Upload
letsdoit
View
220
Download
0
Embed Size (px)
Citation preview
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 1/11
TET-1
A GERMAN MICROSATELLITE FOR ON-ORBIT-VERFICATION
Stefan Föckersperger(1), Klaus Lattner(1), Clemens Kaiser(1), Silke Eckert(2), Wolfgang Bärwald(2),
Swen Ritzmann(2), Peter Mühlbauer(3), Michael Turk(4), Philipp Willlemsen (4),
(1)Kayser-Threde GmbH, Wolfratshauser Straße 48, 81379 München, Germany,
Email: [email protected](2) Astro- und Feinwerktechnik GmbH, Albert-Einstein-Straße 12, 12489 Berlin, Germany,
Email: [email protected]
Deutsches Zentrum für Luft-und Raumfahrt e.V. (DLR), Rutherfordstr. 2, 12489 Berlin
E-Mail: [email protected]
(3) Deutsches Zentrum für Luft- und Raumfahrt e.V. (DLR), 82234 Weßling, Germany,
Email: [email protected]
(4) DLR Space Agency,Königswinterer Straße 522-524, 53227 Bonn, Germany,
E-Mail: [email protected]
ABSTRACT
Due to the high safety standards in the space industry
every new product must go through a verification
process before qualifying for operation in a space
system. Within the verification process the payload
undergoes a series of tests which prove that it is in
accordance with mission requirements in terms of
function, reliability and safety. Important verification
components are the qualification for use on the ground
as well as the On-Orbit Verification (OOV), i.e. proof that the product is suitable for use under virtual space
conditions (on-orbit). Here it is demonstrated that theproduct functions under conditions which cannot or can
only be partially simulated on the ground.
The OOV-Program of the DLR serves to bridge the gap
between the product tested and qualified on the ground
and the utilization of the product in space. Due to
regular and short-term availability of flight
opportunities industry and research facilities can verify
their latest products under space conditions and
demonstrate their reliability and marketability.
The Technologie-Erprobungs-Träger TET (Technology
Experiments Carrier) comprises the core elements of theOOV Program. A programmatic requirement of the
OOV Program is that a satellite bus already verified in
orbit be used in the first segment of the program. An
analysis of suitable satellite buses showed that a
realization of the TET satellite bus based on the BIRDsatellite bus fulfilled the programmatic requirements
best.
Kayser-Threde was selected by DLR as Prime
Contractor to perform the project together with its major
subcontractors Astro- und Feinwerktechnik, Berlin for
the platform development and DLR-GSOC for the
ground segment development. TET is now designed tobe a modular and flexible micro-satellite for any orbit
between 450 and 850 km altitude and inclination
between 53° and SSO. With an overall mass of 120 kg
TET is able to accommodate experiments of up to 50
kg. A multipurpose payload supply system under
Kayser-Threde responsibility provides the necessary
interfaces to the experiments. The first TET mission is
scheduled for mid of 2010. TET will be launched as
piggy-back payload on any available launcher
worldwide to reduce launch cost and provide maximum
flexibility. Finally, TET will provide all servicesrequired by the experimenters for a one year mission
operation to perform a successful OOV-mission with its
technology experiments leading to an efficient access tospace for German industry and institutions.
1. BACKGROUND
The goal of the OOV (On-Orbit-Verification)-Program
is to qualify new technological solutions for their
application in space projects. It focuses on the in-flight
demonstration and verification of highly advanced
technologies. The core element of the program is the
micro-satellite TET (Technology Experiment Carrier) asa platform for the verification flight.
1.1 The need for on-orbit verification
It is necessary to validate new, unproved techniques and
technologies before using them in advanced missions.The OOV-Program fills the gap between a technology
which has been qualified on the ground and its
application in space. In order to support German
industry and research institutes, the German Space
Agency provides flight opportunities to qualify in-flight
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 2/11
new technological solutions in all areas of space craft
technology such as power generation and storage,
propulsion, guidance, navigation and control.
The first part of the program is scheduled for the years
2005-2012. The overall budget of the program within
this time span is about 34 M€. The program isconducted in cooperation with DLR Space Research
(PD-W).
