Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
KAERVTR-1366/99
KR9900237
Operation and Maintenance
Techniques of Cranes and Hoist
in IMEF
3 1 - 0 2
1999Vi 7
-§•
-8-
- 1 -
i .
m.
SL
II. £^-3 ^H 51^ j } g l lc}. A)A^£ 3.
717151 ^«1#
30/5^ ^^-3.511^1 A-la]^ ^ o f l ^151
SUMMARY
I . Project Title
Operation and Maintenance Techniques of Cranes in IMEF.
II. Objective and Importance of the Project
Crane and hoist of 11 sets are installed in the Irradiated Material
Examination Facility (IMEF). IMEF is divided into two parts such as hot
cell area and service area. 30/5-ton overhead crane is installed in
service area for transfer of irradiated material transportation cask
and other several kinds of heavy equipments.
Design, fabrication, installation and function test of crane and hoist
have been performed to comply with the requirements of nuclear
facilities.
Major constituent parts are as follows ;
- Girder
- Guide rail
- Trolley
- Hoist
- Driving system
III. Scope and Contents of the Project
This report describes maintenance techniques, repair procedure and daily
and special checking list, which will ensure safety in routine operation
and even in abnormality.
Descriptions are mainly made for the items as follows :
- Design and Fabrication,
- Installation and Test operation, and
- Operation and maintenance techniques.
_ O _
CONTENTS
Summary 3
Chapter 1. Introdction 10
1. An outline of Facility
2. Crane Equipments 11
7\. Incell Crane
"l-h 30/5-ton Electric Overhead Crane
'C}. 3-ton Electric Overhead Crane
5K 2-ton Electric Monorail Hoist
n\. 30-ton Fixed Hoist
Hj-. 3-ton Electric Suspension Crane
Chapter 2. Overview of Technology Development Status 12
Section 1. Design Requirements
1. General
2. Crane Design Requiremenrs
7\. Over Head Crane
I-}. Electric Monorail Hoist 14
r}. Electric Fixed Hoist
3. Interface Requirements 15
4. Material Requirement
7\. Material Requirements
e}. Structural Components 16
5. Related System Operation Conditions
7\. Electric Overhead Crane installed in Hot Cell
i-}. Electric Overhead Crane installed outside of
Hot Cel 1 18
cf. Electric Monorail Hoist
e>. Electric Fixed Hoist 19
a]-. Electric Suspension Crane
- 4 -
6. Drivers Requirements
7. Name Plate Requirements 20
7. Seismic Requirements 21
8. Electrical Requirements
Section 2. Design Calculation 22
Chapter 3. Research Development Performance Contents & Result 54
Section 1. Fabrication
1. General
2. welding
3. Surface Preparation and Painting
Section 2. Shipping, Handling and Storage 55
1. Preparation for Shipment
2. Delivery and Storage
Section 3. Inspection and Test 56
1. General
2. Material Tests
3. Shop Test
4. Non-destructive Examination
5. Acceptance Test 57
Section 4. General Layout 58
Section 5. Seismic Calculation 71
Chapter 4. Research Development Goal Achievement & Contribution
Proposal 93
Section 1. Test Procedure for Over head Crane
Section 2. Pre. Assembly Test Procedure for Over Head Crane 101
Section 3. Test Procedure for Electrical Hoist 104
Section 4. Test Report of Electrical Hoist 109
Section 5. Runway Cableveyot of Hot Cell Crane 112
Chapter 5. Application Plan of Research Development 119
Section 1. Shop Test & Test Report
- 5 -
1. Load Test Report for 30/5-ton Over-Head Crane
2. No Load Test Report for 30/5-ton Over-Head Crane 125
*fl 6 ^ Bibliography 136
Attachment 1. Bando Electric Hoist Operation Manual • 137
- 6 -
2
Summry 3
^1 1 ^ ^ € • 10
2.
u}. 30/5^5- Electric
r-}. 3 ^ Electric
e>. 2 ^ Electric Monorail :£
H}. 3 ^ Electric Suspension
2 ^ ^-ufl5] 7)^- 7flaj^% 12
1̂ 1 ^
2.
7}.
i-}. Electric Monorail 5L. 7l7fl ̂ -s# ^-^^.4i 16
5. #?l ^ 3
7}.
U . ^-iMl ^^3.511 oj 18
c]-. Electric Monorail S.O]^iS.
eK Electric 3L^Slo|^ 19
n}. Electric Suspension
- 7 -
6.
7. Name Plate &^-£.£ 20
7. Lfl^^^] JSL^-^2 21
afl 2 ^ 'STll 7 ^ 22
3 # g ^ f l t J ^r*3 i-fl-§- S? « 54
*fl 1 ^
2.
3.
2 ^ ^t, %& 51 x i ^ 551.
2.
3 ^ A } ^ 5J ^Af 56
2.
3.
4. Hi 431
5. ' S * ^ ^ #*} 57
^ 1 4 ^ General Layout 58
afl 5 ^ tf l^L^^ ^I^A-1 71
4 ^
1. 30/5S-
2. 30/5^ ̂ ^-3.5)1 o] «.̂ .e|-Al̂ [ 125
136
] 137
- 9 -
*\\ 1 a M
]A ^ Oj=
30/5^
. [1-7]
T I T \_i
1
2
3
4
5
6
7
8
9
10
11
71 71 «1 3L
EF-E-7600-M-K001
EF-E-7600-M-K002
EF-E-7600-M-K003
EF-E-7600-M-K004
EF-E-7600-M-K005
EF-E-7600-M-K006
EF-E-7600-M-K007
EF-E-7600-M-K008
EF-E-7600-M-K009
EF-E-7600-M-KOOlO
EF-E-7600-M-KOOll
71 7} ig
1 ton Crane for Ml to M4
1 ton Crane for M5A to
M5B
1 ton crane for M6
30/5-ton Crane for
Service Area3-ton Crane for
Operating Area I3-ton Crane for
Operating Area II3-ton Crane for
Operating Area III3-ton Crane for Work
Shop2-ton Hoist for
Mechanical Room30-ton Fixed Hoist for
Cask Rec. Yard3-ton Suspension Crane
for Isolation Room
l
l
l
l
l
l
l
l
l
l
l
EF-E-1410-DT
-H101
(SDE) g 7)B}
- 10 -
2.
7}. In Cell
M1-M4, M5a~ M5b, M6a~M6c
£ inter cell door#
hard
M". 30/5^ Electric ^ ^ S
u l , Intervention
cf. 3 ^ Electric
44
e}. 2 ^ Electr ic Monorail
IMEF ^ i l - 3%o\] Aj
n\. 3 0 ^ Fixed 3Ll^S
«l#Al
}. 3-E- Electric Suspension 3.ef|!(lrfl)
M6a M6a
- 11 -
all 2
1
2) fi
3) S ^ 7] XI
4) JE.€- ^ ^ S ^ 3 4 U 3 (̂17> >§-o| *H -IM^H6)1
5)
6)
2.
7f.
(1) 9-S-i- ̂ XI1) JS.S 9-2:§ nj ^l-^r ^71^61 cleaning, brushing, painting
2) ̂ -̂ -i-̂ l 4-g-£|^ steely ASTM A36
(2) Bridge girder and end trucks
1) 3.el]o]^r data sheets] ^ i ^ - ^ tfl.3. double SEfe single girder
|: *}*![, bridge girder^ M f ^ ^ olTfvf !«] ̂ ^ g
2) Bridget hoist trolley-g- &.ir
raiiofl-b 4 4 ^ bridged -g-̂ ofl trolley^]
wheel stopper-^" ^J'^}'*!'0^ ̂ ^1^\.
3) ^ S ^ girder^] ^Xlfe ^tfl over load^H ^ 1-25
- 12 -
4) End carriage^ AA$\ wheel bearing^] ^ e ) ^
(3) Trolley frame
1) Trolley^ general layout^ T-}E}V5 3^*1! over JE^ under
running type]
2)
housing^- ^ . ^ bathS] ^S.7} 90JE-&
3) 7]^Jo|d]o> «}n|, ^ ^ g 3 ] ^ # 7?Tfl
7 } ^ * ! ^>3i^el^l forged steel
K Electric Monorail Hoist
(1) ^-S.^
Tracks-
(2) Trolley frame
Trolley^ well-rolled s tee IS. 4 4 ^ 1 ' H ^ * H , hoist
bearing, JMr!f, 7)E}
(3) Gearing
(4) Monorail Track
1) Monorail beams-=r ^ ^ track system^}- suspension system,
fitting^- ?J S ^ € support ^^; aitfl*>#
2) Track ^£afl carrier^ ^«H^-& ^ l * f e stopper^- ^*l^^i.
(5) Trolley stop
Trolley stopper-g- ' y ^ ] ^ ^.
(6) Drums ^ sheaves, lifting hook block assembly, hoisting
ropes, bearing ^ &
f. Electric Fixed Hoist
(1) Gearing, drums ^ sheaves, lifting hook block assembly
hoisting ropes, bearing ^ ^ #7]
€[. Suspension Crane
- 14 -
(1) Crane runways
1) Crane runwaysfe
3) Runway tracker
space!- H^ot
4) Stopper^ t racks
5l ?tfelHl
span# cover
3.
(2) Track support
1) Crane runways^
2) ^
(3) Trolley frame, drums ^ sheaves, lifting hook block assembly,
hoisting rope, gearing, rail end stops ^ bumpers, shaft 5!
axles, bearing, couplling, guarding -%••£: electric overhead
intercell crane1)
2)
mm height^
4. Material requirements
^ power ^ control line ZLZ]JL
^l*}7l ^ * } ^ 280 mm width x 260
7}.
1) Girder, end trucks ^ trolley ̂ ^ r
- 15 -
ASTM A36
2) Walkway, railing JEEfe c > ^ U] -7-S-i-xfl.g. -^S. ASTM
1) Alloy cast steel ̂ -& ASTM A148]?14
2) f > ^ # ̂ *flS. ̂ ASTM
3) ^ ^ # ^ £ ASTM A235o]7i
4) Plate -g^r ASTM A36^]7lu}
5) 3.%^ ^S. ^ & ASTM A325, A490
6) Hook -^^g. rolled JEfe forged >^^
7) Wil^ej ^ ^ : 4 # ^ 1 %*\3. ^7} ^°M # S f e roller
^ ^ ^ H 1 0 ] ^ ^ * } ^ , AFBMA ^ 2 f ^
8) 7 H ^ f # ^ « g ^ 5 l ^ ^ 1 # A S AGMA
9) Trolley wheel ^ ^SJ- ̂ B l € S ^ 5J ̂ ^ 1 1 " ̂ € forged
steel o]o^o]: «>c]-.
5. ^ |
7\.
(1) Hoist and trolley control
1) Electric hoistfe JL^rgr^Al ^-3.o\] %Z]±r * } # ^ 150
t]^ short stroke^ magnetic disc motor brake#
2) Electric trolley^ trolley SE>ofl ^ e ] ^ full load
125 % S ^^lfe short stroked] magnetic disc motor brake#
(2) Conductors
1) Runway conductors^- ^^S^fTj] S ^ ^ conductor * ] ^
2) Runway conductors^ 3
(3) H.
- 16 -
2) Ji^Ha. A ] ^ I ^ #7l^.°S *HfSIfe 150
holding 51 ^
3) Trolley travel H.eH-3. 4 ^ ! ^ r *)-§-*}# 51
$1 10 % **$)\J\6\}A\ trolley# i
4)
(4)
1) 3.ell1|O> *ft^ ^• ' i ^ i^ 6 ! ! movable type ^ .S 'M^l*}^0]1
- Bridget)
- Hoistif trolley5] ^*5 systemlfe magnetic 3 -S
- Magnetic -g-S-f-ei 4 ^ ^ ^ - local control boxofl $X^ push
button^
2) M5a~M5b
- M1-M4
3) M6 5!
- M1-M4
(6) e]n)E ^
over hoisting^ ^ 1 ^ ^ £lfe limit switch
- 17 -
bridge^ ^ «J trolley^
. SHIM*(1) Hoist and trolley control
(2) «.i
5.
(3) ^
(4) Control points
l̂ g: pendant push button switch^]
- Hoist, bridged ^*|, trolley^) ^ * 5 # -?1*H magnetic
controller^- 4-§-^ ^.
- Magnetic controller ^1^.^-c: pendant push button^] -S]*!-^
(5) e]BIS ^
- 3Lo|>iS^ over hoisting^ ^l^lHr $X^a: limit switch
l ^ bridge^ ^ ^ Rj trolley^
7) fl*HElectric monorail
- Trolley^
7}o]7}
- Monorail
pendant push button controller
- 18 -
- Push button controller^- magnetic
festoon
button^]
- Power t
Electric 3.^
- Hoists
- Push button -g-H-i-ej^ magnetic button7l ^ * M local
push button E}»jo|o]o]: ^}t\.
^l^lfe electric suspension
^ S . i l trolley ^-Hl-
(2) Brake
(3) Wiring
(4) Limit switches
5.7}. (6)2^
(5) Control points
- Push button type£} 47fl̂ l local control box#
isolation room ^ 5 ^ ^^«^] ^ * ] ^ %.
- Push button^ ^ ^ ^ j - type^-S. button^
fl| local control
intetlock system©]
6.
