3.15& 5 MVA Power Transformer Testing

Embed Size (px)

Citation preview

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    1/65

    1

    Protection to TransformerTransformer, being the costliest equipment in any sub-station, should be

    well protected. The transformer is to be protected from external fault (throughfault) and internal fault.

    The best protection technique now and for more than 50 years for faultwith in the Power transformer is known as differential protection. The differentialrelays are triple pole high speed biased designed to protect large three phasepower transformers against internal faults (Below 40 m sec). Biased differentialrelay is extremely stable during through faults and provides high speed operation

    on heavy internal fault. (Below 20 m sec). The relays utilize harmonic restraint toprevent operation by magnetizing in-rush current during the transformer isenergized. In addition, the relays employ fifth harmonics restraint to avoidpossible malfunction under overexcited conditions.

    The minimum operating time of Buchholz relay is about 100 millisecondand an average time is 200 millisecond which is somewhat slow. On theother hand, electrical relays (viz differential relays) can be used for heavy faultswhere high speed (20 40 m sec.) is necessary.

    Differential relay designs vary with different manufacturers and areconstantly changing, especially as microprocessor technology impacts this area.However, protective relaying applications remain basically the same; relativelyindependent of design and their trends.

    In this booklet, the testing of individual differential relay, connecting in theprotective circuit and testing of the entire differential scheme are discussed. Thevarious connections that lead to malfunction, nonoperation, and sluggishoperation are also brought-out for the testing engineers reference.

    I hope this booklet will be a supplement to the ones already brought out on

    this subject.

    2. TERMINOLOGY

    2.1 Differential Relay :

    A relay which, by its design, is intended to respond to differential current.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    2/65

    2

    2.2 Biased (or Percentage) Differential Relay :

    A differential relay in which the designed response is modified by arestraint current.

    2.3 Differential Current :

    In a differential relay, a current which is the phasor difference betweenspecified incoming and outgoing currents.

    2.4 Restraint Current :

    In a differential relay, the combination of incoming and outgoing currents,which restraints operation of the relay.

    2.5 Restraint Percentage :

    The ratio, expressed as a percentage, between the differential current andthe restraint current(s) up to which the relay does not operate.

    2.6 Through Current :

    In a differential relay, that portion of the total incoming current which isalso present in the outgoing current.

    3. WORKING PRINCIPLE

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    3/65

    3

    Figure shows an explanatory diagram illustrating the principle of thecirculating current system. If the two current transformers have the same ratio,

    and are properly connected, their secondary current will merely circulate betweenthe two C.Ts as shown by arrows and no current will flow through the differentialrelay for external faults.

    For the internal faults, the operating current through the differential relaywill be proportional to the vectorial difference between the currents entering and

    leaving the protected circuit, and if the differential current exceeds the relayspickup value, the relay will operate.

    4. DIFFERENTIAL RELAY INPUT SOURCES:-

    Input sources are

    1) Auxiliary DC supply

    2) C.Ts secondary currents

    4.1. Auxi liary Supply

    Check the relays rated auxiliary voltage on the front panel and connect asuitable D.C. supply (or) station battery supply to relay terminal. The connectionshould be correct and tight. Tightness is very important to avoid non-tripping dueto considerable voltage drop at this point of connection.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    4/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    5/65

    5

    4.3. Typical calculations of C.T. requirements for differential protection :

    Transformer particulars

    Rating - 10 MVAVoltage Ratio - 110 KV / 11 KV% impedance - 8.46Vector Group - Dyn 11

    110 KV Side

    Bushing C.T. ratio - 60 /1 A10 x 10

    3

    110 KIV rated current = ----------- = 52.5 A110 x 3

    C.T. secondary pilot 52.5Current = -------- = 0.875 A

    60

    11 KV Side

    If there is no bushing C.T. L.V. breaker C.T. ratio = 600 / 1Acan be used.

    10 x 103

    Rated current = ----------- = 525.5 A

    11 x 3

    525.5CT Secondary Current = -------- = 0.875A

    600

    If connected in delta, the pilot currentin the relay circuit is = 0.875 x3 = 1.516 A

    Since the current is more than the rated current of the relay by 50%, ratiomatching (interposing) current transformers are required. When interposingC.T.s are used, connect main C.Ts in star, interposing primary in star andsecondary in delta.

    Ratio of interposing C.T.s Primary - 1A

    Secondary - 1/3 (or) 0.577A

    Actual Current on Secondary = 0.875/ 3 = 0.505 A

    Pilot current in relay circuit = 0.505 x3 = 0.875A

    The Pilot current in relay circuits both on H.V. and L.V. sides are 0.875A

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    6/65

    6

    Differential Operation during External Fault (Phase to Ground):

    Differential Relay : Does not operate

    120 A

    2 A

    2A 2 A

    120 A

    120 A

    2 A2 A

    2 A2 A

    2 A2 A

    2 A

    60/1600/0.577A

    2078 A

    Current in Pr. Tr.

    Current in CT

    Secondary

    Pr. Tr.110/11kV

    b

    c

    a

    Differential Connection with ICTDYn 11

    ICT

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    7/65

    7

    During External Fault (Phase to Phase) :

    Differential Relay : Does not operate

    2 A

    2 A 2 A

    120 A

    2 A2 A

    2 A2 A

    2 A

    60/1A

    600/0.577A

    2078 A

    Current in Pr. Tr.

    Current in CT Secondary

    Pr. Tr. 110/11kV

    10MVA

    b

    c

    2078 A

    2078 A120 A

    120 A

    120 A

    240 A4 A

    2 A

    2 A

    4 A

    4 A4 A

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    8/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    9/65

    9

    During Internal Fault (Phase to Phase) :

    Differential Relay : Operates

    2 A

    2 A2 A

    120 A

    2 A

    2 A

    60/1A600/0.577A

    Current in Pr. Tr.

    Current in CT Secondary

    Pr. Tr. 110 /11kV

    10MVA

    b

    c

    a

    2078 A

    2078 A120 A

    120 A

    120 A

    240 A4 A

    4 A

    2 A

    2 A

    2 A

    4 A

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    10/65

    10

    4.4. C.T. Requirement:

    Class PS C.T.s are used in differential protection and the C.Ts are

    usually provided in the transformer bushing itself with the required ratio based onthe power transformer voltage and power rating. C.T.s associated withdifferential relay should be of low reactance type as per IS 2705 Part IV. Inaddition, C.T.s should develop knee point voltage as given below.

    Vk > 2 If(RCT+ 2 RL) for star connected CTs

    2 If> ------- (RCT+ 3 RL) for Delta connected CTs

    3Where,

    If = Maxim um through fault current referred to secondaryWinding of s tar connected C.T. with a 3 phase systemFault.

    RCT = Secondary winding resistance of C.T.RL = One way lead resistance between C.T. terminals and

    the relay terminals.(or) Vk = 40 I (RCT+ 2 RL)

    I = Relay rated current

    At the knee point, the C.T becomes saturated and the magnetizing currentis less than 0.03 x I at Vk / 4. The C.T. output being unsymmetrical in the

    positive and negative half cycles generate second harmonic content. Unlessextremely large C.T. cores are used this problem cannot be overcome totally.The relay will be sluggish during heavy internal faults with moderately sizedC.T.s.

    Please refer manual on pre-commissioning and periodical testing ofelectrical installation TNEB and the The practical guide to differential protectivescheme to power transformer by Er. A.S. Kandasamy M.E., Rtd., Chief Engineer

    / Transmission for testing of bushing CTs in detail.

