Upload
ngophuc
View
216
Download
0
Embed Size (px)
Citation preview
43rd CIGRÉ Biennial Session (22nd - 27th August 2010)
The International Council on Large Electric Systems attracts international
delegates to France’s beautiful Capital City of Paris
CIGRE’s 43rd General Session since it’s formation in France in 1921 was held in Paris
in the final week of August 2010. This International Conference and Exhibition on
Large High Voltage Electric Systems continues to attract an increasing number of
international delegates with some 3005 travelling from over 82 countries. The five-
day Technical Programme of the Conference was this year supported by a record
number of 130 Exhibitors representing the industry’s manufacturers, utilities,
consultants and service providers from around the world. The magnificent Palais des
Congrès de Paris was once again the venue for all events, a very attractive and
convenient location from which to walk to the Arc de Triomphe and visit many of
Paris’s famous landmarks
These General Sessions, held every two years in Paris are reputed to be the world’s
largest platform for the electricity industry experts to share their knowledge, expertise
and experience. In 2010 the electricity industry again faces major challenges in order
to satisfy the increasing demand for an economic, reliable and secure of electrical
energy at a time when the global fossil fuel resources are rapidly diminishing. Many
forms of sustainable renewable energy systems have been developed and are now
being commissioned in order to comply with the global and national aims to limit and
reduce global warming.
The content of this year’s Technical Programme therefore addressed all the challenges
presented from the need to interconnect large renewable energy projects to
transmission systems, to the large scale transmission system interconnectors that
employ the latest HVAC and HVDC technologies. The Programme benefits from
CIGRÉ’s organisational structure by presenting the latest developments linked to the
key components of the transmission system namely, rotating machines, substations,
transformers, overhead lines and cables moving forward to consider system design,
2
operation, control, management and performance. The benefits available from the
advanced information and telecommunication systems technologies now in wide-scale
use in the industry were also included in the Programme as they play an increasing
role in the industry and in particular in the development of ‘Smart Grids’ now being
considered by transmission and distribution utilities.
The CIGRÉ General Sessions continues to offer every attendee the opportunity to
benefit and share the knowledge and experience available from the industry’s experts
on all aspects of research, manufacturing and utility management. As previously the
Technical Conference this year was well programmed addressing all the major issues
in the sixteen Specialist Subject Sessions. Therefore, every attendee was given the
opportunity to contribute and participate in the discussions with the industry experts.
Opening Ceremony and Keynote Address
The Opening Ceremony held on Sunday afternoon 22nd August 2010 was followed by
Keynote Address entitled “Initiatives by the Power Industry towards Low Carbon
Emission Society ” given by Mr. Shosuke Mori, Former Chairman of the Federation
of Electric Power Companies of Japan (FEPC) and current Chairman of the Board of
Directors for the Kansai Electric Power Company Inc. The key points of his Address
were as follows: -
“While accepting the need for minimizing the emission of carbon dioxide and the
need for optimal utilisation of the existing fossil fuel sources, Japan a country lacking
in natural energy resources is faced with a dilemma. By concentrating on achieving
energy savings as a result of high energy efficiency, Japan is now one of the lowest
carbon emitting societies in the world.
Japan is trying to establish a Law for the Prevention of Global Warming, legislation
that will address carbon tax, promote emission trading and feed-in tariffs for
renewable energy generation projects. The electric power companies have introduced
the ‘triple E’ concept, namely, Energy security, Economy and Environmental
protection. Nuclear power generation is now regarded as the key ‘triple E’ solution
but ultra-super critical coal fired plants and advanced combined-cycle gas turbine
plants are still being installed.
3
The high economic growth in the 1960’s has resulted in ageing transmission and
distribution assets that are now in need of replacement or refurbishment to achieve
increased efficiency. Consideration of the demand side is expected to lead to energy
savings and reduced emissions from fossil-fuel plants.. In addition to heat pump
technologies for space heating, electric vehicles or plug-in electric vehicles have the
potential for the economic reduction of emissions.
Outlining the Smart Grid situation in Japan, Mr. Mori said, “The challenge
corresponded to a movement towards the huge installation of renewable energy
generation, especially photo-voltaic cells”.
The Government has set an ambitious target of 28GW of photovoltaic cell capacity by
2020, some 15% of the total system demand. This could give rise to surplus power
and frequency disturbances creating major challenges for power system operation as
significant output from the installed solar power would not be required during off-
peak periods when nuclear and hydro-power plants continue to generate. The
Japanese grid has developed the first installations of variable-speed pumped-storage
hydro-systems which could be used to control generated power rapidly and used as a
power storage system.
Therefore while enhancing clean and stable nuclear power generation the unstable
output from photovoltaic cells will be compensated by a new control system. This
system will regulate load following power plants and power storage equipment such
as batteries and variable-speed pump storage hydro power plants and predicting the
output of solar power generation thereby creating Japan’s ‘Smart Grid’
CIGRÉ President
André Merlin (CIGRÉ President) then expressed his thanks to Mr Mori before giving
the CIGRÉ members in attendance an update of the activities since 2008. Membership
had continued to grow and totalled 11,200 equivalent members by the end of 2009,
Asia and South America being the areas responsible for this significant increase. The
number of National Committees is now 57 and CIGRÉ membership now extends to
89 countries.
4
In recognition of their significant contributions of services to CIGRÉ, the CIGRÉ
Medals were awarded to Professor Schramm (Germany) and to CIGRÉ’s retiring
Secretary General, Jean Kowal. At this point the newly appointed Secretary General
Mr. Francois Meslier was introduced to the audience. Before declaring the CIGRÉ
2010 General Session open, the President honoured paying tribute to the four former
CIGRÉ Presidents in attendance at the Ceremony, namely, Mr. Jerzy Lepecki
(Brazil), Mr. Michel Chamia (Sweden), Mr. David Croft (Australia) and Mr. Yves
Filion (Canada).
