242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
1 of 23
Tank Farm Plant Rounds 242-A Evaporator
USQ # EV-18-1574-S, Rev 1
CHANGE HISTORY ( LAST 5 REV-MODS )
Rev-Mod Release Date Justification: Summary of Changes
N-45 12/12/2018 Operations request -
Environmental requirements
Added a new row to page 2 to read: "***Inspect IX Column
Room floor for spills or damage”
Modified page 14 loading room inspections fourth row added
"Inspect for Housekeeping."
N-44 10/02/2018 Operations request Page 14 - Added new "Monitor floor drain" row to Loading
Room Inspection table.
N-43 01/18/2018 Operations request Page 20 stuck out "diesel generator in alarm condition" row and
struck out second table "242A CHGR 101"
N-42 01/04/2018 Operations request
Page 5 Changed normal range of 242A-VV-HT-001 and 242A-
VV-HT-002 from "135°F to 145°F" to
"130°F to 150°F"
N-41 12/21/2017 Operations request
Pg. 20: Split readings for Diesel Tank and Diesel Generator
alarms.
Pg. 23: Updated RECORDS statement to exactly match
requirements for rounds from TFC-OPS-OPER-C-60 for
consistency in rounds.
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
2 of 23
242-A Evaporator Backside Rounds
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Component Number/Condition Normal
Range
Limit
(Basis) D N D N D N D N D N D N D N
Condenser Room Level 1
LG-C100-1
Overflow to TK-AW-102 Loop Seal Sight
Glass Level
> 50% (ES)
*LG-242-A-60 sight glass level 25-75%
*LG-242-A-61 sight glass level 25-75%
*LG-242-A-62 sight glass level 50-100%
** PI-FC1-1
Upstream Pressure Indicator for F-C-1 10-20 psig (ES)
* *PI-FC1-2
Downstream Pressure Indicator
For F-C-1
10-20 psig (ES)
** PI-FC1-1 – PI-FC1-2
Differential Pressure for F-C-1
< 15
psig (ES)
*** No Leakage present in IX Column Room No leaks (ES)
(RPP-16922)
*** Inspect IX Column Room floor for spills
or damage No leaks
(ES)
(RPP-16922)
**** PI-C106-1
Pressure Indicator For P-C106 Pump
140 to 160
psig (ES)
(ES) = Equipment Status
* Normal Range is for when 10# Steam is valved into E-A-1 (REBOILER). N/A reading when 10# steam is not valved into E-A-1 (REBOILER).
** Required to be recorded when process condensate is being sent to LERF. N/A when process condensate is not being sent to LERF.
*** Required when process condensate is diverted to AW-102. N/A when process condensate is not being diverted to AW-102.
**** Required when process condensate is being recycled as seal water. N/A when process condensate is not being recycled as seal water.
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
3 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Component Number/Condition Normal
Range
Limit
(Basis) D N D N D N D N D N D N D N
Condenser Room Level 2
Overflow Section of Weir covered with
water * Y or N (ES)
Condenser Room Level 2C
LG-SP-1,
Vessel Vent Seal Pot Level >25% (ES)
* If weir is low on water, add water and document per 242-85B-005.
(ES) = Equipment Status Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
4 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Component Number/Condition Normal Range Limit
(Basis) D N D N D N D N D N D N D N
Condenser Room Level 5
FIC-CA1-12
De-entrainment pad Lower 1.0 to 1.5 scfh (ES)
FIC-CA1-13
De-entrainment pad Upper 1.0 to 1.5 scfh (ES)
FIT-CA1-20**
Purge Air Flow 4.5 to 6 scfm (ES)
* PI-FCA1L-1,
Inlet Pressure to Left Seal Water Filter
40 to 130
psig (ES)
* PI-FCA1L-2,
Outlet Pressure to Left Seal Water Filter 40 to 130 psig (ES)
*PI-FCA1L-1 - PI-FCA1L-2,
dP across F-CA1-L
< 20
psid (ES)
* PI-FCA1R-2,
Outlet Pressure to Right Seal Water Filter 40 to 130 psig (ES)
* PI-FCA1R-1,
Inlet Pressure to Right Seal
Water Filter
40 to 130
psig (ES)
* PI-FCA1R-1 - PI-FCA1R-2,
DP across F-CA1-R
< 20
psid (ES)
(ES) = Equipment Status
* Readings are required for the sock filter that is valved in, when the seal water system is in service. Note valved out filter as OFF. N/A if seal water is out of service.
