Upload
dequanzhou
View
11
Download
0
Embed Size (px)
DESCRIPTION
Hydraulics
Citation preview
0
Hydraulics and Sedimentation Study for the San Dieguito River Wetland Restoration Project
Prepared for Environmental Services Southern California Edison Company 2244 Walnut Grove Avenue P. O. Box 800, Rosemead, CA 91770
Prepared by Howard H. Chang, Ph.D., P.E. May 2004
Chang Consultants Hydraulic and Hydrologic Engineering Erosion and Sedimentation
P. O. Box 9492 Rancho Santa Fe, CA 92067 TEL.: (858) 756-9050 FAX: (858) 756-9460
1
TABLE OF CONTENTS
GLOSSARY OF TERMS…………………………………………………………………..1
EXECUTIVE SUMMARY …………………………………………………………………3
I. INTRODUCTION……………………………………………………………………… 5
II. BASIC HYDROLOGY……………………………………………………………….. 8
Floods……………………………………………………………………………… 8
Sediment Data……………………………………………………………………… 10
Effective Flow Area and Ineffective Flow Area…………………………………… 12
III. METHODS OF ANALYSIS………………………………………………………….. 13
Mathematical Model for General Scour ……………………………………………13
Selection of the Engelund-Hansen Formula………………………………………. 13
IV. HYDRAULIC DESIGN FOR A WEIR ON NORTHEASTERN BERM……………. 15
Rating Curves for Weir Flow……………………………………………………… 16
Modification of Flood Hydrograph………………………………………………… 19
Effects of Weir on Tidal Basin…………………………………………………….. 19
Summary and Conclusions………………………………………………………… 20
V. MODELING FOR EXISTING CONDITIONS AND PROPOSED CONDITIONS….. 21
Channel-Bed and Water-Surface Profiles Based on the FLUVIAL-12 Model …… 22
Spatial Variations in Velocity Along the River Channel………………………….. 26
Bridge Hydraulics…………………………………………………………………. 27
Simulated Results on Scour………………………………………………………. 27
VI. BEACH SAND SUPPLY……………………………………………………………… 41
Simulation of Sediment Delivery………………………………………………….. 42
Simulated Results on Sediment Delivery by the 100-yr Flood …………………… 44
Simulated Results on Long-Term Sediment Delivery………………………………46
VII. DESIGN FOR BERMS AND BANK PROTECTION………………………………..46
Top Elevation of Berms …………………………………………………………….46
Top Elevation and Toe-Down for Bank Protection ……………………………….. 47
REFERENCES…………………………………………………………………………… ..50
2
LIST OF FIGURES…………………………………………………………………………50
APPENDIX A. MAXIMUM SCOUR PROFILES AT BRIDGE CROSSINGS FOR 100-YR FLOOD
APPENDIX B. MAXIMUM SCOUR PROFILES AT BRIDGE CROSSINGS FOR 50-, 25- AND 10-
YR FLOODS
1
GLOSSARY OF TERMS
Aggradation: A rise in channel bed elevation, usually caused by sediment deposition. Alluvial: Relating to, composed of, or found in alluvium Bank protection: A structure placed on a riverbank to protect the bank against erosion. Such structures are usually made of riprap stones, revetments, dikes, etc. Bed load: That part of the sediment load that travels in contact with the bed by rolling, sliding and saltation. It is also the coarser portion of the sediment load. Channel reach: Any stretch of the channel. Channelization: To make a channel. Cross sections : Channel sections that are perpendicular to the flow direction that are used to define the river channel geometry for a river study. Degradation: A lowering of the channel-bed elevation usually caused by erosion. Drainage basin: A surface area from which rainfall drains toward a single point. Drop structure : A rigid structure erected across a river channel through which there is a drop in channel-bed elevation. Erodible boundary model: A model that considers the changes in channel boundary, including channel-bed scour and fill, changes in channel width and changes related to channel curvature. Erodible bed model: A model that only considers the changes in channel-bed level by assuming that channel width does not change. Field calibration: The correlation of modeling results using field data. It usually involves fine adjustments of certain parameters used in modeling to improve the correlation. Flood hydrograph: A relationship showing how the flood discharge varies with time during its occurrence. Fluvial processes: Processes that are caused by stream action, including sediment transport, flood flow, erosion, deposition, and river channel changes. Grade control structure : A rigid structure constructed across a river channel used to stabilize the bed elevation at the location. A drop structure is also a grade control structure.
2
Head cutting: Channel-bed erosion occurring upstream of a sand or gravel pit or any other depression. Model: For this study, a model is computer software developed to simulate the hydraulics of flow, sediment transport and river channel changes. Pit capture: A stream is diverted from its normal course into a pit of lower elevation Scour (general and local): Erosion or removal of material caused by stream action. General scour is caused by the imbalance (non-uniformity) in sediment transport along a river channel. Local scour is caused by any local obstruction to flow, such as bridge piers, abutments, tree trunks, etc. Sediment delivery: The cumulative amount of sediment that is delivered passing a river section in a specified period of time. Sediment transport/replenishment: Sediment transport is the movement of sediment by flow measured usually in volume or weight per unit time. Replenishment is sediment supply to make up any previous deficit. Study channel reach: A river channel reach that is covered in a study. Such a reach is defined by a series of cross sections taken along the channel. Suspended load: Sediment load that travels in suspension, consisting of the finer portion of the transported sediment. Tractive force: The force exerted by the flow on the channel boundary or on any object in the river channel, usually measured in force per unit surface area.
3
EXECUTIVE SUMMARY
A hydraulic and sedimentation study has been made for the San Dieguito River wetland restoration
project. This study uses the updated channel and sediment data for the final design phase of the project.
The purpose of the study is to provide the necessary information for the final design.
The inlet channel of the San Dieguito River undergoes episodes of opening and closure. Closure is
the effect of littoral sediment transport on the beach that blocks off the stream mouth. Opening is caused
primarily by storm flows. Changes in channel morphology related to sediment flushing and recharge can be
substantial, and they have important effects on the hydraulics of flow, sediment transport, and channel
boundary scour. Major issues for the project include flood control, river channel scour, and sediment
delivery to the beach. In order to assess the project impacts on these issues, it was necessary to apply a
sediment transport model for the study. The FLUVIAL-12 model was employed for this project. The
model was calibrated using 12 sets of field data, including two data sets from the San Dieguito River.
The project plan includes new tidal basins. Berms will be installed to separate the tidal basins from
the effective flow area of the river channel. Flood flow and sand flow will be conveyed through the effective
flow area. The tidal basins do not act as sediment traps to cause a deficit in sediment supply to the beach.
Project Impacts on Flood Level - The proposed project includes berms installed in the river
channel. The northeastern berm encroaches into the floodplain of the San Dieguito River and it may thus
cause backwater effects on the river channel. A scheme was developed to eliminate the backwater effects.
This scheme includes a weir installed near the upstream end of the northeastern berm. The weir has a crest
elevation that is about 7 feet lower than the top of the berm so that it admits a sufficient discharge into the
tidal basin to reduce the backwater effects in the river channel. The 100-yr water-surface elevations were
computed for the existing channel and for the proposed project. These two water-surface profiles are
closely similar with only minor differences. The proposed project will not raise the flood level; therefore, it
will have no flooding impacts.
4
Project Impacts on Flow Velocity - Flow velocities were computed for the existing and proposed
conditions. The proposed project will not raise the velocities at the bridge crossings during the peak 100-yr
flood. The velocity is also a criterion for assessing the need for bank protection.
Project Impacts on River Channel Scour - River channel changes were simulated for the
existing and proposed conditions. The inlet channel is subject to severe scour during the 100-yr flood. The
crossings of the Highway 101 Bridge, the railroad bridge, and the Jimmy Durante Bridge are prone to
severe scour that may lead to failure during the 100-yr flood. The El Camino Real Bridge has a stone
blanket on the channel bed that checks the scour development. The simulated results show that the
proposed project will not increase the maximum general scour at the bridge crossings. Minor increase in
scour depth is predicted at the river bend near river mile 0.7. Protection of the concave bank at the river
bend is a part of the project scope. The present bank protection at the location is inadequate for protection
against the 100-yr flood. The channel reach upstream from the inlet channel is simulated to undergo
changes. These changes consist of minor scour and fill of the channel boundary; they are not nearly as
substantial as those in the inlet channel.
