Upload
dinhminh
View
216
Download
2
Embed Size (px)
Citation preview
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 23 Royal HaskoningDHV
3 PROJECT DESCRIPTION
3.1 The Development Framework
A broad development framework plan has been produced for the development which was approved in 2011
(Figure 1-2). The Spatial Development Framework was developed taking into account current social and
economic conditions which both Tongaat Hulett and the City seek to influence positively, informed by the need to
ensure that the development contributes to the integration and effectiveness of the City’s urban structure, form
and functioning, particularly in respect of the northern region.
The development of Cornubia is significant in that it represents a major break with the current segregated patterns
of development. In developing Breaking New Ground, National Government sought to respond to a number of
significant challenges affecting housing delivery, including the fact that the inequalities and inefficiencies of the
apartheid space economy continue despite government’s commitment to developing more liveable, equitable and
sustainable cities through the pursuit of more compact urban form, higher densities, mixed land use development
and integrated land use and transport planning.
The Development Framework of Cornubia responds powerfully to the key challenges and policy thrusts
articulated by National Government. It provides for a higher density, mixed-use and mixed income development
that significantly responds to housing demand across a broad spectrum of market segments. In achieving the
proposed densities, housing typologies offering enhanced housing design, are being investigated and developed,
the nature of which are such that there is increased possibilities of local integration and hence developing a more
functionally balanced housing market in the northern metropolitan area.
This conceptual framework provides a basic indication of the developers land use intention on the site. The
framework plan should not be seen as the definitive layout or final approved plan for the development, but should
only be used to create an understanding of the conceptual framework for the ultimate development of Phase 2.
This EIA process will confirm if there are any fundamental issues to preclude the proposed development from
proceeding along the broad, conceptual basis as outlined in the Framework and will also deal with the
assessment of the detailed, specific issues and impacts on a micro level.
3.2 The Phase 2 Project
The development being assessed for approval is a 964 hectare site which represents 75% of the total land area of
Cornubia (Figure 3-1).
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 24 Royal HaskoningDHV
FIGURE 3-1: CORNUBIA PHASE 2 LOCATION AND BOUNDARY
Based on the Development Framework, approximately 630ha of the site is developable with 360ha comprising of
open space which includes wetlands, buffers, floodplains, steep slopes, etc. The broad development framework
plan for Phase 2 is as follows:
Approximately 22 000 residential units of which approximately 12 000 units will be low cost subsidised
housing and 10 000 affordable middle-income units;
Provision for appropriate social facilities including fire station, police station, schools, clinics, halls;
60 hectares of industrial platform;
800 000 square meters for bulk – commercial and mixed use;
Rehabilitated open space of approximately 330ha;
New road infrastructure;
Construction of appropriate stormwater features;
Construction of sewer reticulation and its associated bulk gravity trunks; and
A number of wetlands road and services crossings.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 25 Royal HaskoningDHV
Key elements of the development include:
Mix of land uses as above including specific components of low cost housing (referred to as BNG – Breaking
New Ground units) as well as affordable housing and market based housing opportunities;
Community facilities such as schools, clinics, etc;
Use of wetlands and buffers for recreational purposes; and
The installation of general engineering services and infrastructure which include:
Water supply;
Sewage;
Electricity supply;
Stormwater management;
Roads and access; and
Telecommunications.
3.3 Site Context and Zoning
Cornubia is located within the North Urban Development Corridor as defined in the North Spatial Development
Plan. It lies approximately 25km from the Durban CBD and sits adjacent to Umhlanga in the east, Mount
Edgecombe in the south, Ottawa in the west and Waterloo in the North. The site is strategically located along the
axes of the M41 and N2 (Figure 3-2). The study area has prime visibility and potential connectivity to these major
systems. In addition, being closely aligned to the R102 and inland development axis, ensure potential for
metropolitan exposure and connectivity. The site is currently unzoned.
FIGURE 3-2: SITE CONTEXT
Umhlanga CBD
Durban CBD
North Coast
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 26 Royal HaskoningDHV
The Cornubia Project is located within the eThekwini Magisterial District, KwaZulu-Natal and of numerous
subdivisions or land parcels (Figure 3-3). Below is a list of properties located within the Phase 2 site:
TABLE 3-1: LIST OF PROPERTIES AND LAND OWNERS
PROPERTY DESCRIPTION SG 21 DIGIT CODE
OWNED BY THD
Ptn 50 (of 8) of the Farm Lot 31 No 1560 N0FU00000000156000050
Rem of Ptn 4 of the Farm Lot 31 No 1560 N0FU00000000156000004
Ptn 57 (of 21) of the Farm Lot 31 No 1560 N0FU00000000156000057
Rem of Ptn 16 of the Farm Lot 31 No 1560 N0FU00000000156000016
Rem of Ptn 21 of the Farm Lot 31 No 1560 N0FU00000000156000021
Ptn 5 of the Farm Lot 31 No 1560 N0FU00000000156000005
Rem of Ptn 15 of the Farm Lot 31 No 1560 N0FU00000000156000015
Rem of Ptn 6 (of 4) of the Farm Lot 31 No 1560 N0FU00000000156000006
Rem of Ptn 8 of the Farm Lot 31 No 1560 N0FU00000000156000008
Rem of Ptn 14 of the Farm Lot 31 No 1560 N0FU00000000156000014
Rem of Ptn 13 of the Farm Lot 31 No 1560 N0FU00000000156000013
Rem of the Farm Lot A 39 No 1532 N0FU00000000153200000
OWNED BY eTM
Ptn 2 of the Farm Lot 21 No 1529 N0FU00000000152900002
Ptn 8 of the Farm Lot 21 No 1529 N0FU00000000152900008
Ptn 9 of the Farm Lot 21 No 1529 N0FU00000000152900009
Ptn of Rem of the Farm Lot 20 No 1557 N0FU00000000155700000
Ptn of Rem of Ptn 1 of the Farm Lot 20 No 1557 N0FU00000000155700001
Ptn 7 of the Farm Lot 21 No 1529 N0FU00000000152900007
Ptn 4 of the Farm Lot 21 No 1529 N0FU00000000152900004
Ptn 3 of the Farm Lot 21 No 1529 N0FU00000000152900003
Ptn 11 of the Farm Lot 21 No 1529 N0FU00000000152900011
OWNED BY SASA
Rem of Erf 142 Mount Edgecombe N0FU02170000014200000
Ptn 1 of the Farm Lot 21 No 1529 N0FU00000000152900001
Ptn 2 of the Farm Lot 21 No 1529 N0FU00000000152900002
Rem of Portion 17 Mt Edgecombe N0FU02170000000000017
Portion of Rem of Portion 15 Mt Edgecombe N0FU02170000000000015
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 27 Royal HaskoningDHV
FIGURE 3-3: CORNUBIA FRAMEWORK AND CADASTRAL BOUNDARIES
3.4 Project Motivation
The location of the Cornubia Project is ideally positioned for THD together with the eTM to ensure that the
following key objectives can be achieved:
Make a key contribution to building, consolidating and integrating the social and economic base of the
northern portion of eThekwini;
Ensure a sustainable mixed use, inclusionary mixed income development that maximises economic
opportunities for future residents and investment;
Create value by maximising the potential of the land through public-private partnerships so that the
development of the land delivers a positive and a balanced economic, environmental and social return that is
both financially sustainable and contributes to redressing inequalities;
Position both Tongaat Hulett and eThekwini as leaders, innovators and promoters of integrated visionary
planning and development; and
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 28 Royal HaskoningDHV
To use the opportunity for creating substantial black economic empowerment opportunities in property
development ownership and urban management.
Aside from the above mentioned key objectives of the proposed project there are three other motivating factors
that rationalises the need for the Cornubia Mixed Use Phased Development. These are:
Location - the location of Cornubia provides an opportunity to strengthen and consolidate the northern sub-
region of eThekwini as well as providing peripheralised communities access to the benefits of a growing
urban node. Furthermore, Cornubia can complement and enhance the value of public sector investment in
new developments such as the Dube Tradeport. Lastly, the projects can assist to address the legacy of
apartheid planning;
Economic Growth - the Cornubia Project intends to address the City and Province’s competitiveness through
its significant potential to deal with the scale and rated of the release of land for much needed industrial,
commercial and residential development. Furthermore, the project offers significant opportunities to create
new, well located employment opportunities close to new and existing housing and to focus on demand in the
subsidised, gap and middle income housing markets; and
Scale - the scale of the Cornubia Projects allows for the development of environmentally and financially
sustainable innovations in service and housing delivery models. In addition, the project will facilitate new
forms of urban development, choices and lifestyle options previously not available to these markets.
3.4.1 Strategic Importance
Cornubia is a bold undertaking by both THD and eTM and sets out the commitment to the national ideals, as well
as defining and creating benchmarks for similar initiatives. The project aims to apply, leverage, assemble, and
systematically align multiple institutional, financial, human and managerial resources, in a creative and innovative
manner, covering aspects such as - informal settlement eradication, inter-and intra-settlement integration, urban
restructuring and renewal, densification, tenure diversification, improved settlement design, better quality shelter,
poverty eradication, and greater responsiveness to livelihood strategies. These are key components of Cornubia
and relate directly to the strategic activities of Government, its constitutional obligations and the priorities of
creating a better life for all. The very nature of the Cornubia project is of a highly integrated and collective effort.