1.2. Flight opportunities
Flight opportunities for technology demonstration and
verification should ideally be provided on a regular
basis, independent, cost efficient and safe. A market
survey of German industries’ and institutes’
technologies has shown that about 75 % of the
experiments can be verified using a micro-satellite.
The OOV-Program is thus structured into two main
parts with respect to the flight opportunities offered.
The first comprises the micro-satellites TET with a
planned flight every two years. For payloads which do
not fit on TET, the DLR Space Agency cooperates with
national and international partners in order to provide
flight opportunities on other carriers.
2. MISSION OVERVIEW
The whole mission is designed based on the mainmission requirements shown in Tab.1.
Table 1: TET main mission requirementsMission duration: 1 month LEOP incl. Satellite
commissioning and 12 months mission operations
Type of Orbit: circular
Orbit height: between 450 – 850 km
Orbit inclination: 53° to sun-synchronous
Piggy-Back Launch
Reliability requirement: 0.9 (for platform and payload support
system)
Ground stations: Weilheim for TT&C, Neustrelitz for payload
data downlink
TET platform should be based on the BIRD satellite
(maximum use of the BIRD heritage)
TET-1 Satellite mass: 120kg
Total Payload mass: 50kg
Derived from the above mentioned requirements and
following a detailed mission analysis a mission scenario
has been defined as shown in Fig. 1 below. The TET-1
satellite is launched as piggy-back in a LEO orbit. After
LEOP and Commissioning the one year mission
operation is controlled via the mission control centre in
Oberpfaffenhofen. Payload data are stored in the
payload data centre in Neustrelitz and can be retrieved
from the Experimenters via secured web access.
GSOC / Oberpfaffenhofen
DLR groundstation Weilheim
Planning Mission Control
Legend:Data Transfer
Requests
Command & Control
Experimenters
TET-1Mission
Orbit Launch
DLR groundstation & PDC Neustrelitz
e.g. SOYUZ
Figure 1: TET Mission Scenario
The essential conditions for operation of the payload
are:
- Electrical power supplied by the satellite bus to the
single experiment,- Thermal power consumption of the payload
impacts the overall thermal system,
- Pointing mode of the satellite,
- Data take/rate of the experiment limited by the
mass memory.
A careful mission planning for the experiments is
necessary to be compatible with these conditions. The
following principle operational scenarios are foreseen:
- Standard weekly mission scenario: the TET
payload is operated according to a schedule that isrepeated after one week (approx. 15 orbits with
approx. 100 minutes data downlink every day).
- Mission scenario 12: 12 times per year continuous
experiments lasting 4 days are performed.
- Mission scenario 2: 2 times per year experiments
with direct space-ground link is foreseen lasting 2
days.
These operating scenarios are commanded from the
ground station and controlled by the Payload SupplySystem which is detailed in chapter 3.3.2.
The final decision concerning the piggy-back launcheris not jet made, but due to economical reasons a launch
opportunity with SOYUZ/FREGAT from Baikonur is
first choice. TET-1 is intended to be launched together
with a Russian weather satellite METEOR-2. The
adjoining picture shows a possible accommodation of
TET-1 on SOYUZ/FREGAT. The final orbit is a sun-
synchronous, 550km altitude, circular orbit. During
launch the satellite is inactive and after separation from
the launcher the satellite is activated.
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 3/11
Figure 2: TET-1 Accommodation on launcher
The overall mission comprises the following mission
phases.
Transport to Launch Site
Launch Campaign
Launch und Early Orbit Phase
Commissioning
Mission Operation
Disposal
Storage in case of Lauch D elay
Figure 3: TET-1 mission phases
The main phases are described in more details:
- LEOP: The Launch and Early Operations Phase
will last a few days and has the goal to ensure
satellite survival after separation from the launcher.
Solar arrays will be deployed; satellite attitude willbe stabilized to allow battery charging by the solar
arrays and initial housekeeping data will be
acquired from the LEOP ground station network.
LEOP will end when the satellite is in a stable
situation with respect to power, attitude and
communications.
- Bus and NVS commissioning: Components which
were not activated in LEOP will be activated. Allsubsystems of the satellite bus and the NVS will be
thoroughly tested.
- Operational mission: The operational mission willlast 12 months. Payload commissioning and
payload operations will be performed in this phase.
