17
International Journal of Science & Technology Volume 3, No 2, 173-189, 2008 Influences on Selection of the Type of Dam M. Emin EMIROGLU Firat University, Faculty of Engineering, Civil Eng. Dept. Elazig, TURKIYE (Received: 07.05.2007 ; Accepted: 28.07.2008) Abstract: Heuristics and empirical knowledge from experts are vital parts of any water resources planning process. The selection of the type of dam requires a significant amount of empirical input from experts and specialists in the form of heuristic rules, expert opinions and inferences, and rules of thumb. Only very small percentage of such knowledge is well documented in the literature. It is also difficult to obtain all of the relevant knowledge related to the selection of the type of dam at the same time. The objective of this study is to discuss the factors influencing the selection of the type of dam by giving examples from rules of thumb and also to present typical cross sections for types of dams to be constructed on different foundations. Baraj Tip Seçimine Tesir Eden Faktörler Özet: Uzmanlardan edinilen meslek kuralları ve tecrübeye dayalı bilgiler, su kaynakları planlama sürecinde hayati önem taşımaktadır. Baraj tip seçiminde uzmanlardan alınan tecrübelerle edinilmiş bilgiler, uzman fikirleri ve meslek kuralları oldukça önemlidir. Bu tür tecrübeye dayalı bilgilerin çok az bir kısmı literature geçmiştir. Baraj tipi seçimine karar verirken her zaman tecrübeli mühendislerle çalışmak veya onlara her zaman ulaşmak mümkün olmamaktadır. Bu çalışmanın amacı baraj tip seçimiyle ilgili tecrübelere dayalı çok değerli meslek kurallarını literatüre aktarmak ve farklı baraj temelleri üzerine hangi baraj tip enkesitlerinin seçilebileceğini mühendislerin kullanımına sunmaktır. 1. Introduction During the early stages of planning and design, the selection of the site and the type of dam should be carefully considered. It is only in exceptional cases that an experienced engineer can say that only one type of dam is suitable for a given dam site. Except in cases where the selection of type is obvious, it will be found that preliminary designs will be required for several types of dams before it can be shown which is the best solution from the standpoint of direct costs and all other factors. It is, therefore, important to emphasize that the project is likely to be expensive unless decisions regarding selection of the type are based upon adequate study after consultation with competent engineers. The selection of the best type of dam for a particular site calls for thorough consideration of the characteristics of each type, as related to physical features of the site and the adaptation to the purposes the dam is supposed to serve, as well as safety, economy, and other pertinent limitations. The final choice of type of dam is made after consideration of these factors. In this study, factors affecting the selection of the type of dam and the dam types to be constructed on the different foundations were discussed according to experiences. 2. Dam Types The dam types known at present are as follows [1]: Embankment Dams Homogeneous earthfill dam Earthfill with toe drain dam Zoned earthfill dam Earthfill with horizontal drain dam Earthfill with vertical and horizontal drains dam Earth and rockfill, central core dam (CCRD) Earth and sand-gravel, central core dam Earth and rockfill, inclined core dam (ICRD) Concrete face rockfill dam (CFRD) Bituminous concrete face earth and rockfill dam Steel face rockfill dam Thin membrane face earth and rockfill dam

(6) Emiroglu Civil

Embed Size (px)

Citation preview

Page 1: (6) Emiroglu Civil

International Journal of Science & Technology Volume 3, No 2, 173-189, 2008

Influences on Selection of the Type of Dam

M. Emin EMIROGLU Firat University, Faculty of Engineering, Civil Eng. Dept. Elazig, TURKIYE

(Received: 07.05.2007 ; Accepted: 28.07.2008)

Abstract: Heuristics and empirical knowledge from experts are vital parts of any water resources planning process. The selection of the type of dam requires a significant amount of empirical input from experts and specialists in the form of heuristic rules, expert opinions and inferences, and rules of thumb. Only very small percentage of such knowledge is well documented in the literature. It is also difficult to obtain all of the relevant knowledge related to the selection of the type of dam at the same time. The objective of this study is to discuss the factors influencing the selection of the type of dam by giving examples from rules of thumb and also to present typical cross sections for types of dams to be constructed on different foundations.

Baraj Tip Seçimine Tesir Eden Faktörler

Özet: Uzmanlardan edinilen meslek kuralları ve tecrübeye dayalı bilgiler, su kaynakları planlama sürecinde hayati önem taşımaktadır. Baraj tip seçiminde uzmanlardan alınan tecrübelerle edinilmiş bilgiler, uzman fikirleri ve meslek kuralları oldukça önemlidir. Bu tür tecrübeye dayalı bilgilerin çok az bir kısmı literature geçmiştir. Baraj tipi seçimine karar verirken her zaman tecrübeli mühendislerle çalışmak veya onlara her zaman ulaşmak mümkün olmamaktadır. Bu çalışmanın amacı baraj tip seçimiyle ilgili tecrübelere dayalı çok değerli meslek kurallarını literatüre aktarmak ve farklı baraj temelleri üzerine hangi baraj tip enkesitlerinin seçilebileceğini mühendislerin kullanımına sunmaktır. 1. Introduction

During the early stages of planning and

design, the selection of the site and the type of dam should be carefully considered. It is only in exceptional cases that an experienced engineer can say that only one type of dam is suitable for a given dam site. Except in cases where the selection of type is obvious, it will be found that preliminary designs will be required for several types of dams before it can be shown which is the best solution from the standpoint of direct costs and all other factors. It is, therefore, important to emphasize that the project is likely to be expensive unless decisions regarding selection of the type are based upon adequate study after consultation with competent engineers.

The selection of the best type of dam for a particular site calls for thorough consideration of the characteristics of each type, as related to physical features of the site and the adaptation to the purposes the dam is supposed to serve, as well as safety, economy, and other pertinent limitations. The final choice of type of dam is made after consideration of these factors. In this study, factors

affecting the selection of the type of dam and the dam types to be constructed on the different foundations were discussed according to experiences. 2. Dam Types

The dam types known at present are as follows [1]: Embankment Dams

• Homogeneous earthfill dam • Earthfill with toe drain dam • Zoned earthfill dam • Earthfill with horizontal drain dam • Earthfill with vertical and horizontal drains

dam • Earth and rockfill, central core dam (CCRD) • Earth and sand-gravel, central core dam • Earth and rockfill, inclined core dam (ICRD) • Concrete face rockfill dam (CFRD) • Bituminous concrete face earth and rockfill

dam • Steel face rockfill dam • Thin membrane face earth and rockfill dam

Page 2: (6) Emiroglu Civil

M. Emin Emiroglu

Concrete Gravity Dams • Lean roller compacted concrete (RCC) dam • Medium-paste RCC dam • High-paste content RCC dam • The faced symmetrical hardfill dam (FSHD) • Roller compacted dam (RCD) • Conventional concrete gravity dam (CCD) • Prestressed dam