Technical Meetings Programme
The Technical Programme started on Monday 23rd August with two Major Sessions
that always attract the majority of the Conference delegates. This year the first-day
Opening Panel addressed ‘The Need for Technology & Intelligence in the Future
Power System’ in the morning, with the Workshop on ‘Large System Disturbances’
taking place after lunch.
The Need for Technology & Intelligence in the Future Power System’
This Meeting comprised of presentations by speakers from EPRI –USA, Switzerland,
ABB and Australia that covered the spectrum encompassed by the term ‘Smart Grid’
under the following titles: -
• Future Energy Networks – A Vision
• Towards a Smarter Grid: ABB’s Technology Perspective
• CIGRE’s Role – Shaping the Future
• Industry Smart Grid Interoperability – From Roadmap to Action
It was apparent that all the speakers shared a common vision on ‘Smart Grids’ namely
that there was a need to ‘Enhance Efficiency, Engage Customers, Ensure Reliability,
Enable Renewables and Electric Transportation’ . The means by which these goals are
achievable will vary due to the regional differences in electricity demand and
differences in the regional starting points and priorities that have already been
adopted. The various forms of renewable energy were reviewed highlighting their
benefits and disadvantages before presenting the range of existing and new
technologies that can be used to create the Smart Grid. These include technology to
5
improve system intelligence, the application of UHV-AC transmission as in China,
increased use of HVDC transmission whilst taking advantage of the power electronic
devices, new cable technology and wide area control systems (WAMS and WACS)..
For the end-user more smart devices are required to be compatible with the smart
intelligent AMR and AMI energy metering equipment available. The presentations
included a number of examples of the Smart Grid Demonstration projects that feature
smart homes, distributed energy systems, use of electric vehicles and smart
substations etc. Research and development will play a major role if pre-determined
targets are to be met with the need for new systems for operation and control,
protection installation of storage systems and an increasing use of underground cable
networks. Currently, the CIGRÉ Study Committee are actively involved with all the
Smart Grid issues and will continue to play a major role in identifying the solutions
and specifying the equipment to create the ‘Future Energy Networks’.
Workshop (Monday pm) – ‘Large System Disturbances’
This Workshop discussed the latest large disturbances that are normally includes
those caused by natural disasters and human errors. The seven disturbances presented
at this year’s Workshop were almost entirely linked to the extreme weather conditions
experienced in different parts of the world in the period 2009 to 2010.
France/Spain January 2009 – The severe storm ‘Klaus’ that developed into a cyclone
was the worst experienced for 25 years caused extensive damage to the transmission
systems in Spain and France. In Spain the 200 km/hr (125mph) wind speeds caused
the collapsed of a number of 400 kV and 220 kV transmission line tower. The 233
recorded disturbances on transmission system resulted in actions being taken to
minimise the loss of system security. In France the 20 hour duration storm resulted in
115 substations and 116 overhead lines being isolated following the damage to the
overhead line system. The improvements made following the severe storm in 1999
however helped the system to withstand this storm.
Australia (January/February 2009) – The unprecedented heat wave conditions
experienced in south-east Australia resulted in massive bush fires in the Melbourne
Area, which in addition to the loss of human life caused severe damage to the 500kV,
330 kV and 220 kV transmission lines. These multiple circuit failures had an adverse
6
impact on transmission security and the reserve planning strategy that being based on
1 in 10 year conditions proved inadequate. Action is therefore planned to review
design standards to withstand more extreme heat wave conditions as they also de-rate
circuit ratings.
Brazil (November 2009) – The major incident in Brazil that caused the loss of 40% of
the system demand and loss of supply to 50 million customers was excessive rainfall.
This caused multiple tripping of 765 kV transmission lines and flashovers resulting in
under-voltage and under frequency load shedding. Post-fault investigation revealed
that the inability of insulators to remain effective when subject to a rain intensity of
3mm/minute i.e. this reduced the flashover strength by 30%. Since this major outage,
booster sheds have been installed extensively on the transmission system.
Portugal (December 2009) – The REN transmission system in the Algarve and Lisbon
regions of Portugal were subjected to two storms that caused severe damage to the
supporting towers. This was the first time in 60 years that the towers had failed due to
wind speed but with record wind speeds of 220-km/hr (137 mph) they were
considerably in excess of the 150km/hr (93 mph) design wind speed. Some 350,000
customers were disconnected but 95% were re-connected within two days. The cost of
reconstruction was almost €10million.
Northern Ireland ( January 2010) – The snow and ice-storm caused extensive damage
to the 11kV distribution network but the transmission system suffered no physical
damage apart from experiencing numerous transient faults and circuit-breaker
operations on the 400 kV and 275 kV systems. The utility took six days to reconnect
the 130, 000 customers who lost supply, this extended time being due to the loos of
RTU’s caused by the storm.
The transmission system in China has increased rapidly with the China Southern
Power Grid Company (CSG) supplying 2.3 million customers, 18% of the population.
As the load centres are remote from the source of generation the transmission lines are
extremely long and as a result of the number of lightning incidents experienced, the
CSG reported that they have invested in defence schemes ranging from normal under-
frequency load shedding to the use of Wide Area Control Schemes (WACS).
7
The major European incident in November 2006 (loss of supply to Western Europe)
has resulted in a number of changes to the operating rules of the former UCTE now
ENSTO-E, to ensure that each TSO has a greater awareness of the operation of
adjacent grids. . An information platform that allows all TSO’s to observe in real-time
the actual state of the whole UCTE system has been commissioned in order that
TSO’s can quickly react in the event of a large disturbance.
The events discussed in this Workshop serve to illustrate the variety of unpredictable
natural events that can occur. Therefore all transmission system operators should have
system restoration and emergency plans in place in order to cope with these events
that are not likely to diminish in the foreseeable future.