- End of operations (disposal): In this phase the
payloads will be switched off and passivation
measures will be performed for the bus and the
payloads.The TET-1 mission is structured as shown in Figure 4
and consists of three elements:
- the Space segment,
- the Ground segment and
- the Launch segment
Figure 4: TET-1 Mission Elements
Each of these elements has been designed in past project
phases and the results are shown in the forthcoming
chapters.
3. SPACE SEGMENT
3.1. Overview
The TET-1 Space Segment consists of the Satellite Bus
and the Payload. At an overall mass of about 118kg the
Payload including the Payload Supply System and
necessary support structures contributes with about
50kg. Fig. 5 below shows the Satellite Bus with
integrated Payload in the launch configuration where
the two solar panels on the left and right side are notdeployed. The overall height of the Satellite is less than
880mm with a width of approximately 550mm and a
depth of 650mm.
OOV
Programme
ExperimentersTET
Mission #1
Ground
segment
Space
segment
Satellite Platform
Mission Control Centre
Ground Stations
Payload Data Centre
Launch
segment
Launcher
Infrastructure
Ground Support
Equipment
TET 1 Payload
Payload Support System
Payload Segment
TET
Mission TBD
Additional Experiments
Experiment 1
Experiment n
LEOP Network
TT&C Stations
Launcher TT&C Stations
Integration Facilities
Launcher Control Centre
TET Experiments
Mission #1
Experiment 1
Experiment n
Payload Data Station
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 4/11
Figure 5 TET-1 Satellite (launch configuration)
In the deployed configuration as shown in Figure 6
below, the Payload Segment can be seen more clearly. It
is located on top of the Satellite Bus main structure with
the Payload Base Plate as the mechanical and thermal
interface.
Figure 6: TET-1 Satellite (deployed configuration)
To limit the development time and to reduce the projectrisk the TET-1 satellite bus is based on the heritage of
the BIRD satellite bus. The open satellite structure of
the BIRD concept allows for a flexible payload
accommodation which has been adapted for size and
mass to fulfil the TET-1 needs.
11 experiments have been selected by DLR for this first
TET mission. The experiments are developed by 11
different companies and institutions and comprise
newest technology to be demonstrated for usage in
space environment. The technical areas cover next
generation solar arrays, navigation equipment, batteries,
cameras, communication equipment, and satellite
propulsion system and computer hardware.
The Payload to Satellite Bus interface is realized and
managed by a modular Payload Supply System
developed by Kayser-Threde, allowing to be customized
with minimum effort to the experiment needs and
thereby reducing the effort for recurring missions.
Table 2: TET-1 Technical Data
TET-1 Technical Data
Dimensions : 880 mm x 550 mm x 650
mm (H x W x D) with about
90 liters of payload
compartment
Mass : Bus 70 kg
: Payload 50 kg
Number of experiments : 11
Stabilization : 3-axes
Pointing accuracy : 5 arcmin
Payload power consumption : max 20W continuous
Uplink rate : 4 kbit/s
Downlink rate : 2.2 Mbit/s high rate
Orbit : 550 km, SSO
Launch : Mid 2010
Mission duration : one year
3.2. Satellite Bus
The TET satellite bus can carry various adapted. It is a
micro satellite bus based on the successfully employedmicro satellite BIRD (Bi-spectral Infra-Red Detection).
On 22 October 2001 the micro satellite BIRD (Bi-
spectral Infra-Red Detection) was launched successfully
as secondary payload with the Indian rocket PSLV-C3
(Polar Satellite Launch Vehicle) into a circular sun-
synchronous orbit of 572 km height. The satellite was
designed, integrated and tested at DLR Berlin-
Adlershof. The mission goal testing new small satellitetechnologies in space was accomplished as well as
testing a new generation of infrared sensors combined
with a modified WAOSS camera (Wide-Angle
Optoelectronic Stereo Scanner). For the first time it was
demonstrated that the expansion of vegetation fires and
related flame temperatures can be detected with a
special payload on a micro satellite. [1]
During the required life expectancy of 12 months all
components worked correctly. For more than 80 months
BIRD has been successfully sending data to earth.
