22kv Works Kemco

Embed Size (px)

DESCRIPTION

Kemco

Citation preview

  • Activity ID Activity Name OriginalDuration

    Early Start Early Finish Late Start Late Finish Total Float

    Port Buildings and InfrastructurePort Buildings and Infrastructure DTP Rev.03 319 18-Feb-15 03-Jan-16 04-Mar-15 11-Feb-16 39

    Section 2 CP 14 Port Marine Unit Section 2 CP 14 Port Marine Unit Area ecluding the Control Tower Buildin 293 16-Mar-15 03-Jan-16 15-Jun-15 11-Feb-16 39

    Milestone 8 & 10Milestone 8 & 10 293 16-Mar-15 03-Jan-16 15-Jun-15 11-Feb-16 39Infrastructure and External WorksInfrastructure and External Works 293 16-Mar-15 03-Jan-16 15-Jun-15 11-Feb-16 39

    EngineeringEngineering 25 16-Mar-15 09-Apr-15 15-Jun-15 15-Jul-15 97Material SubmittalsMaterial Submittals 25 16-Mar-15 09-Apr-15 15-Jun-15 15-Jul-15 97

    SubmittalsSubmittals 5 16-Mar-15 20-Mar-15 15-Jun-15 19-Jun-15 91Utility BuildingsUtility Buildings 5 16-Mar-15 20-Mar-15 15-Jun-15 19-Jun-15 91

    ElectricalElectrical 5 16-Mar-15 20-Mar-15 15-Jun-15 19-Jun-15 91Substation 13Substation 13 5 16-Mar-15 20-Mar-15 15-Jun-15 19-Jun-15 91

    57.S2.M8.IE.S13.E052 Material Submittals for S13 5 16-Mar-15 20-Mar-15 15-Jun-15 19-Jun-15 91

    ApprovalsApprovals 15 22-Mar-15 09-Apr-15 25-Jun-15 15-Jul-15 69Utility BuildingsUtility Buildings 15 22-Mar-15 09-Apr-15 25-Jun-15 15-Jul-15 69

    ElectricalElectrical 15 22-Mar-15 09-Apr-15 25-Jun-15 15-Jul-15 69Substation 13Substation 13 15 22-Mar-15 09-Apr-15 25-Jun-15 15-Jul-15 69

    57.S2.M8.IE.S13.E054 Material Approvals for S13 15 22-Mar-15 09-Apr-15 25-Jun-15 15-Jul-15 69

    ProcurementProcurement 45 10-Apr-15 24-May-15 16-Jul-15 29-Aug-15 97OrdersOrders 5 10-Apr-15 14-Apr-15 16-Jul-15 20-Jul-15 97

    Utility BuildingsUtility Buildings 5 10-Apr-15 14-Apr-15 16-Jul-15 20-Jul-15 97ElectricalElectrical 5 10-Apr-15 14-Apr-15 16-Jul-15 20-Jul-15 97

    Substation 13Substation 13 5 10-Apr-15 14-Apr-15 16-Jul-15 20-Jul-15 9757.S2.M8.IE.S13.P005 Orders for S13 5 10-Apr-15 14-Apr-15 16-Jul-15 20-Jul-15 97

    Manufacturing and FabricationManufacturing and Fabrication 20 15-Apr-15 04-May-15 21-Jul-15 09-Aug-15 97Utility BuildingsUtility Buildings 20 15-Apr-15 04-May-15 21-Jul-15 09-Aug-15 97

    ElectricalElectrical 20 15-Apr-15 04-May-15 21-Jul-15 09-Aug-15 97Substation 13Substation 13 20 15-Apr-15 04-May-15 21-Jul-15 09-Aug-15 97

    57.S2.M8.IE.S13.P014 Manufacturing and Fabrication for S13 20 15-Apr-15 04-May-15 21-Jul-15 09-Aug-15 97

