million IDR per year: The compost

    produced will be applied to plantation

    and this will result in cost savings due to

    reduced usage of fertilizer. Specific

    information was available from externally

    published sources in relation to thepercentage of fertilizer savings that would

    be able to be achieved using that compost

    technology in that region, thus it is

    justified that Option A template was used

    to calculate the estimated fertilizer

    savings. The price of inorganic fertilizer

    is obtained from the average purchase

    price of Dolomite, Rock Phosphate, Urea

  • 7/30/2019 6511- CPA FVR_26Jun2012

    28/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-16

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    and Potassium for the year of 2009.

    Purchase contracts have been reviewed

    and it was found that the value used in the

    template is consistent with the purchase

    price in year 2009. The fertilizer dosage

    amount is obtained from the historical

    records for fertilizer usage in the year2009. Similarly, these records have been

    reviewed and it was found that the

    amount selected is consistent with the

    original source.

    By participating in the programme, it is

    estimated that this will result in a 35%

    reduction of inorganic fertilizer use due

    to the assumption that 1.5 tons ofcompost is produced from each ton of

    EFB used. It is noted that this is of the

    higher range as compared to figures

    published in academic papers and also

    used in other registered co-composting

    CDM projects, which assumes a compost

    production of 0.35 to 0.6 tons per ton of

    EFB. In addition, this is evidenced by the

    feasibility study. Therefore, this is

    considered conservative and acceptable.

    The assumption used in the financial

    analysis to be in line with the

    requirements of the PoA-DD.

    Currency of 1 USD = 9 013 IDR and 1Euro = 12 049 IDR: Currency rates are

  • 7/30/2019 6511- CPA FVR_26Jun2012

    29/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-17

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    taken from the middle rate dated 27 April

    2010 from the Bank Indonesia currency

    rate calculator. This is inconsistent with

    the requirements of the PoA-DD which

    requires an average exchange rate during

    the twelve months preceding the date of

    the investment decision date. Capital and equipment cost of 14 281

    million IDR: This is sourced from the

    feasibility study. It is considered that the

    feasibility study represents costs

    estimated from technology providers.

    This cost has been cross-checked with

    publicly available information from a

    paper presented during the 2010

    International Conference & Exhibition on

    Oil Palm Biomass and an article

    published in a local newspaper. From

    these two sources, the price of an aerobic

    bunker composting system is reported to

    be 2.00 million USD to 2.31 million USD

    (18.7 billion IDR to 21.6 billion IDR).Capital and equipment cost of 14 281

    million IDR used in the investment

    analysis is lower than the costs published.

    Therefore, this is considered to be

    conservative. The bulk of the initial

    capital cost is for the bunker system

    which is where co-composting takes

    place. For this item, 9.104 million IDR is

  • 7/30/2019 6511- CPA FVR_26Jun2012

    30/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-18

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    allocated and this is equivalent to 63.75%

    of the total investment cost. In addition,

    signed contracts have been reviewed and

    it was found that a total of 4 127 million

    IDR (tax inclusive) of investment

    expenditure has been committed against

    an estimated 7 251 million IDR for thebunker building. These signed contracts

    cover piling works, concrete steel roof

    works and precast concrete panel for the

    bunker building.

    At the time of site visit, the bunker

    building is still under construction and

    more expenditure is expected towards the

    bunker building. In conclusion, DNVconsiders the investment cost of 14 281

    million IDR as per the feasibility study to

    be acceptable and this cost has been

    cross-checked with independent sources.

    CER revenue of 3 510.25 million IDR peryear: This is sourced from the feasibility

    study which is considered to be consistentwith the board or management estimation

    of the CER price. The amount of revenue

    from CER sales is accepted as it is in

    accordance with the requirements of the

    PoA-DD.

    Operation and maintenance cost of 1864.68 million IDR: O&M cost for theproposed CPA comprises of fuel and

  • 7/30/2019 6511- CPA FVR_26Jun2012

    31/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-19

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    electricity costs (410.26 million IDR),

    labour costs (420.80 million IDR) and

    maintenance costs (1 033.62 million

    IDR). These costs are assessed separately.

    The bulk of the O&M cost is incurred for

    the operation and maintenance of the

    bunker system. This is where emissionreduction through aerated co-composting

    takes place. As part of the normal

    operation of the bunker system, waste

    materials fed are required to be pre-

    processed and the bunker is continuously

    aerated using fans. Materials composting

    in the bunker are continuously monitored

    for their temperature and oxygen level.From time to time, maintenance is

    incurred in order to clean the composting

    area, to maintain the control system and

    to service the aeration fans. DNV has also

    verified that the O&M cost applied in the

    financial analysis are sourced from the

    feasibility study. Therefore, this is

    considered to be reasonable.

