Community Meeting: “Design Development” | Frederick | October 28, 2015 | www.baltimore21stcenturyschools.org 1 21 st Century School Buildings Plan SCHOOL Calvin Rodwell School COMMUNITY MEETING 50% Feasibility Study | November 10, 2015

21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

Community Meeting: “Design Development” | Frederick | October 28, 2015 |

www.baltimore21stcenturyschools.org1

21st Century School Buildings PlanSCHOOL Calvin Rodwell SchoolCOMMUNITY MEETING 50% Feasibility Study | November 10, 2015

Page 2: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

Introductions and Agenda

Timeline

Previous Meeting Summary

Review Feasibility Discussion • Changes from 50% submission• Pros/Cons

Next Steps

Nicole Price Director, Public Relations 21st Century School Buildings Program

Alice Burley Project Manager, Feasibility Study21st Century School Buildings Program

Meredith Sullivan Architect Design Collective

Introductions Agenda

2Community Meeting: “50% Feasibility Study” | Calvin Rodwell | February 17, 2016 | www.baltimore21stcenturyschools.org

Page 3: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

21st Century School Buildings Program UPDATE

Contribute $20 million

annually towards the plan.

Current estimates suggest the

funding stream will support:

City Schools’ Plan is the largest public

works project in Baltimore City to date.

$977

millionin Phase I

23-28

school

buildings

Recap

3Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 4: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

Design

4

Summary of Activities: Timeframe

July 2015 - May 2016Planning Construction Occupancy

18-24 Months 18-24 Months

Timeline/Process

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 5: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

5

1. Review process

2. Learn key terms

3. Interactive activity

1. Explore essential

elements of design

1. Review site &

building options

2. Provide feedback

1. Make

recommendation on

building option

Educational Specification & Feasibility Study

March 26, 2014 Oct. 1, 2015 Nov. 11, 2015 Feb. 17, 2016

Planning: 6-8 Months

August 2015 – April 2016Dates subject to change

Meeting #1

Orientation

Meeting #2

Essential Elements

Meeting #3

50% Feasibility Study

Meeting #4

Feasibility Review

Planning

Dates subject to change

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 6: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

6

Feasibility Review

• School stakeholders provide feedback on building recommendation,

• City Schools staff review stakeholder recommendation and other criteria

• 21st Century staff work with MOU partners to finalize recommendation

Selection

• Board of School Commissioners Approval

• Notification to Maryland Stadium Authority

• Interagency on School Construction Approval

• Design Architect/Engineer Request for Proposal

• Award A/E and construction managers

(8-12 months)

Pre Design

Pre-Design: 2-4 monthsPlanning : 6-8 months

Option 1

Option 2

Option 3

Dates subject to change

Summer-Fall 2016

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 7: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

7

Calvin Rodwell Elementary

Community Meeting: “Essential Elements” | Calverton | February 2, 2016 | www.baltimore21stcenturyschools.org

Page 8: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

HOPES FEARS

1. Outdoor learning and play spaces

2. Teacher lounge 3. Student display areas4. Sports fields 5. Rooms designed for art,

technology and music

1. Project will take too long2. Will run out of money before

the project is complete 3. Impact on culture and climate

during transition4. Parking and traffic issues will

continue

8Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Greatest Hopes/Worst Fears

PlanningOrientation Meeting

Page 9: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

9

Results from “THE MONEY GAME”What’s important to school staff, parents and community members…

Characteristic Money Spent Characteristic Money Spent

Flexible and Adaptable $50

Welcoming and Inviting $50

Interactive Social Areas Principal: interactive atmosphere will encourage students to learn. Incorporation of technology

$200 Collaborative SpacesStudent interaction, share ideas

$50

Engaging Spaces $200

Natural Lighting Parent: didn’t spend money on things he assumed are a given. Improves mood.

$250

PlanningEssential Elements Meeting

Page 10: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

10

Improve mood

TechnologyLearning anywhere

Reach divers learners Community

Welcoming

PlanningEssential Elements Meeting

Page 11: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

6 Pre K and kindergarten classes 2 music rooms

6 classes for grades 1 and 2 1 art room

9 classes for grades 3, 4, and 5 1 culinary arts classroom

9 classes for grades 6, 7, and 8 Media center/video studio

5 collaborative learning areas Cafeteria

3 special education classrooms Gymnasium/Fitness Room

1 elementary science room Administrative, Health Suites

1 middle school science room Student services

1 technical education room Community Space

11Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Calvin Rodwell Elementary/Middle Classrooms and Spaces

PlanningOverview

Page 12: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

12

Feasibility Study

What is a Feasibility Study?