Project Impacts on Beach Sand Supply - Sediment deliveries along the river channel were
simulated for the existing and proposed conditions. The net amount of sand delivered to the river mouth is
the sand supply to the beach. For the 30-yr time span of the project, this amount is 214,000 tons for the
existing conditions and 227,000 tons for the proposed conditions. The proposed project will slightly
increase the supply of beach sand by the San Dieguito River.
Recommendations for Top and Toe Elevations of Berms and Bank Protection - The top of
berms and bank protection should stay above the 100-yr flood level to avoid overtopping. According to
the standard of the U. S. Army Corps of Engineers, the top of berms should maintain a freeboard of three
feet above the design flood level. Computed water-surface profiles were used to determine the required top
elevations for the proposed berms and bank protection. The toe of bank protection must entrench beyond
the potential scour. For this project, the recommended toe elevations of bank protection are about 5 feet
below the potential scour. The 5-foot margin is a safety factor used to account for uncertainties, such as
5
erratic hydrologic phenomenon, bank settlement, local scour due to tree trunks, etc. The recommended
top and toe profiles are provided.
6
Hydraulics and Sedimentation Study
for the San Dieguito River Wetland Restoration Project
I. INTRODUCTION
This report presents a hydraulic and sedimentation study for the San Dieguito River wetland
restoration project. This project has undergone several technical reviews in the past. A recent topographic
survey of the river channel has been made and sediment samples have also been collected and analyzed.
This study uses the updated channel and sediment data for the final design phase of the project. The
purpose of the study is to provide the necessary information for the final design.
Fig. 1 is a map of the San Dieguito River west of I-5, and Fig. 2 shows the river channel east of I-5.
The channel geometry is defined at selected cross sections. Locations of cross sections used in the study
are shown in the work map; approximate cross section locations are shown in Figs. 1 and 2. Important
locations and their respective channel stations are listed in Table 1.
Table 1. List of important locations along the river channel
Points of interest Location
River miles
River mouth 0
Highway 101 0.087 - 0.107
Railroad Bridge 0.293 – 0.299
Jimmy Durante Bridge 0.570 - 0.581
River bend 0.706
Interstate 5 Bridge 1.355 – 1.391
El Camino Real 2.806 – 2.813
Upstream limit of study 5.839
7
Fig. 1. Map of the San Dieguito River west of I-5
Fig. 2. Map of the San Dieguito River east of I-5
8
Mouths of coastal streams in semi-arid regions, such as California, undergo episodes of opening and
closure. A sand bar typically blocks the stream mouth during the dry season while floods flush the river
mouth open. Closure is the effect of littoral sediment transport on the beach that blocks off the stream
mouth. Opening is caused primarily by storm flows. For the San Dieguito River, changes in channel
morphology related to sediment flushing and recharge can be substantial, and they have important effects on
the hydraulics of flow, sediment transport, and channel boundary scour.
The San Dieguito River was monitored by Coastal Environment, Inc. Cross-sectional surveys were
made periodically at selected stream gaging stations along the river channel. The 1993 flood, estimated to
be an 18-yr flood, occurred in March and it ended on March 15. Prior to the flood, the channel bed near
the river mouth had been silted up to a level above the mean sea level. Gaging station 0.13 is located 0.13
river mile from the mouth. Cross-sectional profiles at this gaging station surveyed at time intervals before
and after the 1993 flood are shown in Fig. 3. The flood caused scour affecting a width exceeding 200 feet
and a maximum depth over 7 feet at this location as depicted in the figure. The figure also shows that the
channel bed was gradually silted up after the flood. In general, channel changes due to sediment flushing
and recharge are more pronounced at the river mouth and they tend to diminish toward upstream away from
the coastal influence.
Fig. 3. Measured channel changes during the 1993 flood at a location 690 feet from the beach
9
Major issues for the project include flood control, channel boundary scour and sediment delivery to
the beach. In order to assess the project impacts on these issues, it was necessary to apply a sediment
transport model for the river study.
II. BASIC HYDROLOGY
Floods - The San Dieguito River has a total drainage area of 346.5 square miles, of which 303
square miles are above Lake Hodges. Since its completion in 1926, the dam has controlled 87.4 % of the
drainage basin. Lake Hodges cuts off the surface runoff of small storms to the lower reach. The reservoir
spills during larger storms. Significant spillage of the reservoir occurred in 26 years of the last 78 years
(1926-2003). For larger storms, the upper basin above Lake Hodges supplies the discharge in the Lower
San Dieguito River, but for smaller storms, the flow in the lower reach is only supplied by runoff from the
lower river basin below Lake Hodges. A summary of peak discharges for representative return periods is
given in Table 2. There is a lack of sufficient stream flow data for the river channel. The County of San
Diego used hydrological simulation to determine the flood discharges. Peak discharges of other floods may
be estimated based the assumption that the distribution of peak discharges follows a lognormal distribution.
Table 2. Flood discharges for the lower San Dieguito River
Flood event Peak Discharge, cfs
10-yr 5,700
50-yr 31,400
100-yr 41,800
In this study, the 100-yr flood was used together with a flood series representative of the long-term
flood flow. The 100-yr flood hydrograph is shown in Fig. 4. In the future, one should expect various flood
events. In the time span of 100 years, one may expect statistically one flood event exceeding the 100-year
flood, two events exceeding the 50-year flood, four events exceeding the 25-year flood, ten events
exceeding the 10-yr flood, etc. For this stream reach, most of the sediment transport occurs during major
floods. Those events less than the 10-yr flood have limited discharge and hence transport capacity;
10
therefore, only those events equal to or greater than the 10-yr flood were included in the flood series for
simulation. The series of flood events occur randomly. The sequence of occurrence of these floods is
beyond human prediction, but the particular order of flood events does not affect the results pertaining to the
long-term sediment delivery. The sequence of flood events as exemplified in Fig. 4 was employed to
represent the long-term flood flow. It is assumed in this study that the occurrence follows the following
order: 10-yr flood, 30-yr flood, 20-yr flood, 40-yr flood, 15-yr flood, 100-yr flood, 20-yr flood, 15-yr
flood, 70-yr flood, and 10-yr flood. It is recognized that flood sequences are almost infinite in possibility
and the sequence of events assumed in this study is only a special case. However, the objective of the
environmental impact study was to assess the impacts of the proposed project on sediment delivery by the
river channel. The same flood series was used in simulation for the pre-project and post-project conditions.
The results for these two conditions were compared. Since the pre-project and post-project conditions
were simulated based on the same flood series, the comparative results are useful for assessing the project
impacts on sediment delivery by the river.
11
Fig. 4. Hydrograph of the 100-yr flood
Fig. 5. Flood series for 100-yr time span
Sediment Data - The study reach of the San Dieguito River is a sand bed river. Sediment samples
were taken from the river bed at several locations. These samples were analyzed and their grain size
distributions are shown in Fig. 6. The bed material consists primarily of sand with small amounts of fines (silt
and clay) and gravel.
12
Fig. 6. Grain size distributions
Grain Size Distributions
0
10
20
30
40
50
60
70
80
90
100
0.010.1110100
Grain size, mm
Perc
ent f
iner
by
wei
ght
RM=0RM=0.62
RM=1.45RM=2.69
Grain Size Distributions
0
10
20
30
40
50
60
70
80
90
100
0.010.1110100
Grain size, mm
Perc
ent f
iner
by
wei
ght
RM=3.43RM=3.93RM=4.74RM=5.79
13
Effective Flow Area and Ineffective Flow Area - The lower San Dieguito River has a main
channel and a broad floodplain. Distribution of flow velocity in the floodplain is not uniform, as illustrated in
Fig. 7. This velocity distribution was simulated using the two-dimensional hydrodynamic model FESWNS
(Federal Highway Administration, 1992). Based on the velocity distribution, the broad floodplain can be
divided into an effective flow area and an ineffective flow area. The effective flow area has significant flow
velocities and it contributes to the conveyance of most of the flow discharge. The ineffective flow area, on
the other hand, has very small flow velocities and it does not contribute significantly to the conveyance of the
flow discharge. The effective flow area as delineated using the FESWNS model is shown in the figure to be
within the boundaries designated by dashed lines; it is along the main channel of the river and it passes
through the bridge openings. The ineffective flow area is outside the effective flow area.
