2river

Embed Size (px)

Citation preview

  • Page 0 of 72

    PROJECT REPORT

    ON

    RIVER TRAINING WORKS - CASE STUDIES OF

    GANGA BRIDGE NO. 52

    AND

    SHARDA BRIDGE NO. 97

    (PROJECT 526 05)

    BY

    G. Panneerselvam, Dy. C. E. / Br. Line/ S.Rly

    Harpal Singh, Sr. D.E.N. / II / Moradabad/ N. Rly.

    S.C. Srivastava, Sr. DEN/ Coord./ Lucknow / N.E Rly.

    INDIAN RAILWAYS INSTITUTE OF CIVIL ENGINEERING, PUNE

  • Page 1 of 72

    CONTENTS SL.

    No. DESCRIPTION OF ITEMS PAGES

    1. INTRODUCTION 1

    2. DIFFERENT PURPOSES OF RIVER TRAINING

    WORKS

    1 2

    3. TYPES OF RIVER TRAINING WORKS 2 3

    4. DESIGN OF RIVER TRAINING WORKS 3 17

    5. CASE STUDY No. 1 OF GANGA BR. No. 52 18 33

    6. CASE STUDY No. 2 OF SHARDA BR. No. 97 33 40

    7. CONCLUSION 40 41

    8. ACKNOWLEDGEMENT 41

    9. REFERENCES 41 - 43

    10. FIGURES 44 72

  • Page 1 of 72

    1. INTRODUCTION.

    Rivers in alluvial plans are highly variable in their behaviour

    and to an average man often unpredictable. A stream, which is

    quite trouble free during low flow, may attain a threatening

    condition during high stages. It may develop unforeseen

    meanders, breakthrough embankment, attack town and important

    structures, outflank bridges and in general may create havoc.

    Therefore, whenever any hydraulic structure is built across an

    alluvial stream, adequate measures in form of river-training works

    must be taken to establish the river course along a certain

    alignment with a predetermined cross-section. All these works

    which are constructed to train the river are known as river-training

    works. (Figure1 & 2)

    2. PURPOSE OF RIVER TRAINING WORKS:

    The objective of the river training works in general includes to

    guide and confine the flow of a river channel in a defined course

    and to control and regulate the river bed configuration for effective

    and safe movement of floods. The basic purpose of river training

    works in railways context may be said to be of two folds as under .

    (1) To guide the river through the bridges within a constricted

    water- way with as little obliquity as possible.,

  • Page 2 of 72

    (2) To fend the river off the bridge approaches in order to keep in-

    tact the line of flow communication.

    3. DIFFERENT TYPES OF RIVER TRAINING WORKS

    Various types of river training works generally adopted on

    Indian Railways are :

    (1) Guide Bunds

    (2) Spurs

    (3) Marginal bunds

    (4) Closure bunds

    (5) Assisted cut offs

    However choice for adaptation of any particular type or a

    combination of above river training works depends on various

    factors specific to any particular site conditions. In the present

    paper, two case studies have been dealt with in detail to

    emphasize the above aspects.

  • Page 3 of 72

    4. DESIGN OF RIVER TRAINING WORKS :

    4.1 GUIDE BUNDS :

    Aspects of design of guide banks include their shape in plan,

    waterway between them; their lengths upstream and downstream

    of the bridge axis; curved heads; cross- sections; measures for

    their bank and toe protection against scour.

    4.1.1 PLAN- FORM:

    In plan, the guide banks can either be parallel to each other,

    converging upstream or diverging upstream. However, the actual

    form of guide banks depends upon the local topography, location

    of the bridge with respect to banks, flow conditions in the river and

    the alignment of the approach embankments and is best decided

    by the model studies.

  • Page 4 of 72

    4.1.2 Waterway:

    The first step in the design of a bridge on an alluvial river is the

    estimation of the minimum and also a safe waterway. Laceys

    (1929) wetted perimeter P as given by equation no. (1) is used as

    a good guide for providing the clear waterway between the

    abutments.

    Q75.4P = (1)

    where,

    P is expressed in meters

    Q is flood discharge in m3/sec

    4.1.3 LENGTH OF GUIDE BUNDS :

    Figure 3 shows a typical layout of a straight and parallel

    guide bank. According to Springs the straight length of the guide

    bank L1 on upstream of the bridge is 1.1 L, and on downstream

    side L2 is 0.25L, where L is the length of the bridge between the

    abutments.

    4.1.4 RADIUS OF CURVED HEAD :

    For designing the curved heads both upstream and

    downstream (Fig. 3), following recommendations are followed:

    For upstream head R1 = 2.2 Q , sweep angle q1 =1200 to 1450

    For downstream head R2 = 1.1 Q , sweep angle q2 =450 to 600

    Here R1 and R2 are expressed in metres and Q in m3/sec

  • Page 5 of 72

    4.1.5 TOP WIDTH AND FREEBOARD :

    The top width of the guide banks should not be less than 3.0

    m and is generally kept between 6.0m to 9.0m to allow for the

    movement of vehicles carrying construction material. Side slopes

    are generally 2H: 1V. Freeboard 1.5m to 2.5m above the

    anticipated maximum flood level of 100-year flood. Alternatively, a

    freeboard of 1.0m is added to the high flood level of a 500-year

    flood for getting the top level of the guide bank.

    FIGURE 3 LAYOUT OF A GUIDE BUND

    Deepest Scour Hole

    1:2 (V:H)

    Launching Apron

    H.F.L.

    Section A-A

    Section B-B

    H.F.L. H.F.L.