Readings may be performed out-of-sequence to facilitate work progress
Note any missing or illegible labels on Comment Page
** If torr of CA-1 is 170 torr as read on PIC-CA1-7, N/A reading.
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
5 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Component Number/Condition Normal Range Limit
(Basis) D N D N D N D N D N D N D N
Ammonia Monitor
** Ammonia Monitor Status ON / OFF /
STANDBY*
(ES)
RPP-16922
242A-VV-HT-001 130 F to 150 F (ES)
242A-VV-HT-002 130 F to 150 F (ES)
(ES) = Equipment Status
* STBY may be entered for STANDBY Mode.
** Ammonia Monitor shall be operating during Operation Mode.
Readings may be performed out-of-sequence to facilitate work progress
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
6 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
WATER SERVICE BUILDING INSPECTIONS
Inspect process system(s) for integrity and signs of corrosion. (No leakage from
piping, valves, flanges, cabinets, etc. No rust buildup) PLANT STATUS
Inspect room lighting. (No burned out lights, light fixtures intact etc.)
PLANT STATUS
Space for emergency movement of fire, spill and decontamination equipment is
maintained. (Clear walkways) SAFETY
No unsafe conditions exist. Conditions hazardous to personnel and/or detrimental
to equipment. (Wet floors, exposed wiring, housekeeping, belt guards not
installed, water leaking onto electrical equipment etc.) SAFETY
No indications of malfunctioning equipment. (Lack of power to indicating lights,
abnormal noises from operating equipment, etc.) PLANT STATUS
Raw water strainer bank in service. F-RW-1 In operation
F-RW-2 In operation
Blow down raw water strainer banks per TO-600-130.
SPECIAL INSTRUCTIONS: 1. Perform room inspections using the checklist as a guide.
2. If the inspection is performed SATISFACTORY enter a check () in the block.
3. If the inspection is NOT SATISFACTORY enter a number and make a corresponding entry in the “Remarks” documenting corrective actions taken, listing RATL number.
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
7 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
AMU ROOM INSPECTIONS
Inspect room lighting. (No burned out lights, light fixtures intact etc.)
PLANT STATUS
Inspect areas within 2 meters of AMU-side of shield windows on the AMU
lower and mezzanine levels for combustible materials.
(Remove transient combustibles.) FIRE PROTECTION
Inspect AMU lower level and mezzanine for accumulation of combustible
materials. Piles of transient combustibles 1.5 meters x .86 meters x .76 meters
must be maintained 1.5 meters apart. (Remove transient combustibles, notify
Shift Manager.) FIRE PROTECTION
Inspect TK-E-104 Decon and TK-E-101 Eluant Tanks for signs of corrosion,
leakage, and spillage from chem. add equipment. (RPP-16922)
Space for emergency movement of fire, spill and decontamination equipment is
maintained. (Clear walkways) (RPP-16922)
No unsafe conditions exist. Conditions hazardous to personnel and/or
detrimental to equipment. (Wet floors, exposed wiring, housekeeping, belt
guards not installed, water leaking on to electrical equipment etc.) SAFETY
No indications of malfunctioning equipment. (Lack of power to indicating
lights, abnormal noises from operating equipment, etc.) (RPP-16922)
Conversions: 1 Meter = 39.37 inches, 0.76 meters = 29.92 inches, 0.86 meters = 33.87 inches, 1.5 Meters = 59.05 inches, 2.0 meters = 78.74.inches (6 ' 6 43
‘‘).
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
8 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
AMU ROOM INSPECTIONS (Cont.)
Inspect piping for leaks or corrosion
(Ex. No leakage from piping, valves flanges, cabinets, no rust build up, etc.)
