3281-RP124-2!19!0001(Method S...Ment Cable Installation)1

Embed Size (px)

DESCRIPTION

technical

Citation preview

  • PROJECT / CONTRACT REF.: 3281 / GC 12108800

    CONTRACT TITLE: -

    EPIC FOR REPAIR OF SERVICE BERTH NO.4, BUND FOR

    RECLAMATION AREA AT WAKRA DOCK RLC PORT AND NEW

    BERTH FOR MARPOL RECEPTION FACILITIES AT RAS LAFFAN

    DOCUMENT TITLE :

    METHOD STATEMENT FOR CABLE INSTALLATION.

    CONTRACTOR

    SUB CONTRACTOR

    23 MARCH14 0 ISSUED FOR REVIEW / COMMENTS MKR SV SR

    DATE REV.

    NO. REASON FOR REVISION PREP CHECKED BY

    CHKD NEC

    APPD.

    Q.P.

    3281 - RP124 - 2 - 19 - 0001 SHT 01 OF 16

    REV 0

    DOCUMENT NO.

    3281-RP124-2-19-0001 Rev0 Page 1 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    Table of Contents Page

    1 INTRODUCTION.......................................................................................................... 03

    1.1 BACK GROUND........................................................................................................................ 03

    1.2 PROJECT OBJECTIVES.............................................................................................................. 03

    2 BRIEF SCOPE OF WORK- ELECTROMECHANICAL..................................................................... 04

    3 DOCUMENT CONTROL............................................................................................................. 04

    4 HEALTH, SAFETY AND ENVIRONMENTAL................................................................................ 05

    4.1 HEALTH AND SAFETY HAZARDS.............................................................................................. 05

    4.2 ADVERSE ENVIRONMENTAL IMPACTS.................................................................................... 05

    5 CABLING WORK SCOPE............................................................................................................. 05

    6 RESOURCES............................................................................................................................. 06

    6.1 EQUIPMENT............................................................................................................................ 06

    6.2 PERSONNEL (SITE TEAM)........................................................................................................ 06

    7 METHODOLOGY........................................................................................................................ 07

    8 ANNEXURE 1... ..................................................................................................................... 10

    9 ANNEXURE 2. ....................................................................................................................... 14

    10 REFERENCE ............................................................................................................................. 16

    3281-RP124-2-19-0001 Rev0 Page 2 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    1. INTRODUCTION

    1.1 Background

    Part 1 - Repair to Service Berth no. 4

    Service Berth No. 4 was constructed as part of seven service berths in 2000-2001. Four of these berths have

    developed cracking of mass concrete blocks in the quay wall structure attributed to Delayed Ettringite

    Formation (DEF). Three of the most severely affected berths were replaced in 2010-2011 with more

    stringent specification to avoid DEF. The fourth berth, Berth No. 4 was put under monitoring at that time. In

    light of an increase in the number of cracked blocks in the most recent observation and in line with the

    earlier service berths repair and replacement work, repairs to this existing Service Berth No.4, has been

    initiated.

    Part 2 - New Berth for MARPOL Reception Facilities

    i) MARPOL 73/78 is a marine pollution control convention under International Maritime Organisation

    (IMO) that ensures that the signatories shall provide reception facilities for ship generated wastes.

    State of Qatar has ratified MARPOL 73/78 all annexes.

    ii) For the partial fulfilment of the obligations under the MARPOL Convention, a berth with basic

    provisions to receive ship generated waste is to be constructed. The facilities and plant to receive,

    treat and dispose the effluents will be executed separately under a different contract.

    iii) A barge will collect the slops and liquid waste from ships at other locations and deliver the waste

    cargo, which will be received at this berth.

    iv) To utilise the new berth to the maximum, the importation of stone aggregates through this berth is

    under consideration.

    1.2 Project Objectives

    The Project objectives are:

    1) To repair Service Berth No.4, which has cracks in the mass concrete blocks making up the quay wall and

    to construct a bund to demarcate the disposal area at Wakra Dock to contain the dumped material within

    the bunded area?

    2) To construct new berth for MARPOL reception facilities.

