29 NEW END CONTACT US The team can be contacted: Via email : [email protected] Via phone : Site Project Manager Nick Tandy (Blenheim House Construction): 07500 014 063 Project Manager Harry Gavriel (Blenheim House Construction): 07826 947 675 NEWSLETTER | JANUARY 2016 An artists impression of 29 New End Welcome to the ninth newsletter on the redevelopment of 29 New End, Hampstead Village, being delivered by The Linton Group. This newsletter provides information on the progress of works taking place on site, details of forthcoming works and how the project team can be contacted. We will continue to liaise with the local community as we carry on with works on site. Members of the project team are always available to answer queries from any local resident using the details provided in this newsletter. We are also continuing to work closely with the London Borough of Camden as we bring forward this redevelopment. Please note that a dedicated project website – www.29newend.co.uk – is providing regular updates and information on the project. The website contains the latest news from site, contact details and forthcoming works. Please do sign up to this to receive alerts of ad-hoc works and the most up to date site news.

29 NEW END NEWSLETTER | JANUARY 2016...NEWSLETTER | JANUARY 2016 An artists impression of 29 New End Welcome to the ninth newsletter on the redevelopment of 29 New End, Hampstead Village,

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 29 NEW END NEWSLETTER | JANUARY 2016...NEWSLETTER | JANUARY 2016 An artists impression of 29 New End Welcome to the ninth newsletter on the redevelopment of 29 New End, Hampstead Village,

29 NEW END

CONTACT USThe team can be contacted:

Via email : [email protected] Via phone : Site Project Manager Nick Tandy (Blenheim House Construction): 07500 014 063 Project Manager Harry Gavriel (Blenheim House Construction): 07826 947 675

NEWSLETTER | JANUARY 2016

An artists impression of 29 New End

Welcome to the ninth newsletter on the redevelopment of 29 New End, Hampstead Village, being delivered by The Linton Group.

This newsletter provides information on the progress of works taking place on site, details of forthcoming works and how the project team can be contacted.

We will continue to liaise with the local community as we carry on with works on site. Members of the project team are always available to answer queries from any local resident using the details provided in this newsletter. We are also continuing to work closely with the London Borough of Camden as we bring forward this redevelopment.

Please note that a dedicated project website – www.29newend.co.uk – is providing regular updates and information on the project. The website contains the latest news from site, contact details and forthcoming works. Please do sign up to this to receive alerts of ad-hoc works and the most up to date site news.

Page 2: 29 NEW END NEWSLETTER | JANUARY 2016...NEWSLETTER | JANUARY 2016 An artists impression of 29 New End Welcome to the ninth newsletter on the redevelopment of 29 New End, Hampstead Village,

Recently completed worksThe demolition operations, which started onsite on Monday 24 October, have now been successfully completed and preparation for ground works are now also complete.

Forthcoming worksGround works on site commence early February 2017 and will be carried out by a new sub-contractor, Leander, over the next two months. Works they will carry out include:• Completing the removal of the wall and the footing along Christchurch Passage• Preparing ground levels and laying a stone layer over the ground to accept the piling rig for the works to the perimeter wall• Getting ready the front entrance access point for the delivery lorries• Preparing the ground at the front of the site in readiness for the tower crane base• Getting the access road through the site ready for the delivery of the piling rig and associated plant which is planned to arrive

on site in April

Piling works will then begin in April.

HoardingBranded hoarding will be installed around the site within the next week or so. The hoarding will include reference to the new name for 29 New End – Novel House – which has been chosen to reflect the significant literary history of Hampstead and its environs.

No works on the hoarding will take place before 9:30am. Whilst the new hoarding is being erected, the highway will be temporarily reduced in width. We will notify you of further details once the commencement date has been confirmed via the website and e-alerts. Please visit the website to sign up to the e-alerts if you would like to receive these and have not done so already.

Appointment of independent monitorAlistair Redler from Delva Patman Redler LLP has been appointed by Linton on behalf of the Construction Working Party (CWP) to independently assess the noise, dust and vibration monitors onsite.

Christchurch PassageChristchurch Passage was reopened on Monday 9 January following the completion of the temporary works, scaffold gantry and hoarding works. Lighting and CCTV cameras have been installed in the passageway for security purposes. Blenheim will be responsible for the upkeep of the passage including regular sweeping, putting salt down in case of slippery conditions and painting over any graffiti that might appear.

29 NEW END

CONTACT USThe project team are available at all times to answer questions from residents. The team can be reached in the following ways:

Email: [email protected]

Community Liaison Officers Duncan Hepburn or Keziah Harrison will be available to answer queries and will reply as soon as possible.

Via phone: Site Project Manager Nick Tandy (Blenheim House Construction): 07500 014063. Project Manager Harry Gavriel (Blenheim House Construction): 07826 947675

Nick and Harry are based on site and are available to answer questions. They can be found on the top floor of the Village Shul so please do call or visit them if you have any queries.