Fig. 7. Sample two-dimensional velocity distribution in the floodplain
showing effective and ineffective flow areas (Q = 20,000 cfs)
14
III. METHODS OF ANALYSIS
Stream channel scour consists of general scour and local scour. General scour is related to the
sediment supplied to and transported out of a channel reach. Local scour is due to a local obstruction to
flow by a bridge pier/bent or abutment.
To determine general scour, it is necessary to consider the sediment supply by flow to the channel
reach and sediment removal out of the reach. Sediment delivery in the stream channel and supply to the
subject area is related to the flood hydrograph, channel geometry, and sediment characteristics, etc. To
account for these factors, it requires mathematical simulation of the hydraulics of stream flow, sediment
transport and stream channel changes.
Mathematical Model for General Scour - The FLUVIAL-12 model (Chang, 1988) is
employed for this project. For a given flood hydrograph, the FLUVIAL model simulates spatial and
temporal variations in water-surface elevation, sediment transport and channel geometry. Scour and fill of
the streambed are coupled with width variation in the prediction of river channel changes. Computations are
based on finite difference approximations to energy and mass conservation that are representative of open
channel flow.
The model simulates the inter-related changes in channel-bed profile and channel width, based upon
a stream's tendency to seek uniformities in sediment discharge and power expenditure. At each time step,
scour and fill of the channel bed are computed based on the spatial variation in sediment discharge along the
channel. Channel-bed corrections for scour and fill will reduce the non-uniformity in sediment discharge.
Width changes are also made at each time step, resulting in a movement toward uniformity in power
expenditure along the channel. Because the energy gradient is a measure of the power expenditure,
uniformity in power expenditure also means a uniform energy gradient or linear water surface profile. A
river channel may not have a uniform power expenditure or linear water-surface profile, but it is constantly
adjusting itself toward that direction. The model was calibrated using 12 sets of field data. Such calibration
15
studies are as listed in the Users Manual for FLUVIAL-12. Most of the calibration studies were peer-
reviewed.
Selection of the Engelund-Hansen Formula The Engelund-Hansen formula was selected for
the study for the following reasons:
(1) The selection was based on the most extensive evaluation of formulas made by Brownlie (see
Fig. 8); the Engelund-Hansen formula has the best correlation with field data.
(2) The Engelund-Hansen formula was used in many studies in this region. The results of these
studies were verified by field data.
(3) In a calibration study of the FLVUAIL-12 model, the results generated by the Engelund-
Hansen formula can be correlated with the measured channel changes in the San Dieguito River
during the 1993 flood.
Fig. 8. Evaluation of sediment transport formulas by Brownlie
Engelund-Hansen Formula - Engelund and Hansen (1967) applied Bagnold's stream power
concept and the similarity principle to obtain their sediment transport equation:
16
f' ϕ = 0.1 (τ* )5/2 (1) 2gRS with f' = -------- (2) U2 qs τo ϕ = ------------------, τ* = ------------- (3) γs [(s - 1) gd3 ] 1/2 (γs - γ) d
where f' is the friction factor, d is the median fall diameter of the bed material, ϕ is the dimensionless
sediment discharge, s is the specific gravity of sediment, and τ* is the dimensionless shear stress or the
Shields stress. Substituting Eqs. 2 and 3 into Eq. 1 yields
s US RS 1/2
Cs = 0.05 ----- ---------------- [------------] (4) s - 1 [(s - 1)gd] 1/2 (s - 1) d
where Cs (= Qs/Q) is the sediment concentration by weight. This equation relates sediment concentration to
the U-S product (which is the rate of energy expenditure per unit weight of water) and the R-S product
(which is the shear stress). Strictly speaking, the Engelund-Hansen formula should be applied to streams
with a dune bed in accordance with the similarity principle. However, it can be applied to upper flow regime
with particle size greater than 0.15 mm without serious error.
IV. HYDRAULIC DESIGN FOR A WEIR ON NORTHEASTERN BERM
The northeastern berm encroaches into the floodplain of the San Dieguito River and it may thus
cause backwater effects on the upstream river channel. The proposed project includes three berms and
dredging of the main channel. Preliminary FLUVIAL-12 results indicate that the proposed northeastern
berm will cause backwater effects on the river channel. The rises in water-surface elevation due to
backwater, based on the 100-yr flood, are small in magnitude, measured in about 2 inches.
17
A scheme has been developed to eliminate the backwater effects. This scheme includes a weir
installed near the upstream end of the northeastern berm at river mile 2.31. This weir is a cut in the berm; it
has a crest elevation that is about 7 feet lower than the top of the berm so that it may admit a part of the
flood flow into the northeastern tidal basin. In order to achieve the objective of reducing the backwater
effects in the river channel, a sufficient discharge must be admitted into the tidal basin. On the other hand,
the weir flow discharge must be small enough so that it will not cause damages to the tidal basin.
In order to develop the desired weir configuration, a weir with a vertical side slope (rectangular
weir) was first assumed and different sets of weir lengths and crest elevations were tested. Based on the
test results, the following geometric features for the weir were selected:
Weir length: 240 feet
Weir crest elevation: 13.8 feet
At the location of the weir, the berm has the top elevation of 20.5 feet. The performance and effectiveness
of the weir were analyzed as described below.
In subsequent development, weirs with a side slope were considered. Such weirs are trapezoidal in
cross-sectional shape and they may therefore be referred to as trapezoidal weirs. A flat side slope for the
weir will allow human passage along the top of the berm, thereby eliminating the need of a bridge over the
weir opening. Two different flat side slopes were considered; these are: (1) the 5 horizontal units to one
vertical unit side slope, and (2) the 12 horizontal units to one vertical unit side slope.
Rating Curves for Weir Flow - Weir flow occurs when the river stage exceeds the weir crest
elevation of 13.8 feet. Based on the results of FLUVIAL-12 modeling, the river stage at the weir location
reaches 13.8 feet at the discharge of 14,000 cfs, which is the peak discharge of the 25-yr flood. In other
words, weir flow occurs only during floods that are greater than the 25-yr flood.
The discharge overflowing the crest of a rectangular weir was computed based on the following
equation for broad-crested weirs (Chow, Open Channel Hydraulics, MacGraw-Hill, 1959):
18
Q = 3.09 H3/2 L (5)
In which, Q is the weir discharge in cfs; H is the total head above the weir crest; L is the weir length of 240
feet. Based on this equation, weir discharges at various stages were computed as summarized in Table 3.
The stage-discharge relation, or the rating curve, for the weir is also shown in Fig. 9.
The last column in Table 3 is based on results from the FLUVIAL-12 model. At the peak 100-yr
flood discharge of 41,800 cfs, the weir flow is 5,300 cfs, which is roughly 12.7 % of the peak flood flow.
The diverted discharge into the northeastern tidal basin is reintroduced into the main channel at river mile
1.45 through the downstream exit of the tidal basin; the combined flood flows continue downstream to the
ocean.
Table 3. Stage-discharge relations for the river and rectangular weir
River stage feet
Head over weir feet
Weir discharge cfs
River discharge cfs
13.8 0 0 14,000
14.0 0.2 66 15,000
14.5 0.7 434 18,000
15.0 1.2 975 21,000
15.5 1.7 1,644 24,000
16.0 2.2 2,410 26,500
16.5 2.7 3,290 29,000
17.0 3.2 4,245 32,000
17.5 3.7 5,300 42,000
17.8 4.0 5,933 48,000
For a weir with a trapezoidal cross section, the discharge of flow over the weir crest is given by the
equation (Chow, Open Channel Hydraulics, MacGraw-Hill, 1959):
19
5.671 [(L+zy)y]1.5 Q = ----------------------- (6) (L+ 2zy)0.5
In which, L is the weir length that is also the bed width of the trapezoidal channel; z is the side slope in
horizontal units for one vertical unit; and y is water depth over the weir crest. The total head H (or the river
stage) above the weir crest is computed from the equation
H = y + V2/2g (7)
In order to develop the trapezoidal weir configuration for the selected side slopes, different sets of
weir lengths and crest elevations were tested. The purpose of these tests was to match the performance of
the trapezoidal weir with that of the rectangular weir, which has a vertical side slope. Based on the test
results, it was concluded that the same weir crest elevation of 13.8 feet could be used for trapezoidal weirs.