(RPP-16922)*
Inspect floors for spills or damage
(Ex. Wet floors, cracks) (RPP-16922)*
Inspect for equipment malfunctions
. (Ex. Lack of power to indicating lights, abnormal noises from operating
equipment, etc.) (RPP-16922)*
Inspect for housekeeping
(RPP-16922)*
*By the best view possible, use viewing window in AMU Mezzanine to perform inspections except for the pump room which uses the ground floor window. Visual inspections and
access are limited due ALARA.
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
9 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: Normal
Status D N D N D N D N D N D N D N
AMU ROOM INSPECTIONS (Cont.)
Recirc Pump P-B-1
(MCC-3 Cubicle A1) DISCONNECT OFF/ON
Agitator A-E-102
(MCC-1 Cubicle C1) DISCONNECT OFF/ON
Condensate Recycle Pump P-C106
(MCC-1 Cubicle G6) DISCONNECT OFF/ON
Seal Water Pump P-C-105
(Panel B Breaker 12) BREAKER OFF/ON
Pump P-RC-1 Steam Condensate Sample Pump
(Panel B Breaker 26) BREAKER OFF/ON
P-C-105A Seal Water Booster Pump
(Panel B Breaker 29) BREAKER OFF/ON
SC-PB2-CB1 VFD Slurry Pump P-B-2 OFF/ON
PB2-1-DS DISCONNECT OFF/ON
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
10 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
PUMP ROOM INSPECTIONS (use viewing window in AMU Room for inspection)
Inspect room lighting. (No burned out lights, light fixtures intact etc.)
PLANT STATUS
Inspect visible areas within 2 meters of the pump room side of the shield
windows, on the AMU lower and mezzanine levels, for combustible materials.
(Report combustibles for removal.) FIRE PROTECTION
Space for emergency movement of fire, spill and decontamination equipment is
maintained. (Clear walkways) (RPP-16922)
No unsafe conditions exist. Conditions hazardous to personnel and/or detrimental
to equipment. (Wet floors, exposed wiring, housekeeping, belt guards not
installed, water leaking onto electrical equipment, etc.) SAFETY
Inspect Pump Room Sump for overflows. (RPP-16922)
Conversions: 1 Meter = 39.37 inches, 2.0 meters = 78.74 inches (6 ' 6 43
‘‘)
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
11 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
PUMP ROOM INSPECTIONS (Cont.) (use viewing window in AMU Room for inspection)
Inspect piping for leaks or corrosion
(Ex. No leakage from piping, valves flanges, cabinets, no rust build up,
etc.) (RPP-16922) *
Inspect floors for spills or damage
(Ex. Wet floors, cracks)
(RPP-16922) *
Inspect for equipment malfunctions
(Ex. Lack of power to indicating lights, abnormal noises from operating
equipment, etc.) (RPP-16922) *
Inspect for housekeeping
(RPP-16922) *
*By the best view possible, use viewing window in AMU Mezzanine to perform inspections except for the pump room which uses the ground floor window. Visual inspections and
access are limited due ALARA.
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
12 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
HOT EQUIPMENT ROOM INSPECTIONS (use viewing window in AMU Room for inspection)
Inspect process system(s) for integrity and signs of corrosion. (No
leakage from piping, valves, flanges, cabinets, etc. No rust buildup)
(RPP-16922)
Inspect room lighting. (No burned out lights, light fixtures intact, etc.)
PLANT STATUS
Inspect visible areas within 2 meters of hot equipment room side of the
shield window on the AMU mezzanine level for combustible materials.
(Report combustibles for removal.)
FIRE PROTECTION
Space for emergency movement of fire, spill and decontamination
equipment is maintained. (Clear walkways) (RPP-16922)
No unsafe conditions exist. Conditions hazardous to personnel and/or
detrimental to equipment. (Wet floors, exposed wiring, housekeeping,
belt guards not installed, water leaking onto electrical equipment, etc.)