Conference Technical Programme
.The Conference Technical Meetings comprised a four-track programme that started
on Tuesday 24th August 2010 that offered delegates the opportunity to select the
subject of their choice from the 16 - Discussion Group Meetings. These Meetings
discuss the Papers submitted for each of the specialist subjects that CIGRÉ’s Study
Committees selected for presentation. From more than 570 Papers received from
authors around the world the CIGRÉ Technical Committee selected 414 Papers for
discussion. As always these Technical Meetings were well structured to include short
contributions from authors and delegates, who address the key issues and queries
identified by the Study Committee’s Special Reporter in advance of the Meeting. This
form of Discussion Meeting management gives each Chairman the opportunity to
invite delegates in attendance to contribute to the discussion with the authors of the
Papers presented.
The following Table shows the timetable for the Technical Meetings during the four-
track programme that ran from the 24th to 27th August 2010
8
Date Special Subject
(No. of Technical Papers submitted to the Study Committee for each Session)
Tuesday 24th August
A3 – High Voltage Equipment (25 Papers) B4 - HVDC and Power Electronics (26 Papers) C4 - System Technical Performance (25 Papers) C6 - Distribution Systems and Dispersed Generation (23 Papers)
Wednesday 25th August
A2 – Transformers (29 Papers) B2 - Overhead lines (27 Papers) C5 - Electricity Markets & Regulation (22 Papers) D2 - Information Systems and Telecommunication (28 Papers)
Thursday 26th August
A1 - Rotating Electrical Machines (22 Papers) B1 - Insulated Cables (28 Papers) B5 - Protection and Automation (26 Papers) C1 - System Development and Economics (26 Papers)
Friday 27th August
B3 - Substations (26 Papers) C2 - System Operation and Control (26 Papers) C3 - System Environmental Performance (21 Papers) D1 - Materials and Emerging Test Technologies (25 Papers)
Tuesday 24th August
A3 - High Voltage Equipment
This Discussion Session which was very well attended addressed three Preferential
Subjects as follows:
1. Development of HV equipment to cater for increasing system demands – Papers
from China and India the two countries leading the world in the design, construction
and operation of UHV AC and DC transmission system presented complete design
details of the projects now in operation. The former USSR designed circuits for 1200
kV operation but these were operated at 750 kV and Japan has made significant
progress in this field with a transmission line constructed for 1100 kV operation ready
for commissioning at the design voltage in 2015, Detailed design and operational
information was presented on voltage variations, the transient over-voltage specified
for surge arresters together with data on the switching methods employed for
controlling transformers, overhead lines etc.
2. Lifetime management of HV equipment – This subject promoted a number of
contributions recording the failure rates of equipment operating in the voltage range
110 kV to 750 kV. The discussion was centred on whether this was caused by a
change in asset maintenance from TBM to CBM. The value and experience of
diagnostic techniques, on-line systems, economics and safety issues were all
discussed as utilities seek to extend the life of existing assets. Experience and
9
knowledge was shared by the Paper presenters and delegates during the discussion
period at this Session.
3. Prospects for introduction of new HV technologies – The Papers presented covered
vacuum circuit breakers (VCB’s), fault current limiters, instrument transformers and
composite hollow insulators. The differences in the choice of switchgear was a key
point discussed as the practice varies from VCB’s in China and Japan to the use of
SF6 switchgear in Europe and the USA. The mechanical reliability of these two types
of switchgear was also questioned. Various issues relating to the design and testing of
fault current limiters and limited operational experience was presented on their
application and operation. The performance of composite hollow insulators was
reported to be satisfactory but at present type-tests fail to specify the mechanical load,
which is regarded as the most critical design feature. At present this type of insulator
has only been available for installation for a relatively short period so as yet there is
no indication on the length of their service life.
B4 - HVDC and Power Electronics:
This Session which attracted 26 Papers was presented as three Preferential Subjects:
1. Developments in HVDC and FACTS technology – The development of 800 kV DC
was the centre of discussion particularly the excessive creepage distances required for
bushings and insulators etc. The contributors to this Session provided considerable
information over a wide range of topics and the experience gained from the new
800kV systems will provide a valuable contribution to establishing new standards.
Hydro-Quebec presented a paper reporting on the operation of the Quebec and New
England multi-terminal dc system that operates for up 50% of the time in multi-
terminal mode. A number of contributors reported similar satisfactory operational
experience reporting on the protection used when a large number of converters are in
circuit.
2. HVDC and FACTS – operating experience and new projects - Examples of
schemes employing FACTS devices to improve system performance were presented
by contributors from France and Brazil. Also an example of the increased power
transfer capability following the installation of a series compensation scheme and an
SVC in Finland was presented. The need for stringent harmonic filtering equipment
was emphasized by a project in Brazil when problems arose due the different
specifications specified by two different system operators. Similar, specifications are
also necessary when the insulation co-ordination and converters are designed and
10
supplied by different vendors. Further design features discussed were problems with
indoor converter stations in locations subject to salt pollution and the difficulty
experienced with fire regulations if combustible insulation/fluids are used. These
problems were illustrated by projects in Japan and Spain.
3. HVDC and FACTS project development issues. – The use in HVDC systems of an
earth return and ground electrodes were presented by contributors from Brazil and
India together with audible noise problem from the air-core reactors on the Caboro
Bassa project were among the problem issues raised in this Session. When discussing
the regulatory, licensing, project funding and technical risks, the Madeira system
project was presented as a model, but not an easy example of a multi-owner, multi
funding project.
C4 - System Technical Performance
This Session which discussed 25 Papers in three Preferential Subjects attracted some
150 delegates.