    5. PERCENTAGE (OR) BIASED DIFFERENTIAL RELAYS

    In the differential protection for transformers, there will be two groups ofC.Ts each consisting of 3 Nos , one group connected in star with secondary rating1 A and other group connected in delta with secondary rating 0.577A. Thetransformer differential relay compares the currents in the windings of thetransformer through the medium of C.Ts whose ratios are such as to make theirsecondary currents normally equal except for the core magnetizing currents ofthe transformer which are relatively small. Even under normal operatingconditions, small unbalance current in milli amps (spill current) may appear.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    11/65

    11

    At high through fault current, the unbalance between C.Ts secondaryincreases with increase of through currents which is sufficient to actuate thedifferential relay. Bias relay is used to overcome this problem for external faults.

    The spill current required to operate the relay is usually expressed as apercentage of the through currents in the restraining coils and the ratio isgenerally termed as percentage s lope.

    The purpose of % slope characteristics is to prevent undesired relay operationbecause of unbalance between C.T. s during external fault arising from anaccumulation of unbalances for the following reasons.

    1) Tap changing in the power transformer2) The difference between the errors of the C.Ts on either side of the

    power transformer.3) Possible mismatch of ratio among different current transformers.4) Phase displacement between primary and secondary current.5) The difference in the magnetizing characteristic of H.V. & L.V. Side

    C.Ts

    These unbalances are in the same direction to get the total maximumunbalance. The slope of this line is approximately the total percentagemismatch. Then add at least 5% to this value, and the new total is the minimumpercentage slope that should be used. The bias setting will be ensured to avoidunwanted operation due to spill current at through fault and yet maintain highsensitivity for internal fault.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    12/65

    12

    6. RELAY TEST SETUP

    6.1 Relay Test Setup:

    a) 500 V megger - 1 No.b) Supply extension box with RCCB - 1 No.c) DPST Switch - 1 No.d) Variable Voltage Transformer (Variac) - 1 No.e) Rheostart (Non-inductive) 40, 5A - 2 Nos.f) A.C Ammeter range (0 5A) - 1 No.g) A.C Milli Ammeter range (0 1000) - 1 No.h) Diode IN 4007 / 5 Amps - 1 No.i) A.C. Ammeter range (0 20 A) - 1 No.

    j) D.C. Ammeter range (0 1A) - 1 No.

    k) Tim e interval meter (Digital) - 1 No.l) Digital multimeter - 1 No.

    6.2 Insulation Test:

    Before testing of individual relays, the following items are to be measuredwith a 500V megger.

    a) IR values of D.C. Circuit to earth.b) IR values of main current transformer secondary circuit to earth.c) IR values of main current transformer secondary circuit to D.C. Circuit.

    d) IR values between main current transformer secondary circuits.

    The insulation resistance value has relation to the type of wiring and it is tobe considered for getting satisfactory results. However, the values of insulationresistances are to be noted in pre - commissioning test report and measuredfrom time to time to check deterioration of insulation during operation.

    7. TESTING OF THE BIASED DIFFERENTIAL RELAY

    The individual relay may be tested for the following characteristics inaccordance with the manufactures testing manual.

    Pickup test and operating time measurement test Bias characteristic test 2nd Harmonic Restraint test 5thHarmonic Restraint test High set test

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    13/65

    13

    7.1 Pickup test and operating time measurement test:

    Circuit Diagram:

    Ammeter Range - 0 to 500 mA HV - HV C.T. Current Input Terminal

    RCCB Rating - In 16A, In 30 mA LV - LV C.T. Current Input Term inalSpil l Unbalanced Current Terminal

    The Pick up Value indicates the minimum current in terms of percentageof rated current of the relay at which the relay would operate.

    Actual Relay Pick-up(Amps)Phase

    RelayPick-upset at HV LV

    A Phase

    B Phase

    C Phase

    Testing Procedure

    Pickup Test:

    1) Connect over current test set to any one H.V. C.T. input and operatingwinding terminals.

    2) Connect the 230V mains to over current tes t set.

    Bias Coils

    Operating

    Coil

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    14/65

    14

    3) Switch on Auxiliary Supply4) Keep pick-up setting at minimum position (20%) if variable pickup is

    available (or) fixed pickup setting.

    E.g.: 15% for EE make20% for ER make

    5) Switch on over current test set and slowly increase current value till therelay operates.

    6) Note down current value, it must be equal to pickup setting (or) within themanufacturers tolerance.

    7) Switch off the over current test set8) Reset the relay9) Repeat procedure for other HV and LV C.T. inputs.10) Repeat procedure for different pickup setting if available.

    Operating Time Measurement Test:

    1) Connect over current test set to any one HV C.T. input.2) Connect trip contact to stop terminal of timer3) Switch on Auxiliary Supply.4) Keep pickup setting on minimum position5) Switch on over current test set and adjust the current value as per

    manufacturer recommendation ie. 2.0 x In or 3.0 x In.where In - rated current.

    6) Switch off the over current test set and reset timer.7) Switch on the over current tes t and measure relay timing.

    8) Tim ing must be less than or equal to manufacturer specification.

    7.2 Bias Characteristic Test:

    Circuit Diagram:

    IbAmmeter Range - 0 to 4 AmpsIdAmmeter Range - 0 to 2 Amps

    Ib Bias Current (Circulate Around the Balancing Loop)Id- Differential Current (Out of Balance Current flow through operating coil)

    OperatingCoil

    Bias Coil s

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    15/65

    15

    Testing Procedure

    1) Connect test set up as shown in circuit diagram.

    2) Switch on Auxiliary supply.3) Keep bias set switch on required percent position.4) Keep pickup setting at minimum position.5) Adjust bias current Ib= 1 Amp by adjusting the resistance Rb.6) Slowly increase the differential current Id by decreasing resistor Rd

    until relay operate and note the value at which it operates.7) Calculate bias by us ing formula (or) compare the Id current limits as

    specified by the manufacturer.8) It must be equal or with in the tolerance as specified by the

    manufacturer.9) Repeat procedure for other bias setting and all other phases.

    10) After completion of testing, the bias current Vs differential currentcurve m ay be plotted and recorded for future reference.

    Id% BIAS = ----------------- x 100

    Ib+ (0.5 Id)

    Setting PhaseOperating Current

    Measured Id

    (Amps)

    Calculated% Bias

    IdLimits

    A

    BIb:

    CAB

    % Bias : 20 %

    Ib:

    CABIb:

    CA

    B

    % Bias : 30 %

    Ib:CABIb:

    CAB

    % Bias 40%

    Ib:C

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    16/65

    16

    7.3 2nd

    Harmonic Restraint Test:

    For conducting this test at site, the circuit with rectifier can be made use of

    as shown circuit below. In this circuit, the relay is connected to receive both A.Cand half-wave rectified D.C. current. The percentage of second harmonicscurrent component generated in this circuitry is given in the formula.

    0.212 I2= -------------------- x 100

    0.45 I1+ 0.5 I2

    < 20%

    Circuit Diagram:

    A - A.C. Ammeter Range 0 5 Amps

    D.C. Ammeter Range 0 1 Amps

    D - Diode IN 4007 / 5 Amps.

    Phase IDCSet I2(Amps)

    IACmeasuredI1 (Amps)

    % Restraintcalculated

    HVA Phase

    LV

    HVB Phase

    LV

    HVC Phase

    LV

    Testing Procedure:

    1) Connect tes t setup as shown in Circuit Diagram2) Switch on Auxiliary Supply3) Keep I2 (D.C. Current through the test rectifier) 0.467 or 0.8 amps D.C.

    constant for 1 Amp and 2.335 Amp for 5 Amps rated relay.4) Observe, the relay should not operate.

    Bias Coil s

    Operating

    Coil

    1

    2

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    17/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    18/65

    18

    current may be measured by using power quality analyzerand recorded foreach power transformer for future reference.

    7.5 High Set Test:

    The differential relays are provided with a set instantaneous element forhigh speed protection against internal faults in the transformers.