The development of Cornubia is strategically important for the reasons set out below:
It presents an important opportunity to address the integration of the City and the imbalances of apartheid
planning, consolidating and integrating the currently dispersed and dislocated points of urban development in
the region. It does so by contributing significantly towards the development of the Northern Corridor,
enhancing the development opportunities along the R 102, and through the potential to create connections
and links to Umhlanga, Phoenix, Waterloo, Verulam and the Dube Tradeport as well as to the broader urban
system that extends to areas such as Pinetown, Bridge City, Inanda and KwaMashu.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 29 Royal HaskoningDHV
The area in which Cornubia is located is identified in the Integrated Development Plan (IDP) as part of a
major economic investment node. The proposed development of Cornubia presents a significant opportunity
to attract new investment to this area by releasing land to meet the significant demand for well-located
industrial and commercial land being generated as a result of the increased economic growth rate of the
metropolitan economy.
The development will create substantial new job and employment opportunities, particularly for residents of
areas such as Phoenix, Verulam and Waterloo where work opportunities close to places of residence, as a
consequence of apartheid planning, are currently lacking.
It represents an important opportunity for substantial new residential development, significantly addressing
demand for affordable housing and integrated residential developments that are well located in terms of
access to employment opportunities, urban amenities and social facilities.
The development will provide a benchmark for mixed-income, mixed use development in line with the policy
objectives of National Government’s new housing policy, Breaking New Ground. As a result, the development
can make an important contribution to the realisation of the City’s vision of being Africa's most liveable city.
3.4.2 Integrated Development Plan and Spatial Development Framework
Durban’s Spatial Development Framework (SDF), as established through the Integrated Development Plan (IDP)
process, firmly seeks to reinforce the development intensification and improved functioning of the existing “T”
shaped development areas. The SDF depicts the thrust of the IDP indicating the eTM investment intentions and
development management approach.
It is suggested that the SDF will respond to key spatial drivers that will determine investment within Durban.
Umhlanga is considered as an urban investment opportunity and is located strategically along the existing “T”
axes. The SDF acknowledges a northward investment thrust to accommodate the Dube Trade Port as a key
spatial driver in the Northern Region. The SDF identifies Cornubia as an investment opportunity area and is
located within the defined Urban Development Corridor.
In terms of eThekwini’s IDP, the Cornubia site it is situated within the urban edge/boundary of the City, in one of
the three “zones of planning”, the “urban core”, which is intended to be characterised by well-resourced
development, with high density urban form and high value infrastructural investment. The project will be grounded
in the principles of the City’s IDP, and will specifically articulate the following programmes identified in the plan:
New subsidised housing;
Integrated neighbourhood interventions;
Community empowerment and development;
Job creation;
Enterprise development;
Good governance; and
Environmental management.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 30 Royal HaskoningDHV
3.4.3 Northern Spatial Spine
One of the key objectives of the Northern Spatial Development Plan is to redress past imbalances and build for
the future by responding appropriately to future needs and anticipated growth patterns and trends. To this end,
the R102 and the M41 have been identified as a Metropolitan spine and Sub Metropolitan spine respectively. The
purposes of these spines are to promote the efficient and effective linkage between rural and urban areas across
the metropolitan areas as well as the provision of high density opportunities in close proximity to the public
transportation routes.
The Northern Spatial Development Plan suggests the following for Cornubia:
The establishment of Cornubia as a new local node;
The creation of new mixed use with housing densities along the R102 development spine in the region of a
minimum of 40-60 du/ha;
Establish new mixed medium and high density residential in undeveloped zones;
Create industrial opportunity in Ottawa Flats; and
Protect open space assets.
3.4.4 Northern Urban Development Corridor and Verulam/Cornubia Local Area Plan
As part of the innovative package of plans approach adopted by the Municipality, Local Area Plans (LAP) have
been developed for the Northern Urban Development Corridor – the subregion between KwaMashu and Tongaat
to the west of the N2.
The NUDC “…is to be developed as a mixed used development corridor that will consolidate existing and
anticipated future population and economic growth in the northern metropolitan area in a spatial pattern that
reinforces the new airport node as an internationally competitive Aerotropolis whilst simultaneously establishing
and/or enhancing the roles and characteristics of established and/or new development nodes, spines and
neighbourhoods”.
In terms of the Verulam/Cornubia LAP, the primary roles envisaged for Cornubia include:
New Town to accommodate local mixes use, mixed density and mixed income urban living areas – with
densities of between 80 and 150 dwelling units per hectare;
New local light industrial node;
Establishment of part of the new north-south multi modal transit oriented development spine connecting
Phoenix-INK and the metro HPPTN to the Airport and Dube TradePort; and
Protection of the environmental roles of the Ohlanga River systems.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 31 Royal HaskoningDHV
3.5 Development Objectives and Principles
The above spatial informants were taken into consideration during the development planning process for
Cornubia which has the potential to deliver on a range of current metropolitan development objectives given its
scale and strategic location. The following are considered the core objectives:
District Integration: the site represents a strategic opportunity to ‘knit’ together previously separated areas
influenced largely though the imposition and apartheid heritage. Key in this is fostering improved linkage and
integration between the surrounding communities of Phoenix, Mt Edgecombe, Umhlanga, Waterloo and
Ottawa. A key development objective is therefore improved physical integration.
Pursuing Integrated Human Settlement: given the relative unencumbered scale and Greenfield opportunity,
Cornubia represents a significant opportunity to ‘get the basics right’ in terms of achieving integrated
settlement. The core objective here is ensuring that a ‘complete and liveable’ environment is created within
which a range of economic and social opportunities are integrated with the provision of housing.
Ensuring Sustainability: whereby the many facets of sustainability are considered carefully in the
establishment of Cornubia. A key concern here is moving the sustainability agenda further than the ‘green
agenda’. The core objectives here are establishing a framework, management and delivery systems that
embrace all aspects of human settlement, the natural, social and economic environments.
Building a Dynamic Region: based on the strategic location of Cornubia within the northern development
corridor, a key objective is responding to, drawing from and growing the energy within the larger urban and
particularly economic logic of the region. New opportunities that contribute to the broader economic
competitiveness needs to be considered within the planning for Cornubia.
Strengthening the Regional Logic of Space: an important defining quality of the site is the natural
environment. This includes at a regional scale the Ohlanga River which forms an important edge of the site,
the unique landform of the site, as well as the local valley systems within the site. A key objective therefore is
the potential to enhance the regional lattice of open space opportunity and connectivity.
Informed by the development objectives, the following are considered the key principles and development
philosophy for Cornubia:
Access and Structure: a key design principle at the level of the framework and at a local neighbourhood is the
need to facilitate easy access, choice and convenience. At the larger framework scale, it is envisaged that a
series of ‘framework routes’ would facilitate connectivity to the surrounding area and their respective
opportunities. Equally, at a local scale, it is imperative that a robust structure is established which enables
permeability and choice.
Density and Compactness: encouraging density and compactness of settlement is a key design principle for
Cornubia as these qualities provide the preconditions and threshold to support urban opportunity and choice.
Diversity and Complexity: encouraging complexity through missed use and intensification is critical in
delivering environments that offer choice and convenience. A key design objective within Cornubia is ensuring
that a wide range of urban functions are catered for within the framework. This would ensure that future
residents can access a ‘fuller’ set of urban opportunities within close proximity.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 32 Royal HaskoningDHV
High Quality Urbanism: the timeless qualities of high performance built environments much be sought within
Cornubia. A clear departure from conventional housing provision premised on suburban models and patterns
is a firm goal of the project. The critical interplay between form and space, between building and street,
between the built and un-built are important concerns of the development approach.
Meeting Local Needs Locally: the structure of Cornubia should facilitate easy access to local needs for future
residents. A key design objective is ensuring walkability by locating facilities and convenience retail within
local neighbourhoods. At the same time, these facilities should not be embedded within the urban fabric but
should be externalised and contribute to a sense of local structure and legibility. Therefore, establishing local
centres in places that are connected to the wider system is important.
Public Transport and Non Motorised Transport Focus: given the thresholds targeted for the area, it is possible
to achieve the required support for viable public transport. This would not only ensure that a longer term
sustainability focus underpins development, but would maximise local convenience and accessibility. Non
motorised transport would be viable given the density and structure sought for Cornubia.
Access to Open Space: creating a complete environment requires access to a range of landscapes including
natural and recreational. Therefore a key design objective for Cornubia is developing an integrated open
space system as part of the overall urban fabric. The existing valley and wetland systems provide an
important starting point in this regard. Through additional ‘green’ linkages a lattice of opens space opportunity
can be created within Cornubia. It is imperative that the establishment of the open space sis undertaken in a
manner that contributes positively to the overall environment in terms of natural resources and residential
amenity.
Public Space and Facilities: a primary goal is ensuring that a complete and liveable environment is created. A
key ingredient to achieve this is ensuring that adequate provision is made for public facilities and developed
public space.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 33 Royal HaskoningDHV
4 PROJECT ALTERNATIVES
In terms of the EIA Regulations, Section.28 (1) (c) feasible alternatives are required to be considered as part of
the environmental investigations. In addition, the obligation that alternatives are investigated is also a requirement
of Section 24(4) of the National Environmental Management Act (Act 107 of 1998) (as amended). An alternative
in relation to a proposed activity refers to the different means of meeting the general purpose and requirements of
the activity (as defined in Government Notice R.543 of the EIA Regulations, 2010), which may include alternatives
to:
the property on which or location where it is proposed to undertake the activity;
the type of activity to be undertaken;
the design or layout of the activity;
the technology to be used in the activity; and
the operational aspects of the activity
the option of not implementing the activity
4.1 Site Alternatives
No offsite or other site alternatives have been investigated due to the fact that this is the closest, existing large
parcel of land to the existing built up areas of the city and which can integrate naturally and positively into this
existing fabric. The development, as noted above, has a number of and wide variety of objectives to meet and
such objectives would not be possible to achieve if the development was attempted elsewhere. Furthermore,
eThekwini Municipality have purchased land within the Cornubia site for housing purposes and as such require
developing them towards meeting their objectives of housing those people who are not able to house themselves.