    3281-RP124-2-19-0001 Rev0 Page 3 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    2. BRIEF SCOPE OF WORK - ELECTROMECHANICAL

    Part 1 - Repair to Service Berth no. 4

    UNITECHs scope includes EPC for the process, mechanical & piping, electrical, instrumentation, safety and

    environmental design of the following systems:

    a) Utilities Diesel, Potable Water and Fire Water

    b) Lighting, Earthing and Lightning Protection

    Part 2 - New Berth for MARPOL Reception Facilities

    UNITECHs scope includes EPC for the electrical and environmental design of the following systems:

    a) Lighting, Earthing and Lightning protection

    b) Traffic Control

    3. DOCUMENT CONTROL

    This method statement is a controlled document as required by the system procedure Quality Planning and issued in accordance with the system procedure Control of Documents and Data.

    The method statement is subject to amendment during the execution of the Works as a result of periodic review and whenever circumstances require. Revisions will be issued in accordance with the

    system procedure Control of Documents and Data whenever the main text changes or when an

    appendix is added or removed. Revised appendices for substitution will be issued separately and, where

    appropriate, will include a separate schedule of contents.

    4. HEALTH , SAFETY AND ENVIRONMENTAL

    4.1 Health and Safety Hazards

    As required by the Project Health & Safety Plan, the significant health and safety hazards of this work

    have been analyzed and are listed below:

    Electrical hazards

    Falling, slips, trips.

    Weather condition.

    Damage to body parts

    Ergonomic hazards

    Control for the above will be implemented to minimize these hazards as set out in the form of Risk

    Assessment included in Annexure-1 which is enclosed with this document.

    3281-RP124-2-19-0001 Rev0 Page 4 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    4.2 Adverse Environmental impacts.

    As required by the Project Environmental Plan (CEMP Plan), the significant adverse environmental

    impacts of this work have been analyzed and control will be implemented to minimize these adverse

    effects as set out in the form of Environmental Impact Statement included in Annexure-2 which is

    enclosed with this document.

    5. CABLE INSTALLATION WORK SCOPE

    UNITECH shall carry out listed above works, in order to:

    a) Power up all the newly installed facilities in the project.

    b) Tap up the power safely from existing power feeder in substation/feeder.

    6. RESOURCES

    6.1 Equipment

    The following equipment will be used

    Equipment Nos

    Crane 1 No.

    Winch 1 No.

    Slings A set, as required

    D Shackles A set, as required

    Safety Cones (Traffic cones) A set, as required

    Pick-Up 1 No.

    Cable drum jack 2 No.

    Meggers 2 No.

    Gas torch 2 No.

    Crimpers 2 set.

    Hydraulic Knockout punch 1 No.

    Hydraulic Crimper 2 No.

    Hydraulic hammer 1 No.

    Drill machine 2 No.

    Heat Gun 2 No.

    Cabling & termination tool box. 4 No.

    Spindle & Cable drum Jack 2 set.

    3281-RP124-2-19-0001 Rev0 Page 5 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    6.2 Personnel (Site Team)

    The following personnel will be involved for the site execution work.

    Sr. No. Designation Nos

    1 Construction Manager 1 No.

    2 E&I Engineer 1 No.

    3 Safety Officer 1 No.

    4 Electrician 6 No.

    5 Rigger 2 Nos

    6 Helpers 12 Nos

    7 Fitter 2 Nos

    7. METHODOLOGY

    A. DESCRIPTION OF WORK METHOD

    A.1: Pre-Installation Checks for cable laying

    All necessary permits and personnel presence from contractor side & client side (if applicable) should be

    ensured for clearance before commencement of the cable pulling activity.

    The entire route shall be inspected to ensure that the routing is complete, proper bends are used and free from

    any sharp edges.

    Ensure that last revision drawings are used.

    Location of the panels / equipments shall be identified.

    Termination point inside the panels / equipment shall be considered for suitable spare length to be left

    available during pulling of cable termination. The maximum length shall be equal to depth + height + width of

    panels.

    Personnel involved in cable pulling will at all times have safety harness fixed firmly to overhead support.

    Before start of pulling Cable, the actual route length shall be measured and checked for adequate length of

    cable.

    Confirm that all Tools & Tackles required for installation are available. As a minimum the following shall be

    made.

    Check adequate place for unloading the cable drums.

    Check suitable position for placing the Cable pulling winch depending on the length of the cable and the site

    condition.

    Personnel involved in the activity are made aware of the risks and the steps to be taken to mitigate any hazard

    or unsafe situation.

    A.2:Pre-Installation Checks for Termination

    All necessary Permits from QP to be received for working in panels.

