    NOTE

    1 The work that represents the object of the present project is classified in category C -normal level of importance, according to the GO no. 766/21.11.1997, OG no.675/3.07.2002 and to the "Methodology for the classification of constructions withrespect to their importance" - issued by INCERC BAP - SCB Laboratory in April 1996.

    2 The present project is verified with respect to the following performancerequirements in accordance with GO no. 925/20.11.1955 and MLPAT Order no.77/N/28.10.1996

    A4 - resistance and stability at static, dynamic shocks, including seismic activity;Af - resistance and stability of soil masses - consolidation works;A7 - resistance and stability of hydro-technical works;B2 - safety of the public traffic;B5 - liability of hydro-technical works and environment protection;D2 - human health and environment protection

    3 At the beginning of the works the Employer, the Consultant and the Contractor willestablish the recovery means of the materials resulted from demolition.

    4 If the execution of the Works will start more than 1 year after the date the design wasissued, the Designer will confirm the project applicability taking into consideration thetechnical state of the existing structures at the date of the start of the Works.

    5 All the property rights for this documentation belong to PARSONS GROUPINTERNATIONAL LTD and SEARCH CORPORATION LTD., Bucuresti, CadereaBastiliei, no. 65, sector 1, phone: 021/230 40 17, fax: 021/230 52 71.The project is to be exclusively used by the ROMANIAN NATIONAL COMPANY OFMOTORWAYS AND NATIONAL ROADS for the procurement and execution of theworks for REHABILITATION OF DN 76 DEVA ORADEA.The use or reproduction of various parts of the present project by other persons exceptfor the Client can only be done based on the prior written approval of the PARSONSGROUP INTERNATIONAL LTD and SEARCH CORPORATION LTD.

    6 This documentation contains the Technical Project for REHABILITATION OF DN 76DEVA ORADEA.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    2/348

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    3/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 3 of 349

    SPECIFICATIONS

    2.0 GENERAL ITEMS

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    4/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 4 of 349

    Romanian National Company of Motorways and National RoadsRoads Rehabilitation V th ProjectRehabilitation of DN 76 DEVA - ORADEAContract 5R12 Vrfurile - tei, km 69+350 - 102+660

    CONTENTS

    1 - GENERAL 6

    2 - LEGAL PROCEDURES AND LOCAL LEGISLATION 62.1 - Legal provisions.................................................................................................... 62.2 - Quality Assurance and Control System for Civil Engineering Works ....................72.3 - State Quality Inspection of Construction Works....................................................9

    3 - CONTRACTOR'S DUTIES 103.1 - Maintenance of the Existing Road during Execution .........................................10

    3.2 - Drawings.............................................................................................................113.3 - Possession and Use of the Site ..........................................................................113.4 - Site Compound...................................................................................................123.5 - Temporary works ................................................................................................123.6 - Existing Structures and Underground Services .................................................. 133.7 - Dealing with Water..............................................................................................133.8 - Information..........................................................................................................133.9 - Utilities Relocation and Protection ......................................................................143.10 - Safeguarding the Environment..........................................................................143.11 - Traffic Management...........................................................................................163.12 - Works done Off Site. .........................................................................................173.13 - Other Contractors..............................................................................................173.14 - Documents to be submitted to the Engineer......................................................183.15 - As Built Drawings ..............................................................................................183.16 - Clearing and disposal of Unexploded Ammunition ............................................183.17 - Erection of site identification boards..................................................................18

    4 - QUALITY ASSURANCE AND CONTROL 194.1 - Quality Assurance Management System............................................................194.2 - Specifications and Standards ............................................................................. 194.3 - Site Laboratory ...................................................................................................194.4 - Sampling, Testing, Trials and Method Statements .............................................20

    4.5 - Alternative Materials ...........................................................................................204.6 - Engineer's approval of the Works .......................................................................20

    5 - SURVEY 215.1 - Existing Ground and Road Levels ......................................................................215.2 - Survey and Setting Out.......................................................................................21

    6 - FACILITIES, SERVICES and EQUIPMENT for the ENGINEER and for PROJECTIMPLEMENTATION UNIT (P.I.U.) 226.1 - Engineer's Main Office........................................................................................226.2 - Laboratory Office for the Engineer......................................................................226.3 - Furniture and Equipment for the Engineer's Offices and for P.I.U. .....................22

    6.4 - General Requirements for Engineer's Offices..................................................... 236.5 - Communication Facilities for the Engineer .........................................................236.6 - Operatives for the Engineer's staff......................................................................24

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    5/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 5 of 349

    6.7 - Vehicles for the Engineer and for the P.I.U.........................................................246.8 - Miscellaneous Services for the Engineer and for the P.I.U.................................256.9 - Disbursement of Items supplied under Subclauses 6.1 to 6.8 ............................26

    7 - applicable standards 26

    APPENDIX 1 - Offices for the Engineer 27APPENDIX 2 - Furniture and Equipment for the Engineer and for P.I.U. 28

    APPENDIX 3 - Laboratory Equipment 30

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    6/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 6 of 349

    1 - GENERAL

    These Specifications are designed with the purpose of the works construction control for RoadsRehabilitation V Project, Lot D DN76, Deva Oradea, Contract 5R12.

    The Specifications are concerning items of works, materials and construction methods that aregenerally applicable to Romanian contracts for Roads and Bridges execution works.

    2 - LEGAL PROCEDURES AND LOCAL LEGISLATION

    2.1 - Legal provisions

    These Technical Specifications have been produced in compliance with both the specificlegislation in force in Romania applicable from time to time to each design phase of the Works, andthe provisions of the Romanian law ratifying the project FIFTH ROADS REHABILITATIONPROJECT EIB Loan 21.489, financed out by the European Investment Bank and RomanianGovernment, which regulates the rules and procedures to be followed for the procurement of works(i.e. type of procurement procedure, standard format of works contract, etc).

    The list of the legal provisions presented below is to be considered neither complete norexhaustive.

    o The Government Emergency Ordinance no. 159/20.11.2002 - published inRomanian Official Bulletin no. 862, dated 29 November 2002, regarding theratification of the Financing Agreement concluded between Romania and EuropeanInvestment Bank for the financing of the Fifth Roads Rehabilitation Project signedin Bucharest on 8 th March 2002

    o Law no. 37/1995 Environment protectiono Law no. 10 regarding the quality in the field of construction works published in

    Romanian Official Bulletin no. 12, dated 24 January 1995;o Law no. 137 regarding the environment protection published in Romanian Official

    Bulletin no. 304, dated 30 December 1995;o M.L.P.A.T Order no. 1743 for approval of methodological norms regarding the

    projects framework content on design phases of bidding documents, of tendersand contracts for investment performance published in Romanian Official Bulletinno. 232, dated 26 September 1995;

    o Romanian Government Decision no. 766/21.11.1997 for approval of someregulations regarding the quality in the field of construction works, published in

    Romanian Official Bulletin no. 352, dated 10 December 1997: approval of: regulations regarding the metrology activity in the field ofconstruction works;

    approval of: regulations regarding the quality assurance and management inthe field of construction works;

    approval of: regulations regarding the determination of importancecategories in the field of construction works;

    approval of: regulations regarding the supervision of behaviour duringoperation, of interventions and constructions post-operation;

    approval of: regulations regarding the technical agreement for new products,methods and equipments in the field of construction works;

    approval of: regulations regarding the conformity certification of the quality of

    products used in the construction field;o Romanian Government Decision no. 877 regarding the performance of laboratorytests and analyses by the suppliers of materials, construction elements andproducts only in authorized laboratories, published in Romanian Official Bulletin partI no. 538, dated 4 November 1999:

