20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
Kiosk building - Setting out works for 500 mm dia CFA piles.
Kiosk building. - Concrete Temperature Test (SRC M30) for 500mm dia CFA Piles
20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
Kiosk building. - Slump Test ( SRC M30) for for 500mm dia CFA Piles.
Kiosk building. -Concrete Cube Test (SRC M30) for for 500mm dia CFA Piles
20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
Kiosk building. -SRC M30 Poured into Concrete Pump.
Kiosk building -Boring of 500mm dia CFA Piles @ 1m Below Ground Level
20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
upto Pile Head level.
at 13m Below Ground Level.Kiosk building -Termination Depth of 500 mm dia Bored CFA Piles
Kiosk building -Installation of Epoxy coated rebar Cages for 500 mm dia CFA piles
20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
Expansion-1- Pile Static load Test for CFA Pile No- P230 in School building
20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
level to receive Pile Caps in exp-1.
Pile Foundation - Earthwork excavation to receive Pile Caps in exp-1.
Pile Foundation -Trimming of CFA pile head upto Pile cut off
20 Classrooms Boys School (5-10) at Sur Hilal ,Wilayat Al-Suwaiq in Batinah North Governorate
level to receive Pile Caps in exp-2.
load test in Pile No- 206 in expansion- 3
Pile Foundation - Earthwork excavation& Trimming of Concrete upto Pile cut off
School Building - Preparation of Pile head level to required height for Static