Payload
Segment
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 5/11
In contrast to BIRD a higher payload total mass of 50
kg in a bigger dimension of 460 x 460 x 428 mm³ is
available for the payloads that should be verified. The
Payload Segment contains, besides the experiments,satellite bus components which need a dimension of
approx. 100 x 275 x 220 mm³ for star cameras and
140 x 55 x 45 mm³ for magnetic field sensors(Figure 7 ).
Figure 7: Available Payload Volume within TET-1
The satellite bus offers the possibility of fixing a
payload panel above the central solar panel. Additional
solar cells can also be installed on a special area on the
central panel.
Figure 8: TET-1 Satellite Bus with Solar Cells and freespace to install Payload Panels
Some other basic features of the TET satellite bus are
the compact micro satellite structure with high
mechanical stability and stiffness and a cubic shape in
launch configuration with a dimension of 650 x 550 x
880 mm³ (envelope) (see Figure 9).
The TET satellite bus relays on a passive thermal
control system with radiators, heat pipes, MLI,
temperature sensors and contingency heaters.
Figure 9: Envelope of TET Satellite Bus
The Power Subsystem consists of Power Control and
Power Distribution Units, NiH2 cell battery stacks
including T-control and solar panels. The solar array
consists of 3 panels; one fixed body mounted middle
panel and 2 deployable side panels. The array is
equipped with 246 solar cells (triple junction GaAs,
efficiency 28%), with an electrical power of 220W
(maximum power point). The capacity of the battery is
240Ah, energy transfer is done by DET
(DirectEnergyTransfer).
The Spacecraft Bus Computer (SBC) controls allactivities of the satellite bus. The SBC receives, stores
and processes the commands, gathers and evaluates the
housekeeping data of all subsystems and controls the
telemetry. Furthermore it is also the attitude control
computer of TET. The SBC consists of 4 identical SBC
boards and watchdog circuits for failure detection and
recovery. The architecture of the redundant SBC boards
(nodes) is totally symmetric, that means, each of the
boards is able to execute all control tasks. One node (the
worker) is controlling the satellite while a second node
(supervisor) is supervising the correct operation of the
worker node. The two other node computers are sparecomponents and are disconnected. If an anomaly of the
worker node is detected by the supervisor node the
supervisor substitutes the worker and takes over the
control of the satellite. [2]
The Attitude and Orbit Control System (AOCS) consists
of two star sensors, two gyroscopes, two
magnetometers, 2 sets of sun sensors, 4 reaction wheels,a magnetic coil system. The attitude control system
provides a high degree of autonomy basing on a state-
space representation of the attitude estimation,
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 6/11
prediction and control, a real-time operation system
embedding the attitude control software and a
combination of the attitude control with an on-board
navigation system (see Fig. 10 and 13).
Figure 10: Scheme of the AOCS Interfaces
One of the most complicated tests during the
verification process of the TET satellite bus is the
testing of the Attitude and Orbit Control System.
Software-in-the-loop simulations and hardware-in-the
loop simulations are well established test methods, but
the best solution is real end-to-end test of the AOCS
with a corresponding test facility. Based on theexperiences with the BIRD AOCS test facility during
the last years and the AOCS requirements, Astro- und
Feinwerktechnik Adlershof GmbH has developed and
built a new test facility for the end-to-end verification of
the AOCS (see Fig. 11). [3]
The communication takes place using S-Band with high
bit rate (2,2 Mbit/s) and low bit rate. The transmitter and
receiver channels are redundant and can be switched to
all antennas. (see Fig. 12).
Figure 11: Components of the TET Satellite Bus
Figure 12: Scheme of the Communication System
The TET Satellite bus consists of three compact
segments. In the service segment a battery, reaction
wheels, the power control and distribution unit and laser
gyro are installed. The Satellite Board Computer and the
Payload Supply System are located in the electronicssegment. The modifiable payload platform is the link
between electronics segment and payload segment. In
the payload segment are the experiments and also
satellite bus components (star sensors, magnetic fieldsensors and antennas (low-gain and GPS) (see Figure
13).
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 7/11
Figure 13: Components of the TET Satellite Bus
3.3. Payload
3.3.1. TET-1 Payload Segment incl. Experiments As mentioned, 11 experiments are accommodated in theTET-1 satellite. The list of experiments is given below:
- three different types of next generation solar cells
including thin-layer technology
- Lithium Polymer Battery
- two GPS receiver systems
- sensor bus system
- pico satellite propulsion system
- infrared camera as follow-up of the BIRD camera
system
- Computer hardware
- RF communication system.
