Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
3,500’ SMO RUNWAY
Issues and Questions
May 2, 2017
Joe Schmitz Graphics: Andrew Wilder
Airport Commission Member
1
COMMISSIONER SCHMITZ:FOUR QUESTION AREAS
1. What primary FAA airport design directive(s) did you use for Options A & B?
2. How would you characterize the benefits that Options A & B provide using the
following criteria:
• Takeoff Distance Available (TODA)
• Speed, size, & weight of aircraft able to use SMO with each option
• Overrun and undershoot hazards to residents
• Fine particulate exposure to the surrounding communities; and
• Excessive noise: ~ 85 dB
3. Why not submit a single proposal that commits both the City and FAA to: (1) shorten the
runway and (2) replace excess asphalt/concrete with compacted earth?
• Does/can the City obtain a legally binding guarantee from the FAA that after Phase 1 shortening – that both parties agree to Phase 2 runway end removal?
4. When did the City initiate an environmental review?
2
SMO Today: Non-compliant With Present FAA Safety Rules
Takeoff Distance Available (TODA) = 4,973’
■ NO RSAs: Expressly non-compliant since 2012!
■ FAA, NBAA, and local advocates have claimed safety is not compromised
■ Used by 60,000+ lb. Gulfstream IV, etc., but the 60,000 lb. limit is unenforceable 3
What would SMO look like now…if it complied with FAA safety rules?
■ SMO should have looked like this after 2012
– 300’ RSA: 100’ Jet blast asphalt; 200’ Compacted Earth
– FAA safety requirements that neither the FAA, nor the NBAA, or local advocates deemed necessary
4
The Consent Agreement: 3,500’ SMO Runway
■ Exceeds all FAA safety requirements
■ Excess runway (asphalt/concrete) removed
■ Compacted earth provides added overrun and undershoot protection
5
3,500’ SMO Option BTakeoff distance available: Runway + Stopway = 4,236’
■ Scant (takeoff) difference from an FAA compliant SMO
■ Excess Runway + Stopway = larger, faster aircraft
■ Gulfstream IV @ 60,000 lbs. can still takeoff from SMO 6
3,500’ SMO Option ATakeoff distance available: Runway + Stopway = 4,535’
■ Excess Runway + Stopway accommodates heavier, faster aircraft
■ Longer takeoff distance available than an FAA compliant SMO
■ Gulfstream IV @ 60,000+ lbs. can takeoff from SMO
7
Do I have this right?
DESIGN TAKEOFF DISTANCE
AVAILABLE LENGTH
(TODA)
FAA
COMPLIANT?
Current SMO 4,973’ No!
Compliant SMO 4,473’ Yes
Plan A 4,535’ Yes
Plan B 4,236’ Yes
Consent
Agreement 3,600’ Yes
8
Environmental Assessment
■ Has the contract been let for the environmental
assessment (CEQA) to remove the excess runway from
the shorter SMO runway?
– Preliminary work can be done now – consider closing
SMO several nights if necessary
■ Given the high stakes
– If not; why not?
9
Two Phase Project Requirements: Fulfilling the City Council Promise
■ Phase 1: Reconfigure (paint and procedures) the centered Option B – 3,500’ SMO
– Do not permit aircraft to use the decommissioned runway ends
■ Monitor compliance with cameras, frangible barriers, etc.
■ Relocate the Noise Monitors and enforce the Noise Code
■ Phase 2: Remove runway concrete/asphalt at the runway ends
– Environmental assessment (CEQA) initiated now!
– Complete with requisite speed
■ 3,500’ runway shortening: A two-part integrated package!
– The compacted earth provides ~ 450’ safety margins exceeding those required by the FAA
– Given the Western Parcel loss for 12 years (a 2,800’ runway forgone), we must limit both takeoff and landing runway available to 3,500’
– Fulfills the City Council pledge to obtain Local Control to the maximum extent possible under the Consent Decree!
10
COMMISSIONER SCHMITZ:FOUR QUESTION AREAS
1. What primary FAA airport design directive(s) did you use for Options A & B?
2. How would you characterize the benefits that Options A & B provide using the
following criteria:
• Takeoff Distance Available (TODA)
• Speed, size, & weight of aircraft able to use SMO with each option
• Overrun and undershoot hazards to residents
• Fine particulate exposure to the surrounding communities; and
• Excessive noise: ~ 85 dB
3. Why not submit a single proposal that commits both the City and FAA to: (1) shorten the
runway and (2) replace excess asphalt/concrete with compacted earth?
• Does/can the City obtain a legally binding guarantee from the FAA that after Phase 1 shortening – that both parties agree to Phase 2 runway end removal?
4. When did the City initiate an environmental review?
11