Arch Dams

• Thin arch dam • Conventional concrete arch gravity dam • RCC arch gravity dam • Cupola (double-curvature arch) dam

Buttressed Dams

• Flat slab buttress dam • Round-head buttress dam • Diamond head buttress dam • Decked buttress dam • Multiple arch dam

3. Factors Affecting the Selection of the Type of Dam

Topography

Topographic considerations include the surface configuration of the dam site and of the reservoir area and accessibility to the and to construction materials. Topography, in large measure, dictates the first choice of the type of the dam. A few examples are given below related to this issue:

The curve of the river in plan, and changes in valley cross section, may favor adoption of an upstream sloping core rather than central core to reduce the quantities of earthfill. Local changes in slope of the abutments may lead to differential settlement and cracking, necessitating more extensive filter drains, or favoring CFRD construction. A narrow stream flowing between high, rocky walls would naturally suggest a concrete overflow dam. The low, rolling plains field would, with equal fitness, suggest an earthfill dam with a separate spillway. Earthfill dams have been constructed in almost every conceivable type of topography but are generally not used where deep gorges with extremely steep abutment walls are present. Broad valleys lead to central core dams. Steep canyon walls at the dam site can

mean settlement problems for core type dams and it might be better to construct some type of concrete dam (e.g. RCC). One of the primary factors in determining the suitability of a site for an arch dam is the width-to-height ratio. Ideally, the ratio should be relatively small (4 or less) for the use of thin arch dam. The V-shaped dam site are, generally, more favorable to the design of an acceptable arc dam than are U-shaped dam sites. Although not often a controlling factor in the selection of the type of dam, a symmetrical or nearby symmetrical dam site is desirable for an arc dam. Another dam type (e.g. CFRD) may prove to be a more economical structure if the dam site is extremely asymmetrical.

• Valley Shape. • Gorge. • Narrow V-shaped. • Wide V-shaped. • Narrow U-shaped. • Wide U-shaped. • Wide valley. • Quite wide valley. • Valley with irregular cross-sections.

• Simplicity of constructing a road to the dam site.

• The existence of deep gorges with extremely steep abutment walls and the difficulty of transport of earth material to dam site.

• The possibility of valley to transport earthfill material in every level.

• Changes in valley cross section. • The condition of the river in plan (curve

or flat). • Local changes in slope of the abutments. • Gradient of abutments of the valley. • Bottom width of the valley.

Geotechnical and geological structure of the dam site

Foundation conditions depend upon the

geological character and thickness of the strata which are to carry the weight of the dam, their inclination, permeability, and relation to underlying strata, existing faults, and fissures. The foundation will limit the choice of type to a certain extent, although such limitations can frequently be modified, considering the height of

174

Page 3: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

the proposed dam. For example, a foundation of competent rock is essential for any arch dam. The rock should be sound and durable to provide a satisfactory foundation for the life of the structure. Another of example of this issue, if a high dam is being considered, compressive strength of the foundation is an important

consideration in the selection of the type of dam. In cases where the river section of a wide valley provides a competent rock foundation close to the surface and the overburden increases towards either or both abutments, composite dams (concrete dam + embankment dam) can be selected.

• Foundation type.

• Rock. • Alluvium. • Gravel. • Silt and fine sand. • Clay. • Non uniform (lithologies).

• Condition of the bearing capacity of the foundation of rock. • Very good (>7 MPa) • Good (4 to 7 MPa) • Medium (2 to 4 MPa) • Low (1 to 2 MPa) • Very low (<1 MPa)

• Condition of the bearing capacity of the foundation of alluvium. • Good (>600 kPa) • Medium ( 200 kPa to 600 kPa) • Low (<200 kPa)

• Condition of the bearing capacity of the foundation of gravel. • Good (>600 kPa) • Medium ( 200 kPa to 600 kPa) • Low (<200 kPa)

• Condition of the bearing capacity of the foundation of silt or fine sand. • Good (>300 kPa) • Medium ( 100 kPa to 300 kPa) • Low (<100 kPa)

• Condition of the bearing capacity of the foundation of clay. • Very good (300-600 kPa) • Good (150-300 kPa) • Medium (75-150 kPa) • Low (<75 kPa)

• Shearing resistance of the foundation materials. • The existence of the wedge or block failures. • Condition of necessity of the foundation grouting.

• Very low (0.0 to 12.5 kg/m) • Low (12.5 to 25.0 kg/m) • Moderately low (25 to 50.0 kg/m) • Moderately high (50 to 100 kg/m) • High (100 to 200 kg/m) • Very high (>400 kg/m)

• Modulus of elasticity of the rock foundation. • Good (>3.40 GPa) • Medium (2 to 3.40 GPa) • Low (1 to 2 GPa) • Very low (<1 GPa)

• Modulus of elasticity of the non-rock foundation. 175

Page 4: (6) Emiroglu Civil

M. Emin Emiroglu

• The existence of deeply weathered rock at higher levels of the dam site. • Condition of the permeability of the foundation. • Stability of the abutments. • Safety of the abutments of valley. • The presence of instability on the left or right abutment due to large triangular wedge blocks

dipping steeply towards the river. • The existence of joint patterns in an abutment (their orientation, inclination and filled with clay or

silt etc.). • The existence of badly fractured rock in abutments. • Presence of differential deformation of the foundation along the axis of the dam. • Bedrock depth below stream channel. • The possible landslide or rock slide areas at the dam site. • Compressibility of the foundation. • The nominal value of hydraulic gradient, for seepage under a dam varies by at least one order of

magnitude according to type. • The association between the dam height and the alluvium depth.

• Depth of the alluvium more than the dam height. • Depth of the alluvium approximately near the dam height. • Depth of alluvium approximately half of the dam height. • Depth of the alluvium much less than half of the dam height.

• Condition of the relative density of the sand-gravel foundations. • Very loose (0-15) • Loose (15-35) • Medium dense (35-65) • Dense (65-85) • Very dense (85-100)

Availability of construction material

Elimination or reduction of transportation

expense for construction materials, particularly those which are used in great quantity, will affect a considerable reduction in the total cost of the project. Therefore, sometimes the most economical type of dam is the one for which acceptable construction materials exist within a relatively short distance from the site. The whole question of suitable construction materials and reasonable haul distance is one of economics,

and the selection of type of dam is usually based upon economy. A few examples are given below related to this issue:

An abutment supply of a single material points to the use of a homogeneous dam. Sufficient quantities of both previous and impervious materials lead to the use of zoned dams. If the local supply of aggregate is not adequate or the distance cement must be transported from the source is long, concrete gravity dam should not be selected. Instead of the dam type, CFRD can be selected.