    DeliveryDelivery 20 05-May-15 24-May-15 10-Aug-15 29-Aug-15 97Utility BuildingsUtility Buildings 20 05-May-15 24-May-15 10-Aug-15 29-Aug-15 97

    ElectricalElectrical 20 05-May-15 24-May-15 10-Aug-15 29-Aug-15 97Substation 13Substation 13 20 05-May-15 24-May-15 10-Aug-15 29-Aug-15 97

    57.S2.M8.IE.S13.P023 @@Delivery of S13 20 05-May-15 24-May-15 10-Aug-15 29-Aug-15 97

    ConstructionConstruction 183 04-Jul-15 03-Jan-16 30-Aug-15 11-Feb-16 39Utility BuildingsUtility Buildings 0 04-Jul-15 04-Jul-15 30-Aug-15 30-Aug-15 57

    SCH35-Substation 13SCH35-Substation 13 0 04-Jul-15 04-Jul-15 30-Aug-15 30-Aug-15 5757.S2.M8.35.C000 Submittals Completion SCH35 0 04-Jul-15 30-Aug-15 57

    InfrastructureInfrastructure 127 29-Aug-15 03-Jan-16 16-Dec-15 11-Feb-16 39SCH45-Electrical worksSCH45-Electrical works 127 29-Aug-15 03-Jan-16 16-Dec-15 11-Feb-16 39

    57.S2.M8.45.C000 Submittals Completion SCH45 0 29-Aug-15 14-Jan-16 138

    Distribution Transformers, 2Distribution Transformers, 22kV & LV Switchboards, Isolators and Battery & UPS S 42 29-Oct-15 10-Dec-15 16-Dec-15 02-Feb-16 5557.S2.M8.I.C.45.0001 Installation of distrib transf, 22kV distrib & LV switchboard 14 26-Nov-15 10-Dec-15 13-Jan-16 26-Jan-16 48

    57.S2.M8.I.C.45.0002 Installation of MDB Potable Water Pump Station 14 29-Oct-15 12-Nov-15 16-Dec-15 29-Dec-15 48

    57.S2.M8.I.C.45.0003 Installation of MDB Fire Fighting / Fresh Water Pump Sta 14 12-Nov-15 26-Nov-15 30-Dec-15 12-Jan-16 48

    57.S2.M8.I.C.45.0004 Installation of MDB Land Fuel Control Room 20 29-Oct-15 17-Nov-15 14-Jan-16 02-Feb-16 77

    Diesel Generator SetDiesel Generator Set 7 10-Dec-15 17-Dec-15 27-Jan-16 02-Feb-16 4857.S2.M8.I.C.45.0008 Installation of diesel generator set Substation 13 7 10-Dec-15 17-Dec-15 27-Jan-16 02-Feb-16 48

    Power CablesPower Cables 14 06-Dec-15 19-Dec-15 28-Jan-16 11-Feb-16 5457.S2.M8.I.C.45.0009 Roads power cables laying 14 06-Dec-15 19-Dec-15 28-Jan-16 11-Feb-16 54

    Duct BanksDuct Banks 25 28-Oct-15 21-Nov-15 22-Dec-15 02-Feb-16 7357.S2.M8.I.C.45.0010 Road excavation of electrical trenches 10 28-Oct-15 06-Nov-15 22-Dec-15 31-Dec-15 55

    57.S2.M8.I.C.45.0011 Installation of conduit spacers 8 31-Oct-15 07-Nov-15 25-Dec-15 01-Jan-16 55

    57.S2.M8.I.C.45.0012 Conduit laying 8 31-Oct-15 07-Nov-15 26-Jan-16 02-Feb-16 87

    c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul g2015 2016

    03-Jan-16, Port Buildings and Infrastru

    03-Jan-16, Section 2 CP 14 Port Marin

    03-Jan-16, Milestone 8 & 10

    03-Jan-16, Infrastructure and External09-Apr-15, Engineering09-Apr-15, Material Submittals