    Launching Apron

    Deepest Scour Hole

    2 2R = 1.1 Q2

    R2

    R = 2.2 Q1

    1

    R1

    1

    A A

    B

    B

    1

    2

    Flow

    L = 1.1L

    L = 0.25L

    1

    Top Width

    Rear Apron

    Side Slope

    Front Apron

    Axis of the Bridge

    L

    L

    q = 120 to 145

    q = 45 to 60

    1:2 (V:H)

    q

    q

    o

    2

  • Page 6 of 72

    4.1.6 Stone Pitching On Sloping Sides And Launching Apron:

    The sloping face of the guide bank as well as its nose are

    susceptible to severe erosion by the river flow, therefore, they are

    protected by large size stones . Normally the thickness of such

    stone pitching on the slope is estimated by the following empirical

    equation given by Inglis (Garde and Ranga Raju, 2000)

    T = 0.04 to 0.06 Q1/3 (2)

    where,

    T = Thickness of the pitching in metres and Q is in m3/sec

    This pitching should extend upto 1.0m higher than the

    expected maximum flood level. Further, it should be ensured that

    the minimum size of the boulder used in this pitching is such that it

    is not washed away during flood. This minimum size of stones of

    relative density 2.65 may be calculated by the following empirical

    equation as given by Garde and Ranga Raju (2000).

    dmin = 0.023 to 0.046U2max

    (3)

    in which

    dmin is expressed in m, and U max is the maximum velocity of

    flow (in m/s) in the vicinity of guide bank.

    A geosynthetic filter or a conventional sand gravel filter

    0.30m thick is generally placed on the sloping bank of the

  • Page 7 of 72

    guide bank facing river flow to prevent washing out of fine

    material from the subgrade or backfill and the pitching is

    provided over this filter. The pitching is placed in a closely

    packed formation inside a grid formed by masonry walls of

    0.30m width provided along the bank slope at a spacing of

    6.0m measured in the direction of flow.

    4.1.7 LAUNCHING APRON :

    Figure 4 shows the general arrangement of the launching

    apron that is generally provided at the head and the shank of

    the guide bank to prevent undermining of the bank pitching

    and consequent failure of the guide bank. The design of the

    launching apron involves the estimation of the maximum

    scour that is likely to occur at different portions of the guide

    bank and the provision of the adequate quantity of stone to

    cover the face of the scour hole at that location.

    Inglis (Garde and Ranga Raju, 2000) has related this

    maximum scour depth D1 to Laceys depth R as per the

    following relation:

    D1 = XR (4)

    where,

    R = 0.473/1

    fQ (5)

  • Page 8 of 72

    Here D1 and R are both measured from the high flood level

    and are expressed in metres; Q is in m3/sec and f is Laceys

    silt factor given as

    f = 1.75 50d (6)

    in which d50 is the median size of the bed material in mm and

    the coefficient X is taken from Table1.

    Table1 Values of X in Equation (4)

    Location Value of X

    Scour at straight spurs facing upstream 3.8

    Scour at straight spurs facing downstream 2.25

    Scour at nose of large radius guide banks 2.75

    Transition from nose to straight portion of

    guide bank 2.25

    Straight portion of the guide bank 2.0

    It is assumed that the launching apron placed on the river

    bed would launch into the scour hole to take a slope of IV: 2H with

    an average of 1.25T. To ensure this volume of boulder material,

    the average thickness of the launching apron on the riverbed

    comes to 1.86T.The apron is originally laid on the riverbed in a

    width of 1.5Ds where Ds is the scoured depth measured below the

    bed at that location.

  • Page 9 of 72

    To account for the non-uniformity in launching, the thickness

    of the apron calculated above is provided in the form of a

    wedge as shown in Fig.4.

    FIGURE 4 DETAILS OF A LAUNCHING APRON

    Thus, making use of Table 1 and Fig.4, the widths of the

    launching apron at various locations of the guide bank can be

    estimated. Smooth transitions need to be provided to

    accommodate the varying widths of the apron.

    4.2 PERMEABLE SPURS

    Permeable spurs have been used more often for bank protection

    than for diverting the flow. These spurs stabilise a reach of the

    river by inducing siltation along the bank from which they are

    H.F.L.

    Average Thickness 1.25T after Launching

    River Bed

    Deepest Scour

    1.5 T

    20 cm Soling of Ballast

    1:2 (V:H)

    Boulder Pitching

    Total thickness including Soling (T)

    2.25Ds

    1:2 (V:H)

    sD

    1D = xR

    Launching Aprons

  • Page 10 of 72

    projected. They are generally provided as a series of spurs

    projecting from the bank, which requires protection against

    erosion. Design considerations include their cross-section, length

    and spacing, stability and protection against scour.

    4.2.1 CROSS- SECTION :

    Spurs are built of rectangular section with a top width of about 1.50

    m. Vertical ballies' (wooden piles made of bamboos) are driven in

    two rows at the spacing equal to top width of the spur. They are

    tied longitudinally, laterally and diagonally for achieving greater

    rigidity and strength. The space between the two rows of ballies'

    is filled with brushwood and stones. The recommended

    thicknesses of brushwood and stones to be placed in alternate

    layers are 0.90 m and 0.30 m respectively. It is also suggested that

    the spur should have a permeability of about 40%.

    4.2.2 LENGTH AND SPACING :

    There is no specific information available regarding length of these

    spurs. The length is however decided mainly from the

    consideration that these spurs are required to promote silting and

    not to deflect the current away from the bank. Further, short spurs

    would have comparatively less hydrodynamic force on them

    thereby reducing the chances of their failure. The width of the river

    is also considered in fixing the length of the spur. For the railway

  • Page 11 of 72

    bridge at Garhmukteshwar the width of the river during high flood

    in the reach affected by bank erosion was 300.0 m and permeable

    spurs of 10.0 m long were proposed.

    4.2.3 STABILITY OF PERMIABLE SPUR :

    The main criterion for the stability of the spur is that it should

    not overturn under the various forces that act on it. The stability on

    the basis of this criterion should be examined both in the

    unscoured and scoured conditions. Therefore, the length of the

    ballies below the riverbed should be adequate to ensure their

    stability.