The accommodation of the experiments in the PayloadSegment is shown on the following two figures. The
accommodation has been driven by the various
experiments needs as e.g. viewing directions,
unobstructed view angles for antennas, heat dissipation,
etc.
Figure 14: Accommodation of Experiments (1)
Figure 15: Accommodation of Experiments (2)
The solar cell experiments have been accommodated on
the sun pointing side of TET-1 next to the Satellite Bus
solar arrays, as shown in the next figure.
Figure 16: Accommodation of Solar cell Experiments
The TET-1 Payload configuration data is summarized in
Tab. 4.
Table 3: Payload configuration data
TET-1 Payload Data
Dimensions : 428 mm x 460 mm x 460
mm (H x W x D)
Max. Payload Mass : 50 kg incl. mass of PayloadSupply System
Power consumption cont. : 0 – 20 W incl. Payload
Supply System
Power consumption max. : 160W limited in time and
occurrence
Supply Voltage : 18 – 24VDC
Current max. : 8A
TM Data Rate : 2.2 Mbit/s max.
Storage : 512 MByte
Heaters : 0 to 15W
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 8/11
3.3.2 Payload Supply System
Via the Payload Supply System the interface between
the Satellite Bus and the experiments is controlled. The
Payload Supply System provides therefore a fixed part
that interfaces to the Satellite Bus and a flexible part
that can easily be adjusted to the experiments needs.
Satellite Bus ExperimentsPayloadSupply
System
Figure 17: Payloads Supply System Interface
Based on this concept the Payload Supply System can
be separated into three different parts:- the power supplies responsible for the supply of the
experiments and the Payload Supply System itself
- the processor boards that are used to control all
Payload Supply System activities
- the I/O boards that provide the interfaces to the
experiments.
All these parts will be realized on several printed circuit
boards that will be connected via backplane. Theexperiments will be connected via front panel
connectors.
The Payload Supply System is accommodated inside the
Electronic Segment of the Satellite Bus next to theSatellite Bus Controller as shown in the figure below.
Figure 18: Accommodation of the Payloads Supply
System
A block diagram of the Payload Supply System is
shown in Fig. 19.
NVS Power
NVS Controller
NVS Power 4
NVS Prozessorboard A/B
Memory
T r a n c e i v e r
T r a n c e i v e r
Digital I/OFPGA
CPUserial IF
GPIO
SpacewireMemory IF
Analog I/O
7x RS-422 / 1x I²C
8 x Relais Cmnd.
5 x Relais-Status
24 x GPIO/DAC
12 x AD590
4 x PT1000
16 x Analog In
3 x Spacewire
N u t z l a s t e n
S B C D a t a I F
2x RS-422
Power Control
18..24V
S
B C P o w e r
4 x A D 5 9 0
18..24V
NVS Power 5
HK Voltage Measurementprimary / switched
Latch Relais
Latch Relaiscurrent limiter
breaker
current limiterbreaker
NVS Power 1
Latch Relaiscurrent limiter
breaker
DC/DCconverter
Latch Relaiscurrent limiter
breaker
DC/DCconverter
NVS Power 2
HK primary CurrentMeasurement
Latch Relaiscurrent limiter
breaker
DC/DCconverter
DC/DCconverter
+/- 5VLatch Relaiscurrent limiter
breaker
NVS Power 3
Latch Relaiscurrent limiter
breaker
DC/DCconverter
DC/DCconverter
HK secondary VoltageMeasurement
5V (NL17)
12V (NL2)
Latch Relaiscurrent limiter
breaker
relais on
relais off
HK secondary VoltageMeasurement
+/- 5V
1 x PPS
18..24V
Latch Relaiscurrent limiter
breaker 18..24V
Latch Relaiscurrent limiter
breaker
1..4 (NL1, NL6, NL16, Heating)
1..4 (N4, NL7, NL15, N18)
2x sync. IF
1x PPS
Figure 19: Payload Supply System Diagram
The functions provided by the software executed on the
Payload Supply System processor cover the followingtasks:
- control of experiments with minimal built-in
processing logic
- acquisition of housekeeping data of the experiments
and the Payload Supply System itself
- acquisition of measurement data of the experiments
- temporary storage of all acquired measurement and
housekeeping data
- formatting and packaging of data according
CCSDS for downlink
- reception and execution of commands from the
Satellite Bus Controller- Control of Payload Supply System devices as
switches, circuit breakers, etc.