As noted in Section 3 above, the Development Framework has been based upon a number of, in essence,
existing constraints including wetlands and river, roads and rail line, noise contours, topography and limited
access and linkage opportunities. As such there is limited scope for alternatives related to the primary structure of
the framework plan. Without doubt each and every potential access opportunity has been utilised together with
identifying potential new linkages to existing and future development in the region.
It is therefore submitted that the Development Framework structure is sound and, critically, delivers upon the
strategic objectives that have been identified by both Tongaat Hulett Developments and the eThekwini
Municipality. Furthermore, it is noted that the two parties have spent a considerable amount of time and effort in
the planning and contextualisation of the development and there is broad acceptance that the development
framework plan (at a principle level at least) is appropriate and will add value to the region and enable the
Cornubia development to fulfil its regional responsibilities, objectives and mandate. This is illustrated by the
acceptance of the Development Framework by DAEA in 2011.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 34 Royal HaskoningDHV
During the detailed design process for Phase 2, there may well be slight adjustments to road alignments etc. and
the final land use details will also be resolved through the EIA process.
4.2 Land Use Alternatives
4.2.1 Alternative 1 (Preferred)
The creation of a broad range of uses in a compact city type of form, that seeks to enable the creation of a
“sustainable city” with higher densities, employment, commercial, recreational and social facilities. Cornubia is
located immediately to the west of one of eThekwini’s major economic investment nodes, Umhlanga. In terms of
eThekwini’s Integrated Development Plan (IDP), it is situated within the urban edge/boundary of the City, in one of
the three “zones of planning”, the “urban core”, which is intended to be characterized by well-resourced
development, with high density urban form and high value infrastructural investment. The site is currently unzoned
and under commercial sugar cane production by Tongaat Hulett. It currently has no development rights, and
accordingly, a full township establishment process will have to be initiated to secure development rights. This is
the preferred land use.
4.2.2 Alternative 2
Alternative 2 would be focused upon different land use mixes – solely residential or a significantly reduced
commercial component, solely commercial or significantly reduced residential component or a much lower
residential density. Alternatives that include solely commercial and/ or industrial land uses have however been
discounted due to the eThekwini Municipality’s need to provide housing and the fact that sustainable cities need
to provide a broad mix and range of uses and encourage and design for closer living-working relationships.
4.3 Operational Alternatives
Tongaat Hulett and eThekwini Municipality are committed to ensuring that the development is sustainable and
adheres to stringent environmental management procedures. With this is mind, operational methods and
approaches must adhere to best-practise alternatives, which this EIA process seeks to achieve. The EIA phase
will seek to establish best-practise approaches for the following:
Water management;
Land management;
Waste management;
Air quality management;
Rehabilitation and closure.
These aspects will be specifically detailed in the Environmental Management Programme.
4.4 No-go Alternative
This option involves retaining the existing land use – agriculture. The property would remain under cane, and
would continue to operate as a working sugar cane farm.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 35 Royal HaskoningDHV
This is a mixed use development that entails a huge component for housing; as such the no-go alternative will
prevent all the positives that can be associated with housing developments as well as for economic growth. This
option does not facilitate integration nor does it address the housing backlog and opportunity to redress the
spatial planning imbalances of apartheid.
The no-go option for a development in terms of the spatial framework plan will limit the opportunities within the
Municipality in providing housing to a community in dire need of appropriate housing with “proper” services.
Government is committed to solving the housing crisis but it requires Greenfield land to deal effectively with this
and Cornubia represents a unique, strategic opportunity to make a significant dent in the housing backlog. The
location of Cornubia within the broader region is such that housing will be extremely well located for easy access
to employment and urban amenities – in stark contrast to traditional low cost housing developments that have
historically been developed on the periphery of the city at huge costs – not only from a servicing perspective but
from a living perspective.
The location and situation of Cornubia also dictates that it be appropriately and sustainably developed to uses
and activities which offer the best value, returns and benefits to the city.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 36 Royal HaskoningDHV
5 GENERAL DESCRIPTION OF THE STUDY AREA
BIOPHYSICAL
5.1 Climate
The Cornubia area is coastal with a summer rainfall and a warm humid climate throughout the year. No frost
occurs within the project area and is thus ideal for most crops including sub-tropical crops.
TABLE 5-1: CLIMATE DATA FROM SASA EXPERIMENT STATION, MOUNT EDGECOMBE
TMX TMN DBA WBA RHA DBP WBP RHP SUN RAIN EVP WND
ºC ºC ºC ºC % ºC ºC % h mm mm/d km/d
Jan 27.3 19.7 23.8 21.0 77.3 26.2 22.2 69.9 6.0 126.7 5.6 163.9
Feb 27.5 19.9 23.7 21.2 79.5 26.6 22.6 69.9 6.4 122.0 5.4 152
Mar 27.0 19.3 22.7 20.5 80.9 26.0 22.0 69.4 6.6 105.1 4.6 136.9
Apr 25.6 16.7 20.3 18.2 80.8 24.6 20.3 66.2 7.0 67.1 3.7 114.7
May 24.2 13.7 17.3 14.9 75.9 23.2 18.2 60.6 7.3 50.7 2.9 94.9
Jun 22.7 11.4 14.4 11.6 69.8 21.7 16.0 53.6 7.4 30.9 2.5 90.7
Jul 22.4 11.1 14.2 11.4 70.6 21.4 15.7 53.8 7.5 31.5 2.7 101.4
Aug 22.8 12.3 16.0 13.4 74.1 21.7 16.6 58.6 7.0 40.2 3.2 128.9
Sept 23.3 14.4 18.4 15.7 74.8 22.0 17.7 64.4 6.0 65.8 3.8 156.7
Oct 24.1 16.2 20.2 17.3 74.1 22.6 18.6 67.7 5.6 93.5 4.4 178.0
Nov 25.2 17.7 21.9 18.8 74.0 23.7 19.9 69.8 5.6 107.6 4.9 177.6
Dec 26.6 19.1 23.3 20.3 75.1 25.2 21.3 70.0 5.9 115.0 5.5 170.3
Mean 24.9 16.0 19.7 17.0 75.6 23.7 19.3 64.5 6.5 79.7 4.1 138.8
Legend:
TMX Maximum temp WBP Wet bulk 14:00
TMN Minimum temp RHP Relative humidity 14:00
DBA Dry bulb 8:00 SUN Sunshine hours
WBA Wet bulk 8:00 RAIN Rainfall
RHA Relative humidity 8:00 EVAP A-pan evaporation
DBP Dry bulk 14:00 WND Wind run
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 37 Royal HaskoningDHV
5.2 Geology, Soils and Topography
The following information has been extracted from the Preliminary Geotechnical Assessment undertaken by
Drennan, Maud and Partners.
5.2.1 Statigraphy
The geological formation present within the area is provided below:
TABLE 5-2: GEOLOGICAL FORMATIONS
Alluvium/Colluvium Unconsolidated sandy and clayey soils
Berea-type Red Sand unconsolidated reddish brown clayey sands and sand clays and derived
grey sand
Karoo Dolerite (intrusive) Dolerite
Vryheid Formation Shales and sandstones
Pietermaritzburg Formation Shales
5.2.2 Occurrence and Distribution
The Pietermaritzburg Formation shale occurs only in the lower generally gently sloping north-western potion of
the area. The central and eastern portions of the area, as well as its south-western portion, which is the majority
of the area is underlain by the Vryheid Formation with its frequent subaccordant intrusions of Karoo dolerite
sheets of varying thickness. The Berea-type red sand only occurs as a capping of the bedrock Vryheid Formation
in the south-eastern corner of the area. Generally sandy alluvium occurs along the flood plain of the Ohlanga,
while clayey colluvium generally of several metres depth occupies the bottoms of the stream valleys in the area in
question.
5.2.3 Soil Forms
The soils occurring in the area were classified according to eh S.A soil Taxonomy (1991) and are as follows:
TABLE 5-3: SOIL FORMS AND RELATIONSHIP TO GEOLOGY
GEOLOGICAL
FORMATION
SOIL FORM S.A
SOIL TAXONOMY
SOIL DESCRIPTION
Colluvium Katspruit
Rensburg
Shallow to deep, dark grey to black, sandy and silty clay
(hydromorphic)
Alluvium Dundee
Oakleaf
Moderately deep to deep greyish brown stratified sand and silty
sand (in places hydromorphic)
Berea-type Red Sand Hutton
Fernwood
Moderately deep to deep reddish and greyish brown sand and
clayey sand and grey sand.
Karoo Dolerite Shortlands Shallow to moderately deep reddish brown (Shortlands) and dark
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 38 Royal HaskoningDHV
GEOLOGICAL
FORMATION
SOIL FORM S.A
SOIL TAXONOMY
SOIL DESCRIPTION
Colluvium Katspruit
Rensburg
Shallow to deep, dark grey to black, sandy and silty clay
(hydromorphic)
Arcadia grey to black (Arcadia) silty clay soils.
Vryheid Formation Mispah
Milkwood
Swartland
Kroonstad
Very shallow (Mispah) to moderately deep dark greyish brown
sandy clay to clay soils.
Pietermaritzburg
Formation
Mispah
Milkwood
Very shallow (Mispah) to moderately deep dark grey clay soils.
The clayey valley-bottom soils of colluvial origin are generally characterized by shallow or surface water table
conditions, seasonally at least. The sandy alluvial river flood soils are generally not so affected though occasional
flooding of them during major flood events is possible.