The weir lengths were adjusted for the trapezoidal weirs; the selected weir lengths are summarized in Table
4. The rating curves for these three weir configurations are plotted as shown in Fig. 9 for comparison. It is
easy to see that these rating curves are closely similar. In other words, at a river stage, closely similar
discharges will be diverted into the northeastern tidal basin through these weirs.
20
Fig. 9. Rating curves for weirs (Series 1 is for rectangular weir with L=240 feet; Series 2 is for the
trapezoidal weir with L=225 feet and z = 5; and Series 3 is for the trapezoidal weir with L=215 feet and z =
12)
Rating Curves for Weirs
0
1000
2000
3000
4000
5000
6000
7000
13.5 14 14.5 15 15.5 16 16.5 17 17.5 18 18.5
River Stage, feet
Dis
char
ge, c
fs
Series1Series2Series3
21
Table 4. Summary of weir configurations
Side slope Crest elevation, ft Weir length, ft
0 (rectangular weir) 13.8 240
5 to 1 (trapezoidal weir) 13.8 225
12 to 1 (trapezoidal weir) 13.8 215
Modification of Flood Hydrograph - When a portion of the flood discharge is diverted into the
tidal basin through the weir. The flood discharge in the river channel adjacent to the berm (from Section
1.457 to Section 2.240) is reduced. The reduction of river discharge is equal to the weir discharge and it
varies in direct relation to the river stage. In the modeling study, the modified flood hydrograph was used
for the river reach adjacent to the northeastern berm from Section 1.457 to Section 2.240. The section
numbers are in river miles. At the confluence of the main channel and the northeastern tidal basin between
Section 1.402 and Section 1.457, the diverted flow is again reintroduced into the main channel and the
combined discharge was used in the modeling study.
Effects of Weir on Tidal Basin - Since a portion of the flood flow will be routed through the tidal
basin, the effects of this flow on the tidal basin need to be investigated. The flow through the tidal basin has
the maximum discharge of 5,300 cfs during the 100-yr flood. The flow velocity through the tidal basin
depends on the tidal basin configuration. For the proposed tidal basin design, the minimum cross-sectional
area of flow through the tidal basin is at the berm opening (mouth) to the river channel at river mile 1.45.
The flood stage at this section is computed to be 15.4 feet at the 100-yr peak discharge. The river stage
also controls the stage at the berm opening. At this stage, the cross-sectional area of flow at the berm
opening is about 2,000 square feet. With the discharge of 5,300 cfs, the velocity is computed to be 2.7 feet
per second. This velocity is very small and it is considered to be a non-scouring velocity. At other places in
the tidal basin, the velocities are lower than 2 feet per second. It may therefore be concluded that the flow
through the tidal basin will not cause scour damages. Of course, the weir structure and its adjacent areas
need to be hardened.
22
Another important consideration for the flow diversion scheme is whether the weir flow would cause
sediment deposition in the tidal basin. This potential impact is now analyzed as described below. The weir
has the crest elevation of 13.8 feet, which is well above the adjacent channel bed elevation of about 2-3
feet. For this reason, bed sediment will not be transported into the tidal basin. In other words, the potential
for siltation in the tidal basin due to bed sediment is insignificant.
Suspended sediment load and floating debris will be transported into the tidal basin during weir
flows. Suspended load and floating debris should not be significant maintenance problems for the tidal
basin for the following reasons.
(1) The occurrence of weir flow is very rare; its return period is 25 years.
(2) The duration of weir flow is much shorter than the flood duration. As shown in Fig. 4, the 100-yr
flood has the duration of roughly 50 hours, but the duration of weir flow is less than 20 hours. The
discharge of weir flow is very small during most of the flow period.
(3) Only the suspended load in the top layer of the river flow can be transported into the tidal basin. It
consists of the finest portion of the suspended load, or the wash load. In sedimentation engineering,
it is well known that the wash load has a very slow settling velocity and it tends to stay in suspension
for a long period of time. For this reason, much of the wash load, after entering the tidal basin, will
actually be transported out of the tidal basin to re-enter the downstream river channel.
(4) Floating debris is normally near the water surface but with most of its volume submerged in the
water. In order for the debris to be carried into the tidal basin, it will require a certain water depth
for the weir flow. The maximum water depth over the weir crest is about 3 feet. Because of the
limited water depth, large debris may not be carried into the basin. Smaller pieces that enter the
tidal basin may also be transported out of the basin.
Summary and Conclusions : A scheme has been developed to eliminate the backwater effects of
the northeastern berm on the upstream river channel. This scheme includes a weir installed near the
upstream end of the northeastern berm at river mile 2.31. A portion of the flood flow in the river channel
will be diverted into the tidal basin through the weir. For a rectangular weir, a weir length of 240 feet and
23
crest elevation of 13.8 feet have been selected based on performance and effectiveness, evaluated based on
hydraulic computations and FLUVIAL-12 modeling.
The 100-yr water-surface elevations for the river channel were simulated using the FLUVIAL-12
model for the existing conditions without the berms and the weir and proposed conditions with the berms
and weir. The comparison will be presented in a later section of the report; it shows that these two water-
surface profiles are closely similar with only minor differences. Water-surface elevations for the proposed
conditions are generally lower especially along the inlet channel. Upstream from the east end of the berm at
river mile 2.31, backwater effect due to proposed wetland project is totally eliminated.
With flow diversion through the weir, the flow velocity through the tidal basin varies with the tidal
basin configuration. For all the planned alternatives, the minimum cross-sectional area of flow through the
tidal basin is at the berm opening to the river channel at river mile 1.45. The maximum velocity through the
opening is computed to be 2.7 feet per second. This velocity is very small and it is considered to be a non-
scouring velocity. At other places in the tidal basin, the velocities are lower than 2 feet per second. It may
therefore be concluded that the flow through the tidal basin will not cause scour damages. Of course, the
weir structure and its adjacent local areas need to be hardened.
This potential impact of the weir flow on tidal basin sedimentation was also analyzed. The weir
crest elevation of 13.8 feet is well above the adjacent channel bed elevation of about 2-3 feet. For this
reason, bed sediment will not be transported into the tidal basin; the potential for siltation due to bed
sediment in the tidal basin is insignificant. Suspended sediment load and floating debris will be transported
into the tidal basin during weir flows. The effects of siltation due to suspended load and floating debris are
not significant maintenance problems for the tidal basin.
V. MODELING FOR EXISTING CONDITIONS AND PROPOSED CONDITIONS
The FLUVIAL-12 model was used to simulate the hydraulics of river flow, sediment transport,
together with potential changes in river channel geometry during the 100-yr flood. Modeling runs were
24
made for the river channel under existing conditions and with the proposed wetland restoration project. The
results for these two cases are compared in order to assess the project impacts. The modeled results
pertaining to water-surface profiles, flow velocities, bridge hydraulics, and river channel scour are presented
and described below:
Channel-Bed and Water-Surface Profiles Based on the FLUVIAL-12 Model - The channel
reach from the river mouth to river mile 0.6 is referred to as the inlet channel. This reach is subject to
significant scour during major floods; therefore, the water-surface profile is affected by the scour
development. Channel-bed scour has the direct effect of lowering the flood level. For this reason, a water-
surface profile computed using the FLUVIAL-12 model with scour consideration should be lower than the
corresponding profile obtained based on the HEC-2 model that assumes rigid channel boundary.