- management of thermal control of experiments and
Payload Supply System
- Boot, self-test and software update management
- Failure Detection, Isolation and Recovery,
redundancy management
Via the housekeeping sensors of the Payload Supply
System the software controls the heaters installed in the
Payload Segment to maintain the required temperatures
for operating the experiments.
Payload Supply
System
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 9/11
4. GROUND SEGMENT OVERVIEW
TET – Ground Segment Overview
Launch
Service
Provider
Launch
Service
Provider
11 Users / Experiments:2 GPS-TechExperiments3 New Generation Solar Cells
4 Space-BusExperiments1 BatteryTechnology1 IR-Camera (BIRD-heritage)
11 Users / Experiments:2 GPS-TechExperiments3 New Generation Solar Cells4 Space-BusExperiments
1 BatteryTechnology1 IR-Camera (BIRD-heritage)
PayloadData CenterNeustrelitz
DFD-BN
Payload DataCenterNeustrelitz
DFD-BN
Neustrelitz
O‘Higgins
(Antarctica)
German RemoteSensingData Center
DFD-BI
CSA -CanadianSpace Agency
CSA -Canadian
Space Agency
SKT, SHB (Canada)
Weilheim
German Space OperationsCenter
GSOC
FlightDynamics
FlightOperations & Management
Communications
& GroundStations
LEOP and Routine Operations
Launchand Early Orbit Phase only
Figure 20: TET Ground-Segment Overview
Ground Segment project management, integration, test
and training as well as all LEOP activities, routinemission operation and satellite control will be
performed at the German Space Operations Center
(GSOC).
Interfaces are established to the German Remote-
Sensing Data Center (DLR-internal) and to external
partners such as the launch-provider (data-exchange)
and to the Canadian Space Agency (CSA) as provider of
additional ground-station for LEOP-support. This isdone on a co-operative basis (no exchange of funds), as
DLR-GSOC supports Canadian missions with its
resources.
DLR-owned S-Band ground stations in Weilheim,
Neustrelitz and O’Higgins/Antarctica (for LEOP only)provide the necessary access to the satellite in all
mission phases.
This ground station concept based mainly on DLR-
owned resources is one of the reasons for cost-effective
project design. However, operational requirements
sometimes need to be tailored to the available uplink-
and downlink resources.
A so called Payload Data Center (PDC) will be
provided at the location of the data reception station in
Neustrelitz. The main tasks are acquisition, extraction,
processing (formatting to a generic ASCII format)
archiving and provision of payload data.
The 11 users with their experiments onboard TET-1retrieve (download) their data via a secure FTP
interface. The main goals for the design andimplementation process of the Ground Segment can be
summarized as follows:
- Minimize number of project-specific systems and
tools
- Make use of multi-mission core systems (Mission
Data System, Flight Dynamics, networks,…)
- Use of multi-mission documentation and combining
documents reasonably
- Efficient pooling of multi-project resources and
personnel
Figure 21: TET Ground Segment Functional Structure
and Interfaces
Above figure illustrates the main functions of the
ground-segment and their interfaces. The core element –
the so-called Mission Data System (MDS) – is already
fully operational and available and just needs to be
configured for TET. The only exception being the
Mission Information Base (MIB) which is specific for
each project as it contains the definitions of TM and TC.
5. MISSION OPERATIONS
For the TET-1 mission the ground-segment will
basically provide the execution of all necessary
activities for a sound operation of the space segmentand a continuous survey (Monitoring & Control) of
functionality and integrity of all project elements. DLR-
GSOC will perform this for all mission phases after
launch for both the space segment and the ground
segment.
During the mission preparation phase detailed analysis
and planning of the mission operation will be
undertaken and the operations processes will be
designed, implemented, tested and validated. In the
LEOP, bus commissioning- and routine operations
phase telemetry data of the satellite and payload status
is received and processed and telecommands for
controlled changes of the satellite are sent. Onboard
power and data storage availability, S/C attitude andpayload requirements for previously scheduled payload
events are compiled and executed.