    For the stability analysis, the spur is considered as a

    permeable, two-dimensional anchored pile. The various forces to

    be considered per unit length of the spur are as below and are

    shown in Fig.5

    (i) Drag force , FD

    (ii) Soil resistance, Fs

    (iii) Self weight of the spur, W

  • Page 12 of 72

    The method of estimating these forces is given below:

    FIGURE 5 FORCES ON THE SPUR

    Drag force, FD :

    The drag force per unit length is conventionally expressed as

    FD = C D 21 f U

    2 Hs (7)

    in which CD is the drag coefficient of the spur, r f is the density

    of water, Hs is the height of the spur above the river bed. Here

    the value of CD can be estimated using the results of Ranga Raju

    et al.(1988) for the flow past porous fences as shown in Fig.6.

  • Page 13 of 72

    FIGURE 6 RELATIONSHIP FOR CD

    In this figure d is the thickness of the boundary layer, Hf is

    the height of the fence and h is its porosity. The relationship shown

    in Fig. 6 does not consider the effect of blockage on CD. As the

    length of the spur is generally quite small in comparison to river

    width, the effect of blockage on CD could be ignored. For the spur

    projecting from the river bank, Hf is taken as the length of the spur

    and d as equal to half the width of the river

    The value of CD also depends on the angle of inclination of

    the spur. However, the results of Ranga Raju and Garde (1969)

    show that for the angle of inclination between 600 and 900, the

    value of CD remains practically constant.The drag force FD may

    be taken to act at Hs/2 above the river bed level.

  • Page 14 of 72

    Soil resistance, Fs :

    For considering the overturning of the spur about its base, the soil

    resistance Fs per unit length of the spur is computed using the

    following equations (Ranjan and Rao, 1991)

    Fs=21 g, (kp - ka ) D

    2 (8a)

    kp = tan2 (45 + j /2 ) (8b)

    ka= tan2 (45 - f /2 ) (8c)

    Here g, is the submerged weight of the soil, f is the angle of

    internal friction and D is the depth of ballies below the river bed. In

    calculating the value of Fs from Eq.(8), the extra resistance

    offered by the launching apron has not been considered. This

    assumption would give the value of Fs on the conservative side.

    The line of action of the force Fs is at 2D/3 below the river bed

    level.

    Self weight of the spur, W:

    The self weight of the spur, W, per unit length may be computed

    as

    W = s b (Hs + D) (9)

    in which s is the submerged unit weight of the spur material

    and b is the width of the spur. This weight acts vertically down

    at b/2 through the centre of gravity of the spur.

  • Page 15 of 72

    4.2.4 STABILITY ANALYSIS IN UNSCOURED CONDITION :

    Figure 7 shows the forces on the spur in the unscoured

    condition. The unknown grip length D of the spur below riverbed

    could be calculated with these forces and adopting no tension

    criterion in which resultant of all the forces passes through a point

    within the middle third of the base.

    FIGURE 7 FORCES ON THE SPUR IN UNSCOURED CONDITION

    Stability analysis for the required grip length with scour

    Figure 8 shows the spur, with deepest scour at its nose and the

    resulting launched position of the apron.

    As can be seen from this figure, the soil has a sloping profile of

    IV:2H below the bed level. For the computation of soil resistance in

  • Page 16 of 72

    this case, the effective depth of soil has been assumed as 2/3D

    instead of the full depth D. This is shown as equivalent horizontal

    soil level in Fig.8. Here D is the required grip length below riverbed

    level. Following the criterion of no tension at the toe, the required

    grip length D can be worked out. The resistance offered by the

    launched apron will provide additional margin of safety.

    FIGURE 8 FORCES ON THE SPUR IN SCOURED CONDITION

    4.2.5 Stabi lity of spur at the riverbed level

    In analyzing the stability of the spur at the riverbed level, it is

    assumed that the grip length as estimated on the basis of scour

    condition will provide enough rigidity at the riverbed level for

    considering the bending of the spur. This bending needs to be

    considered under the action of various forces acting on it above

  • Page 17 of 72

    the riverbed level. Schematic diagram showing forces on the spur

    above the riverbed level is shown in Fig.9.

    FIGURE 9 FORCES ON THE SPUR ABOVE THE RIVERBED LEVEL

    Also, the spur above the riverbed may be assumed as a solid

    structure though it will function as a permeable spur to start with.

    The assumption is on the conservative side. The analysis requires

    permissible stresses on the ballies used for the spur. These

    stresses depend on the grade of the timber used for ballies and

    are given in National Building Code of India (1970). Knowing

    forces shown in Fig.7, the analysis can be carried out to determine

    the factor of safety against overturning and stresses at the toe and

    heel of the spur. The width of the spur could be modified if required

    on the basis of such an analysis. Protection against scour at the

    nose of these spurs is provided in the form of the usual launching

    apron.

  • Page 18 of 72

    5. CASE STUDY NO. 1: RIVER TRAINING AND PROTECTION

    WORKS AT BRIDGE NO. 52 ON RIVER

    GANGA AT GARHMUKTESHWAR ON

    MORADABAD-GHAZIABAD-DELHI (BG)

    RAILWAY LINE ON NORTHERN RAILWAY.

    5.1 BRIDGE DETAILS(Existing) :

    Span - 11 x 61 m.

    Design Discharges - 7600 cumecs

    Foundation - Well foundation in brick masonry

    (5.00 x 10.00 m round nose & 25 m

    Depth, stein. 1.20 m)

    Rail Level - 204.9 m.

    Bottom of girder - 202.44 m.

    H F L (1924) - 200.25 m

    Danger level - 199.35 m.

    L W L - 195.4 m.

    Permissible scour level - 183.0 m

    Bottom of foundation - 169.7 m

    A Road bridge of span 2 x 53.30m + 11x 54.21 m also exist

    at 180 m on down stream side of this bridge .