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    7/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 7 of 349

    o Romanian Government Decision no. 925 regarding the regulations for verificationand quality technical examination of designs, works performance and constructions,published in Romanian Official Bulletin no. 286, dated 12 December 1995;

    o Romanian Government Decision no. 261/08.06.1994 regarding the approval ofsome regulation in the field of construction works;

    o Romanian Government Decision no. 272 regarding the Quality State Control in thefield of construction works, published in Romanian Official Bulletin no. 193, dated 28July 1994:

    o Romanian Government Decision no. 273 regarding the approval of taking-overregulations for construction works and related installations published in RomanianOfficial Bulletin no. 193, dated 28 July 1994:

    o Romanian Government Decision no. 102 regarding the determination of theconditions for launching on the market of products for constructions, published inRomanian Official Bulletin no. 129, dated 27 February 2003:

    o Ministry of Transport Order no. 44 regarding the norms for environment protectionas a result of the road environment impact, published in Romanian Official Bulletinno. 138bis, Part I, dated 6 April 1997;

    o Ministry of Transport Order no. 48 regarding the norms for location and exploitationof ballast pits in the area of roads and bridges, published in Romanian OfficialBulletin no. 138bis, Part I, dated 6 April 1998;

    o Romanian Government Decision no. 393/15.07.1994 regarding the approval ofregulations for authorization and agreement of testing laboratories, published inRomanian Official Bulletin no. 200, dated 4 August 1984;

    o Ministry of Public Works and Territory Planning no. 31/N, dated 2 October 1995,regarding:

    procedure for authorization of testing laboratories for construction works; procedure for the audit of testing laboratories for construction works in order

    to obtain the authorization; procedure for certification of auditors for testing laboratories for construction

    works; instructions for preparation and implementation of a quality system in testing

    laboratories for construction works; instructions regarding the exigencies that the testing laboratories for

    constructions works have to comply with in order to obtain the authorization; procedure regarding the setting up and operation of the authorization

    committee for testing laboratories in construction works; procedure for certification of specialized personnel from testing laboratories

    for construction works and from quality control activity; instructions regarding the fill in of testing bulletins issued by testing

    laboratories for construction works.

    o Romanian Emergency Ordinance no. 60 regarding the public acquisitions, publishedin Romanian Official Bulletin Part I, no. 241, dated 11 May 2001

    If there are conflicts between the provisions of the Instructions to Bidders, the Bidding Data and theConditions of Contract, Parts I and II, and the provisions of this section, the provisions in the formerwill prevail.

    2.2 - Quality Assurance and Control System for Civil Engineering Works

    This clause refers to the general quality assurance system, as required by the Law No. 10/1995.As far as the construction works are concerned, the specific provisions for the quality of materials,plant and workmanship are detailed by the clause 7 of the General Conditions of Contract.Any contracts, subcontracts, instructions, approvals, etc. to be concluded or issued during theconstruction and defects liability period, shall comply with the above-mentioned Law No. 10/1995dated 24.01.1995.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    8/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 8 of 349

    The quality system applied to the civil engineering works is a set of organisational procedures,responsibilities, regulations and means to be implemented for achieving the required quality of civilengineering works during the design, construction, and defects liability period stages.

    The quality system applied to civil works shall consist of the following:

    a. civil engineering technical regulations, norms and standardsb. quality of materials applied for civil engineering works

    c. technical agreements or licences required for applying new procedures and using newproducts

    d. verification of design and workmanship as well as specialist examinations of design andconstruction works

    e. quality assurance and control management

    f. authorization and certification of laboratories where analyses and tests are performed forthe on-going construction works

    g. metrological activity related to the construction worksh. acceptance of construction works (provisional and final taking-over)

    i. behaviour of construction works during the defects liability period

    j. maintenance of the construction works

    k. quality state inspections of construction works.

    The products or materials with quality not certified at the time of delivery by a Quality Certificateissued by the producer and specifying their full compliance to the related requirements, shall not beused.

    The technical quality certificates issued for the new materials, procedures and equipment to be

    used for construction works shall also specify, under the current law, their application range, aswell as their manufacturing, transport, storage, placement and maintenance requirements, incompliance with the provisions of the HG. n. 766/97.

    Where a certain construction quality requirement is to be ensured in accordance with qualityspecifications, only the products, procedures, plant and equipment with technical agreements, shallbe used. The supervision of the execution of the construction works is mandatory and it isundertaken by a consultant entity called Engineer, nominated by the Employer, in the spirit of fullcompliance with the Conditions of Contract defining both the activity (supervision) and the entity(Engineer).

    Only technical experts and inspectors who are authorized through the law shall carry out thetechnical checking of drawings and respectively the technical supervision of the constructionworks.The laboratories envisaged to be used in performing the testing and trials activities imposedthrough the technical specifications shall be authorised in accordance with the Romanian Law.

    The measurement activity related to the construction works shall be developed in compliance withthe legal provisions regarding calibration, checking and operational reliability required for themeasuring and control devices used in this field.

    Technical assistance

    Considering the stipulations of Law 10/1995 regarding quality in constructions, the Designersobligations referring to the technical assistance that must be ensured on Site, during the worksexecution are as follows:

    a. In accordance with Law 10/1995, chapter III, section II, art.22, the Designer mustoperatively solve all non-conformities and irregularities, with reference to thedesigns produced by him.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    9/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 9 of 349

    b. The Designer must take part to all the quality controls on site, run in accordancewith the Program of Quality Control by the representatives of the State Inspectoratefor Constructions for all the Determinant Phases as defined.

    c. The Designer establishes how to treat the defects appeared in execution due to the

    defaults in design and monitors the implementation on site of the solutions adoptedin this respect.

    d. The Designer is involved in the Technical Book of Constructions compilation and inthe taking over procedures.

    2.3 - State Quality Inspection of Construction Works

    This clause describes the duties of the State Inspectorate responsible for the quality of Works, inaccordance with the law in force. The cost of these inspections will be borne by the Contractor, bythe payment of a specific governmental tax.

    The State Quality Inspections include quality systems and quality requirements application duringthe activities developed by the Employer for the design, construction and maintenance stages.

    The State Quality Inspections for construction works are carried by the "State Inspectorate inConstructions" which is responsible for the state control of the legal procedures adequately appliedto achieve the required quality of construction works.

    The State Quality Inspections of construction works shall be performed in compliance with the"Regulations for the State Quality Control of Construction Works" which stipulates the generalstandard requirements, their tasks, contents, organisational frame and methods applied for thestate quality control of construction works.

    The instructions included in these Regulations are compulsory for all the parties involved in the

    issuing the territory planning certificates, building permits, site location and for those responsiblefor the design, construction, and maintenance of civil engineering works.

    The provisions of these regulations are mandatory for all the Romanian and foreign companies,public units, central and local administrations, which, under the law, contribute to the constructionactivities or represent the Employer, or the Users of these construction works, regardless of thefinancial sources used for the works or the type of the ownership right.

    The "List of Romanian Standards and Norms for Roads and Bridges Design and ConstructionWorks, Inspections, Investigations and Laboratory Tests Specific for various Types of Works" islisted in the Technical Specifications Preamble. This list is only indicative and cannot beconsidered either complete or exhaustive.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    10/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 10 of 349

    3 - CONTRACTOR'S DUTIES

    3.1 - Maintenance of the Existing Road during Execution

    Summer maintenance

    In order to allow a normal traffic in the summer seasons, the Contractor shall undertake all theroads maintenance activities in accordance with the Norms in force for both the existing roads,during the execution of the Works and the Works during the Defects Liability Period.

    The N.A.R. Norm no. 554/2002 Norm regarding the public roads maintenance and repairingstipulates the works necessary to be undertaken. For the information purposes only, please findhereunder some of the main works to which the Norm 554/2002 relates, as:

    bituminous surface and cement concrete repairs, including patching of the surface, sealingof the joints and the cracks, etc.;

    shoulders reshaping for ensuring of the side drainage of the surface water; water drainage: cleaning of the ditches, of the fall chambers, of the footbridges, etc.;

    maintenance and replacement of the road safety equipments (guardrails, fencing,guideposts, portals, brackets, traffic signs, etc) and of the horizontal marking,

    all in accordance with Employers requirements.

    Winter maintenance

    In order to allow a normal traffic in the winter seasons, the Contractor shall undertake all the roadsmaintenance activities in accordance with the Norms in force for both the existing roads, during the

    execution of the Works, and the Works during the Defects Liability Period.The N.A.R.s Instruction no. 525/2000 Instruction regarding the public roads protection duringwinter season, preventing the slipping and snow covering stipulates the works necessary to beundertaken.

    Here are some of the main specific works to which the Instruction no. 525-2000 refers:

    The snow fences assembling in the places indicated by the D.R.D.P.;

    The snow evacuation from the road should be done with a set of equipment duringminimum 105 days of the year:

    o 1 grader;

    o 1 tractor grader;o 1 snow blower;

    o 1 dozer;

    o 1 loader;

    o 1 spreader for antiskid materials;

    The equipment should be accompanied by mechanics and equipment attendants asnecessary.