    Exiting system should not be disturbed while working in panel.

    Ensure that last revision drawings are used.

    Location of the panels / equipments shall be identified.

    3281-RP124-2-19-0001 Rev0 Page 6 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    Termination point inside the panels / equipment shall be considered for suitable spare length to be left

    available during pulling of cable termination. The maximum length shall be equal to depth + height + width of

    panels

    Personnel involved in cable termination will at all times have safety harness

    Before start of termination checked for adequate length of cable.

    Ensure sufficient quantities of Cable Tags are readily available.

    Ferrule and core marking should be done.

    Personnel involved in the activity are made aware of the risks and the steps to be taken to mitigate any hazard

    or unsafe situation.

    B. Material withdrawn from warehouse

    Material inspection will be carried out to ascertain that no damage has occurred to the cables. In case of any

    damages common inspection and report will be issued.

    Cable shall be tested on cable drums prior to removal and work site with insulation tester.

    The values will be noted for Core to Core and Armor.

    After the test, the end of the cable shall be sealed to prevent the ingress of moisture.

    Store material requisition shall be made.

    The material shall be transported in their original packing to location.

    The cable drums shall be off-loaded at the site location.

    It shall be ensured that there is no obstruction to movement of vehicles or any hindrance to works of other

    companies.

    C. Description of sequence

    1. In Trench Cable Pulling

    All the permits for opening the trench to be received.

    Crane/forklift for opening the trench should be stand and movement to be plan prior to the lifting in such a way

    the make an ease to move the lifted block without fouling own movement.

    Cables shall be laid mainly in trench cable trays perforated and ladder type.

    Cable rollers shall be placed at every 6-12 meters or less if required to avoid touching of the cable to tray.

    Cable winch, if used, shall be positioned in proper place for cable pulling.

    The cable drum intended for cable pulling shall be identified as per that indicated in the drum schedule.

    The cable drums shall be unpacked.

    The cable shall be fixed in the winch by means of a cable sock or gripper.

    Required number of persons will be posted at the winch, if used, and near the drum.

    Cable laying will generally start from one end of the route length from other suitable point if required.

    Depending on the weight and size of the drum, suitable size of the cable rolling shaft (Spindle) shall be placed

    inside the central axis of the drum.

    Suitable jacks shall be placed firm ground and jacked-up to allow clearance from the ground depending on the

    size of the cable drum.

    The drum shall be lifted by required equipment and placed on the jacks.

    The cable drum will be correctly positioned and the direction of cable pulling as indicated by arrow on the drum

    shall be complied..

    Cables will be laid / pulled by hand and / or winch.

    3281-RP124-2-19-0001 Rev0 Page 7 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    Cable laying in tray maximum portion of laying will be done manually to avoid the cable damage from tray

    sharp edges.

    Cables will be pulled according to drum-cable cutting schedule and as shown in the relevant drawings.

    Bending radius of cables shall comply to cable manufacturers recommendation.

    Unless the lengths exceed the maximum drum lengths joints shall be avoided.

    Before cutting the cable, both ends must be inspected to ensure sufficient length is for proper dressing and end

    termination.

    The open ends will be sealed till termination.

    Soon after completion of every cable the cables will be tested for insulation resistance.

    Cable tags shall be installed as per Client Specification

    The cable schedule and drum schedule will be updated with the information on cable pulling.

    Daily progress report will be submitted for the activity.

    After completion of all cables in the same route the cables shall be dressed and clamped.

    Cables shall be fixed in horizontal or vertical runs with or plastic type straps.

    Interval of clamping will be as per Client Specification but will not exceed 10Mtr for the horizontal runs and

    1.0Mtr for vertical runs.

    Inspection of the installation and punch list.

    As-Built mark-up drawings certified by Contractors Supervisor and Engineer will be prepared.

    Empty cable drums will be transported back to stores.

    2. TERMINATION & GLANDING

    Updated drawing and cable schedule to be checked

    Check the terminal detail, panel detail & tag.

    As per the termination schedule start termination.

    As per the cable size, respective cable gland hole to be fabricate in gland plate and gland to be installed.

    Ensure all joints and terminations and glanding are made by appropriately qualified Person.

    Cut all cable ends immediately prior to terminating. Seal cables left unconnected for more than 24 hours to

    prevent the ingress of moisture.