  • Page 19 of 72

    5.2 BRIDGE DETAILS(In Progress 30 m D/S of existing) :

    Span - 11 x 61 m.(UP/DN)

    Design Discharges - 8300 cumecs (Return period 50

    year)/12748 cumecs(Return period 2000 years corresponding

    to H.F.L of 1924)

    Foundation -Well foundation in R.C.C 2.5 m Stein.

    - Pier 12 m circular & 48 m Depth with

    - Abut. 12m circular & 46.6 m Depth

    Rail Level - 204.9 m.

    Bottom of girder - 202.44 m.

    H F L (1924) - 200.25 m

    Danger level - 199.35 m.

    L W L - 195.4 m.

    Permissible scour level - 170.25 m

    Bottom of foundation - 147.93 m

    A Road bridge of span 2 x 53.30m + 11x 54.21 m also exist

    at 150 m on down stream side of this bridge and another is in

    progress 14.80m up stream of existing road bridge.

  • Page 20 of 72

    5.3 STATEMENT OF PROBLEM :

    Moradabad-Ghaziabad line of Northern Railway,crosses river

    Ganga near Garhmukteshwar at km 66/8 to 67/4.The Ganga at the

    bridge site ,in alluvium stage with sand (Silt factor 0.9) in its bed, is

    nearly 500 km down stream of its source of origin and catchment

    area is approx. 29709.0 sqkm. At the time of construction, river

    with Khadir width of 7-8 km was flowing hugging its extreme edge

    of khadir on Ghaziabad side.The bridge was constructed in 1900

    with guide bunds 670 m long on u/s side and 150 m long on

    downstreamside for right guide bund.Similarly 460 m long on u/s

    side and 150 m on d/s side for left guide bund were constructed.

    Left guide bund was kept shorter than the right guide bund,

    keeping in view the proximity of the edge of the island. Mr. W.A

    John, who constructed the bridge,clearly recorded that length of

    left guide bund has been purposely kept shorter to allow more

    passage of water in between the guide bund and island.He further

    recorded that if required,its length can be increased.Since

    constrction of this bridge the river has been changing its course

    intermittently causing serious threat to left approach

    embankment,guide bund and also to right guide bund .Till date

    various studies and protective measures have been/are being

    taken.After construction of one spur of 600 feet long during 1903

  • Page 21 of 72

    ,1500 feet away from left, the river straightened itself and caused

    no serious problem till 1947except in 1924 when flow of river was

    only 200 m away from the Matwali bridge and some portion of the

    Ganga flood water was diverted towards Matwali bridge.As such

    breach took place in the approaches of Matwali Bridge.After the

    breach,span was increased from 3x12.2 to 6x12.2m.Depth of well

    foundation was increased from 12.5 m to 21.3 m (for newly

    constructed wells). Two bridges,one each at Chhoiah Nallah

    (Bridge no 50) and Matwali Nallah(Bridge no 51)were provided to

    avoid flooding of water in nearby area for longer duration

    considering that these bridges will pass on the discharge to the

    down stream side.(However it is suspected that during the heavy

    flood, river Ganga also somewhat attracted towards the bank due

    to bridge constructed over Matwali Nallah.Sometime it was feared

    that river may outflank through Matwali bridge.Later on,Railway

    administration corresponded with the State Govt. regarding closure

    but the same could not be materialized on account of resistance of

    the villagers on the plea that they will be mostly submerged in

    water). During the flood of 1948, the river attacked railway bank at

    km 63-64. Member engineering flew over the site and in

    consultation with C.W.P.R.S/Pune the left guide bund was

    extended by 1200 feet with additional curved head of 600 feet

  • Page 22 of 72

    radius. A 4.5 km long diversion was constructed from km 66/11 to

    65/12 .The river immediately after execution of these works

    retreated back. Again in floods of 1950,1954,1956,1977,1996,1998

    some flood repair works were carried out on the left approach bunk

    and the guide bunds by dumping boulders and

    constructing/extendig solid and permeable spurs.During

    1955,nearby Tigree & Lathira villages were endangered and

    Lathira village partly washed away.To protect the villages , one

    spur was constructed thereby tying the river between to obligatory

    points i.e Tigree spur and guide bund of Garhmukteshwar bridge,

    meandering and coming close to embankment .

    For protection measures various further studies were got done by

    Railway from IRI /Roorkee in 1978,1980 ,from IIT/Roorkee in

    1997,1999. Based on them a large number of solid and permeable

    spurs have been provided on the left bank of the river for

    controlling the flow so that the railway embankment is not subject

    to bank erosion.(In 1996 & 1998 in a reach X1X2 (a distance of

    about 825m) as shown in Fig.l,in fact at location 64/7 km on this

    reach, the river is only 70. m away from the centre line of the track

    and is subject to serious bank erosion. Therefore protective

    measures were to be taken immediately).A barrage 70 km

    upstream has also been commissioned in 1988 from which canal

  • Page 23 of 72

    takes off from right bank.

    However, before a further detailed physical model study

    could be conducted, a new Railway Bridge as well as a new

    roadways were also sanctioned for construction within 180 m in

    down stream side of existing Railway Bridge and in up stream side

    of existing road bridge. Keeping in view the fact that the

    construction of these two new bridges in close vicinity of existing

    bridges may further affect the river behaviour, it was thought

    prudent to have a fresh detailed study including physical model

    study taking holistic consideration of all aspects including effect of

    existing and proposed ghats. Accordingly department of civil

    engineering of IIT Roorkee along with Irrigation Research Institute,

    Roorkee were asked for a detail study and interactive design.

    Based on their recommendations submitted in year 2004 various

    further measures as detailed below are being adopted at site.

  • Page 24 of 72

    5.4 RECOMMENDED REMEDIAL ACTIONS TAKEN IN

    VARIOUS STAGES :

    (I) Year 1903:

    600 feet left embankment spur at 1500 feet from abutment

    constructed.