• The haul distances and costs of transportation of suitable materials to the dam site. • The availability of suitable earthfill within economic haul distance. • Quantity and quality of available materials. • The uniformity of the available earthfill. • The existence of material in thin bed formal and despoliation very large area of beautiful land or in

adequate thickness. • Groundwater level of the borrow area. • Usability of the excavated material in dam.

176

Page 5: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

• The quantities and properties of the materials from the “required excavation” for the spillway, foundation cutoff trench, outlet works and other appurtenant structures.

• Supply of materials. • Cost of the expropriation of the material in the borrow area. • Soils for embankments.

• Rock for embankments and riprap. • Sandy clay, clayey sand and gravel-sand-clay soils. • Concrete agregate (sand, gravel, crushed stone). • Cementitious materials

• Portland cement • Flyash • Ground fines • Calcined clay • Limestone fines • Ground granulated blast furnace slag

Spillway size and location

The spillway is a vital appurtenance of a

dam. Frequently its size and type and the natural restrictions in its location will be the controlling factors in the choice of the type of dam. For example, the cost of constructing a large spillway is frequently a considerable portion of the total cost the project. In such cases, combining the spillway and dam into one structure should be desirable, indicating the adoption of a concrete overflow dam. Another of example of this issue, if topographic conditions or spillway capacity requirements are such that the spillway cannot be located away from the dam, an overflow spillway can be provided over the buttresses. • Magnitudes of the floods to be bypassed. • The presence or absence of suitable sites for

spillway. • The presence of large spillway for required

capacity and devotion of a major part of the dam for the spillway.

• The existence in unstable abutments for spillway excavation.

Cost

After safety and fulfillment of the purpose

for which the project is designed, cost is usually the most important factor in the selection of the type of dam. For example, Ita dam is located on

Uruguay River in Southern Brazil. Two types of dam (ICRD and CFRD) were compared with respect to cost. Cost of the CFRD was 43.416 x 106 $ and cost of the ICRD was 49.383 x 106 $. Therefore, the CFRD was selected [12]. Another of example of this issue, four dam types were considered in detail by the design engineers for Monksville dam in the USA. Cost of RCC was 18.1 x 106 $, cost of earthfill was 20.3 x 106 $, cost of CFRD was 25.6 x 106 $, and cost of CCD was 33.6 x 106 $. Therefore, RCC was selected [2].

• Estimates of cost for dam alternatives.

Environment and public opinion

Environmental considerations have very important in the design of dams. These factors can have a major influence on the type of dam constructed. The principal influence of the environmental laws and regulations on selection of a specific dam type is the need to consider maximum protection for the environment which can affect the type of dam, its dimensions, locations, location of spillway and appurtenant facilities. For example, if the dam is large and central core rockfill dam is the cheapest dam type and core material is available only in thin beds and to obtain sufficient will be despoiled a very large area of beautiful land, in this case, public opinion can have a major role in the adoption of a thin arch dam instead of rockfill dam despite difficulties with the foundations.

177

Page 6: (6) Emiroglu Civil

M. Emin Emiroglu

The possibility of flood inundation during

construction

The possibility of inundation by floods during construction may favor a concrete dam. For example; it is important to mention the behavior of RCC dams in the case of overtopping. During the construction of the Santa Eugenia dam, two floods occurred which exceeded the capacity of the river diversion outlet; these overtopped the dam during its construction with significant flow volumes. The concrete placed did not sustain any damage, but the machinery at the site was washed away [3].

The economical condition of the country

The amount of production of cement, pozzolan and steel, parallel to the industrial development of a country, can be effective on the selection of the type of dam. For example, if there is a lack of the steel, then buttress dam should not be selected • The supply of manufactured material such as

cementitious materials, steel, asphalt in the country. • The possibility of the application of new technology

by contractors in the country.

Climate and time available for construction

The design of a dam is often considerably

affected by climate, mainly because of the importance of the weather during the construction period. It is difficult to construct earthfill embankments during wet weather, or in freezing temperatures [4]. In these cases, it is often advantageous to adopt CFRD or ICRD. In very arid areas there may be a shortage of water for construction, therefore, favoring CFRD than earthfill dam. For the design and construction of the most satisfactory and economical dam, an adequate amount of time is required. For example, the time available for construction may influence dam type selection, particularly, if considered in relation to other factors such as climate, in a climate of well defined wet and dry seasons it may be practicable to construct an earth and rockfill or earthfill dam, but only two dry seasons. A CFRD may be constructed in

lesser time by continuing to place rockfill in the wet season. Another example of this issue, If constructing a dam on a permeable soil foundation, cutoff may be achieved by a cutoff wall at the upstream toe rather than a rolled earth cutoff under the central core, so that the cutoff wall can be constructed at the same time as the rest embankment. The mean annual precipitation; • Excessively rainy (>1000 mm) • Rainy (500 to 1000 mm) • Semiarid (200 to 500 mm) • Arid (< 200 mm)

Non availability of side personnel with

particular skills

At many sites neither skilled contractors nor artisans are available. This can preclude the adoption of dams that require intricate formwork or very high-quality concrete. The embankment type of dam or a masonry gravity dam may then prove most suitable.

Seismicity

Although many dams have failed throughout history, very few of these failures resulted from earthquakes, and none involved major concrete dams. However, the earthquake-induced damage to the Koyna Dam, near Poona, India, in 1967 and the Hsinfengkiang Dam, near Canton, People's Republic of China, in 1962 indicated that concrete dams not immune to earthquake damage as had commonly been presumed [5]. Because millions of people live in the floodplains downstream of these dams, it is essentials that increasing attention be given to the selection of the type of dam of these structures.

Height of the dam

Height of the dam is an important factor for the selection of the type of the dam. For example, earthfill with toe drain has been used for larger dams in the past, but should be limited to low (say less than 10 m) dams in low hazard locations. Heights of the dam suggested according to experience are given below.

