Upload
madeline-boone
View
42
Download
7
Tags:
Embed Size (px)
DESCRIPTION
6 th Zimbabwe Mining and Infrastructure Indaba 8-10 October 2014 Harare, Zimbabwe. Content of Presentation. Ministerial Powers Energy Policy Implementing the plan Eskom Africa Strategy Opportunities for Zimbabwe. The Powers of the Minister of Energy. - PowerPoint PPT Presentation
Citation preview
6th Zimbabwe Mining and Infrastructure Indaba
8-10 October 2014Harare, Zimbabwe
Xxxxx-xx/Footer2
Ministerial Powers
Energy Policy
Implementing the plan
Eskom Africa Strategy
Opportunities for Zimbabwe
Content of Presentation
Xxxxx-xx/Footer3
Total responsibility for the energy industry
Policy development
Plan for new capacity
Decide who to build new capacity
Procure new capacity
The Powers of the Minister of Energy
Xxxxx-xx/Footer4
Ensure energy security of supply through:
Introducing Independent Power Producers
Cleaner technologies
Least cost technologies
Support regional integration and development
Key policy considerations
Xxxxx-xx/Footer5
IRP Revised Balance Scenario
Xxxxx-xx/Footer6
INTEGRATED RESOURCE PLAN IMPLEMENTATION
New build optionsCoal
(PF, FBC, imports, own
build)
Nuclear Import hydro Gas – CCGT Peak – OCGT Wind CSP Solar PV
MW MW MW MW MW MW MW MW2010 0 0 0 0 0 0 0 0
2011 0 0 0 0 0 0 0 0
2012 0 0 0 0 0 0 0 300
2013 0 0 0 0 0 0 0 300
2014 5001 0 0 0 0 400 0 300
2015 5001 0 0 0 0 400 0 300
2016 0 0 0 0 0 400 100 300
2017 0 0 0 0 0 400 100 300
2018 0 0 0 0 0 4004 1004 3004
2019 250 0 0 2373 0 4004 1004 3004
2020 250 0 0 2373 0 400 100 300
2021 250 0 0 2373 0 400 100 300
2022 250 0 1 1432 0 805 400 100 300
2023 250 1 600 1 1832 0 805 400 100 300
2024 250 1 600 2832 0 0 800 100 300
2025 250 1 600 0 0 805 1 600 100 1 000
2026 1 000 1 600 0 0 0 400 0 500
2027 250 0 0 0 0 1 600 0 500
2028 1 000 1 600 0 474 690 0 0 500
2029 250 1 600 0 237 805 0 0 1 000
2030 1 000 0 0 948 0 0 0 1 000
Total 6 250 9 600 2 609 2 370 3 910 8 400 1 000 8 400
First Determination
Second Determination
1. Built, owned & operated by IPPs 2. Commitment necessary due to required high-voltage infrastructure, which has long lead time 3. Commitment necessary due to required gas infrastructure, which has long lead time 4. Possibly required grid upgrade
has long lead time and thus makes commitment to power capacity necessary
Xxxxx-xx/Footer7
First Determination
1st Determination – 3724 MW of renewable energy of which over 2400 has be procured
The department and Eskom signed contracts with 47 preferred bidders
Some projects under window 1 are already supplying power into the grid whilst majority are due for connection in 2014
Most window 2 project are under construction and are due for connection into the grid in 2016 - 2017
MW to be procured
Xxxxx-xx/Footer8
Second Determination
Determination – 3200 MW of renewable energy Added to the current Renewable Procurement Programme
Determination – Base load/ mid-merit - 2500 MW of coal based load/ import hydro - 2652 MW of gas fired plant mead married Separate procurement documents being developed
19 December 2012 Determinations
Determination – Medium Term Risk Mitigation - 800 MW from cogeneration - 475 MW from gas of coal base load Separate procurement documents developed
Xxxxx-xx/Footer9
Eskom’s Africa Strategy
To increase imports through supporting the RSA Department of Energy
Support the development of strategic transmission corridor and generation projects
To be involved in Operations and Maintenance (O&M)
In future to export surplus power
11
22
33
44
Xxxxx-xx/Footer10
• Zambia • Botswana• Mozambique• RSA• Namibia
Opportunity for Zimbabwe
To develop interconnectors with:
To participate in future Procurement Programmes
11
22
Xxxxx-xx/Footer11
Thank You