Page 1of 3 Progress 25-March -2014 P039 - MARINA TOWER PROJECT PROGRESS & VARIANCE STATUS 25/03/2014 Activity ID Activity Name Status/Remark P039- Marina Tower, COM 27 Project (3B+G+3P+18F) 546 1-Jan-14 30-Jun-15 0 PROJECT MILESTONE 546 1-Jan-14 30-Jun-15 1-Jan-14 0 39_PM_1000 Commencement Date 0 1-Jan-14 1-Jan-14 Completed 39_PM_1040 Project Finish 0 30-Jun-15 PRE QUALIFICATION & APPROVAL OF SUBCONTRACTORS/SUPPLIERS 70 10-Feb-14 20-Apr-14 9-Jun-13 -16 39_SC_1020 MEP Subcontractor 30 100% 10-Feb-14 11-Mar-14 9-Jun-13 28-Jul-13 Completed 39_SC_1030 Form Work Supplier 30 100% 17-Feb-14 18-Mar-14 26-Aug-13 29-Aug-13 Completed 39_SC_1050 Facade SubContractor 30 10-Feb-14 11-Mar-14 -43 In Progress 39_SC_1370 Alumnium Works SubContractor 30 10-Feb-14 11-Mar-14 -43 In Progress 39_SC_1200 Stone Cladding Supplier 30 20-Feb-14 21-Mar-14 -33 In Progress 39_SC_1096 Garbage Chute Subcontractor/Supplier 30 25-Feb-14 26-Mar-14 -28 In Progress 39_SC_1150 BMU Suppliers 30 25-Feb-14 26-Mar-14 -28 In Progress 39_SC_1070 Gypsum Board SubContractor/Supplier 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1090 Steel Doors SubContractor/Supplier 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1100 Handrail Supplier 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1110 Paint Supplier/ SubContractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1130 Tile Suppiler 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1240 Marble/Granite work Subcontractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1170 Interlock Supplier 30 9-Mar-14 7-Apr-14 -16 In Progress 39_SC_1340 Intumscent Paint Supplier/Subcontractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1350 Decorative Laminate Supplier /Subcontractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1310 Obstruction Lights Supplier 30 8-Mar-14 6-Apr-14 -17 In Progress 39_SC_1320 Landscape Subcontractor 30 8-Mar-14 6-Apr-14 -17 In Progress 39_SC_1290 Parking Barier Supplier 30 11-Mar-14 9-Apr-14 -14 In Progress 39_SC_1180 Vehicle guard Supplier 30 11-Mar-14 9-Apr-14 -14 In Progress 39_SC_1060 Elevator SubContractor/Supplier 30 12-Mar-14 10-Apr-14 -13 In Progress 39_SC_1080 Wooden Work SubContractor/Supplier 30 16-Mar-14 14-Apr-14 -9 In Progress 39_SC_1210 Kitchen/Pantry Units Supplier 30 16-Mar-14 14-Apr-14 -9 In Progress 39_SC_1300 Steel Canopy Supplier/Subcontractor 30 16-Mar-14 14-Apr-14 -9 In Progress 39_SC_1120 Sanitary Wares Supplier 30 22-Mar-14 20-Apr-14 -3 In Progress 39_SC_1270 Toilet Partition Supplier 30 22-Mar-14 20-Apr-14 -3 In Progress 39_SC_1360 Toilet Accessories Supplier 30 22-Mar-14 20-Apr-14 -3 In Progress ENGINEERING 162 1-Feb-14 12-Jul-14 0 Submission & Approval of Shop Drawing 120 1-Feb-14 31-May-14 1-Feb-14 0 39_ED_1010 Submission of Redesign (Requsted by Client ) 28 95% 1-Feb-14 28-Feb-14 1-Feb-14 -25 In Progress 39_ED_1020 Approval by Consulatnt for Redsign requested by the Client 15 1-Mar-14 15-Mar-14 0 Submission & Approval of Material / Equipment 62 12-Mar-14 12-May-14 28-Apr-13 -15 MEP Materials & Equipment 58 16-Mar-14 12-May-14 28-Apr-13 0 Plumbing System 41 26-Mar-14 5-May-14 28-Apr-13 0 39_ME_7860 PPR Pipes 21 31-Mar-14 20-Apr-14 39_ME_7870 Copper Pipes 21 31-Mar-14 20-Apr-14 39_ME_7880 uPVC Pipes 21 100% 5-Apr-14 25-Apr-14 28-Apr-13 B129-Jul-13 Completed 39_ME_7890 Valves and Accessories 21 26-Mar-14 15-Apr-14 39_ME_7900 GRP Sectional Water Tanks 21 7-Apr-14 27-Apr-14 39_ME_7910 Water Heaters 21 11-Apr-14 1-May-14 39_ME_7960 Booster and Elevating Pumps, Submersible Pump and Irrigation Pump 21 15-Apr-14 5-May-14 39_ME_7980 Grey Water System 21 5-Apr-14 25-Apr-14 39_ME_7990 Floor Drain, Area Drain, Roof Drain 21 13-Apr-14 3-May-14 39_ME_8050 Water Hammer Arrestor 21 3-Apr-14 23-Apr-14 Electrical Power & Lighting 51 16-Mar-14 5-May-14 39_ME_7920 Generator 21 15-Apr-14 5-May-14 Original Duration Activity % Complete BL Project Start BL Project Finish Actual Start Actual Finish Variance-BL Project Finish Date