    (II) Year 1948: River main channel was only 480 feet away from

    track. . On Member engineering visit to site and in

    consultation with C.W.P.R.S/Pune the left guide bund was

    extended by 1200 feet with additional curved head of 600

    feet radius. A 4.5 km long diversion was also constructed

    from km 66/11 to 65/12 .

    (III) Year 1950: UP Govt. constructed a spur to save village tigri

    situated 8 km u/s of bridge.However since then the river has

    been flowing hugging this spur and passing through railway

    bridge.

    (IV) Year 1954: Repairs by dumping boulders along railway

    embankment & linking track on diversion.

    (V) Year 1956-58: IRI/oorkee recommended curved mole head

    for right guide bund and 3500 feet long spur at km 63-

    64.Somehow none of these proposal materialized.

    (VI) Year1977: Diversion repaired with 16 feet bank width and

    1.5 : 1 side slope.A reseve stock of 1lakh cft of boulders at

  • Page 25 of 72

    km 63-64 was also collected and kept.With the

    commissioning of earthen dam over river Ramganga at

    Kalagarh the dry weather flow of river ramganga is

    discharged in River Ganga 4 km u/s of village Tigri to

    augment discharge of lower ganges canal taking off from

    Narora Since the current at km 63/7-8 was 10-12 feet deep

    the const. Of even small spures to arrest the local erosion

    could not be taken up as time leftover was very little.

    (VII) Year 1978: IRI/ROORKEE in1978( report no50) suggested

    two spurs one 250 m long at km 64.06 and another 400 m

    long at km 65.50 normal to the track based on model study.

    (VIII) Year 1980: IRI/Roorkee in1980( report no51) suggested (i) A

    kinked spur having 60 m shank length and 90 m nose at 165

    degree included angle at km 63.75(ii) Existing 50 m long

    inclined spur at km 65 may be extended straight normal to

    track beyond its nose making total length 100m.(iii) A mole

    head of radius 200m at 120 degree sweep angle may be

    provided to the nose of right guide bund.

  • Page 26 of 72

    (IX) Year 1981 :

    (i) 305 Nos. large size trungers dropped around the nose of

    spur at KM: 63 /12.

    (ii) 3000 trees planted on the RGB, LGB and along the bank of

    Ganga.

    (iii) Turfing of the slops of retarded alignment was done.

    (X) Year 1997 :

    Department of civil engineering of the then University of

    Roorkee had suggested in its 1st report that following action should

    be taken as short term measures to safeguard the bridge guide

    bunds an its approach embankments from any threat in oncoming

    monsoon.

    1. Twenty five permeable dikes 5. 0m long at a spacing

    of 30 m and at locations shown in Fig.15 be

    constructed on the left bank of the river. The construction

    details of the dikes and the launching apron are given

    in Fig.16.

    2. A pilot channel 10.0m wide, 1.0m deep and 225.0 m

    long be excavated on the existing bed opposite the

    proposed location of the dikes to reduce the discharge

    intensity in the main channel in the vicinity of the dikes.

  • Page 27 of 72

    3. Sandbag revetment be provided on the left bank

    both upstream and downstream of the proposed

    dikes. The length of revetment may be 100.0m on

    the upstream side and 50.0m on the downstream side.

    While follow up action on item No. 1 and 3 were taken at site,

    action on item No. 2 was deferred till detailed model study as its

    efficacy was considered doubtful.

    (XI) Year 1999:

    However, before a detailed physical model study as earlier

    recommended by IIT, Roorkee, could be got conducted, serious

    problems were felt in flood of 1998 and 1999. The river came very

    close to the railway embankment over a distance of 825 m posing

    a serious threat to its safety. Nose of exisiting spurs along with

    molehead of the existing left guidebund were seriously damaged.

    Department of a Civil Engineering of IIT, Roorkee were again

    requested to study the following aspects :

    To examine the need of extending the newly built solid spurs.

    Identification of the number and the location of additional solid

    permeable spurs on the left bank of the river

  • Page 28 of 72

    To suggest safety measures for the protection of the molehead of

    the left guidebund of the bridge and the existing solid spurs.

    IIT Roorkee, based on a detailed theoretical analysis

    recommended that

    (a)To extend all the three solid spurs that were built during

    1998(shown in fig.20).

    (b)To build two new solid spurs at locations Km 64/8-9 and 65/4-

    5(Shown in fig. 20)

    (c)To build a series of permeable spurs 5 m long at 30 m center to

    center spacing in the entire affected reach (Shown in fig.20 ).

    (d)To strengthen the molehead of the existing left guide bund and

    the three solid spurs built in 1998.

    (e)To provide stone pitching along the left bankline over a distance

    of 100 m u/s of the existing solid spur at km 64/3-4and over a

    distance of 100 m d/s of the last permeable spur (Shown in fig. 20)

    (XII) Year 2004 :

    As the basic purpose of study conducted in 2004 was to study the

    behavior of river based on holistic approach the scope of the study

    to be conducted by Irrigation Research Institute Roorkee included:

  • Page 29 of 72

    (a) To study the effect of river stream on left and right guide bunds

    and other river training works required to protect railway

    embankment as well as bridge.

    (b) To study for making uniform distribution flow of water from all

    spans of bridges during monsoon.

    (c) Scour depth in the vicinity of bridge piers.

    (d) Shape and section of piers.

    (e) Merging of Nala into right guide bund.

    (f) Any other suitable suggestions.

    A model study based on distorted model of River Ganga from

    about five km up stream to 4 km down stream of existing Railway

    Bridge Built on scales 1 in 250 (horizontal ) and 1 in 40 (Vertical)

    was conducted by Irrigation Research Institute Roorkee to

    examine the efficacy of various measures suggested by

    department of Civil Engineering, IIT Roorkee based on theoretical

    considerations. Various measures suggested by department of

    Civil Engineering, IIT Roorkee based on theoretical considerations

    were as under :

    1. Afflux at the existing railway bridge is expected to be less than

    10.0 cm and the freeboard provided at the guide bunds is

    adequate.