    Armored cable will be strapped properly, a hacksaw is used to cut the cables, a suitable angle to the cable for

    making a cut through one section of the spiral amour and care will be taken not to cut the wires.

    The glands for various single core and multi core cables will be on the purposed made and suitable for rigid

    mounting to the enclosure.

    All glands shall be of weatherproof and water tight type as per QP specification.

    Ensure cable glands complete with earth tag, shroud, locknut, seal etc.

    Earthling tags shall be fitted to each gland, on assembly.

    Where cable sheaths are used as earth continuity conductors, glands shall have the necessary contact surfaces

    or straps to provide a low resistance path under fault conditions.

    Strip cables to bring out the cores and expose conductors, for the minimum length required for connection, to

    leave no exposed length of conductor after termination.

    Ensure that strands are not damaged when stripping cable cores. Twist strands together. Do not reduce

    number of strands. Secure all strands at terminations.

    Clean arm our thoroughly prior to terminating. At connections to equipment and switchgear, use compression

    type lugs for bolted terminal connections.

    All cable connections shall be made with approved cable lugs, compression type together with the usage of

    proprietary tools.

    Cable terminals will be suitable for the specified cable sizes. Adequate space will be provided for cable

    terminations.

    3281-RP124-2-19-0001 Rev0 Page 8 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    Continuity tests of all cables before finally making off ends and connecting up.

    Mark cable conductor phasing, or other core identification, at each end of all cables.

    The neutral cable is connected to the neutral strip, which is turning in grounded with a bare wire.

    Do not bunch more than three cores at clamping terminals or bolted connections.

    Dressing of cables will be done by using ferrules, sizes suitable for accommodating all stands of the cables.

    For instrument cable termination SP, 2 pair & 3 pair, pin type or flat type lug will be used

    Lug will be crimp by hand crimper.

    Termination as per the JB termination schedule will be done.

    All the instrument pair will be ferruled before termination as per the schedule.

    3281-RP124-2-19-0001 Rev0 Page 9 of 16

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    ANNEXURE-1

    HAZARDS, CONSEQUENCES / IMPACT, RISK ASSESSMENT & CONTROL MEASURES

    3281-RP124-2-19-0001 Rev0 Page 10 of 16

  • Step

    No.

    Description of

    Task Step/Activity

    Who or what might be harmed S L R Control measures/ Recovery measures

    1.Work permit from Client to be

    obtained.working crew and equipment L M M

    Authorized PTW holder shall ensure obtaining and

    maintaining valid work permit.

    The worksite supervisor responsible for this activity

    has to check the PPE of his staff to ensure that all

    required items are available and properly used.

    Inform all workers regarding permit condition before

    work starts.

    Worksite supervisor shall conduct toolbox talks about

    nature of works and associated potential hazards and

    their essential precautionary measure.

    2. Pre-task briefing toolbox talks. working crew and equipment L M M

    Ensure that the pre task briefing is given out in a

    language understood by the work force, have it

    translated.

    Ask question regarding the briefing to get feedback

    from the staff, this ensures full comprehension.

    Issue required appropriate PPE and replace PPE that

    has signs of defect.

    PPE must include both hearing protection as well as

    dust inhalation protection.

    3.Transportation of materials to

    site.working crew and equipment L M M

    Before transporting the loads to the site, rest assure

    that the materials are secured and tight with nylon rope

    for the safe transporting.

    Ensure that a driver is having knowledge to the hazard

    while transporting the materials.

    The driver shall not have driving attitude while using

    the road.

    Driver is driving only in the minimum speed limit.

    4. Preparation of working area working crew and equipment L M M

    Isolate the work zone.

    Keep barricading and post signage.

    Inspect site and clear area of any obstructing material

    or debris.

    EPIC FOR REPAIR TO SERVICE BERTH NO. 4, BUND FOR RECLAMATION AREA AT WAKARA DOCK RLC PORT AND

    NEW BERTH FOR MARPOL RECEPTION FACILITIES AT RAS LAFFAN

    GC12108800

    JOB SAFETY ANALYSISTask Name:Electrical work Excavation,Sand Bedding,Cable

    Laying,BackFilling & Compaction

    Team Composition: Construction Manager, Site Engineer and Supervisor, Safety Officer Date: 29.03.2014

    HAZARD

    - potential incident

    Action/ Responsible party

    Unauthorized commencement of

    works may result in exposing

    workers and or potential to harm or

    danger

    Construction Manager,

    Site Engineer and

    Supervisor, Safety Officer

    The work force does not

    understand the pre task briefing

    therefore does not understand the

    potential dangers and control

    measures to be implemented. Some

    of the workers could be lacking PPE

    or using defective PPE.