Shallow water table conditions, except for very localized perching, are not normally present in the deep well
drained soils of the Berea-type red sand.
Dark grey or black clayey soils of the Arcadia soil form, as opposed to the normal reddish brown Shortlands soil
form developed thereon, are present on the Karoo dolerite mainly in the south-western potion of the area in
question.
Soil distribution on the major potion of the area that is underlain by the shales and sandstones of the Vryheid
Formation can be very complex with clayey soils developed on the shales occurring in an intimate relationship
with the less widely occurring more sandy sandstone-derived soils.
On steep eroded slopes and on the crest of the central ridge in the area, very shallow soils, and even weathered
rock outcrops, are very frequently present on the shales of the Pietermartizburg Formation, the shales and
sandstones of the Vryheid Formation and the intrusive Karoo dolerite.
5.2.4 Topography
The area comprises a central southwest to northeast-trending broad ridge whose top approximates an elevation
of some 150 m above msl. To the north and northwest after an initial steep fall from the ridge tops the land slopes
moderately to gently to the Ohlanga River, while to the south after an initial similar steep fall, the land falls
moderately to the southern boundary of the area. Elevation along the Ohlanga River rises from about 10m above
msl on the north eastern boundary of the area to about 30m on its north western boundary. On its southern
boundary elevation ranges from about 120m in the southeast corner of the area to about 80m in its southwest
corner. Narrow fairly deeply incised stream valleys rising on the central elevated ridge of the are have dissected
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 39 Royal HaskoningDHV
the northern potion of the area below the ridge into a number of generally northwards trending interfluve r idges, a
similar though less pronounced situation existing on the southern side of the central ridge, the stream valleys here
being broader and less deeply incised between the adjoining ridges.
5.3 Agricultural Potential
The following information has been extracted from the Agricultural Potential Study of Cornubia undertaken by
Mottram and Associates cc.
Cornubia was formerly part of Blackburn Estate, which in turn was part of the Natal Sugar Estates. This property
has been producing sugarcane for decades and is regarded as on the better sugar estates in the industry.
5.3.1 Climate
The site is characterized by a coastal climate with a summer rainfall and a warm humid climate throughout the
year. No frost occurs in these areas. The climate is ideal for most crops including subtropical crops. This area Bio
Resource Unit (BRU) has a climatic capability rating of C1, with little or no limitations for crop production. For the
purpose of determining crop water requirements, effective rainfall is taken as 80% of the total rainfall. The rainfall
distribution and the corresponding temperatures verify the area experiencing a summer rainfall and warm humid
conditions through all seasons. Crop evaporation is significantly less than evaporation measured from a Class-A
evaporation pan, so far planning purposes subtracting 20% will provide a practical estimate. If perennial crops are
to be produced under optimum conditions then supplementary irrigation is essential. Due to the terrain and
proximity to the coast these areas experience windy conditions, predominately from the NE and SE.
5.3.2 Terrain
The entire area varies from gentle slopes on the top areas of the project area to steeper slopes leading down to
the Ohlanga River. There are a few ‘river lands’. The upper areas are exposed with respect to wind, whereas the
lower areas will have some protection from northerly ‘berg’ winds and from the coastal easterly and south easterly
winds. The drainage lines of the area run in all directions.
5.3.3 Current Situation
Most of the arable land is under sugarcane production. With the exception of 35ha under overhead irrigation, all
production is under dryland (rainfed) conditions. Three sugar cane varieties are being cultivated namely, 376, N27
and N12. The mean 14 month yield being achieved is 84 tonnes cane per hectare with an RV of 11.4. The annual
yield being 72t ha-1. The irrigated yields being achieved are >120 t cane ha-1 with sucrose contents above
13.6%. Whilst the mill was operating 120ha was being irrigated with mill effluent. During site visits this area was
experiencing extremely dry conditions as a result of El Nino and effects of cyclones off Mozambique and
Madagascar. This accounted for the poor looking sugarcane. There exist a very good infrastructure with respect
to buildings, roads, equipment and staff. All equipment appeared in a good well maintained condition, which is
indicative of good motivated management.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 40 Royal HaskoningDHV
5.4 Vegetation and Fauna
The proposed site for development currently has limited biological diversity and is considered, from a vegetative
perspective, to be highly degraded. Alien vegetation that currently exists on site is the single biggest concern that
faces the proposed development of conservation areas and linkages between different fragments.
Alien vegetation has a very serious and negative impact on vegetation as well as land usage and the ecological
functioning of systems. There are a number of negative impacts that are directly related to the presence and
abundance of alien vegetation namely:
Increased erosion potential,
Loss of biological integrity,
Reduced functioning of ecosystems,
Ability to spread and rapidly colonise new areas previously not infested,
Competition with indigenous plant species for resources in particular, nutrients, light and water.
Currently three fragments of vegetation exist that are relatively well preserved in terms of their existing species
assemblage and have not been impacted upon as severely by alien invasives as have the remainder of the
fragments.
The alien species that are currently of most concern, as they are the most abundant and well represented across
the site are Litsea glutinosa, Eucalyptus grandis, Schinus terebinthifolius, Tecoma stans, Ipomoea purpurea and
Chromolaena odorata. The other species that is of major concern, but was only recorded in two areas is Rivina
humilis.
There are a number of areas that are of conservation importance, in terms of fauna, on the site. As faunal
distributions are inextricably linked to vegetation structure, quality and the disturbance co-efficient, the sensitive
areas are discussed in terms of the vegetation zones present on site.
5.5 Water Resources
5.5.1 Regional
The Cornubia Projects fall within the Mvoti to Mzimkulu Water Management Area and specifically within the Mgeni
Key area and Mdloti & Tongati Key area. The responsible water authority for the catchment and sub-catchment of
the project area is the DWAF, KZN Region.
5.5.2 Local and Surface Water
The site is primarily planted to sugar cane, with the exception of the most prevalent drainage lines and areas of
permanent wetland, or where soil or topography is unsuitable for sugar cane production. Within the Cornubia
Project area is the perennial Ohlanga River. Figure 5-1 indicates the Ohlanga River where it passes under the N2
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 41 Royal HaskoningDHV
highway. This picture was taken during the dry period when flow was minimal. The oHlanga river and estuary is
situated immediately north of the coastal resort town of Umhlanga approximately 20 km north of Durban. The
lower part of the estuary was proclaimed as an additional part of the Umhlanga Lagoon Nature Reserve in 1986
and includes the surface area of the lagoon up to the high water mark of the river, seaward of the provincial main
road and up to the high water mark of the Indian Ocean. In addition, there are a number of wetlands present on
the site (Figure 5-2).
FIGURE 5-1: OHLANGA RIVER ON CORNUBIA
5.6 Mining Reserves
The Phase 2 development area includes a small portion of clay (Corobrik) reserves which are located primarily in
the noise contours.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 42 Royal HaskoningDHV
FIGURE 5-2: CORNUBIA FRAMEWORK WITH WETLANDS ON THE SITE
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 43 Royal HaskoningDHV
SOCIAL
5.7 Noise Considerations
Noise levels must also be considered in the development of Cornubia and for this reason, cognisance of noise
contours has been taken in the development of the Cornubia Framework Plan.
5.8 Socio-Economic Profile of the Receiving Environment
The receiving area includes areas surrounding the Cornubia site which will be part of the impact zones. Cornubia
is immediately surrounded by nine quite distinct “suburbs”, reflecting an extremely diverse range of socio-cultural
views, economic baselines and consequently, expectations.
The Phase 2 site is located in Ward 102 and is situated in close proximity to Wards 35, 48, 49, 50, 51, 58 and 60,
and given the size of the proposed development, and its proximity to the new development of the Dube Trade
Port and King Shaka Airport, the impacts of the development will ripple out to the secondary areas surrounding
the site. The following zones of impact were identified:
FIGURE 5-3: ZONES OF IMPACT
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 44 Royal HaskoningDHV
From a socio-economic perspective it is anticipated that the Cornubia Project has an overall positive impact on
the affected ward areas by:
Spatial integration – the site is ideally located to connect the areas of Verulam, Phoenix, Ottawa, Umhlanga,
the King Shaka Airport and the N2 corridor (north and south);
Job and business opportunities – currently there are high levels of unemployment in the affected wards and
with this project there is the opportunity to provide employment not only during the construction phase but
beyond this phase as jobs will be created in retail facilities and the industrial area;
Housing – the project aims to ease the housing shortage in Durban and surrounding areas by providing
affordable housing;
Infrastructural improvements – provide important transport connectors and other improvements to adjacent
areas;
Revenue for the city – it is estimated that the project could result in a rates revenue of approximately R207
million per annum;
Shopping and retail facilities – additional facilities would benefit the poorer surrounding communities who
would have easier access to them;
Industrial and business estates – the increase in economic activity in Durban has resulted in increased
pressure on existing industrial business estates. As a result of the project locality and its accessibility to
transportation routes this would encourage growth and development of industrial and business estates; and
Leisure and recreational – the design and management of the open green space within the Cornubia site
could contribute to providing the poorer communities with access to leisure and recreational facilities.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 45 Royal HaskoningDHV
6 PUBLIC PARTICIPATION PROCESS
Public participation is a process that is designed to enable all interested and affected parties (I&APs) to voice their
opinion and/ or concerns which enables the practitioner to evaluate all aspects of the proposed development, with
the objective of improving the project by maximising its benefits while minimising its adverse effects. I&APs
include all interested stakeholders, technical specialists, and the various relevant organs of state who work
together to produce better decisions. The primary aims of the public participation process are:
to inform interested and affected parties (I&APs) and key stakeholders of the proposed application and
environmental studies;
to initiate meaningful and timeous participation of I&APs;
to identify issues and concerns of key stakeholders and I&APs with regards to the application for the
development (i.e. focus on important issues);
to promote transparency and an understanding of the project and its potential environmental (social and
biophysical) impacts (both positive and negative);
to provide information used for decision-making;
to provide a structure for liaison and communication with I&APs and key stakeholders;
to ensure inclusivity (the needs, interests and values of I&APs must be considered in the decision-making
process);
to focus on issues relevant to the project, and issues considered important by I&APs and key stakeholders;
and
to provide responses to I&AP queries.