3 Delay Analysis - 25 March 2014.xlsx

Embed Size (px)

Citation preview

Page 1: 3  Delay Analysis - 25 March  2014.xlsx

Page 1of 3 Progress 25-March -2014

P039 - MARINA TOWERPROJECT PROGRESS & VARIANCE STATUS

25/03/2014

Activity ID Activity Name Actual Start Actual Finish Status/Remark

P039- Marina Tower, COM 27 Project (3B+G+3P+18F) 546 1-Jan-14 30-Jun-15 0 PROJECT MILESTONE 546 1-Jan-14 30-Jun-15 1-Jan-14 0 39_PM_1000 Commencement Date 0 1-Jan-14 1-Jan-14 Completed 39_PM_1040 Project Finish 0 30-Jun-15 PRE QUALIFICATION & APPROVAL OF SUBCONTRACTORS/SUPPLIERS 70 10-Feb-14 20-Apr-14 9-Jun-13 -16 39_SC_1020 MEP Subcontractor 30 100% 10-Feb-14 11-Mar-14 9-Jun-13 28-Jul-13 Completed 39_SC_1030 Form Work Supplier 30 100% 17-Feb-14 18-Mar-14 26-Aug-13 29-Aug-13 Completed 39_SC_1050 Facade SubContractor 30 10-Feb-14 11-Mar-14 -43 In Progress 39_SC_1370 Alumnium Works SubContractor 30 10-Feb-14 11-Mar-14 -43 In Progress 39_SC_1200 Stone Cladding Supplier 30 20-Feb-14 21-Mar-14 -33 In Progress 39_SC_1096 Garbage Chute Subcontractor/Supplier 30 25-Feb-14 26-Mar-14 -28 In Progress 39_SC_1150 BMU Suppliers 30 25-Feb-14 26-Mar-14 -28 In Progress 39_SC_1070 Gypsum Board SubContractor/Supplier 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1090 Steel Doors SubContractor/Supplier 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1100 Handrail Supplier 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1110 Paint Supplier/ SubContractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1130 Tile Suppiler 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1240 Marble/Granite work Subcontractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1170 Interlock Supplier 30 9-Mar-14 7-Apr-14 -16 In Progress 39_SC_1340 Intumscent Paint Supplier/Subcontractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1350 Decorative Laminate Supplier /Subcontractor 30 4-Mar-14 2-Apr-14 -21 In Progress 39_SC_1310 Obstruction Lights Supplier 30 8-Mar-14 6-Apr-14 -17 In Progress 39_SC_1320 Landscape Subcontractor 30 8-Mar-14 6-Apr-14 -17 In Progress 39_SC_1290 Parking Barier Supplier 30 11-Mar-14 9-Apr-14 -14 In Progress 39_SC_1180 Vehicle guard Supplier 30 11-Mar-14 9-Apr-14 -14 In Progress 39_SC_1060 Elevator SubContractor/Supplier 30 12-Mar-14 10-Apr-14 -13 In Progress 39_SC_1080 Wooden Work SubContractor/Supplier 30 16-Mar-14 14-Apr-14 -9 In Progress 39_SC_1210 Kitchen/Pantry Units Supplier 30 16-Mar-14 14-Apr-14 -9 In Progress 39_SC_1300 Steel Canopy Supplier/Subcontractor 30 16-Mar-14 14-Apr-14 -9 In Progress 39_SC_1120 Sanitary Wares Supplier 30 22-Mar-14 20-Apr-14 -3 In Progress 39_SC_1270 Toilet Partition Supplier 30 22-Mar-14 20-Apr-14 -3 In Progress 39_SC_1360 Toilet Accessories Supplier 30 22-Mar-14 20-Apr-14 -3 In Progress