1.EMC/EMF and Power Quality for future networks - Harmonic emissions emanating
from HVDC installations, the measurement of harmonics and harmonic losses
featured in the first part of this session. The sources of new emissions for example,
wind power, distributed generation and compact fluorescent lamps now impact on
power quality measurements The presentations indicated that in the European systems
there has been no significant change in emissions during the last decade, but time was
given to discussing how to handle and evaluate the huge volume data now available
on power quality data collected by the range of monitoring equipment in use.
2. Advances in insulation coordination and lightning knowledge for improved
performance of modern electric power systems. – This subject was considered in three
topics, stresses that influence insulation performances, dielectric and environmental
stresses. There were a variety of contributions relating to the stress issues including a
comparison of helical and straight profile silicone insulators that gave equivalent
pollution performance under identical conditions. This was followed by a discussion
on lightning modelling where more work is required for use when considering UHV
systems.
3. Techniques and Tools for power balancing assessments and risk-based security
assessment. – The emerging tools and techniques that relate to power system analysis
were particularly welcomed by the delegates in the light of the discussions on ‘Smart
Grids’. Many of the existing simulation programs were discussed highlighting both
11
their merits and limitations. There appeared to be unanimity amongst the contributors’
that all models should be clearly presented so that the users are aware of all the
limitations. Finally attention was drawn to the increasing application of mathematical
and probabilistic theories for the assessment of power system security, planning and
operation but as yet more research and development is required before they can be
applied in the field.
C6 - Distribution Systems and Dispersed Generation
This Session attracted a large delegate attendance in view of the interest in active
distribution systems. Three Preferential Subjects were selected for discussion as
follows;
1 Planning and Operation – The goals and services provided by distributed energy
resources (DER) were presented together with the benefits in terms of voltage
support, frequency regulation and wind power variation. In addition to examples, it
was also reported that customers willing to support the smart grid initiative had
achieved energy savings of 10%. Work on networks with a large number of connected
distributed generation (DG) sources indicate that reactive voltage control was the
preferred option although the effectiveness is reduced on underground cable
networks. Hence, more research was recommended on the integrated voltage control
of distribution networks.
2. Demand Side Integration – Based on the discussions it can be concluded that the
potential for demand side resources is very significant with the Germany Energy
Association (VDE) suggesting that in Germany that there is 18GW of DSM available
from heating and heat storage. Furthermore the penetration of electric vehicles (EV)
in Germany was estimated to be two million vehicles. Based on the contributions
received which detailed a limited number of demonstration projects of the hundreds
currently in progress, there is a real need to coordinate the results in order to
maximize the benefits of these projects. Advanced metering is set to play an important
role in demand side integration but the discussions highlighted the need for an energy
interface device for homes and small business. Various solutions were presented
including an EPRI solution but standards remain a critical requirement at present.
3. New concepts and technologies for electrification of remote and rural areas. – The
main points on this discussion focused on micro-grids that are regarded as being
particularly suitable to rural areas with weak connections to the grid. For rural
electrification applications low cost technologies developed to extract power from
12
high voltage lines were presented. Auxiliary Services Voltage Transformers (ASVT)
offers a solution but this relatively low cost scheme is subject to poor voltage
regulation when remote from the source high voltage lines. The practical steps
required to encourage World Governments to tackle rural development on a
sustainable basis was discussed and reference was made to a number of reports to re-
think the rural development strategies. It was generally accepted that this was a matter
for World Governments together with the international community but identifying the
organization to take the lead on this difficult issue remains an unanswered question.
Wednesday 25th August
A2-Transformers
A total of 29 Papers were selected for this Session and such was the interest in
transformers 55 contributions were received for discussion. Three Preferential
Subjects were again established for this session as follows:
1. Transformer incidents in service. – This subject created great interest with
contributors from Australia, Japan and India reporting on the failures of transformers
and other substation equipment. A number of recommendations were made including
frequent oil changes in on-line tap changers and the replacement of bushings every 20
years to avoid failures. The advantages and disadvantages of the transformer
insulating medium were discussed at length as mineral oil is now being replaced by
the environmentally friendly ester fluids and silicone liquid. But no firm conclusions
on their respective benefits could be drawn from the contributions given by delegates
from the USA, Germany UK, France and Japan.
2. Transformer life – This subject prompted a number of contributions related to the
diagnostic testing and monitoring undertaken to predict the remaining life of a
transformer with valuable contributions from Sweden Canada and Germany.
Examples of the techniques used by utilities in Canada, Japan, and Zambia were
presented some suggesting that service life of the transformer could be beyond 60
years, but huge variations will occur as a result of the transformer loading cycles
while in service.
3. Transformer Modelling – this subject was addressed by a review of the transformer
modelling tools and techniques available with some presentations showing the
comparison between the models and transformers in service. The most interesting
contribution was from Korea where they identified four ‘thermal areas’, of
13
transformer engineering that they considered should be open for debate. They were
existing transformer cooling conceptions: cooling pipe-work arrangements, heat
exchangers; plate fin-type designed heat exchangers, suggesting that oil flow, oil flow
rates and temperature distribution need to be determined more accurately. A report
was then presented detailing the design and performance of a plastic oil-flow meter
designed to be positioned within the winding bottom end insulation system.
B2 - 0verhead Lines
This topic always attracts a large number of Papers and Conference delegates and this
year three Preferential Subjects were selected by the Study Committee:
1.Managing the environmental impact of new and existing overhead transmission
lines – This subject dealt with the practical aspects of overhead lines and reports on
new materials. EMF and audible noise dominated the discussion and evidence was
presented on the surface treatment of new conductors that can reduce audible noise.
Delegates received information on the different designs of supporting towers,
different types of structure, namely, wood, steel and concrete and the life-cycle
costs of these alternatives. Compacted tower configurations suitable for urban areas
and a comparison of losses of composite and standard conductors were presented as
this is often used when deciding whether to erect a new line or reconductor the
existing line.