The public participation process must adhere to the requirements of Regulations (GNR 543) under the NEMA.
The public participation process for the Cornubia Phase 2 EIA process will be undertaken according to the stages
outlined below.
FIGURE 6-1: RESPONSABILITIES OF I&APS IN THE DIFFERENT PPP STAGES
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 46 Royal HaskoningDHV
Real Consulting is working with Royal HaskoningDHV on the Public Participation Process (PPP) for the Cornubia
Project. In recent years Tongaat Hulett Developments has taken a much more participatory approach to their
property development projects, with the understanding that the socio-political and economic context of the times
invites this more public approach. Communities that surround the developments are invited to “inform and be
informed” about developments through the establishment of fora in order to achieve the most positive impacts
possible. It is also noted that engaging stakeholders even before developments are built can achieve the best
impacts. It is for this reason that the PPP that forms part of the EIA becomes the basis of a long-term stakeholder
engagement process.
For the purposes of the scoping phase, the PPP aims to ensure that the full range of stakeholders is informed
about Cornubia and its complex profile throughout the period in question. In order to achieve this, a number of
key activities have taken place and will continue to take place. These included the following:
The identification of stakeholders is a key deliverable at the outset, and it is noted that there are different
categories of stakeholders that must be engaged, from the different levels and categories of government, to
relevant structures in the NGO sector, to the communities of some nine areas that straddle Cornubia at
different places;
The development of a living and dynamic database that captures details of stakeholders from all sectors;
The convening of focussed and general meetings with stakeholders at different times throughout the EIA
process (and beyond);
The engagement of public leaders to whom the public generally turn for information, keeping such individuals
well informed about process and progress;
The fielding of queries from I&APs and others, and providing appropriate information;
The convening of specific stakeholder groupings/fora as the need arises;
The preparation of reports (both baseline and impact assessment) based on information gathered throughout
the EIA via the PPP and feeding that into the relevant decision-makers;
The PPP could include distribution of various types of pamphlets and other information packs; and
Where appropriate site visits may be organised, as well as targeted coverage by the media.
Specifically the Cornubia PPP has entailed the following activities.
6.1 Authority Consultation
The competent authority which is the KwaZulu-Natal Department of Agriculture and Environmental Affairs (KZN
DAEA) is required to provide an environmental authorisation (whether positive or negative) for the project. The
KZN DAEA was consulted from the outset of this study, and has been engaged throughout the project process.
Authority consultation included the following activities:
Submission of an application for environmental authorisation in terms of Section 26 of the EIA Regulations
(2010) on 15 June 2012.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 47 Royal HaskoningDHV
Approval of the application documentation by KZN DAEA was received on 20 June 2012 with the following
DAEA reference number DM/0030/2012 and NEAS Reference KZN/EIA/0000762/2012 (see Appendix A).
6.2 Consultation with Other Relevant Stakeholders
Consultation with other relevant key stakeholders were and will continue to be undertaken through telephone calls
and written correspondence in order to actively engage these stakeholders from the outset and to provide
background information about the project during the Environmental Scoping Phase. These stakeholders included:
TABLE 6-1: KEY STAKEHOLDERS CONTACTED AS PART OF THE PUBLIC PARTICIPATION PROCESS
OWNERS AND OCCUPIERS OF LAND ADJACENT TO THE SITE
Refer to detailed database in Appendix B
LOCAL AUTHORITY
Cllr Mxolisi Ndzimbomvu Ward 58 Councillor - Waterloo
Cllr Musa Dludla Ward 102 Councillor – Mt Edgecombe
Cllr Solly Singh Ward 50 - Phoenix
Cllr Patrick Pillay Ward 61 - Phoenix
Cllr Heinz de Boer Ward 35 - Umhlanga
Cllr Chocks Chillapen Ward 60 - Verulam
Diane van Rensburg eThekwini Municipality
PROVINCIAL AUTHORITY
Felicity Elliot Ezemvelo KZN Wildlife
Weziwe Tshabalala Amafa aKwaZulu-Natali
Carolyn Schwegman WESSA KZN
Malcolm Moses / Yugeshni Govender
KwaZulu-Natal Department of Agriculture and
Environmental Affairs
STATE DEPARTMENTS
Manisha Maharaj Department of Water Affairs
Roy Ryan Department of Transport
Wiseman Rozani Department of Agriculture, Forestry and Fisheries
Nonhlanhla Mnyeni Department of Agriculture
6.3 Site Notification
The NEMA EIA Regulations require that a site notice be fixed at a place conspicuous to the public at the
boundary or on the fence of the site where the activity to which the application relates is to be undertaken and on
any alternative sites. The purpose of this is to notify the public of the project and to invite the public to register as
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 48 Royal HaskoningDHV
stakeholders and inform them of the PP Process. Royal HaskoningDHV erected six site notices at various
noticeable locations around the perimeter of the site (refer to Appendix B).
6.4 Advertising
In compliance with the EIA Regulations (2010), notification of the commencement of the EIA process for the
project was advertised in a local newspapers as follows:
o North Coast Courier on 4 September 2012
o Phoenix Rising Sun on 5 September 2012
o The Mercury on 5 September 2012
o Isolezwe on 5 September 2012
o Umafrika on 7 September 2012
(refer to Appendix B). Interested and affected parties (I&APs) were requested to register their interest in the
project and become involved in the EIA process. The primary aim of these advertisements was to ensure that the
widest group of I&APs possible was informed and invited to provide input and questions and comments on the
project.
6.5 Identification of Interested and Affected Parties
I&APs were identified primarily through an existing database as well as from responses received from the notice
boards mentioned above. E-mails were sent to key stakeholders and other I&APs on the existing database,
informing them of the application for the project, the availability of the draft Environmental Scoping Report (ESR)
for review and indicating how they could become involved in the project. The contact details of all identified I&APs
are updated on the project database, which is included in Appendix B.
This database will be updated on an on-going basis throughout the EIA process.
6.6 Briefing Paper
A briefing paper or Background Information Document (BID) for the project was compiled in English (refer to
Appendix B). The aim of this document is to provide a brief outline of the application and the nature of the
development. It is also aimed at providing preliminary details regarding the EIA process, and explains how I&APs
could become involved in the project. The briefing paper was distributed to all identified I&APs and stakeholders,
together with a registration/comment sheet inviting I&APs to submit details of any issues, concerns or inputs they
might have with regards to the project.
6.7 Issues Trail
Issues and concerns raised in the public participation process during the EIA process will be compiled into an
Issues Trail. The ESS-phase Issues Trail is attached as Appendix B, in which all comments received and
responses provided have been captured.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 49 Royal HaskoningDHV
6.8 Public Review of the Draft Scoping Report
All registered I&APs were notified of the availability of the report at the meetings and electronically.
The draft ESR, together with the Plan of Study for EIA was made available for authority and public review for a
total of 40 days from 3 October to 12 November 2012. In addition, the report was made available at the following
public locations within the study area, which are all readily accessible to I&APs:
Libraries
Phoenix Library Playpark Place Shastri Park, Phoenix
Umhlanga Library, 4 Lagoon Drive, Umhlanga
Verulam Library, 8 Groom Street. Verulam
Councillors’ offices
Cllr Mxolisi Ndzimbomvu, Ward 58, Support Centre, 187 Woodpecker Rd, Waterloo
Cllr Musa Dludla, Ward 102, Room 102, White House Shopping Centre Mt Edgecombe
Cllr Solly Singh. Ward 50, Suite 3, 1st Floor, Gem City, 80 Parthenon Street, Phoenix
Cllr Patrick Pillay, Ward 61, Suite 3, 1st Floor, Gem City, 80 Parthenon Street, Phoenix
Cllr Heinz de Boer, Ward 35, Sizakala Centre327 Umhlanga Rocks Drive, Umhlanga Rocks
Cllr Chocks Chillapen, Ward 60, 47 Honeysuckle Rd, Brindhaven, Verulam
Mount Edgecombe Country Club ;
Tongaat Hulett Developments: 305 Umhlanga Rocks Drive, La Lucia; and
Royal HaskoningDHV Website : www.rhdhv.co.za
6.9 Final Environmental Scoping Report
The final stage in the Environmental Scoping Study process will entail the capturing of responses and comments
from I&APs on the draft ESR in order to refine the ESR, and ensure that all issues of significance are addressed.
The final Environmental Scoping Report will be submitted to KZN DAEA for review and decision-making.
6.10 Summary of Findings and PPP
TABLE 6-2: SUMMARY OF PUBLIC PARTICIPATION PROCESS
ACTIVITY DESCRIPTION REFERENCE
SCOPING PHASE
Identifying stakeholders Stakeholders were identified and a
database of all I&APs were compiled.
Appendix B
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 50 Royal HaskoningDHV
ACTIVITY DESCRIPTION REFERENCE
Publishing newspaper
adverts
North Coast Courier, Phoenix Rising
Sun, The Mercury, Isolezwe, Umafrika
Appendix B
Distribution of a BID BIDs were distributed electronically and
by hand to I&APs
Appendix B
Erection of site notices Six A2 site notices were erected on the
perimeter of the site.