  • Page 30 of 72

    2. The right guide bund is required to be extended on the

    upstream side along its straight length by 107.0 m keeping the top

    width the same as in the existing guide bund, viz. 13.0 m and by

    providing side slopes of IV: 2.0 H. berms on both sides of the

    sloping banks of the extended straight length of the right guide

    bund be provided at the same level as in the existing right guide

    bund viz. 198.058 m. The width of these berms may also be kept

    the same as in the straight portion of the existing right guide bund.

    3. The curved head at the end of the extended portion of the right

    guide bund be provided as per the details shown in Fig. 23.

    4. The bank revetment and the launching apron in the modified

    portion of the right guide bund i.e. straight extended length and the

    curved head be provided as per the details shown in Figs. 23,24

    Geosynthetic filter is recommended instead of sand-gravel filter in

    view of quality control and convenience in its laying.

    5. The mole head of the existing left guide bund be modified as per

    the design proposed for the curved head of the right guide bund.

    The details of the proposed modifications are shown in Fig. 26.

    6. A 850.0 m long pilot channel 10.0 m wide, 1.0 m deep with

    1V:2.0 H side slopes as shown in Fig. 18 be excavated on the

    existing' island along the left guide bund to reduce the

    concentration of main flow on the right bank of the river. The

  • Page 31 of 72

    channel is to be excavated below the existing surface level of the

    island.

    7. Provision of Ghats on the upstream side on the right guide bund

    is recommended as such a provision is not expected to alter the

    flow characteristics from what have already been considered in the

    present design. The rise and the tread of the steps in these Ghats

    would however, need adjustments as per the existing and the

    proposed side slopes of the right guide bund.

    However during the detailed model study by Irrigation Research

    Institute Roorkee, it was found that extension of right guide bund

    by 107 m in upstream and construction of a pilot channel as

    suggested by IIT Roorkee have no effect on activating the left side

    spans and channel was found to get silted during the recession of

    flood as such these two items were dropped and various other

    measures as suggested by IIT Roorkee and found to be

    satisfactory in Irrigation Research Institute Roorkee Report are

    being implemented at site as detailed (fig. 22)

    6. Case study II :

    River training and flood protection works between Br. No. 97

    and Br. No. 98 between Palian Kalan Bhirakheri Station on

    Mailani Gonda (MG) Section of N.E. Railway.

  • Page 32 of 72

    6.2 Details of Br idge No. 97

    Rail cum Road Bridge 19 x 24.38 m

    Location 241/ 1-5

    Rail Level 158.95 m

    Maximum scour Level 14.85 m below Rail Level

    Bottom of Girder 156.80 m

    Danger Level 155.00 m

    Top of Foundation 7.68 m below Rail Level

    Bottom of Foundation 25.98 m below Rail Level

    Highest Flood Level 155.32 m (1934)

    Length of Guide Bund (Plain end) 472 m

    Length of Guide Bund (Bhira end) 500 m

  • Page 33 of 72

    6.2 Details of Bridge No. 98

    Rail Bridge Span 9 x 6.1 m + 1 x 12.2 m

    Location 247/ 7-8

    Rail Level 157.38 m

    Top of Girder 157. 16 m

    Bottom of Girder 155.80 m

    Danger Level 155.20 m

    Floor Level 153.375 m

    Highest Flood Level 156.32 m (1987)

    Length of Guide Bund (Plain end) 77 m

    Length of Guide Bund (Bhira end) 73 m

    Statement of Problem

    River Sharda crossed the Mailani Gonda (MG) Railway

    Line through a 501.92 m long rail-cum road bridge no 97 in district

    Lakhimpur Kheri. Earlier the river course was almost straight and

    perpendicular to the bridge. However during last 10 years the river

    Sharda, due to meandering towards right has taken a sharp curve

    in which flow is taking about 180 degree turn and river has come to

    very close (even up to 15 m) to the railway embankment posing

    serious threats to its safety (Fig. 27). Furthermore due to its

  • Page 34 of 72

    meandering and coming very close to the Railway track, a

    significant part of River flow has started passing through a smaller

    bridge No.98 (9x 6.1 +1 x 12.2. m) situated in u/s side of bridge

    No. 97. It is apprehended that flow of exceptionally high discharge

    through bridge No. 98 and parallel to Railway embankment in

    close proximity of 15-30 m may cause serious damage to the

    bridge No. 98 and Railway embankment in this stretch. Discharge

    in the river Sharda is controlled by a barrage of UP Iriigation Dept

    at Banbasa which is approximately 100 km of u/s of bridge No. 97.

    6.3. RECOMMENDED REMEDIAL ACTIONS.

    Originally the river Sharda was flowing quite away from the

    Railway embankment between bridge No. 97 and 98 and was

    crossing bridge No. 97 almost perpendicular to the track. However

    it started meandering towards Railway embankment around 1990.

    There upon UP Irrigation Department was requested to under take

    necessary river training works. Accordingly UP Irrigation

    department planned a scheme of Rs. 1.36 Cr. in the year 1990.

    But no work was actually done by them.

    Thereafter UP state Irrigation department again finalized a

    scheme of provision of 40 No. spurs (16 m long @ 60 m c/c at a

    cost of Rs 1.84 cr.) to control its meandering. However only 3

  • Page 35 of 72

    spurs out of 40 could be constructed which were also seriously

    damaged in monsoon.

    In the mean time, U.P govt. appointed a committee of three

    chief engineers to study the problem and suggest remedial

    measures .The committee has recommended provison of sufficient

    no of spurs along with a cunnette/marginal bund. Based on above

    a detailed model study was conducted by irrigation research

    institute Roorkee ,which recommended construction of 10 km long

    cunnette along with a 12 km long bund with boulder pitching, which

    was estimated to cost rs 164.64 cr.