(1) Buyers 440V, 3^, 60Hz AC power 7>
control power^ seller^ 5^*H ̂ ^ f e 4 4 ^
Sll-b control trans formerl-
(2) Electric motor^ appendix 4HE-02, 03^1
- 19 -
(3) Crane bridged HeW^--§- S^fe 4 4 3 wheel
interlock system^-
(4) Drive unit£] fi§
gear coupling*]
(5)
(6) fiBjs.^ B-^-g-5] ^-̂ «l 2]- W
(11) ^7]a|ti ^U] 5| JHHHi£ IEEE, NEMA ZLe]3. ANSI
7. Name Plate
5 ^ metric
(1)
tag
- 20 -
- Span
- Speed, hoist, trolley, bridge
(2) 3>1^S. ^ 3.^ jL
tag
-
2 ^ Design Calculation
R E SERVICE AREA 3O/5T0N O.H CRANE
ITEM NO. : EF-760O-M-K004
tfAj Prepared JS-i-ieviewed --£-•>! Approved
- 22 -
TABLE OF CONTENTS
I . OESTCJN SPECIFICATION
PACK
1. DESIGN SPECIFICATION — 1
2.' LOAD COMBINATION 2
3. ALLOWABLE STRESS 3
4. FACTORS 3
5. LOAD TABLE 4
31 . STRUCTURAL PART CALCULATION
1. DETERMINE TROLLEY WHEEL LOAD 5
2. LIVE LOAD MOMENT (LLM) 6
3. IMPACT LOAD MOMENT (Mdi) 6
4. GIRDER SECTIONAL PROPERTIES 7
5. GIRDER PROPORTION • 8
S. DIAPHRAGM THICKNESS : 8
7. TOTAL DEAD LOAD MOMENT (DLM) 9
8. MOMENT FOR INERTIA FORCES FROM DRIVES (IFDM) 9
9. SEISMIC LOAD MOMENT FOR LATERAL DIRECTION (SFM) 10
10. MOMENT FOR SKEWING (SKM) 10
11. SUMMATION OF MOMENT 11
12. SUMMATION OF BENDING STRESS 12
13. MAX. ALLOWABLE DEFECTION 13
14. BRIDGE WHEEL LOAD 15
15. RAIL CLAMP BOLT CALCULATION 10
Iff . MECHANICAL PART CALCULATION
1. DESIGN DATA 19
2. WIRE ROPE 19
3. MOTOR 21
4. CALCULATION OF WHEEL 23
5. CALCULATION OF HOOK 24
- 23 -
DESIGN SPECIF1CAITON
1. DESIGN SPECIFICATION
• CAPACITY
• SPAN
• SERVICE & CLASS
• QUALITY CLASS
• SPREAD (TROLLEY WIDTH)
• TROLLEY WEIGHT
• TROLLEY WHEEL
2 . LOAD COMBINATION (PER CM.A.A TABLE NO. 3 . 3 . 2 . 4 )
1) CASE 1 : CRANE IN REGULAR USE UNDER PRINCIPAL LOADING (STRESS LEVEL 1)
DL ( D L F B ) + TL ( D L F T ) + LL (1 + 11LF) + IFD
2) CASE 2 : CRANE IN REGULAR USE UNDER PRINCIPAL AND ADDITIONAL
LOADING (STRESS LEVEL 2)
DL (DLFB) * TL (DLFT) + LL (1 + HLF) + IFD + WLO + SK
3) CASE 3 : EXTRAORDINARY LOADS (STRESS LEVEL 3)
DL + TL + SF
WHERE ;
DL : DEAD LOAD
DLF : DEAD LOAD FACTOR
TL : TROLLEY LOAD
LL : LIFTED LOAD
HLF : HOIST LOAD FACTOR
IFD • INERTIA FORCES FROM DRIVES
WLO : OPERATING WIND LOAD
SF : SEISMIC FORCE
SK : FORCE DUE TO SKEWING
THIS OVERHEAD CRANE SHALL BE INSTALLED ON INDOOR. THEREFORE, THE OPERATING
WIND LOAD (WLO) FORCE SHALL BE TAKEN NO THROUGH FROM LOAD CASE I.
AND THE SEISMIC FORCE (SF) ACCORDING TO THE REQUIREMENTS OF 1988 VERSION
OF UNIFORM BUILDING CODE (UBC) SECTION 2312 SHALL DE TAKEN THROUGH FROM
LOAD CASE I.
- 25 -
3 . ALLOWABLE STRESS (PER CM.A.A TABIJ- 3 . 3 . 3 . 4 )
1) STRESS LEVEL 1.
a a - 0 . 6 cry = 0 . 6 x 2400 KG/CM2 = 1440 KG/CM2
r a = 0 . 3 5 cry = 0 .35 x 2400 KG/CM2 = 840 KG/CM2
2) STRESS LEVEL 2 .
era = 0 . 6 6 cry = 0 .66 x 2400 KG/CM2 = 1584 KG/CM2
r a = 0 . 3 7 5 a y = 0.375 x 2400 KG/CM2 = 900 KG/CM2
3) STRESS LEVEL 3 .
aa. = 0.75 ay = 0.75 x 2400 KG/CM2 = 1800 KG/CM2
ra = 0.43 cry = 0.43 x 2400 KG/CM2 = 1032 KG/CM2
WHERE ;
: ALLOWABLE COMPRESSION STRESS
: ALLOWABLE SHEAR STRESS
: YIELD STRESS
4. FACTORS
1) DEAD LOAD FACTOR (DLF) PER CMAA 70 REVISED 1988 FROM TABLE 3.3.2.1.1.4.1-1
UP TO
OVER
TRAVEL
200.
200.
FPM
FPM
SPEED
(60.96 M/KIN)
DEAD LOAD
1.1
1.2
FACTOR
2) HOIST LOAD FACTOR (IILF) PER CMAA 70 REVISED 1988
1ILF = 0 . 1 5 ^ (0.005 x HOIST SPEED)(FT/MIN)
2.8= 0.005 x FT/MIN = 0.0459
0.3048
.'. USE 15% FOR HOIST LOAD FACTOR.
3 ) INERTIA FORCES FROM DRIVES (1FD)
PER CMAA 1 9 7 5 AND CRANE HAND BOOK (WHITING)
- LATERAL LOAD DUE TO ACCESERATION OR DECELERATION IS CONSIDERED
AS 2 . 5 % OF THE LIVE LOAD AND THE CRANE BRIDGE, EXCLUSIVE OF END TRUCKSAND END T I E S , FOR CLASS "A" CRANES.
- 26 -
5 . LOAD TABLE
• GIRDER ONE SIDE *
• DEAD LOAD (ONE GIRDER + MIS.) : DL
• TROLLEY LOAD (4850/2) : TL
• LII-TED 1DAD (3000 + 3OO)/2 : LL
L — HOOK LOAD
• DEAD LOAD FACTOR : DLF
• HOIST LOAD FACTOR (15%) : 1+1ILF
• INERTIA FORCES FROM DRIVES : IFD
• FORCES DUE TO SKEWING : SK
• SEISMIC LOAD : SF
5.1 • 2 .7 = 7.8 TON
2.325 TON
15.15 TON
1.1 (CMAA 3 . 3 . 2 . 1 . 1 . 4 . 1 )
1.15 (CMAA 3 . 3 . 2 . 4 )
0.56 TONG (REFER TO PAGE 9)
0.62 TON (REFER TO PAGE 10)
1.57 TON (REFER TO PAGE 10)
- 27 -
IE. £->'i~R.ucr.n..jRyvi- I^ART C A L C U L A T I O N
1 . DETERMINE TROLLEY WHEEL LOAD
/ " 2190 (W.B)
> = 793
•fi=1Q90
RAMAIN
12.4 TON H 0 0 K tPI
1090
P2=2 56 TON
7.58 TON
• rQ-19.98 TON
• TROLLEY LOAD = 4.65 TON
• LIFTED LOAD = 30.3 TON
* FOR ONE SIDE OF TROLLEY (DLF =1.1, HLF =1.15)
30.3• LIFTED LOAD = x (IILF) = 15.15 x 1.15 = 17.42 TON (Pi)
2
4.G5• TROLLEY LOAD = x (DLF) = 2.325 x 1.1 = 2.56 TON (P2)
2
• LIVE LOAD = 17.42 + 2.5S = 19.98 TON (Q)
* REACTION
(Pi x ^ i ) + ( P 2 x €z) (17.42 x 793) + (2.56 x 1090)RB =
-6 2190
= 7.58 KG
RA = Pi + P2 - RB = 17.42 + 2.56 - 7.58 = 12.4 TON
(MAX. TROLLEY WHEEL LOAD = TRA)
- 28 -
2. LIVE LOAD MOMENT TO G- l GIRDER (LLM)
Ll=6734.5
SPAN L = 14 3OO
d=83i . . . 1359
RAj tRB7580 KG
415.5.415.- 6734.5
B
7150 7150
"d» = DISTANCE OF RESULTANT "Q~ FROM NEAREST WHEEL
RES x W.B 7 . 5 8 x 2190d = —
Q 19.98= 830.84 = 831 MM
* LIVE LOAD MOMENT (LLM)
(RA + RB) L I 2 19.98 x 673.45 2LLM = —
1430= 6336.8 TON.CM
3 . IMPACT LOAD MOMENT TO G-l GIRDER (ONLY HOIST LOAD FACTOR MOMENT CAL')
• IMPACT LOAD (F)
F = 15 .15 x 0 .15 = 2.2725 TON
PER C.M.A.A (PARA 3 . 3 . 2 . 1 . 1 . 4 . 2 ) USE 15% OF RATED CAPACITY
* IMPACT LOAD MOMENT (Mdi)
Mdi =2.2725 x 673.45 Z
1430= 720.74 TON.CM
- 29 -
4. GIRDER SECTIONAL PROPERTIES
ID
r-
0 4
r—
it
271
295
34
271 _
600
7
%
295
590 y-
00
TOP PLATE : 12T x 590
WEB PLATE : 8T x 1176
BOTTON PLATE : 12T x 590
HORIZONTAL STIFFENER : L50 x' 50 x 6t
* MOMENT OF INERTIA (VERTICAL DIRECTION)
Ixx = 716483 CM4
* SECTION MODULUS "Zxx"
Zxx = 11941 CM3
* MOMENT OF INERTIA (LATERAL DIRECTION)
Iyy = 179272 CM"
* SECTION MODULUS "Zyy"
Zyy = 6077 CM3
- 30 -
5 . GIRDER PROPORTION ( C M . A . A PARA 3 . 3 . 3 . 1 )
PROPORTION
MAX.
ALLOWABLE
L/b
26.78
65
b/c
4 4 . 5
60
WHERE ;
L = SPAN : 14300 MM
b = DISTANCE BETWEEN
WEB PLATE : 5 3 4 MM
c = THICKNESS OF TOP PLATE : 12 MM
h = D1PTH OF WEB : 1176 MM
t = THICKNESS OF WEB : 8 MM
6 . DIAPHRAGM THICKNESS ( C M . A . A PARA 3 . 3 . 3 . 1 . 5 . 5 )
h/b
2.2
DOES NOr DEFINE ON
SPECIFICATION
3 0 k gKS S 8106-77Ol S E 1101 - 74
WHERE
RB
P
T
td
(1856 KG/CM2) (RB + 2T) t d
= WIDTH OF RAIL BASE = 1 0 7 . 9 5 MM
= TROLLY WHEEL LOAD : 10 .835 TON
= TOP PLATE THICKNESS : 12 MM
= DIAPHRAGM THICKNESS (MM)
(USE MIN. 6MM)
< 30KG RAIL >
.-. td =1O.835TON x 1000
(10.795 + 2 .4) x 1856
= 0 .442 CM = 4 .42 MM < 6 MM O.K
- 31 -
7 . TOTAL DEAL) LOAD MOMENT (GIRDER ONE SIDE)
• GIRDER : 5 . 1 TON
• TIM VERSING POWER, PLATFORM : 1.5 TON
+ MISCELUNEOUS : 1.2 TON (PANEL, BRACKET ETC.)
TOTAL DEAD LOAD = 7 . 8 TON (UNIFORM LOAD)
* DEAD LOAD MOMENT (DUD
WLMOMENT DUE TO GIRDER VT = x DLF ( 1 . 1 )
WHERE " L " I S SPAN
7.8 x 1430DLM = x 1.1 = 1533.68 TON.CM
MOMENT FOR INERTIA FORCES FROM DRIVES : (IFD)
FOR CUSS " A " CRANE USE 2.5%
10.2
IFD = 2.5% x (2 .325 + 15.15 + ) = 0.56 TON2
0 .56 x 673 .45 2
IFDM = = 177.61 TON-CM1430 •
- 32 -
9. SEISMIC LOAD MOMENT TOR LATEIMl. DIRECTION
(PHI 1908 VERSION OF UBC, SECTION 2312)
• SEISMIC LOAD (SO
Sf = ZICpWp = 0.15 x 1.25 x 0.75 x 11.14 = 1.57 TON
* SEISMIC LOAD MOMENT (SFm)
1.57 x 673.452
• SFm = = 497.94 TON-CM1430
- CODE
- Z
T
- CP
- WP
1988 VERSION OF UNIFORM BUILDING CODE (UEC) SECTION 2312
SEISMIC ZONE FACTOR AS SET FORTH IN TABLE NO. 23- I .
Z = 0.15 (ZONE 2A)
OCCUPANCY IMPORTANCE FACTOR AS SET FORTH IN TABLE NO. 23-L
I = 1.25
NUMERICAL COEFFICIENT IN TABLE NO. 23-P
CP = 0.75
COMPONENT WEIGHT EXCLUDE LIFTED LOAD.