2. Increasing the power capacity of existing overhead lines by conversion of AC to
DC or by increasing voltage levels.- Based on the contributions it appears that he
case for AC to DC line conversion is only economical for circuits longer than 100 –
200km (124 miles) and the care must be taken to limit the circuit outage costs. So
increasing the AC circuit voltage is generally the simplest and economical method
of increasing the circuit load transfer capacity. Reference was also made to the re-
use of foundations and towers bases in lines subject to AC and DC conversions as
the mechanical reliability needs to be much greater in order to be capable of higher
load transfers.
3.Assessment of overall electrical and mechanical availability of overhead lines. -
This subject was addressed by a variety of contributions from many parts of the
world. The non-destructive testing methods used in France and the Russian
Federation were described while in Brazil thermal and mechanical tests are used to
determine the ageing of conductors. Interest was shown in the subject of robots now
14
used for the inspection and maintenance of overhead line conductors, and in Brazil a
robot has been developed for the installation of warning devices. Methods to
determine overall circuit reliability were presented with Russia using line length and
its impact on failures, whereas in Brazil, a formula based on line length is used to
determine the circuit reliability.
C5 - Electricity Markets and Regulation
A total of 22 Papers were submitted for this topic that attracted some 200 delegates to
the auditorium. The discussion was planned with the Study Committee selecting three
Preferential Subjects:
1. Challenges of national or state regulations of transmission and system operators in
regional markets. – Organisation and governance in India’s first power exchange
market was just one of a number of contributions. Speakers from Europe, Brazil and
Japan dealt with issues ranging from capacity allocation to balancing markets.
2. Impact of Intermittent Resources or Demand Response on Market Designs: -
Contributions for Ireland, Italy, China and France were among the reports on the
impact of wind generation. All forms of renewable energy sources were presented
based on a number of US studies, while a Paper on the integration of storage
technologies on the New York wholesale electricity market completed the
presentations for this discussion period.
3. Interactions of environmental incentives and markets (e.g. carbon) with electricity
markets: - The key issues linked to CO2 emission trading system in China, the impact
of CO2 reduction targets on the power market applicable to the Italian and French
systems were the key contributions to this short discussion that attracted only four
Papers.
D2 – Information Systems and Telecommunications
This topic was discussed under two Preferential Subjects selected by the Study
Committee as follows: -
1. Practical implementation of IEC 61850 in electric power systems. - For this
discussion 17 Papers were accepted from 15 countries. Examples of the projects
employing the IEC 61850 protocol were presented by authors from a number of
European countries, India, South America and the USA. Further contributions
15
followed on the IT protocols used on topics as diverse as Wide Area Monitoring
Systems (WAMS) and Cyber Security.
2. Information and information technology (IT) security for power utilities: - This
topic again created wide-scale international interest indicating the number and variety
of incidents linked to cyber security. Contributions from Brazil presented the use of
merits of IT applications for system emergencies and cyber security, while in Japan
and Croatia action has been taken following cyber security incidents. Similar IT
security problems were reported by contributors from Romania.
Thursday 26th August
A1 – Rotating Electrical Machines
This Discussion attended by some 150 delegates was arranged under two Preferential
Subjects.
1. Developments in Electrical Machine Design and Experience in Service: - Nine
Papers were selected that presented a number of new design innovations and
excitation control systems and the advantages of indirectly hydrogen cooled
generators. Among the topics raised during the open discussion were the
environmental and health issues during plant manufacture and commissioning.
2. Life Management: - The topics accepted for discussion included use of monitoring
and diagnostics, refurbishment, improvement and site experience. Papers presented
were mainly linked to real-time condition monitoring with examples of optical and
vibration monitoring systems in Brazil and reports on continual partial discharge
monitoring and fault detection in rotor windings.
B1 – Insulated Cables
The Study Committee arranged the discussion of the 28 accepted Papers under three
Preferential Subjects
1. Technical challenges that have been overcome in newly installed underground and
submarine cable systems: - This well attended discussion included numerous reports
on the latest major underground and submarine cable projects ranging from NorNed
the longest submarine cable installation in the world to the feasibility studies linked to
the Malta – Italy subsea cable interconnector. Both AC and DC cable projects were
discussed together with the range of compact joints now available for jointing fluid-
filled to extruded cable.
16
2. Key factors in current and foreseen development of cable systems: - Among the
topics presented in this period were new innovative methods for laying cables and a
description of the forced cooling system designed to allow the uprating of 400 kV
cable in Vienna. Considerable interest was shown in a report from Japan that shows
the failure rate of their cable systems is lower than the worldwide statistics.
3. State-of the art and trends for cable system testing: - In this discussion period the
Papers covered a variety of topics linked to the on-site commissioning test used on
cable systems, the results of the Very Low Frequency (VLF) program applied by
utilities in the USA plus a report on a new monitoring system for partial discharge
(PD) detection developed for two 220 kV cables in Spain.
B5 – Protection and Automation
For this discussion the Study Committee selected two Preferential Subjects.
1.Protection, control and monitoring for the next decade – This discussion offered the
opportunity of leading manufacturers to present future developments in this field with
contributions from ABB, Areva, Siemens and Toshiba. This subject also attracted
papers from Egypt, Romania, China, Brazil and Argentina. Among the protection
systems presented were the Real-Time Dynamic Monitoring System (RTDMS) used
by the State Grid Corporation in China, thermal overload protection in Argentina,
wide area monitoring (WAM) in Romania and disturbance recording with the IEC
61850 protocol in Egypt.
2. Impact of renewable generation and cogeneration on substation automation and
protection – The majority of Papers discussed in this period were submitted by
manufacturers some with the support of utility contributors. A consortium of
manufacturers from Japan reported on protection systems for distributed generation
and manufacturers in USA and Canada, namely GE Global, GE Digital and
Powertech described a system for the optimal control of microgrid resources.