ENGINEERING 162 1-Feb-14 12-Jul-14 0 Submission & Approval of Shop Drawing 120 1-Feb-14 31-May-14 1-Feb-14 0 39_ED_1010 Submission of Redesign (Requsted by Client ) 28 95% 1-Feb-14 28-Feb-14 1-Feb-14 -25 In Progress 39_ED_1020 Approval by Consulatnt for Redsign requested by the Client 15 1-Mar-14 15-Mar-14 0 Submission & Approval of Material / Equipment 62 12-Mar-14 12-May-14 28-Apr-13 -15 MEP Materials & Equipment 58 16-Mar-14 12-May-14 28-Apr-13 0 Plumbing System 41 26-Mar-14 5-May-14 28-Apr-13 0 39_ME_7860 PPR Pipes 21 31-Mar-14 20-Apr-14 39_ME_7870 Copper Pipes 21 31-Mar-14 20-Apr-14

Original Duration

Activity % Complete

BL Project Start

BL Project Finish

Variance-BL Project Finish Date

Page 2: 3  Delay Analysis - 25 March  2014.xlsx

Page 2of 3 Progress 25-March -2014

P039 - MARINA TOWERPROJECT PROGRESS & VARIANCE STATUS

25/03/2014

Activity ID Activity Name Actual Start Actual Finish Status/RemarkOriginal Duration