    Circuit Diagram:

    A - A.C. Ammeter Range 0 20 Amps

    Actual Relay Pick-up

    (Amps)Phase

    Relay

    Pick-up

    set at HV LV

    A Phase

    B Phase

    C Phase

    Testing Procedure

    1) Connect test set up as shown in circuit diagram2) Switch on Auxiliary Supply.3) Keep High set at required position.

    Bias Coils

    Operating

    Coil

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    19/65

    19

    4) Switch on over current set and slowly increase current value till relayoperates.

    5) Note down current value it must be equal to within +/- 10%

    6) Repeat procedure for al l the three phases any one input.

    Operating time measurement test:

    1) Switch on over current tes t set and adjust the current value to 2 timesof High set value.

    2) Switch off the over current test set and reset timer.3) Switch on the over current test set and measure relay tim ing.4) Timing must be less than 20 milli seconds.

    8. CLASSIFICATION OF RELAYS AND THEIR TECHNICAL DATA

    8.1 Classification of Relays :

    Before we discuss the salient features of relays, what are the relaysavailable in board and their technical data are to be studied first.Static relays were mostly used in TNEB. The advanced microprocessor basedstatic relays are also nowadays utilized.

    The following make relays are available in board.

    Hindustan brown boveri

    Easun Reyrolle

    Asea brown boveri

    Ashida

    English Electric

    Duobias-M (ER-Make)

    All the above relays are classified in the categories of static and

    microprocessors based. Duobias-M relay is latest numerical version for

    transformer protection suitable for 2 & 3 winding.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    20/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    21/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    22/65

    22

    8.2 Comparison of Technical Data:

    S.No Description EE HBB ER ABB Ashida Duobias-M

    1. Current Rating 1 or 5A 1 or 5A1,1.73,

    5A1 or 5 A

    1 or 5Amp.

    1 or 5 Amp.

    Bias Setting 15 45% 10 50% 20 -40% 20 - 50% 20 45%10 70%(in steps of5%)

    Pickup Setting 15 % Fixed 20 50%20 %Fixed

    20 - 50% 20 -100%10 50%(in steps of5%)

    2.

    High Set

    Setting10 In Fixed - Optional

    8,13,20

    In2 20 In 4 to 25 In

    3.OperatingTime

    45m sec.

    30 60m sec.

    50m sec.

    30m sec.

    < 35m sec.

    30 m sec.

    4. Burden 0.39 VA 0.3 VA 1 VA 0.02 VA < 0.2 VA < 0.05VA

    5.Aux. supplyD.C.

    30, 110 205 V

    48, 110,250 V 30 V

    24 55 V110-250V

    18 40V85 250V

    24 to 135V88 to 280V

    6.Over loadingcapacity

    2 Incontinuously40 In 3 sec

    5 x In

    Continuously

    80 x In1 sec

    -

    10 x Incontino

    usly

    40 x Innormalcurrent

    3 x In Continuously250 x In1 sec

    7. Insulation Test2 KV

    50 Hz for1 min

    2 KV50 HzFor

    1 min

    2 KV50 Hz

    For1 min

    2.5 KV50 HzFor

    1 m in

    2.0 KV50 HzFor

    1 min

    2.0 KV50 HzFor1 min

    8.ImpulseVoltage Test

    5.0 KV / 1.2

    / 50 s5 KV

    1.2/50 s-

    5.0 KV

    1.2/50s5.0 KV

    5.0 KV

    1.2 / 50 s

    9.TemperatureRange -

    - 20C to+ 60 c -

    - 25C to+ 55C -

    -10oto

    + 55oC

    10.OperationalIndicator

    Flag LED Flag LED LED LED

    11.High SetIndication

    Nil Nil Nil LED LED LED

    12.ICTrequirement

    Yes Yes Yes Yes Yes Nil

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    23/65

    23

    8.3 Typical Block Diagrams and Connections:

    English Electric

    Ashida Relay

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    24/65

    24

    9. COMPARISION OF OLD AND NEW VERSION RELAYS

    9.1 Principle and Operation of Old Make ER 4C21 Relay

    Schematic Diagram

    C.T. Secondary currents circulate through the primary winding of the biastransformer, the rectified output of which is applied to the bias windings of thetransductor via the shunt resistor. Spill current (or) out-of-balance current flowsfrom the centre top of the primary winding of the bias transformer energizing thetranductor input winding and the harmonic bias unit.

    Normal Condition / Through Fault Condition

    As long as the power transformer is healthy, the transductor bias-windingis energized by full-wave rectified current which is proportional to the load (or)through fault current, this bias current saturates the transductor. The smallamount of out-of-balance currents in the transductor input winding i.e., operatingm.m.f does not exceed the bias m.m.f., resulting change in working flux density issmall and consequently the output to the relay is negligible.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    25/65

    25

    Internal Fault Condition

    If there is an internal fault, the operating m.m.f. produced by the

    secondary fault current in the transductor input winding exceeds the bias m.m.f.resulting in a large change in working flux density. This produces acorrespondingly large voltage across the relay winding; the resultant currentoperates the relay.

    Magnetizing in-rush conditions

    The harmonic bias unit is a simple tuned circuit which responds to thesecond harmonic component of the magnetizing current. When magnetizing in-rush current flows through the relay operating circuit, the rectified output of theharmonic bias unit is injected into the transductor bias winding and restrains the

    relay.

    9.2 New Version A.B.B. Make RADSB Type

    Principles and Operations

    Schematic Diagram

    The output voltage from biased transformer T1 is rectified and obtainedregulated Negative voltage Ut after pass ing through non-linear circuit. Thetransformer T2 has two secondary winding with suitable adapted load resistors.One of the winding provides the voltage that initiates operation at internal fault.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    26/65

    26

    The voltage passes through a low-pass fil ter and then rectified in an idealrectifier. Finally the positive voltage Udis obtained. Another winding providesthe voltage to restraint the operation at inrush. The voltage passes through two

    band-pass filters tuned for 2nd and 5th harmonics and provides after an idealrectifier a negative voltage Uh is obtained. The bias voltage Ut, harmonicsNegative voltage Uhand differential voltage Udare summed and supplied to leveldetector. The resultant voltage Usis compared with reference voltage Urwhich isselectable in front of Relay panel. The output voltage Ua is constant amplitudeand the time is proportional to variation of voltage with reference voltage. Thevoltage pulses Uaare integrated (Ub) and compared permanently set referencevalue Uzof the level detector. If Ube xceeds Uz, relay drive output trips relay.

    Magnetising in-rush Condition: The harmonic voltage Uh is opposite to thevoltage Udand prevents operation.

    Internal Fault Condition: The voltage Uh will be lower than voltage Ud, thedifferential relay will therefore operate.

    Normal Condition : The voltage U t opposite to Ud, the restraint the relayoperation small at small through currents and large at large through currents.

    9.3 NUMERICAL VERSION RELAY :

    Duo Bias M (ER Make):

    Duo Bias - M is an integrated multi microprocessor relay capable ofproviding all the transformer protection and alarm function for a 2 or 3 windingpower transformers. The protection function provided are current differential

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    27/65

    27

    protection with load bias and second harmonic bias, differential high set overcurrent and restricted earth fault for each transformer winding. For a transformerdifferential protection it is necessary to correct the phase relationship and

    magnitude of the C.T. secondary currents resulting from the arrangement of theprimary and secondary power transformer winding. Previously this wasaccomplished using a complicated combination of interposing C.T. s and star /delta arrangements to the current circuit. Duobias M eliminates this for almostall application.

    The relay includes internal vector group compensation and currentamplitude correction for each transformer winding. Duo Bias M includes apowerful storage facility of HV and LV waveforms, indication and the status ofeach d.c. plant input and each output relay. The LCD on the front of the relayshows values for operate and restraint currents, and those following amplitude

    and vector correction. This feature greatly simplifies commissioning and enablesthe rapid verification of data.