    The spreading of the antiskid materials during minimum 105 days on the year, usingpermanent equipment.

    The approximate quantities of antiskid materials for a winter season are as follows:

    o about 4 tons of salt per km;

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    11/348

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    12/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 12 of 349

    and whenever possible, temporary access shall be provided. In no case shall any access beclosed for more than twelve hours.

    Roads, accesses, rights of way which are being used by the Site traffic shall at all times be keptclean of dirt, mud and materials dropped from vehicles or from tyres.

    The Contractor shall provide, maintain and use suitable maintenance equipment.

    3.4 - Site Compound

    The Contractor shall find his own site or sites for setting up one or more compounds as temporaryworks, to which his offices, workshops, stores, plant, stockpiles, etc are to be placed, including theaccess to and from them. The sites shall be close to the land provided by the Employer and onwhich the Engineer's main office and laboratory are to be built-in.

    The Contractor will ensure the access and communication between his own and the Engineersworking places.

    On completion of the relevant section of the Works for which specific temporary works have beenprovided, the Contractor shall remove them, clean the site and carry out other works to return thesite to the original condition.

    The Contractor shall also identify his own areas for the location of collection and disposal of wasteand unnecessary materials, complying with the local regulations and procedures for transport anddisposal.

    The identification, arrangement and finally reinstatement to the initial grade of the land necessaryfor the borrow pits, depositing of the excavated material and any other kind or type of temporarywork required for ensuring the operation at the full designated capacity of the site organization andthe development of the project itself, is falling under the exclusive responsibility of the Contractor.

    The complete endowment of the site organization with the access ways, water supply, electricaland thermal energy, lighting, sanitation, etc., as required by the provisions of the Conditions ofContract falls under the direct and exclusive responsibility of the Contractor.

    The entire design for the establishment, arrangement for setting-up the site organization andreinstatement of the land shall be subject to the Engineers approval.

    In accordance with the provisions of the Ministry of Public Works Order no. 63/1998, the Contractorshall erect within 28 days after the Commencement of Works, the Project Identification Signs,subject to the Engineers approval. The Project Identification Signs shall be:

    - installed on locations instructed by the Engineer, at both ends of the project. For each locationa single faced signs shall be provided, both in Romanian and English;

    - manufactured in accordance with the above ordinance ;- dimensions of the board: 3 m height, 2 m width;

    - mounted on steel posts on concrete foundations at 1 m above the ground level;In accordance with the provisions of Ministry of Public Works Order no. 38/2000, the Contractorshall erect Commemorative Plaques in places instructed by the Engineer, at both ends of theProject and on the major bridges.

    3.5 - Temporary works

    The Contractor shall design, arrange, provide and remove at his own cost all Temporary Worksneeded in order to carry out the Permanent Works. The Temporary Works shall include theprovision of diversions of the road(s) as necessary. All temporary works shall be subject to theEngineers approval, but this shall not relieve the Contractor of his responsibility for their design

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    13/348

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    14/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 14 of 349

    3.9 - Utilities Relocation and Protection

    Whenever an existing over or under-ground utility/service carrying live main services is to bediverted in order to perform the Works, the Contractor shall arrange for these works to be carriedout by the owner of the services/utilities or by any authorised subcontractor under the supervision

    of the owner and in accordance with the specific laws, including the assurance of the technicalassistance from the designer in accordance with the Law no. 10/1995. The Contractor shall provideattendance as necessary and will be responsible for undertaking all measures to provide theprotection of such utility and for the consequences of damages that could appear.

    The Contractor will obtain prior approvals from the utilities owners/administrators and all therelevant authorities regarding such utilities not shown in the drawings and shall be responsible foragreeing the programme of the work and for paying any necessary costs and fees, when and asinstructed by the Engineer. For the utilities shown in the drawings, the prior approval is to beobtained by the Designer of the Works and provided to the Contractor before the start of the Workson Site, but the Contractor remain liable for agreeing the related programme of work and for payingany necessary costs and fees, when and as instructed by the Engineer.

    The final approvals from the utilities owners, both for the utilities shown or not shown in thedrawings have to be obtained by the Contractor as follows:

    The utilities owners/administrators issue a prior approval necessary for the Employer to obtainthe Construction License for the Works. The prior approvals usually impose a series oftechnical requirements, according to the specific legislation, which regulates the utilitiesoperation under the new condition of the road. The prior approvals also usually specify that thefinal approval must be obtained before the start of the Works.

    The owners of the utilities issue the final approval usually after the formal approval bythemselves of the relocation/protection working drawings. The relocation/protection designsshall be correlated with the final Working Drawings of the Works.

    The Contractor is entitled to recover the cost of the design and execution for the utilities notshown in the drawings and the cost of all necessary permits, licenses and approvals requiredby the law as a prerequisite condition for the execution of relocation/protection of the utilitiesshown or not in the drawings, from the related items provided for in the Bill of Quantities.

    The execution of the utilities works shall be performed only by specialized companies agreedby the owners/administrators, based on the designs and technical specifications approved asmentioned above and with the necessary specialised technical assistance provided for underthe Law no. 10/1995.

    Whenever during the execution of the Works the Contractor discovers utilities to be removed orprotected not shown in the drawings, he shall immediately notify the Engineer and the Employer.

    In case that there is no need for the utilities to be diverted, it shall be the Contractor's responsibilityto maintain and protect them while working in their vicinity, all with the approval of the utilitiesowners/administrators and the Engineer.

    The Contractor shall inform immediately the relevant authorities in the event of any damageproduced to the public or private utilities shown on the drawings and shall perform the necessaryrepairs at his own cost.

    The responsibilities of the Contractor described hereunder will last until the end of the DefectLiability Period.

    3.10 - Safeguarding the Environment

    The Contractor shall execute all the works and take any measures for the environmental protectionand impact mitigation, during the construction period and the Defect Liability Period, in fullcompliance with the relevant local legislation and regulations in force. He shall obtain from theRelevant Environment Agencies, all the necessary updated information and all the required permits

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    15/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 15 of 349

    and shall carry out in this respect any complementary studies whenever necessary. He shall obtainenvironmental approvals for all the temporary works.

    During the construction period, including the Defects Liability Period, the Contractor and his Sub-contractors, in full compliance with the norms and regulations in force in Romania, shall implementall necessary environmental mitigation measures aiming to:

    ensure the reduction of the Equipment and Plant noise when working in urban or rural areasand in the proximity of occupied buildings;

    minimise the Plant and Equipment adverse impact on the natural, human and socialenvironments, including the locations for crushers, bitumen plants, batching plants and othersimilar plants;

    minimise the effect of the site traffic and to safeguard the public and the Contractor's workforce, including the enforcement of an adequate Traffic Management Plan;

    protect the rivers, lakes, lands in crop and any areas surrounding the Site, against any kind ofpollution, which may be originated either from the permanent road works or from other

    activities, related to the Contractor's operations on Site; ensure a strict observance of the standards and specifications in defining, applying and

    controlling the methods of stockpiling and handling the materials, especially those mostsensitive such as fuel, bitumen, lubricants, cement, explosive, etc.;

    protect and accurately reinstate, at the end of the works, the land used for the borrow pits,quarries, services and diversion roads, and for any temporary or preparatory work;

    provide, install and test for proper operation the specific equipment required for the propermonitoring of all kind of pollution factors such as noise, gas, dust, liquids, etc., deriving fromthe Site activities;

    reduce the pollutants emissions, under the admissible levels, in accordance with theRomanian current legislation and norms;

    prevent any pollution to the land and the underground waters, the biodegradable materials andresidues shall be carefully storied, by types, in containers or on platforms in locations approvedby the Engineer and the local Environmental Agency, and consequently properly eliminatedunder due security conditions;

    maintain all the time a clean and proper environment in performing the Works, inclusive by anefficient and in time watering of all the affected areas of land or establishments (access roads,platforms, etc.);

    ensure a continuously and in-real-time determination of the following indices: NOx, SOx, CO,heavy metals, particle in suspension, deposited dust, etc. In this respect, a proper equipment

    shall be procured and installed on the location instructed by the Engineer, including theprovision and use of the adequate software for gathering, analysis and interpretation of theregistered data;

    monitor the water level variation within the area of the Works, by constructing a 3 hydro-geological observation wells with minimal depth of 20 m in the locations instructed by theEngineer;

    ensure a proper and adequate completion and maintenance of the Works, through gatheringof witness samples from the points instructed by the Engineer in order to determine the qualityof the environment (air, water, soil, vegetation);

    take any other action, as instructed by the Engineer and as required by the current Romanian

    legislation. (Law No. 137/dated 30.12.1995).Upon the Engineers instruction, the Contractor shall carry out any environmental measurements todemonstrate that the requirements of this Clause are met. The tests shall be carried out at the

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    16/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 16 of 349

    locations and at the time instructed by the Engineer. The Contractor shall carry out such tests athis own expenses with instruments supplied by him.