Activity % Complete

BL Project Start

BL Project Finish

Variance-BL Project Finish Date

39_ME_7880 uPVC Pipes 21 100% 5-Apr-14 25-Apr-14 28-Apr-13 B129-Jul-13 Completed 39_ME_7890 Valves and Accessories 21 26-Mar-14 15-Apr-14 39_ME_7900 GRP Sectional Water Tanks 21 7-Apr-14 27-Apr-14 39_ME_7910 Water Heaters 21 11-Apr-14 1-May-14 39_ME_7960 Booster and Elevating Pumps, Submersible Pump and Irrigation Pump 21 15-Apr-14 5-May-14 39_ME_7980 Grey Water System 21 5-Apr-14 25-Apr-14 39_ME_7990 Floor Drain, Area Drain, Roof Drain 21 13-Apr-14 3-May-14 39_ME_8050 Water Hammer Arrestor 21 3-Apr-14 23-Apr-14 Electrical Power & Lighting 51 16-Mar-14 5-May-14 39_ME_7920 Generator 21 15-Apr-14 5-May-14 39_ME_7930 Transformer 21 100% 16-Mar-14 5-Apr-14 3-Aug-13 8-Sep-13 Completed 39_ME_7940 MV Panel (MV) 21 15-Apr-14 5-May-14 39_ME_7950 Capacitor Bank 21 31-Mar-14 20-Apr-14 39_ME_8510 Distribution Board (DB) 21 31-Mar-14 20-Apr-14 39_ME_8520 Busway System 21 31-Mar-14 20-Apr-14 39_ME_8530 Earthing & Lightning Protection System 21 100% 16-Mar-14 5-Apr-14 11-Mar-13 28-Jul-13 Completed 39_ME_8540 Isolating / Disconnecting Switch 21 100% 1-Apr-14 21-Apr-14 14-Aug-13 21-Aug-13 Completed 39_ME_8550 Kilowatt-Hour (kWH) Meter 21 21-Mar-14 10-Apr-14 39_ME_8560 Central Battery System 21 21-Mar-14 10-Apr-14 39_ME_8580 Lighting Fixtures 21 10-Apr-14 30-Apr-14 39_ME_8590 PVC Conduits 21 100% 16-Mar-14 5-Apr-14 13-Jun-13 23-Jun-13 Completed 39_ME_8595 Cable Tray, Cable Ladder, Cable Trunking 21 100% 6-Apr-14 26-Apr-14 11-Aug-13 21-Aug-13 Completed CONSTRUCTION 519 18-Jan-14 20-Jun-15 Substructure 416 18-Jan-14 9-Mar-15 3rd Basement 359 18-Jan-14 11-Jan-15 Civil works 76 18-Jan-14 3-Apr-14 Area 1 (B3 Tower Area) 65 18-Jan-14 23-Mar-14 Retaining Walls 65 18-Jan-14 23-Mar-14 29-Jan-14 39_CSB3_1010 Water proofing Retaining Wall 23 100% 18-Jan-14 9-Feb-14 29-Jan-14 6-Mar-14 Completed 39_CSB3_1130 Retaining Wall Steel Rft 7 75% 8-Feb-14 14-Feb-14 16-Feb-14 -40 In Progress 39_CSB3_1140 Retaining Wall Shuttering 10 15% 10-Feb-14 19-Feb-14 15-Mar-14 -42 In Progress 39_CSB3_1150 Retaining Wall Pouring 20 15% 11-Feb-14 2-Mar-14 18-Mar-14 -39 In Progress 39_CSB3_1510 External Retaining Wall Water Proofing 6 4-Mar-14 9-Mar-14 -39 39_CSB3_1520 External Retaining Wall Backfilling 14 10-Mar-14 23-Mar-14 -39 Core 14 29-Jan-14 11-Feb-14 39_CSB3_1160 Core Wall Steel Rft 12 100% 29-Jan-14 9-Feb-14 4-Feb-14 9-Mar-14 Completed 39_CSB3_1190 Core Walls Internal shuttering 1 100% 10-Feb-14 10-Feb-14 13-Feb-14 10-Mar-14 Completed 39_CSB3_1180 Core Wall Pouring 1 100% 11-Feb-14 11-Feb-14 2-Mar-14 11-Mar-14 Completed Water Tank 8 1-Feb-14 8-Feb-14 39_CSB3_1250 Water Tank Walls External shuttering 3 100% 1-Feb-14 3-Feb-14 14-Jan-14 28-Feb-14 Completed 39_CSB3_1240 Water Tank Wall Steel Rft 1 100% 4-Feb-14 4-Feb-14 3-Feb-14 9-Mar-14 Completed 39_CSB3_1270 Water Tank Internal shuttering 2 100% 5-Feb-14 6-Feb-14 22-Feb-14 10-Mar-14 Completed 39_CSB3_1260 Water TankWall Pouring 2 100% 7-Feb-14 8-Feb-14 2-Mar-14 11-Mar-14 Completed Coulmns & Shear Walls 9 4-Feb-14 12-Feb-14

Page 3: 3  Delay Analysis - 25 March  2014.xlsx

Page 3of 3 Progress 25-March -2014

P039 - MARINA TOWERPROJECT PROGRESS & VARIANCE STATUS

25/03/2014

Activity ID Activity Name Actual Start Actual Finish Status/RemarkOriginal Duration