    The input I1 represents the current on the HV side of the protectedtransformer after any necessary phase shifts and amplitude modification hasbeen applied, and I2 represents the equivalent current on the protectedtransformer LV s ide. The Algorithm calculates the functions I1, I2and these twosignals are processed to form the operate and restraint signals respectively.Both signals are digitally filtered to remove any unwanted DC and the filteredsignals are converted to RMS value calculated over the previous cycle beforecomparison. Second harmonic quantities are calculated from the signal I1 I2to

    provide an inhibit signal to prevent the protection operating for magnetizinginrush conditions. The high set protection operates when the RMS value of thesignal I1 I2is greater than a Pre set value which can be varied. All settings onthe characteristic are under software control and characteristic has been madeflexible to cover the wide range of application encountered in transformerprotection.

    Typical Connections Diagram :

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    28/65

    28

    9.4 COMPARISION OF OLD AND NEW RELAYS

    S.No. Old Version New Version

    1. Static circuiting is employedMicroprocessors based circuiting is

    employed.

    2.5

    thharmonic by pass circuit is

    employed.

    5thharmonic restraint circuit is

    employed.

    3. Fixed pickup only Variable pick up is possible.

    4. Bias range is limited Wide bias range is possible.

    5.Only one trip indication for all

    phases

    Individual phase has separate

    indication for trip.

    6.No separate indication for High Set

    trip.

    There is separate indication for

    High Set.

    7. High set is fixed High set is selectable

    8. Limited Auxiliary supply range Wide range is available.

    9. Operating time is large Operating time is lesser

    10. Burden is high Burden is minimum

    11.

    Mechanical checking is necessary to

    flag indicator and output armature

    pickup relay for free from dust.

    There is no need for mechanical

    checking because of separate

    enclosure for dust proof.

    12. No Data Storage Facility

    Data Storage facility is available

    for pre-fault and post fault

    information.

    13.Self Monitoring Facility is not

    availableSelf Monitoring Facility is available

    14. ICT maybe required ICT is not required

    15.

    External auxiliary relays are required

    for other protection like Buchholz, oil

    and winding temperature etc.,

    Auxiliary relays function is also

    provided in a single unit of

    Differential relay.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    29/65

    29

    9.5 TYPICAL TEST RESULTS - I

    Tamilnadu Electricity BoardGobi Electricity Distribution Circle, GobiSub Division: MRT

    Date: 19-01-05Name of the SS : Chennampatty 110/22KVSSRelay Make : ABBType : RADSBArt No. : IN7454 3344 CESerial No. : 807062Current Rating : 1AVoltage Rating : 110V

    (Isr) Bias Setting Available : 0.2, 0.25, 0.35 & 0.5 In Adopted: 0.35 In(Isu) High Set Available : 8, 13 & 20 In Adopted: 13 InFlag Operation : LED

    Connections

    Phase Injection Terminals RADSB Aux-supply terminal

    A H.V. 3

    L.V. 6

    Spill12RXTUG2H

    B H.V. 4 T.B. TerminalL.V. 7 +ve116

    Spill13 -ve 118

    C H.V. 5L.V. 8

    Spill14

    IR Values:-

    i) D.C. Circuit to Earth : 40 M ohm

    ii) C.T. Circuit to Earth : 50 M ohm

    iii) C.T. Circuit to D.C. Circuit : 40 M ohm

    iv) Main C.T. to ICT Circuit : 70 M ohm

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    30/65

    30

    Pick Up Test

    Actual Relay Pick-up (Amps)Phase

    RelayPick-upset Isr HV LV

    ManufacturerLimit

    A Phase 0.35 0.33 0.33B Phase 0.35 0.33 0.33C Phase 0.35 0.33 0.33

    + 10% of setCurrent

    Bias Characteristic:

    Setting PhaseOperating Current

    Measured Id(Amps)

    ManufacturerIdLim its(Amps)

    A 0.78B 0.75Ib: 1.5A

    C 0.74

    0.65 to 0.95A

    A 1.78B 1.78

    Isr set at0.35 In

    Ib: 3.0A

    C 1.73

    1.6 to 2.2A

    2nd

    Harmonics Test :

    0.472 I2% Restraint = ---------------------- x 100

    I1+ 1.11 I2

    Keep I2 = 0.8A DC Constant for 1 A relay

    PhaseIDCSet I2

    (Amps)

    IACmeasured

    I1 (Amps)

    % Restraint

    calculated

    Manufacturer

    Limits of I1

    HV 0.8 1.52 15.6A Phase

    LV 0.8 1.59 15.2

    HV 0.8 1.67 14.7B Phase

    LV 0.8 1.68 14.6

    HV 0.8 1.69 14.6C Phase

    LV 0.8 1.68 14.6

    14% to 18%

    (1.2 to 1.8A)

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    31/65

    31

    High Set Test :

    Actual Relay Pick-up (Amps)Phase

    RelayPick-upset Isu HV LV

    Manufacturer

    Limits of setcurrent

    A Phase 13A 12.7 12.7B Phase 13A 12.3 12.3

    C Phase 13A 12.6 12.6

    + 10%

    Operating Time Measurement

    Manufacturer Data : 3 Isr = approx 30 m sec.Isr = 0.35A

    3Isr = 0.35 X 3 = 1.05 A

    Operating time measured for 3Isr= 27 m sec.

    High Set Operating Data : 2 Isu = 10 to 20 m sec.Is u = 13 Amps

    2 Isu = 13x2 = 26 Amps

    Operating time measured for 2 Isu = 12 m sec.

    BIAS SLOPE CURVE

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    32/65

    32

    9.6 TYPICAL TEST RESULTS - II

    Tamilnadu Electricity BoardGobi Electricity Distribution Circle, GobiSub Division: MRT

    Date : 26.05.05Name of the SS : Nambiyur 110 / 11 KVSSRelay Make : EEType : DTH31Art No. : DTH31FF8011A (m)Serial No. : m432840Current Rating : 1AVoltage Rating : 30V

    Pickup Setting Available : 15% Fixed% Bias setting Available : 15, 30 and 45 Adopted : 30%High set Available : 10 Amps Fixed Adopted : -Flag Operation : Flag

    Connections

    Phase Injection Terminals DTH31 Aux-supply terminal

    A H.V. 11

    L.V. 14

    Spill 12

    B H.V. 15 T.B. TerminalL.V. 18 +ve19

    Spill 16 -ve 20

    C H.V. 7L.V. 10

    Spill 8

    IR Values:-

    i) D.C. Circuit to Earth : 30 M ohm

    ii) C.T. Circuit to Earth : 40 M ohm

    iii) C.T. Circuit to D.C. Circuit : 30 M ohm

    iv) Main C.T. to ICT Circuit : -

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    33/65

    33

    Pick Up Test

    Actual Relay Pick-up (Amps)Phase RelayPick-upFixed HV LV

    ManufacturerLimit

    A Phase 0.15 0.15 0.15B Phase 0.15 0.15 0.15C Phase 0.15 0.17 0.17

    12% to 18%of ratedcurrent

    Bias Characteristic:Id

    % Bias = --------------- x 100

    Ib+ (0.5 Id)

    Setting Phase

    OperatingCurrent

    Measured Id(Amps)

    Calculated %Bias

    ManufacturerLimits

    A 0.34 29%

    B 0.34 29%Ib:1.0A

    C 0.36 30.5%A 0.68 29%

    B 0.68 29%

    % Bias :30%

    Ib:2.0A

    C 0.69 29.4%

    + 10% ofBias Setting

    (%)

    2ndHarmonics Test:

    0.212 I2% Restraint = ---------------------- x 100

    0.45 I1+ 0.5 I2

    Keep I2 = 0.467A DC Constant for 1 A relay

    PhaseIDCSet I2

    (Amps)IACmeasured

    I1 (Amps)% Restraintcalculated

    ManufacturerLimits

    HV 0.467 0.99 14.5%A Phase

    LV 0.467 0.97 14.7%

    HV 0.467 1.11 13.5%B Phase

    LV 0.467 1.11 13.5%

    HV 0.467 1.07 13.8%C Phase

    LV 0.467 1.07 13.8%

    12% to 20%

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    34/65

    34

    High Set Test :

    Actual Relay Pick-up (Amps)Phase

    RelayPick-upFixed HV LV

    Manufacturer

    Limits of setcurrent

    A Phase 10A 9.2 9.2B Phase 10A 9.4 9.4

    C Phase 10A 9.5 9.5

    + 10%

    Operating Time Measurement

    Manufacturer Data : 45 m sec at 2 times Setting CurrentSet Current Id= 0.15 Amps

    Operating time measured for 2 Id= 46 m sec.