Figures 10 and 11 show the simulated water-surface profiles and channel-bed profile changes
during the 100-yr flood for the existing and proposed conditions, respectively. It can be seen that the
channel bed is susceptible to major scour along the inlet channel from the river mouth to river mile 0.6.
Such scour development is primarily because the flow is now constricted to a narrow channel. After scour
and sediment flushing by a flood, the inlet channel also undergoes refill by beach sand related to the littoral
process. Major channel bed scour is also predicted at channel bends. The scour depth at channel bends is
directly related to the flood discharge; it is the greatest near the peak flow and it tends to be refilled, at least
in part, during the falling flood discharge.
The computed water-surface elevations are based on the peak 100-yr flood discharge. Numerical
comparison of the water-surface elevations for these two conditions as given in Table 5 shows that these
two water-surface profiles are closely similar with only minor differences. Water-surface elevations for the
proposed conditions are generally lower especially along the inlet channel. Since a portion of the flow is
diverted into the northeastern tidal basin through a weir, backwater effects due to tidal basin is eliminated.
Since the proposed project will not cause increased flood level, the project will have no flooding impacts.
25
Fig. 10. Water-surface and channel-bed profile changes
Longitudinal Profiles During 100-yr Flood for Existing Conditions
-20
-15
-10
-5
0
5
10
15
20
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Channel station, river miles
Ele
vatio
n, f
eet
Peak W. S.Initial bedBed at peak flowBed after flood
Interstate 5 -
River bend -
River m
outh
Highw
ay 101 -
R. R
. Bridge -
Durante B
r. -
Longitudinal Profiles During 100-yr Flood for Existing Conditions
-15
-10
-5
0
5
10
15
20
25
1.5 1.6 1.7 1.8 1.9 2 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3
Channel station, river miles
Ele
vatio
n, f
eet
Peak W. S.Initial bedBed at peak flowBed after flood
- El C
amino
Real
River bend -
26
during 100-yr flood for existing conditions
Fig. 11. Water-surface and channel-bed profile changes during 100-yr flood
Longitudinal Profiles During 100-yr Flood for Proposed Conditions
-15
-10
-5
0
5
10
15
20
25
1.5 1.6 1.7 1.8 1.9 2 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3
Channel station, river miles
Ele
vatio
n, f
eet
Peak W. S.Initial bedBed at peak flowBed after flood
- El C
amino R
eal
River bend -
River bend -
27
for proposed conditions
Longitudinal Profiles During 100-yr Flood for Proposed Conditions
-20
-15
-10
-5
0
5
10
15
20
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Channel station, river miles
Ele
vatio
n, f
eet
Peak W. S.Initial bedBed at peak flowBed after flood
Interstate 5 -
River bend -
River m
outh
Highw
ay 101 -
R. R
. Bridge -
Durante B
r. -
28
Table 5. Comparison of computed for 100-yr flood elevations based on FLUVIAL-12
Computed water-surface elevation feet, NGVD
Section
river mile
Location Existing conditions Proposed plan
0.00 River mouth 0 0
0.107 Highway 101 Bridge 3.0 2.8
0.191 4.6 4.2
0.293 Railroad Bridge 6.7 6.2
0.374 7.6 7.2
0.493 9.1 8.6
0.581 Jimmy Durante Bridge 9.3 8.7
0.706 River bend 11.6 11.2
0.967 12.5 12.5
1.192 13.8 13.7
1.391 I-5 Bridge 14.9 14.9
1.596 16.0 16.0
2.062 17.1 16.9
2.183 17.3 17.1
2.311 East end of berm 17.5 17.4
2.479 17.8 17.7
2.688 18.6 18.6
2.806 El Camino Real 20.3 20.3
3.048 21.7 21.7
3.148 21.9 21.9
29
3.453 23.0 23.0
3.567 23.5 23.5
Spatial Variations in Velocity Along the River Channel - The flow velocity is often used as a
criterion to assess the potential for scour. The cross-sectionally averaged velocities are included in the
output of the FLUVIAL-12 model. Such velocities simulated at the peak 100-yr flood and their spatial
variations along the river channel are shown in Fig. 12 for the existing and proposed conditions. The spatial
variations in velocity are useful to characterize the flow along the river channel. The figure shows that the
river channel has very high velocities along the entire inlet channel. This is related to the concentration of
flow in the confined channel width. The high velocities are also responsible for the severe scour
development.
Fig. 12. Spatial variations of velocity along river channel for existing and proposed conditions
The velocities are higher than 6 feet per second along the entire inlet channel and at the I-5 Bridge
and near the El Camino Real Bridge crossings where the flow is also concentrated. For the rest of the river
channel shown in Fig. 12, the flow velocities are generally lower than 6 feet per second. When the
Spatial Variations of Flow Velocity During 100-yr Flood
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8
Channel station, river miles
Vel
ocity
, fps
Existing conditions
Proposed conditions
- Durante B
ridge
Flow toward left
I-5 Bridge -
30
velocities for the existing and proposed conditions are compared, it can be seen that the proposed plan will
result in increases in flow velocity along the bermed reaches. Such increases are directly related to the
encroachment of flow by the berms. Since the velocities within the encroachment are still lower than 6 feet
per second, such encroachment is permissible under the local guidelines.
The velocity is also used as a criterion to assess the need for bank protection for the berms. For
berms that are made of cohesive materials, planted with vegetation, and parallel to flow, the permissible
velocity of 6 feet per second is normally used as the criterion for bank stability. In other words, a berm that
meets these conditions does not require additional protection. The south berms on both sides of the I-5
Bridge are parallel to the river flow and they will be constructed with cohesive materials and planted with
vegetation. For this reason, additional bank protection is not needed for these berms. The berm northeast
of the I-5 Bridge is not parallel to the river flow and therefore it will need bank protection.
Bridge Hydraulics - Flow velocities at the bridge crossings during the peak 100-yr flood for the
existing conditions and proposed plan are summarized in Table 6 for comparison. It can be seen that the
proposed project will not raise the velocities at the bridge locations.
Table 6. Comparison of bridge hydraulics Velocity, feet/sec Structure Location
river mile Existing conditions Proposed conditions
Highway 101 Br. 0.107 11.0 9.4
Railroad Bridge 0.293 8.3 8.3
Jimmy Durante Br. 0.581 10.8 10.8
I-5 Bridge 1.391 6.0 6.0
El Camino Real Br. 2.806 5.7 5.7
Simulated Results on Scour - The lower San Dieguito River is a sand bed river. Grain size
distributions of sediment samples are shown in Fig. 6. The 100-yr flood was used to simulate sediment
31
transport and stream channel changes for the lower San Dieguito River under the existing conditions as well
as under the proposed plan. Simulated results are presented in graphical forms, in Figs. 10, 11, 13, 14, 15,
16, 17, 18, 19, 20, 21, 22, 23 and 24. In each figure, the graphical results usually include those before the
flood, at the peak flow, and at the end of flood. These results are described below. Simulated results
pertaining to potential channel-bed scour during the 100-yr flood for the existing conditions are shown in
Fig. 10; those for the proposed plan are shown in Fig. 11. The cross-sectional changes as simulated
Changes at Sec. 0.107 (Highway 101 Bridg) for Existing Conditions
-20
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 0.107 (Highway 101 Bridg) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
Initial
At peak flowAt end of floodPeak W. S.
32
are shown in Figs.13 through 24.