Cogeneration protection was presented by contributors from Romania while
contributors from Spanish utilities presented system protection systems for networks
with a high concentration of wind power.
C1 – System Development and Economics
This discussion centred on 26 papers which the Study Committee arranged as three
Preferential Subjects.
17
1. Solutions for planning power systems for a low carbon energy future. - There was
considerable international interest in this subject judged by the contributions that
came from academia, manufacturers and utilities. Probably the most significant
contribution was the European Wind Integration Study (EWIS) representing a number
of European utilities, supported by the grid integration of offshore wind turbines from
France. The economic and reliability issues were addressed in a paper authored by
General Electric Company.
2. New businesses processes to support/facilitate power system design for a low
carbon energy future. – The impact of wind power on the operation of large
transmission systems was the key issues that were presented by authors from China,
UK and Poland. The market benefits arising from wind energy was discussed in a
Paper from Australia but the only contribution linked to power storage was covered in
a contribution from ETH Zurich.
3. Asset management challenges/strategies (replacement, refurbishment and
maintenance) for a low carbon energy future. – A number of topics were presented in
this session with the large-scale integration of wind power into bulk transmission
systems being presented by utilities from Brazil and France. The contribution to a low
carbon energy future that a reduction in system energy losses offers is now being
studied in depth by the RTE, the TSO in France where 80% of all losses are attributed
to overhead lines and underground cables the remaining 20% being losses associated
with power transformers and substation auxiliaries.
Friday 27th August
B3 – Substations
The Study Committee identified three Preferential Subjects to form the basis of
discussion on substations
1.New techniques/New design of substations:- The average age of substations is
estimated to be some 40 years, hence supply security remain a key issue of the
network operator but this discussion period was dominated by contributions linked to
the equipment developments for 800 kV HVDC and 1200 kV HVAC systems. Two
contributions discussed examples of projects employing Gas Insulated Lines (GIL)
while a consortium of Japanese utilities and manufacturers presented a Paper on the
design of ‘Megacapacity’ underground substations.
18
2. Existing substations, new challenges: - A number of different approaches to the
application of new technologies were presented in this period. Again the Japanese
consortium of utilities and manufacturers outlined the technologies used to upgrade
and uprate substations, whereas in Switzerland the different technologies have been
subject to environmental analysis. New asset management strategies have been
introduced in Mexico to extend asset lifetimes while in Russia the maintenance of 110
kV GIS substations is used as an opportunity to upgrade the voltage to 220 kV. A
further contribution presented the steps being taken in India to provide the Mumbai
Megacity with a reliable supply.
3. New secondary system challenges in substations : -The impact of IEC 61850 had a
marked impact on this period with R & D based Papers from a consortium of German
manufacturers and from Korea, an intelligent and compact substation. Contributions
from Scandinavian utilities on the maintenance procedures required for IEC 61850
and the implementation of IEC 61850 on the Java-Bali transmission system in
Indonesia were the highlights of this period.
C2 – System Operation and Control
The 25 Papers submitted for this discussion meeting were allocated into two
Preferential Subjects by the Study Committee:
1. Enhancement of operational reliability:- The majority of the presentations were on
the monitoring and control of the power grid to enhance operational reliability.
Examples of Wide Area Monitoring (WAM) was the subject of contributions from
Korea, and the UK while the Southern Grid Company (SGC) in China employ a Wide
Area Damping control System (WADC). Further applications to improve operational
reliability were outlined in contributions from Russia who use an Automatic
Emergency Control system ( AEC), Dynamic Security Assessment (DSA) in Italy
while France and Belgium have adopted ‘Ampacimon’ to provide the real-time
dynamic ratings for the overhead transmission system.
2. Consistency and coordination of system control and operation: - Contributions to
this period illustrated the efforts being made to improve the coordination between
interconnected TSO’s. Examples were presented on the technical coordination
between TSO’s in Western Europe and also the European ENTSO –E system. Similar
action has been taken by the TSO’s connected to the Nordic System while in Brazil
19
the responsibilities of all the country’s TSO’s as now specified were outlined in the
discussion.
C3 – System Environmental Performance
For this discussion meeting the Study Committee chose two Preferential Subjects.
1. Innovative environmental studies for power transmission corridors: - The majority
of the papers discussed were linked to ways of reducing the impact of overhead
transmission lines. The Environmental Impact Studies (EIS) now forms a key issue in
the right-of way (ROW) negotiations and a number of major utilities reported on
actions taken to minimise environmental damage. In Finland the frequency of ROW
clearance has been extended; in France where the majority of transmission lines are in
woodland stakeholders are more actively involved in decisions, while in Brazil the
(Geographical Information System)GIS is now used in order to select potential routes
for transmission lines. In Norway, tower painting and low reflection insulators are
some of the camouflage innovations being used to reduce the visual impact.
2. External costs accounting of environmental and social impact of power generation
and transmission – The papers discussed were dominated by a number from Brazil but
overall all the contributions stressed the need to include the external costs associated
with the construction of transmission lines in the total project cost. In Brazil
compensation payments amount to 1% of the total cost and in California where
external costs were negligible in 1970 they now average some 5% of the project cost.
Projects. Studies in Italy indicate that in some circumstances the external costs can be
some 1.5M€/annum/km while studies by RTE in France suggest the cost of
environmental protection and local employment can range from 4% to 6% of the total
cost.
