~~-~.~~ ~ 31'R "l1ACl) "WTcR~-226011Tele./F'ax : 0522-2452581E-mail:[email protected]
•
'., ' ' ... Government of IndiaMinistry of RailwaysResearch, Designs &. Standards
~ ~ ....Organization,LUCKNOW- 226011
No. EL/ 1.2.9.1 Dated: 28.12.2018
Principal Chief Electrical Engineer,All Zonal Railways & CLW.
Sub: Minutes of Performance ReviewMeeting of 180 KVA
Static Converter held RDSO on 21.12.2018.
***The minutes of performance review meeting on Static Inverter held at RDSO
on 21.12.2018 is enclosed herewith for kind information and necessary
action. Compliance for the items mentioned as action plan may be sent
quarterly. Data in excel sheets. (already circulated earlier) with updated
position upto Dee 2018 may also be sent by 15th Jan 2019.~~'lP\to
(Aseem Kumar)Encl: As above for Director General/Elect.
Copy to:
1. Secretary (Elect.), Railway Board, Rail Bhawan, New Delhi- 110 001
- Kind attention: Sri A.K. Goswami DEE/RS/Railway Board.
2. M/s. Autometers Alliance Ltd., C-63, Sector - 57, Noida - 201 307
3. M/s. Siemens Ltd., Industry Sector, Mobility Division, I MO RS IS, 5th
Floor, R&DCentre Building, Kalwa, Thane, Mumbai - 400601
4. M/s. Medha Servo Drive Pvt. Ltd, P-4/5B, IDANacharam, Hyderabad - 76
5. M/ s. Hind Rectifier, Lake Road, Bhandup (W),MUMBAI- 400 0785.
6. M/s.ABB Limited, Survey No 88/3, 88/4. Basavanhalli Kasaba Hobli,
Nelamangala Taluk, Bangalore 562123.
- for kind information and necessary action please.\ ~:\Ib
~~,\i:(lP
(Aseem Kumar)for Director General/ElectEnd: As above
mailto:[email protected]
Minutes of Performance Review Meeting of 180 kVAStatic Converter
held at RDSO on 21.12.2018 on 22.12.2018.
Present: As per list enclosed.
1. At the outset PEDSE IRDSO welcomed all the participants from railwaysand industries for the meeting on 180 KVAStatic converter at RDSO.
180 KVASIVs which are available in conventional locomotive will being
services for a decade and more. Therefore, proper attention is required
from Railways and Suppliers for its maintenance. It is also informed that
for new procurement of SlY, Railways have to follow the guidelines issued
by Railway Board vide Railway board's letter no. 2018 IElect (TRS)441 I 5pt 1 dated 28.08.2018 and all the new procurement of SIV by railways
shall be done as per revised specification no. RDSOj2018jELj Specj0140
Rev 0 dated July 2018. Consequently any replacement of old SIVs has to
be with SIVas per revised specification.
The compliance report of previous meeting which was held at CNBhas not
been received. Only ELSI Anguli ECoR have sent the compliance report.Other railways are requested to send the compliance report timely. Firms
are also advised to send the feed-back and compliance of the work done as
mentioned in MOMs of both the meetings. Only Mj s. Hind Rectifier sends
the performance report regularly.
Railways are requested that the consolidated failure data upto Dee 18
(April 18 onwards) should be sent to RDSO by 15.01.2018 in the excel
sheet formats as already circulated.
2. Performance review:-
Discussions were held on progress of modifications and failure analysis
presented by RDSO based on the data taken from the sheds which are as
follows:-
2.1 MIs AAL
SN Subject Action to be taken by firm & RailwaysjRemarks
a) Cooling Fans: 1. Zonal railways have reported that1.Reasons of cooling fan there are no failures of modifiedfailure were mainly due to cooling fan (Havells make of 02 HP).bearing failures. Firm has All the units are In service.
MOM lRl??l 70f SIV at RDSa
developed new designedcooling fan (Havells make)and validated m fieldtrials. {Firm supplied 184units of (Havells make)and supplied 168 KIT torailways Total - 352 units.RDSO also issuedModification sheet no.RDSO/2016/EL/MS/0449 Rev '0' dated30.03.2016 for providingmodified cooling fan.