Appendix B
Preparation of an on-going
Issues Trail
Comments, issues of concern and
suggestions received from
stakeholders thus far have been
captured in a Comment and
Response Report.
Appendix B
Release of the Draft Scoping
Report
The Draft Scoping Report has been
advertised and made available for a
period of 40 days for public review.
Appendix B
Public Meetings / Open Days Six public meetings were held during the
Scoping Phase to afford I&APs the
opportunity to comment on the project
and engage with the EIA team. A
Comments and Responses report will be
drafted to address all comments raised
and appended to the Final Scoping
Report.
Appendix B
Refer to Appendix B – Public Participation Process (Issues Trail) for full responses & comments from I&AP’s &
comments and a summary of the Public Participation Process.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 51 Royal HaskoningDHV
7 POTENTIAL IMPACTS ASSOCIATED WITH THE PROJECT
This Environmental Scoping Study (ESS) aims to identify the potential positive and negative impacts (both
biophysical and social) associated with the proposed Cornubia Phase 2 Project. The potential impacts have been
identified through baseline investigations and below are a summary per phase.
7.1 Construction Phase
The construction phase of this project refers to the land which is to be developed and lasts only while the
proposed development is being constructed. The following potential impacts will be considered in the Impact
Assessment Phase:
TABLE 7-1: POTENTIAL CONSUTRUCTION PHASE IMPACTS
AFFECTED ENVIRONMENT ANTICIPATED IMPACT
BIOPHYSICAL IMPACTS
Geology Disturbance of surface geology for the development of foundations.
Topography Alteration of topography due to stockpiling of soil, building material, debris
and waste material on site.
Erosion potential is anticipated to increase during the site clearance and
construction activities for proposed project.
Soils Removal and compaction of soil during construction activities.
Erosion, degradation and loss of topsoil due to construction activities as well
as surface and stormwater runoff.
Contamination of soils due to spillage, leakage, incorrect storage and
handling of chemicals, oils, lubricants, fuel and other hazardous material.
Disturbance of soils and/ or land use potential due to location of construction
camp and associated infrastructure.
Degradation of soil due to exposed roads and open areas.
Geohydrology
(groundwater) and
Hydrology (surface water)
Contamination of surface and groundwater due to spillage, leakage,
incorrect storage and handling of chemicals, oils, lubricants, fuel and other
hazardous material.
The consumption of groundwater can lead to the depletion of a natural
resource.
Vegetation Loss of vegetation
Removal of alien invasive species
Wetlands Potential negative impacts on wetlands and/or loss of wetlands
Agricultural Loss of agricultural land through clearing of all sugar cane and vegetation on
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 52 Royal HaskoningDHV
AFFECTED ENVIRONMENT ANTICIPATED IMPACT
site
Air Quality During the construction assessment phase it is expected that, the main
sources of impact will result due to vehicle movement within the plant area.
These predicted impacts cannot be quantified, primarily due to the lack of
detailed information related to scheduling and positioning of construction
related activities. Instead, a qualitative description of the impacts will be
provided in the EIA study. This will involve the identification of possible
sources of emissions and the provision of details related to their impacts.
Construction usually consists of a series of different operations, each with its
own duration and potential for dust generation. Dust emission will vary from
day to day depending on the phase of construction, the level of activity, and
the prevailing meteorological conditions1.
The following possible sources of fugitive dust have been identified as
activities which could potentially generate dust during construction
operations at the site:
- Scraping;
- Debris handling;
- Emergency venting; and
- Truck transport and dumping of debris.
Noise Noise will be generated during the construction; however with the
appropriate mitigation measures in place the impact will be minimal.
Waste The potential waste streams for the project include general, hazardous and
sewage waste.
General waste generated on site includes domestic waste and building
rubble. General waste will not have a significant impact on the environment
provided that the correct waste streams are used for the disposal of the
waste.
Hazardous waste will be generated through the spillage of raw material. All
material cleared after a spillage must be treated as hazardous waste and
disposed off at a hazardous waste disposal site.
Generation and disposal of sewage waste of temporary construction toilets.
Health and Safety The safety of the construction staff could be compromised unless adequate
1 U.S Environmental Protection Agency, (1996). Compilation of Air Pollution Emission Factors (AP-42), 6th Edition, Volume
1, as contained in the AirCHIEF (AIR Clearinghouse for Inventories and Emission Factors) CD-ROM (compact disk
read only memory), US Environmental Protection Agency, Research Triangle Park, North Carolina. Also available at
URL: http://www.epa.gov/ttn/chief/ap42/.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 53 Royal HaskoningDHV
AFFECTED ENVIRONMENT ANTICIPATED IMPACT
safety measures are implemented.
The safety measures outlined in the draft Environmental Management
Programme (EMPr) must be adhered to during construction.
Odour Release of odours as a result of the chemical toilets on site.
Spillage and incidents Contamination of soils, surface and groundwater due to spillage, leakage,
incorrect storage and handling of: Chemicals; Oils; Lubricants; Fuels; and
Other Hazardous Materials.
Fires or explosions may occur which would result in a significant risk to the
biophysical and socio-economic environment.
Sites of Archaeological,
Historical and Cultural
Significance
Disturbance of possible graves or other sites of cultural significance on site.
SOCIO-ECONOMIC IMPACTS
Employment The development will result in job creation and provision of employment.
Housing Housing will not be provided for the contractors during the construction
phase. Only contract and project managers will reside on site.
Population Changes Job creation during the construction phase could result in the influx of
people to the area. However, this should be temporary.
Uncontrolled settlements The potential job creation could result in an influx of people to the area and
associated informal and uncontrolled settlements.
Traffic Traffic disruptions and congestion during construction period.
Security and Social Ills Contractors, the influx of people and potential job creation will result in the
proliferation of social ills and issues such as crime, prostitution, the spread
of HIV/AIDS, informal settlements etc.
Safety The safety of the construction staff could be compromised unless adequate
safety measures are implemented.
The safety measures outlined in the draft EMPr must be adhered to during
construction.
Visual Alteration of existing visual perspective of green cane lands. However, due
to the location, an insignificant impact is anticipated
7.2 Operational Phase
The following potential environmental impacts have been considered:
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 54 Royal HaskoningDHV
TABLE 7-2: POTENTIAL OPERATION PHASE IMPACTS
AFFECTED ENVIRONMENT ANTICIPATED IMPACT
BIO-PHYSICAL IMPACTS
Soils Erosion and loss of soil after construction activities.
Vegetation Loss of vegetation.
Wetlands/Estuary Disturbance of wetland/estuary habitats.
Geohydrology (groundwater)
and Hydrology (surface
water)
Pollution of surface water and wetlands.
Cumulative & Downstream impacts.
The consumption of groundwater can lead to the depletion of a natural
resource.
Agricultural Loss of good agricultural land through clearing of all sugar cane and
vegetation on site
Air Quality Release of dust from building activities, equipment and construction
vehicles into the atmosphere.
Generation of fumes from vehicle emissions may pollute the air.
Noise Noise disturbance from the development activities.
Waste Generation and disposal of domestic waste by the proposed development.
Generation and disposal of sewage waste by the proposed development.
SOCIO-ECONOMIC IMPACTS
Employment The completion of the development will lead to the stimulation of direct and
indirect job creation. (However, it is not possible to accurately predict this.)
Population Changes The establishment of housing will increase communities and the number of
people in the region.
Provision of infrastructure The establishment of the development will result in the provision of
infrastructure such as sewage and water pipelines, telecommunications,
electricity, etc.
Housing The development will meet some of the current and potential housing
demand in the area and within the municipality.
Recreational facilities Recreational facilities such as churches, schools, public open spaces and
other institutional establishments will be developed.
Traffic Alleviation of traffic congestion for the surrounding areas.
New and alternative access rotes and off ramps.
Security and Social Ills Contractors, the influx of people and potential job creation will result in the
proliferation of social ills and issues such as crime, prostitution, the spread
of HIV/AIDS, informal settlements etc.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 55 Royal HaskoningDHV
7.3 Decommissioning Phase
There is no decommissioning phase for this project.
7.4 Cumulative Impacts
Cumulative impacts associated with the project will be further investigated in detail during the EIA study.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 56 Royal HaskoningDHV
8 PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT
Potential environmental impacts (biophysical and social) associated with the proposed gas plant upgrade, have
been identified in the Environmental Scoping Study (ESS). No fatal flaws or highly significant impacts have been
identified to date. All potentially significant and cumulative impacts will be further investigated and assessed within
the Environmental Impact Assessment (EIA) phase of the project. Mitigation measures will be contained in the
Environmental Management Programme (EMPr) to be compiled during the EIA phase. Mitigation measures
recommended in the ESS will also be included in the EMPr.
The EIA phase will aim to adequately assess and address all potentially significant environmental issues in order
to provide the KwaZulu-Natal Department of Agriculture and Environmental Affairs (KZN DAEA) with sufficient
information to make an informed decision regarding the proposed project.
8.1 Purpose of the EIA
The purpose of the EIA is to provide/determine:
An assessment of the environment likely to be affected by the proposed project;
An assessment of the environments likely to be affected by any identified alternatives;
An assessment of the extent, duration, intensity, probability and significance of the identified potential
environmental, social and cultural impacts of the proposed project;
A comparative assessment of the identified land use and development alternatives and their potential
environmental, social and cultural impacts;
The appropriate mitigation measures for each significant impact of the proposed project;
Details of the engagement process with I&AP’s followed during the course of the assessment and an
indication of how the issues raised have been addressed;
Identify knowledge gaps and report on the adequacy of predictive methods, underlying assumptions and
uncertainties encountered in compiling the required information;
A description of the arrangements for monitoring and management of environmental impacts; and
Inclusion of technical and supporting information as appendices, if available.