D1 - Materials and Emerging Test Techniques
The Study Committee arranged the discussion of the 25 papers under three
Preferential Subjects
1. New materials for improved efficiency and sustainability of AC and DC power
equipment – This period provided delegates with an insight into the research and
studies on new materials for transmission system applications. The need to upgrade
existing transmission lines in Egypt resulted in the utility selecting to use GAP
20
(unique construction) or INVAR (unique material) conductors. RTE reported on work
in France on a comparison of the properties and benefits of mineral versus ester
(vegetable oil) insulating oil which revealed no definitive conclusion. Looking ahead
work is in progress in Japan to develop new insulating materials and gases for
advanced gas insulated systems. Manufacturers reported on the properties of
composite insulators that require high quality fillers to ensure that adequate rubber
properties are maintained and research is in progress to evaluate the dielectric material
responses for highly stressed HVDC insulator design.
2. Challenges for testing and diagnostics – As power transformers are the key and
highest capital cost component of a transmission system they proved to be subject of
the majority of contributions in this period. Optical fibre sensors for temperature
monitoring, the merits of off-line and on-line UHF partial discharge monitoring,
furfurals in transformer oil, the use of dissolved gas analysis (DGA) to determine the
oxidation on mineral and ester insulating oils and the UHF techniques formerly
developed for use on gas insulated switchgear now being used on power transformers
were presented. In Mexico, studies on use partial discharge measurements at gas
insulated substations during commissioning and in fault analysis are now being used
as part of the complete range of diagnostic tools. Finally, joint R & D between Union
Fenosa and LCOE in Spain has resulted in the development of a mobile, compact unit
able to perform over-voltage tests on a complete substation i.e. transformer, GIS,
cables and accessories.
3. Endurance of materials especially in harsh electrical and physical environments. -
Two papers were accepted for this period, the first from Egypt presented the
deterioration of fibre reinforced materials caused by chemical and coastal pollution.
The utility who reported transmission lines in close proximity to chemical plants, the
use of fibre reinforced poles and composite insulators have identified that salt
pollution, sulphuric and nitric acids are the main causes of component deterioration
and failure. In Japan, R & D work is in progress to ensure the characteristics and
integrity of polymer insulated materials (cables) is sufficiently robust to comply with
the rigorous standards applicable to installation in the country’s Nuclear Power Plants
Poster Sessions
This year the CIGRÉ Organising Committee arranged six Poster Sessions that were
open to delegates from Tuesday 24th August to Thursday 26th August 2010. This gave
21
delegates the opportunity of a one-to-one discussion with the authors of the Papers
presented in A2, B3, B1, C1, C2, and D1 Discussion Meetings.
Technical Exhibition
The number of applicants for the CIGRÉ 2010 Technical Exhibition at the Palais des
Congrés exceeded the space available so the Exhibition but with 110 Stands
representing 22 countries it was the largest Exhibition ever staged at a CIGRÉ
General Session.
The Exhibition which remained open to all delegates during the five-day Conference
included displays and demonstrations by many of the world’s leading manufacturers
who develop, design and market the latest innovative equipment and technologies
designed to meet the current demands of the power generation and transmission
utilities. This year the manufacturers producing accessories, test equipment and
computer software had the largest number of Stands but all the world’s leading
manufactures were present displaying transformers, switchgear, overhead line
components and UHV and EHV cable systems.
The exhibitors presented the full range of equipment developed for smart grid
applications, sustainable energy solutions and details of the plant and equipment
installed on the most recently commissioned UHV and EHV transmission system
interconnectors in the world. So the Exhibition continues to be recognised as the
showcase that maintains and strengthens the vitally important links between research
institutions, manufacturers, end-users and the industry’s key decision and policy
makers. Hence, every CIGRÉ General Session attracts members and visitors from
around the world. This ensures that the interests of all sectors of the industry is
represented at this Conference.
(The Schedule of Exhibitors is attached to this Report)
CIGRÉ’s Perspective for the Future
Since CIGRÉ was founded in France in 1921, the objectives of this international
electricity organisation have remained unchanged but with the passage of time
changes have been made to respond to the growth and technical developments within
electricity utilities.
22
Currently on an international basis, the industry is faced with ever-increasing
investment programmes to supplement existing energy supplies and cater for the
continual growth in demand. Although CIGRÉ’s international forum now almost a
90-year reputation for developing technologies and establishing the industry’s
standards, the Technical Committee are now establishing the strategic directions for
the next decade. As a result of considering the factors that will shape the future of the
electricity industry four major strategic directions have been identified: -
1. The electrical power system of the future
2. Making the best use of the existing system
3. Focus on the environment and sustainability, and
4. Interactive communication and information.
CIGRE’s well-structured organisation has an increasing membership in over 89
countries that continues to attract the world experts who look forward to sharing their
diverse range of technical expertise with all their fellow professionals attending
CIGRÉ 2010.
(For full details on how to become a member of CIGRÉ and for information on
CIGRÉ’s on-going programme of activities, please visit www.cigre.org)
23
Schedule of Exhibitors
3M United States
www.3M.com/ACCR
ABB Ltd Switzerland www.abb.com ALROC SAS France www.alroc.fr AMA-SYSTEMS GMBH Germany www.ama-systems.com
American Superconductor – AMSC United States www.amsc.com
AREVA T&D France www.areva-td.com ARKEMA France France www.arkema.com BAUR Pruef- und Messtechnik GmbH Austria www.baur.at BCP Busarello + Cott + Partner AG Switzerland www.neplan.ch BPL Global France www.bplglobal.net Brugg Kabel AG Switzerland www.bruggcables.com CableCURE Germany www.cablecure.de CESI S.p.A. Italy www.cesi.it CIRED Belgium www.cired.net Coil Innovation GmbH Austria www.coilinnovation.at
Cooper Power Systems United States www.cooperpower.com
CYME International T&D Inc. (Cooper Power Systems) Canada www.cyme.com DALEKOVOD Croatia www.dalekovod.com DIgSILENT GmbH Germany www.digsilent.de DILO Armaturen und Anlagen GmbH Germany www.dilo-gmbh.de Doble Engineering Company Norway www.doble.com Dow Wire & Cable Switzerland www.dowwireandcable.com Dynamic Ratings Australia www.dynamicratings.com Efacec Portugal www.efacec.pt Electricité de France CIST France www.edf.com ELECTROTECNICA ARTECHE HERMANOS S.A. Spain WWW.ARTECHE.COM
Ellis Patents United Kingdom www.ellispatents.co.uk
Energy Support GmbH Germany www.energy-support.de FISO TECHNOLOGIES INC. Canada www.fiso.com FUGRO GEOID SAS France www.fugro.com
GE Energy United States www.itsyoursmartgrid.com
GLOBAL INSULATOR GROUP LTD. Russia www.gig-group.com Haefely Test AG Switzerland www.haefely.com Hapam bv Netherlands www.hapam.nl
High Voltage Inc. United States www.hvinc.com
HSP Hochpannungsgeräte GmbH Germany www.hspkoeln.de
IEEE Power & Energy Society United States www.ieee-pes.org
24
Ingeteam Transmission & Distribution, S.A. Spain www.ingeteamtd.com Iris Power LP Canada www.irispower.com ISA Europa Sarl France www.isatest.com JAPAN AE POWER SYSTEMS CORPORATION Japan www.jaeps.com JST transformateurs France www.jst-transformers.com KALKI Communication Technologies Limited India www.kalkitech.com
KEMA The Netherlands http://www.kema.com/events/Default.aspx
KoCoS Messtechnik AG Germany www.kocos.com KONCAR Croatia www.koncar.hr Lamifil Belgium www.lamifil.be Lapp Insulators GmbH Germany www.lappinsulators.de LIOS Technology GmbH Germany www.lios-tech.com Lumpi-Berndorf Draht-und Seilwerk GmbH Austria www.lumpi-berndorf.at Manitoba HVDC Research Centre Canada www.pscad.com Maschinenfabrik Reinhausen GmbH Germany www.reinhausen.com Maxwell Technologies SA Switzerland www.maxwell.com MEGGER France www.megger.com METAL DEPLOYE RESISTOR France www.mdresistor.com mica informationstechnologie gmbh Austria www.ohtlgrid.com
Mitsubishi Electric Europe B.V. United Kingdom http://global.mitsubishielectric.com/
Morgan Schaffer Inc. Canada www.morganschaffer.com Mosdorfer GmbH Austria www.mosdorfer.com MTE Meter Test Equipment AG Switzerland www.mte.ch Nanjing Nari-Relays Electric Co., Ltd P.R.China www.nari-relays.com
Narec United Kingdom www.narec.co.uk
National Electric Coil United States www.highvoltagecoils.com
Neoptix Fiber Optic Sensors, Inc. Canada www.neoptix.com NEXANS FRANCE France www.nexans.com nkt cables GmbH Germany www.nktcables.de OMICRON electronics GmbH Austria www.omicron.at Opal-RT Technologies Inc. Canada www.opal-rt.com Opsens Canada www.opsens.com OPTEN Russia www.optensolutions.com P.M.V. SYSTEMS B.V./DECISION SUPPORT ASSOCIATES Netherlands www.decsa.nl
Parsons Brinckerhoff United Kingdom www.pbworld.com/power
PFISTERER SAS France www.pfisterer.fr
PHENIX TECHNOLOGIES INC United States www.phenixtech.com
Power Diagnostix Systems GmbH Germany www.pdix.com
Power Line Systems Inc United States www.powline.com
Protecta Hungary www.protecta.hu PRYSMIAN CABLES & SYSTEMS Italy www.PRYSMIAN.COM
Psymetrix Limited United Kingdom www.psymetrix.com
Qualitrol Corporation United www.qualitrolcorp.com
25
Kingdom
Quintas & Quintas, Condutores Eléctricos, S.A. Portugal www.quintascondutores.pt RESEARCH&DEVELOPMENT&TESTING NATIONAL INSTITUTE FOR ELECTRICAL ENGINEERING - ICMET Craiova ROMANIA www.icmet.ro RTDS Technologies Inc. Canada www.rtds.com RTE - Réseau de Transport d'Electricité France www.rte-france.com RuggedCom Inc. Canada www.ruggedcom.com Schniewindt GmbH & Co. KG Germany www.schniewindt.de Schweitzer Engineering Laboratories Netherlands www.selinc.com SDCEM France www.sdcem.com SebaKMT Germany www.sebakmt.com SecuControl Produktions GmbH Germany www.secucontrol.com Sediver S.A. France www.seves.com SELTA SPA Italy www.selta.it SERGI France France www.sergi-france.com
SGB- Smit Group The Netherlands www.smittransformers.com
Siemens AG Germany www.siemens.com/energy Silec Cable France www.sileccable.com SOLVAY FLUOR GMBH Germany www.solvay-fluor.com Statnett SF Norway www.statnett.no STRI AB Sweden www.stri.se TAURUS POWERTRONICS PVT LTD India www.tauruspowertronics.com TOSHIBA Japan http://www3.toshiba.co.jp/power/index3.htm
Transmission & Distribution World Magazine United States www.tdworld.com
Trench France SAS France www.trenchgroup.com TYCO ELECTRONICS SIMEL S.A.S. France www.energy.tycoelectronics.com
UCA International Users Group United States www.ucaiug.org
Von Roll Transformers Ltd Switzerland www.vonroll.com Wacker Chemie AG Germany www.wacker.com WIKA Alexander Wiegand SE & Co. KG Germany www.wika.de ZENSOL AUTOMATION INC. Canada www.zensol.com ZIV APLICACIONES y TECNOLOGIA, S.L. Spain www.ziv.es
ooOOoo
Final Edit from Gerry George, International Editor
26th October 2010