    Fuel and electricity cost of 410.26 millionIDR: Fuel cost is sourced from historical

    company purchase records, while the

    estimation of fuel usage is sourced from

    the feasibility study and information from

    the technology provider. Under the

    project activity, additional fuel is required

  • 7/30/2019 6511- CPA FVR_26Jun2012

    32/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-20

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    for the operation of the spreader machine,

    tractor, wheel loader and truck. The

    additional amount of diesel consumed by

    the project activity is 29 522.39 litres.

    Additional diesel is used for the operation

    of the spreader machine, tractor, wheel

    loader and trucks. DNV has cross-checked this amount with the feasibility

    study and confirmed that this is sourced

    from the equipment

    manufacturer/technology provider. DNV

    has reviewed the historical diesel

    purchase records and found that average

    diesel prices paid for the months of

    January 2010 to March 2010 is IDR 5764 per litre. The months of January 2010

    to March 2010 were selected as these

    were the months of the feasibility study

    period. Diesel price used in the financial

    analysis is IDR 4 500 per litre. The diesel

    price used in the financial analysis is

    lower than the actual price paid as per the

    historical company purchase records

    (between IDR 5 533 to IDR 6 006 at the

    time when the FSR was finalised in April

    2010). This is considered to be

    conservative.

    The project assumes no additional

    electricity cost will be incurred for theCPA. Equipment and facilities related to

  • 7/30/2019 6511- CPA FVR_26Jun2012

    33/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-21

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    the CPA use electricity generated from

    the mill adjacent to the composting plant.

    Due to this, DNV considers the exclusion

    of electricity cost from the investment

    analysis to be acceptable and

    conservative.

    Labour cost of 420.80 million IDR: Theamount of labour is sourced from thetechnology provider. The labour rate is

    based on the internal labour rate of PT

    Socfin. DNV considers that the CPA

    requires additional amount of labour

    since the project activity requires

    additional material handling. In addition,

    the co-composting system is operating

    continuously and therefore requires

    continuous supervision and manpower.

    DNV considers the technology provider

    recommendation that 12 additional

    manpower required for continuous day to

    day operation of the composting plant to

    be reasonable. DNV has also reviewedthe actual historical labour rates of PT

    Socfin which were available at the time

    of decision making. It was checked that

    the internal labour rates of PT Socfin

    were between 28 million to 147 million

    IDR while labour rates applied in the

    financial analysis are between the range

    of 24 million IDR and 80 million IDR.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    34/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-22

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    This is lower than the actual labour rates

    of the CPA which is reasonable

    considering the additional manpower for

    the composting plant could be met by

    lower skilled workers. Hence, DNV has

    accepted the labour cost applied in the

    financial analysis. Maintenance cost of 1 033.62 million

    IDR: This is obtained from information

    provided by the technology provider. In

    addition, the maintenance cost is

    supported by the feasibility study

    prepared for the project activity.

    Therefore, the maintenance cost is

    deemed acceptable.

    Land rental cost. This is not applicable asthe project activity takes place in the

    premises of the CPA project proponent.

    Rental of land from third parties is not

    applicable.

    Licensing and royalty cost: As PT Socfinis the owner of the composting plant a ndthe palm oil mill. there is no royalty or

    licensing costs imposed on the CPA

    owner (PT Socfin) as confirmed during

    the site visit. This cost is taken as zero in

    the financial analysis and this is

    considered conservative.

    Insurance: Expenses related to insuranceare taken as zero in the financial analysis.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    35/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-23

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    This is considered to be reasonable and

    conservative.

    Feedstock costs: Expenses related to thecosts for raw material feedstock inputs

    into the compost facility are taken as zero

    in the financial analysis. This is

    considered to be reasonable andconservative.

    Calculation and conclusion:Pre-tax project IRR calculations over 20

    years of operation period were provided in a

    spread sheet. The IRR without CDM

    revenues were calculated as -5.14%. With

    CDM benefits, the IRR of the project

    increases to 21.96%.

    Sensitivity Analysis:

    This analysis has been carried out for

    parameters contributing more than 20% to

    revenues or cost to check on the robustness

    of the financial analysis. -10% to 10%variations were made to the project revenue,

    project investment and O&M cost. It was

    shown and calculated in the financial analysis

    spread sheet that none of the variations on the

    3 parameters result in the IRR exceeding the

    benchmark.