WP = (DEAD LOAD + TROLLEY LOAD) x DLF
= (7.8 + 2.325) x 1.1 = 11.14 TON
10. MOMENT FOR SKEWING FORCES : (SK)
SPAN 1430
RATIO = = 3.11WHEEL BASE 460
.-. SKEWING FACTOR : Ssk = 0.05 (CMAA : 3.3.2.1.2.2)
• SKEWING FORCES (SK)
SK = Ssk x TRA = 0.05 x 12.4 = 0.62 TON
(MAX. TROLLEY WHEEL LOAD : TRA = 12.4 TON)
* SKEWING MOMENT (SKm)
0.62 x 673.452
SKM = = 196.64 TON-CM1430
- 33 -
11. SUMMATION OF MOMENT (ONLY GIRDER ONE SIDE)
CASE 1.
DEAD LOAD MOMENT (DLM)
LIVE LOAD MOMENT (LLM)
IMPACT LOAD MOMENT (nidi)
INERTIA FORCE FROMDRIVE LOAD MOMENT (IFDM)
TOTAL El
VERTICAL MOMENT
1533.68
6336.8
720.74
4i = 8591.22 TON-CM
LATERAL MOMENT
177.61
CASE 2.
DEAD LOAD MOMENT (DLM)
LIVE LOAD MOMENT (LLM)
IMPACT LOAD MOMENT (mdi)
INERTIA FORCE FROMDRIVE LOAD MOMENT (IFDM)
VERTICAL MOMENT
1533.68
6336.8
720.74
SKEWING FORCE MOMENT (SKM)
177.61 TON-CM
LATERAL MOMENT
177.61
196.64
TOTAL SM2 = 8591.22 TON-CM
CASE 3
DEAD LOAD MOMENT (DLM)
LIVE LOAD MOMENT (LLM)
SEISMIC LOAD MOMENT (SFM)
VERTICAL MOMENT
1533.68
6336.8
374.25 TON-CM
LATERAL MOMENT
497.94
TOTAL SM3 = 7870.48 TON-CM 497.94 TON-CM
- 34 -
12 . SUMMATION OF BENDING STRESS (ONLY GIRDER ONE SIDE)
CASE 1.
(DEAD LOAD MOM. * LIVE WAD MOM. + IMPACT LOAD MOM.) IFO MUM.
SECTION MODULUS OF "Zxx" Zyy
12-1) TENSION OR COMPRESSION STRESS ( f b i )
8591.22TON-CM 177.61TON-CMfb, = + = 0 .720 TON/CM2 + 0.029 TUN/CM7
11941 CM3 6077 CM3
= 720KG/CM2 + 29KG/CM2 = 749 KG/CM2 < 1440 KG/CM2 0. K
CASE 2.
(DEAD LOAD MOM. + LIVE LOAD MOM. + IMPACT LOAD MOM.) (IFD MOM. + SKM MUM.)fbz =
SECTION MODULUS OF "Zxx" Zyy
12-2) COMBINED STRESS (fb 2 )
8591.22 TON-CM 374 .25 TON-CMfb2 = + 0.720T0N/CM
2 " 0.0S2TON/CM2
11941 CM3 6077 CM3
= 720KG/CM2 + 62KG/CM2 = 732 KG/CM2 < 1584 KG/CM7- O.K
CASE 3 .
(DEAD LOAD MOM. + LIVE LOAD MOM.) SEISMIC MOM.f b 3 = +
SECTION MODULUS OF "Zxx" Zyy
12-3) COMBINED STRESS (fb 3 )
7870.48 TON-CM 497 .94 TON-CMfb 3 = + = O.659TON/CM
2 + 0.082TON/CM2
11941 CM3 6077 CM3
= 659KG/CM2 + 82KG/CM2 = 741 KG/CM2 < 1800 KG/CM2 O.K
- 35 -
1 3 . MAX. ALLOWABLE DEFLECTION : AMAX. (TECH* SPEC 4 . 5 . 2 . l . b )
SPAN 1430AMAX. = = = 1.79 CM = 17 .9 MM
800 800
1 3 - 1 . DEAD LOAD DEFLECTION ( D L A )
* FIND EQUIVALENT UNIFORM DEAD LOAD " W "
S.W.L3
THEN, DEAD LOAD DEFLECTION =384 El
5 . W . L 3 5 x 8580 x 1 4 3 0 3
" D L A " = =3 8 4 El 3 8 4 x 2 . 1 x 10 6 x 71S483
= 0 . 2 1 7 CM
WLLET DEAD LOAD MOMENT, M =
8M 8x1533.68W = = = 8.58 TON
L 1430
M = DEAD LOAD MOMENT
= 1533 .68 TON-CM
L = SPAN 1430 CM
I x = MOMENT OF INERTIA (VERTICAL DIRECTION)
= 716483 CM4
- 36 -
1 3 - 2 . LIVE LOAD DEFLECTION ( I X A )
FIND EQUIVALENT CUNCENTRATED LIVE LOAD " P "
PL 3
THEN, LIVE LOAD DEFLECTION =
48EI
17730 x 1430 3
A 70
43 x 2.1 x 10* x 716483 — = = = = =
PLLET LIVE LOAD MOMENT " M " =
4
WERE, P = EQV. LIVE LOAD & L IS SPAN IN CM
6336.8 x 4p = 1 7 . 7 3 TON ( E Q V . LIVE LOAD)
1430
13-3 . TOTAL DEFLECTION
"DLA" + "LLA" = 0.217 + 0 .72
= 0.937 CM < 1.79 CM (ALLOWABLE) OK
- 37 -
14. BRIDGE WHEEL LOAD
1150
1397
13150
T S RAIL1G50
T"H. i
2190
G1 GIRDER
12 400 KG ^ 7 5 8 0. Mil
G-2 GIRDER
L..
SPAM 14 300
B
SPAM 14 300
2190
RA-.124OOKG RB-7580
13150
< LEFT SIDE >
- 38 -
STATIC LIVE LOAD ON GIRDER CORNER : LL
19.98 x 13150LL = = 18.37 TON/CORNER
14300
STATIC DEAD LOAD ON GIRDER CORNER : DL
CRANE TOTAL WEIGHT WITHOUT TROLLEY WEIGHTDL = x 1.1
422.21 - 4 .65
= x l . l = 4 .85 TON/CORNER
4
LOAD OF ONE SIDE OF GIRDER
= LL + DL = 18.37 • 4 . 8 5 = 23.22 TON
BRIDGE WHEEL LOAD OF LEFT SIDE OF GIRDER (A)
= 23.22 TOM/WHEEL
(MAX. WHEEL STATIC WHEEL LOAD = 23.22 TON/WHEEL)
SPAN 14 300
< RIGHT SIDE >
- 39 -
19.98 x 12650» LR = = 17.67 TON/CORNER
14300
° DL = 4.85 TON/CORNER
o LOAD OF ONE SIDE OF GIRDER
= LR + DL = 17.67 + 4 .85 = 22.52 TON
.". BRIDGE WHEEL LOAD OF RIGHT SIDE OF GIRDER (B)
= 22 .5 TON/WHEEL
- 40 -
15. KAIL CLAMP fJULT CAI.CUUTION
STUD POL/Rr TRAVELLING RAU.-|-
(Kh
TOTAL WT:22.21 TON
TRAVELLING RAIL ' ! ? [
-rM4?1-S: ^-"J RAlLo-ll CLAM1 HULT
W.8 4 60O
L y TOP QF T.LRAIL
''VHf.F.1 LOAD DATA • PmJ»
P H = P I ^ SF .
FV : MAX. WHEEL LOAD = 23.22 TUN(MAX. WHEEL LOAD PAGE 1G)
Pt :
Sf
?.0Z)
6-̂ l 10%)
= 4.
= 2.32?. TON
^l^]oflS|«V 4 - - ^ ^ = 1.57 1UN(SEISMIC LOAD PAGE 10)
( P H )
PH = P t + Sf = 2 . 3 2 2 + 1 . 5 7 = 3.892 TON
*
2)
CRANE
lO^o
27ila]
BOLT
V
WHEEL CENTER ^d
BOLT - S - J L
s] ?A^4
PH
2A
3.892
SL 7f
7^]AV
7]e) 46OOMM 4 '
1 BOLT ^ ? 4
V
*\°\] H20 CLAMP B0LT7]-
--& 20%°] 2M
Ill . MECHANICAL I'AliT CALCULATION
1. DESIGN DATA
o CAPACITY
» LIFT
• SPAN
o SPEED
• MAIN HOIST
• TROLLEY DRIVE
• BRIDGE DRIVE
o WEIGHT
• HOIST BOTTOM BLOCK
• TROLLEY
• CRANE TOTAL Wt
o WHEEL DIA & QUANTITY
• TROLLEY
• BRIDGE
2. WIRE ROPE
1) MAIN HOIST
* REQUIRED BREAKING
LM x S• TLJ —• 1M —
N
WHERE,
: MAIN 30 TON. AUX.
: MAIN 16.2 MR., AUX.
: 14.3 MR.
: 0.28-2.8 M/MIN, AUX.
: 7 M/MIN
: 10 M/MIN
: MAIN 0.3 TON, AUX.
: 4.65 TON
: 22.21 TON
: DIA. 250 x 4EA
: DIA. 630 x 4EA
STRENGTH OF WIRE ROPE :
LM : WORKING LOAD :
N : NO. OF PARTS OF
WIRE ROPE DIA. :
S : MIN. REQUIRED
SAFETY FACTOR :
: 5
: 17
: 0
: 0
TM
30.3
6
^22.;
5
TON
.3 MR
.56-5.6 M/MIN
.05 TON
TON
- 42 -
30.3TON x 5
• TM = = 25.25 TON
6
USE, ?.2.4 MM (6 x F i 2 5 ) IWRC B-f- ZZL°d.
MIN. BREAKING STRENGTH : 3 3 . 7 TON
SAFETY FACTOR OF WIRE ROPE
• s -
_
2) AUX. HOIST
• TM =
• TM =
33.7TON x 6
30 .3 TON
6 67 > 5
LM x S
N
WHERE, LM :
N :
S :
5.O5TON x 5
WORKING LOAD :
NO. OF PARTS OF
WIRE ROPE DIA. :
MIN. REQUIRED
SAFErY FACTOR :
= 1 2 . 6 2 5 TON
5 . 0 5 TON'
2
16 MM ( 6 x F i 2 S ) IWRC Bf- Z
MIN. BREAKING STRENGTH : 1 7 . 2 TON
SAFETY FACTOR OF WIRE ROPE
17.2TON x 2
S =5.05 TON
= 6.81 > 5 . . O.K
- 43 -
3. MOTOR
1) MAIN HOIST
Lii x VKW =
6.12 x E
WHERE, LH = WORKING LOAD : 30.3 TON
V = HOIST SPEED : 2.8 H/MIN
E = MECHANICAL EFFICIENCY
WHERE, E = Eg" x Esm
Eg = GEARING EFFICIENCY
n = NO. OF GEAR REDUCTION
Es = REEVING EFFICIENCY
m = 0 . 9 7 3 x 0 . 9 9 7 = 0.851
30.3T0N.X 2.8 M/M1NKW = : : = 16.31 KW
6.120 x 0.851
USE 17KW x 8P
2) AUX. HOIST
LH x V• KW = :
6.12 x E
WHERE, LH = WORKING LOAD : 5.05 TON
V = HOIST SPEED : 5 .6 M/MIN
E = MECHANICAL EFFICIENCY : 0 .85
5.O5TON x 5.6 M/MIN
KW = = 5.44 KW6.12 x 0.85
USE 5.5KW x 6P
- 44 -
3) TROLLEY DRIVE
W x V
KW - x f1 x E
6 . 1 2
WHERE ;
W = RATED LOAD + TROLLEY W.T : 3 4 . 9 5 TON
V = TROLLEY SPEED : 7 M/HIN
P = MOTOR FACTOR : 2 . 5
F = FRICTION FACTOR : 0 . 0 0 6 8
(FROM CMAA TABLE 5 . 2 . 9 . 1 . 2 . 1 - D BASE ON 250
4 . CALCULATION OF WHEEL
1) TROLLEY WHEEL LOAD :
• MAX. TROLLEY WHEEL LOAD : P = 12 .4 TON
(STRUCTURE PART CALCULATION PACE 5)
• WHEEL DIA (USE 3OKG/M RAIL)
• BY CMAA-ACCORDING TO CMAA TABLE 4 . 1 1 . 3 Cb\SS "A"
P(LB) = 1600 x DUN) x W(IN)
P(LB)DUN) =
D(CM) =
1600 x W(IN)
P(KG)
112.5 x (b-2r)
12400
WHERE ;
W : EFFECTIVE WIDTH OF RAIL ( b - 2 r )
30 kg
112.5 x (6 .033 - 2 x 0.8)
= 24.86 CM = 248.6 MM
USE 250 DIA WHEEL
2) BRIDGE WHEEL
. • MAX. BRIDGE WHEEL LOAD : Pmax = 23.22 TON/WHEEL
(STRUCTURE PART CALCULATION PAGE 16)
WHEEL DIA (USE 37KG/M RAIL)
BY CMAA METHOD
P U G )D(CM) =
112.5 x (b-2r)
23200
112.5 x (6.27 - 2 x 0.8)
= 40.28 CM = 402.8 MM
USE 630 DIA WHEEL
37
C
C
c
k g Ml "I
( -
^~ Tto *l
C O
«?
en
1.59"13'
KS BJ I S E
— 62.71—-
!W ^
.5
8 1 0 6 -1101 •
•(•
T:}'i3.J9_-r'-.