    20-Mar-15, Submittals20-Mar-15, Utility Buildings20-Mar-15, Electrical20-Mar-15, Substation 13

    Material Submittals for S1309-Apr-15, Approvals09-Apr-15, Utility Buildings09-Apr-15, Electrical09-Apr-15, Substation 13

    Material Approvals for S1324-May-15, Procurement

    14-Apr-15, Orders14-Apr-15, Utility Buildings14-Apr-15, Electrical14-Apr-15, Substation 13

    Orders for S1304-May-15, Manufacturing and Fabrication04-May-15, Utility Buildings04-May-15, Electrical04-May-15, Substation 13

    Manufacturing and Fabrication for S1324-May-15, Delivery24-May-15, Utility Buildings24-May-15, Electrical24-May-15, Substation 13

    @@Delivery of S1303-Jan-16, Construction

    04-Jul-15, Utility Buildings04-Jul-15, SCH35-Substation 13Submittals Completion SCH35, 04-Jul-15

    03-Jan-16, Infrastructure03-Jan-16, SCH45-Electrical works

    Submittals Completion SCH45, 29-Aug-15

    10-Dec-15, Distribution Transformers, 22kV

    Installation of distrib transf, 22kV distrib & L

    Installation of MDB Potable Water Pump Station

    Installation of MDB Fire Fighting / Fresh Wate

    Installation of MDB Land Fuel Control Room17-Dec-15, Diesel Generator Set

    Installation of diesel generator set Substat19-Dec-15, Power Cables

    Roads power cables laying21-Nov-15, Duct Banks

    Road excavation of electrical trenches

    Installation of conduit spacers

    Conduit laying

    Actual Level of Effort

    Primary Baseline

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    summary

    Detailed Classic Schedule Layout (UCE) Page 1 of 3 IA 15/16C 008GDate Revision Checked Approved

    21-Jun-15 Rev 00 FBM

  • Activity ID Activity Name OriginalDuration

    Early Start Early Finish Late Start Late Finish Total Float

    57.S2.M8.I.C.45.0013 Installation of formwork 8 02-Nov-15 09-Nov-15 27-Dec-15 03-Jan-16 55

    57.S2.M8.I.C.45.0014 Concrete pouring 5 06-Nov-15 10-Nov-15 31-Dec-15 04-Jan-16 55

    57.S2.M8.I.C.45.0015 Curing duration 7 11-Nov-15 17-Nov-15 05-Jan-16 11-Jan-16 55

    57.S2.M8.I.C.45.0016 Backfilling of electrical trenches 4 18-Nov-15 21-Nov-15 30-Jan-16 02-Feb-16 73

    ManholeManhole 29 28-Oct-15 25-Nov-15 05-Jan-16 02-Feb-16 6957.S2.M8.I.C.45.0017 Road excavation of electrical manholes 10 28-Oct-15 06-Nov-15 05-Jan-16 14-Jan-16 69

    57.S2.M8.I.C.45.0018 Construction of electrical manholes 10 31-Oct-15 09-Nov-15 08-Jan-16 17-Jan-16 69

    57.S2.M8.I.C.45.0019 Curing duration of electrical manholes 7 10-Nov-15 16-Nov-15 18-Jan-16 24-Jan-16 69

    57.S2.M8.I.C.45.0020 Backfilling of electrical manholes 4 17-Nov-15 20-Nov-15 25-Jan-16 28-Jan-16 69

    57.S2.M8.I.C.45.0021 Installation of manhole covers and fittings 7 19-Nov-15 25-Nov-15 27-Jan-16 02-Feb-16 69

    Power Management System Power Management System (PMS) 14 20-Dec-15 03-Jan-16 02-Jan-16 16-Jan-16 1357.S2.M8.I.C.45.0023 Setting-up the SCS/PMS and FO cables Substation 13 14 20-Dec-15 03-Jan-16 02-Jan-16 16-Jan-16 13