    Since then Railway has been consistently requesting the UP

    Irrigation Department to undertake necessary river training works

    but no work was actually done by them. In the mean time the river

    came very close to the Railway embankment and Br No. 98,

    posing serious threat to its safety itself. To ensure the safety of

    Railway embankment & Br. NO. 98, following works were executed

    by Railway in different stages:

    (i) Construction of 35 no spurs in different stages(Fig. 28 & 35).

    (ii) Strengthening and extension of the guide bund of Br. No. 98.

    (iii) Strengthening of the flooring system of Br. No. 98 (Fig. 34).

  • Page 36 of 72

    However as the cost of the river training works as suggested

    by IRI Roorkee was exorbitantly high , UP Irrigation department

    again referred this problem to Irrigation Research Institute

    Roorkee to suggest alternative cost-effective river training works

    taking into account various flood protection works already

    executed at site by Railway dept. After a detailed physical model

    study in Jan 2004 considering following alternative

    (a) Provision of 8.65 km long marginal bund with 100 m

    wide cunnette at 350 m from bund (Fig. 36).

    (b) Provision of 11 km long marginal bund with 200 m wide

    cunnette at 275 m from bund (Fig. 37).

    (c) Provision of 11.10 km long marginal bund with 200 m wide

    cunnette at 685 m from bund (Fig. 38).

    (d) Provision of 4.10 km long marginal bund from Railways existing

    spurs (Fig. 39).

    (e) Provision of 4.10 km long marginal bund with spur and

    extention of 8 nos Railways existing spurs (Fig. 40).

    IRI Roorkee in its report of march 05 has recommended for

    Construction of 4.00 km long marginal bunds along with spurs /

    studs along the right bank of river Sharda in up stream of the

    Railways flood protection work (and Bridge No. 98) and extension

    of existing 8 no. spurs constructed by the Railway. It also

  • Page 37 of 72

    recommended that extension of existing spurs along Railway

    embankment and construction of new spurs along proposed

    marginal bunds should be constructed in 1 working season. It is

    estimated to cost approximately Rs. 25 Cr.

    However there is now a dead lock about financing of the

    above scheme. State Government is demanding the full fund from

    the Railway on the pretext that this work is to be executed by

    them for protection of Railway bridge and track , and therefore

    full cost is to be given by the Railway. However Railway is

    opposing the above on the ground that this work is not for safety of

    Railway bridge and track only but also for the safety of Civil area.

    Further more the Railways also say that scope and cost of work

    has increased so much only because of timely action not taken by

    state govt. and therefore Railway is not liable to pay. This issue

    needs to be resolved still.

    Br. No. 98 has got 9 girders of span 6.1 m each and 1 girder

    of span 12.2 m. The bottom of girder of 12.2 m span is 590 mm

    below the bottom of the girder of 6.1 m span due to which many

    times water level in 12.2 m span comes above bottom of its girder

    whereas water level in other spans of 6.1 m length still below

    bottom of girders necessitating suspension of traffic. As such

    changing of girder of 12.2 m span with the restricted height has

  • Page 38 of 72

    been got sanctioned and is to be executed during current year so

    that suspension of traffic on this account may be eliminated.

    7. CONCLUSION :

    7.1 It is seen from the above case studies that timely action in

    provision of various river training works not only mitigates

    serious threat to the safety of Railway bridges and

    embankment at later stages but also prevents many fold

    escalation of cost.

    7.2 It is also noted that many times obvious theoretical measures

    contemplated for river training works may not be required at

    all or may even be counter productive. Therefore it is

    desirable to go for detailed physical model studies before

    undertaking any major river training works.

    7.3 The River Training works after model study should be

    implemented expeditiously i.e. without delay.

    7.4 Trees planted on and along guide bunds/ spurs serve as

    natural protection measures.

    7.5 For more effective results spacing of solid spurs should be

    kept between 2 to 3 times of their lengths & permeable spurs

    used for bank protection be spaced at 5 to 6 times their

    length.

  • Page 39 of 72

    7.6 Distribution of discharge through all bays useful for safety

    and economy of bridge can be achieved through suitable

    river training works like bed bars etc.

    7.7 Execution of river training works require special attention.

    The mole head of the left bank of Ganga Bridge need

    Geometric correction and left bank spurs need further

    strengthening keeping in view HFL of 1924.

    8. ACNOWLEDGEMENT :

    Authors gratefully acknowledge the assistance and guidance given

    by Shri N.C. Sharda, Sr. Professor Works, Indian Railways

    Institute of Civil Engineering, Pune for the Project Report.

    9. REFERENCES :

    i. Indian Railways Bridge Manual 1998

    ii. River Behaviour management and Training, Publication No.

    204, Volume 1 1989 by Central Board of Irrigation and power

    N. Delhi

    iii. Indian Railways Standard Code of Practice for the Design of

    Substructure and foundations of Bridges.

    iv. Member Engineering, Railway Board New Delhi, Technical

    Paper No. 6.

    v. Irrigation Research Institute Roorkee Report No. 50 of 1978.

    vi. Irrigation Research Institute Roorkee Report No. 51 of 1980.