    The outcome of all the above will be subject to a distinctive section in the Contractors monthlyReport.

    3.11 - Traffic Management

    Within two weeks of the date of Commencement of the Works, the Contractor shall inform theEngineer in writing the name of a fully qualified person responsible for the compliance with thisClause.

    The Contractor shall submit to the Engineer for approval a Traffic Management Plan describinghow he intends to minimise the impact of the construction activities on the public road circulation.The Traffic Management Plan shall be preliminarily submitted for its approval to all the relevantauthorities (Police Department, Employer's local branch, etc.). The Traffic Management Plan shallinclude all the details and information as necessitated by the Works or as the Engineer may

    require. Throughout the execution of the Works and the remedying of any defects therein, theContractor shall shall:

    have full regard for the safety of all persons on Site or unauthorised and keep the Site (so faras the same is under his control) as well as the Works (so far as the same are not completedor occupied by the Employer) in an appropriate state to avoid any danger to all persons; and

    provide and maintain, at his own cost, all lights, barriers and warning signs, when and wherenecessary or when required by the Engineer for the protection of the Works or for the safetyand convenience of the public or others.

    The structure of the document will contain at least the following information:

    o temporary signing of the works performed on the public road, including details of theprinciples of temporary road signing;

    o classification and features of the road signs and ancillary means for works signing;

    o installation/dismantling of road temporary signing, including night and emergency signing;

    o alternating circulation;

    o temporary marking;

    o signing of the vehicles that take part in works execution;

    o protection of personnel;

    o traffic lighting, including calculation sheets;

    o duties and responsibilities of the persons involved in the traffic safety;The Contractor shall manufacture, install and maintain the Contract Identification Boards asrequired by the Ministry of Public Works Order no. 63/N 11.08.98.

    The location, dimensions and content of the Contract Identification Boards shall be subject toEngineers approval.

    Approval of request for setting up of traffic restrictions

    Periodically and based on the provisions of the Traffic Management Plan, requests for setting up oftraffic restrictions are presented to the Engineer in accordance with the Works progress from therevised and up-dated Updated Program of Works, according to Sub-Clause 8.3 of General andParticular Conditions of Contract:

    The documents attached to the request are the followings:

    o the request for the related road sectors;

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    17/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 17 of 349

    o the approval of the Police County Inspectorate and National Roads Local Department;

    o traffic designs (schemes) related to the restrictions;

    o calculation and annexes, if necessary.

    The Employer issues the approval for setting up of traffic restrictions for the requested time periodand the involved road sectors.

    Where the circumstances of any particular case are not described in the Traffic Management Plan,the Contractor shall submit proposals for dealing with such situations to the Engineers approval.Compliance with the foregoing shall not relieve the Contractor of any of his other obligations andliabilities under the Contract.

    The Contractor shall not commence any work that affects the public roads until all traffic safetymeasures necessitated by the work are fully operational. The traffic signs, road markings, lamps,barriers and traffic control signals shall be in accordance with the requirements applicable at thedate of the execution of the Works (Common instructions issued by Ministry of Public Works,Transport and Housing and Ministry of Internal Affairs regarding Methodological norms concerning

    the conditions for traffic closing in order to perform works in the area of the road and/or to protectthe road published in Romanian Official Bulletin no. 397, dated 24 August 2000).

    The Contractor shall keep clean and readable at all times all traffic sign, road markings, lamps,barriers and traffic control signals and shall position, re-position, cover or remove them asnecessitated by the progress of the Works.

    Roads, accesses, rights of way, etc. which are being used by the site traffic shall at all times bekept clean of all dirty, mud and material dropped from vehicles or from tyres arising from such use.The Contractor shall provide, maintain and use suitable equipment for this purpose. In carrying outthe Works, the Contractor shall ensure that all road drains, ditches and grips shall be kept clear ofany spoil, mud, slurry, or other materials likely to impede the free flow of water.

    3.12 - Works done Off Site.

    When major components of the Works are manufactured outside the Site, the Contractor shallmake the necessary arrangements to allow the Engineer to inspect the works during the wholeperiod of manufacture.

    The Contractor shall give to the Engineer written notice of the workshops and places where worksis being, or is about to be, done or from which materials of manufactured articles are about to be orare being supplied. He shall also give such notice and keep the Engineer advised of the timeswhen such materials will be ready to be inspected, so that such inspection may take place withoutdelaying the delivery of the materials to the site. Such notices shall be given at such times to

    permit the inspection of the whole of the work at all stages of the processes of manufacture.

    3.13 - Other Contractors

    The Contractor is advised that other Contractors employed by the Employer and employees of theEmployer may be working on and around the Site. The Contractor shall liase with the Employerand shall plan and execute the Works for mutual convenience and ensure satisfactory progress ofthe Works.

    The Contractor and his subcontractors shall not interfere with any works whether the property ofthe Employer or of a third party, except where such interference is specifically described as part ofthe Works either in the Contract or in an instruction issued by the Engineer. The Contractor shallbe held responsible for any loss or damage thereto if caused by him.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    18/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 18 of 349

    3.14 - Documents to be submitted to the Engineer

    At specified intervals specified, the Contractor shall supply to the Engineer updates / revision of thefollowing documents:

    Program of Works;

    Cash Flow;

    List of Labour, Plant and Equipment.

    The Program of Works (Critical Path Method) to be provided under the Conditions of Contract shallbe submitted in the form of a Time-Location Chart clearly indicating the phasing of all the Work.Plant and labour resource teams shall be listed for all operations.

    The Program shall be revised at the intervals specified in the Contract or as requested by theEngineer, following any major variation or extension of time granted, or when any critical operationhas fallen behind its planned duration by more than 10 per cent.

    Along with the revised version of the Program of Works, the related Cash Flow shall be submittedto the Engineer.The Contractor shall submit to the Engineer at the end of each calendar month, or at such othertimes as may be agreed, detailed schedules and reports on the progress of works in the month inquestion of the plant, equipment and labour engaged on Site, divided into categories, detailed asthe Engineer may reasonably request, showing separately the Contractor's and each sub-contractor's labour, equipment and plant. As far as the equipment and plant are concerned, thecondition of each item shall be indicated in the schedules.

    3.15 - As Built Drawings

    The Contractor shall keep records as the Works proceed to enable him to mark up a set of As BuiltDrawings during construction. These As Built Drawings shall be made available for inspection fromtime to time by the Engineer.

    On completion of the works and not more than 90 days after the issue of Taking Over Certificate,the Contractor shall submit to the Engineers approval two sets of As Built Drawings (hard copy)and one set of As Built Drawings on electronic format covering the complete construction of theWorks. The As-Built-Drawings shall be accompanied by all records taken during the construction ofthe works.

    3.16 - Clearing and disposal of Unexploded Ammunition

    Before the Commencement of works, the Contractor submits his proposal for a subcontractor,properly authorized to perform the clearing of unexploded ammunition.

    The area from where the unexploded ammunition will be removed is settled based on the projectslayout considering the width of the construction limits with additional 7 m on both sides. Theremoval of the unexploded ammunition is performed on a depth of minimum 1 m below the bottomof the construction (sub-grade, foundation etc.).

    3.17 - Erection of site identification boards

    Within 28 days of the Commencement Date the Contractor shall supply and erect two projectidentification boards, one at each end of the Site. The signboards, 3m high and 2m wide made ofaluminium, shall be installed on steel poles on concrete foundations. The lower end of thesignboard shall be 1m above ground level. Details on format, content and location shall beprovided by the Engineer.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    19/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 19 of 349

    4 - QUALITY ASSURANCE AND CONTROL

    4.1 - Quality Assurance Management System

    Within 60 days of the Letter of Acceptance, the Contractor shall prepare and submit to theEngineer a written Quality Assurance Management System similar to that described in ISO 9000series. This shall show the Contractor's Site organisation and responsibilities for all members ofthe Contractor's organisation to check and report on the quality of materials and workmanship. Itshall also show the procedures for communication with the Engineer.