Fig. 13. Simulated changes at Highway 101 Bridge crossing
for the existing and proposed conditions
Fig. 14. Simulated changes at the railroad bridge crossing
Changes at Sec. 0.293 (Railroad Bridge) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
33
for the existing and proposed conditions
Changes at Sec. 0.293 (Railroad Bridge) for Existing Conditions
-15
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
34
Fig. 15. Simulated changes in the inlet channel for the existing and proposed conditions
Changes at Sec. 0.454 (Inlet Channel) for Existing Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 0.454 (Inlet Channel) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
35
Fig. 16. Simulated changes at Jimmie Durante Bridge crossing
Changes at Sec. 0.581 (Durante Bridge) for Existing Conditions
-20
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 0.581 (Durante Bridge) for Propsoed Conditions
-20
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
36
for the existing and proposed conditions
37
Fig. 17. Simulated changes at river bend for the existing and proposed conditions
Changes at Sec. 0.706 (River Bend) for Proposed Conditions
-20
-15
-10
-5
0
5
10
15
20
25
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 0.706 (River Bend) for Existing Conditions
-20
-15
-10
-5
0
5
10
15
20
25
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
38
Fig. 18. Simulated changes at section 0.866 for the existing and proposed conditions
Changes at Sec. 0.866 for Existing Conditions
-10
-5
0
5
10
15
20
4300 4500 4700 4900 5100 5300 5500 5700
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 0.866 for Proposed Conditions
-10
-5
0
5
10
15
20
4500 4700 4900 5100 5300 5500 5700
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
39
Fig. 19. Simulated changes at I-5 Bridge crossing for the existing and proposed conditions
Changes at Sec. 1.391 (I-5 Bridge) for Existing Conditions
-10
-5
0
5
10
15
20
25
30
4300 4400 4500 4600 4700 4800 4900 5000 5100
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 1.391 (I-5 Bridge) for Proposed Conditions
-10
-5
0
5
10
15
20
25
30
4300 4400 4500 4600 4700 4800 4900 5000 5100
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
40
Changes at Sec. 1.596 for Existing Conditions
-5
0
5
10
15
20
25
4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400 5500 5600
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 1.596 for Proposed Conditions
-5
0
5
10
15
20
25
4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
41
Fig. 20. Simulated changes at section 1.596 for the existing and proposed conditions
Changes at Sec. 1.805 (River Bend) for Existing Conditions
-10
-5
0
5
10
15
20
25
4300 4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Berm
Changes at Sec. 1.805 (River Bend) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
25
4000 4100 4200 4300 4400 4500 4600 4700 4800 4900 5000 5100 5200
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Berm
42
Fig. 21. Simulated changes at section 1.805 for the existing and proposed conditions
43
Fig. 22. Simulated changes at section 1.874 for the existing and proposed conditions
Changes at Sec. 1.847 (River Bend) for Existing Conditions
-10
-5
0
5
10
15
20
25
4300 4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Berm
Changes at Sec. 1.847 (River Bend) for Proposed Conditions
-10
-5
0
5
10
15
20
25
4100 4200 4300 4400 4500 4600 4700 4800 4900 5000 5100 5200
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Berm
44
Fig. 23. Simulated changes at section 2.311 for the existing and proposed conditions
Changes at Sec. 2.311 (River Bend) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
25
4300 4400 4500 4600 4700 4800 4900 5000 5100 5200
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Berm
Changes at Sec. 2.311 (River Bend) for Existing Conditions
-10
-5
0
5
10
15
20
25
4300 4400 4500 4600 4700 4800 4900 5000 5100 5200 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Berm
45
Fig. 24. Simulated changes at Camino Real Bridge crossing
Changes at Sec. 2.806 (El Camino Real) for Existing Conditions
0
5
10
15
20
25
30
4300 4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400 5500
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
Changes at Sec. 2.806 (El Camino Real) for Proposed Conditions
0
5
10
15
20
25
30
4300 4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400 5500
Station (looking downstream), ft
Ele
vatio
n, f
eet
InitialAt peak flowAt end of floodPeak W. S.
46
It can be seen from the channel-bed changes that the inlet channel is subject to severe scour during
the 100-yr flood. The changes in bed elevation are especially pronounced at the bridge crossings. Since
the depths of general scour at the bridge crossings are so large, these bridges (including the Highway 101
Bridge, the railroad bridge, and the Jimmy Durante Bridge) are prone to severe scour damages that may
lead to failure during the 100-yr flood. The El Camino Real Bridge has a stone blanket on the channel bed
that checks the scour development. The stone blanket has a surface elevation of 3.5 feet.
Changes in the inlet channel are exemplified in Fig. 15 by the cross-sectional changes at Section
0.452. Such changes are characterized by channel-bed erosion and widening. Since the current bank
protection is not engineered; it is subject to significant damages during the flood. Changes at the river bend
are shown in Fig. 17 by the cross-sectional changes at Section 0.706. At this section, the scour is
concentrated near the concave bank. The present bank protection is not adequate for protection against the
100-yr flood. The maximum scour at this location would be slightly increased by the proposed project.
Protection of the concave bank at the river bend is a part of the project scope.
The channel reach upstream from the inlet channel is simulated to undergo changes as exemplified in
Figs. 18 through 23. These changes consist of minor scour and fill of the channel boundary; they are not
nearly as substantial as those in the inlet channel.
The maximum scour profiles at the bridge crossings for the existing and proposed conditions are
shown in the Appendix. The minimum bed elevations reached by scour at selected locations as simulated for
the existing and proposed conditions are summarized in Table 7 for comparison. The table shows that
general scour depths under the proposed plan are generally less than the corresponding ones for the existing
conditions. The proposed project will not increase the maximum scour at the bridge crossings. Minor
increases in scour depth are shown to occur at the river bend. The basic fact is that tidal basins are
designed to stay separate from the effective flow area of the river and therefore, they do not act as sediment
traps to cause a deficit in sediment supply to the river channel.
47
Table 7. Comparison of general scour during 100-yr flood
Minimum elevation reached by
general scour, ft (NGVD)
Structure Location
river mile Existing conditions Proposed plan
Highway 101 Br. 0.107 -14.0 -9.3
Railroad Bridge 0.293 -18.0 -16.8
Jimmy Durante Br. 0.581 -17.2 -16.5
River bend 0.706 -22.1 -23.0
I-5 Bridge 1.391 -5.1 -5.1
El Camino Real Br. 2.806 3.5 3.5
VI. BEACH SAND SUPPLY
Simulation of Sediment Delivery - Sediment delivery is defined as the cumulative amount of
sediment that has been delivered passing a certain channel section for a specified period of time, that is,
?
Y = ∫ Qs dt (5) T where Y is sediment delivery (yield); Qs is sediment discharge; t is time; and T is the duration. The sediment
discharge Qs pertains only to bed-material load of sand, gravel and cobble. Fine sediments of clay and silt
constituting the wash load may not be computed by a sediment transport formula. Sediment delivery is
widely employed by hydrologists for watershed management; it is used herein to keep track of sediment
supply and removal along the channel reach.
Spatial variations in sediment delivery are manifested as channel storage or depletion of sediment
associated stream channel changes since the sediment supply from upstream may be different from the
removal. The spatial variation of sediment delivery depicts the erosion and deposition along a stream reach.
48
A decreasing delivery in the downstream direction, i.e. negative gradient for the delivery-distance curve,
signifies that sediment load is partially stored in the channel to result in a net deposition. On the other hand,
an increasing delivery in the downstream direction (positive gradient for the delivery-distance curve)
indicates sediment removal from the channel boundary or net scour. A uniform sediment delivery along the
channel (horizontal curve) indicates sediment balance, i.e., zero storage or depletion. Channel reaches with
net sediment storage or depletion may be designated in each figure on the basis of the gradient. From the
engineering viewpoint, it is best to achieve a uniform delivery, the non-silt and non-scour condition, for
dynamic equilibrium.
Sediment deliveries were simulated based on the 100-yr flood as well as the 100-yr flood series.
The proposed wetland restoration project has a life span of 30 years. While major flood events are
responsible for most of the sediment delivery, the occurrence of floods in the next 30 years is clearly beyond
human prediction. For this reason, the long-term sediment delivery along the river channel is simulated using
the 100-yr flood series. The delivery in the 30-yr time span is prorated based on the total amount of
delivery for the 100-yr time span.
Simulated Results on Sediment Delivery by the 100-yr Flood - Spatial variations in sediment
delivery by the 100-yr flood along the river channel are shown in Fig. 25 for the existing and proposed
conditions, respectively. The spatial patterns are similar; they both show a general increasing trend of
delivery toward the downstream direction, depicting the general pattern of sediment removal, or scour, from
the channel boundary. Most significant scour is along the inlet channel from river mile 0 to 0.6 where the
stored sediment is simulated to be removed by the major flood event. Sediment removal from the inlet
channel does not contribute to a net supply of beach sand since the inlet channel is recharged by beach sand
during the dry season. The channel reach from river mile 0.6 to 1.8 is upstream from the inlet channel.