178

Page 7: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

• Homogeneous earthfill dam, less than 5 m • Earthfill with toe drain dam, less than 10 m • Zoned earth fill dam, less than 20 m • Earthfill with horizontal drain dam, less than 10m • Earthfill with vertical and horizontal drains dam,

less than 50 m • Earth and rockfill, central core dam, very high,

but bigger than 15 to 20 m. • Earth and sand-gravel, central core dam, less than

140 m. • Earth and rockfill, sloping core dam, very high but

higher than 15 to 20 m. • Concrete face rockfill dam (CFRD), very high but

higher than 20 m. • Bituminous concrete face earth and rockfill dam,

less than 50 m. • Steel face rockfill dam, less than 40 m. • Thin membrane face earth and rockfill dam, less

than 30 m. • Lean roller compacted concrete (RCC) dam, very

high or very low • Medium-paste RCC dam, very high or very low • High-paste content RCC dam, very high or very

low • The faced symmetrical hardfill dam (FSHD), very

high or very low • Roller compacted dam (RCD), very high or very

low • Conventional concrete gravity dam, very high or

very low • Cupola (double-curvature arch) dam, high or very

high • Thin arch dam, very high or very low • Arch gravity dam, very high or very low • Multiple arch dam, very high or very low • Flat slab buttress dam, very high or very low • Round-head buttress dam, very high or very low

Function of the reservoir

Depending on the use planned for the reservoir, different designs may be justified at a given site. The reservoir function determines in part the tolerable loss of water due to leakage through and under the dam. It also determines the reservoir hydrograph which influences the dam stability. At some reservoirs the water level is never lowered and the upstream slope never subjected to "rapid drawdown" conditions. At the other extreme, the reservoirs for some hydroelectric power installations are kept full for long periods of time and then lowered in a span

of a few hours to obtain "peaking" power. For dams constructed to retain reservoirs of such specialized types, especially conservative slopes and zonings for the upstream embankment portions are often justified. The reservoir fluctuation condition;

• > 1 - 2 m/hour • 0.5 to 1 m/ hour • 0.125 to 0.5 m/ hour • 0.060 to 0.125 m/ hour • 0.015 to 0.060 m/ hour • 0.0125 to 0.015 m/ hour • <0.0125 m/ hour

Rapidity of construction

Foundation treatment and zoning details

may also be influenced by the time available for construction. A CFRD dam may be constructed in lesser time by continuing to place rockfill in the wet season. The very rapid rate of placement of RCC has many advantages; e.g. it can allow a relatively high dam to be constructed in one dry season, and thus reduce requirements of the diversion works [6]. The time of placement of RCC dams is very short. For example, Stagecoach dam, 46 m high with RCC volume of 34 000 m3, was built in little more than 37 days. Another example of this issue, Galeswille dam, 51 m high and 161 000 m3, was built in ten weeks.

Intended use of water in reservoir and benefit-cost relation

Consideration of the purpose a dam is to

serve often suggests the type most suitable. The tolerable seepage loss for some domestic water supply projects may be very low. For flood control dams, on the other hand, there is no economic limitation on the maximum quantity of leakage. Few sites exist where a safe and serviceable dam could not be build. But in many instances, conditions inherent in the site result in a project cost in excess of the justifiable expenditure. The results of a search for desirable dam sites often determine whether a project can be built at a cost consistent with the benefits to be derived from it.

179

Page 8: (6) Emiroglu Civil

M. Emin Emiroglu

Staged construction condition

It is often economic to construct a dam in two or more stages. In water supply, irrigation or hydropower projects, demand in the early years can be met with a lower dam and smaller storage. If staging is planned, this favors adoption of CFRD or ICRD.

Knowledge and courage of the engineers

Safety, construction feasibility, adaptability of type features, cost, and existing conditions, such as climate, geology, availability of materials, and topography, are thoroughly evaluated to assist in making a type choice. However, except in the rare cases where site conditions preclude consideration of more than one type, the choice depends to a certain extent on individual preferences which reflect the judgment and experience of the designer.

Contracts, standards, and conservative decisions for every country

Conservative designs may be advisable for

dams in parts of the world where experienced contractors and supervisory personnel are not available. Even in the United States, earth dams constructed by U.S. Bureau of Reclamation just after World II, when no dams had been built for a long period, were provided with somewhat flatter slopes than usual, mainly because it was feared that the personnel would not have the skill necessary to produce embankment of high quality.

Simplicity of river diversion

All construction considerations contribute to the selection of type. Certain features, such as relative simplicity of diversion, may favor the selection of a concrete gravity dam. Diversion can be made over low blocks or through permanent or temporary sluices. Forming is simple. To these advantages may be added the fact that the dam can be designed for overtopping during construction without serious damage. These factors affect the construction schedule and thereby the cost.

Safety

Safety, of course, is the first consideration. It is impossible to build with safety some types of dams if certain foundations and other characteristics of the site exist. Consideration of these factors will often decrease considerably the number of possible types from which to choose.

Probable wave action

An earth dam must be protected from damage caused by the erosive action of waves beating on the upstream slope. The severity of the wave action and amount of protection needed for the embankment are related to the length of the reservoir surface over which the wind velocities in the locality.

Probable ice action

Ice load is usually important only for small dams. Ice load can be important in circumstances where ice sheets form to appreciable thicknesses and persist for lengthy periods. In such situations ice pressures may generate a considerable horizontal thrust near crest level. The pressure exerted on the dam is complex function of ice thickness, scale and rate of temperature rise resulting in expansion, and the degree of restraint existing at the perimeter of the ice sheet.

Foundation excavation

Economic considerations dictate that the excavation volume should be minimized.

Whether the water intakes structures to be passed through the dam

In some cases, passing through the dam of

water intake structures may be necessary. This case may influence the selection of the type of dam.

Discharge of the river

Narrow valleys, good foundations, and large stream flows tend to favor the selection of concrete dams, whereas wide valleys, poor foundations, and small stream flows tend to favor embankment dams.

180

Page 9: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

The design flood peak flow; • Very large (>10 000 m3/s) • Large (7 500 to 10 000 m3/s) • Medium (2 000 to 7 500 m3/s) • Little (500 to 2 000 m3/s) • Fairly little (<500 m3/s)

The effects of aggressive water on dams

The reservoir water may include the dissolved chemicals (e.g. acids) that might be harmful for concrete. This case may influence the selection of the type of dam.

The water difference between headwater and tailwater

The water difference between headwater and

tailwater is important for the concrete gravity dam. Most foundation materials are acceptable for consideration of a gravity dam under 15 m in height and with a difference between headwater and tailwater less than 6 m.

The effects of uplift force under the dam

The uplift pressure is a major factor in gravity dam. Buttress dams have an advantage over solid gravity dams where uplift pressures are concerned. The hydrostatic pressure or uplift at the base of the dam is relieved between the buttresses and the small remaining uplift pressure on the buttresses does not materially affect the stability of the structure.

Danger of war and sabotage The dam sites where is danger of war and

sabotage are chosen more resistant dam types. For example, buttressed dams are more subject to damage or destruction by sabotage or military attack than massive dams. Because of the thinness of their members they are sensitive to even moderate deterioration of the concrete; hence they must be carefully built and careful consideration must be given to any unusual exposure conditions.

Lack of water for construction

In dry climates where lack of water may prevent the use of earth core material a diaphragm type rockfill dam can be used. For large rivers, this item is relatively unimportant except for quality of the water. For small streams and offstream reservoirs, water for construction purposes may be difficult to obtain.