•-122.24
8374
- 46 -
( 3O ) TON HOOKO.I
oi ; _ n oil ° |OUi p X||*j = SF5O~ 55 'Q = M § 5 | g 30000 kg
h 1 -- U . 5 CM
b2 - 3 . 4 CM
1)h b l + 2b2
e l = * = (CM)3 b l + b2
1 6 . 5 11 .5 +2 * 3 . 4_ „ •% — b • I D
3 1 1 . 5 + 3 . 4
e 2 = h - e l = 1 6 . 5 - 6 . 7 6 = 9 . 7 4 (CM)
2}
3)
4)
Cl- Oi W1— 1 —1
A =
I
ZII
b lh *ii -r- —
= 16.5 *
IT 3
36
16.5"
36
= 2514
I
e l
+ b2- ( PM**" 9 ̂— \ O i l C. I
2
1 1 . 5 + 3 . 4
2
( b l + b 2 ) " 2 + 2
b l + b2
3 ( 1 1 . 5 + 3 . 4
11 .5
2514_ _ IT)— " — 0 ( 0
6.76
2514= 258
123
*bl*b2
) " 2 + 2 * l l .
t 3.4
„-,
CM" 3
(CM"4)
5 * 3 . 4
e2 9.74
M = Q * ( + e l ) = (KG-CM)2
16= 30000 x ( + 6 . 7 6 ) = 442800
2
SEE DWG NO. B04-5O8
- 47 -
6)M Q
ZI A
4 4 2800 30000
372 123
= 1434 KG/CM"2 i 1600 KG/CK"2
H I - IV O||
SEE DWGN0.BO4-508
3)
M q -4 42800 30000
ZII A 258 123
=-1473 KG/CK"2 < 1600 KG/CH"2
r- b l - 1 1 . 5 cm r ' = 1 0 . 2 cmb2 = 4 . 7 erah = 14.4 cm
— a = 16 era
1)
2)
h b l + 2b2e l = _ _ _ * ••= (CM)
3 b l + b2
14.4 1 1 . 5 + 2 * 4 . 7= * = 6.2
3 1 1 . 5 + 4 . 7
e2 = h - e l = (CM)
= 14.4 - 6.2 = 8 .2
b l + b2= h * = (CMr2)
2 (
11 .9 + 4 .7 i= 14.4 * . — — = U6. .5
2,
h"3 (b l + b 2 ) " 2 + 2bl * b2I * = (CM"4)
36 b l + b2
1 4 . 4 ^ 3 . ( 11 .5 + 4 . 7 T 2 + 2 * 11.5 * 4 .7
36 1 1 . 5 + 4 . 7
= 1808
- 48 -
I 1898Z H I = = = 306.1 (CM'3)
e l 6.2
I 1898Z IV = = = 232 (CM"3)
e2 8.2
H = — * tan 60 " * r 1 = (KG/CM)2
30000= * tan 60° * 10.2 = 265004
2
6)
M 265004^ C7 e t = t O b = + = = 866 KG/CM'2 < 1600 KG/CM~2
ZII I 306.1
M 265004^ a ec = -C7b= = =-1143 KG/CM"2 < 1600 KG/CM"2
ZIV 232
0 | E S O.K
- 49 -
(5)TON HOOKS-I
Oil
[= SF50- 55 bl = 5..JCM= M § o ( g 5000 kg b2 = 2.2CM= T 3 ° ^ ^ | 2 9 CM h = 8 .4CM
h bl + 2b2e l = * = (CM)
3 bl + b2
8 . 4 5 . 4 + 2 * 2 . 2=3.61
3 5 .4 + 2 . 2
e2 = h - e l = 8.4 - 3 . 6 1 = 4 . 7 9 (CM)
2) E S l ^ t b l t b2
A = h * = (CM* ')2
5.4 + 2 . 2= 8 .4 * = 3 1 . 9 2
2
> 3) 2! h"3I - *
36 b l + b2= (CM~4)
8.4*3 ( 5 . 4 + 2 . 2 ) ^ 2 + 2 * 5 . 4 * 2 . 2
36 5 .4 + 2 . 2
4)
= 176.6
I 176.6ZI = = = 48.92 CM~3
. e1 3.61
176.6ZII = = 36.87 CM"3
4.79
5) S| PI a «! e aM = Q * ( — + e l ) = (KG/CM)
29
= 5000 x ( - - - + 3.61) = 405502
- 50 -
6) I - II 2| ^ O et = to b + O I
3 J 2J
I =
— T
M
ZI
= 986
^ G ec = -O b + O t
= -943
IV 0|| °iOi A-J r~ blb2h
- a
KG/CM"
M
£11
KG/CM"
= 5.4= 2.2= 8.4= 9
Q
—A
2 <
Q
—A
2 <
CMCMCMCM
40550
48.92
1200 KG/CM"
-40550
36.87
1200 KG/CM*
r' = 5.86
5000
31.92
2
5000
31.92
2
CM
2)
h b l f 2 b ~ 2 .e l = — * = (CM)
3 b l + b2
8 .4 5 .4 + 2 * 2 . 2= * = 3 . 6 1
3 5 .4 + 2 . 2
e2 = h - e l = (CM)
= 8 .4 - 3 . 6 1 = 4 . 7 9
i
b l + b2A = h * = (CM"2)
2
5.4* + 2 . 2- 8 .4 * = 3 1 . 9 2
2
"3 (b l + b2)~2 + 2bl * b2* _ (CM"4)
36 b l + b2
. 4 " 3 . ( 5 . 4 + 2 . 2 ) ~ 2 + 2 * 5 . 4 * 2 . 2+
3 6 5 . 4 + 2 . 2
- 51 -
4)
I 176.6Z I I I = = = 48.92 (CM"3)
e l 3.61
I 176.6Z IV = = = 36.87 (CM~3)
e2 4.79
5) s S^E
QM - -— * tan 60 °* r1 = (KG/CM)
2
5000= * t a n 60 * * 5.86 = 25375
2
6) a g^ (seem si?.* a s ^ s nys
M 25375e t = +O b = + : = = 519 KG/CM"2 < 1200 KG/CM" 2
Z I I I 48.92
M 25375ec = -C7 b= = =-688 KG/CM'2 < 1200 KG/CM"2
ZIV 36.87
0 | H £ O.K
- 52 -
REVISIONS
HOOK Tsrso! ~ SF55
NO | DESCRIPTIOK'S | UTl
PROJECT
TITLE
CO10
REMARKS
DATI
1991. 10. 01
SCAL£
LOAD BLOCK HOOK N/S
DRAWN DESIGNED I CHECKED
%
fo)BANDOV h y UACH1NERY CO..LTD.
APPROVZD I Rtr DRAV/INC
BO< - 5 0 8
Ml
1) Material handling #H]#ofl
2)
3)
fe 3 H 5| standard
field
2.
1)
2)
3)
marking^
-^^ appendix AM-Ol (general
welding requirements)^
51fin
51
submerged arc f l u x e d AWS S H
3.
4)
5) Slagfe S.^
6)
7) - g - ^ ^ ^^)
cleaning 4 ^ ^ : Structural Steel Painting
Council (SSPC)-SP "Commercial Blast Cleaning)^ 7]^-^] tcf
2) Dry Film Thickness
- £ £ dry 1-tSj T ^ f c ^ ^ 4 scM ^M" 5 . SSPC-PAl:Shop,field iJ -fi-^lJt^1 SflSPU HZ]3. SSPC-PA2: nfzL*]*%•# dry sflolE
3) *f|*!*3
717)1^
^ 1 S'S ^ ^
3-§•*>*] ?tfet:}.
4) Seller^ Appendix 4HP-02
51
2)
4 ^ # 51
2)
3) %7\ 51
2.
3.
Certified mill sheet JiL3.A-)|| ASME a f e ASTM 46cMl
7l
5.
. 4
4
2)
3)
4)
5)
6)
7) 4
711
8) ZL
125
^ 4 ^ 4
- 57 -
4 ^ General Layout
GENERAL LAYOUT
FIGNO. EQUIPMENT NO. EQUIPMENT NAME
1. EF-7600-M-K001 1.0 Ton Electric Overhead Crane for Ml to M4
Cell
2. EF-7600-M-K002 1.0 Ton Electric Overhead Crane for M5 Cell
3. EF-7600-M-K003 1.0 Ton Electric Overhead Crane for M6 Cell
4. EFT7600-M-K004 30/5 Ton Electric Overhead Crane for Hot Cell
Service Area
5. EF-7600-M-K005 3.0 Ton Electric Overhead Crane I for Ml to M4
Hot Cell Operating Area
6. EF-7600-M-K006 3.0 Ton Electric Overhead Crane II for M6 Hot
Cell Operating-Area
7. EF-7600-M-K007 3.0 Ton Electric Overhead Crane III for M5a to
M5b Hot Cell Operating Area
8. EF-7600-M-K008 3.0 Ton Electric Overhead Crane for Workshop
9. EF-7600-M-K009 2.0 Ton.Electric' Monorail Hoist for Mechnical
Room
10.EF-7600-M-K010 30 Ton Electric Fixed Hoist for Cask Receiving
Yard
11.EF-7600-M-K011 3.0 Ton Electric Suspension Crane for
Isolation Room
- 58 -
FiG.r.i.owN ELECTRIC OVERHEAD CRANE FOR MI TO NI CELL
FOUIP. NO. : EF-7600 -H-KOOI
SCALE : 1/50
oooc
320SPAN = ?
FIC. 2: I.OTON ELECTRIC OVERHEAD CRANE EOR m * TO M5I) CELL
EQUIP. HO. : EF -7600 -N-K002
SCALE : / . / " 5 0
ooV
oo
o
oo
--$=
700, -, SPAN= .1800 7000)
iE
.AQJL.
/ TOf/
r.ooX
-200.0.
s'AA
EL.82l000_
_ JAIL,
GATE
Opening si?'*
I 8 0 "slccl i.-l
EL. 77,300 DKTAIL AA.
.60Q,__9Q0 _,
•8QQ
H40Q
; lupollOOK COVERAGE LENGTH
114 CELL
\ \
HOOK COVERAGE AREA
M5-B CELL
\t
900 . 500
8QGL
CEL
18
- 60 -
FIG. 3 : 1.0 TON ELECTRIC OVERHEAD CRANE FOR N6CEI.I
EQUIP. NO. : EF-76OO-H- K003
SCALE : 1/50
-20.0-
f-15CELL
.400 900
117'\CELl
A2Q.Q.
/ion ..2Q00 ._±LQ.Q...
M6CI LL
1
125600_
22300
HOOK CO\Vt\RAGE AREA
900
co
?8
ZKI
'81
C)o
- 61 -
FIG. -1: 30/5 TON ELECTRIC OVERHEAD TRAVELLING FOR SERVICE AREA
EQUIP. NO.: EF-7600-M-KOO'I
SCALE \ I/IOO
ZQO.
EL 92,017
o
c
J5.4DGL
SPfiM-1^300
\30/5 TON\\
ooo
1Q.0 l.20i
-ZQQ
82,200
• EL. 77.300( isr FLOOR)
EL. 72.300( BASEMENT)
EL.67,300
(POOL BOTTOM!
0/2)
- 62 -
1
I
1
1
— 1
11
j1
!
iii
•'I1
iI
• i
ii
j — i —
i t
\ 1i i
L, L_
2050
^ ^
2850
5
. - _ . _
t o
- — —
oF RA
IL/
oo
oo
J
ffS-A
»
i r
J L• •
11800
i\
i
Ii
1
2150
i
•
2;
• - j
O l
li
\
i
M5-B !_ . J
15400
1
. J
\M7
1550
oo oo
o.o
ooo
(2/2)
- 63 -
FIG. 5 : 3.0 TON ELECTRIC OVERHEAD CRANE I FOk Ml TO M4 HOT CELL OPERATING AREA
EQUIP. NO. : EF-7600-N-K005
SCALE :
- 64 -
FIG. 6: 3.01OH ELECTRIC OVERHEAD CRANEl FOR M$ I DT CELL OPERATING AREA
EQUIP. NO.: EF-7600 -M-K006
SCALE : 1/100
EL 8 5,700
EL. 8 2.200
M 6
6300
SPAH =525C
500
n. i
6O3
t90f
en
80Q
OF RAIL
M6
21100
-2M.QSL.
25 tOO
\ \
HOOK COVERAGE AREA
HOP 1300? H
- 65 -
FIG.T.3.0T0N ELECTRIC OVERHEAD CRANE II FOR M5a TO M5I) IDT CELL OPERATING AREA
EQUIP. NO. : EF-7600-M - K007
SCALE : I^'IOO
I
7300
SPAN-6P5O
90C
JL
50C
1
EL. 82.000
EL. 77.300
too
®\
MOO
28000
15400
24900
N5-A H5-B (17
\ \
HOOK CO '£ IAGE AREA
6300
1400 2Q.0-
3—,C
3-
- 66 -
F/6.8: 3.0T0N ELECTRIC OVERHEAD CRANE FOR WORKSHOP
EQUIP. NO. : EF-7600-M -K008
SCALE : 1/50 , t/100
©7300
5G.Q
]
EL. 81,800
_9QQ_ sen\
EL. 7 7,300
IOK COVERAGE ARfA
- 67 -
FIG.
FIG.10: 30 TON ELECTRIC FIXED HOIST FOR CASK RECEIVING YARD
EQUIP. NO. : EF- 760O-M-KOI0
SCALE • 1/100
30 TON FIXED HOIST
- 69 -
FiG.ii : 3.0TON SUSPENSION CRANE FOR ISOLATION ROOM.'
EQUIP NO. : EF -7600 - M - KOI I i
SCALE : 3 0 / l , 5 0 / l j : .