    Bias Slope Curve :

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    35/65

    35

    10. ANALYSIS OF DIFFERENTIAL PICKUP FEATURE

    A series of tests have been done with the object of confirming that the

    relay is capable of differentiating between the harmonic content of a magnetizingsurge and harmonics present in the output current of a heavily saturated C.T.under internal fault conditions.

    The relay is extremely stable during through faults and provides highspeed operation on internal faults.

    In addition, fifth harmonic restraint to avoid mal operation under over-excited condition.

    While conducting the test, the following problems are associated with the

    application of differential relay.

    10.1 Pickup Test:

    An object of confirming that, the relay required minimum current inoperating coil to cause operation.

    a) What is the setting of bias at pickup test?

    During the test, the current is passed through one half of the bias windingand the operating winding.

    The pickup value of operating coil is independent of the bias setting.Therefore, keep the bias setting at the lowest value.

    b) How to select pickup setting?

    In old relays, the biased differential element has a fixed setting of the ratedcurrent. It indicates the minimum current in terms of percentage of the ratedcurrent of the relay at which it would operate.

    In practice there will always be some differential current flowing due toC.T. errors, ratio mismatch and tap changing. Therefore, the differential current isrequired to be a certain percentage of the mean through current before the relaywill operate. To prevent the relay operating on the steady state magnetizingcurrent of the transformer, a fixed setting is incorporated of 15% (or) 20% of therelay rated current. Initial pickup is continued with bias slope characteristic.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    36/65

    36

    The following conditions should be considered in addition, while selectinga proper pickup setting.

    a) The interconnecting leads of the main CTs are of the same length(or) different length on each side of the relay.

    b) Interpose C.T.s are connected on one side of the differential relay.

    c) The prior loading of the current transformer meant for the differentialrelay is in series with breaker over current relays.

    d) Whether main current transformers are of different rating, their over-current factors and their accuracy class.

    Conclusion:

    Normal setting of pickup for Power Transformer Differential relayis 20% of rated current.

    At any time, the pickup setting should not exceed 50% of rated current.

    11. ANALYSIS OF BIAS CHARACTERISTIC FEATURE

    An object of confirming that the relay is capable of differentiating betweenthe faults is external or internal. The relay is extremely stable during throughfault and high speed operation on internal fault and yet maintains high s ensitivityfor internal faults when the differential current may be relatively small.

    SettingRange( 0.1-0.5 )

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    37/65

    37

    a) What is the setting of pickup at Bias characteristic test?

    Selected pickup as per previous discussion may be adopted. If the relay

    is tested for the first time, conduct bias slope characteristic with minimum pickupand then conduct with selected pick up as per our requirement. The two slopecharacteristics may be plotted and recorded for Bench Marking.

    b) What is the effect of bias slope characteristic at higher pickup?

    If higher pickup is adopted inadvertently, the bias slope characteristic ofthe relay not followed set bias characteristic initially. The through fault currentexceeds the 200% of rated current then it followed set bias characteristic.

    Test Example: 1

    Name of the SS : Thalavaipettai 110/22KV SS

    Relay Make : Ashida, 1 Amp, 110V

    Type : ACDF31HA

    S.No. : 2KBDF005

    Date : 25-08-2005

    Setting Ib PhaseOperating CurrentMeasured Id

    (Amps)

    Calculated% Bias

    0.5 A 0.20 33.331.0 A 0.34 29.061.5 A 0.52 29.542.0 A 0.69 30.532.5 A 0.87 29.64

    % Bias : 30 %Pickup : 20 %

    3.0 A 1.06 30.03

    0.5 A 0.59 74.211.0 A 0.59 45.55

    1.5 A 0.60 33.332.0 A 0.67 28.692.5 A 0.86 29.35

    % Bias : 30 %Pickup : 60 %

    3.0 A 1.04 29.54

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    38/65

    38

    The fig. has shows that, the Relay operating bias characteristic if selectedhigher pickup of 0.6 x In instead of 0.2 x In, it is clear that, the relay is sluggish atlow incipient fault because of non-operating region increases at low through fault.

    c) What is the exact bias slope?

    The differential current (Id) Vs through fault current (Ib) gives the bias slopecharacteristic. The relationship between % bias, differential current and thethrough fault current is,

    Id% Bias = ------------------------- x 100

    Ib+ (0.5 Id)

    The operating current Idat various through fault current Ibis given below.

    BiasCurrent

    0.5 1 1.5 2 2.5 3

    20% 0.11 0.22 0.33 0.44 0.55 0.6625% 0.14 0.29 0.43 0.57 0.71 0.8630% 0.18 0.35 0.53 0.71 0.89 1.135% 0.21 0.42 0.64 0.85 1.06 1.2740% 0.25 0.5 0.75 1.0 1.25 1.545% 0.29 0.58 0.87 1.16 1.45 1.74

    Id limit is + 10% Therefore % bias limit is + 2%

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    39/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    40/65

    40

    Bias Slope Curve

    For Example,

    Test Example : 2

    Name of the SS : Kolappalur 110/11KV SSRelay Make : ABB, 1 Amp, 110VType : RADSBS.No. : 407093Date : 27-08-2005

    Setting Ib PhaseOperating Current

    Measured Id(Amps)

    Calculated% Bias

    0.5 A 0.34 50.741.0 A 0.53 41.89

    1.5 A 0.69 37.392.0 A 0.94 38.052.5 A 1.39 43.50

    3.0 A 1.84 46.933.5 A 2.32 49.78

    0.35 In

    4.0 A 2.75 51.16

    It is clear that, the various bias at various through current (Ib). The % biasis high at First and Last. The % bias is low at Middle as compared with other.

    ie. 0.35 x Ingives 50% bias at First and last.0.35 x Ingives 40% bias at middle.

    Hence the Protection Engineer has to select particular bias feature forparticular power transformer carefully.

    % Bias Vs Ib

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    41/65

    41

    4) How to decide the healthiness of relay if slightly beyond the limits oftest results?

    If the test results are beyond the limit as per manufacture prescribedsettings and instruction, the relay may not be declared as defective immediately.The Protection Engineer has to analyze what are the options available in therelay for re-use effectively and to avoid procurement of new relay at a heavy costand revenue loss due to interruption.

    Hence the following steps should be carried out and desired.

    1) Conduct the bias test at various bias current.Ie. Ib= 0.5 ,1, 1.5, 2, 2.5, 3.0, 3.5 and 4.0 Amps.

    2) Bias curve plotted from the test reading.

    3) The drawn curve is to be compared with the slope curve mentioned incompany manufacturer.

    4) In case of major deviation during comparison, the particular relay shouldnot be allowed for commissioning.

    5) If there is a small deviation from manufacturer bias slope, the deviationregion is to be considered as,

    1stregion, Ib= 0 to 1 A, Idrequired to operate relay is 0.5 In.

    2nd

    region, Ib= 1 to 2.5A, Idrequired to operate relay is 1 In.3rdregion, Ib= 2.5 A and above, Idrequired to operate relay is above 1.5

    Permissible Limits

    Ist

    Region :

    The relay is sensitive up to differential current 0.5 Inat 100% through faultcurrent. Hence, deviation may be allowed differential current up to 0.5 In.