Appearance

Appearance does not usually influence the selection of the type of dam. After the choice is made, every effort is made to achieve a pleasing appearance. 4. Typical Cross Sections for Types of Dams to be Constructed on Different Foundations

Rock Foundation

A strong low permeability rock foundation is suited to any type of dam construction, but may favor construction of a CFRD, RCC or in particular circumstances arch dam. The economy of materials or the overall cost should be the ruling factor. The removal of disintegrated rock together with the sealing of seams and fractures by grouting is frequently necessary. Karst limestone foundations are a special case, where extensive grouting and other work may be needed to limit leakage to acceptable level. Such situations favor adoption of a design, which allows for grouting to continue during embankment construction or after it is completed. This may tend to favor CFRD or ICRD. Weaker rocks such as clay shales, some sandstones, weathered basalt, etc., may present significant problems to the design and construction of a dam and may heavily influence the type of dam selected. In some sedimentary rocks, particularly interbedded weak claystone and mudstone, and strong sandstone, which have been subject to folding and/or faulting, bedding plane shears may exist, resulting in low affective friction angles. In these circumstances, flat slopes may be required on the embankment, favoring earthfill with vertical and horizontal drains. Cross sections belong to dam types to be constructed on the rock foundations are given in Fig. 1. These cross sections were developed according to experiences.

181

Page 10: (6) Emiroglu Civil

M. Emin Emiroglu

Alluvium Foundation

For the wide valley and deep overburden, an earthfill dam is usually the best solution. The embankment dam base is so wide that the load-bearing capacity is seldom a problem except in the case of soft clays. Alluvial foundation mean seepage problems will be present and their permeability and depth can mean changes in the earthfill type used. If special cutoffs are used, a definite type can be suggested depending on the cutoff location.

Nonrock foundation such as silt, sand, gravel and clay may be acceptable for RCC dam, CCD, and FSHD at low heights of dam. It is suggested by experts that gravity dams less than 20 m height can be constructed on alluvium foundations. The Lower Chase Creek, Cedar Falls and Dryden dams, RCC dams, constructed in USA was located in a valley where the foundation was alluvium [7].

The foundation geology at a dam site often dictates the type of dam suitable for that site. Unlike arch, high-gravity, and buttress dams, which require a sound rock foundation, embankment dams are readily adapted to earth foundations. Therefore, it can be said that earthfill dam can be constructed on the alluvium foundations. It is possible to construct on alluvium foundation an earth and sand-gravel, central core dam that is 140 m height. It is possible to show as examples for earthfill dams constructed on alluvium foundations Bor-Akkaya Dam in Turkey; Rose Valley Dam in Canada; Duncan Lake Dam in Canada; Kennewick Levee, McNary Dam in USA; Wanapum Dam in USA and Mangla Closure Dam in Pakistan [8, 9 and 10]. There are necessity rock foundations for rockfill dams. If the foundation is alluvium, expert human due to excessive settlement does not suggest it using of large rocks in shell. In this case, sand-gravel material is used as shell material. Santa Juana dam can be shown as an example for above conclusion. Santa Juana dam was a rockfill concrete face on the Huasco River in the northern Chile. Santa Juana dam was founded on 30 m deep clean gravel-cobble alluvium. The

Santa Juana dam is 103 m high, with a crest length of 400 m [11].

Cross sections belong to dam types to be constructed on the alluvium foundations are given in Fig. 2.

Clay Foundation

Sites with thick deposits of soft and

compressible soil generally have been avoided in the past, but as time passes and the better sites are gradually built upon, sites with soft foundations must be used with increasing frequency. However, there are not easy or economical methods to deal with soft clay foundations.

Foundations of fine-grained soils are usually impermeable enough to preclude the necessity of providing design features for under seepage and piping. However, inclined and horizontal filter-drainage blankets provide good protection against unknown geologic conditions, cracking, dispersive soils, and design and construction defects. The main problem with these foundations is stability. In addition to the obvious danger of bearing failure of foundations of saturated silts and clays, the designs must take into account the effect of foundation saturation of the dam and of appurtenant works by the reservoir.

Soil foundations should have strength properties equal to or greater than that of the embankment. The entire area to be occupied by the dam should stripped to a sufficient depth to remove all unsuitable materials, including surface boulders, loose rock, debris, topsoil, and vegetation, that might interfere with the paper bonding of the embankment with the foundation. So, a stiffer foundation should be achieved. A good drainage should be achieved for protecting the embankment soil from saturation, and facilitates the dissipation of pore water pressures from beneath the embankment, thus allowing the consolidation of the soft foundation soils. As consolidation occurs, the shear strength of the foundation is increased, resulting in an increase in the factor of safety against bearing capacity failure.

Clay foundations can be used for the support of earthfill dams but require special treatment. If the foundation material is weaker than the earthfill, the critical slip surface would generally pass

182

Page 11: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

through the foundation. Therefore, to maintain equilibrium, designers extend the slip surface using flatter slopes or toe berms. Since there may be considerable settlement of the dam if the clay is unconsolidated and the moisture content is high, clay foundations ordinarily are not suitable for the construction of concrete gravity dams, should not be used for CCRD, ICRD, CFRD, bituminous concrete face earth and rockfill dam, steel face rockfill dam. Clay foundations are acceptable for consideration of a gravity dam under 15 m in height and with a difference between headwater and tailwater less than 6 m. Foundations for rockfill dams must be capable of resisting settlement and deformation.

Sand drains are useful for clay foundations. In addition to this, staged construction of the embankment with pore pressure monitoring could be adopted. Cross sections belong to dam types to be constructed on the clay foundations are given in Fig. 3. These cross sections were developed according to experiences.

Silt or Fine Foundation

Arc dams are suited to narrow gorges, subject

to uniform sound rock of high strength and limited deformability in foundation and abutments. Concrete gravity dams are suited to wide valleys, provided that excavation depth is less than 5 – 10 m. Buttress dams are suited as gravity dams, but higher contact stresses require sound rock. Rockfill dams are constructed on the rock foundations. Therefore, dam types above mentioned are not suitable for silt or fine sand foundations. However, this foundation type is acceptable for consideration of a gravity dam under 15 m in height and with a difference between headwater and tailwater less than 6 m and introducing necessary foundation treatment. Silt or fine sand foundations are suitable for the construction of earthfill dams. But, foundation treatment is necessity.

Cross sections belong to dam types to be constructed on the silt or fine sand foundations are given in Fig. 4.

Non Uniform Foundation

Occasionally, situations may occur where

reasonably uniform foundations of any of the foregoing descriptions cannot be found and where a non uniform foundation of rock and soft material must be used if the dam is to be built. Such unsatisfactory conditions can often be overcome by special design features. Each site, however, presents a problem for appropriate treatment by experienced engineers.