    Section 3 CP 12 Coast Guard AreSection 3 CP 12 Coast Guard Area 311 18-Feb-15 25-Dec-15 04-Mar-15 05-Feb-16 42

    Milestone 6Milestone 6 311 18-Feb-15 25-Dec-15 04-Mar-15 05-Feb-16 42Infrastructure and External WorksInfrastructure and External Works 311 18-Feb-15 25-Dec-15 04-Mar-15 05-Feb-16 42

    EngineeringEngineering 27 18-Feb-15 16-Mar-15 04-Mar-15 09-Apr-15 24Material SubmittalsMaterial Submittals 27 18-Feb-15 16-Mar-15 04-Mar-15 09-Apr-15 24

    SubmittalsSubmittals 6 18-Feb-15 23-Feb-15 04-Mar-15 16-Mar-15 21Utility BuildingsUtility Buildings 6 18-Feb-15 23-Feb-15 04-Mar-15 16-Mar-15 21

    ElectricalElectrical 6 18-Feb-15 23-Feb-15 04-Mar-15 16-Mar-15 21Substation 11Substation 11 6 18-Feb-15 23-Feb-15 04-Mar-15 10-Mar-15 14

    57.S3.M6.IE.S11.E062 Material Submittals for S11 6 18-Feb-15 23-Feb-15 04-Mar-15 10-Mar-15 14

    Substation 12Substation 12 5 18-Feb-15 22-Feb-15 12-Mar-15 16-Mar-15 2257.S3.M6.IE.S12.E062 Material Submittals for S12 5 18-Feb-15 22-Feb-15 12-Mar-15 16-Mar-15 22

    ApprovalsApprovals 16 23-Feb-15 16-Mar-15 15-Mar-15 09-Apr-15 18Utility BuildingsUtility Buildings 16 23-Feb-15 16-Mar-15 15-Mar-15 09-Apr-15 18

    ElectricalElectrical 16 23-Feb-15 16-Mar-15 15-Mar-15 09-Apr-15 18Substation 11Substation 11 15 24-Feb-15 16-Mar-15 15-Mar-15 05-Apr-15 13

    57.S3.M6.IE.S11.E064 Material Approvals for S11 15 24-Feb-15 16-Mar-15 15-Mar-15 05-Apr-15 13

    Substation 12Substation 12 15 23-Feb-15 15-Mar-15 22-Mar-15 09-Apr-15 1957.S3.M6.IE.S12.E064 Material Approvals for S12 15 23-Feb-15 15-Mar-15 22-Mar-15 09-Apr-15 19

    ProcurementProcurement 46 16-Mar-15 30-Apr-15 05-Apr-15 25-May-15 24OrdersOrders 6 16-Mar-15 21-Mar-15 05-Apr-15 15-Apr-15 24

    Utility BuildingsUtility Buildings 6 16-Mar-15 21-Mar-15 05-Apr-15 15-Apr-15 24ElectricalElectrical 6 16-Mar-15 21-Mar-15 05-Apr-15 15-Apr-15 24

    Substation 11Substation 11 5 17-Mar-15 21-Mar-15 05-Apr-15 10-Apr-15 1957.S3.M6.IE.S11.P005 Orders for S11 5 17-Mar-15 21-Mar-15 05-Apr-15 10-Apr-15 19

    Substation 12Substation 12 5 16-Mar-15 20-Mar-15 10-Apr-15 15-Apr-15 2557.S3.M6.IE.S12.P005 Orders for S12 5 16-Mar-15 20-Mar-15 10-Apr-15 15-Apr-15 25

    Manufacturing and FabricationManufacturing and Fabrication 21 21-Mar-15 10-Apr-15 10-Apr-15 05-May-15 24Utility BuildingsUtility Buildings 21 21-Mar-15 10-Apr-15 10-Apr-15 05-May-15 24