    The Contractor's Quality Assurance Management System shall comply with the provisions of theLaw No.10/95.

    The Contractor shall be wholly responsible for ensuring that the quality of all materials andworkmanship is in accordance with the Technical Specifications.

    The Contractor shall carry out his own inspection of materials and workmanship and satisfy himselfthat they meet the Specification before submitting them to the Engineer for certification.The Engineer shall issue Non-Conformity Notices if any work, material, workmanship or any otherthing is not in accordance with the Contract. Until such non-conformity notice is rescinded, theEngineer shall not certify any payment for the work or item affected.

    The Contractor shall, within 28 days of the Letter of Acceptance, submit to the Engineers consentthe names, CVs and duties of all key personnel.

    4.2 - Specifications and Standards

    The Contractor shall comply with the provisions of the Romanian Standards, Specifications andNormas, including the additions and amendments in force 28 days prior to the latest date forsubmission of the tender.

    In case of a discrepancy between the provisions of the Technical Specification and the Standardsin force, the Engineer will issue the necessary clarification.

    Upon the Engineers instruction, the Contractor shall provide specialised publications such as:FIDIC and ICC books and publications, ISO Collections and Guides, roads and bridges specialtybooks, standards, norms, magazines, etc.

    4.3 - Site Laboratory

    The Contractor shall provide, subject to Engineers consent, a building to form the Site Laboratoryfor carrying out sampling and testing as required by the Technical Specification. The laboratoryshall be located within the limits of the Site or close to it.

    The size and layout of the laboratory shall be suitable to carry out all sampling and testing ofmaterials and workmanship. It shall contain special storage rooms for samples of materials, etc.,as agreed with the Engineer.

    The laboratory shall be set up in accordance with the MLPAT Order No. 31/N/I995 and shall obtainthe required accreditation from the State Inspectorate. The Contractor shall provide the equipmentand consumables necessary for carrying out the sampling, testing and recording as required by theTechnical Specification and additional numbers of tests as instructed or carried out by the

    Engineer. The minimal list of the laboratory equipment is presented in Appendix A.3 hereunder.The list is not exhaustive. The Contractor is responsibility to provide any other necessary items ofequipment to ensure the proper performance of the activities in the laboratory. The testingequipment shall be new and maintained in a clean and serviceable state and shall be checkedand/or calibrated at required intervals or when instructed by the Engineer.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    20/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 20 of 349

    The Contractor shall staff the laboratory with a fully qualified engineer (Chief of Laboratory) andqualified technicians fully experienced and properly authorized in testing the materials. Thesampling and testing shall be supported by an adequate number of laboratory and field labourers.

    The Contractor shall provide mobile facilities for sampling and testing carried out in the field, at thelocation of Works.

    The laboratory shall be maintained in a clean and tidy condition to the satisfaction of the Engineer.

    The laboratory shall be completed and ready for use within 12 weeks of the Commencement Date.If the Contractor commences any selection or testing of materials for submission to the Engineerfor approval of any permanent works before the 12 weeks period, temporary testing facilities,subject to Engineera approval, may be used.

    The Contractor shall assist the Engineer to carry out tests for the Contract using the equipment,consumables, etc., or to carry out supplementary tests as instructed by the Engineer.

    4.4 - Sampling, Testing, Trials and Method Statements

    The sampling and testing shall be in accordance with the relevant Standard Specification, with thisSpecification and with the applicable regulation.

    Before placing orders for materials for incorporation in the Works, the Contractor shall submitcomplete information to the Engineer. This information should include the name of the supplier, theorigin of the material, manufacturer's specification, quality, description, together with details ofmaterials. The Contractor shall deposit the samples of such materials when requested and whereappropriate.

    The Contractor shall supply Method Statements describing the sequence, materials and otherrelevant details for all key activities or for any other activities requested by Engineer. TheContractor shall not start any works prior to obtain Engineers approval for the relevant methodstatement.The Contractor shall carry out trials of all concrete or asphalt mixes showing by tests that theconstituent materials and the resulting mixture comply with the Technical Specification.

    During the construction period, upon Engineers instruction, the Contractor shall repeat any tests inhis own laboratory or in a laboratory nominated by the Engineer.

    At the completion of the Works (before the Taking Over) and at the end of the Defects LiabilityPeriod, the Contractor shall carry out the following measurements and tests:

    - evenness measurements by APL equipment;

    - roughness measurements by GRIPTESTER equipment;

    - bearing capacity measurements;- finished surface evaluation and non-conformities by DEGY equipment.

    4.5 - Alternative Materials

    The Contractor may apply for using alternative materials. In such cases, the Contractor shallsubmit his technical proposal to the Engineers approval at least 4 weeks before the material is tobe used, or longer if such longer period is required for testing of the material. The use of alternativematerials is allowed only with the Engineer's approval (given after due consideration of theRomanian regulations.

    4.6 - Engineer's approval of the Works

    No works shall commence until the Engineer's written approval has been given.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    21/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 21 of 349

    For Site inspections and approval of the Works, the Contractor shall give adequate notice in writingto the Engineer. Where no period of notice is stated in the Contract, such notice shall be not lessthan 8 hours of normal working time, before the Work is ready for inspection. The forms provided inthe QAMS shall be used.

    This will not release the Contractor from any of his obligations or responsibilities under theContract.The Engineer shall require reasonable time during normal working hours to carry out hisinspection.

    For off-site works, the Contractor shall give the Engineer at least 7 days notice in writing statingwhen such works are due to commence.

    5 - SURVEY

    5.1 - Existing Ground and Road Levels

    The Contractor shall satisfy himself that the existing ground and road levels as indicated in theDesign are correct. Should the Contractor wish to dispute any levels he shall submit to theEngineer a schedule of the position of the levels considered to be in error and a set of revisedlevels. The existing ground relevant to the dispute levels shall not be disturbed before theEngineer's decision as to the correct levels is given.

    In case of foundation works or where the Engineer considers it necessary, the Contractor shall,before the surface of any portion of the ground is disturbed or the work is put in hand, inconjunction with the Engineer examine the Site and the plants and sections of the work and takesuch additional levels or other measurements as may be necessary, and shall agree as to thesurface levels, etc., with the Engineer. Such agreement shall be recorded in writing, and shall formthe basis of the measurement of the Works.

    5.2 - Survey and Setting Out

    The Contractor shall, within 8 weeks of the Date of Commencement, check the permanentbenchmarks upon which the design of the Works has been based, and if any discrepancies arefound, the Contractor shall inform the Engineer in writing and the appropriate solution should befound. He shall also establish temporary benchmarks adjacent to each bridge site and atintermediate points. The benchmarks will be located within 60 m. of the Site and the agreed valueof each shall be legibly recorded thereon. The Contractor shall correlate the levels with those onadjacent contracts.The Contractor shall, as soon as practicable, submit to the Engineer the data concerning thereference pegs and temporary benchmarks and shall keep such records up to date by formalnotice to the Engineer. All pegs shall be painted in distinguished colours.

    The Contractor shall do everything necessary to facilitate any checking which the Engineer maycarry out.

    The Contractor shall supply all instruments and equipment new for the use within 4 weeks from theCommencement Date.

    The Contractor shall provide and maintain, for the exclusive use of the Engineer during the periodof execution of the Works, all surveying equipment, pegs and tools as described in the Bill ofQuantities. All equipment shall be kept in accurate working order during the period of the Contractand shall be replaced if reported to the Contractor as being inaccurate or unsatisfactory.

    Where the case may be, patterns will be used to indicate the slope gradient and the changingpoints of the gradient.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    22/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 22 of 349

    All survey reference pegs shall be carefully preserved except where construction requires theirremoval, and before such removal the Engineer shall be notified accordingly.

    At each bridge crossing, the Contractor shall establish reference pegs to indicate the intersectionof the centre line of the road and the centre line of the bridge and shall preserve such pegs insimilar manner to other reference pegs.

    Where centre lines have been fixed and running chainage established, reference pegs shall beplaced in protected places at every 100 m. The pegs will be placed perpendicular to the centre line.