    2nd

    Region :

    This region is very im portant due to presence of incipient fault. The

    deviation in that region may be allowed + 2% only.

    3rd

    Region :

    The through fault stability is desired in that region at 250% and abovethrough fault current. The slope of bias may be deviated up to 80% ispermissible.

    (or)

    If you select either lower (or) higher bias settings to achieve the requiredbias s lope for particular power transformer.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    42/65

    42

    12. ANALYSIS OF 2ND

    HARMONICS RESTRAINT FEATURES :

    Test has been made to verify that the relay will remain inoperative under

    magnetizing in rush current up to 30 times the C.T. rating when the transformeris energized. In addition, confirming that the relay is capable of differentiatingbetween the inrush current and fault currents.

    1) What is inrush? How will affect the differential relay?

    During power transformer charging, an instantaneous change in fluxlinkage in a power transformer will cause abnormally large magnetizing(2

    ndharmonics) current to flow and has no counterpart on the secondary winding

    side. Consequently there is a spill current in the differential circuit which cancause the differential relay to mal operate.

    2) What is the purpose of diode in the 2ndharmonics restraint test circuit?

    The second harmonic restraint is effective to block the relay operationwhen the second harmonic current content of the differential current exceedsabout 20% of the fundamental. For testing this circuit at site, wheneverarrangements to generate second harmonic current is not available, an alternatecircuit with test rectifier can be made use of in this circuit the relay is connectedto receive both AC and half-wave rectified D.C. current.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    43/65

    43

    The percentage of second harmonic current component generated in thiscircuitry is given in the formula.

    0.2 1 2 I2------------------------------ x 100 < 20%

    0.45 I1+ 0.5 I2

    I1 = A.C. Current I2 = D.C. Current at constant value of 0.467 A

    Another method to derive the % 2nd

    harmonics restraint particularly ABBrelay recommends the following setting and the formula is given below.

    Set I2 D.C. Current at constant value of 0.8ATherefore, 2

    ndHarmonic restraint calculated from the formula,

    0.472 x I2------------------ x 100 = 14 to 18%I1+ (1.11 x I2)

    The comparison of I2settings (0.467 and 0.8 A) :

    Test Example : 3

    Name of the SS : Kolappalur 110/11KV SSRelay Make : ABB, 1 Amp, 110VType : RADSBS.No. : 407093Date : 27-08-2005

    Setting I2 PhaseOperating Current

    Measured I1(Amps)

    Calculated% Restraint

    0.8 A 1.53 15.610.8 B 1.54 15.55

    IsrSetting0.35 In%

    0.8 C 1.59 15.230.467 A 1.0 14.48

    0.467 B 1.0 14.48

    Isr

    Setting0.35 In%

    0.467 C 0.98 14.47

    The variation of the percentage restraint of the above two DC constantsare very small for the same relay at the same settings.

    3) What is the Bias setting at harmonic restraint test?

    The harmonic restraint values are independent of bias and pickup setting.Hence the bias and pickup settings are kept at selected rating.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    44/65

    44

    Test Example:

    Name of the SS : Thalavaipettai 110/22KV SS

    Relay Make : Ashida, 1 Amp, 110VType : ACDF31HAS.No. : 2KBDF005Date : 25-08-2005

    BiasSetting

    PickupSetting I2 Phase

    Operating CurrentMeasured I1

    (Amps)

    Calculated% Restraint

    20% 20% 0.467 A 0.49 21.845% 20% 0.467 A 0.49 21.8

    20% 60% 0.467 A 0.5 21.5945% 60% 0.467 A 0.5 21.59

    4) How to decide the healthiness of relay, if the 2nd

    harmonics % restraintexceeds slightly more than 20 %?

    Before we decide the healthiness of relay, we should understand theinrush phenomena when the transformer is energized.

    If the transformer is re-energized at the instant the voltage wave formcorresponds to the residual magnetic density within the core, there would be asmooth density within the core, there would be smooth continuation of theprevious operation with no magnetic transient.

    1

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    45/65

    45

    In practice, however, the instant when switching takes place in rush currentcannot be controlled and a magnetizing transient is practically unavoidable. Ifhowever, it is assumed that the circuit is re-energized at the instant when the flux

    would normally be at its negative maximum value (-max) the residual fluxwould have a positive value. Since magnetic flux can neither be created nor

    destroyed instantly, the flux wa ve, will start with the residual (R) and trace thecurve (1).

    Since power transformers operate near the knee of the saturation curve, a flux

    demand of 2mdrives the transformer core deep into saturation, causing it todraw a very large magnetizing current with a peaky non-sinusoidal waveform.Such non-sinusoidal or distorted waveform is known as harmonics. Themagnetizing current is, therefore, very high, of the order of 8 to 30 times the full-lode current. This current is known as inrush current. The inrush currentdecays rapidly for the first few cycles and then very slowly. Sometimes they take4 to 6 seconds to subside.

    The inrush wave form is predominantly 2nd

    Harmonic content, whereas,the internal fault current consists of only of the fundamental. Thus, we candevelop additional restraint based on harmonic content of the inrush current.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    46/65

    46

    The Percentage second harmonic restraint value should be less than20%. Even if the Percentage restraint exceeds slightly more than 20%, the relayis considered to be healthy if the differential relay does not actuate for inrush

    current for ten operations of power transformer without load.

    In recent years improvem ents in core steel and design has resulted in lessinrush current harmonics with possibilities of the second harmonics being as lowas 7%. Now a days power quality analyzerinstruments are available to studyactual harmonic present in the current wave while transformer energized withoutload. Record the values for benchmark with future comparison.

    5) What is the working principle of zero crossing detection methodand how it will effectively utilize 2

    ndharmonic & 5

    th harmonic restraint in

    new differential relays?

    This method, does not involve harmonic filter circuit and their associateddelay. A different approach, working on the direction of zero crossing in thecurrent wave form, was therefore evolved to distinguish between genuine faultconditions and conditions of inrush and over fluxing.

    An examination of the wave form reveals there is a substantial period ofthe half cycle when the current remains zero (or) near zero, unlike in a faultcurrent wave form passes through zero current quickly. It can be seen that the

    gap detecting method as shown can distinguish between fault condition andother by looking at the duration of the gap produced. This basically comprisestwo timers. Their operation in conjunction with the differential comparator (theheart of the relay).

    In simple terms, the arrangement is such that timer 2 is set to trip after acertain time while timer 1 is set to inhibit timer 2 after its operating time, unlessit itself is prevented from doing so by the comparator. The latter does not inhibittim er 1 unless the current magnitude is above the set threshold. The thresholdlevel is varied by the current setting on the front of the relay.

    DifferentialComparator

    Timer 1 Timer 2Trip

    Bias

    Differential

    Threshold

    Inhibit Inhibit

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    47/65

    47

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    48/65

    48

    Circuit Diagram

    D=Diode (IN4007 / 5 Amps)

    Relay OperationPhases S1

    S2 Closed S2 Open

    HV ClosedA Phase

    LV Closed

    HV ClosedB Phase

    LV Closed

    HV Closed

    C PhaseLV Closed

    Testing Procedure:

    1) Connect tes t setup as shown in circuit diagram.2) Switch on Auxiliary supply.3) Close Switch S1and S2and set the current equal to rated current of relay,

    check that the relay operates.4) Open Switch S2, Close Switch S1and check that relay does not operate.

    In this test, % 2nd

    harmonics restraint could not be measured. Themanufacturer has recommended energizing transformer 10 times without loadand checking that the relay does not mal - operating. If the % 2nd harmonicsrestraint value is required, the routine 2

    nd harmonic bias test will be conducted

    and record the % value for future comparison.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    49/65

    49

    13. ANALYSIS OF HIGH SET FEATURE

    The differential relays are provided with a set instantaneous element for

    high speed protection against internal faults in the transformers. Such faultinvolves very high fault currents and this causes the C.Ts to go into partialsaturation and the resulting harmonics slow down relay operation. To take careof such a contingency, the differential relay is provided with an unrestrained highset element. A setting of at least ten times rated current is usual to preventoperation of this element during transformer inrush.