    ElectricalElectrical 21 21-Mar-15 10-Apr-15 10-Apr-15 05-May-15 24Substation 11Substation 11 20 22-Mar-15 10-Apr-15 10-Apr-15 30-Apr-15 19

    57.S3.M6.IE.S11.P014 Manufacturing and Fabrication for S11 20 22-Mar-15 10-Apr-15 10-Apr-15 30-Apr-15 19

    Substation 12Substation 12 20 21-Mar-15 09-Apr-15 15-Apr-15 05-May-15 2557.S3.M6.IE.S12.P014 Manufacturing and Fabrication for S12 20 21-Mar-15 09-Apr-15 15-Apr-15 05-May-15 25

    DeliveryDelivery 21 10-Apr-15 30-Apr-15 30-Apr-15 25-May-15 24Utility BuildingsUtility Buildings 21 10-Apr-15 30-Apr-15 30-Apr-15 25-May-15 24

    ElectricalElectrical 21 10-Apr-15 30-Apr-15 30-Apr-15 25-May-15 24Substation 11Substation 11 20 11-Apr-15 30-Apr-15 30-Apr-15 20-May-15 19

    57.S3.M6.IE.S11.P025 @#@Delivery of S11 20 11-Apr-15 30-Apr-15 30-Apr-15 20-May-15 19

    Substation 12Substation 12 20 10-Apr-15 29-Apr-15 05-May-15 25-May-15 25

    c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul g2015 2016

    Installation of formwork

    Concrete pouring

    Curing duration

    Backfilling of electrical trenches25-Nov-15, Manhole

    Road excavation of electrical manholes

    Construction of electrical manholes

    Curing duration of electrical manholes

    Backfilling of electrical manholes

    Installation of manhole covers and fittings03-Jan-16, Power Management Syste

    Setting-up the SCS/PMS and FO cable25-Dec-15, Section 3 CP 12 Coast Gua

    25-Dec-15, Milestone 6

    25-Dec-15, Infrastructure and External W16-Mar-15, Engineering16-Mar-15, Material Submittals

    23-Feb-15, Submittals23-Feb-15, Utility Buildings23-Feb-15, Electrical23-Feb-15, Substation 11

    Material Submittals for S1122-Feb-15, Substation 12

    Material Submittals for S1216-Mar-15, Approvals16-Mar-15, Utility Buildings16-Mar-15, Electrical16-Mar-15, Substation 11

    Material Approvals for S1115-Mar-15, Substation 12

    Material Approvals for S1230-Apr-15, Procurement

    21-Mar-15, Orders21-Mar-15, Utility Buildings21-Mar-15, Electrical21-Mar-15, Substation 11

    Orders for S1120-Mar-15, Substation 12

    Orders for S1210-Apr-15, Manufacturing and Fabrication10-Apr-15, Utility Buildings10-Apr-15, Electrical10-Apr-15, Substation 11

    Manufacturing and Fabrication for S1109-Apr-15, Substation 12

    Manufacturing and Fabrication for S1230-Apr-15, Delivery30-Apr-15, Utility Buildings30-Apr-15, Electrical30-Apr-15, Substation 11

    @#@Delivery of S1129-Apr-15, Substation 12

    Actual Level of Effort

    Primary Baseline

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    summary

    Detailed Classic Schedule Layout (UCE) Page 2 of 3 IA 15/16C 008GDate Revision Checked Approved

    21-Jun-15 Rev 00 FBM

  • Activity ID Activity Name OriginalDuration

    Early Start Early Finish Late Start Late Finish Total Float

    57.S3.M6.IE.S12.P025 @#@Delivery of S12 20 10-Apr-15 29-Apr-15 05-May-15 25-May-15 25

    ConstructionConstruction 179 30-Jun-15 25-Dec-15 08-Nov-15 05-Feb-16 42InfrastructureInfrastructure 179 30-Jun-15 25-Dec-15 08-Nov-15 05-Feb-16 42