SAFETY
Conversions: 1 Meter = 39.37 inches, 2.0 meters = 78.74 inches (6 ' 6 43
‘‘)
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
13 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
HOT EQUIPMENT ROOM INSPECTIONS (Cont.) (use viewing window in AMU Room for inspection)
Inspect piping for leaks or corrosion
(Ex. No leakage from piping, valves flanges, cabinets, no rust build up, etc.)
(RPP-16922) *
Monitor pump room sump and inspect floors for spills or damage
(Ex. Wet floors, cracks)
(RPP-16922) *
Inspect for housekeeping
(RPP-16922) *
*By the best view possible, use viewing window in AMU Mezzanine to perform inspections except for the pump room which uses the ground floor window. Visual inspections and
access are limited due ALARA.
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
14 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
LOADING ROOM INSPECTIONS (use viewing window in AMU Room for inspection)
Inspect room lighting. (No burned out lights, light fixtures intact, etc.)
PLANT STATUS
Curtain status (O = OPEN, C = CLOSED)
PLANT STATUS
Inspect visible areas within 2 meters of the loading room side of the
shield window on the AMU mezzanine level for combustible materials.
(Report combustibles for removal.)
FIRE PROTECTION
Space for emergency movement of fire, spill and decontamination
equipment is maintained. (Clear walkways) Inspect for Housekeeping.
(RPP-16922)
Monitor floor drain. (Free of obstructions, no liquid back-up)
(RPP-16922)
No unsafe conditions exist. Conditions hazardous to personnel and/or
detrimental to equipment. (Wet floors, exposed wiring, housekeeping,
belt guards not installed, water leaking onto electrical equipment, etc.)
SAFETY
Conversions: 1 Meter = 39.37 inches, 2.0 meters = 78.74 inches (6 ' 6 43
'' )
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
15 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
HVAC ROOM INSPECTIONS
Inspect process system(s) for integrity and signs of corrosion. (No
leakage from piping, valves, flanges, cabinets, etc. No rust buildup)
PLANT STATUS
Inspect room lighting. (No burned out lights, light fixtures intact, etc.)
PLANT STATUS
Space for emergency movement of fire, spill and decontamination
equipment is maintained. (Clear walkways) SAFETY
No unsafe conditions exist. Conditions hazardous to personnel and/or
detrimental to equipment. (Wet floors, exposed wiring, housekeeping,
belt guards NOT installed, water leaking onto electrical equipment, etc.)
SAFETY
No indications of malfunctioning equipment. (Lack of power to
indicating lights, abnormal noises from operating equipment, etc.)
PLANT STATUS
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
16 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
CONDENSER ROOM INSPECTIONS
Inspect C-100 tank and process system(s) for integrity and signs of
corrosion. (No leakage from tank, piping, valves, flanges, cabinets, etc.
No rust buildup) (RPP-16922)
Inspect TK-C-100 and process condensate system for labels which state
“Process Condensate” (RPP-16922)
Inspect installed radiological catch containers for overflow of liquid.
PLANT STATUS
Inspect room lighting. (No burned out lights, light fixtures intact, etc.)
PLANT STATUS
Space for emergency movement of fire, spill and decontamination
equipment is maintained. (Clear walkways) (RPP-16922)
No unsafe conditions exist. Conditions hazardous to personnel and/or
detrimental to equipment. (Wet floors, exposed wiring, housekeeping,
belt guards not installed, water leaking onto electrical equipment, etc.)
SAFETY
No indications of malfunctioning equipment. (Lack of power to
indicating lights, abnormal noises from operating equipment, etc.)
(RPP-16922)
Inspect area to verify that combustible material has not been allowed to
accumulate. Combustible materials other than those required for routine
plant operation and/or maintenance must be reported to the SOM and
noted in the Remarks section. Fire Protection
Verify a 10 foot combustible free zone around the exhaust inlet is
maintained at all times. Fire Protection
(Continued on next page)
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
17 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter: D N D N D N D N D N D N D N
CONDENSER ROOM INSPECTIONS (Cont.)
Inspect tanks and piping for leaks or corrosion
(Ex. No leakage from piping, valves flanges, cabinets, no rust build up,
etc.)