RUN WAY
I-BEAM
800
700 SPAN *• 2 0 0 0 700
700
500 2700 iI
700
i 700
HOOK COVERAGE'
• i
300
oj —
- F L ^8650 •:
i
! I
- i.' • K
7 700
•I
I . i
J 800
••; i> I
I
1 8
! s; o
T 8: Oi O
s
- 70 -
HOIST AND CRANE
1991. 5.
7]
- 71 -
4.
5.
*
3.
o
"^ "d^r-i IMEF Building MfcHl -y*| 31 Hoist !< Craned
* H **1 a J 7 H r *HH*J"CK °1 •:?-2i-&-& Seismic Category. WON (SIR) Equipments.^,
CMAA No. 70 or 74 s\ AISC ofl a]7J*|-H Hoist & Crane S} -?\2- -^-^-fMI cfl*>o=J *I=il
Craned
Code
OBE (/2 SSE) ^ SSE
Bridge, Saddle (End Truck). Hoist ^ -^-cj| Ĵ-*]ofl cfl*H
?1*M
2. ^ji Code ui Standard
7f-,
cf,
nr.
Technical Specification for Crane and Hoist.
(Doc. No. EF-E-1410-DT-H101)
CKAA No. 70 Specification for Electrical Overhead Travelling Crane
CMAA No. 74 Specification for Top Running 8< Under Running Sigle Girder
Electric Overhead Travelling cranes
AISC American Institute of Steel Construction
ANSI B30.11-Honorail Electric Wire Rope HOists
HMI-100 Specification For Electric Wire Rope Hoists
SOFINEL Documents
KU/GI - 82.7264 : Siraplif led Method For Seismic Calculation
KU/GI - 82.7273 : Seismic Date
KU/GI - 83.7141 : Miscellaneous Handling Equipment Runway Checking
- 73 -
3. #To
-cr CMAA No. 70 AND/OR 74 ^ K N r 7l-£.£_S.
Drawing
4,
"2" *J-al «}^- Code •*} Standardo|| a}-*:^.
^ A J - * ^ , OBE * ^ ( 5 4 SSE), SSE *}^ *$ °]^-s] 2S
*H°fl *&&& *}&.
SOFHTELAPPENDIX ! ::AGE l / 4
N KU/GI - 8 2 . 7 2 6 4 REV 3
A P P E N D I X
S I M P L I F I E D METHOD FOR S E I S M I C CALCULATION
- 75 -
1. DEFINITION
A floor response spectrum i s the maximum response(accelerat ion) of a one degree of freedom osc i l l a t o r (of agiven frequency and damping) on tha t floor when the plant issubmitted to the ear thquake.
At a frequency g r e a t e r than 33 Hz, a'one degree of freedomo s c i l l a t o r behaves as a body which i s r ig id ly bonded to theconcrete s t r u c t u r e . Thus the asymptotic values of thespectra are the maximum acce le ra t ions of the concreteitself.
As the frequency decreases, there is an amplificationfollowed by a. disamplification of the mechanical structurein relation to the concrete structure.
2. USE
The steel structure which is submitted to the floor responsespectrum is a multidegree of freedom oscillator. Therefore amodal analysis is necessary to derive accelerations andforces in the steel structure. The modal analysis is complexand requires :
- determination of Eigen frequencies,
- determination of Eigen vectors,
u- reading of ampli'cation factors on the spectrum for each
mode,- recombination of modes.
However a simplified and conservative approach can beadopted :
1°) Determination of the f i r s t preponderant Eigenfrequencies (or at least frequency-ranges) = two orthree are generally enough.
2° ) Reading of the spectrum and determination ofamplification factors for those frequencies (orfrequency-ranges) at the steel damping (4 and 7 %).
Many cases may occur :
KU / GI - 8 :: . 7 2 6 4 REV. B
a) A
iieauencv rsnae
frequency
Then the spectrum is conservatively enveloped by thestraight line A for frequencies greater than f̂
cX g = max (A, B, C, D, E, F)
The forces in the steel structure are enveloped bythe following loading case assuming constantacceleration oi g :
j//7*~r-7 77/ / /
It should be noted that in this particular case, iand f-j (and any higher Eigen frequencies) need notbe evaluated.
D
b) There is a peak between f-, and f-j (or f7_and f-̂
. _ . _ A
If f-[_, f2r £3 a r e accurately known, then
^, Freauencv
. oC 9 = m a x (A, B, C, D, E, F) line A.
If ±2 and f2 are unknown, then
o/ g = peak of the spectrum line Z\'
- 77 -
APPENDIX I PAGE,; / '4
N' KU/G1 - 32.7264 REVB
It should be noted that line J\ ' is a conservativevalue which dispenses from determining any otherfrequency.
It is furthermore recommended that ĉ g should be noless than the asymptotic value of the floor responsespectrum.
2 The.same procedure applies for the vertical responsefrom the vertical floor response spectrum,
a
<
03OCM
5aOu
a
0
a
o
LU
zu_OCO
UJ
a:03
- 78 -
PROJECT DESIGNATION SHEET
BPE UP DATED WITH TRAVELLING BEAMS
17.2.84 BPE FIRST ISSUE RA
Rev. Date Status Modifications- Observations Approved by
FRAMATOME - KOREA ELECTRIC CO.
KOREA NUCLEAR UNITS No 9 AND 10JOB No.
KEPCO No. DOCUMENT No. UNIT
Application
KU
Classification codes Subdivisions
9 4 7 E 3
Document title
MISCELLANEOUS HANDLING EQUIPMENT
RUNWAY CHECKING
Document type TECHNICAL NOTE Class
Issued by :
Tour FIAT Cadsx 16 32 084 Paris la Difensa
SFL K U / G I . 8 3 . 7 1 4 7 NESymbol Internal identif ication number
This document is the property of SDFINElIt must not be used, reproduced, transmitted or disclosed without the prior written permission of- S0FIHE1,
- 79 -
APPENDIX E PAGE 1 / 1 |
N" KU/GI - 8 2 . 7 2 7 3 R E V C
LU
u_O
: |coj
LU:
coi
A P P E N D I X
SEISMIC DATA
Two kinds of earthquakes are taken into account forcalculation :
- the Safe Shutdown Earthquake (SSE)- the half SSE (1/2 SSE)
ccThe corresponding accelerations to be considered for thedesign of the miscellaneous handling equipment are the
co followingOf
- Hor i zon ta l acce le ra t ion = 1,2 g (SSE) or 0,6 g (1/2 SSE),
o - V e r t i c a l acce le ra t ion = 0,4 g (SSE) or 0,2 g (1/2 SSE).a
.O For c a l c u l a t i o n c r i t e r i a , see the c a l c u l a t i o n note KU/GI -63.7147 NE. Miscellaneous handling equipment. Runwaychecking. Design c r i t e r i a .
° C I The c o n t r a c t o r shall submit t o FRA.MEX. the correspondingc a l c u l a t i o n no te s .
- 80 -
UJ
ZUJ
LA
DE
F9
20
8-.
P
AR
ISU
PO
LE"S
C
O1.
PL
AC
E
DE
£
)—<
"XDOI—
_ IUJ
Of-
I
m
UJ
SF
L8
-
b
B
OF
1.
1.
1.
2.
2.
2.
2.
3.
3.
3.
3.
3.
4.
4.
4.
4.
4.
in-AGE 1 / 12
N. KU/GI - 83.7147 R e v B
CONTENTS
.OBJECT AND DEFINITION
1.
2.
Ob j e c t
Definition
DESIGN RULES
1. Design rules
2. Grade of steel
3. Definition of load cases
RUNWAY CHECKING FOR MONORAILS
1.
2.
3.
4.
Checking procedures
Checking of beam without seismic action
Checking of beam under seismic action
Checking of flange of beam
RUNWAY CHECKING FOR TRAVELLING BEAMS
1.
2.
3.
4.
Checking procedures
Checking of beam without seismic action
Checking of beam under.seismic action
Checking of.flange of beam
- 81 -
a
Ou
LUQ
UJO
GC
Do
UJ
O
j
UJ'
CD;
1 . OBJECT AND DEFINITION
1.1. Object
This specification aims at setting forth the design criteria•and specific rules for the runway beams of the miscellaneoushandling equipment to be used in KNU 9/10 Nuclear PowerBlocX, scope C and G.
It is presented in terms of French design practice but maybe modified to allow alternative design in terms of Koreandesign practice should the need arise.
° 1.2. Definition
Secondary steelwork : this term covers the runway beams, andthe supports of the runway beams.
- 82 -
PAGE 3 /
N. K U / G I - 8 3 . 7 1 4 7 REVB
2 . DESIGN RULES
z
Q
<
5
CDO
OaDoo
LUQ
UJ
U
2.1. Design rules
The following general rules shall be applied unless extendedor modified by the present specification :
- CM 66 (ref. 1) Regies de calcul des constructions enacier. (Code for the calculation of steel structure).
The following particular documents shall be applied andshall take precedence over the general rules (ref. 1) :
- SOFINEL documents :
In addition to the present specification :
. KU/GI - 82.7264 rev. B Secondary steelwork designcriteria and specific rules (ref. 2),
. KU/GI - 82.7273 rev. C Miscellaneous handling equipment.Equipment specification. Scope C (ref. 3),
. KU/GI - 83.7091 rev. B Miscellaneous handling equipment.Equipment specification. Scope G (ref. 4).
2.2. Grade of steel
The grade of structural steel shall be E 24.2 qualityin accordance with the AFNOR definition (yield stress :(fe = 24 kg/mra2)
O
UJ
O
2.3. Definition of load cases
The loads shall be in accordance with ref. 2 :(in the center of the span)
Lo or Lo
DoLo
Lo1
PvPhf
A
i-
•» IUUUI U
I Iself weight of the runway beam = q x_concentrated load : equipment loaded, is taken intoaccount as a concentrated loadconcentrated load : equipment unloaded, is taken intoaccount as a concentrated loadload combination under seismic action (vertical)load combination under seismic action (horizontal)deflection of the runway beam
- 83 -
PAGE d
N. KU/GI - 83.7147 REV'B
The load cases shall be in accordance with rule CM 66,ref. 1.
Load combination A (checking of stress on members)
4 3 .1 Y = dynamic poefficient_ Do + _ W Lo 0> = 1.15, class A3, Groupe II, FKM)
UJ O ~> * 't/1Z
Load combination B (checking of stress on members under 1/2o SSD
4 17_ Do + (Lo1. + seismic loads]3 1 2 . '
SOriOcLPAGE 5 /
N. KU/GI - 83 .7147 REV. B
3 . RUNWAY CHECKING' FOR MONORAILS
3.1. Checking procedures
For the fixed runway beams and removable runway beams ofhandling equipment scope C and G (see ref. 3 and 4), it isnecessary to verify the yield stress obtained for structural
2 steel. Two cases are considered :UJ
- checking of the beam without seismic action with equipmentloaded (Lo) :
jjj Verification of stress and deflection :
. load combination A for stress (j f .£, (Je = 24 kg/mm203
o f 1. load combination D for deflection _ /
750
O9- - checking of the beam under seismic action with equipment
unloaded (Lo') :
Verification of stress :
Q . load combination B Q 1o X ' 3 3 •
. load combination C1, 10
O 3.2. Checking of beam without seismic action
(In accordance with CM 66 reference 1).UJ
3.2.1. For load combination A
Max. Bending moment2
3 D qj^ flM max. = _ U Lo " + = (9 Lo + 4Do)
8 ' 6 24
m
UJ
a.CO
to
- 85 -
PAGE 6 /
N- KU/GI - 8 3 . 7 1 4 7
oCN
en
m
u.10
. Stress
r̂ M max .Of = < 24 kg/nun2 = Q e
V
UJ where — = Section Modulus of beam2 VUJ
UJ
Q3.2.2. For load combination D
incc
Oa
o • Stress
M max .UJo
Max . b e n d i n g moment
M max. = . .+ . = _ ( 2 < P L O + Do)
.4 8 8
UJ
° V
Deflection
2 4 3Cf 0 5q £ Do £
f = I _ _ or +h 384 El 48 El
f 1UJ
750u_Oto
3.3. Checking of beam under seismic action
(in accordance with CM 66 ref. 1).
The accelerations corresponding to SSE or 1/2 SSE to beconsidered for the design of the miscellaneous equipment arethe following (see references 3 or 4, Appendix C) .
- 86 -
SiUJIL_UJQ
_ J
10
cc
Q .
0 3
CNai
UJ
o
o
UJ
aUJ
o
PL
A
<
cc
1—
1
oC/)
')
ca
UJ
tr
0 3
iu.to
SoFin
1 / 2
1 / 2
S S E
S S E
Bean
si
SSE Ver t ica l acce le ra t ion :
SSE Horizontal acce le ra t ion
Ver t i ca l acce le ra t ion : 0,4
Horizontal acce le ra t ion : 1,
i i s checked with monorail inno load charging.
3. 3.
P v =
1. Load combination B (under
4 17= _ Do + (Lo + 1/2 SSEV)
3 12
w i t h 1 / 2 S S E V = 0 , 2 . (Do + Lo')
P h =17 17
= x 1/2 SSE, = x 0 , 6 x12 12
w i t h 1 / 2 S S E h = 0 , 6 (Do + L o )
Mv =
Mh =
24 q(L 17 L o ' l 17
( ) + ( ) + x3 8 12 4 12
I(97 Do + 204 Lo)
4 8 0
17 q l Lo'J?. v n,fi f + )
12 8 4
PAfP 1 /rMuC / /
N." K U / G I - 8 3 . 7 1 4 7 R E V B
0, 2 g
: 0, 6 g
g
2 g
the center of the span with
1/2 SSE)
(Do + Lo')
2 .q I L o ' l
0 , 2 x ( + )8 4
111(Do + 2Lo)
1 6 0
Mv _ Mh= Oh = I ' y = l / 2 Iy given by the p r o f i l e
Ix I ' yV ' V
/r~ Ue= ()v + Oh <
1,33
- 87 -
UJ
u_Oto
(.*
oo
to,
3 . 3 .