    6 - FACILITIES, SERVICES and EQUIPMENT for the ENGINEERand for PROJECT IMPLEMENTATION UNIT (P.I.U.)

    6.1 - Engineer's Main Office

    The Contractor shall provide offices for the Engineer as detailed in Appendix A1. The EngineersOffice shall be made available within four weeks of the Commencement Date. It shall be locatedclose to the Site and to the Contractors Site Office. The location, design and arrangements for thepermanent office shall be subject to the Engineers approval.

    If no permanent office can be made available within four weeks of the Commencement Date, theContractor shall provide temporary facilities until the permanent office can be made available. Thetemporary facilities shall be similar to the permanent office and shall be subject to the Engineersapproval.

    The office shall be provided with furnishings, fittings and equipment, all subject to the Engineersapproval, as specified in Clause 6.5, Clause 6.6 and Appendix A2.

    The water supply, sanitary arrangements, heating and lighting for the office shall be provided andmaintained by the Contractor in accordance with the requirements of Clause 6.5.

    The office and the access thereto shall be properly maintained by the Contractor in accordancewith the requirements of Clause 6.5. until the end of the Defects Liability Period.

    6.2 - Laboratory Office for the Engineer

    The Contractor shall provide a laboratory office for the Engineer as detailed in Appendix A.1, withinthe laboratory specified in Clause 4.3.

    The laboratory office shall be provided with furnishings, fittings and equipment, all subject to the

    Engineers approval, as specified in Clause 6.5, Clause 6.6 and Appendix A.2.The water supply, sanitary arrangements, heating and lighting for the laboratory office shall beprovided and maintained by the Contractor in accordance with the requirements of Clause 6.5.

    The laboratory office shall be completed and ready for occupation and use by the Engineer at thesame time as the laboratory.

    6.3 - Furniture and Equipment for the Engineer's Offices and for P.I.U.

    The Contractor shall supply new furniture and new equipment of good quality suitable for hard andprolonged use, as required by the Engineer.

    The lists given in Appendix A.1 and Appendix A.2 of the Specification General Items areindicative of the requirements. The Engineer may make alterations when the Contractor'sorganisation, methodology and the location and layout of new buildings are known.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    23/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 23 of 349

    The computer software shall be in English language; separate software licensed packages shall beprovided for each computer. The Contractor shall supply adequate electronic supports (floppy disk,CDR, CDRW, DVD, DVDRW, backup cartridges), as well as printings and plotting facilities andconsumables. The Contractor shall also supply a complete set of operating instruction manuals, inEnglish, for all hardware and software.

    A local network with internet access shall be installed. All computers in the office shall beconnected to the network.

    The Contractor shall insure all items against loss and damage.

    6.4 - General Requirements for Engineer's Offices

    All buildings shall be insulated and weatherproof suitable for the climate. All windows shall bedouble-glazed and have rolling blind and curtains. Entrances shall be provided with two sets ofdoors. Natural lighting and ventilation shall be provided to each room but adequate electricallighting shall be provided. Every room shall be provided with at least three earthed electric power

    sockets, with a maximum total supply of 4 kilowatt per room;Each room shall be provided with a through-the-wall heating/cooling air conditioning unit suitable tomaintain an internal temperature of about 21 C whatever the external temperature might be.

    Ceiling heights shall be at least 2.8 metres.

    Each kitchen shall be equipped with a sink, base and wall cupboards, a 180 litre refrigerator and atwo ring electric hotplate. Wash-hand basins, showers and kitchen sinks shall be continuouslyprovided with hot and cold water.

    The Contractor shall properly clean and maintain the offices as long as the Engineer requires use.

    The Contractor shall carry out the repairs to the buildings, their contents and services, and to the

    equipment as soon as the need arises.The Contractor shall make all arrangements, and pay all necessary charges, for the continuousprovision and maintenance of the following services, until the offices are no longer required by theEngineer:

    electricity for power and lighting;

    air conditioning and heating;

    fresh drinking water;

    hot water;

    disposal of sewage and waste water;

    disposal of solid waste;

    international telephone and fax lines.

    6.5 - Communication Facilities for the Engineer

    The Contractor shall provide the Engineer with 1 (one) international direct line for telephone andfax at the Main Office. In addition, the Contractor shall also provide 2 (two) national telephone lineswith internet connections at the Main and Laboratory offices, with fax facilities at the Main Office.

    The Contractor shall provide to the Engineer 2 (two) new GSM mobile phones with international

    access and 8 (eight) new GSM mobile phones with local access - model and brand as approved bythe Engineer.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    24/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 24 of 349

    The Contractor shall allow for all purchasing, rental, servicing, subscriptions costs or fees andmaintenance. The charges for use of the telephone fax facilities and mobile phones shall be paidby the Contractor but reimbursed at invoice cost by the Employer.

    Telephone, internet connections and fax facilities shall be available contemporary to the offices inwhich they are located; the mobile phones shall be provided within 14 days of the CommencementDate.

    6.6 - Operatives for the Engineer's staff

    The Contractor shall provide to the Engineer with such assistance as he shall reasonably require.

    The Contractor shall provide skilled personnel for the tasks required, and maintain continuity ofemployment. Chainmen shall be experienced in assisting the Engineer in survey work. Laboratoryhandymen shall be capable to assist the Engineer with routine tasks in the Laboratory.

    Chainmen, drivers and laboratory handymen shall have valid driving licenses and drivingexperience suitable for the vehicles to be provided.

    6.7 - Vehicles for the Engineer and for the P.I.U

    The Contractor shall provide the Engineer and the P.I.U. with new vehicles as detailed bellow andin the appropriate items of the Bill of Quantities for the exclusive use of the Engineer and otherpersons authorised by the Engineer including the Employer, at all times, including the days off andweekends.

    The vehicles shall be licensed and comprehensively insured for use on the public roads by anylicensed driver authorised by the Engineer. The insurance cover shall extend to liability to thirdparties arising from accidents involving the vehicles used by the Employer or the Engineer. TheContractor shall provide fuel, oil and maintenance (including replacing defective parts, tyres, etc,whenever required), arrange the service and legal technical checking in accordance with theRomanian Law (and obtain the appropriate certificate). The vehicles shall be provided as soon aspracticable after receipt of an appropriate instruction from the Engineer, and shall be fuelled, oiledand maintained as aforesaid until the end of the Defects Liability Period, unless released earlier atthe direction of the Engineer.

    Each of the vehicles shall be fitted with a fire extinguisher, first aid kit, tow rope, tool kit, wheelwrench, jack and handle, tyre pump, spade, torch, etc. One battery charging unit shall be providedfor the Engineers use.

    The Contractor shall provide a similar replacement for any of the vehicles out of service for morethan twenty four hours, and shall also replace any vehicle by a similar new vehicle after it hascompleted 100,000 km if, in the opinion of the Employer or the Engineer, such vehicle cannot bemaintained in a satisfactory condition.

    The Contractor shall arrange for and pay all costs, custom fees, charges, and any other taxes etc.,in providing on site and maintaining the vehicles for the Engineer and for the P.I.U.

    The Contractor, at his cost, shall fuel the Engineer's vehicles without withdrawing their availabilityto the Engineer.

    The Contractor shall pay all costs, fees, charges, etc., in providing and maintaining the vehicles forthe Engineer and for the P.I.U.

    The vehicles for the Employer and Engineer shall be new and similar in size, quality andperformance as specified bellow:

    4 wheel drive, 5 doors, 2500 TDi, EURO 4 emission class, air conditioning, ABS, ESP, SLS,ACE, solar protection windows;

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    25/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 25 of 349

    4 wheel drive, 5 doors, 2000 TDi, EURO 4 emission class, air conditioning, ABS, ESP, SLS,ACE, solar protection windows;

    4 wheel drive, 5 doors, 1600 TDi, EURO 4 emission class, air conditioning, ABS, ESP, SLS,ACE, solar protection windows;

    The vehicles shall be supplied within 12 weeks of the Letter of Acceptance or such later time asinstructed by the Engineer.

    The Contractor shall provide the Engineer, as and when required, with the services, of drivers forthe Engineer's vehicles. These drivers shall also carry out general duties as requested by theEngineer.

    6.8 - Miscellaneous Services for the Engineer and for the P.I.U.