Along this reach, a mild increasing trend for sediment delivery is depicted for the both conditions. Total
deliveries of sediment at selected river locations for both cases are listed in Table 8 for comparison.
As shown in Fig. 25, there is more sediment inflow to the inlet channel measured by delivery at the
entrance (river mile 0.6) for the proposed conditions, but there is greater sediment outflow at the river
49
mouth for the existing conditions. In other words, dredging removal of material from the inlet channel under
the proposed plan would result in reduced deliveries. However, the reduction in delivery is less than the
dredged amount of 135,000 tons. The supply of beach sand would not be reduced by the proposed
dredging so long as the dredged sand is placed on the beach.
Fig. 25. Spatial variations of sediment delivery during the 100-yr flood for the existing and proposed
conditions
Table 8. Comparison of sediment deliveries by 100-yr flood
Total sediment delivery 1,000 tons
Structure Location river mile
Existing Proposed plan
River mouth 0 722 620
Highway 101 Bridge 0.107 634 551
Railroad Bridge 0.293 445 418
Jimmy Durante Bridge 0.581 226 273
Spatial Variations of Sediment Delivery During 100-yr Flood
0
100
200
300
400
500
600
700
800
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8
Channel station, river miles
Sedi
men
t del
iver
y, 1
000
tons
Existing conditions
Proposed conditions
- Durante B
ridge
Flow toward left
I-5 Bridge -
Sediment recharge zone
50
I-5 Bridge 1.391 122 168
El Camino Real Br. 2.806 87 84
The above analysis applies to the short-term sand supply due to a single 100-yr flood. For the
proposed plan, sand dredged from the inlet channel will be placed on the beach and the inlet channel will be
maintained at the design bed level. Sand recharge to the inlet channel from the beach through littoral drift
will also be returned to the beach. Under these conditions, sand supply to the beach by the San Dieguito
River is controlled by the supply from the upstream river channel in the long term. As shown in Fig. 25,
sediment deliveries at upstream locations are closely similar for these two conditions. In other words, the
existing sand flow through the lagoon area would not be altered by the proposed plan.
Simulated Results on Long -Term Sediment Delivery – Long-term sediment deliveries were
simulated based on the 100-yr flood series. The proposed wetland restoration project has a life span of 30
years. The delivery in the 30-yr time span is prorated based on the total amount of delivery for the 100-yr
time span. Spatial variations in sediment delivery as shown in Fig. 26 depicts simulated results by
FLUVIAL-12. The constant delivery along the recharge zone of the inlet channel is used to depict that
there is no net sand supply from this channel reach. As it has been described previously that the inlet
channel is subject to flushing during floods and flushing is followed by sediment recharge from the beach
during the tidal exchange. Different delivery patterns for the two cases shown in the figure are described
below separately.
The spatial variations in sediment delivery as shown in Fig. 26 are described, reach by reach,
starting from upstream toward downstream. The first channel reach just upstream from El Camino Real at
river mile 2.806 is under the backwater influence from the bridge and its road embankment. The backwater
effects contribute to the low sediment delivery along the reach.
For the next reach from El Camino Real to river mile 2.2, the delivery pattern has a decreasing trend
toward downstream and it indicates that this channel reach is subject to sediment deposition. The next
channel reach from river mile 2.2 to 0.6 has an increasing trend for sediment delivery toward downstream.
51
This trend depicts general erosion of the channel boundary along the channel reach. Since this channel
reach is outside the recharge zone, sediment eroded from the boundary plus those transported through the
reach contribute to a net sand supply at the beach.
Fig. 26. Spatial variations of sediment delivery during 30-yr time span
for the existing and proposed conditions
Along the recharge zone from river mile 0.6 to the river mouth, the constant delivery is used to
depict no net contribution of beach sand from the reach. The net amount delivered to the river mouth is due
to sediment supplied from other upstream reaches; this amount is 214,000 tons for the existing conditions
and it is 227,000 tons for the proposed conditions in the 30-yr time span. The total amount of sand delivery
for the proposed conditions is slightly more than that for the existing conditions. This increase in sand
delivery is related to the encroachment of flow by the berms and the associated increase in flow velocity.
Spatial Variations of Sediment Delivery During 30-yr Time Span
0
50
100
150
200
250
300
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8
Channel station, river miles
Sedi
men
t del
iver
y, 1
000
tons
Existing conditions
Proposed conditions
- Durante B
ridge
Flow toward left
I-5 Bridge -
Sediment recharge zone
52
A summary of the spatial variations in sediment delivery for the existing and proposed cases is given
in Table 9. It can be seen from the table that the proposed plan will not decrease the supply of beach sand.
53
Table 9. Comparison of sediment deliveries in 30-yr time span
Total sediment delivery
1,000 tons
Structure Location
river mile Existing Proposed
River mouth 0 214 227
Highway 101 Bridge 0.107 214 227
Railroad Bridge 0.293 214 227
Jimmy Durante Bridge 0.581 214 227
I-5 Bridge 1.391 113 154
El Camino Real Br. 2.806 72 72
VII. DESIGN FOR BERMS AND BANK PROTECTION
Top Elevation of Berms - The top of berms and bank protection should stay above the 100-yr
flood level to avoid overtopping, which can cause erosional damages. According to the standard of the U.
S. Army Corps of Engineers, the top of levees should maintain a freeboard of three feet above the design
flood level. Computed water-surface profiles are used to determine the required top elevations for the
proposed berms and bank protection. The recommended top elevations for the berms as shown in Table
11 are based on water-surface elevations computed using the FLUVIAL-12 model, which considers
channel-bed scour.
Water-surface profiles of the river channel have been computed using two different computer
models: the HEC-2 model and the FLUVIAL-12 model. The former is a fixed boundary model that
assumes fixed channel boundary during a flood. The latter is an erodible boundary model that considers
channel boundary changes during a flood. Since the lower San Dieguito River is subject to significant
changes during floods, water-surface profiles obtained using these two models are therefore quite different.
Computed water-surface elevations together with the recommended top berm elevations are listed in Table
10.
54
Table 10. Computed water-surface elevations and recommended
top elevations for berms
Computed water-surface elevation feet River mile
per HEC-2 per FLUVIAL-12
Recommended
Top elevation feet
0.581 (J. Durante Br.) 15.8 8.7
0.830 (D/S end of berm) 16.9 11.8 16.0
1.045 17.0 13.0 16.3
1.192 17.1 13.7 16.6
1.343 (D/S face of I-5) 17.2 14.5 17.0
1.391 (U/S face of I-5) 17.2 14.9 17.5
1.457 18.3 15.3 18.5
1.674 18.4 16.4 19.0
1.805 18.6 16.7 19.5
2.122 18.8 17.1 19.8
2.311 18.9 17.5 20.0
Top Elevation and Toe-Down for Bank Protection – The top of bank protection should stay
above the 100-yr water surface. Recommended top elevations of bank protection as listed in Table 11
were selected based on computed water-surface profile at the peak discharge of the 100-yr flood plus a
freeboard.
The toe of bank protection must entrench beyond the potential scour. For this project, the
recommended toe elevations of bank protection are about 5 feet below the potential scour. The 5-foot
55
margin is a safety factor used to account for uncertainties, such as erratic hydrologic phenomenon, bank
settlement, local scour due to tree trunks, etc. The recommended top and toe profiles are also shown in
Figs. 27 and 28.