Pv =
Ph =
=
Mv =
Mh =
2
.3.4.
EL
2. Load combination C (Under
Do + Lo + SSEV, with SSEV
SSEh
i , 2 . (Do +
q£ Lo'l+ +
8 4
7 •? .. {8
Mv f~~ ( j h :
IxV
=
UJLO2UJ
UJQ
CO
cr
0.
r00O
en
UJ
OQ.
OCJ
UJ
aUJ
CJ
a.—'
i—
a.
aoh-_JLLJ
)FIN
uCO
en
UJK
CD
tu_(/I
B
OrJOELPAG £ 9 /
N. KU/GI - 83.7147 REVB
4. RUNWAY CHECKING FOR TRAVELLING BEAMS
4.1. Checking procedures
(ditto monorail)
4.2. Checking of beam without seismic action
(In accordance with CM 66. Ref. 1).
4.2.1. For load combination A
. Bending moment
a) Self weight action
Uniformly distributed load, the moment is Mo, calculatedaccording to the real situation of the beam.
b) Travelling beam action
With concentrated loads to, the maxi bending moment, Ml,depends on the ratio e/ ̂ of the rollers spacing to the spanof the beam.
It can be determined by using influence curves or by a stepby step calculation with several roller positions.
The maxi factored bending moment is :
M max = 4/3 x Mo + 3/2 x Ml
• Stress
r- M max , t—
PAGE i o /
N . KU/GI - 83 .7147 REV. B
UJto
UJ
Q
inQ:
OCNOl
oo.OO
UJO
o<
o
UJ
u_O
-/I.
UJ
z
O
a.
O
en
OaDOo
UJ
o
o
UJ
zli_Oen
03
>UJ
B
Concentrated loads
M'HI = 0>6 x L'° x M1
Lo
Factored bending moments
M'v max = Mo (i + g x °'2
M ' = ( M o x O , 6 + M l xo ma x
, stresses
NS
E
ULJU_
LA D
EP
AR
IS
CO
92
0
III
A C
OU
PO
LI
UJQ
.AC
E
i
a
:IA
T.
TO
UR f
NE
LS
OF
I
UJ
a:ao'
^OFsflcL
B
, stresses
4 S-
i PAGE 1 / 1 1 1
I . . I IBDS - I P - 6 0 7 n
• % •
m^ HOIST-M 2
- * 2 : < = > .
I 2. -g-
92. 6. 10.
0I . i . i . .
2 - 1 71] °4 ^ t - ^ ^ l
2 - 2 ^ ° J 5.«J
2 - 3 KS & J I S Hi ANSI B 3 0 . l l
2 - 4 ? m ^ » ^ q
3. ± *% 7d 4
3 - 1 °J °| =S *3
2)
3) 7)
•4), - ^
-fr *|**i;I-. (MAKER MILL SHEET ^ °] )
*j ̂ *3 «>.c> . (MAKER MILL SHEET ^ ?] £ - °! **$•*]
3 - 2
2) l^)-. (MAKER MILL SHEET
l ; ; ; i
- 93 -
BDSi
j
BDS -i
IP -
si 4
607
1I
i
i
i1
r| PAGE 2i
14 : 92. 6.
! j£ : 0
/H 111
10. |i1
— ^
3) y\ ?i] *j 4 *J - t *5 *J c|- . (MAKER MI LL SHEET % °J £ -fe fj *j °< *} -
) 7 r q 1̂1 -1- ^ ^] 2. o] a4 -f nj ^ «l »> 2 , 5 DJ, 5. J
5)
(1) B | *i ^
3) 7]E} ^ ° J § - ^ : l i * > 3 4 - t *3*Jtl-.
5. *d -7- 2- -t 7J 4
5 - 1 *] 4 ^ 4
, ^1^^711 }̂ CAMBERi] 4=8 , ^^--S] ^l-^-^^l. BOLT
_ J
- 94 -
BDS
.?\ A $•*!%•>•}•+-
=3 -4L .
i 1I P A G E 3 / l l |i . I
: 92. 6. 10. I
BDS - IP - 607| i i i |
HOLE
5 - 2
KSB 0236
, CAMBER, «1 » 3 J ,
c|- . )
5 - 3 . a ] v\ 2] ^ 4
1) GIRDER ^ o | - i - - l - ^ - ^ - e AWS D14.1 CODE ^| «] 4 if ^ 4 1*1"-H
2)
^(IMEF-HC-I02)o)l tcl-ej- SPOT5. RADIOGRAPHIC TESTING-fr
RADIOGRAPHIC TESTING^ GIRDER^ Dxv°l -3-
6.
i
6 - 1
6 - 2
(mm)f-1 12 o] o\
II 12 5:2} 25 o\o\
(ram) |_ ^ t
1.5 |
I2.5 Ii i
-1-S] f i • ? - *
6 - 3 -fe- CAMBER, 7(
' ->- > - r
6 - 4 ^•*333-*] ^ RAIL CLAMP i
3 * 3 5 . , *1-*BOSS 4 % - t ^
-(HOISTS 2.2}?! )•! ^=8
RAIL CLAMP $ Jl3??*l-fe- ̂ l ^ *
7.
7 -
i ; |
- 95 -
BDS
lv s. 4 A^-AA s] 4 I
+-BDS - IP - 607 |
4
\±E.AA n ^ ? ! 7d41^H I ^
i 1I P A G E 4 / l l |
- T - - -"- HI ?H=S ° J 4 : 92. 6. 10. I
- + -
? -M
7 - 2
=3 n JL 2} *' * ^ * -f =3 s|
1 °J I afl -y 3} EARTH 4 1 # ^ 5 MO o\
± 10%
± 10%
± 10%
± 10%i
| GIRDER 5-]i , , .
CJ, GIRDERS)
7 - 3
SJ
7 - 4 JjL
2)
=a-5 ^ =9
^ P A I N T I N G PROCEDURE (IMEF-HC-I03)6ll
- 96 -
BDS
Ml
BDS - IP - 607• + -
5.«1±S^ S.HH°J 3-
I PAGE 5 / 1 1 |i i
I A^ °l*} •• 92 . 6. 10. |_ i . i
I 71 'S t! i : 0 |
BANDO
- e P A C K I N G ^
10.
ay E> x f e | l > c > . (Q.A MANUAL{| 2] ?]
11 .
1 1 - 1 DEFLECTION >
BDS | PAGE 6 / l l[
I (: 92 . 6 . 10 .
BDS - IP - 607 ±^-q ^ efl °] 3-4
5)
6)
'"7)
8)
* - i A iE-fe 7)- -I- o\ °i -f ttl) o]
^ . ^-"J- C.A.B5]
DEFLECTION^ f -tf o] *V 7]- a. ^ o) *J cj- .
1 1 - 2 HOOK APPROACH
HOIST?}- °o> SIDE 2] RAIL STOPPER OR LIMIT SWITCH $]*]*$ "S $-& ttfi
H00K5) CENTERS] ^ * - t £) 3tl-*jcvj}£] 7-) E] -f CHECK 5h -fe- 5 *1 D1 , HOOKB]
1 1 - 3 ' - *§ WHEEL BASE
WHEELS) ^
1 1 - 4 4-*^
CHECK
1 1 - 5 •& ?
•1) ^
S * B R A I L
^*l RAIL
CHECK *} ± 5 *>| D^ WHEELS RAIUl - f
-f CHECK 1>C)-.
± - 5 . CHECK S } - D 1 ,
2)
3)
•&?•!•
=8-3*
- 98 -
BDS | PAGE 7 / l l |, , ; j |
I t5.7]?b^ysi]A} | % • * } £ . $ : I A*&o±*\ •• 92 . 6. 10. |i . i I I
BDS - IP - 607 | S. »1 ± E. AA 2 . ell ?! ̂ tM
1 ^•f-tfej-f ^ ? ! 4 2 ̂ *o" STOPPERS]
STOPPERS] $\*\7\ =a ̂ lv 7)- -f 2foi«fcl-.
1 1 - 6 ?7] ^7)1 /-l*j
2)
3)
4)
13. H
1 3 - 1
-2:5 ^^^Efl-t-l:
5) 3M-§. ^
6) =2-2^51 «H^ £-b ai-a-gr ? f ? * M 3E-« S|
I IBDS | PAGE 8 / 1 1 1
. ," i I
I 11 s.y) n ̂ AA n ̂ \ I 7tl 4 it € I^^°J4 : 92. 6. io.|I I I I
BDS - IP - 607 | 5.6l±S.-q êl|°J ^ 4 H 4 A| [ J p ^ I : 0 |
13 - 10 TEST REPORT FORMAT FOR TRAVELLING (FUNCTION) 1-f
13 - 11 TEST SHEET OF HOIST FORMAT 1-?-
13 - 12 TEST REPORT FORMAT FOR CRANE DIMENSION 1-?-
- 100 -
HOISTSI PAGE 9 / 1 1 1
HOI
1. GIRDER ± eJ 7j 4
1 - 1 S P A N
1 - 2 GITDER CAMBER
1 - 3 cl| TV X\
1 -' 4 WHEEL BASE
1-5 4 € ^?°1 43
1 - 7 x)--g- BOSS -f 4 •
1 - 8 A|is. BUMPER ^U!
-fe KS B 5209^1 ^ ^ ^ *]• q s3 ^ .g.
i • . . I
- 101 -
BDS I PAGE 1 0 / 1 1 :
GIRDER •}-
- 4 %' •%• I o-l - 2 -
BDS I PAGE 1 1 / 1 1 !
• • * ! • '
p •
A
WHEEL BASE± 2 . 0 com
1.0
BASE
* ! • • & • crjj WHEEL BASE£j n)| •£
=3 -t
R-J R-
SPAN x ( ~ — — )5 0 0 0
2J 4- 1̂ ^ 3Y N *t -f —
^ ' * ' %.*> !»• ^ °J oil ci|'GIRDER CAMBER ^ ^ Si ofl
SADDLER ^ •=•
r ~iI PAGE 1 / 5 |
H4 Til -?- A4 £1 4
• + -4 °J 4 : 92. 6. 10.
-HBDS - IP - 606 -I- t!
1.
-S-
2.
* ] •
2 - 1 7i| q> 4 o> ^
o _ o -*. o] c tr̂
" ^ o i_ —•— v_
2 - 3 K.S ^J J I S
2 - 4 ?1 E[ 3V aj ^3.
1) -? i 3 4
3) %
r iBDS z^ rfa . I PAGE 2 / 5 |
I >» 5.-A n 5-Al s\ •>•} I 3 4 ' S. § |7f l^°J*l- : 92. 6. 10. |i I i . i
BDS - IP - 606 | *'-f 2.°] ±E 7J4 1 4 ^ | I ' g ? ! ! : 0 |i i . . . . . i . . I
(9)
(11)
(13)
(15)
si *3 (10)
(12)
(14)
4.
4 - 1
4 - 2
2) -& 3.25]
£ 40 °C °Jt
t £ 1. ]
r
[_•_,—.—_
1 ? TI71
1 _ _ _
^3 * } * i ]
r
r TT
!
"I"7]M
A •§E -^B 4F •§
A i?E ^B ^F #
T"
1
r
--ir 1
5 ?!^ ol
^J o?
— _50657085
_)
658090
115
deg
55707590
_;658090
115
i|
i1
—1
——
JL
*•] *
: 92- 6.I l
BDS - IP - 606 |I I
TI
2) >g
3) 4r
O
O
4 - 4 iL
1) £
O]
2 ) *«
± 10 %
± 10 %
A | * J )
0 . 5 n ] E i o ] ^ n)--g- 7)] jjfl 7)-§
% 6] o\
3) s
4 - 5 -
-1-D1 ^JTr-f
2) -& 3.5.121 l 50MMO1-U 7J o\
4 - 6 *1 =2 °J ^1 *j A] ̂ .
1) f i ^1*J •£ =8 9 ^»>4=-ofl-H =S74°F*»1 -5-
2) *12
BDS I PAGE '1 / 5 |
. A A -?- A-i s\ 4 i, i
: 92. 6. 10.. I
} BDS - IP - 606L
v . w6120. P
7} ^ 4. a] 71 £-§• ( % )
=8 3 «!• f- ( Kg )
N = * 100
V :
N :
W :
P :
A t!i i
KW
°J a4 -f 7} 2]
2) -S- 3.721
4 - 8
1) 125%
=9
2. ]
°J
CYCLE
Si
, , I ,
500
| 1
1 2
1 3
1 5
| 7.5
1 10
15
| 20
30
Kg
TON
TON
TON
TON
TON
TON
TON
TON
TONJ
40
45 |
50 1
50 |
50 |
50 |
50 |
50 |
50 |
50 Ii
H]
- 107 -
- 108 -
TEST SHEET OF HOISTCustomer: $y«i#S? Machine No. :
Type ffi ffit Weight
Rating
HoistingCapacity
t
ssLift
m
£ tSRacing
m in
HoistingMotor
•& ± m atHoistingAmp
A
HoistingSpeed
m/min
TraversingMotor
kw
TraversingAmp
A
MMTraversingSpeed
m/min
Phase V'olt.npo
V
mmFrcqiien• c . v
Hz
Characteristic Test M Tested at Hz)
ft ffiLoad
%
ffi-" h f»5 Hoisting.1: U P
7D HitCurrent
A
A )}Power
KW
m mSpeedM/min
r- D O W N
W 5SKCurrent
A
i* &'SpeedM/m in
"1 31 $Slipmm
I r n v c* i" s i n
m vs.Current
A
A •))Po w c r
KWSpeedM/min
IS A- #J ¥ Total Efficiency %
Inspection Item
»J m as i$ s
Gear Box
Push Button
Limit Switch
Magnetic Brake
Magnetic Switch
ft itif& fill K i l
u-x^T-mm
Outside View
Feed Oiling Unit
U-X Line Voltage
125% Load Test
V
Minimum Operating Voltage at 100% Load Good
i^l^ Temperature Rise Test ±IM|it tl Temperature Rise In V.
it. Nntc : (I!) $Un.& Hcsislancc
HoistingMotor Coil (R)
•c
MagneticBrake Coil (R)-
m m mOenr Box
TC
'U M Insulation & Dielectric Test
MISffit.il Insulation Resistance (by J ^ ° V Megger) Mil HSIiWiSs Pressure Test(60Hz lmin.) Good
• Note: JtflB-Si t*ttl^la(|ff.fe Magnet Braked mMR&°] "iSf^J ̂ °J.In the above current & Power of characteristic Test, they Contained Consumption of Magnetic Brake.