    In addition, the following variations are

  • 7/30/2019 6511- CPA FVR_26Jun2012

    36/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-24

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    needed for reaching the benchmark:

    i) Project revenue: The IRR of the projectactivity will reach the benchmark if

    project revenue is increased by 70%.

    Revenue delivered by the project is in the

    form of cost savings and this is dependenton the amount of fertilizer savings and

    fertilizer cost. Based on this, the

    maximum amount of revenue delivered

    by the project is limited by the fertilizer

    costs that would be incurred in the

    absence of the project activity. It is

    assessed that apart from CDM, the project

    does not introduce new revenue streamsor causes an increase in existing revenue

    streams (e.g. increased palm oil

    production). Therefore, i t is assessed that

    an increase of the project revenue of 70%

    is deemed to be unlikely.

    ii) Project investment: The IRR of theproject activity will reach the benchmark

    if the project investment cost is reduced

    by 80%. At the time of validation, the

    project proponent has already committed

    to expenditures related to the project

    activity. Signed contracts have been

    reviewed and it was found that a total of 4

    127 million IDR (tax inclusive) ofinvestment expenditure has been

  • 7/30/2019 6511- CPA FVR_26Jun2012

    37/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-25

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    committed. This represents 29% of the

    estimated project investment cost of 14

    281 million IDR. From this, it is

    concluded that a reduction of project

    investment cost of 80% is not achievable.

    iii)O&M cost: The IRR of the projectactivity will reach the benchmark ifO&M costs are reduced by 85%. It has

    been assessed that these costs are

    estimated conservatively and supported

    by external evidences. Annual O&M cost

    is calculated to be about 13% of total

    investment cost. This has been compared

    with other registered CDM projects

    involving co-composting of EFB andPOME in the host country of Indonesia

    (Project 444516%, Project 406426%

    and Project 371721%). Due to this, it is

    concluded that a reduction of O&M cost

    by 85% is unlikely.

    In conclusion, given the above investment

    barrier, it is sufficiently demonstrated that the

    project is not a likely baseline scenario and

    that emission reductions thus are additional

    to what would otherwise have occurred.

    B.3. Calculation of GHG Emission ReductionsProject emissions

    It is assessed whether the project emissions are stated according

    to the methodology and the PoA-DD and whether the

  • 7/30/2019 6511- CPA FVR_26Jun2012

    38/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-26

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    argumentation for the choice of default factors and values -

    where applicableis justified.

    B.3.1 Is the calculation of project emissions of the CPAin accordance with the procedure described in the

    PoA-DD?

    /1/

    /3/

    /5/

    /14/

    /46//49//50/

    DR

    IThe calculation of project emissions in the

    CPA has been checked and it is in

    accordance with the procedure described in

    the PoA-DD.

    The PoA-DD lists project emissions of theCPA as follows:

    a. CO2 emissions due to incrementaltransportation distances;

    b. CO2 emissions from electricity and/orfossil fuel consumption by the project

    activity facilities;

    c. Methane emissions during compostingprocess;

    d. Methane emissions from runoff water;e. In case the compost is stored under

    anaerobic conditions and/or delivered to

    a landfill: the methane emissions from

    the disposal/storage of compost.

    CO2 emissions due to incremental

    transportation distances:

    The calculation of this source of emission is

    done as per the procedures specified in the

    PoA-DD. It has been confirmed through site

    visit the co-composting facility is located inthe boundary of the project activity. As a

    result of this, incremental transportation for

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    39/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-27

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    POME and EFB is not anticipated. Therefore,

    this source of emission is disregarded.

    CO2 emissions from electricity and/or

    fossil fuel consumption by the project

    activity facilities:

    Project emission due to final composttransportation is estimated to be 248.04

    tCO2e per year. This is based on the

    anticipated diesel oil consumption of

    76 582.36 kg per year which is based on

    internal estimations and supported by the

    feasibility analysis. The NCV of diesel oil of

    43.3 TJ/kg and the CO2 emission factor of

    diesel oil of 74 800 kg/TJ. These values areapplied from the upper default values of the

    2006 IPCC Guidelines for National

    Greenhouse Gas Inventories. The density of

    diesel oil of 0.84 kg/litre was soruced from

    PERTAMINA (national oil supplier,

    http://www.pertamina.com/index.php/detail/r

    ead/minyak-diesel)