    High set is determined by the m agnitude of the inrush current to the powertransformer and thus affected by the rating and the connection of the powertransformer. High set should be set as low as possible but not less than themaximum 3 phases through current and not less than maximum magnetizing

    current. If the power transformer connection is Dy and the rating between 10 to100 MVA, the recommend high set value is around 13 In. If below 10 MVA, the

    high set value will be around 20 In. The operating time of high set will be alwaysless than 20 milli seconds. When the differential relay is also to provide busprotection, the setting (20 In) should be chosen to ensure stability for through busbar faults . To ensure still better through fault stabil ity this element has also anauto ranging setting feature whereby it is caused to increase in the throughcurrent. Hence optimum performance is ensured at all times.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    50/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    51/65

    51

    Voltage drop e = 2 x R x I

    (or)

    e = 2 x L x I/ (K x q)

    Where,

    e = Voltage drop in voltsR = Resistance in ohm (Lead One Way)

    I = Line current in AmpsL = Length in meter (Lead One Way)q = Conductor cross section in sq.mm.K = Conductivity (for Cu = 56, Al = 35)

    14.3 Secondary Current Injection:

    Open intentionally two pilot wire terminals at the C.Ts secondary terminalsand inject current just above the pickup value and ensure D relay picks up andtripping command is sent from the D relay to the master relay. This can bedone on either sides H.V. as well as L.V. and on all three phases. After theabove test, ensure that all the pilot wires are properly connected to the terminalswith adequate tightness, and test the connections by primary current injection.Do not open circuit the secondary circuit of a current transformer under load

    conditions since the high voltage produced may be lethal and could damageinsulation.

    14.4 Testing the Protective Scheme by Injecting Three Phase PrimaryCurrent:

    This method is mainly applied to check the differential protections toensure that the current transformer connections have been made according tothe vector group. Possible errors on the diagram or in the actual secondarywiring are,

    a) C.T. s starred on wrong side.

    b) Wrong delta connection used on C.T.

    c) Pilots between C.T.s crossed over.

    d) C.T. polarities are interchanged.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    52/65

    52

    Figure shows the test circuit set up for checking a differential protectionscheme of a power transformer. The transformer is solidly shorted on the lowvoltage side by means of a set of temporary test short circuit conductors andthree phase supply from 400V tes t main is applied to high voltage winding.

    The through currents measured at relay terminals both H.V. and L.V. s idewill be in milli amps. The operating current measured should be negligible if therelay is connected correctly to the current transformers and if the C.T. polaritiesare correct.

    14.5. The possibilities of secondary wrong connections :

    The possibilities of secondary wrong connections of powertransformer bushing C.Ts and the corresponding spill currents at

    differential relay end were taken at

    THALAVAIPETTAI 110/22 KV Sub-Station

    Power transformer ANDREW YULE make 10 MVA

    Tested date : 10-06-2004

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    53/65

    53

    1. Correct Connection:

    2. Wrong Connection:

    B and C phase pilot wire transposed on H.V. Side

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.6 ma (I)

    HVB : 42.2 ma (I)HVc : 42.7 ma (I)

    LVa : 42.3 ma (I)LVb : 41.8 ma (I)

    LVc : 41.7 ma (I)Spill A : 0.3 ma

    Spill B : 0.3 maSpill C : 0.5 ma

    HVN : 0.1 ma

    Current measured at the Di fferential

    Relay Terminals:-

    HVA : 42.8 ma (I)HVB : 41.9 ma (I)

    HVc : 43.0 ma (I)LVa : 42.5 ma (I)

    LVb : 41.9 ma (I)LVc : 41.8 ma (I)

    Spill A : 0.3 ma

    Spill B : 72.7 ma (3I)Spill C : 70.4 ma (3I)HVN : 0.1 ma

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    54/65

    54

    3. Wrong Connection:

    C phase C.T. reversed on H.V. Side

    4. Wrong Connection :

    B & C Phase C.T. Reversed on H.V. Side

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.8 ma (I)

    HVB : 42.3 ma (I)

    HVc : 42.6 ma (I)

    LVa : 42.6 ma (I)LVb : 42.6 ma (I)

    LVc : 42.0 ma (I)

    Spi ll A : 0.4 maSpi ll B : 0.6 ma

    Spill C : 84.1 ma (2I)

    HVN : 84.7 ma (2I)

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.7 ma (I)

    HVB : 42.3 ma (I)HVc : 42.3 ma (I)

    LVa : 42.5 ma (I)LVb : 41.9 ma (I)

    LVc : 41.5 ma (I)Spi ll A : 0.5 ma

    Spill B : 84.5 ma (2I)Spill C : 83.4 ma (2I)

    HVN : 85.5 ma (2I)

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    55/65

    55

    5. Wrong Connection:

    S1 Star on H.V. Side

    6. Wrong Connection:

    B & C Phase transposed and A Phase C.T. Reversed on H.V. Side

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.3 ma (I)HVB : 42.0 ma (I)HVc : 42.0 ma (I)

    LVa : 42.6 ma (I)LVb : 41.5 ma (I)

    LVc : 41.6 ma (I)

    Spill A : 84.4 ma (2I)

    Spill B : 84.0 ma (2I)Spill C : 83.4 ma (2I)

    HVN : 0.6 ma

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.3 ma (I)

    HVB : 39.3 ma (I)HVc : 43.0 ma (I)LVa : 42.0 ma (I)

    LVb : 41.5 ma (I)

    LVc : 41.7 ma (I)Spill A : 84.2 ma (2I)

    Spill B : 72.5 ma (3I)Spill C : 72.4 ma (3I)HVN : 84.5 ma (2I)

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    56/65

    56

    7. Wrong Connection:

    S1 - out on LV Side

    8. Wrong Connection:

    Reverse Delta, S2 - out on LV Side

    Current measured at the Di fferential

    Relay Terminals:-

    HVA : 43.0 ma (I)

    HVB : 42.5 ma (I)HVc : 42.9 ma (I)

    LVa : 41.6 ma (I)LVb : 41.3 ma (I)

    LVc : 42.6 ma (I)

    Spill A : 72.6 ma (3I)Spill B : 72.6 ma (3I)Spill C : 73.0 ma (3I)HVN : 0.4 ma

    Current measured at theDifferential Relay Terminals:-

    HVA : 42.1 ma (I)

    HVB : 41.8 ma (I)HVc : 42.8 ma (I)

    LVa : 42.0 ma (I)LVb : 41.8 ma (I)LVc : 43.2 ma (I)

    Spill A : 40.8 ma (I)Spill B : 42.5 ma (I)Spill C : 41.6 ma (I)

    HVN : 0.4 ma

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    57/65

    57

    9. Wrong Connection:

    Reverse Delta, S1 - out on LV Side

    10. Wrong Connection:

    a & c PhasePilot Wire transposed on LV Side

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.5 ma (I)HVB : 42.9 ma (I)HVc : 42.6 ma (I)

    LVa : 42.2 ma (I)LVb : 41.6 ma (I)

    LVc : 41.6 ma (I)

    Sp ill A : 83.8 ma (2I)

    Sp ill B : 84.6 ma (2I)Sp ill C : 83.6 ma (2I)

    HVN : 0.5 ma

    Current measured at theDifferential Relay Terminals:-

    HVA : 42.0 ma (I)HVB : 42.3 ma (I)HVc : 42.8 ma (I)

    LVa : 41.2 ma (I)LVb : 41.7 ma (I)