8.2 Approach to undertaking the EIA Phase of the Project
The following points below outline the proposed approach to undertaking the EIA phase of the project. It is
believed that the proposed approach will adequately fulfil the competent authority’s (KZN DAEA) requirements,
the requirements of the EIA Regulations (2010) and the objectives of environmental best practice, so as to ensure
transparency and to allow an informed decision regarding the project to be made.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 57 Royal HaskoningDHV
8.2.1 Authority Consultation
Ongoing consultation with KZN DAEA, the Municipality (eThekwini Municipality), Ward Councillors, and all other
authorities identified during the Environmental Scoping Study (ESS) phase of the project (and further ones that
may be identified during the EIA phase) will continue throughout the duration of the project. Authority consultation
is therefore seen as a continuous process that takes place until completion of the environmental investigations.
The KZN DAEA assessing officer will be updated on a regular basis, so as to ensure their continued
understanding of the proposed project and to ensure that all requirements are met by the environmental team.
8.2.2 Detailed Project Description
A detailed project and location description will be developed and included in the EIA Report. This will include a
description of the property, need and desirability for the project, components of the proposed project (i.e. tourism
facilities, residential, commercial, etc.) and a timeline for the delivery of the different phases of the project.
8.2.3 Detailed Studies to be undertaken in the EIA Phase – Specialist Studies
The following specialist studies have been envisaged and will play a crucial role in the EIA process:
8.2.3.1 Traffic Assessment
The specialist consultant will undertake a Traffic Impact Assessment, determining suitable road networks and
routes as well as any possible linkages.
8.2.3.2 Infrastructural Assessment
The specialist consultant will undertake to identify the requirements and appropriateness for bulk services.
8.2.3.3 Wetland Assessment
The specialist will identify and delineate all wetland areas falling within the project site and assess the potential
impacts that may arise from development activities and associated infrastructure. The health Status of the
wetlands will also be assessed within this assessment.
8.2.3.4 Heritage Assessment
The specialist consultant will undertake a heritage impact assessment for the proposed development in terms of
the KwaZulu Heritage Act No. 10 of 1997. A heritage impact assessment is not limited to archaeological artefacts,
historical buildings and graves. It is far more encompassing and includes intangible and invisible resources such
as places, oral traditions and rituals. In the KwaZulu-Natal Heritage Act 1997 a heritage resource is defined any
place or object of cultural significance i.e. of aesthetic, architectural, historical, scientific, social, spiritual, linguistic
or technological value or significance.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 58 Royal HaskoningDHV
8.2.3.5 Vegetation (Biodiversity) Assessment
The specialist consultant will undertake an assessment of the current vegetation, including existing biodiversity on
the site. In addition, as part of the Scope of Works, the consultant will be requested to make recommendations
regarding open space areas to ensure the free flow of plant and animals through the development and facilitate
the “greening” of the development area and provide vital ecological functioning that will aid in ensuring a more
sustainable form of development.
8.2.3.6 1: 100 year floodline
This specialist study will involve the determination of the 1:100 year Floodline and the assessment of the
Cornubia development in relation to the the floodline identified.
8.2.3.7 Geotechnical Study
The specialist consultant will undertake an assessment of the topography, geology, soils, existing land use and
agricultural potential. In addition there will be an assessment of the geotechnical conditions in terms of the
following:
General Constraints – topography and flooding;
Slope stability;
Seepage and groundwater conditions;
Excavations and Earthworks;
Founding conditions;
Erosion;
Sewerage;
Road subgrade conditions; and
Construction materials.
8.2.3.8 Socio-economic study
The specialist consultant will undertake as assessment of the following:
Identify the expectations of the stakeholders in relation to Cornubia;
Provide sound informational basis for the areas surrounding the Cornubia site in terms of:
Socio-economic profile for each region;
Issues relevant to different areas;
Needs for each area;
Potential opportunities in the different areas;
How the areas could be impacted upon by Cornubia; and
How different communities could impact on Cornubia.
Provide information to assist in the design of an effective community communication mechanism;
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 59 Royal HaskoningDHV
Lay the basis for developing assessment indicators to assist in the monitoring of the impact of the
development on an ongoing basis;
Inform solutions to managing sensitivities associated with the site (inclusionary housing, etc); and
Serve EIA information requirements.
8.2.3.9 Social Impact Assessment
The specialist consultant will undertake a social impact assessment to report on the potential impacts of the
development or policy on any grouping of people associated with the action.
8.2.3.10 Agricultural Potential Assessment
The specialist consultant will undertake an agricultural potential of the project area, in order that it might be
compared to the sustainability and viability of a development that meets their objectives. In assessing the
agricultural potential of these areas of land, a study of the climate, soils, terrain, aspect, suitable crops, utilities
available, market, spatial development, labour and management will be carried out. Site visits will be carried out
to assess the past and current agricultural practices being carried out, assess the physical properties of the soils,
infrastructure and water resources.
In addition to the above mentioned specialist studies, further studies which have not been anticipated for this
project but emerge as necessary studies to be undertaken from the comments on the scoping report, will be
conducted during the EIA phase. The following specialist studies have not been anticipated for this development:
Visual Impact Assessment;
Air Quality Assessment; and
Noise Impact Assessment.
8.2.4 Environmental Impact Assessment
An EIA will be undertaken to determine the effects of the proposed project on the environment. The EIA will
comprise of the following:
An assessment of the environment likely to be affected by the proposed project, including cumulative
environmental impacts;
An assessment of the environment likely to be affected by the identified alternative land use or developments,
including cumulative environmental impacts (if applicable);
An assessment of the extent, duration, intensity, probability and significance of the identified potential
environmental, social and cultural impacts of the proposed development, including cumulative impacts;
A comparative assessment of the identified land use and development alternative and their potential
environmental, social and cultural impacts (if applicable); and
Inclusion of technical and supporting information as appendices, if any.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 60 Royal HaskoningDHV
8.2.5 Impact Assessment Methodology
The potential environmental impacts associated with the project will be evaluated according to it nature, extent,
duration, intensity, probability and significance of the impacts, whereby:
Nature: A brief written statement of the environmental aspect being impacted upon by a particular action or
activity.
Extent: The area over which the impact will be expressed. Typically, the severity and significance of an
impact have different scales and as such bracketing ranges are often required. This is often useful during the
detailed assessment phase of a project in terms of further defining the determined significance or intensity of
an impact. For example, high at a local scale, but low at a regional scale;
Duration: Indicates what the lifetime of the impact will be;
Intensity: Describes whether an impact is destructive or benign;
Probability: Describes the likelihood of an impact actually occurring; and
Cumulative: In relation to an activity, means the impact of an activity that in itself may not be significant but
may become significant when added to the existing and potential impacts eventuating from similar or diverse
activities or undertakings in the area.
Refer below and to Tables 8-1 and 8-2 for an explanation of the risk assessment methodology.
Attention will also be provided to the cumulative nature of impacts as required by the EIA Regulations
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 61 Royal HaskoningDHV
TABLE 8-1: CRITERIA TO BE USED FOR THE RATING OF IMPACTS
CRITERIA DESCRIPTION
EXTENT National
The whole of South Africa
Regional
Provincial and parts of
neighbouring provinces
Local
Within a radius of 2km of the
construction site
Site
Within the construction site
DURATION Permanent
Mitigation either by man or
natural process will not occur in
such a way or in such a time
span that the impact can be
considered transient
Long-term
The impact will continue or last
for the entire operational life of
the development, but will be
mitigated by direct human
action or by natural processes
thereafter. The only class of
impact which will be non-
transitory
Medium-term
The impact will last for the
period of the construction
phase, where after it will be
entirely negated
Short-term
The impact will either
disappear with mitigation or will
be mitigated through natural
process in a span shorter than
the construction phase
INTENSITY Very High
Natural, cultural and social
functions and processes are
altered to extent that they
permanently cease
High
Natural, cultural and social
functions and processes are
altered to extent that they
temporarily cease
Moderate
Affected environment is
altered, but natural, cultural
and social functions and
processes continue albeit in a
modified way
Low
Impact affects the environment
in such a way that natural,
cultural and social functions
and processes are not affected
PROBABILTY
OF
OCCURANCE
Definite
Impact will certainly occur
Highly Probable
Most likely that the impact will
occur
Possible
The impact may occur
Improbable
Likelihood of the impact
materialising is very low
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 62 Royal HaskoningDHV
Significance is determined through a synthesis of impact characteristics. Significance is an indication of the
importance of the impact in terms of both physical extent and time scale, and therefore indicates the level of
mitigation required. The total number of points scored for each impact indicates the level of significance of the
impact.
TABLE 8-2: SIGNIFICANCE RATING OF CLASSIFIED IMPACTS
Very Low impact
(1 - 3 points)
Impact is negligible.
Low impact
(4 - 6 points)
A low impact has no permanent impact of significance. Mitigation measures are
feasible and are readily instituted as part of a standing design, construction or
operating procedure.
Medium impact
(7 - 9 points)
Mitigation is possible with additional design and construction inputs.
High impact
(10 - 12 points)
The design of the site may be affected. Mitigation and possible remediation are
needed during the construction and/or operational phases. The effects of the
impact may affect the broader environment.
Very high impact
(12 - 14 points)
Permanent and important impacts. The design of the site may be affected.
Intensive remediation is needed during construction and/or operational phases.
Any activity which results in a “very high impact” is likely to be a fatal flaw.