    This is calculated as per option B specified in

    the procedures specified in the PoA-DD. It

    has been checked that the same equation,

    assumptions and input parameters were used

    in the CPA-DD. The selection of option B to

    calculate this emission is considered

    acceptable as the chemical composition ofdiesel oil is not available at the time of

    http://www.pertamina.com/index.php/detail/read/minyak-dieselhttp://www.pertamina.com/index.php/detail/read/minyak-dieselhttp://www.pertamina.com/index.php/detail/read/minyak-dieselhttp://www.pertamina.com/index.php/detail/read/minyak-dieselhttp://www.pertamina.com/index.php/detail/read/minyak-diesel
  • 7/30/2019 6511- CPA FVR_26Jun2012

    40/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-28

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    validation.

    Methane emissions during composting

    process:This emission is considered to be zero. This

    is considered acceptable as the temperature

    and oxygen content of the compostingprocess are monitored. This assumption is in

    line with the specifications of the PoA-DD

    and the methodology AMS-III.F version 10.

    Methane emissions from runoff water:

    There is no run-off water from the project

    activity and this is evidenced from theprojects design. Unutilized POME will bere-applied to the co-composting process and

    the co-composting area is roofed to isolate

    rainwater. Therefore, this emission is

    considered to be zero and this is acceptable.

    Methane emissions from the

    disposal/storage of compost:

    It has been confirmed during the site visit

    that the final compost from the project

    activity will be directly applied in the

    plantation. It does not involve anaerobic

    storage of compost or landfill disposal.

    Therefore, this source of emission is taken tobe zero and this is consistent with the

    specifications of the PoA-DD.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    41/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-29

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    B.3.2 Are CPA-specific conservative assumptions usedwhen calculating the project emissions?

    /3/ DR CPA-specific conservative assumptions are

    used when calculating the project emissions.

    OK

    B.3.3 Are CPA-specific uncertainties in the projectemission estimates properly addressed?

    /3/ DR There are no CPA-specific uncertainties in

    the project emissions calculation.

    OK

    B.4. Calculation of GHG Emission ReductionsBaseline emissions

    It is assessed whether the baseline emissions are stated

    according to the methodology and the PoA-DD and whether the

    argumentation for the choice of default factors and valueswhere applicableis justified.

    B.4.1 Is the calculation of baseline emissions of theCPA in accordance with the procedure described

    in the PoA-DD?

    /1/

    /3/

    /5/

    /21/

    /22/

    /27//42/

    /49/

    /50/

    DR

    I

    CC

    The calculation of baseline emissions in the

    CPA has been checked and it is in

    accordance with the procedure described in

    the PoA-DD.

    The PoA-DD lists project emissions of the

    CPA as follows:

    a. Baseline emission due to methanegeneration potential of the solid waste

    composted

    b. Baseline emission due to methaneemission from baseline wastewatertreatment system

    c. Baseline emission due to methaneemissions on account of inefficiencies inthe baseline wastewater treatment

    systems and presence of degradableorganic carbon in the treated wastewater

    discharged into river/lake/sea

    d. The amount of methane that would have

    OK

  • 7/30/2019 6511- CPA FVR_26Jun2012

    42/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-30

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    to be captured and combusted in the year

    to comply with the prevailing regulations

    Baseline emission due to methane

    generation potential of the solid waste

    composted:

    This source of emission is regarded as zero.According to the baseline practice as

    observed during the site visit, EFB from the

    palm oil mill is disposed in the plantations. Itwas confirmed during the site visit that the

    EFB dump site is located in plantation lands

    and in patches of not more than 2 meters

    high and 5 meters wide. Therefore, anaerobic

    decomposition of EFB cannot be ascertained

    to the MCF values prescribed by Tool to

    determine methane emissions avoided from

    disposal of waste at a solid waste disposal

    site referred by the methodology in the

    calculation of BECH4,SWDS,y.

    Therefore, the baseline emission from the

    current dumping situation of the EFB istaken as zero, and is consistent with

    paragraph 7 of AMS-III.F. This is considered

    to be acceptable and conservative.

    Baseline emission due to methane

    emission from baseline wastewater

    treatment system:The baseline emissions are estimated form

  • 7/30/2019 6511- CPA FVR_26Jun2012

    43/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-31

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    the influent flow rate and the COD value of

    POME applied to the co-composting process.

    The wastewater flow is estimated from the

    average POME generated by the mill for the

    past three years (2008 to 2010), which is 47

    612.39 m3 per year. This has been verified

    from the historical data of the mill.