    The Contractor shall supply all necessary stationary and consumables (paper for photocopier,plotter and printer, pens and inks for plotter, toner for photocopier, CDR, CDRW, DVD, DVDRW,printer cartridges, notebooks, pads of writing paper, file holders, lever arch file, ball pens, pencils,erasers, staplers, and staples, punches, clips, adhesive tape, marking pens, wipers, etc.) for theEngineer's staff in the offices and for the Employer as instructed by the Engineer.

    The Contractor shall ensure at all times the necessary quantities for a reasonable consumption ofcoffee, tea, sugar, mineral water and other items as instructed by the Engineer.

    The Contractor shall provide the Engineer with a Digital Video Camera and two DigitalPhotographic Camera and all the necessary accessories for carrying, standing, processing andprinting, including extra memory, as described in the Appendix A.2.

    The Contractor shall arrange to take full colour record photographs of the Works as the Engineershall direct. Each month, the Contractor shall deliver to the Engineer the digital format of thephotographs and four printed sets, each set up to 40 photographs. All photographs shall benumbered and retained on the Site; on completion of the Works the digital format and onecomplete set of all the photographs shall become the property of the Employer. The copyrights ofall photographs shall be vested with the Employer.

    The Contractor shall provide the Engineer with safety helmets, reflective jackets, reflectiveweatherproof suits, warm outer coats, waterproof safety boots and other protective clothing innumber and size instructed by the Engineer.

    The Contractor shall provide and maintain a full set of surveying instruments, all new, for theexclusive use of the Engineer. The set of surveying instruments shall consist of the following:

    - Total Station with sighting targets 1 set;

    - ranging rods;

    - automatic level 1 piece;

    - metric level staff 2 pieces;

    - walkie-talkie equipment 1 set;

    - 30m tape 1 piece;

    - 50m tape 1 piece;

    - 5m tape 10 pieces.

    All necessary consumables shall be provided to the Engineer as required, among which: pegs,hammers, nails, torches, sunshade, etc.

    Based on the Engineers request, the Contractor shall provide the Engineer with topographicassistance. The Contractor shall provide personnel for the requested tasks and shall ensure acontinuous presence of the personnel on site (including overtime and weekends). The topographicworkers will have relevant experience to be able to assist the Engineer in land survey works.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    26/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 26 of 349

    6.9 - Disbursement of Items supplied under Subclauses 6.1 to 6.8

    It should be noted that on final completion of the Contract and expiry of the Defects Liabilty Periodthat all buildings, equipement, vehicles and furniture detailed in Subclauses 6.1 to 6.8 will remainthe property of the Contractor.

    7 - APPLICABLE STANDARDS

    The Tenderers must observe all the requirements of the legislation, regulations, technical normsand standards concerning the Scope of the Works, in force in Romania at the date 28 days beforethe deadline for submission of the tender.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    27/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 27 of 349

    APPENDIX 1

    Main Office for the EngineerLaboratory Office for the Engineer

    Description Unit Main Office Laboratory Office

    Rooms > 16 m 2 number 8 2 Minimal total surface Sq.m. 135 25 Toilets number 2 1 Sinks number 2 1 Shower number 1 1 Kitchen number 1 1

    Storage room number 1 1 Meeting room > 25 m 2 number 1 - Parking platform - concrete Places 6 2

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    28/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 28 of 349

    APPENDIX 2

    Furniture and Equipment for the Engineer and for P.I.U.

    ItemMainOffice

    LaboratoryOffice P.I.U.

    Through the wall air conditioning units 8 2 -Desks (1.8m x 0.9m) with lockable cabinet (3 drawers) 10 2 -Padded high back swivel chairs for desks 10 2 -Desk (1.8m x 0.9m) 6 2 -Lockable filling cabinets (3 drawers) 6 2 -Chairs with padded seats 6 2 -Meeting room table (4.0m x 1.6m) 1 - -Meeting room chairs 10 - -Drawing tools set 1 - -Shelf units (1.8m x 0.3m) 10 4 -Cupboard (1.8m x 0.9m) with 3 shelves and lock 5 1 -Wall notice pin board (2m x 1.2m) 10 1 -PC Intel Core 2 Duo 2.4 GHz computer, Intel DG965RY mainboard,1 GB 533 MHz DDR2 RAM, 250 GB 7200 rot/min HDD, DVD RWDouble layer, video-card GeForce4 256 MB DDR, media cardreader, Logitech cordless keyboard and mouse, internet andnetwork cards;LCD 19 screen;Software: Windows XP Professional

    MSOffice XP ProfessionalAUTO CAD latest version

    7 1 2

    Laptop HP 17 display, Intel Core 2 Duo 2.4 GHz, 1 GB 667 MHzDDR2 RAM, 100 GB HDD, DVD RW Double layer, media cardreader, internet and network cards;Software: Windows XP Professional

    MSOffice XP ProfessionalAUTO CAD latest version

    1 - -

    Network Color Laser printer (A3/A4) with scanning/copy facility 1 - -Color DeskJet Printer A4 format 7 - 2UPS (Uninterrupted Power Supply) 7 - -Local network for computers and printers 1 - -Primavera Project Planner P3, including training, service andupgrading 1 - 1

    Digital video camera: min. 10 Mega pixels, large colour display,mini DVD and card recording, steady Shot, audio/video input,incorporated light, night shot;lens extension, UV external filter, tripod stand, case

    1 -

    Digital Photo camera: min 10 Mega pixels, large colour display,incorporated light, night shot;lens extension, UV external filter, tripod stand, case

    1 1 -

    Colour A4 Scanner 1 - -Heavy duty comb binder and punch 2 1 -Paper shredder 1 -Refrigerator (180 liter) 1 1 -Waste bins 10 2 -

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    29/348

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    30/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 30 of 349

    APPENDIX 3

    Laboratory Equipment (minimal list)

    Nr. crt. Description Quantity1 Laboratory oven 100 l 12 Laboratory oven 220 l 23 Analytical balance: sensitivity 0.01g, weight 500-600g 14 Analytical balance: sensitivity 0.1g, weight 10,000g 15 Analytical balance: sensitivity 0.1-1g, weight 30,000g 16 Pharmaceutical balance precision 0.01 g 17 Hydrostatic balance 18 Platform scale 100 kg 19 Hot plate 20-30 cm 2

    10 Gas oven 211 Sieve set for soils (see SR-EN 933-2/1998) 112 Sieve set for aggregates (see SR-EN 933-2/1998) 113 Sieve set for concrete (see SR-EN 933-2/1998) 114 Sieve set for mixtures (see SR-EN 933-2/1998) 115 Sieves shaker 116 Aggregate sample splitter 117 Extruder 118 Desiccators 219 Compression testing machine for concrete max. 2000 KN 120 Room thermometer 221 Outdoor thermometers 222 Digital thermometer for asphalt, concrete etc. 423 Rain gauge 124 Core drilling machine 125 Los Angeles machine 126 Methylene blue test set 127 Pichnometers 228 Unit weigth measures to measure the density 529 Aggregate shape gauge (determination of shape factor) 130 Scoop 131 Slump test set 332 Vibrating table 133 Concrete mixer 134 Testing moulds (15 x 15 x 15) 135 Water tank with thermostat 136 Curing room vaporiser with temperature control 137 Mortar mixer 138 Jolting apparatus 139 Vicat apparatus + consistency plunger 140 Le Chatelier rings 141 Centrifuge extractors with filler separator 242 Marshall compression tester (manual sau mecanic) 143 Compression tester for cubic samples 144 Sample mixer 1

    45 Water bath with thermostat 146 Penetrometer 247 Ring and ball apparatus 248 Asphalt oven for TFOT or RTFOT 1

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    31/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    General Items Page 31 of 349

    Nr. crt. Description Quantity49 Ductility testing mashine 150 cm 150 Fraas breaking point apparatus 151 Spectrophotomenter 152 CBR Equipment 153 Standard and Modified Proctor mould + hammers 3054 Benkelman beam 255 Lukas plate 156 Liquid limit device - Cassagrande apparatus 157 Areometers 258 Sand equivalent test set 259 Sand cone equipment 460 Specific gravity frame + gravity tank + basket 261 Compression testing machine for ciment 162 Chronometer 363 Polish stone device 164 Thermo-hygrograph -35 +45C; 0 - 100% humidity range 165 Field Dynamic penetrometer (FDP) for soil 166 Viscometer 167 Skin Resistance Test Device 1

    The above list is indicative only. The Engineer may amend the list as necessary.Before purchase, the Contractor shall seek Engineers approval for the proposed number, model and qualityof the items of Laboratory equipment.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    32/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 32 of 349

    SPECIFICATIONS

    2.1 ROAD WORKS

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    33/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 33 of 349

    CONTENTS1 Earthworks2 Form layer made of ballast

    3 Layer of ballast or optimal ballast4 Crushed stone

    5 Layer of ballast stabilized with cement

    6 Base course of hot rolled asphalt mixtures7 Bituminous surfaces8 Concrete pavement

    9 Road signing10 Road marking

    11 Traffic safety

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    34/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 34 of 349

    TECHNICAL SPECIFICATION

    - 1 -EARTHWORKS

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    35/348

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    36/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 36 of 349

    GENERAL PROVISIONS

    This Technical Specification applies to earthworks in public roads construction and includes theconditions to follow during the earthworks construction with regard to excavation, transport,

    compaction, levelling and finishing of the works, as well as the quality control and acceptancecriteria.