Only one dam or composite dam can be constructed on the non uniform foundations. Composite dam use the advantages of both the embankment dam and the concrete dam. They generally consist of concrete gravity (conventional or rcc) or buttress sections in combination with earthfill or rockfill sections. The concrete dam portion incorporates the ability to pass flood flows over or through the section during construction and act as the spillway after construction, and the earth or rockfill sections take advantage of flow cost construction and local materials. Except for the hydraulic considerations mentioned above topography is the main reason for the selection of a composite dam. The topography for combination dams is usually associated with plains locations or zone of land where plains and mountains meet, but seldom with mountains terrain itself. Wide valleys often provide favorable sites for the use of combination dams. Foundation conditions are the second most important factor in selecting a combination type dam. In cases where the river section of a wide valley provides a competent rock foundation close to the surface and overburden increases toward either or both abutments, composite dam can be economical. If a combination concrete-embankment structure is being considered, the concrete portion must have a foundation of acceptable quality. Cross sections belong to dam types to be constructed on the non uniform foundations are given in Fig. 5.

183

Page 12: (6) Emiroglu Civil

M. Emin Emiroglu

Earthfill

RiprapEarthfill

Riprap

Earthfill

Riprap

Chimneydrain

Earthfill

RiprapInternal sand drain

Grout curtain

Earthfill

Riprap

Earthfill

Riprap Internal sand drain

Rock slope protection

Rolled clay core

Earthfill

Riprap

Water level

1Steel plateCompacted graveland stone1

Non-cohesivefines

Concrete faceAsphaltic concreteimpervious membrane

Grave

l with

fine

s

RockfillClean gravel

Rockfill

Non-cohesivefines

Parapet wall

Gravel and rock

m

mCoffer dam

Chimneydrain

Spillway crest

RCC

ConcretefacingConcrete

facing

(Roller compactedconcrete)

The faced symmetricalhardfill dam

(FSHD)

Water level

Grout curtain

Thin membran(thickness0.2 mm to 2 m)

Chimneydrain

Water level

Water level Water level

Water level Water level

Water level

Water level

Water level

Drain

Drain

RandomEartfill

EarthfillRiprapWater level

Horizontal drain EarthfillRiprapWater level

EarthfillRiprapWater level

Toe drain

RiprapWater level

Grout curtain

Clay

RiprapWater level

Grout curtain

RandomRando

m

Clay

Sand and gravel

R O C K F O U N D A T I O N S

Grout curtain

Cut off levelGeneral excavation level

Cut off level General excavation level

Cut off level

General excavation level

Cut off level

General excavationlevel

Cut off level General excavationlevel Cut off levelGeneral excavation

levelCut off level

General excavationlevel

General excavation level Cut off level

Grout curtain

General excavationlevel Cut off level

Grout curtain

Grout curtainGrout curtain

Water level

General excavationlevel Cut off level

Cut off level Cut off level General excavation level

Cut off level

General excavation level Cut off level

General excavation level

Grout curtainGrout curtain Grout curtain

Grout curtainGrout curtain

Grout curtain

Water level

Water level

Thin claycore

Riprap

Rockfill

Water level

General excavationlevel Cut off level

Grout curtain

(Convensional concrete dam)

Drain

Riprap

Rockfill

Water level

General excavationlevel

Rockfill

RockfillRockfillRockfillRockfill

RockfillRockfill

RockfillRockfill

Rockfill

Asphalt or concrete

Convensional concrete(Arc Gravity Dam)

Water level

RC

C A

rcG

ravi

ty D

am

Thin Arc Dam

Miscellaneous

fill Rockfill

Quarryfines

MiscellaneousfillRockfill

Rock

fill

Core Material

RiprapPit run gravelly sand

Washed gravelly sand

Riprap

Grout curtain Weak rock foundation

Water level

Flat slabbuttress

Water level

Multiple archor multiple cupola m

1

Water level

Massive buttress:Roundhead

m=0.8 - 1.0

m1

m=0.75 +-

m1

Water level

Massive buttress:Diamond head

m=0.8 - 1.0

Water level

Decked buttress

Water level

Cupola ordouble-curvatura arc Top gallery

Lower gallery

Pulvino

Max tailwater level

Earthfill

Clay

Coffer dam

CCD

General excavation level

Water level

Fig. 1. Some cross-sections of dams to be constructed on rock foundations

184

Page 13: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

Alluvium Cut off wall

Earthfill

Riprap

. ... .. ...

. ...

... ....

.

.. .....

...

... ..

.. ... ..

. ... . ... .. . .... .

... .

..

... ..... .

. . ....

.. .Alluvium Cut off wall

EarthfillRiprap

.... ...

. ....

...

.

. ...

...

.. .. .. .. . .. . ... .

. .... ...

.... ..

...

. . ... . Alluvium

EarthfillRiprap

..

.... .

...

..

. ... . ... ..

. .. . ..

. .... .. . .....

...

.

..

. .. .... ..

.Alluvium..

. ..

.. .

.

Alluvium

Chimneydrain

Earthfill

Riprap

.........

.

....

. ... . .... .. ..

. ... . ... ..

..

.......

. ..

Internal sand drain

.. ..

..

Grout curtain

Alluvium

Earthfill

Riprap

. .... .

.

.. .

.....

..

. .... ..

.. .. ...

... .. .... ... ..

..

....

... .

. . .... .

Blanket

...

... .... . .

.

.. ...

Bedrock

Bedrock

Alluvium

Earthfill

Riprap

....

..

...

.

.. . .

.. ... .....

. .. . ... ..

. .. ... ...

.. ..

..

. .. .

Internal sand drain

... .. .

.

. ...... .. .

Bedrock

Blanket

Rock slope protection

Alluvium Cut off wall

Rolled clay core

. ..... .

..

. ...

... ....

.

......

...

.. ..

. . ... ... ... ... .. ... ....

....

...

.

.. .

. . ... .

Bedrock

.......

. . ..

. .

Clay

Riprap

Alluvium

Clay

.... ..

..

.. ....

.. ... ... ..

..

.Sand andgravel

Riprap

..... . ..

Water level

1

AlluviumCut off wall

Steel plate Compacted graveland stone

1

Non-cohesivefines

Concrete face

Gravel Graveland rock

Concterecut off

Alluvium

Asphaltic concreteimpervious membrane

Concterecut off

Alluvium

Gravel

with fi

nes

Randomgravel fill

Clean gravel

Graveland rock

G r a v e l

Non-cohesivefines

Parapet wall

Grout curtain

Gravel and rock

m

m

. ... .. ..

... .

..

... ..

.

. ...

. ..

..

. .. ... .....

.. . .. .

. ..... .

...

. .....

.... . .

.

...

..

..

...

.

. ...

..

.. ..

. .... ... ......

.. . ..

. . ..

.

..... ..

. .. ...

Plinth

Sand andgravel

Sand andgravel Sand and

gravel

Coffer dam

Chimneydrain

Bedrock

Spillway crest

RCC

ConcretefacingConcrete

facing

Reinforcedconcreteapron

RiprapReinforcedconcrete apron

GetextileDrain pipeAlluvium. ... .. .