Status Denotes the perceived effect of the impact on the affected area.
Positive (+) Beneficial impact.
Negative (-) Deleterious or adverse impact.
Neutral (/) Impact is neither beneficial nor adverse.
The suitability and feasibility of all proposed mitigation measures will be included in the assessment of significant
impacts. This will be achieved through the comparison of the significance of the impact before and after the
proposed mitigation measure is implemented. Mitigation measures identified as necessary will be included in an
EMPr. The EMPr will form part of the EIA Report.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 63 Royal HaskoningDHV
8.2.6 EIA Report
The EIA Report (EIAR) will contain the following:
Details of the EAP who compiled the report and their expertise to carry out an EIA;
Detailed description of the activity/ies;
A description of the environment that might be affected by the activity and the manner in which the physical,
biological, social, economic and cultural aspects of the environment may be affected by the proposed activity;
Details of the public participation process conducted during the Scoping Phase and the ongoing consultation
during the EIA phase;
Description of the need and desirability of the activity including advantages and disadvantages that the
activity may have on the environment and the community that may be affected by the activity;
An indication of the methodology used in determining the significance of potential environmental impacts;
A summary of the findings and recommendations of any specialist report or report on a specialised process;
A description of all environmental issues that were identified during the environmental impact assessment
process, an assessment of the significance of each issue and an indication of the extent to which the issue
could be addressed by the adoption of mitigation measures;
An assessment of each identified potentially significant impact, including cumulative impacts, the nature of the
impact, the extent and duration of the impact, the probability of the impact occurring, the degree to which the
impact can be reversed, the degree to which the impact may cause irreplaceable loss of resources and the
degree to which the impact can be mitigated;
A description of any assumptions, uncertainties and gaps in knowledge;
An opinion as to whether the activity should or should not be authorised, and if the opinion is that it should be
authorised, any conditions that should be made in respect of that authorisation;
An environmental impact statement which contains a summary of the key findings of the environmental
impact assessment; and a comparative assessment of the positive and negative implications of the activity.
A draft Environmental Management Programme (EMPr) and
Copies of any specialist reports and reports on specialised processes.
8.2.7 Draft Environmental Management Programme (EMPr)
During the compilation of the EIA, a draft EMPr will be compiled in accordance with the EIA Regulations (2010).
The draft EMPr will provide the actions for the management of identified environmental impacts emanating from
the project and a detailed outline of the implementation programme to minimise and/or eliminate the anticipated
negative environmental impacts. The draft EMPr will provide strategies to be used to address the roles and
responsibilities of environmental management personnel on site, and a framework for environmental compliance
and monitoring.
The EMPr will include the following:
Details of the person who prepared the EMPr and the expertise of the person to prepare an EMPr;
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 64 Royal HaskoningDHV
Information on any proposed management or mitigation measures that will be taken to address the
environmental impacts that have been identified in the EIA Report, including environmental impacts or
objectives in respect of operation or undertaking of the activities, rehabilitation of the environment and closure
where relevant;
A detailed description of the aspects of the activity that are covered by the draft EMPr;
An identification of the persons who will be responsible for the implementation of the measures;
Where appropriate, time periods within which the measures contemplated in the draft EMPr must be
implemented;
Proposed mechanisms for monitoring compliance with the EMPr and reporting thereon;
An environmental awareness plan; and
Procedures for managing incidents which have occurred as a result of undertaking the activity and
rehabilitation measures.
8.3 Public Participation Process
The primary aims for the public participation process include the following:
meaningful and timeous participation of I&APs;
promoting transparency and an understanding of the proposed project and its potential environmental (social
and biophysical) impacts;
accountability for information used for decision-making;
serving as a structure for liaison and communication with I&APs;
assisting in identifying potential environmental (social and biophysical) impacts associated with the
development; and
the needs, interests and values of I&APs must be considered in the decision-making process.
8.3.1 Advertising
The primary aim of adverts in the EIA phase is to provide information regarding the availability of reports for public
review, as well as, if necessary, the advertisement of dates of public meetings.
8.3.2 Identification of and Consultation with Key Stakeholders
The identification of I&APs and key stakeholders will continue into the EIA phase of the project as the public
participation process is a continuous process that runs throughout the duration of an environmental study.
8.3.3 I&AP Database
All I&AP information (including contact details), together with dates and details of consultations and a record of all
issues raised is recorded within a comprehensive database of I&APs. This database will be updated on an on-
going basis throughout the project, and will act as a record of the communication/involvement process.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 65 Royal HaskoningDHV
8.3.4 Consultation and Public Involvement
Consultation with I&APs is considered to be critical to the success of any EIA process. Therefore, one-on-one
consultation (via telephone calls, fax and emails) and a public meeting (if necessary) during the EIA phase will be
undertaken. The aim of this process will be to provide I&APs with details regarding the process and to obtain
further comments regarding the project. Minutes of all meetings held will be compiled and forwarded to all
attendees. These minutes will also be included in the EIA Report.
8.3.5 Issues Trail
All issues, comments and concerns raised during the public participation process of the EIA study will be
compiled into an Issues Trail. This Issues Trail will be incorporated as part of the EIA Report.
8.3.6 Public Review of the Draft Environmental Impact Report
The draft EIA Report will be made available at public places for public review and comment. A 40 day period will
be allowed for this review process. An advertisement indicating the availability of this report for public scrutiny will
be placed in the local newspaper. I&APs registered on the project database will be notified of the availability of
this report by correspondence.
8.3.7 Authority Review of the Environmental Impact Report
After the public review period, all relevant comments received from the public will be considered and included into
a final EIA report. This final document will be submitted to KZN DAEA for final review and decision-making.
8.4 Other Authorisation / Licensing Requirements
In addition to the authorisation required from the KZN DAEA, a waste license as well as a water use license and
heritage license may be required for this development. This will be determined during the EIA phase and will be
undertaken at a later stage, if required. Waste License
8.5 Environmental Authorisation
On receipt of the environmental authorisation for the project, I&APs registered on the project database will be
informed and its associated terms and conditions by correspondence.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 66 Royal HaskoningDHV
9 CONCLUSIONS AND RECOMMENDATIONS
This Environmental Scoping Study (ESS) for the Cornubia Mixed-Use Phased Development has been undertaken
in accordance with the Environmental Impact Assessment Regulations (2010) published in Government Notice R.
543 of 18 June 2010 read with Section 44, of the National Environmental Management Act, 1998 (Act No. 107 of
1998) (as amended).
In line with Regulation 28 (Chapter 3) of the EIA Regulations, this issues-based ESS aimed to identify and
provide:
A description of the ongoing activity;
A description of the environment that may be affected by the activity and the manner in which the physical,
biological, social, and economic aspects of the environment may be affected by the proposed activity;
The identification of all legislation and guidelines applicable to the development;
A description of environmental issues and potential impacts, including cumulative impacts, that have been
identified;
Details of the public participation process conducted to date; and
A Plan of Study for Environmental Impact Assessment (refer to Chapter 9) including the methodology that will
be adopted in assessing the potential impacts that have been identified, including specialist studies or
specialised processes that will be undertaken.
Some of the anticipated impacts that will be addressed in the EIA phase or/and in the EMPr are:
Alteration of the topography of the project area (EMPr);
Erosion of soil due to construction activities(EMPr);
Disturbance and destruction of some of the wetland areas (EIA & EMPr);
Impacts on wetlands that will be traversed by the planned roads and services infrastructure (EIA & EMPr);
Loss of Agricultural land (EIA);
Noise impact zones in relation to King Shaka Airport; (it has being agreed by eThekwini Municipality that the
Cornubia development will be subjected to the 2015 Noise Contours, as such development within the 55 db
noise contour will be attenuated within the EMPr);
Traffic impacts during the construction and operational phase (EIA);
Social Impacts of the development with regard to allocation of housing, housing typologies, social amenities,
job opportunities etc. (EIA);
Cumulative & Downstream impacts on the Ohlanga River System (EIA);
Disturbance of possible graves on site (EIA);
Generation, handling and disposal of waste generated by project activities (EMPr);
Vegetation and fauna (EIA);
Services and Infrastructure (EMPr); and
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 67 Royal HaskoningDHV
Planning Assessment (EIA & EMPr).
The information contained in this Scoping Report provides a comprehensive description of the aim, purpose and
benefit of the proposed development. In addition the Scoping Report provides a basic description of the
predevelopment environment in which this development is planned and which will be impacted upon, positively as
well as negatively. The aim of the environmental investigations and in particular the EIA Phase is to ensure that
the positive impacts are enhanced and the negative impacts are eliminated or reduced as far as possible. The
Plan of Study for the EIA contained in this report, describes the proposed way in which this will be done.
Based on the Environmental Scoping Study (ESS) undertaken, it can be concluded that there are no fatal flaws
associated with the project. From the outcomes of the Scoping phase, it is the view of the EAP that all possible
environmental red flags/sensitivities have been identified. The full extent of bio-physical and socio-economic
impacts associated with the proposed development however needs to be determined and assessed in the EIA
phase. It is further the view of the EAP that although positive spin offs are associated with the development (i.e.
job creation, etc), the EIA phase must carefully consider all aspects of the environment equally (social,
environmental and economical) to determine a way forward for the development.
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 68 Royal HaskoningDHV
APPENDIX A
APPROVAL OF ACCEPTANCE
DRAFT ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED CORNUBIA MIXED USE PHASED DEVELOPMENT – PHASE 2 MOUNT EDGECOMBE
E02.DUR.000375 Page 69 Royal HaskoningDHV
APPENDIX B
PUBLIC PARTICIPATION REPORT