ENERGY:CRITICAL FACTS & FIGURES
Fossil fuel (coal/oil/gas) - limited and fast depleting; an urgent
need of renewable source of energy - solar/wind.
Average per capita electricity production in industrially
advanced nation is 14,000 units, while it’s only 900 in India
against the need of 2000 (only 45%) .
People without electricity = ~ 30 Cr; Unelectrified Villages: 35K
India’s installed power generation capacity is 285GW (Aug-2016)
RE contribution is 43 GW, i.e., 13% (Aug-2016)
Solar contribution is only 8 GW (Till Aug-16) while target is 100
GW by 2022. Rooftop Target is 40 GW by 2020.
Wind Power is 25 GW against target of 60 GW by 2022.
Solar Potential: Energy in 1 hr > World’s Annual Energy Reqmnt
India is in sunny region with 4-7 KWH/m2 with more than 300
Sunny days; India’s Potential=750 GW
Gujarat is more blessed with 5-6.4 KWH/m2 and 330 sunny days.
RPO for Solar to go up from 0.25% in 2011-12 to 8% by 2022
Fund needed is $100 Billion
Why Renewable?
PER CAPITA ENERGY CONSUMPTION
With 11 GJ, long way to go…
Rest of World at 18 is much above India
India only dreams for it
India needs 1250 Million Units more to improve from 11 to 12 GJ per capita and 8750 Mn to reach ROW level
6
KP Group: Surat, Gujarat based, Established in 1994; 120 Cr Turnover
Highly Qualified, Experienced, Skilled & Visionary Leadership Team
consisting of Business Leaders, Ex-ISRO Scientist and Senior Ex-Govt. Officers
Well experienced in Solar, Wind, Telecom Infra
Owns two well equipped modern Factories at Surat & Vadodara for:
Telecom and Transmission Towers – Design & Fabrication
Solar Modules Mounting Structure – Design & Fabrication
Hot-dip Galvanizing facility
Group Companies:
KPI Global Infrastructure Ltd
KP Buildcon Pvt Ltd
KP Energy Ltd (BSE Listed under SME – Code: KPEL)
KP Structural & Galvanizing Pvt Ltd & others
For more details, please visit www.solarism.kpgroup.co
KP GROUP – AT A GLANCE
7
SOME OF THE PROJECTS EXECUTED
SOLAR POWER PROJECTS
Have executed large Solar
projects totaling 105 MW in
Bhachau, Charanka, Jamnagar
(Gujarat) & Sakri (Maharshtra)
Supplied MMS Structures from
own factory
Solar Water Pump of UGVCL
MNRE Accredited; Several
Rooftop Sites Commissioned
Our Esteemed Customers:
Some More Customers:
Accord Communications
Mahagenco
GPPC
Sunborn
Alex
WINDFARM INFRA PROJECTS A land portfolio for 390MW
allocated by Government of
Gujarat in the districts of
Bhavnagar & Porbandar
Wind Masts installed at these
sites for Wind Data collection
and Energy Yield study.
33.6 MW (16 Nos x 2.1MW WTG
already commissioned at our
Ratdi Windfarm in Porbandar;
33.6MW (16x2.1MW WTG’s)
execution are in advanced
stages in Palitana, Bhavnagar;
12 are already commissioned, 1
WTG is owned by KP.
30 MW, 66KV Substation work
is in progress at Kuchhdi in
Porbandar.
Our Esteemed Customers:
Colourtex, Surat Municipal
Corporation, SPL, Filatex , Jay
Bharat and Others
MOBILE COMMUNICATION PROJECTS
Executed large projects of
Mobile Telecommunications in
15 major States of India as TSP
Low cost, excellent quality and
on-time delivery using
innovative ways of execution
Executed OFC Project work of
more than 1700 KM
Vodafone, 1800 KM of OFC
O&M for patrolling, fault
rectification
Our Esteemed Customers:
9
SITE DATA
Lat 21.894
Long 72.903
District Bharuch
State Gujarat
Capacity 50 MWp
(Part-1: 15 MWp)
Total Private Land 260 Acre
Land Needed 5 Acre / MW
Irradiance 5.23 KWH/m2
Expected EYR per MW/Year 1.7 MWH
PLF Expected 20%
Revenue Model REC+PPA/OA/CAPTIVE
DISCOM DGVCL (GUVNL)
State Nodal Agency GEDA
Evacuating GETCO S/S Amod 66 KV
PV Technology Poly Crystalline PV
Sun Tracking No (Fixed)
Project ID with GoG 11106
COD of 2MW 13-Jan-2016
COD of 3MW 30-Mar-2016
Expected COD next 10MW Dec-2016
Expected COD next 35MW Dec-2017
SOLAR PARK @ A GLANCE
Solarism
AMOD
TORRENT POWER
DAHEJ GIDC
VILAYAT GIDC
VAGRA GIDC
10
1. Better/Higher Radiation
2. Lower ambient Temperature
3. Less dusty area surrounded by agricultural lands
4. Use of Improved and more efficient PV Technology
5. Selection of best, reliable & efficient Solar panels, inverters, cables and
transformers, etc.