    The Contractor shall perform, in an authorised laboratory, all the tests required by the TechnicalSpecifications and any other tests required by the Engineer.

    Apart from the Technical Specifications, the Contractor shall respect the stipulations of thestandards and norms in force.

    14 days before starting the works the Contractor shall submit for the Engineers approval, theMethod Statement for earthwork construction and that shall include:

    Detailed programme of earthworks construction The equipment necessary for excavation, transport, spreading, watering, compacting and

    finishing Borrow pits and earth storage places (temporary and permanent) and the related Method

    Statement and also the access to each of them. Temporary road diversions for the public traffic during the works construction Diagram of Earthworks Displacement.

    In order to determine the details of the compaction Method Statement, trial sections shall beexecuted by the Contractor, on his own expense; the size and location of the trial sections shall bedecided together with the Engineer.After executing the trial section, the Method Statement shall be completed with informationregarding the compacting Method Statement:

    - The features of the compaction equipment (weight, width, tire pressure, vibrationparameters, speed)

    - Number of passes with and without vibration to achieve the degree of compaction accordingto the Technical Specification stipulations.

    - The thickness of the layer before and after compaction.

    The Contractor shall ensure that by all procedures applied, he fulfils the requirements of theTechnical Specifications.

    The Contractor shall record on a daily basis data related to the construction of the works and theobtained results of measurements, samples and tests.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    37/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 37 of 349

    1 MATERIALS

    1.1 Top Soil

    The topsoil good for vegetation shall be used to cover the surfaces that have to be seeded andplanted.

    1.2 Soils for earthworks

    The types of soils used for earthworks are showed in Tables 1a and 1b.

    In case the soil, in the area where earthworks are to be executed, is of bad or very bad quality(see Table 1b) it shall be replaced with a suitable quality soil or it shall be stabilised eithermechanically or using binders (quick lime, power plant ashes etc).Replacing or stabilising the earth shall be executed over the entire width of the platform with aminimum 20 cm depth for the bad quality soil and minimum 50 cm for the very bad quality soil orin case the dry density is less than 1.5g/cm 3 .The clayey soil type 4d shall be replaced or stabilised in at least 15 cm depth.The clayey soils of medium quality can be used provided that the STAS 1709/1,2,3-90 stipulationsregarding the prevention of deterioration caused by freezing thawing are respected.

    The inorganic soils of bad and very bad quality as well as the organic soils, silts, mud, top soil,soft soils (consistency index less than 0.75) and soils containing more than 5% water soluble saltsshall not be used for embankment construction.The Contractor shall not use materials that:

    - are frozen;- contain organic matter in decay (grass, branches, roots).

    The soil containing water soluble sulfates more than 1.9 g/l (SO 3 ) shall not be stored or used asfilling material nearby/in the proximity of the concrete works.

    1.3 Water

    Water used for compaction of the earthworks shall be clear and it shall not contain either inorganicor organic suspensions.

    1.4 Quality control of soils

    Before starting the works, the Contractor shall determine the quality and estimate the quantity ofmaterials from the borrow pits. The documents will be submitted to the Engineer for approval.The materials used for earthworks shall also have the Engineers approval before starting the works.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    38/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 38 of 349

    Table 1a Soil types (non-cohesive soils)Content in fine parts in % of the

    total massThe main types of soil name, featuresType

    (Symbol ) 5

    medium and fine:fraction < 2 mm is morethan 50% of the mass

    Gravel sand, coarsegrained sand, medium orfine id 2a, discontinuous grading 2b

    < 6 < 20 < 40

    5

    With very many fine parts;Very sensitive to freezing thawing;The fine fraction has low swellingcapacity

    3a

    medium and fine withcohesive soils as bindingmaterialfraction < 2 mm is morethan 50% of the mass;cohesive soils as bindingmaterialGravel sand; coarsegrained sand, medium andfine, with mud as bindingmaterial

    Id 3a, the fine part has medium orhigh swelling capacity

    3b

    6 20 40 -

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    39/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 39 of 349

    Table 1 b Type of soils (cohesive)

    Name and characteristics of the maintype of soils

    Symb ol Grading according to Cassagrande nomographic chart

    Inorganic :- C and U low- S i-d medium

    4a

    Inorganic :- C medium- U low or medium- S i-d very high

    4b

    Plasticity Index I p 70Organic (OM>5%):

    - C and U low- S i-d medium

    4c60 4d

    50Inorganic :- C and U high- S i-d medium 4d 40 4a W

    c =

    5 0 %

    30 W c =

    3 0 %

    4bOrganic (OM>5%):- C medium- U medium or low- S i-d very high

    4e 204f

    10

    4c 4e

    10 20 30 40 50 60 70 80 90 100

    Cohesive soils:o Dusty sando Sandy dusto Clayey sando Dusty,

    clayey sando Dusty clayo Dusto Dusty, sandy

    clayo Sandy clayo Clayo Fat clay

    Organic (OM>5%):- C high- U high or medium- S i-d very high 4f

    Flow limit- W c (%)Diagonal: I p = 0,73 x (W c 20)

    Note: OM = organic matterC = compressibilityU = swelling capacityS i-d = sensitivity to freezing thawing

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    40/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 40 of 349

    Table 2 - Tests to verify the soil

    No . Characteristics Minimum frequency

    1 Grading Depending on the irregularity of the soil, at least one test each 5000 m 3. 2 Plasticity limits Depending on the irregularity of the soil, at least one test each 5000 m 3.

    3 Compaction characteristics Depending on the irregularity of the soil, at least one test each 5000 m3..

    In case of filling behind the works of art and for soils in protective layers, for each laid layer.4 Irregularity index Depending on the irregularity of the soil, at least one test each 5000 m 3. 5 Swelling capacity In case of filling behind the works of art and for soils in protective layers, at least one test each 1000 6 Sensitivity to freezing

    thawingIn the natural ground under the embankment and in cutting, at least one test each 250 m of road.

    7 Moisture content Either daily or at each 500 m 3. 8 Maximum dry density Depending on the irregularity of the soil, at least one test each 5000 m 3.

    Note: 1. When approving the source for soil it is necessary to present the tests regarding the organic matter (in compliance with STAS 7107/1-7compliance with STAS 7107/3-74) and compressibillity (in compliance with STAS 8942/1-84).

    2. The Contractor may request the Engineers approval for other Norms and testing methods that have Technical Agreement in Romania.

  • 8/10/2019 5R12 Volume 2 Specifications.pdf

    41/348

    Roads Rehabilitation V Project EIB Fl 21.489DN 76 DEVA ORADEAContract 5R12 DN76 Vrfurile tei km 69+350 to km 102+660

    Volume 2 Specifications

    Road Works Page 41 of 349

    2 EARTHWORKS CONSTRUCTION

    2.1 Pegging out

    The Engineer shall hand over to the Contractor the benchmarks located outside the construction

    limits (at least 2 benchmarks/km) and a list indicating the coordinates of the main points of thealignment and of the benchmarks.

    Before starting the works, the Contractor shall re-establish the benchmarks (if necessary) and heshall execute the pegging out of the cross-section, at his own expense.

    On completion of the pegging out of the centre line, the Contractor shall mark on the ground thefollowing:

    - height of the filling- the intersectio