    The COD value of the POME is estimated

    through a 10-day measurement campaign

    done during 11 to 23 August 2011. DNV has

    cross-checked the results of the measurement

    campaign with original wastewater test

    certificates issued by an independent

    laboratory. In addition, historical data hasalso been checked to ensure that the

    measurement campaign is conducted during

    typical operation conditions. It is noted that a

    complete set of 1 year data as required by

    paragraph 26 of AMS-III.H version 16 is not

    available as the COD records of the

    untreated POME were not available. The

    monitoring of untreated POME is not part of

    the normal operation of the mill as

    confirmed during the site visit.

    In accordance with the methodology,

    average value from the measurement

    campaign has been used and the result has

    been multiplied by 0.89 to account for theuncertainty range. Hence, baseline emission

  • 7/30/2019 6511- CPA FVR_26Jun2012

    44/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-32

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    from anaerobic lagoons has been calculated

    in accordance to paragraph 27 of AMS-III.H

    version 16. The COD value of the POME is

    taken to be 58.5 kgCOD/m3.

    The COD removal efficiency of the baseline

    treatment is calculated using a final CODdischarge value of 0.197 kgCOD/m3. This is

    determined from past 3 years monthly

    records of the COD of the final discharge to

    water body. The COD removal efficiency

    calculation has been checked and it is

    correctly calculated at 99.7%.

    The methane correction factor (MCF) for thebaseline wastewater treatment system is 0.8

    and this is correctly applied. It was

    confirmed during the site visit that the

    baseline wastewater treatment system

    involves anaerobic deep lagoons. Lagoon

    depth confirmed during the site visit and via

    engineering drawings of the lagoons was 5

    meters and this is more than the limit of 2

    meters. Therefore, the MCF value applied is

    consistent with the default value listed in

    AMS-III.H.

    The methane producing capacity of the

    wastewater (Bo,ww) and the global warmingpotential of methane (GWPCH4) are correctly

  • 7/30/2019 6511- CPA FVR_26Jun2012

    45/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-33

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    taken as 0.25 kgCH4/kgCOD and 21

    respectively. These values are appropriately

    sourced from the default values listed in

    AMS-III.H.

    The baseline emissions will be calculated

    based on the actual amount of methanerecovered. For ex-ante estimation purposes,

    the estimated baseline emission calculated is

    10 378.58 tCO2e annually.

    Baseline emission due to methane

    emissions on account of inefficiencies in

    the baseline wastewater treatment systems

    and presence of degradable organic

    carbon in the treated wastewater

    discharged into river/lake/sea:This emission is estimated from the amount

    of wastewater discharged to water body in

    the baseline and the COD of the wastewater

    discharged. The wastewater flow is

    estimated from the average POME generated

    by the mill for the past three years (2008 to

    2010), which is 47 612.39 m3 per year. This

    has been verified against the historical data

    of the mill. The final COD discharge value is

    taken as 0.197 kgCOD/m3 and this is

    determined from past 3 years monthly

    records of the COD of the final discharge towater body.

  • 7/30/2019 6511- CPA FVR_26Jun2012

    46/58

    DET NORSKE VERITAS

    Protocol for assessing compliance of specific CPA with the PoADNV Report No. 2011-9535/01, rev. 01 A-34

    CHECKLIST QUESTION Ref. MoV* COMMENTSDraft

    Concl.

    Final

    Concl.

    The methane correction factor (MCF) for the

    discharge pathway of the wastewater

    treatment system is 0.1 and this is correctly

    applied. It was confirmed during the site visit

    that the treated wastewater of the baseline

    wastewater treatment system is discharged tothe water body. Therefore, the MCF value

    applied is consistent with the default value

    listed in AMS-III.H.

    Similarly, the methane producing capacity of

    the wastewater (Bo,ww) and the global

    warming potential of methane (GWPCH4) are

    correctly taken as 0.25 kgCH4/kgCOD and21 respectively. These values are

    appropriately sourced from the default values

    listed in AMS-III.H.

    The baseline emissions will be calculated

    based on the actual amount of wastewater

    discharged. Forex-ante estimation purposes,

    the estimated baseline emission calculated is

    4.38 tCO2e annually.

    The amount of methane that would have

    to be captured and combusted in the year

    to comply with the prevailing regulations:

    This emission is taken to be zero as there are

    no prevailing regulations mandating the

  • 7/30/2019 6511- CPA FVR_26Jun2012

    47/58

    DET NORS