In preparation for this, training sessions will be
performed during project-phase D for all operations
personnel at DLR/GSOC. The training comprises of
class room and simulation sessions.
Due to the BIRD-heritage, the operational ground
processes are already largely known to the experienced
operations personnel at the control center GSOC and at
the PDC in Neustrelitz.
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 10/11
TET – Ground Station Network and orbital injection
LEOP: LEOP and Routine:
Saskatoon(CSA) St. Hubert (CSA) Neustrelitz (DLR-DFD)
O‘H iggins (D LR -D FD ) Wei lheim (DLR-GSOC , 2 x TM/TC )
Figure 22: TET-1 Ground-Station Coverage and Orbit
Tracks
After launch and successful orbit-injection andseparation of TET from the launcher, GSOC is
responsible for execution of early orbit operations.
Above figure illustrates the first orbits after launch and
the related coverage zones by the available ground-
stations. LEOP is characterized as follows:
- Launch from Baikonour with Soyuz as secondary
payload (“piggy-back”)
- Separation from Fregat upper-stage after injection
in desired orbital altitude. Separation location is still
TBD
- Spacecraft initiates automatic activation sequence
and transits to safe-mode (attitude, power, thermal,communication)
- Initial acquisition of signal over DLRs O‘Higgins
(Antarctica) or Weilheim (Germany) ground-
stations
- Begin of orbit determination process utilizing
tracking data gained from the ground-station in
Weilheim respectively from the external LEOP -
support stations
- Start of checkout and ground-commanded
configuration activities
- Support by 2 Canadian ground-stations begins after
4 orbits
- LEOP and bus commissioning duration: 7 days- followed by activation of payloads and their
checkout
- The routine mission operation and satellite control
will be performed by GSOC engineering personnel
during normal working hours with the support of a
multi mission flight operations team (MMFS-team)
responsible for shift operations as required. Three
different pre-defined operational scenarios are
identified to the present:
- General activities on a weekly basis,
- Additional activities during 4 days once per month,
- Specific activities during 2 days at start and end of
mission.
Routine operation is characterized as follows:
- Ops-planning, health-monitoring and onboardmaintenance at GSOC
- Upload of time-tagged executable commands to bus
and payload: 3 days in advance, weekly cycle
- Commanding and TM-reception: once per day via
Weilheim ground-station- Upload of S/W and maintenance on request
- Download of data (payload and bus): 4 times per
day
- Data reception and processing at Payload Data
Center: automatic, 7 days a week
Operational tasks and responsibilities within the ground-
segment during mission conduct:
- The DLR ground station in Weilheim will serve as
main uplink (TC) and housekeeping telemetry
reception (HK-TM) station.
- The DLR ground station in Neustrelitz will be used
as main downlink station for payload data
- S-band data will be routed in real time from
Weilheim and Neustrelitz to the Operations Center
in Oberpfaffenhofen (GSOC) and all raw data will
be stored at the receiving ground-stations for a
limited period.
- Calibrated housekeeping data (i.e. uplink and
downlink) will be archived at DLR/GSOC and canbe used at GSOC for offline analysis, while payload
data will be formatted to an additional generic
ASCII format, provided and archived at Neustrelitz
together with the raw instrument sourcee packets
and other auxiliary data products
- Mission control, preparation and execution of
flight-operations, health-monitoring and
performance analysis is performed at GSOC, as
well as permanent orbit determination utilising
- GPS data and ‘station predicts’ will be generated to
support acquisition of the satellite by the ground-
stations.
- Initially, a dedicated control team consisting of engineers and spacecraft-operators will conduct
LEOP and the initial commissioning phase (1-3
weeks, depending on mission progress).
- A soon as spacecraft and experiment activation and
checkout are completed, all operations is transferred
to the multi-mission environment – this refers to the
control-facilities (consoles, control-room) as well as
the operations concept (monitoring and control
done by the Multi-Mission-Flight-Support-Team
under offline and on-call supervision by engineers).
8/2/2019 4S_Paper_TET_Rhodos_080526
http://slidepdf.com/reader/full/4spapertetrhodos080526 11/11
The above outlined operations concept for TET based
on DLR-internal resources and on the multi-mission
approach will make the most efficient use of the
existing facilities, processes and teams as TET will beanother mission added to the pool of presently 5
satellites permanently operated at GSOC.