Date Tested by Approved by
- 109 -
: 13 - \-
CUSTOMER : DATE
SPEC INSPECTED BY
ITEM OF MEASUREMENT POINT OF MEASUREMENT VALUE OFMEASUREMENT
l.SPAN
Within 10m10—20m
20~30m
More tlian30m
i 2. 5mm
+ 3. 0mm
i 3. 5 mm
4 . 0 mm
2.CAMBERWithin ±50% of Span 800
SPAN
DRIVING:
FOLLOWING:
3. DIAGONAL DIFFERENCE
Within ~20m
More than20m
±2.0m
± 3 . 0mm
4.SADDLE WHEEL BASE± 2 . 0 mm.Right&Left wheel basedifference ± 1.0mm
5. 4-point Level Differenceof wheel Contact Surface
Spanx {±-57000")
6. Rail Gauge of Traversing
Gauge X(± 1 . 5 •5.000
R-
3-points(A. B. C)to be contactedvertical differenceof l-point(D)
Rl =R2 -R3 =
7.Right & Left HorizontalDifference ofT. S Rail SurfaceGauge X-JTQQO-
H 8. T. SRail Straightness
S.Wlie&l-Px ŝs -Gap
Machined Condition
± 1.0mm
S =wheel diameter =
-E
10. Stopper of T. S wheelwithini 5 mm
^ A—A'= Within 2 mm
A =A'=A-A'«=
ESI
A'
11. STOPPER OF ENDCARRIAGE
B — B ' = within 3 mm
FOLLOWING:B -B'=B-B =
DRIVING:B -B'=
("}i*)*l3-t- 19)2-2 ( g ) BANDO MACHINERY CO., LTD.
- 110 -
.X- 1 3 - 1 :
CUSTOMER: DATE
SPEC INSPECTED BY:
ITEM OFMEASUREMENT POINT OF MEASUREMENT
VALUE OFMEASUREMENT
1 . Span
Within 10m
10m- 20m
20m -30m ± 3.5mm
±2.5ir
±3.0mra
2 . Camber
Within ± 50% of Span1
800
SPAN
FOLLOWING:
DRIVINC :
Vs™ mm
3 . Diagonal difference
Within 20m
More than20m ±3.Omm
±2.0mm
4 . Saddle Wheel Base
Within ±2.0mm
Right&t Left Wheel basedifference
Within ± 1.0mm
B -
A-B-
W'
5 . 4 - Point Level
Difference of wheel
Contact Surface
SpanX ( + 15, 000
CD CD
CD CDCD CD
6. Traversing Stopper
Wi
A 5Runway Cableveyor
TKP-TYPE
TKF-TYPE
FTP-TYPE
- 112 -
\TYPE
CABLEVEYORNO.
BENDINORADIUS
(mm)
CHAIN PITCH(mm)
FREi SPAN[m)
MOVCH6
STROKE
WITHOUTSUPPORTROLLERWITH ONESUPPORTROLLERWITH TWOSUPPORTBOLLER
CABLE/HOSE OUT DIAImmJ
CABLE/HOSE WEIGHT
t ^ - ' ' • •
MOVING SPEED(m/m!n)
TWIN CHAIN WEIGHT(kaf/m)
USING TEMPERRATURECC)
OMU'KTINO CONDITION
PAITMATERIAL
CHAIN
SUPPORTER
END LINK
TK
TKO7O
75
90
125
145
70
3.5
6.7
10.1
13.4
27
50
TK095
125
145
200
250
300
95
4.5 •
8.7
13.0
17.4
46
60
TK130
200
250
300
400
130
6.0
11.6
17.4
23.2
60
70
60
•- 1 0 - -150
TK180
250
300
400
500
600
700
180
8.0
15.7
23.5
31.4
80
80
21
H
H2S0
350
450
600
750
250
11.5
22
33
44
110
100
60
40
-10
150
INSIDE
STEEL
ALUMINIUM
STEEL
STEEL
ALUMINIUM
STEEL
TKS
TKS070
75
90
125
145
70
3.5
6.7
10.1
134
27
10
TKS095
125
145
200
250
300
95
4.5
8.7
13.0
17.4
42
10
60
6 8
0-50
TKP0320
2
37
32
0.9
1.7
15
1.2
TKP
TKP0450
IB
50
95
125
150
2B
50
95
125
150
45
1.0
1.9
22
2
TKP0625
2B
75
90
125
200
62.5
2.25
4.4
31
5
90
(0.4) (0.8) (1.1)
0-50
(1.9)
TKF
TKFOSS
60
100
150
20
1.5
2.7
22
12
(1 .4)
TKF085
100
200
250
20
2.0
3.7
35
21.5
TKF115
140
225
300
25
2.5
4.7
48
30
TKF175
185
250
350
30
2.75
5.2
60
40
(2) (3) (5)
0 — 50
ACIDITY/AKAU(X)
STEEL
A L U M I N U M/PLASTIC
STEEL
PLASTIC
STEEL STEEL
-V 678 5048.
Oval ( ABI.IiVfYOK (TK Type)
Univers.il lypc
I he TK Type CABLE VEYOR is composed of a
steel chain with aluminum stays to give high
strength and durability for diverse applications.
The holes of the stays are order made to fit
the cables or hoses properly.
Ihe TK Type is very versatile and can fit most
industrial machines.
length of travel: 24 m and under
Speed of travel: 60 m/min. or under
Diameter of the cables or hoses: 80 mm and
under
A stainless steel chain can be manufactured
for use in highly corrosi*^ ei*Hronments.
I i , H I T ( A!'>1! Vl.YOK
(TKS Type)
()nc-!mi< h \l Itii limi'iil
The TKS Type chain section is the same as
the TK Type, however, the supporter has a
different construction. The frame is structured
in a special way which makes it easier to set
or remove your cables or hoses {the bars at
the stays are removable). The plastic dividers
of the stays are adjustable to the diameter of
your cables or hoses.
The TKS Type is suitable for machine tools
that use only a few light weight hoses or
cables.
Moving stroke: 17 m or underMoving speed: 60 m/min. or underToj^ft-eight of the cables and hoses: 1 o kgf/morJ^Jaerr
Outer diameter of the cables and hoses:
42 mm or under
Temperature range: 0 ~ 5 0 ° C
Avoid use in acidic of alkaline conditions.
ta*A\.Supporter (inner side)
' Supporter {outer side)
1
1End Stay 1 ^
/ (outer side) L
1 / Divider /
/ /^Moving End BracKet
Release Bar/(inner side)
/chain__
% -
i-«C^__ fixed End Bracket
- 114 -
GUaiLAllON Of NUMHfrR OP CHAIN 1 INKS
70
f is rounded off to the nearest larger number.f' = Number of chain linksS: Moving stroke (mm)R: Standard chain bending radius (decided by chain si?e)
K' =
Freespan without support roller
Freespan with one support roller
Freespan with two support rollers
F0=-g- + K
r i—~ -t~ ix
F,=4 + K'
The values of fo. ft. fi must not exceed the maximum freespanfrom the capability graph on p. 24. If it does, a larger chain sizemust be chosen or more support rollers added, but only up to af>ij!^*um of two.
DECIDING ON I I I ! : SUPPORTER
Dimension AThe size of the supporter may be chosen from the table belowwith reference to d (maximum cable/hose diameter).
DimensionB ' = S D + S C + M i n . 20
B S B '
8': Calculated maximum supporter widthB: .Standard supporter width as chosen from the table below.Supporter hole sue D may be decided by this equation.
D S d X 1.1D should be an even number from
Number of supporters (n) would then be as follows: —
When
When
chain
chain
link
link
number
number
(O
(O
Is
is
even
£'2
odd.
2
number
number
of supporters
of supporters
Is,
is.
S9
dbte/bo$e MaximumOuto CHamrta
* ! 8
*27
Dtmtnskxi A
35
45
60
O
O
SO
OO
tooOO
125
O
O
Dimension
150
oo
B
200
O
o
250
O
o
300
-
o
350
-
o
- Total chainflength = Number of links x 70 - j - 95 *.s
• t - l H !
( ' / ) inner dimensions forsplit supporter type
Chain guide
For odd for evennumber of links number of links
(B+M.5) No clip is used withB-^« i or» piece Supporters/ =
fixed bracket
||SC|| CHS! S-S|
Mwing bracket
678-5048. 671-9572. 675-81895-1 °l?,'S
- 115 -
TK09
I A K I U A I I O N ( M N U M I 5 ! ! ; < < : - • r . . w
95
f is rounded of! to Ihe neatest larger number.
f = Number of chain links
S: Moving stroke (mm)
R: Standard chain bending radius (decided by chain we)
9
Frccspan
Freespan
Freespan
5,'-(f + *R)2
without support roller
with one support roller
with two support rollers
F - -
* - !
F i = f
+ K'
+ K'
+ K'
The values of fo. Fi. F2 must not exceed the maximum freespan
from the capability graph on p. 24. If it does, a larger chain si/e
must be chosen or more support rollers added, but only up to a
maximum of two.
DIMI.N.SIONS YQR SIANDAKI) NUFTURilU
The
with
size of the
reference
supporter may
to d (maximum
IV =XD+S(
B2IS '
be chosen
cable/hose
: + M i n . 3 C
from the table
diameter).
below
B': Calculated maximum supporter width
B: Standard supporter width as chosen from the table below
Supporter hole sire D may be decided by this equation:
I ) - B < I X 1 . 1D should be an even number from
Number of supporters (n) would then be as follows:—
When chain link number (V) is even, number of supporters is.
- I'
„ __When chain link number ({') is odd. number of supporters is.
I'- 1
Cable/hose MaximumOuter Diameter
* 3 I
Dimension A
50
65
80
O
-
100
oo
123
O
O
150
O
o
Dimension
200
OO
250
O
O
0
300
O
o
350
OO
-100
O
O
450
-
o
500
-
o
Tola! chain'length =: Number of links x 95 -r >^ -
NUMBER• OF LINKSxH) 95
A-A CROSS SECTION
° )I 70 I 70__ MOVING
BRACKET
B+«0B+25
Chain Guide
FIXED BRACKEr
WFor even
nurrber of finks_. L
For odd nunrbofof links
' ' B.8 •
17n45 n
t Ftt—
•!:fHB+19.!
4 —MS
1
CABIE/HOSE d M A X V - . .
FRAME DIMENSION B •»
oivioeRMIN. NO
MAX. NO
•1«M
0
5
t
5>
! • " • ' • • •
• 200
2
13
MDVING BRACKET
45 15
TOTAL NUMBERA- :. CHAIN LENGTH = OF LINKSX95 125 A-A CROSS SECTION
95 1 95 j MOVINGBflACKET
CABIE/HOSE i MAX
FRAME DIMENSION B
DIVIDERMIN. NO
MAX. NO
100
0
A
150
1
B
200
7
n
FIXED BRACKET MOVING BRACKET
678-5048. 671-9572. 675-8189
- 117 -
CAPABILITY GRAPH (TK.TKS, TKP. TKF . H TYPE)
36
., Wtrh no (^forl lng roller /
With or* HTf
5 9-
1l. 30/5S.
TEST B.EPORT
PROJECT NAME. 3
HOISTING
I LOCATION | OI 1I TEST RErORT NO |
J 1
SITE
PART NAME
1. HOISTING (NO LOAD)
MOTION
1 1 1I SPEC f ACTUAL II j 1 RESULT
/ 1 /
I UP
IIi! DOWN
] SPEED (M/MIN)I t
I CURRENT (A)
I VOLTAGE (V)j jI SPEED (M/MIN) II CURRENT (A)j I1 VOLTAGE (V)
I
STOP WATCH |I . _ _ j
I CURRENT METElj
I VOLT METER |j 1I STOP WATCH |
\ CURRENT' HETEOJj 1
I VOLT METER- |
2 . HOISTING (F.OAD)
MOTIONI SPEC" I ACTUAL |I — + 1 RESULT
j, j i__j j r
I SPEED (M/MIN) ]>.,/> /£>.>
BS - FT - 01
T K S T REPORT19
( PART NAME | HOISTING (3 />-£> I CURRENT METEH
Y + + h-— -\ 1I VOLTAGE (V) \ wo /iHo .\i&>- /4** 1 'Groc-b I V 0 L T M E T E R I. JL -
oO LIMIT SWITCH?]-
TEST BY -,)
•§-^
APPROVED BY
B A N D O M A C H I N K R y C O - ' , L T D
- 120 -
BS - FT - 02
TEST9 ?3
i PROJECT NAME | Q^^p _ Z M ^ T ? tK°o£> \ CURRENT METER
t* ltd* '/&*•.) 6rt*>0 I VOLT METER JVOLTAGE (V)
3 . o r.RAiur-'l-
BS - FT - 03
T E S T RETORT//
PROJECT NAM I? | I ' N A T I O N I O
. 1
SITEQtotfP- XHS-fT CKCdCl) I U O I I W N I u HIHM'\>>*>o> 511s i
PAUT NAME j TRAVELLING (JOO.fi. Hi.7 ) TEST UKTORT NO |
1. TRAVELLING (NO LOAD)
MOTIONSPEC | ACTUAL |
1 -^ RESULT
| SPEED (M/MIN) |
RIGHT I CURRENT (A) |I I
i VOLTAGE (V) II I i
I SPEED (M/MIN) |i . j _ .