Table 11. Recommended elevations for berm and bank protection
Bank protection Section River mile
Top elevation of berm Feet Top elevation, feet Toe elevation, feet
Protection along river bend
0.640 11.7 -20.5
0.666 12.0 -25.0
0.706 12.0 -28.0
0.745 12.5 -16.0
Northeastern berm
1.457 18.5 17.0 -10.5
1.522 18.7 17.2 -11.0
1.596 18.8 17.3 -10.5
1.674 19.0 17.5 -10.5
1.737 19.3 17.8 -12.0
1.805 19.5 18.3 -22.5
1.847 19.8 18.3 -25.0
1.895 19.8 18.3 -17.5
1.979 19.8 18.3 -13.2
2.062 19.8 18.3 -8.5
2.122 19.8 18.3 -8.0
2.183 19.9 18.4 -7.0
56
2.240 19.9 18.4 -10.5
2.270 20.0 18.5 -17.0
2.311 20.0 18.5 -18.0
57
Fig. 27. Top and toe profiles of bank protection near the river bend
Fig. 28. Top and toe profiles of bank protection along the northeastern berm
Longitudinal Profiles for Northeastern Berm
-25
-20
-15
-10
-5
0
5
10
15
20
25
1.5 1.6 1.7 1.8 1.9 2 2.1 2.2 2.3 2.4Channel station, river miles
Ele
vatio
n, fe
et
Top of bermExisting bed profileMaximum scour profileToe of bank protection
Upstream
end of berm -
Longitudinal Profiles for Bank Protection Near River Bend
-30
-25
-20
-15
-10
-5
0
5
10
15
20
0.5 0.55 0.6 0.65 0.7 0.75 0.8
Channel station, river miles
Ele
vatio
n, fe
et
Top of bank protectionExisting bed profileMaximum scour profileToe of bank protection
River bend
D/S lim
it of protection
U/S lim
it of protection
Durante B
ridge
58
REFERENCES
Brownlie, W. R., "Prediction of Flow Depth and Sediment Discharge in Open Channels," Rept. No. KH-R-43A, W.M. Keck Laboratory of Hydraulics and Water Resources, California Institute of Technology, Pasadena, California, November 1981. Chang, H. H., Fluvial Processes in River Engineering, John Wiley & Sons, New York, NY, 1988, 432 pp. Vanoni, V., Sedimentation Engineering, ASCE Manual 54, 1975. LIST OF FIGURES
Fig. 1. Map of the San Dieguito River west of I-5
Fig. 2. Map of the San Dieguito River east of I-5
Fig. 3. Measured channel changes during the 1993 flood at a location 690 feet from the beach
Fig. 4. Hydrograph of the 100-yr flood
Fig. 5. Flood series for 100-yr time span
Fig. 6. Grain size distributions
Fig. 7. Sample two-dimensional velocity distribution in the floodplain showing effective and ineffective
flow areas (Q = 20,000 cfs)
Fig. 8. Evaluation of sediment transport formulas by Brownlie
Fig. 9. Rating curves for weirs (Series 1 is for rectangular weir with L=240 feet; Series 2 is for the
trapezoidal weir with L=225 feet and z = 5; and Series 3 is for the trapezoidal weir with L=215 feet and z =
12)
Fig. 10. Water-surface and channel-bed profile changes during 100-yr flood for existing conditions
Fig. 11. Water-surface and channel-bed profile changes during 100-yr flood for proposed conditions
Fig. 12. Spatial variations of velocity along river channel for existing and proposed conditions
Fig. 13. Simulated changes at Highway 101 Bridge crossing for the existing and proposed conditions
Fig. 14. Simulated changes at the railroad bridge crossing for the existing and proposed conditions
Fig. 15. Simulated changes in the inlet channel for the existing and proposed conditions
Fig. 16. Simulated changes at Jimmie Durante Bridge crossing for the existing and proposed conditions
59
Fig. 17. Simulated changes at river bend for the existing and proposed conditions
Fig. 18. Simulated changes at section 0.866 for the existing and proposed conditions
Fig. 19. Simulated changes at I-5 Bridge crossing for the existing and proposed conditions
Fig. 20. Simulated changes at section 1.596 for the existing and proposed conditions
Fig. 21. Simulated changes at section 1.805 for the existing and proposed conditions
Fig. 22. Simulated changes at section 1.847 for the existing and proposed conditions
Fig. 23. Simulated changes at section 2.311 for the existing and proposed conditions
Fig. 24. Simulated changes at Camino Real Bridge crossing for the existing and proposed conditions
Fig. 25. Spatial variations of sediment delivery during the 100-yr flood for the existing and proposed
conditions
Fig. 26. Spatial variations of sediment delivery during 30-yr time span for the existing and proposed
conditions
Fig. 27. Top and toe profiles of bank protection near the river bend
Fig. 28. Top and toe profiles of bank protection along the northeastern berm
60
APPENDIX A. MAXIMUM SCOUR PROFILES AT BRIDGE CROSSINGS DURING 100-YR
FLOOD
Maximum Scour Profile at Sec. 0.107 (Highway 101 Bridg) for Existing Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile at Sec. 0.107 (Highway 101 Bridg) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
61
Maximum Scour Profile at Sec. 0.293 (Railroad Bridge) for Existing Conditions
-20
-15
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile at Sec. 0.293 (Railroad Bridge) for Proposed Conditions
-20
-15
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
62
Maximum Scour Profile at Sec. 0.581 (Durante Bridge) for Proposed Conditions
-20
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 100-yr Floodat Sec. 0.581 (Durante Bridge) for Proposed Conditions
-20
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
63
Maximum Scour Profile at Sec. 1.391 (I-5 Bridge) for Existing Conditions
-10
-5
0
5
10
15
20
25
30
4300 4400 4500 4600 4700 4800 4900 5000 5100
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile at Sec. 1.391 (I-5 Bridge) for Proposed Conditions
-10
-5
0
5
10
15
20
25
30
4300 4400 4500 4600 4700 4800 4900 5000 5100
Station (looking downstream), ft
Ele
vatio
n, f
eet
64
APPENDIX B. MAXIMUM SCOUR PROFILES AT BRIDGE CROSSINGS FOR 50-, 25- AND 10-
YR FLOODS
Maximum Scour Profile during 50-yr flood at Sec. 0.107 (Highway 101 Bridg) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 50-YR Floodat Sec. 0.107 (Highway 101 Bridg) for existing Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
65
Maximum Scour Profile during 50-yr Flood at Sec. 0.293 (Railroad Bridge) for Existing Conditions
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 50-yr Flood at Sec. 0.293 (Railroad Bridge) for Proposed Conditions
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
66
Maximum Scour Profile during 50-yr Floodat Sec. 0.581 (Durante Bridge) for Existing Conditions
-20
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile During 50-yr Flood at Sec. 0.581 (Durante Bridge) for Proposed Conditions
-20
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
67
Maximum Scour Profile during 25-yr Floodat Sec. 0.107 (Highway 101 Bridg) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 25-yr Floodat Sec. 0.107 (Highway 101 Bridg) for existing Conditions
-15
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
68
Maximum Scour Profile during 25-yr Flood at Sec. 0.293 (Railroad Bridge) for Existing Conditions
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 25-yr Flood at Sec. 0.293 (Railroad Bridge) for Proposed Conditions
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
69
Maximum Scour Profile during 25-yr Floodat Sec. 0.581 (Durante Bridge) for Existing Conditions
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 25-yr Floodat Sec. 0.581 (Durante Bridge) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
70
Maximum Scour Profile during 10-yr Floodat Sec. 0.107 (Highway 101 Bridg) for Proposed Conditions
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 10-yr Floodat Sec. 0.107 (Highway 101 Bridg) for Existing Conditions
-10
-5
0
5
10
15
20
4650 4700 4750 4800 4850 4900 4950 5000 5050 5100 5150 5200 5250 5300
Station (looking downstream), ft
Ele
vatio
n, f
eet
71
Maximum Scour Profile during 10-yr Flood at Sec. 0.293 (Railroad Bridge) for Proposed Conditions
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 10-yr Flood at Sec. 0.293 (Railroad Bridge) for Existing Conditions
-10
-5
0
5
10
15
20
4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000
Station (looking downstream), ft
Ele
vatio
n, f
eet
72
Maximum Scour Profile during 10-yr Floodat Sec. 0.581 (Durante Bridge) for Proposed Conditions
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet
Maximum Scour Profile during 10-yr Floodat Sec. 0.581 (Durante Bridge) for Existing Conditions
-15
-10
-5
0
5
10
15
20
4800 4850 4900 4950 5000 5050 5100 5150
Station (looking downstream), ft
Ele
vatio
n, f
eet