46274432 Key Concept and Formulas for PMP Exam (1)

Embed Size (px)

Citation preview

  • 8/12/2019 46274432 Key Concept and Formulas for PMP Exam (1)

    1/4

    Key Concept and Formulas for PMP Exam

    Earn Value Formulas

    PV (Planned Value) = BCWS (Budgeted Cost of WorkScheduled

    EV (Earned Value) = BCWP (Budgeted Cost of WorkPerformed)AC (Actual Cost) = ACWP (Actual Cost of Work Performed)SV = EV PV (minus is ehind schedule)

    CV = EV AC (minus is o!er udget)SP" = EV#PV ($ess than % is ehind schedule)CP" = EV#AC ($ess than % is o!er udget)EAC = AC & (BAC'EV) se hen !ariances are at*+ical

    EAC = AC & ,(BAC'EV)#CP"- se hen !ariances aret*+ical(.ote/ 0his is the same as EAC = BAC#CP")VAC = BAC EAC

    E0C = BAC EV se hen !ariances are at*+icalE0C = (BAC EV)#CP" se hen !ariances are t*+icalE0C = EAC AC se hen original estimates ere flaed

    Project Selection Financials

    .PV (.et Present Value) = FV#(%&r)nFV= Future Value1 r= interest rate1 n= no2 of time +eriods

    3igher .PV is etter"44 ("nternal 4ate of 4eturn) = Sol!e the .PV e5uation for6r7Also called 3urdle 4ate

    3igher "44 +ercentage is etterBC4 (Benefit#Cost 4atio)

    3igher BC4 is etter2Beare1 e8am can call it CB41 here loer is etter

    49" (4eturn on "n!estment) = Earnings#"n!estment3igher 49" is etter

    Pa*ack Period = 0ime to reco!er cost of the +ro:ect$oer +a*ack +eriod is etterCash Flo = Cash "n Cash 9ut

    .etork ;iagramPrecedence ;iagramming e using either 0hree'Point Estimates orCP