  • Page 40 of 72

    vii. Irrigation Research Institute Roorkee Report No. 75 RR

    (H105 ) of 2004.

    viii. Irrigation Research Institute Roorkee Report No. 75 RR (H1

    07 ) of 2005.

    ix. Report on Protection of Left Bank of the River Ganga

    Near Garhmukteshwar Railway Bridge of Department of

    Civil Engineering of IIT Roorkee dated Jun1997.

    x. Report on Measures for Control of Erosion of Left Bank

    of the River Ganga Near Garhmukteshwar Railway

    Bridge of Department of Civil Engineering of IIT Roorkee

    dated Mar 1999.

    xi. Proceedings of Workshop on Bridge scour, River Training

    and Protection works by Department of Civil Engineering and

    Bridge Engineering Group of IIT Roorkee dated Oct 2003.

    xii. Final Report on Hydraulics Design of Proposed Railway

    Bridge on the River Ganga at Garhmukteshwar of

    Department of Civil Engineering of IIT Roorkee dated July

    2004.

    xiii. IS:10751 (1994), Planning and design of guide bunds for

    alluvial rivers, Guidelines, BIS, New Delhi.

    xiv. Lacey G. and Inglis, C.C. (1944), Maximum depth of scour

    at heads of guide banks, groynes, pier noses and

  • Page 41 of 72

    downstream of bridges, Annual Report (Technical),

    CWPRS, Pune.

    xv. Ranga Raju, K.G.(1993), Flow through open channels , Tata

    McGraw Hill Publishing Company Limited, New Delhi.

    xvi. Ranga Raju, K.G., Mittal, M.K., Verma, M.S. and Ganeshan,

    V. (1980), Analysis of flow over baffle blocks and end sills ,

    Jour. of Hyd. Research, Vol. 18, No. 2, pp. 227-241.

    xvii. River Training and Protection Works for Railway Bridges.

    Published by IRICEN, Pune.

  • Page 42 of 72

    FIG 1: TYPICAL LAYOUT OF GUIDE BUND

  • Page 43 of 72

    FIG.2

  • Page 44 of 72

    FIGURE 10 : COURSE OF RIVER GANGA IN 1900 AND 1978 AT

    GARHMUKTESHWAR RAILWAY BRIDGE

    U.P. I R I ROORKEE TRAINING OF RIVER GANGA AT GARHMUKTESHWAR BR. NO. 52

    INDEX PLAN

    1978

  • Page 45 of 72

    FIGURE 11: TOPOGRAPHICAL AND HYDROLOGICAL MAP OF GANGA BRIDGE NO. 52

  • Page 46 of 72

    FIG

    .12

  • Page 47 of 72

    FIG

    .13

  • Page 48 of 72

    FIG

    . 14

  • Page 49 of 72

    FIG

    . 15

  • Page 50 of 72

    FIGURE 15a :

    COURSE OF RIVER GANGA IN 1996 AT GARHMUKTESHWAR

    RAILWAY BRIDGE

    Dry Channel (B)

    Railway Crossing No. 49

    km 64/7X2

    X1

    km 65/0

    BarLeft Guide Bank

    km 66/0

  • Page 51 of 72

    FIGURE 16: PLAN VIEW OF PROTECTION WORKS USING PERMEABLE SPURS

    30m

    A

    GHAZIABADMORADABA

    DRAILWAY TRACK

    km 64/7

    EXISTING SPUR

    EXISTING BANK LINE PROPOSED DIKES

    PERPENDICULAR TO THE EXISTING BANK

    EXPECTED BANK LINE

    REVETMENT(ABOUT 100m LONG)

    BARPROPOSEDPILOT CHANNEL

    RIVETMENT(ABOUT 50m LONG)

    B

    4

    1

    101520

    25

    5

    X

    X2X

    1

    825m

    RAILWAY CROSSING No. 49

  • Page 52 of 72

    FIGURE 17: DETAILS OF THE PROTECTION WORKS FOR THE SPUR

  • Page 53 of 72

    FIG.18 (a)

    FIG.18 (b)

  • Page 54 of 72

    FIG. 19 : COURSE OF THE RIVER GANGA IN 1997 AND 1998 AT

    GARHMUKTESHWAR RAILWAY BRIDGE NO. 52

  • Page 55 of 72

    FIG. 20 : PLAN VIW OF PROPOSED PROTECTION WORKS FOR LEFT BANK OF GANGA BRIDGE NO. 52 (IITR 1999 REPORT)

  • Page 56 of 72

    FIGURE 21 : PROPOSED SOLID SPUR AT LOCATION 65 / 4 - 3

    H.F

    .L 2

    00.2

    5 H

    .F.L

    200

    .25

    195.

    54 m

  • Page 57 of 72

    FIGURE 22 : FINAL PROPOSAL FOR PROTECTION WORKS

  • Page 58 of 72

    TA

    BL

    E 2

  • Page 59 of 72

    FIG. 23

  • Page 60 of 72

    FIG. 24

  • Page 61 of 72

    FIG. 25

    26

  • Page 62 of 72

    FIGURE 26 : PLAN AND SECTIONS SHOWING DETAILS OF THE MODIFICATIONS FOR THE MOLE HEAD OF THE LEFT

    GUIDE BUND

  • Page 63 of 72

    FIGURE 27 : COURSE OF THE RIVER SHARDA BETWEEN

    1991 TO 2004 BRIDGE NO. 97 & 98

  • Page 64 of 72

    FIGURE 28 : PLAN SHOWING RIVER SHARDA EDGE

    BETWEEN BRIDGE NO. 97-98 AS ON 12-08-2004

  • Page 65 of 72

    FIGURE 29 : VIEW OF RIVER SHARDA DURING FLOOD (TREE PLANTATIO ACTING AS NATURAL PROTECTION MEASURE / SPURS)

  • Page 66 of 72

    FIGURE 30 : VIEW OF RIVER SHARDA DURING FLOOD

  • Page 67 of 72

    FIGURE 31: VIEW OF RIVER SHARDA DURING FLOOD AT BRIDGE NO. 98

  • Page 68 of 72

    FIGURE 32: VIEW OF RIVER SHARDA DURING FLOOD AT BRIDGE NO. 98

    FIGURE 33: VIEW OF RIVER SHARDA DURING FLOOD AT BRIDGE NO. 98

  • Page 69 of 72

    FIGURE 34 : DETAILS OF PROTECTION WORKS OF FLOOR AND EMBANKMENT AT BRIDGE NO. 98

  • Page 70 of 72

    FIGURE 35 : DETAILS OF SPUR OF RIVER SHARDA