    Construction Manager,

    Site Engineer and

    Supervisor, Safety Officer

    Traffic Accidents, Fatality, Serious

    personnel injury, Property damage,

    Damage to the truck or third party if

    involved in an accident, Driving

    against the road traffic rules,

    Unsecured materials on the truck,

    Overloading of truck.

    Construction Manager,

    Site Engineer and

    Supervisor, Safety Officer

    Slips, trips and falls to the workers

    working in the vicinity.

    Construction Manager, Site

    Engineer and Supervisor,

    Safety Officer

    working crew and equipment ML M

    Material scattered to access and

    egress of work area that causing

    slips, trips and falls for the person

    passing through to the area.

    Ensure that the access and egress are clear from any

    material and people are free to access and safe to any

    risk.

    Ensure proper housekeeping to the working area and

    free of any objects or materials from construction

    activities.

    Construction Manager, Site

    Engineer and Supervisor,

    Safety Officer

    Providing proper access before

    starting the works5.

    3281-RP124-2-19-0001 Rev0 Page 11 of 16

  • Step

    No.

    Description of

    Task Step/Activity

    Who or what might be harmed S L R Control measures/ Recovery measures

    6. Pre works activity working crew and equipment L M M

    Locate underground / above ground services referring

    to the site maps / drawings.

    Endorsement of excavation notification from the

    concerned teams for the services in the area being

    excavates.

    Ensure that department representative have conducting

    underground locator to identify the underground

    utilities.

    Ensure to clearly mark at the drawing the possible

    underground utilities.

    Hold pre-job safety meeting.

    Ensure prior to start the activity, the excavation

    certificate has done and completely signed by every QP

    department authority.

    Ensure the work permits are signed by the HSE

    department prior to work.

    Avoid improper positioning during excavation works.

    Avoid manual lifting of heavy debris materials

    If manual handling is unavoidable, ensure operatives

    involved are train in basic lifting techniques. Selection

    maybe required of suitable, fit individuals depending

    upon the nature of the task.

    Ensure workers are wearing dust mask to protect from

    dust inhalation that cause respiratory infection

    Use hand protection to avoid blistering and any other

    hand injury

    Proper positioning required

    Ensure that workers are wearing appropriate eye

    protection to avoid dust particles that can cause eye

    irritation.

    Proper arrangements regards weather condition.

    Proper shoring, benching, sloping must apply to any

    kind of excavation to avoid trench collapse.

    Include in the toolbox talk regarding emergency

    procedure in case of gas leak

    Construction Manager, Site

    Engineer and Supervisor,

    Safety Officer

    working crew and equipment

    Back Pain

    Dust inhalation

    Hand blistering

    Ergonomics

    Eye injury

    Cave-in

    MML

    Location of underground / above

    ground services (such pipeline,

    cables etc.)

    Non compliance of QP-

    Excavation Procedure-Ras-laffan

    Fields and QP HSE Regulations for

    Contractors.

    Construction Manager,

    Site Engineer and

    Supervisor, Safety Officer

    HAZARD

    - potential incident

    Action/ Responsible party

    Excavation Of Route Marker

    And Rectification Of Route

    Marker Position

    7.

    EPIC FOR REPAIR TO SERVICE BERTH NO. 4, BUND FOR RECLAMATION AREA AT WAKARA DOCK RLC PORT AND

    NEW BERTH FOR MARPOL RECEPTION FACILITIES AT RAS LAFFAN

    GC12108800

    JOB SAFETY ANALYSIS

    Task Name: Electrical work Excavation,Sand Bedding,Cable

    Laying,BackFilling & Compaction

    Team Composition: Construction Manager, Site Engineer and Supervisor, Safety Officer Date: 29.03.2014

    3281-RP124-2-19-0001 Rev0 Page 12 of 16

  • 8. Housekeeping working crew and equipment L M M

    Regular housekeeping at site shall be performed

    Adequate and correct stacking of materials

    Regular inspection and immediate corrective action.

    Keep always clear of obstruction.