...

...

....

...

. . ..

. .. ..

. .. .. . .. . . .

.. .... .

... .

... ..

Sheet pile cutoff

Spillway crest

(Conventional concrete dam)

Reinforcedconcrete apron Riprap

Reinforcedconcrete apron

GetextileGravelDrain pipe

Alluvium. ... .. .

. ...

..

...

. .. .

. .. .. . .. . .. ..

. ... .

... ..

Sheet pile cutoff

(Roller compactedconcrete)

CCD

Bedrock

. .... . .. .. .. .. . . .. .... .. . ... .. ... .. . .. .. .. . ..

Alluvium. .. ...

.... .. . .

.. ..... .

..

.

Sheet pile cutoff

Reinforcedconcrete apron

. ....

...... ..

....

. ...

. ........ .....

The faced symmetricalhardfill dam

(FSHD)

Water level

Grout curtain

Alluvium Cut off wall. .. . ...

.....

.

.

. ...

...

.. ..... .. .

. . ... ..

.....

...

. .. . ...

Thin membran

Bedrock

(thickness0.2 mm to 2 m)

Bedrock

Chimneydrain

Water levelWater level

Water level Water level

Water level Water level

Water level

G r a v e l

Water level

Water level

Bedrock

Drain

Drain

Filter

Randomeartfill

Alluvium Cut off wall

Earthfill

Riprap

. ... .. ...

. ...

.. .....

.

...

....

..

...

. .. .. ....

.. ... . ... .

. . .....

... ..

.......

.

..

. . ....

.. .Bedrock

Water level

Horizontal drain

Alluvium Cut off wall

EarthfillRiprap

. ... .. ...

. ...

.. .....

.

...

....

..

...

. .. .. ....

.. ... . ... .

. . ....... ..

......

.

..

. . ....

.. .Bedrock

Water level

Alluvium Cut off wall

EarthfillRiprap

... .. ...

. ...

....

...

.

.....

..

. .. .. ..

...

..

. ... ...

.. . ...

.. ....

......

.

. . ..

... .

Bedrock

Water level

Toe drain

Alluvium

Riprap

..... ..

. ..... ... ..

..

. ...... .

.. ...

Bedrock

Water level

Alluvium

Sand andgravel

Riprap

. .. ..

. ...

.. ..

..

. .. .... ....

.. ..

.. . .

. .

Blanket

..

... .... . .

.

. ..

Bedrock

Water level

Slurry trench

Grout curtain

Clay Sand and gravel Clay

.. . ...Alluvium

Riprap

...

. ........ ... ..

..

... .

.. . ..

. ...

Bedrock

Water level

Grout curtain

.. . ...

RandomRand

om

Sand and gravel

Sand and gravel

Clay

Gravel

Sand and gravel

A L L U V I U M F O U N D A T I O N S

Fig. 2. Some cross-sections of dams to be constructed on alluvium foundations (Emiroglu, et al., 2002)

185

Page 14: (6) Emiroglu Civil

M. Emin Emiroglu

Earthfill

Riprap

Earthfill

Riprap

Earthfill

Riprap

Chimneydrain

Earthfill

RiprapInternal sand drain

Clay Clay

Riprap

ClayEarthfill

Riprap

Earthfill

Earthfill EarthfillCoffer dam

Spillway crest

RCC

ConcretefacingConcrete

facing

FSHD

Water level

Chimneydrain

Water levelWater level

Water level

Water levelWater levelWater level

Drain Randomearthfill

Earthfill

Riprap

Water level

Earthfill

Riprap

Water level

Toe drain

Riprap

Water level

Clay Earthfill

Riprap

Water level

RandomRand

om

Earthfill EarthfillClay

C L A Y F O U N D A T I O N S

Clay

Clay

Clay

Clay

Clay

Clay

Clay

Clay

Clay

Clay

Clay

Clay

Miscellaneousfill

Miscellaneousfill

Clay

Miscellaneousfill

Miscellaneousfill

Blanket drain

Water level

Chimneydrain

Earthfill

Internal sand drain

Blanket drain

Riprap

Thin membran(thickness0.2 mm to 2 m)

Water level

Earthfill

Clay Horizontal drain

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

Bedrock

BedrockBedrock

Vertical sand drain

Shear Key

Horizontal drainClay fill

Concrete core wall

Clayfill

Bedrock

Clay

Riprap

Water level

Earthfill Earthfill

Earthfill

Miscellaneousfill

Miscellaneousfill

Shear key

EarthfillRiprap

Water level

Clay

Bedrock

Stabilizing fillStabilizing fill

D>>H

D<< H

Shear keyD<< HD<< H

Clay Foundation Depth

Dam Height

D>>H

Water level

CCD, RCC and FSHD can be constructed on the clay foundation if height of dam is low.

Shear key can be constructed if the clay foundation depth is low.

Vertical sand drains can be constructed if the clay foundation depth is very high.

Note:

Note:

Note:

D:

H:

Shear KeyDrain

Asphalt core wall

Bedrock

Clay

RiprapWater level

EarthfillEarthfill

D<< H

CC

RCD or RCC

Water level

Clay

CC: Convensional concrete

RCD: Roller compacted dam

Water level

(Staged construction)

CCD

CCD:Convensional concrete dam

RCC:Roller compacted concrete

Fig. 3. Some cross-sections of dams to be constructed on clay foundations

186

Page 15: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

Earthfill

RiprapEarthfill

Riprap

EartfillRiprap

Chimneydrain

Earthfill

RiprapInternal sand drain

Earthfill

RiprapEarthfill

Riprap Internal sand drain

Rock slope protection

Clay Clay

Riprap

ClayEarthfill

Riprap

EarthfillEarthfill

EarthfillCoffer dam

Chimneydrain

Spillway crest

RCC

ConcretefacingConcrete

facing

FSHD

Water level

Thin membran(thickness0.2 mm to 2 m)

Chimneydrain

Water levelWater level

Water level Water level

Water level Water level

Water level

Water level

Water level

Drain

Drain

RandomEarthfill

EarthfillRiprapWater level

Horizontal drain

EarthfillRiprapWater level

EarthfillRiprapWater level

Toe drain

Riprap

Water level

Clay Earthfill

RiprapWater level

RandomRand

om

Earthfill EarthfillClay

Earthfill

S I L T O R F I N E S A N D F O U N D A T I O N

CCD

Earthfill

Silt or fine sand Silt or fine sandSilt or fine sand

Silt or fine sandSilt or fine sand

Silt or fine sand

Silt or fine sand Silt or fine sand Silt or fine sand

Silt or fine sand

Silt or fine sand

Silt or fine sand

Silt or fine sand Silt or fine sand

Silt or fine sand

Silt or fine sandSilt or fine sand

CCD: Convensional concrete damRCC: Roller compacted concrete dam

FSHD: The faced symmetrical hardfill damNote: CCD, RCC and FSHD can be consructed on the silt or fine foundation if height of dam is very low