(RPP-16922)
Inspect floors for spills or damage
(Ex. Wet floors, cracks)
(RPP-16922)
Inspect for equipment malfunctions
(Ex. Lack of power to indicating lights, abnormal noises from operating
equipment, etc.)
(RPP-16922)
Inspect for housekeeping
(RPP-16922)
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
18 of 23
242-A Evaporator Backside Rounds (Cont.)
The following parameters are in the required status: Starting Date:
Parameter Description Required Status
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
D N D N D N D N D N D N D N
K1 STACK CAM CABINET VERIFICATION
Red Indicator Light K1 Stack Monitor Alarm Not Activated
DEBRIS/COMBUSTIBLE VERIFICATION
Parameter/Required Status
(Basis)
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Days Days Days Days Days Days Days
No transient combustibles within 5 feet of building penetrations North and
West sides of 242-A Condition Met ()
(HNF-SD-WM-FHA-024)
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
19 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter (Basis) Days Days Days Days Days Days Days
DAYS ONLY EVAPORATOR DOORS/GATES
* Exterior Doors Closed & Locked When Not Staffed (RPP-16922) (Yes/No)
** Doors/gates in Good Condition And Functioning Properly with Posted Warning
Signs in Place (RPP-16922) (Yes/No)
Fire Lanes Clear of Vehicles Or Other Obstructions (RPP-16922) (Yes/No)
*** Confirm signs restricting fuel truck access to within 50 feet of southwest corner of
242-A rollup door are in place and legible Condition Met ()
(HNF-SD-WM-FHA-024)
EVAPORATOR LIGHTING
Parameter Sunday Night Only
Outdoor and Indoor Lighting Sufficient to Allow Visual Observation of the Facility. ()
SPECIAL INSTRUCTIONS:
If any above condition is answered no or found unsatisfactory, comment below and inform the Shift Operations Manager.
* Main entrance and office area entrances may be open when the building is staffed.
** Posted warning signs saying "DANGER - Unauthorized Personnel Keep Out" or equivalent, should be posted on all exterior doors leading directly to areas containing
radioactive or dangerous wastes.
Readings may be performed out-of-sequence to facilitate work progress.
Note any missing or illegible labels on Comment Page
*** Condition only required to be met during Evaporator “Operation Mode”, N/A otherwise.
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
20 of 23
242-A Evaporator Backside Rounds (Cont.)
Starting Date: Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Parameter (Basis) Days Days Days Days Days Days Days
EVAPORATOR DIESEL GENERATOR TANK
Diesel Tank in Alarm Condition (RPP-16922) (Yes/No)
Fire, Spill or Release Emergency Contact Information Sign Posted and Legible at Diesel
Storage Tank Fill Station (RPP-16922) (Yes/No)
RATL # Remarks:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
21 of 23
242-A Evaporator Backside Rounds (Cont.)
COMMENT PAGE
Record Any Extra Comments Below
AMU:
HVAC:
Pump Room:
Hot Equip:
Load Out:
Condenser Room:
IX Room:
Other Areas:
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
22 of 23
242-A Evaporator Backside Rounds (Cont.)
EVAPORATOR BACKSIDE ROUNDS SIGNATURE SHEET
Starting Date:
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Days
Performed
By:
(First and Last)
Sign
Date/
Time
Reviewed
By:
(First and Last)
Sign
Date/
Time
Nights
Performed
By:
(First and Last)
Sign
Date/
Time
Reviewed
By:
(First and Last)
Sign
Date/
Time
242-A Evaporator Backside Rounds
Type
CONTINUOUS Document No.
TF-OR-A-02 Rev/Mod
N-45 Release Date
12/12/2018 Page
23 of 23
Records
The following records are generated during the performance of this procedure. Hard copy
records are submitted to the File Custodian, located at 274-AW. Electronic records are
entered into IDMS.
Submit the entire round procedure as a record
Rounds Action Tracking List (RATL).
The record custodian identified in the company-level Records Inventory and Disposition
Schedule (RIDS) is responsible for record retention in accordance with TFC-BSM-
IRM_DC-C-02.