6. SERVICES AND PRODUCTS
All users with experiments onboard TET-1 will beprovided two payload data sets with different formats on
a ftp-server. The Payload Data Centre (PDC) processes
the received payload data during and immediately after
data reception, which is planned 4 times a day.
The products (instrument source packets in raw binary
form and as ASCII text file) will be made available at
the ftp server 15 min after finishing data reception,
secured by protected and selective access.
The format of both payload data products for all 11
users is identical, while contents differ of course.The user additionally receives all auxiliary data
(required for calibration purposes or additional
processing) provided by GSOC via the same interface.
All data is stored on a permanent archive and a function
for later retrieval is provided.
Table 4: TET Ground-Segment Data Products
One genericformat for allusers, contentsspecific.
User Specific(pass-wordprotectedaccess)
ASCIIConverted File
Generic format,but specificcontent foreach user
User Specific(pass-wordprotectedaccess)
BinaryRaw InstrumentSource Packets(ISP)
PayloadData
variousNot restrictedASCII- Logs
Not restrictedASCII- Bus-HK-data(including NVS)
Not restrictedtbd- Attitude
Not restrictedtbd- Orbit
Not restrictedtbd- Ops-planningand as flown
AuxiliaryData
RemarkAvailabilityTypeContentDataProducts
One genericformat for allusers, contentsspecific.
User Specific(pass-wordprotectedaccess)
ASCIIConverted File
Generic format,but specificcontent foreach user
User Specific(pass-wordprotectedaccess)
BinaryRaw InstrumentSource Packets(ISP)
PayloadData
variousNot restrictedASCII- Logs
Not restrictedASCII- Bus-HK-data(including NVS)
Not restrictedtbd- Attitude
Not restrictedtbd- Orbit
Not restrictedtbd- Ops-planningand as flown
AuxiliaryData
RemarkAvailabilityTypeContentDataProducts
7. SUMMARY
The TET-1 mission is a national program funded from
the German Space Agency. The TET program started
with Phase A in January 2005, which ended October
2006. The TET-1 Phase B started in June 2007,
followed by a successful SRR in August 2007 and was
completed after the PDR beginning 2008. With PhaseC/D Kick-off in May 2008 and the launch date mid of
2010 not only the satellite has to be ready within two
years also the ground segment and the launch segment.
The goal of TET is the support of German industry and
research institutes with the on-orbit verification of new
and innovative satellite technologies. For this purpose
regular and reliable flight opportunities shall be offered,
which can be realized on short notice. TET shall provide
the required verification platform and shall be based on
a satellite bus which was qualified on orbit during the
BIRD mission.
The launch of the first satellite, TET-1, is scheduled formid 2010. In total, eleven different payloads were
selected to be demonstrated on TET-1. These include
optical experiments such as an infrared camera as well
as novel solar cells, batteries, on-board computers, GPS
receivers and a propulsion system.
After the LEOP and commissioning phase, the one year
mission operation will begin. Payload data will be
transmitted to the TET ground segment and provided to
the experimenters via the Payload Data Center.
8. REFERENCES
1. E. Lorenz and H. Jahn, BIRD: more than 3 years
experience in orbit; Small satellites for Earth
Observation, Selected Proceedings of the 5th
International symposium of the International
Academy of Astronomics, 102-109 (2005)
2. Sergio Montenegro and Felix Holzky:
BOSS/EVERCONTROL OS/Middleware Target
ultra high Dependability; DASIA2005, 30th May –
2nd June 2005 Edinburgh, Scotland
3. Z. Yoon, T. Terzibaschian, C. Raschke: OptimalThree-Axis Attitude Control Design, Simulation
and Experimental Verification for Small Satellites
Using Magnetic Actuators; Small Satellites
Systems and Services - The 4S Symposium; 26-30
May 2008
4. S. Roemer, T. Terzibaschian, A. Wiener, W.
Bärwald: Expertises with the BIRD ACS test
facility and the resulting design of a state of the art
mini- and micro-satellite ACS test facility; 6th IAA
Symposium on Small Satellites for Earth
Observation; 23th - 26th April 2007