    SCH25-Electrical worksSCH25-Electrical works 179 30-Jun-15 25-Dec-15 08-Nov-15 05-Feb-16 4257.S3.M6.25.C000 Submittals Completion SCH25 0 11-Dec-15 24-Dec-15 13

    Distribution Transformers, 2Distribution Transformers, 22kV & LV Switchboards, Isolators and Battery & UPS S 178 30-Jun-15 24-Dec-15 09-Nov-15 07-Jan-16 1357.S3.M6.I.C.25.0053 Installation of MDB Firefighting/Fresh Water Pump Statio 14 09-Sep-15 22-Sep-15 24-Dec-15 07-Jan-16 106

    57.S3.M6.I.C.25.0054 Installation of MDB Potable Water Pump Station 14 11-Dec-15 24-Dec-15 24-Dec-15 07-Jan-16 13

    57.S3.M6.I.C.25.0055 Installation of distrib transf, 22kV distrib & LV switchboard 14 12-Oct-15 25-Oct-15 24-Nov-15 08-Dec-15 43

    57.S3.M6.I.C.25.0056 Installation of distrib transf, 22kV distrib & LV switchboard 14 30-Jun-15 13-Jul-15 09-Nov-15 22-Nov-15 132

    Diesel Generator SetDiesel Generator Set 107 15-Jul-15 29-Oct-15 08-Nov-15 09-Jan-16 7257.S3.M6.I.C.25.0025 Installation of diesel generator set Substation 12 7 23-Oct-15 29-Oct-15 03-Jan-16 09-Jan-16 72

    57.S3.M6.I.C.25.0026 Installation of diesel generator set Substation 11 7 15-Jul-15 21-Jul-15 08-Nov-15 15-Nov-15 116

    Power CablesPower Cables 14 05-Oct-15 19-Oct-15 22-Jan-16 05-Feb-16 10957.S3.M6.I.C.25.0030 Power cables laying 14 05-Oct-15 19-Oct-15 22-Jan-16 05-Feb-16 109

    Duct BanksDuct Banks 28 11-Sep-15 09-Oct-15 15-Nov-15 07-Jan-16 8957.S3.M6.I.C.25.0031 Backfilling of electrical trenches 4 05-Oct-15 09-Oct-15 03-Jan-16 07-Jan-16 89

    57.S3.M6.I.C.25.0038 Curing duration 7 28-Sep-15 05-Oct-15 02-Dec-15 09-Dec-15 64

    57.S3.M6.I.C.25.0043 Concrete pouring 5 23-Sep-15 28-Sep-15 27-Nov-15 02-Dec-15 64

    57.S3.M6.I.C.25.0044 Installation of formwork 12 16-Sep-15 28-Sep-15 20-Nov-15 02-Dec-15 64

    57.S3.M6.I.C.25.0046 Conduit laying 12 14-Sep-15 26-Sep-15 26-Dec-15 07-Jan-16 102

    57.S3.M6.I.C.25.0047 Installation of conduit spacers 12 14-Sep-15 26-Sep-15 18-Nov-15 30-Nov-15 64

    57.S3.M6.I.C.25.0049 Excavation electrical trenches 14 11-Sep-15 25-Sep-15 15-Nov-15 29-Nov-15 64

    ManholeManhole 33 11-Sep-15 14-Oct-15 15-Nov-15 07-Jan-16 8457.S3.M6.I.C.25.0029 Installation of manhole covers and fittings 7 07-Oct-15 14-Oct-15 31-Dec-15 07-Jan-16 84

    57.S3.M6.I.C.25.0032 Backfilling of electrical manhole 4 05-Oct-15 09-Oct-15 29-Dec-15 02-Jan-16 84

    57.S3.M6.I.C.25.0042 Curing duration of electrical manholes 7 28-Sep-15 05-Oct-15 02-Dec-15 09-Dec-15 64