6. Optimum angle of inclination
7. Use of optimum inter-row spacing between two adjacent rows to avoid
shadow effect
8. Shadow free land
9. Own O&M and regular panel cleaning
10. Heavier Hot Dip Galvanized MMS for long life span of 25 years
11. Panther Towers for 66KV Transmission Line – Future proof
12. Proximity with GIDC’s like Dahej, Vagra, Vilayat where the power
demand is more than 2000MW
SOLARISMTM– UNIQUE FEATURES
11
SOLARISMTM– LATEST STATUS
SN TASK DESCRIPTION STATUS REMARK
1 Land Acquisition of 260 Acres Completed 50 MW
2 Land NA Conversion for Phase-I Completed 30 MW
3 Signing of MOU with Govt of Gujarat Completed
4 GEDA & NLDC approval under REC Completed
5 GETCO Connectivity Agreement Completed
6 CEIG-Gujarat’s Approval Completed
7 Wheeling Agreement with DGVCL Completed
8 Signing of PPA with Manikaran Power Ltd Completed
9 Excise Duty Exemption Certificate by MNRE Completed
10 Boundary Walls/ Internal Road / Borewells Completed 30 MW
11 Civil Foundation Completed 20 MW
12 Module Mounting Structure, MMS, Erection Completed 7 MW
13 66 KV Transmission Line Work Completed 50 MW
14 66/11 Switchyard Work Completed 50 MW
15 Commissioning of 5MW Solar Plant Completed 30-Mar-16
16 Installation &Commissioning of next 10MW In Progress Dec-16
PROJECTED MONTHLY GENERATION
Projected Annual Generation is 17.5 Lac Units and Avg 146,010 Units per month
Month Generation
Jan 161,000
Feb 153,885
Mar 174,348
Apr 163,587
May 162,646
Jun 130,541
Jul 104,315
Aug 104,432
Sep 132,540
Oct 159,295
Nov 151,768
Dec 153,767
Yearly 1,752,125
Average 146,010
16
1,0
00
15
3,8
85
17
4,3
48
16
3,5
87
16
2,6
46
13
0,5
41
10
4,3
15
10
4,4
32
13
2,5
40
15
9,2
95
15
1,7
68
15
3,7
67
-
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
200,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Monthly Generation for 1MW (Units)
Highest Generation
Lowest Generation
Confidential 13
FINANCIALS PARAMETERS – 1MW
KEY PARAMETERS Project Cost: Value Unit
Plant Capacity 1 MW
Project Cost 6.25 Rs. Crore
Operational Parameters:
Generation (Units) 17.52 Lakhs
Transmission losses 4.0% % of Gen’tion
Performance Degradation 0.8%
PLF 20.0%
O&M + Lease 13.0 Rs.Lakhs
Free O&M + Lease 1 Years
Service Tax 14.5%
Escalation 4.0% Per Annum
Insurance 0.1%
Transmission Charges 2785 Rs/Day
Cross Subsidy Charges 0 Rs/KWH
Additional Surcharge 0 Rs/DKWH
Tariff Details
Base Tariff - Captive 6.7 Rs/KWH
Escalation 6.0% Rs/KWH
Equity 30% 187.5 Lakhs
Debt 70% 437.5 Lakhs
Rate of Interest 12.5% Per Year
Repayment Years 12 Years
RESULTS Project IRR 17.73%
Equity IRR 21.84%
Average DSCR 1.73
Minimum DSCR 1.07
Payback Period - Project 6.35
Payback Period - Equity 7.29
KEY BENEFITS 1. ACCELERATED DEPRECIATION (AD) 2. MAT / 80I 3. EDEC / CDEC 4. SAVING MOTHER NATURE
85% UNITS GENERTION GUARANTEED BACKED BY FINANCIAL GUARANTEE
20
SOLARISMTM– EQUIPMENTS USED
Equipments used are best-in-class keeping 25 Years plant life
S.NO. EQUIPMENTS SUPPLIER MAKE MODEL
1 Solar P V Panel Goldi Green
Technologies ,Surat Goldi Green GOLDI250PM
2 Module Mounting
structure KP Buildcon Pvt Ltd KP -
3 Array Junction Box RPG Raychem Fimer Italy SBC24
4 Inverter RPG Raychem Fimer Italy R7500TL
5 Transformers
Transformers and
Rectifiers (India) Ltd.
Ahmedabad
T & R
1. 7.5/10 MVA
(11/66 KV )
2. 1.5 MVA
(0.27/11 KV )
6 HT Panels Akshar Infra Pvt. Ltd.
Vadodara CGL 11 KV
7 SF6 Breakers Akshar Infra Pvt. Ltd.
Vadodara ABB
EDF SK1-1
66 KV /1600 A
8 SCADA
Dynamic Innovations Pvt.
Ltd.
Ahemdabad
GE Proficy Scada
9 Weather Monitoring
System
Aeron Systems Pvt. Ltd.
Pune
Hukseflux
Thermal Sensors SR20-T1