LEFT I CURRENT (A)| .. . _|.1 VOLTAGE (V)I
|
STOP WATCH |I .
| CURRENT HETElj
| VOLT METER |j || STOP WATCH |
-4- -4| CURRENT METEff
- + -I| VOLT METER |i i
2 . TRAVELLING (LOAD)
i
MOTION
KlfillT
f—
I S P E C | ACTUAL I |1 ( 1 RESULT 1 :I Uo-I / k)t>. > I AJo. I I AJO, a | I |
I SPEED (M/MIN) | / o / /o U s / 9 i | £rcn>& I STOP WATCH II _ _ j _ _ LZl L _ Z i _ _ j - _ L _ j
| CURRENT' (A) \hf / I fir-c^xi I CURRENT METEIjL _^ L_ L^11_/-_Z_J-_I___ L_I -| | | |_ -jI VOLTAGE; (V) | ^ / W o | ^ a / ^ \ 6r*W I VOLT METER |
LEFT
I S P E E D ( M / M I N ) l / o / z o L i / o i l # c 2 t 6 I S T 0 P WATCM II j / [.Zi_j___-j__ ( [
I CURRENT (A) | ^ / /J-J. \ $..
BS - FT - 09 | PAGR /. _ i j
I r "~
SIIRRT NO. 7. I j .
CRANK NAHK
PART NAME GIRURR DBFLKCTIOM GRAPH
I LOCATION | O SHOP_[
! TKST REPORT NO I
StTE
! I 1 .
?A
30
:m2A2220
f'_,... . |
SI•> A NT
n?.
4: LKGRKI).
TIJST HY
ir.i
NO LOADR : UliCK I,TNI5
! DOI OPPOSITE. s:i nil
i ! •. . . : '• •
1005.' XOA0 'H : RED LINK
AfPlfOVKIl IJV
LOADG : GlffiBN LINE
BAN.DO M.ACHINI1.RY LTD -
- 123 -
BS - FT - 08
TM'.&T m.s.F'O.RM1
CRAMK HAMK
| PAGE /i
S H E E T H O . 1 / 2
SITE
PART MAHIJ j GIRDER DEFLECTION j TEST REPORT MO j '
DO
D11
02 '
SPAMtS)
1 .
0 % -LOAD
| CHECK POINT,{ |_ r _,_
I I).I | DOI _ . [ .
SIDE I / „
orro. S
| DlflVK SI HE100 % MA!) I —
0 X LOAD
. ,
£
OITO. smic
|. I DI?.TVI? S I D EJ - - I 2 0 * LOAD II I ori'o. SIHKh . _ +I | H 1 U V K S J I ) RI {> i : TOAD I 1- -| • | OPPO. SJDK
~LO j —T •£ I _/Jy
/ | • I' / •_££ i__*?„_L_< *_
REMARKS
^ .
Gt
I
*—/ * ^ t
|
I|
I
I
IHIIIiTEST I!Y «2 _4- n ny
•". JyANDO , MA.CIJ.I. Nlvl/Y ( X> - , .LM.'O.
- 124 -
2.
BS - FT - 01
TEST REPORT
I PROJECT NAME | £ W W / C , . J : M ? F C KOOQ.J • LOCATION |. 1
O SITE
( PART NAME1
HOISTING TEST REPORT NO
1. HOISTING (NO LOAD)
| . •• [ S P E C | ACTUAL | .I MOTION | 1 .: [ RESULT
[ I I I I ' _ j
[ | SPEED (M/MIN) p - t P /O.S | z.f /o. a 9 | fy^€> I STOP WATCH |j [ : j j f_\ ; j ; ; I
UP | CURRENT (A) \B9-£/9-O I >$ / 3. ? I /v , o f i I CURRENT METElfi j • « • . _ • = _ _ \-~ I - I
| VOLTAGE (V) \6£ /S>.C I &- i CURRENT'METErfI j j |-__r__r__i j| VOLTAGE (V) \uOo /U \ ilU-t /tl I v o r 'T METER |i t I : L _ £ _ _ _ _ _ J I
2. HOISTING (LOAD)
I SPEC' I ACTUAL I I IMOTION i ( 1 RESULT | yt^7\7] \
I / I / I , I Il i \-—/— 1 i
I SPEED (M/MIN) I / I / y I STOP HATCH || j ^+-
UP | CURRENT (A) | / | / X [ | CURRENT METEfI ; j I /_ I
I l'{)I.TA(.'K,(V) I / I X / .. I • | VOLT MICTKR
•f
h 1 • -\ \/- —\ 1- ^SPEED (M/MIN) I / A / I I STOP WATCH J(. + •_-/-+ - + --+ -j
DOWN I CURRENT (A) | // I / I I CURRENT METElI I / I n _j i (I VOLTAGE (V) I // I / . I • I VOLT METER \1 . 1 * ___) •_ j 1 1
3 . O DRAKE?]- ft]*JSl
O LIMIT SWITCH? j-
TEST BY APPROVED BY
- 125 -
BS - FT - 0 1
TEST REPORT
1 9
PROJECT NAME | LOCATION | O__j : I
-HSITE I
I PART NAME | HOISTING TEST REPORT NO
1. HOISTING (NO LOAD)
| SPEC I ACTUAL |MOTION 1 f— ( RESULT
\WG*1 AJti \M/CrH /_*_ I I I
| SPEED (M/MIN) \c{, /O'H \J".$ / e>,fl I
BS - FT - 02
T E S T " REPORTin -' -ft •
I PROJECT NAME
I PART NAME
- IMS"K | LOCATION | O £. + —+TRAVERSING t»C>,l£>.) | TEST REPORT NO [
I i I
SITE
1 . TRAVERSING (NO LOAD)
i 1 i 1 1 1| SPEC | ACTUAL | | I
MOTION | • 1 1 RESULT I y\^-7\y\ j\/0&.f /JJO. ±\U& 1/ fi)u>$\ I |
| SPEED ( M / M I N ) 1 / ? / / ; | 6.f / 6.J I ^ c r a O I S T 0 P W A T C " I
| 1- — — — ——f 1 - - — - - - 1FORWARD I CURRENT ( A ) | A . £ fa.£ \s.f / J > , / I fr&f) I CURRENT METEtj
| VOLTAGE (V) \u I V 0 L T METER |
|_ 1 -| \- {-- (- -j
I SPEED (M/MIN) I ? /
BS - FT - 03
I TT5ST nJSJ^DUT~Tr'—~—~r~;—--.--- — •I " T * WfS^ 6 •••••. / / .
J PROJECT NAME | , . . . TWP-ZT CZOOU.) \ LOCATION" | O SilOP\^5> SITE+ ^ Lt*^/ClLi'lHlt'_.i^i__Zl_ l j ,
1-TART NAME | TRAVEL1.I NO (/JO.l£ : O I TEST REPORT NO |
1. TRAVELLING (NO LOAD)
I j SPKC | ACTUAL | jI MOTION 1 1 H RESULT | \ |I \jOo.l f /JU±\J06. I I JOO. i\ | |
| | SPEED (M/MTN) | / o / / o I £
BS - FT - 04
—SlIEEHNQ..... 1 / 2CHECK SHEET
PROJECT NAME LOCATION I O SFIOlN^U SITE
TART NAME | VISUAL CHECK SHEET_i
CHECK ITEM ' CHECK CONTENTS
CHECK SHEET NO|r !
[ CHECK RESULTREIMRKS
GOOD BAD
GREASEDEVICE
Grease N ipp le Check
Grease Filling Clieck
BOLTFIXING
Check Tor Connection Par t or GirderSaddle Q. £ O K
j Coupling Check (T/L)I ;
| Hand Rail Fixing Bolt Check
_ J
N/A
j{JjoaGhUE-40-54 KG-K
A
| Stopper & Saddle Stopper Touch Check1 .
STOPPER | Stopper Fixing CheckI
I I.imLI, Switch Unu:kcl; Fixing Check
• O
f-
h-!r-
Specification Check
WIRE | Twist CheckI .| Wire End Clamp Fixing Check
O
o
oCRAKE | Magnetic Drake Adjustment Check |
. j . . . . i
| Check for Appearance of Piping Parts |I (Distortion, Damage)
PI PI NG| Connector Fixing Check
Touch Chock, When Walking
O
i
| Terminal Block Check(Bolt Fixing,etc)i I . j I
| Joint Check (Press Terminal & Cable) |I I
[ Color Cap & Number Ring Using Check |
0
6 HI
HI
•HWIRING
O
o
oI Cable Check (Capacity, Core,| Appearance, Arrangement, Kind) O
BANDO MACHINERY C O . , LTD.
-M29 -
BS - FT - 05
CIIECK s3 rite E:-.r-Tf^-—-SHEET-NO.—2—/—2—- j
• 6 -
PK0.IECT NAME LOCATION . - | O SHOI'XN^S SITE |
TART NAME
CHECK ITEM
VISUAL CHECK SHEET I CHECK SHEET NO |1 , U.
CHECK CONTENTS
| . _ -f- j_
SAFETY
I CHECK RESULT |I 1 1 REMARKS1 GOOD 1 BAD I
Check for Wheel CoverO_
OI Touch Check, When T/L&T/S Operating || . i
| Warning Lamp Operating Check {SIR6W") I c
Check for i.hc other Items of Safety
I- +1
. j.
I |
(
HI
H
TEST BY j \ J-L BY
BANDO MACHINERY CO- , LTD .
-' 130 -
BS - FT - 06
-SHEET-NO.—1--/—1 - I
PROJECT NAME
T E S T K E P O R T ;
| LOCATIO'N | O S ! I O P \ ^ 3 SITE-4I
-4PART NAME MEGGER TEST | TEST REPORT NO |
-I L
1. ELECTRIC EQUIPMENT MEGGER TEST
TEST POSITIONi r"I NO || I
| 1 | POKER COLLECTOR — INPUT N . F . Bi i
I 2i
I -TH—I ih —I 5i
I r>
RATED VALUE
5MQ UP
VALUE RESULTIi
1 7I—I 8,l
INPUT N . F . B — CONTROL PANEL I 5MQ UP
1IOTSTING CONTROL PANEL — MOISTING MOTOR I HMO UP
"+•
\|
—{
HOISTING CONTROL PANEL — HOISTING BRAKE I
T/S CONTROL PANEL — T/S MOTOR I
T/S CONTROL PANEL — T/S BRAKE I
u l
T/L CONTROL PANEL -- T/L MOTOR | 5MQ UP I , I| -].jT6Oi!Zl4-.
T/L CONTROL PANEL — T/L BRAKE [
* 2. TROLLEY MEGGER TEST ( BUS - BAR )
i r
i NO I
h I1
TEST POSITION
R PHASE —- EARTH
-1
S PHASE
T PHASE
R PHASE
EARTH
EARTH
S PHASE
| RATED*VALUE j VALUE |
.+ + +| 5MO" UPi •
| 5HO UPX : . I\ *
RESULT I|
.r)MQ UP
5MQ' UP
HA
MEASUREMENT : 500V MEGGER TESTER USE
TEST BY APPROVED BY
JBANDO MACHINERY C O . , LTD.
- 131 -
BS - FT - 07
CRANK NAMK
| PACK / I
— r .
f—^ C K00a) LOCATION"
SHIJKT NO. .t / 1.
19 ?3 6 . / /
-I-O SIIO1:7 SJTK
PART NAMIJ SAFETY DKV.TCK CHI5CK CHECK SIIRIJT NO
HO. CUllCK ITEM| CIIKCK 1U7.SUJ,T ji i
J GOOD :| DAD |IU5MARKS
I
Mechruiicnl Type,Ovc>rDevice
I N/A 0% Lood Set t ing j
| K.locl.r.ic Type \ O \I — — I |I' ElecLrcmjc Typo | N/A I
Current. EcU.intf |I
HO* l.ond Sc• 4 - -I-
SeLLinj; of theRnl.nd S
An t.i c o l l i s i o n | Phol.o Sensor Typo J N/A In.-ui.-i-. l _ _ I I-
| Micro Wcivo Type | N/A |i . , i i
Out;r .Speed Delect.or Device. Opcral-ion |
- r
N/A
5i.
.S'i("«n Onoral. jou
Wtirnind Lamp OpernUnn
Stopper D'ubricat i.on
j ^ |I J.
| Q .|
7 | llrind Rai l l- 'abrieul.ion| . .
0 | Walk Way t 'abr i i-.nt. ionI -,i
D | CotipJ f.njj Cover of RuLaLidn| Ktilir vcnt.i on
_i
I o. . 1 .
](] I S'iif 'el.y D e v i c e oJ ' l l n o kt
U I Nnmcs Vl;\la of ReU-: