Upload
amirul-nazri-pmi-rmp-gpm-b-
View
1.316
Download
3
Embed Size (px)
Citation preview
Project Risk Management in Project Life Cycle/Phases
Addressing risk through Procurement
Where Project Risk Management should begin?
Engineering is most critical
Getting the most out of Construction
Addressing risk through Procurement
Where Project Risk Management is begin?
Engineering is most critical
Getting the most out of Construction
Project Risk Management in Project Life Cycle/Phases
Project Risk Management activities at Asset Owner’s level
Select Define Execute Operate
Commercial and technical concept is pinned down. Feasibility is proven by the end
Identify
RM: Preliminary Risk Identification activities
Several Conceptual options are outlined, One is selected for further development
RM: Support decision making; Decision tree Analysis
Detail study on implementation plan; define cost estimate, schedule Obtain Approval
RM: Develop RM Plan. Refine strategies Developed reserved/contingency for cost and schedule
Implemented the approve project and completed
RM: Developed Monitoring & Control Plan
Project completed and move into operation during lifetime & decommissioned
RM: Risk Register Close!
At Asset Owner’s level, Risk Management influence is high at “Identify” stage;
Identify Select Define Execute Operate
SmallLow
INFL
UEN
CE
CON
TRAC
T C
UM
U LA T
IVE
SPE
ND
Major Influence Rapidly Decreasing Influence Low Influence Zero Influence
High
Descending Trend
Contractors - Service Providers
Project Risk Management influence at Contractor @ Services Provider level …
Execute
Proposal Award for Project execution
CompletedInitiate Planning Executing
Operate
• Risk Identification, Assessment & Response plan
• Risk need to be identified as many as possible. The larger the nos. of risk, the smaller the “Unknown Unknown”
• Develop first project contingency
• Risk Register to be refine and detailed further
• Develop Risk Management Plan that focuses on implementation of Mitigation efforts , detailed project contingency
• Monitor the implementation, control, reporting & Closing
Project Risk Management influence . The trend is descending
In many cases, Project Manager is absent at proposal stage!
Monitoring
Controlling
Identify
Proposal Award
CompletedInitiate Planning Execution
Select Define Execute Execute
Focus of risk management from Strategic Asset Management down towards completion of the project
• High Level of risks identified
• Goal: To improve the value versus risk profile of the proposed asset Development
• Assessed at broader perspectives Including impacts to strategic, economic, Environment, society
• Specify Project Risk Governance and standard procedures
Assessed at project perspectives; Cost, Schedule, Quality , Safety etc.
Monitoring
Controlling
Project Risk Management influence . The trend is descending
Addressing risk through Procurement
Where Project Risk Management should begin?
Engineering is most critical
Getting the most out of Construction
Project Risk Management in Project Life Cycle/Phases
Engineering Design is the first and most critical, of the execution of a project …
ENGINEERING
Buyer purchase all equipment and materials based on “Material
Requisition” prepared by Engineer
Engineer’s design the facilities, produce the list, specifications and datasheets of all equipment and materials based on Basis Of Designs
Construction Manager to install all equipment's
purchased by Procurement
• Functional requirements• Client expectations.• Design codes
“They write a music, you guys sing the song…and dance”
Expect many interdependencies between all parties.
ENGINEERING
CLIENT
VENDOR
• Study documents such as P&IDs, Calculation notes etc.
• Interface documents showing all connections at the supply battery limits,
• Documents required at the construction site, preservation procedures, list of components, commissioning/start up operations and etc.
Document submission
Approval / comments
Document submission
Comments
• Project Management Team (Project Manager, Engineering Manager) are responsible for managing integration;
• requires timely inputs from all parties to not delay design development.
It is the most critical, typically due to the following factors that lead to risk
ENGINEERING
VENDOR
Validation/Review Cycle Time (General Uncertainty)
Design MaturityLevel of Project Novelty (General Uncertainty)
Right Resources
Including new geography and /or new technology
Adding new requirements
Scope changes
Standards / Specification Changes
Multilayer level of approvals. 21 working days as generally conditioned in the contract seems no longer practical.
“Right” defines experiences, skill sets and qualities.
Adding more resources just exacerbated the problems – longer learning curve - demotivated .
History had proven the case of Engineering related risk is high …
Source: http://www.subseaiq.com/data/PrintProject.aspx?project_id=1247&AspxAutoDetectCookieSupport=1
Facility Name: Gumusut-Kakap Floating Production Unit
Contract Award: Jan 2008 – March 2009
Schedule to come on stream : 2010
Early production: 2012 - using interim evacuation system tied into the FPSO nearby KIKEH field (FPU was not even 100% completed that time)
The project was delayed due to “DESIGN ISSUES” with the production facility and laying the new subsea export pipeline
Addressing risk through Procurement
Where Project Risk Management should begin?
Engineering is most critical
Getting the most out of Construction
Project Risk Management in Project Life Cycle/Phases
Upon finalization of Work Package development, there procurement kicks in……
• Integration with vendors start here!
1. Define requirement2. Research the market 3. Check track record 4. Invite tenders5. Evaluate tenders6. Select suppliers 7. negotiate contractual terms
• Each work package will subject to project contracting strategy of the procurement
Package Specific Risk
External Risk
Bidder Specific Risk
• In general, there 3 type of procurement risks need to be assessed in parallel of the procurement selection process.
Sources of Procurement Risk – Package Specific
• What type of contract should be proposed and why? (Cost Plus? Fixed Price?)
• What interfaces should be managed due to selected size, scope and schedule? (communication channel? Stakeholder engagement analysis?)
• What should be the optimal size , scope, schedule of the package? (Sequence of work? Scope decomposition?)
• If applicable, how should technical novelty be handled? (technological risk?)
• Are there un-usual safety hazards and how should they be managed? (LTI record? HSE Procedures?)
• Its estimated at US$4 Billions
• Production is projected at between 500 million cubic feed/day (MMcfd) – 750 MMcfd
• Key component: CPP topsides module that contains the carbon dioxide or acid gas removal unit, which is required to handle the field’s sour gas.
- The following questions should be addressed -
Sources of Procurement Risk – External
Client: ESSO HIGHLANDS LIMITED (incorporated in PNG), • JV between ExxonMobil (41.6%), Oil Search Ltd. (34.1%), Santos (17.7%), Nippon Oil Exploration (1.8%), AGL (3.6%), EDA Oil and MRDC (1.2%).
Key elements of the project construction logistics plan are as follows: Materials and equipment - enter at the port of Lae and be transported by road from Lae to Hides via
the Northern Logistics Route.
Security is a critical factor as locals don’t take to well with foreigners in their tribal territory.
• Various construction permits needed and custom regulation
• Logistic Issues (Transportation mode: Air freight etc.?)
• Possibility of blockage of delivery routes and /or sites (by local communities/NGO?)
-The “external” is not just about weather conditions or features of climates-
Sources of Procurement Risk – Bidder Specific
Bidder’s core competencies versus package size, scope and schedule
Availability of required skills and history of labor relations
Workload forecast
Quality Assurance/Quality Control, technical capabilities, management efficiency, risk management, financial and etc.
Previous experiences with a bidder (positive or negative).
-Consider the following factors -
Each type of contracts has own risk attributes.
• Minimize the risk of price changes.
• However, a contractor is likely to reduce a scope of work or change delivery
schedules to minimize the impact of overspends
• Work best for off-the-shelf products where technical risk is low.
• Useful where the technical scope is uncertain & risks unknown
• Need a greater visibility of the contractor’s detailed cost, changes and methods
As per survey done by Accenture – High Performance in Procurement Risk Management (2010).
• PRM main effort here is focus on reducing dependency by tapping a wider swathe of suppliers
• Often out of control. PRM suggest anticipating prices increases during tender development.