The maintenance schedule andreplacement of bearing of Havellsmake of 02 HP motor has not beenprescribed by firm. This IS to besubmitted by firm.2. ELS/BZA reported Havells makecooling fan with 1 HP motor are alsoreliable and reported no failures.3. In the meeting at ELS/TKD It wasadvised by RDSO to complete theconversion of ZIEHL-ABEGGcoolingfan to modified one so that thefailures due to cooling fan can bereduced. Railways are requested toexpedite conversion of ZIEHL-ABEGGcooling fan to modified one and givefeed back to RDSO.
4. Firm reported that apart fromOEM supplied there are locallymodified cooling fan for which it isdifficult to work on AMC. In theminutes dated 21.03.2018 for themeeting held at ELS/TKD dated16.03.2018, it was decided that theunits which are having local modifiedcooling fan may not be taken in thescope of AMCbut firm has to provideproportionate reduction in the cost ofAMCon such SIVs.
b) GDU card:GDU card of inverter andbattery charger
1. Failures of GDU card are still takingplace.
2. Firm has agreed to repair /rehabilitate failed GDU cards ofinverter and battery charger duringAMC. It is decided that the repair /rehabilitation of failed GDU cards ofinverter as well as battery charger willbe done in phased manner in SlVsunder AMC and will be completedwithin SIX months. OEM IS beingadvised to submit the plan to thisoffice so that concerned railways maybe intimated.
MOM 181221 70f SIV at RDSO
c) Churning Fan 1. Firm has not given any feedbackas decided during last meeting. Firm isagain advised to study the case andsubmit the feed back to RDSO by15.01.2019 for needful.
d) K -2 and K-3 model ofSIVs
1. About 100 units are in service. Itis advised that the loco sheds where :older versron SIV exists and hascompleted their codal life, same may beplanned for replacement by 2 X 130KVASIV.
2.2 M!s Siemens
SN Item Decisions! Target
a) Indigenized Batterycharger:Indigenized Battery chargerfailed due to failure .ofrectifier module .
1. Railways reported that the failures inIndigenized Battery charger haveincreased even after this modification.In some cases battery chargingvoltages shows 104V - 105 V and locobattery is not properly charged andbattery became dried up.
2. M/ s. Siemens have investigated thecase and they have concluded that themajor problem is in voltage setting.Firm is being advised to advise theirservice engineers to verify the voltagesetting in every unit during scheduleinspection during AMCattention.
3 It IS decided m the preVIOUSmeetings that K -8 contactor is to beremoved j bypass m all types ofbattery charger of Mj s Siemens asper RDSO issued Modification sheetno RDSOj2016jELjMSj0452 Rev 0dated 29.04.2016. It is decided thatfor remaining work in K -8 contactormodification, firm will assist shedsto implement the modification in theAMC awarded units where in thematerials are duly supplied by thesheds.
MOM 181221 70f SIV at RDSO
b) Input isolatorProper locking of inputisolator jRemoval of inputIsolator (to be done by shedfor SIV's supplied upto2009 where isolator exists)
1. It is recommended by RDSO that
c) Other points
the input isolator which exists in SIVsupplied upto 2009 is. to be properlylocked, or removed. This modificationhas not been completed by railways.
2. It is decided that for remaining workm Proper locking of input isolator jRemoval of input Isolator (if any), firmwill assist to implement themodification in loco shed.1. ELSj ET reported that there ISrepeated failure of input voltage low. Asa precautionary measure, U -1 sensorwas replaced and problem resolved.Mj s. Siemens is advised to look intothe matter and submit action plan sothat such failures can be eliminated.
2.3 M/s. Medha Servo Drive
SN Item Decisions/ Target
a) TDC-IFCard:The tripping of SIV
1. Loco sheds reported that even aftermodification of TDC_IF card, the failuresof TDC_IF card still persists. It is advisedthat during AMC attention the TDC_IFcards are to be checked. If any problemnoticed the cards are to be replaced. Firmstated that the failures are due to overaging of capacitors in TDC_IF card. In themeeting held at CNB, RDSO advised firmto check and replace the capacitors ofTDC_IF card during AMC attentionwithout fail.
b)
occurred due to sensmgover voltage of OHE thoughoHE voltage was belowspecified limit.
dvI dt capacitors 1. The failures of dv/ dt capacitors stillpersist as reported by Railways. OEMstated that they are replacing capacitorswhere capacitance values are less than20% or have service period of 4 to 5years.