Water level

Note: Slopes for embankment dams must be very flat (e.g. 1 vertical and7 horizontal)

Fig. 4. Some cross-sections of dams to be constructed on silt or fine sand foundations

187

Page 16: (6) Emiroglu Civil

M. Emin Emiroglu

Earthfill

RiprapEarthfill

Riprap

Earthfill

Riprap

Chimneydrain

Earthfill

RiprapInternal sand drain

Grout curtain

Earthfill

Riprap

Earthfill

Riprap Internal sand drain

Rock slope protection

Non-cohesivefines

Concrete face

Asphaltic concreteimpervious membrane

Grave

l with

fine

s

Rockfill

Clean gravel

RockfillNon-cohesivefines

Parapet wall

Chimneydrain

Spillway crest

RCC

ConcretefacingConcrete

facing

(Roller compactedconcrete)

(The faced symmetricalhardfill dam)

FSHD

Water level

Grout curtain

Thin membran(thickness0.2 mm to 2 m)

Chimneydrain

Water level Water level

Water level Water level

Water level

Water level

Water level

Drain

Drain

RandomEarthfill

Earthfill

Riprap

Water level

Horizontal drain EarthfillRiprap

Water level

Toe drain

Sand and gravel

N O N U N I F O R M F O U N D A T I O N S

Grout curtainCut off level

General excavationlevel

Cut off levelGeneral excavation level

Cut off levelGeneral excavationlevel

Cut off level General excavationlevel

Cut off levelGeneral excavationlevel Cut off level

General excavationlevel

Grout curtainGrout curtain

Water level

General excavationlevel Cut off level

Cut off levelCut off level

General excavation levelGrout curtain Grout curtain

Grout curtainGrout curtain

Grout curtain

(Convensional concrete dam)

Drain

RockfillRockfill

Miscellaneousfill Rockfill

Quarryfines Miscellaneous

fillRockfill

RockfillCore Material

RiprapPit run gravelly sand

Washed gravelly sand

Riprap

Grout curtain Weak rock foundation

m1

m=0.75 +-

Earthfill

Clay

Coffer dam

Clay core

Riprap

Rockfill

Water level

Perviousmaterial

Grout curtain

AlluviumClay

Spillway excavation zone

Upsttreamcofferdam

Alluvium

Rockfill

Rock foundation

Riprap

Crushedrock

Clay core

RiprapWater level

Semi - perviousmaterial

Grout curtain

Alluvium

Clay

Upsttreamcofferdam

Alluvium

Sound rock foundation

Riprap Semi - perviousmaterial

Alluvium

Sound rock foundation

Clay

Upsttreamcofferdam

Riprap

Wastefill

Rockfill

ClayClayRiprap

Protective shell

Sound rockfoundation

Alluviu

m

Protective shell

Clay core

Riprap

Rockfill

Water level

Rockfill

Grout curtain

Clay

Upsttreamcofferdam

Sound rock foundation

Riprap

Rockfill RockfillWaste fill

Rock foundation Rock foundation

Riprap

Semi - perviousmaterial

Water level

Clay

Alluvium

Decomposed volcanic seriesMarn

Alluvium

Clay Clay

Sand gravelfill zone Rockfill zone

Clay

Weak rockSou

nd ro

ck

Weak rock

Sound rock Weak rock

Alluvium

Water level

Rockfill

Random fill

Clay

Silty - sandy gravel

Impervious fill

Rock foundationGrout curtain

Clay

Silty - sandy gravel

Berm fillPervious fill

Riprap

Water level

General excavation level

EarthfillClay

Clean fine sand

Earthfill

Alluvium

Random fill

Riprap

Chimneydrain

Water level

Cut off level Fractured rockGrout curtain

Alluvium

Random fill

RiprapWater level

Alluvium

Allu

vium

Weak rock

Clay

Drainage boreholes

Surcharging fill

Random fill

Riprap

Water level

Weak rockSound rock

Clay

Drain

CCD

Fig. 5. Some cross-sections of dams to be constructed on non-uniform foundations

188

Page 17: (6) Emiroglu Civil

Influences on Selection of the Type of Dam

Conclusions

There is one type of dam that, in combination with its spillway and other ancillary works, will produce the most economical development of a particular dam site. Many factors influence the selection of the type of dam. Before reaching a decision to select a dam type, of all the factors influencing the selection of a type of dam must be

taken into account all together. The selection of the type of dam requires a significant amount of empirical input from experts and specialists. In this paper, a lot of rules of thumb and cross sections of dams for different foundations are presented. By considering of the rules of thumb, the designing engineer can reduce his/her change of error in selection of type of dam.

References

1. Emiroglu, M.E., Tuna, A., and Arslan, A., (2002). Development of an Expert System for Selection of Dam Type on Alluvium Foundations, Engineering with Computers, 18(1), pp 24-37.

2. Hansen K. D., (1994). Built in the USA-RCC dams of the 1990’s. International Water Power & Dam Construction, April 1994, pp. 24-32.

3. Franco, M. A., and Cordova, J. Y., (1995). The Spanish approach to RCC dam engineering. The Int. Journal On Hydropower & Dams, Volume 2, pp. 72-79.

4. Fell, R., MacGregor, P., and Stapledon, D., (1992). Geotechnical engineering of embankment dams, A. A. Balkema / Rotterdam/ Brookfield.

5. Thomas, H. H., (1976). The Engineering of large dams. Jhon Wiley & Sons, London.

6. Dunstan, M.R.H., (1994). The state - of - the - art of RCC dams, The International Journal On Hydropower & Dams, March 1994, pp. 44-54.

7. Hansen, K.D., and Reinhardt, W.G. (1991). Roller-Compacted Concrete Dams. McGraw-Hill, Inc., New York.

8. Jones, J. C. (1967). Deep cut offs in pervious alluvium, combining slurry trenches and grouting. Ninth Congress on Large Dams, vol. I, 509.

9. Design of small dams. (1987). Bureau of Reclamation, U.S. Govt., Printing Office, Denver, Colorado.

10. State Water Works, (1997). Dams and Hydroelectric Power Plants in TURKEY, General Directorate of State Hydraulic Works, Ankara.

11. Astete, J.; Martin, L. S., and Alvarez, L., (1992). The Santa Juana CFRD for irrigation in northern Chile. International Water Power & Dam Construction, April 1992.

12. Sobrinho, J. A. and da Cunha, J. C. (1985). Ità dam-selection of type. published in Concrete Face Rockfill Dams-Design, Construction and Performance, edited by J. B. Cooke, J. L. Sherard, ASCE, pp. 601-607.

189