• While execution, re-visiting escalation clauses in the contract may appropriate.
• Establish close relationship between both parties for quality assurance and control management efforts.
• Adopt “Cost of Quality” methodologies to assessed impact on cost
Project Risk Management in Project Life Cycle/Phases
Addressing risk through Procurement
Where Project Risk Management should begin?
Engineering is most critical
Getting the most out of Construction
Engaging and Communicating with stakeholders should be the main focuses
• Each party mush have done stakeholder analysis and should have been established prior 1st steel cut or commencement of the construction activities.
• “Never too late” paraphrase is applied at any time, but in during the construction, it has price!
OwnerProject ManagerIn-house staffs
Specialists/Consultants
Design ProfessionalEngineering Team Leader
Engineering disciplinesDesign sub consultants
ConstructorConstruction Manager
Subcontractors / Fabricators
Suppliers/Vendors
• Any potential changes must be anticipated and well communicated to the other parties. Late changes is expensive and miss communication has zero validity to justify claim.
Line o
f Auth
ority
(defined
by contr
act)
Line of communication
Construction has unique problems – How should you handle these?
• The construction is a custom rather than routine
• If anything goes wrong, the non-conforming work is very difficult to rectify and remedial action is sometimes not possible. Any activity has to be done right from the onset
• the non-conforming work is very difficult to rectify and remedial action is sometimes not possible.
• Most of the projects or their individual work phase are of relatively short duration. As such, the workforce must be assemble and maintained, cannot be shaken out or restructured before the project or work phase completed.
• Operations are out door, exposed to numerous weather conditions and interruptions
• The construction often needs highly skilled craftsmen rather than unskilled workers as it involves of various installation and integration of various equipment's, materials or other components
• Construction project work against the defined scope, schedules and budget to achieve the specified result.
• Performance of construction projects can be evaluated only after it is completed and put into use/operation.
Typical project risk during construction stage, overview from project perspective
Space constraint.(General Uncertainty)
Soil failure (Risk Event)
Unauthorized change (Risk Event)
Specification non compliance(General Uncertainty)
Safety & Quality Issues.(General Uncertainty)
Productivity.(General Uncertainty)
Weather.(Risk Event)
• How the success or lack of it is monitored?
• What are warning signals?
• How will they be recognized in time for corrective action?
• What early indications will be there if serious engineering problems are imminent?
The rig then need to mobilize for a job, which the second order however is still in 3 months time.
While unutilized, who should bear the rig waiting cost?
The infil drilling works at Bokor b complete ahead of schedule
Control of Construction is all that matters.
• “Cost of Quality” should help assessed the construction cost i.e. Internal failure cost : Cost associated with defects found before partial handover (scrap, re-work, troubleshooting)External failure cost: include cost of damaging reputation, loss of opportunities, recalls, unplanned field repair)Appraisal cost: The cost incurred to determine the degree of conformance to quality requirements (lab testing, calibration)Prevention cost: Quality Planning, design review, constructability review
Constructability = “prevent is better than cure” – is it just a compliance to contract condition?
It is beneficially applied to reduce the time and cost of construction, among others:
• Planning the flow of components to their assembly site
• Providing adequate facilities and equipment for assembly.
• Avoiding of excessively tight tolerances; provision for flexibility and adjustment in connections.
• Selection of structural systems that will utilize skills and trades on a relatively continuous and uniform basis.
• Avoidance of intermittent peaks in the demand for the labor force
• Avoidance of procedures that are overly sensitive to weather conditions
• Selection of construction methods which are appropriate to the specific structure
• Concurrent fabrication of major components in the most favorable location and conditions
• Subdivision into as large components and modules as is possible for fabrication and assembly
Constructability is used during construction project planning and it involves methods to optimize the design in consideration of the effective performance of construction activities. Alternate materials, unique construction sequencing (i.e. activity logic), and construction technologies are key considerations. AACE Total Cost Management Framework, 1st Edition,2012
Any Questions?