Upload
griffin-golden
View
212
Download
0
Embed Size (px)
Citation preview
4 November 20101
CSCExcellence in Risk Management
QuantifyingCost and Schedule Risks
forMajor Energy Projects
PRMIA Luncheon Presentation4 November 2010
CSC Project Management Services200-321 19 Street NW. Calgary, Alberta. T2N 2J2
(403) 233-7994 [email protected]
4 November 20102
CSCExcellence in Risk Management
Major Project Blues
Over the last two decades, almost every major energy project has suffered significant cost overruns, significant schedule delays, and/or poor quality work.
Exceptions are rare and most projects that tout being “On Time and Under Budget” have re-cast schedules, significantly modified scope or revised base estimates.
The problem isn’t new. In the late 1980’s the Rand Corporation published a study showing that 80% of all major projects had significant cost and schedule overruns.
The problem is not restricted to the Alberta Environment, the oil industry, or to Canada. It is a global problem.
4 November 20103
CSCExcellence in Risk Management
Major Project Blues - the Issues
Major energy projects are truly colossal in scope. Capital costs are routinely in excess of $1 Billion, equipment is sourced world-wide, labour pools are stretched.
The boom in oil prices that drives new projects results in competing project impacts on everything from bulk materials to major equipment, from camp beds to hotel rooms and from field labour to construction management.
After many years of industry retrenchment, project management and construction supervision experience has been scarce. Owner groups are not resourced to deal with the issues driven by massive capital projects.
4 November 20104
CSCExcellence in Risk Management
Major Project Blues - the Solution
These major projects are being driven by economics. In order to capture the project value, a fully functioning (nameplate) project must be completed on schedule and within the capital budget.
The Project Team must identify and understand the wide range of risks facing them, and put in place an action plan that mitigates these risks. Failure to assess and identify risk issues will almost certainly doom a project.
The Project Team must bring resources to bear on the risk issues throughout the project execution life. As a project proceeds the risks change, and the risk management plan should reflect this changing reality.
4 November 20105
CSCExcellence in Risk Management
StrategicPlanning
ProjectDefinition
ProjectFinancing
Mid-Construction
ProjectStart Up
Year 1Full
Operations
ProjectExecution
Internal ReviewProject Execution Team
Operations Team
Risk Contractor Involvement
Risk Management Life Cycle
Corporate Planning
Corporate Review
4 November 20106
CSCExcellence in Risk Management
Risk Management:
• The most important risks and their impacts are identified and communicated to the project management and stakeholders.
• All sources of risk and opportunity are identified including “soft” items such as “organization performance” and “competing project environment”.
• Expert judgments about the likelihood of uncertain events are documented, and their impacts quantified.
• Budgets and performance targets are set at appropriate confidence levels, and areas for mitigation are identified and explored.
• Project strategies are tested in a “best case/worst case” scenario to analyze mitigation plans and alternatives.
4 November 20107
CSCExcellence in Risk Management
ProbabilityDistributions
Tornado Diagrams Step DiagramsInterview Issues Model and Test Options
Scheduled, Formal ReviewsUpdated Model Results(Probabilities, Tornados, Steps)Management Risk Reporting
Base Design & Operating Plans
Contingency Plans
Risk Monitoring
System
Project Targets Immediate RiskControl Measures
Risk Analysis
Risk Analysis is the centerpiece of a Risk Management Process
UncertainEnvironment
4 November 20108
CSCExcellence in Risk Management
The general Risk Analysis Process proceeds in a systematic sequence
1Frame
TheProblem
2DevelopAnalysis
Basis3
EvaluateThe
Risks4
InterpretThe
Results
RiskManagement
Recycle to Focus onMost Important Risks
ReviewAlternativeStrategies.
Identify allImportant Sources ofUncertainty.
Model how underlyinguncertaintiesinteract to influence outcomeson the Project.
Identify the Experts in eachof the uncertainvariables.
Assess the impact and theprobability ofoccurrence foreach uncertainvariable.
Calculate the uncertainty inthe key resultmeasures.
Quantify therisk & return for each scenario.
Analyze anddocument theresults.
Identifypreemptiveactions.
Developcontingencyplans.
Recommendactions.
5
4 November 20109
CSCExcellence in Risk Management
Framing the problem is often the most difficult but most valuable step in the process
• Project scope, basic assumptions, and cost & schedule milestones are identified.
• Strategic alternatives and logical development paths are identified, and decision criteria are defined.
• All project decisions (both made and not made), and the logical links between decisions, are identified.
• All risk issues and their potential impact areas for the project are identified.
4 November 201010
CSCExcellence in Risk Management
The Influence Diagram shows how the risks influence each other and their impact on the project. Correlations between variables must be properly captured.