1. Review existing conditions:

• Is the building structurally sound?

• What is the condition of the mechanical, electrical and plumbing systems?

• Does the building meeting current building and ADA codes?

• Do the educational spaces serve the programmatic needs of the students?

2. Provide design options to comply with the site specific educational specification:

• Strategic Renovation

• Modernization

• Replacement

3. Analyze options for:

Compliance with educational specification

Cost comparison

Construction phasing and logistics

4. Make final recommendation based on all factors for state funding request.

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 13: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

13

Existing Conditions

• Original Building Constructed in 1980 37,537sf

• Grove Park MS will be added to Calvin Rodwell at the completion of

construction to make it a PreK-8 school

Original Building

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 14: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

14

Location Map

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 15: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

15

Existing Site Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 16: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

16

Pedestrian Circulation

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 17: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

17

Vehicular Circulation

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 18: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

18

Site Topography

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 19: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

19

Existing Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 20: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

20

Existing Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 21: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

21

Existing Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 22: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

22

Option 1: Ground Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 23: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

23

Option 1: First Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 24: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

24

Option 1: Second Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 25: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

PROS CONS

• New gymnasium sized for Middle School athletics

• New second floor media center @ 2700sf

• New classrooms @ 900sf per the Ed Spec

• Dedicated art, music, science and technology classrooms

• Infill existing gymnasium with classroom space on two levels

• Undersized kitchen / cafeteria based on student population

• Minimal separation of elementary and middle school

• Inefficient use of space in existing building on second floor

25Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 |

www.baltimore21stcenturyschools.org

Option 1

Page 26: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

26

Option 2: Ground Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 27: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

27

Option 2: First Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 28: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

28

Option 2: Second Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 29: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

PROS CONS

• Relocation of Main Entry further south along Hillsdale Road

• Pre-K and K classrooms on ground level with direct access to play area

• New gymnasium sized for Middle School athletics

• New first floor media center @ 2700sf

• New classrooms @ 900sf per the Ed Spec

• Dedicated art, music, science and technology classrooms

• Infill existing gymnasium with classroom space on two levels

• Expanded kitchen / cafeteria

• Minimal separation of elementary and middle school

• Inefficient use of space in existing building on second floor

29Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 |

www.baltimore21stcenturyschools.org

Option 2

Page 30: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

30

Option 3: Ground Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 31: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

31

Option 3: First Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 32: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

32

Option 3: Second Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 33: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

33

Option 3: Third Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 34: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

PROS CONS• Separate community entry further south along

Hillsdale Road

• New gymnasium sized for Middle School athletics

• New cafeteria and kitchen to support the school population

• New second floor media center @ 2700sf

• New classrooms @ 900sf per the Ed Spec

• Dedicated art, music, science and technology classrooms

• Good separation of elementary and middle school

• Three-story building plan maximizes site for play areas

• Required relocation of students during construction

34Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 |

www.baltimore21stcenturyschools.org

Option 3

Page 35: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

35

Option 4: Ground Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 36: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

36

Option 4: First Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 37: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

37

Option 4: Second Floor Plan

Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 | www.baltimore21stcenturyschools.org

Page 38: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

PROS PROS

• New first floor media center @ 2700sf

• New classrooms @ 900sf per the Ed Spec

• Dedicated art, music, science and technology classrooms

• Good separation of elementary and middle school

• Allows for students to remain in existing building during construction of replacement school

• Reorientation of main entry and school along Maine Avenue

• Expanding parking area along Liberty Heights Road

• Service access from Maine Avenue

• New gymnasium sized for Middle School athletics

• New cafeteria and kitchen to support the school population

• New first floor media center @ 2700sf

38Community Meeting: “50% Feasibility Study” | Calvin Rodwell | November 10, 2015 |

www.baltimore21stcenturyschools.org

Option 4

Page 39: 21 Century School Buildings Plan · 6 Pre K and kindergarten classes 2 music rooms 6 classes for grades 1 and 2 1 art room 9 classes for grades 3, 4, and 5 1 culinary arts classroom

21st Century School Buildings ProgramBaltimore City Public Schools200 East North Avenue Room 407-BBaltimore MD 21202(443) 642-4600

Mignon R. AnthonyExecutive Director, 21st Century Buildings ProgramBaltimore City Public Schools

Gary McGuiganSenior Vice President, Capital Development DivisionMaryland Stadium Authority

Dawn KirstaetterDeputy Mayor, Health, Human Services, Education and YouthCity of Baltimore

David LeverExecutive Director, Public School Construction ProgramState of Maryland

www.baltimore21stcenturyschools.org

This presentation is brought to you by the

21st Century School Buildings Program

and Design Collective.

Thank You!

39