    57.S3.M6.I.C.25.0045 Construction of electrical manholes 14 14-Sep-15 28-Sep-15 18-Nov-15 02-Dec-15 64

    57.S3.M6.I.C.25.0050 Excavation of electrical manholes 14 11-Sep-15 25-Sep-15 15-Nov-15 29-Nov-15 64

    Power Management System Power Management System (PMS) 120 28-Aug-15 25-Dec-15 24-Dec-15 07-Jan-16 1257.S3.M6.I.C.25.0001 Setting-up the SCS/PMS and FO cables Substation 11 14 28-Aug-15 10-Sep-15 24-Dec-15 07-Jan-16 118

    57.S3.M6.I.C.25.0003 Setting-up the SCS/PMS and FO cables Substation 12 14 12-Dec-15 25-Dec-15 24-Dec-15 07-Jan-16 12

    Milestone 10Milestone 10 84 03-Oct-15 25-Dec-15 23-Dec-15 23-Jan-16 29Infrastructure and External WorksInfrastructure and External Works 84 03-Oct-15 25-Dec-15 23-Dec-15 23-Jan-16 29

    SCH12-Substation 11SCH12-Substation 11 18 03-Oct-15 21-Oct-15 23-Dec-15 09-Jan-16 81Testing and CommissioningTesting and Commissioning 18 03-Oct-15 21-Oct-15 23-Dec-15 09-Jan-16 81

    57.S3.M6.I.C.12.0063 Testing & Commissioning of electrical and earthing system 18 03-Oct-15 21-Oct-15 23-Dec-15 09-Jan-16 81

    SCH13-Substation 12SCH13-Substation 12 14 12-Dec-15 25-Dec-15 10-Jan-16 23-Jan-16 29Testing and CommissioningTesting and Commissioning 14 12-Dec-15 25-Dec-15 10-Jan-16 23-Jan-16 29

    57.S3.M6.I.C.13.0063 Testing & Commissioning of electrical and earthing system 14 12-Dec-15 25-Dec-15 10-Jan-16 23-Jan-16 29

    c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul g2015 2016

    @#@Delivery of S1225-Dec-15, Construction25-Dec-15, Infrastructure25-Dec-15, SCH25-Electrical works

    Submittals Completion SCH25, 11-Dec-15

    24-Dec-15, Distribution Transformers, 2

    Installation of MDB Firefighting/Fresh Water Pump Station

    Installation of MDB Potable Water Pump

    Installation of distrib transf, 22kV distrib & LV switchb

    Installation of distrib transf, 22kV distrib & LV switchboards, isolators an29-Oct-15, Diesel Generator Set

    Installation of diesel generator set Substation 12

    Installation of diesel generator set Substation 1119-Oct-15, Power Cables

    Power cables laying09-Oct-15, Duct Banks

    Backfilling of electrical trenches

    Curing duration

    Concrete pouring

    Installation of formwork

    Conduit laying

    Installation of conduit spacers

    Excavation electrical trenches14-Oct-15, Manhole

    Installation of manhole covers and fittings

    Backfilling of electrical manhole

    Curing duration of electrical manholes

    Construction of electrical manholes

    Excavation of electrical manholes25-Dec-15, Power Management System

    Setting-up the SCS/PMS and FO cables Substation 11

    Setting-up the SCS/PMS and FO cables25-Dec-15, Milestone 10

    25-Dec-15, Infrastructure and External W21-Oct-15, SCH12-Substation 1121-Oct-15, Testing and Commissioning

    Testing & Commissioning of electrical and earthing s25-Dec-15, SCH13-Substation 1225-Dec-15, Testing and Commissioning

    Testing & Commissioning of electrical an

    Actual Level of Effort

    Primary Baseline

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    summary

    Detailed Classic Schedule Layout (UCE) Page 3 of 3 IA 15/16C 008GDate Revision Checked Approved

    21-Jun-15 Rev 00 FBM