    Regular clearing of work site shall be implemented

    Waste bins with cover shall be provided for oily rags

    Flammable materials shall be stored separately away

    from possible ignition source

    Minimal inventory to be stored at work area

    Appropriate fire extinguisher shall be provided when

    necessary

    Keep 9kg dry powder fire extinguisher to the area

    during the excavation activities

    Daily housekeeping shall be done, Closed bins for

    foods waste.

    Regular housekeeping at site shall be performed

    Adequate and correct stacking of materials

    Regular inspection and immediate corrective action.

    Keep always clear of obstruction.

    Regular clearing of work site shall be implemented

    Waste bins with cover shall be provided for oily rags

    Flammable materials shall be stored separately away

    from possible ignition source

    Minimal inventory to be stored at work area

    Appropriate fire extinguisher shall be provided when

    necessary

    Keep 9kg dry powder fire extinguisher to the area

    during the excavation activities

    Daily housekeeping shall be done, Closed bins for

    foods waste.

    Valentine Onyeakazi

    HSE Manager

    Date Approved by NEC

    Team Composition: Construction Manager, Site Engineer and Supervisor, Safety OfficerTask Name: Electrical work Excavation,Sand Bedding,Cable

    Laying,BackFilling & CompactionDate: 29.03.2014

    JOB SAFETY ANALYSIS

    EPIC FOR REPAIR TO SERVICE BERTH NO. 4, BUND FOR RECLAMATION AREA AT WAKARA DOCK RLC PORT AND

    NEW BERTH FOR MARPOL RECEPTION FACILITIES AT RAS LAFFAN

    GC12108800

    Construction Manager, Site

    Engineer and Supervisor,

    Safety Officer

    Debris causing Slips, trips and falls

    Fire risk due to presence of

    combustible materials / debris

    Infestation of rodents leading to

    equipment & materials damage

    (Cables, cords, documents, etc.)

    Reviewed by NECPrepared by

    Electrical Manager Valentine Onyeakazi

    HSE Manager

    3281-RP124-2-19-0001 Rev0 Page 13 of 16

    mohsinLine

  • METHOD STATEMENT FOR POWER

    CONTROL & INSTRUMENT CABLE

    INSTALLATION

    ANNEXURE-2

    ENVIRONMENTAL ASPECT AND IMPACT RISK ASSESSMENT (RISK REGISTER)

    3281-RP124-2-19-0001 Rev0 Page 14 of 16

  • ENVIRONMENTAL IMPACT CEMP PLAN

    WORK ACTIVITY: _________________________________________________________________________________________________________________

    SITE SUPERVISOR:__________________________ JOB LOCATION:___________________________ PERMIT NO. :_________________________

    No Environmental impact Contents

    Who/ What Might

    Be Harmed

    Control / Recovery Measures

    Responsible/ Action By

    1.

    Earth pollution

    Contaminated waste due to tyrex suites,

    rollers brushes, filter masks, paint stirrers,

    drop cloth, masking tape, plastic bag, waste

    paints and solvent, cements waste etc.

    Human

    Waste deduction program,

    Waste reprocessing program,

    Waste disposal program

    Site supervisor and Site

    Safety Officer.

    2

    Air Pollution Chemical waste, transport waste,

    Dust dirt during excavation Human

    Waste deduction program,

    Vehicle inspection and maintenances

    Transportation program.

    Excavation program

    Site supervisor and Site

    Safety Officer.

    3 Noise pollution

    Transportation

    Power tools

    Heavy machine

    Human

    Vehicle inspection and maintenance

    Power tools inspection and maintenance

    Heavy machine inspection and

    maintenance program

    Site Supervisor and

    Safety Officer

    4 Water pollution

    waste due to tyrex suites, rollers brushes, filter

    masks, paint stirrers, drop cloth, masking tape,

    plastic bag, waste paints and solvent, cements

    waste etc.

    Human

    Waste deduction program,

    Waste reprocessing program,

    Waste disposal program

    Site Supervisor and

    Safety Officer

    3281-RP124-2-19-0001 Rev0 Page 15 of 16

  • METHOD STATEMENT FOR CABLE

    INSTALLATION.

    Reference:

    1. 3281-RP124-2-66-0001

    2. 3281-RP124-2-64-0001

    3. 3281-RP124-2-63-0001

    4. 3281-MS-ELE-0005

    3281-RP124-2-19-0001 Rev0 Page 16 of 16