MOM 181221 70f SIV at RDSO
c) Card failure
2.4 M/s. Hind
SN Item Decisions/ Target
a) QCONtimer card: 1. The firm is advised that remainingunits (04 no) should be modified by15.01.2019.
b) Crow Bar Thyristor: 1. ELSjBNDM stated that cases areThe problem was unwanted there even after modification of EAU.firing pulse to crow bar The message of DC link high voltage wasthyristor. Firm introduced an seen in VFD panel and sometimes SIVenergy absorption unit. got tripped with message of De link high
voltage. This to be rectified. Firm ISadvised to visit ELSjBNDMjSER toinvestigate the problem and make jointreport and action plan.1. Railways reported the failures in A702 & A-703 card have reduced asproper maintenance are being carriedout during schedule inspection.2. Firm reported that the mamcauses of failure of cards are due todust accumulation in cards. Thefailures have reduced as cards areproperly cleaned during AMC.
SN
PEe card
2.5 MIs ABB
Item Decisions/ Target
a) 1. ELSj JHS reported that there aretwo failures of PEe card. One failure isunder warranty. Firm reported that thefailure IS due to erratic operation ofrelay.2. During previous meeting at CNB itwas decided that defective PEe card ofELS/ JHS are to be investigated andsubmit report to RDSO within onemonth. As no report has been receivedso, firm is again advised to investigatethe causes of PEe card failure.
MOM 181221 70f SIV at RDSO
Cooling fan:Mainly there are failuresdue to jamming ofbearings.
1. Firm stated that the cooling fanb)bearings are failing after a service life of04 years and advised that they are to bereplaced after a service period of 04years. The bearing number has alreadybeen circulated vide MOM of CNBmeeting dated 27.09.2018.
3.0 Other points noted during meeting:
3.1 Replacement of bearing should be done as per the recommendation of
OEM.
3.2 The OEMs of Static converter are advised to develop 2 X 130 KVASIV
and register in RDSO online vendor registration portal.
3.3 For review of the clauses of AMC of SlY, Railways are advised to
submit the additional clauses to be included in SMl to RDSO, so that
it can be reviewed and improved further.
3.4 Zonal railways are advised to finalise the AMC at the earliest for
improving the reliability.
The Meting concluded with vote of thanks to chair.
MOM 181221 70f SIV at RDSO
********
(B)List of participants:-
SN Name (Sj Shri) Designation Railway
1 O.P.Kesari PEDSEjRDSO RDSO2 Aseem Kumar DSEjPn RDSO3 P. Raviteja DEEjTRSjBZA SCR4 N.S.Rongala DEE/ELSjED SR5 Atamjeet Singh DEEjTRSj ANGL ECoR6 Abhisekh Singh DEEjTRSjJHS NCR7 Shivam Srivastava AEEjTRSjCNB NCR8 P.K.Sharaf AEEjTRSjBIA SECR9 Mohan Choudhary AEEjTRSjBSL CR10 Deepak Kumar AEEjTRSjMGS ECR11 R.C.Meena AEEjTRSjBL WR12 A.K.Rana AEEjTRSjHWH ER13 Kirtesh Meena AEEjTRSjNKJ WCR14 Sukant Singh SSEjELSjBZA SCR15 S.K.Das SSEjELSjSRC SER16 Mukesh Kumar SSEjTRSjLDH NR17 Abhijeet Kumar SSEjTRSjBKSC SER18 Prasant Kumar SSE19 P.C. Sanu SSEjTRSjNKJ WCR20 R.K. Bhagat SSEjTRSjTATA SER21 Dinesh Kumar SSEjELS/MGS ECR22 S.R.Senapati SSEjTRSjJHS NCR23 Ambuj Sharma SSEjTRSjCNB NCR24 Sandeep Verma SSE/TRS/CNB NCR25 D. K.Ojha SSEjELSjBSL CR26 Pradeep Gupta SSEjTRSjBRCY WR27 Sudhansu Mishra JEjELS/BNDM SER28 V.K.Salvi SSEjTRSjBL WR29 K.M.Sumesh SSEjELSjED SR30 P. Suresh Kumar JEjELSjED SCR
MOM 181221 70f SIV at RDSO
31 Dr. Akther Alam AAL32 Sumit Wahi AAL33 Ankur Tiwari AAL
34 Sudhanshu Pal AAL35 Rajesh Srivastava Siemens36 Manu Garg Siemens
37 V.K.L. Swamy Medha Servo Drive
38 A.N.V.Rao Medha Servo Drive
39 Shivendra Singh ABB40 Deepak Aher Hind Rectifier41 Himanshu Shukla Hind Rectifier
**********
MOM 181221 70f SIV at RDSO