Activity % Complete

BL Project Start

BL Project Finish

Variance-BL Project Finish Date

39_CSB3_1290 Columns External shuttering 3 100% 4-Feb-14 6-Feb-14 15-Jan-14 28-Feb-14 Completed 39_CSB3_1280 Columns Steel Rft 3 100% 7-Feb-14 9-Feb-14 20-Jan-14 2-Mar-14 Completed 39_CSB3_1310 Columns Internal shuttering 1 100% 10-Feb-14 10-Feb-14 27-Jan-14 2-Mar-14 Completed 39_CSB3_1300 Columns Pouring 2 100% 11-Feb-14 12-Feb-14 27-Jan-13 3-Mar-14 Completed Area 2 53 Retaining Walls 53 10-Feb-14 3-Apr-14 39_CSB3_1350 Water proofing Retaining Wall 8 100% 10-Feb-14 17-Feb-14 23-Feb-14 2-Mar-14 In Progress 39_CSB3_1360 Retaining Wall Steel Rft 5 30% 16-Feb-14 20-Feb-14 11-Mar-14 -36 In Progress 39_CSB3_1370 Retaining Wall Shuttering 10 18-Feb-14 27-Feb-14 -35 39_CSB3_1380 Retaining Wall Pouring 10 19-Feb-14 28-Feb-14 -35 39_CSB3_1530 External Retaining Wall Water Proofing 10 10-Mar-14 19-Mar-14 -39 39_CSB3_1540 External Retaining Wall Backfilling 15 20-Mar-14 3-Apr-14 -39 Core 13 13-Feb-14 25-Feb-14 39_CSB3_1390 Core Wall Steel Rft 5 100% 17-Feb-14 21-Feb-14 20-Feb-14 10-Mar-14 Completed 39_CSB3_1400 Core Walls External shuttering 4 25% 13-Feb-14 16-Feb-14 15-Mar-14 -40 In Progress 39_CSB3_1420 Core Walls Internal shuttering 3 22-Feb-14 24-Feb-14 -35 39_CSB3_1410 Core Wall Pouring 1 25-Feb-14 25-Feb-14 -35 Water Tank 17 10-Feb-14 26-Feb-14 39_CSB3_1430 Water Tank Wall Steel Rft 4 100% 19-Feb-14 22-Feb-14 25-Feb-14 10-Mar-14 Completed 39_CSB3_1440 Water Tank Walls External shuttering 9 100% 10-Feb-14 18-Feb-14 11-Mar-14 15-Mar-14 Completed 39_CSB3_1460 Water Tank Internal shuttering 3 100% 23-Feb-14 25-Feb-14 16-Mar-14 20-Mar-14 Completed 39_CSB3_1450 Water TankWall Pouring 1 100% 26-Feb-14 26-Feb-14 22-Mar-14 25-Mar-14 Completed Coulmns & Shear Walls 11 19-Feb-14 1-Mar-14 39_CSB3_1470 Columns Steel Rft 4 100% 22-Feb-14 25-Feb-14 13-Feb-14 28-Feb-14 Completed 39_CSB3_1480 Columns External shuttering 3 100% 19-Feb-14 21-Feb-14 15-Feb-14 1-Mar-14 Completed 39_CSB3_1500 Columns Internal shuttering 3 100% 26-Feb-14 28-Feb-14 16-Feb-14 1-Mar-14 Completed 39_CSB3_1490 Columns Pouring 1 100% 1-Mar-14 1-Mar-14 16-Feb-14 2-Mar-14 Completed 2nd Basement 348 13-Feb-14 26-Jan-15 -3 Civil Works 124 13-Feb-14 16-Jun-14 -3 ( Tower Area) 49 13-Feb-14 2-Apr-14 0 Slab 39 13-Feb-14 23-Mar-14 0 39_CSB2_1021 Shuttering for Slab 5 13-Feb-14 17-Feb-14 -40 39_CSB2_1031 Steel Rft for Slab 4 18-Feb-14 21-Feb-14 -40 39_CSB2_1041 Embedded Parts 2 20-Feb-14 21-Feb-14 -40 39_CSB2_1025 Pouring of Slab 1 23-Mar-14 23-Mar-14 -25