Conditioning Variables
ImpactVariables
Results
CapitalCost
CapitalCost
MaterialRates
MaterialRates
OrganizationalPerformance
OrganizationalPerformance
RegulatoryEnvironment
RegulatoryEnvironment
CompetingProjects
CompetingProjects
ProductivityRates
ProductivityRates
RegulatoryDelays
RegulatoryDelays
OperatingCosts
OperatingCosts
LabourAvailability
LabourAvailability
ScopeChanges
ScopeChanges
WeatherDelays
WeatherDelays
ContractorRates
ContractorRates
ContractorDefault
ContractorDefault
OperatingRevenue
OperatingRevenue
ScheduleSchedule
NPVNPV
4 November 201011
CSCExcellence in Risk Management
Conditioning Variables
• Organization, Distribution of Authority• Continuity of Design, Coordination of Engineering• Information Gathering and Communication Tools• Baseline and Performance Measuring Tools• Contracting Strategies• Construction Productivity• Owner Involvement and Commitment
Organization Performance
Competing Project Environment• Labour Resources• Engineering Resources• Contractor Availability• Material / Vendor Shop Availability• Construction Equipment Availability
4 November 201012
CSCExcellence in Risk Management
Risk Variable Assessments
• Probability of a Cost Variance, a Specific Cost, or an increase / decrease from the Base Cost
Cost Variables
Schedule Variables• Probability of a Duration, a Specific Date, or a Delay / Advancement to the Base Schedule
• Discuss the Assumptions in the Base Cost / Schedule, including
Manpower and Equipment levels
• Identify Risk and Opportunity factors influencing the range of
uncertainty
• Discuss what factors are included and excluded from the risk
range for the item
• Collect the risk range information (Assessment is a value and
the probability of that value occurring)
• Identify what is driving the high and low values
Risk Discussion
4 November 201013
CSCExcellence in Risk Management
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1200 1600 2000 2400 2800
Pro
bab
ilit
y
CAPEX ($MM)
Base = 1600 $MM
P50 = 2000 $MM
P10 =1780 $MM-9%
P90 =2220 $MM+11%
The risk analysis calculates the probability distribution of potential cost outcomes. This distribution can be used to :
Slope of Class V Estimate
Slope of Class 2 Estimate
400 $MMContingencyRequired forP50 Confidence
1. Determine the contingency required for any confidence level (probability).2. Compare the estimate uncertainty (slope) with traditional estimate class definitions.
4 November 201014
CSCExcellence in Risk Management
-60 -40 -20 0 20 40 60Start Date
EV = 20-Dec-07
Days
The tornado diagram identifies and ranks the key project risks and is a tool that helps the project team to focus on the most important drivers.
Road Preparation Duration 3 6
Labour Productivity Delays -1.25 1.75
Plant Pad Preparation Duration 3 6
Labour Unrest Delays 0 2.3
Execution Organization Performance Best Worst
Regulatory Duration 11.3 16.5
Competing Project Environment Low Heated
Start-up & Commissioning Duration (Early Steam) 1.5 2.4
Terms of Reference - Duration 3 4
Regulatory Environment Relaxed Stringent
Terms of Reference - Application Date 1-Aug-02 1-Oct-02
Labour Availability Delays 0 1.4
OTSG Manufacture & Delivery Duration 12 16
Weather Delays 0 0.5
Long Lead Equipment Delays -1 2
4 November 201015
CSCExcellence in Risk Management
• Risk management is fundamental for accountability on corporate governance and on maximizing shareholder value.
It begins with strategic definition and continues in a consistent manner throughout the project life cycle.
• Range Estimating is not Risk Analysis.Risk analysis must consider the specific uncertainties of a project, and
incorporate these underlying risks into the project value. Processes that provide single-point outcomes or risk distributions based on the probability of fixed outcomes (decision trees, KT, range estimating) do not meet the definition of risk analysis.
• Risk Management ensures that there are no surprises. Documentation of assumptions and all risks. Communication of the risk management plan (avoid, accept, manage) focusing on the underlying project risks.
“Ignoring risks to a project is not an option; important decisions will be made anyway, shouldn’t they be made with the best information available?”
(Project Manager Today, October 2000)
Modern Day Application of Risk Management
4 November 201016
CSCExcellence in Risk Management
Specifics:
• Supports Owner Organizations in major project development.• Group formed in 1982, over 250 project assignments worldwide.• Extensive and varied background in Project Planning and Management.
Specialties:
• Risk & Decision Analysis for a wide range of capital Projects.• Strategic & Mitigation Planning for projects using risk models.• Facilitation of Project Management, Business Planning, Environmental &
Safety Planning & Management and Team Building.• Project Management Education Workshops.• Development of Contract Claims and disputes and litigation support.
CSC
Excellence In Risk Management