    LVc : 42.4 ma (I)Spill A : 71.3 ma (3I)Spill B : 0.6 ma

    Spill C : 72.5 ma (3I)HVN : 0.4 ma

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    58/65

    58

    11. Wrong Connection:

    c Phase CT Reversed on LV Side

    12. Wrong Connection:

    b &c phase CT reversed on LV Side

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 41.5 ma (I)

    HVB : 42.4 ma (I)

    HVc : 42.3 ma (I)

    LVa : 23.8 ma (I/3)LVb : 41.5 ma (I)

    LVc : 24.0 ma (I/3)

    Sp ill A : 47.7 ma (2I/3)Spill B : 0.4 ma

    Sp ill C : 48.0 ma (2I/3)HVN : 0.2 ma

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.0 ma (I)

    HVB : 42.3 ma (I)HVc : 42.4 ma (I)

    LVa : 24.0 ma (I/3)LVb : 23.7 ma (I/3)

    LVc : 41.5 ma (I)Spill A : 47.7 ma (2I/3)Spill B : 47.8 ma (2I/3)Spill C : 83.2 ma (2I)

    HVN : 0.7 ma

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    59/65

    59

    13. Wrong Connection:

    a & c phase Pilot Wire Transposed and c phase CT reversed on LV Side

    14. Wrong Connection:

    a & c phase Pilot wire Transposed and b & c phase CT reversed on LV side

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.2 ma (I)

    HVB : 42.4 ma (I)HVc : 42.6 ma (I)

    LVa : 24.6 ma (I/3)LVb : 41.9 ma (I)

    LVc : 24.2 ma (I/3)Sp ill A : 23.7 ma (I/3)

    Spill B : 0.5 maSp ill C : 23.8 ma (I/3)HVN : 0.1 ma

    Current measured at the Di fferentialRelay Terminals:-

    HVA : 42.9 ma (I)

    HVB : 42.9 ma (I)HVc : 42.7 ma (I)

    LVa : 41.3 ma (I)

    LVb : 23.7 ma (I/3)LVc : 24.1 ma (I/3)Sp ill A : 40.5 ma (I)

    Sp ill B : 47.9 ma (2I/3)Sp ill C : 24.0 ma (I/3I)HVN : 0.2 ma

    LV

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    60/65

    60

    15. Wrong Connection:

    C phase CT reversed on HV Side and a phase CT reversed on LV side

    16. Wrong Connection:

    C phase CT reversed on HV side, a & b phase CT reversed on LV side

    Current measured at the Di fferential

    Relay Terminals:-

    HVA : 42.1 ma (I)

    HVB : 41.7 ma (I)

    HVc : 42.4 ma (I)

    LVa : 23.4 ma (I/3)LVb : 23.9 ma (I/3)

    LVc : 41.6 ma (I)Spill A : 47.7 ma (2I/3)Spill B : 48.8 ma (2I/3)Spill C : 83.2 ma (2I)HVN : 85.2 ma (2I)

    Current measured at the Di fferential

    Relay Terminals:-

    HVA : 42.4 ma (I)

    HVB : 42.8 ma (I)HVc : 42.6 ma (I)

    LVa : 23.5 ma (I/3)

    LVb : 41.3 ma (I)LVc : 24.2 ma (I/3)Spill A : 47.9 ma (2I/3)Spill B : 84.0 ma (2I)

    Spill C : 48.3 ma (2I/3)HVN : 84.6 ma (2I)

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    61/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    62/65

    62

    CONCLUSION:

    H.V. Side C.T. reverse reflects in common neutral (H.V.N) and Spill. H.V. Side Pilot transposed reflects in spill. L.V. Pilot transposed reflects in spill. L.V. Side Pilot taping at positive junction (S1out) reflects in spill. L.V. Side C.T. DELTA B connection (reverse delta) reflects in spill. L.V. Side C.T. reverse reflects in spill and L.V. pilots . H.V. and L.V. side C.T. reverse reflects in common neutral (H.V.N), L.V.

    Pilots and spill.

    NOTE: Any transposition in pilot wires of HV & LV side of differential relays is

    found out by injecting current at C.T. terminals of power transformer.

    14.6. Tripping and Inter Tripping Tests :

    Connect the auxiliary supplies to relay. Operate relay by hand (testprovision) and see that circuit breakers operate only when the appropriate linksare inserted and that the indicators operate correctly.

    14.7. Before Putting In To Service :

    a) See that trip supply is connected.

    b) See that all relays are reset.c) Restore alarm link and trip link normal position.

    14.8. Magnetising S urge Tests :

    Perform ten switching operations of the power transformer with out load,the relay should not operate.

    14.9. Tests When Power Transformer Is Energized and In Load Service :

    a) Current measurement should be made at relay terminals with the help of

    digital clip on millimeter of suitable range.b) This spill current when expressed as a percentage of the load current

    used in the test, indicates the minimum amount of bias necessary on therelay to maintain stability on through faults. It is advisable to measure thespill current through the relay operating coil during load test with tapchanger set on its maximum and minimum tap.

    The transient condition cause unequal C.T. saturation and spill which canplay with the differential relay stability. C.T. requirement has been made possibleto improve stability.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    63/65

    63

    Under through fault conditions, the protection is stable with fault currentequivalent to 25 times rated current with up to 30% mismatch of the line currenttransformer and the content of the third harmonics can be up to approximately

    60% of the fundamental.

    Max. Through fault current beyond which scheme (mal) operatesStability ratio = ------------------------------------------------------------------------------------------------

    Min. Internal fault current required for tripping

    The higher the stability ratio, the better is the ability of the system todiscriminate between external and internal faults. Ensure whether the adopted %bias setting is adequate. (This can be ensured during through fault condition, ifnecessary raise the % bias).

    14.10. Maintenance :

    The following test should be performed yearly and recorded.

    a) General check of connectionsb) Relay calibrationc) IR value measurementd) Tests using load current

    14.11. Relay requirement :

    The biased (%) differential relay meet requirement as per IEC 255-13.

    15. TROUBLE SHOOTING AND REMEDIES

    It is not very uncommon to have certain unexplainable operation of relaysin spite of very careful selection of relay settings. In many such cases definitefaults were found to exist outside the sphere normally scrutinized by theprotection engineer. It is therefore, necessary that engineer should proceed withan open mind to inves tigate such apparent mal operations. The followingoccurrence is an example.

    15.1 Bushing C.T. terminal loose connection :

    At one sub station, the transformer was tripped by differential relay. Thetes t on transformer and relay were found normal. Repeated tests on transformerand relays were in vain. Finally the wiring and connections were checked fromrelay to power transformer and found that bushing C.T. terminal connection wasloose. After tightness, the power transformer was put back into service andfound normal.

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    64/65

  • 8/11/2019 3.15& 5 MVA Power Transformer Testing

    65/65

    C.Ts and relay as when ICTs are introduced the circuit connection to the primaryand secondary sides of the ICTs will be considered as different domains forgrounding the neutral circuit. The intent is to emphasize that all neutral circuits in

    the protection have an earth reference but one and only a s ingle earth reference.

    The reason why the ground should be made at only one point is to avoidimproper relay operation and cause damage to the C.T. interconnections. Ifgrounds are made at two or more locations circulating current may be caused toflow in the differential circuit because of difference of potential between thegrounding points owing to the flow of large ground fault current.

    A ground in the yard and another in the switch house put the secondarywiring in parallel with the ground mat so that part of the heavy fault current canflow in the secondary winding directly to either damage or cause mal-operation.

    Only one ground in the circuit is sufficient to minimize any electrostatic potentialref. 9(b).

    15.7. Effect of Ambient Temperature:

    The relay is suitable for indoor m ounting and should be installed in a placefree from damp, dust, corrosive vapors and the like. There must also be a freecirculation of air around the relay. The operation of relay may be nuisance ifambient temperature limits is exceeded.

    -----------------